Professional Documents
Culture Documents
Renewable Energy
journal homepage: www.elsevier.com/locate/renene
a r t i c l e i n f o
a b s t r a c t
Article history:
Received 5 September 2014
Received in revised form
27 February 2015
Accepted 28 June 2015
Available online 10 July 2015
A simple method is proposed to site turbines and choose their power output, evaluate costs and incomes
and provide useful indications for Micro Hydro Power (MHP) plant design in existing irrigation systems.
This method, based on simple models available in literature and requiring a reduced number of input
parameters easy to survey in preliminary design stages, has been applied and veried in an existing
irrigation system located in Calabria (Italy).
The results have highlighted that in the case study the smallest protable turbine would produce
5 kW. A lower number of plants (with higher output) would produce no particular monetary savings
compared to a greater number of smaller turbines. Furthermore, neither was the option of increasing
pipeline diameter found to provide savings.
In general, an appreciable potential from MHP operation has been shown in existing irrigation systems, providing a return on investment higher than that provided by the Italian nancial market.
Finally, MHP protability noticeably increases with total annual operation time, being on average 55%
higher in a wet year (eight months of electrical production/four month of irrigation) compared to a dry
year (six months of electrical production/six months of irrigation).
2015 Elsevier Ltd. All rights reserved.
Keywords:
Water User Association
Micro hydro power plant
Optimal discharge
Collective irrigation system
Annual operation time
Hydroelectric energy
1. Introduction
Hydroelectric power is by far the most mature renewable energy used for electricity generation, being totally inexhaustible and
carbon-free [1,4,8,13]. Furthermore, today, installation of hydroelectric power turbines allows additional economic resources for
users thanks to the subsidies granted by the national energy policies for decreasing CO2 emissions.
SHP plants (i.e. with a nominal power lower than 10 MW [4,13],
have found special importance due to their low installation and
management costs, short construction time, robust technology and
reliability [4,7,13]. The adoption of SHP plants has been recommended in rural or marginal areas, because they do not require
major construction works (which may involve environmental impacts), can be operated entirely by remote control with few operating personnel and enhance rural electrication [4,13].
The availability of geodetic heads in existing water systems
suggests the possibility of integrating SHP plants at sustainable
* Corresponding author.
E-mail address: dzema@unirc.it (D.A. Zema).
http://dx.doi.org/10.1016/j.renene.2015.06.066
0960-1481/ 2015 Elsevier Ltd. All rights reserved.
Abbreviations
A
AC
CCEME
CDE
CED
CNPV
COM
Cp
CPTL
CRR
CSA
CTD
D
DN
E
FC
G
Hj
I
IC
J
Jen
L
MHP
NPV
P
PE
pmax
Pn
499
P(irr)
n
500
Fig. 1. Flow chart of the method for assessing MHP feasibility in existing irrigation systems.
p < pmax of the existing pipeline. Otherwise, where p > pmax, a new
pipeline with higher strength must be installed.
2.3. Hydraulic calculations
The proposed adjustments require water network verication:
to this aim, the n equations of mass balance (1) (as many as the
number of the network nodes) and m motion equations (1) (as
many as the number of the network pipelines) must be satised:
8
r
>
<PQ
s
P
Qk;out 0
i1
j1
>
: DH H H
j
j1
i;in
(1)
Q2
Pn hgQ DHn hgQ DH DY hgQ DH JL
xk
2gA2
k1
(2)
t being the number of the concentrated hydraulic losses.
If J is calculated by a common monomial equation, as:
J lQ l Dp
(3)
Q2
Pn hgQ DH lQ l Dp L
xk
2
2gA
k1
!
(4)
Q*
DHDp 1=l
1 llL
(5)
Pn
(6)
501
Rout
Qav
Rirr
Qmax
(7)
Cp aDn
(8)
I PE E PE Pn Ta
(9)
502
difference between income and costs for each year actualised at the
rst year of the investment by the future ination rate), and CNPV
for the overall plant lifespan are evaluated; nally, ROI, given by the
ratio between the CNPV and the IC and averaged on the plant lifespan, is calculated.
2.5.2. Costs
The economic analysis methods are proposed according to the
guidelines reported by Hosseini et al. (2005) [7].
IC are the sum of CCEME (turbines, generators, control systems as
well as civil works for adapting the existing small dams and
building the equipment housing, etc.), CPTL, CED and CSA (purchase of
land, management, inspection and supervision costs).
For estimating the cost of the electro-mechanical equipment,
there are graphs which can approximately calculate those costs, but
these graphs have not recently been updated. Furthermore, manufacturers of turbines and alternators do not supply any information
about cost, since every installation is different and complex [12]. In a
simpler but reliable way, CCEME can be calculated as a function of
hydraulic characteristics of the hydro site such as DH and Q or DH
and Pn, as reported in many studies [2,6,14]. In this method the
equation reported by Papantonis (2001) [14] who estimated the
costs of different components of the hydro plant based on the European data available at that time, has been adopted:
CCEME
N
X
0:7
bPn;i
DHi0:35
(10)
i1
503
Table 1
Layout of turbines (Ti) for three MHP schemes in the Spilinga-Ricadi irrigation
system.
Pipeline
Scheme
1
P1
P7
P5
P8
P4
P2
P3
P6
T4
T6
T1
e
T2
T3
T7
T5
T10
T10
T8 (D 200 mm)
T8 (D 500 mm)
T9
T9
e
T7
e
e
T7
e
504
Fig. 3. Regression equation of CCEME of SHP plants in the Italian market versus those
estimated by Equation (10) (b 25635 V kW0.7 m0.35).
Table 2
Hydraulic parameters and Pn calculated for three MHP schemes in the Spilinga-Ricadi irrigation system.
MHP turbine
Scheme n. 1
T1
T2
T3
T4
T5
T6
T7
Total scheme n. 1
Scheme n. 2
T7
T8
T9
T10
Total scheme n. 2
Scheme n. 3
T7
T8
T9
T10
Total scheme n. 3
(a) equal to Qs.
Pipeline
DH [m]
L [m]
Q* [L s1]
Q [L s1]
J [m3 km1]
DY JL [m]
DHn [m]
Pn [kW]
P5
P4
P2
P1
P6
P7
P3
60.9
118.5
59.9
81.7
117.0
80.0
82.4
600.4
3043
1545
1363
1882
1941
1529
1696
12998
27
57
33e67
42
50
19e22
44
27
57
14
24
16
10(a)
44
7.01
26.9
0.22e4.14
5.48
2.52
4.14e5.61
17.04
21.3
41.5
4.0
10.3
5.0
7.4
28.9
118.4
39.5
76.9
56.0
71.4
112.1
72.6
53.5
482.0
9.0
36.3
6.5
14.3
14.7
6.1
19.8
106.7
P3
P5
P4 P8
P1 P7
82.4
134.1
178.7
161.7
556.9
1696
2800
2349
3411
10256
44
44
27e57
22e42
44
44
45
10(a)
17.56
16.79
17.56e67.16
1.08-5.61
29.8
47.0
81.1
9.5
167.4
52.7
87.1
97.6
152.2
389.6
19.8
31.9
36.6
12.7
101.0
P3
P5
P4 P8
P1 P7
82.4
134.1
178.7
161.7
556.9
1696
2800
2349
3411
10256
44
57
27e57
22e42
44
230(a)
45
10(a)
17.56
3.29
17.56e67.16
1.08e5.61
29.8
9.2
81.1
9.5
129.6
52.7
124.9
97.6
152.2
427.4
19.8
243.7
36.6
12.7
312.8
505
Table 3
IC and AC as well as average NPV and CNPV estimated for three MHP schemes in the Spilinga-Ricadi irrigation system.
MHP scheme
IC [kV]
AC [kV]
1
2
3
275
198
1249
16.5
11.9
74.9
CNPV [kV]
Years 1e20
Years 21e25
Years 1e20
Years 21e25
46.2
47.0
106.5
8.2
9.2
13.8
923
939
2131
41.1
46.2
69.0
506
Table 4
Total E, CNPV and RUE of three MHP schemes in the Spilinga-Ricadi irrigation system.
MHP scheme
Years 1e20
1
2
3
Years 21e25
1
2
3
Years 1e25
1
2
3
Total E [MWh]
CNPV [kV]
RUE [V/kWh]
10755
10181
31530
923
939
2131
0.09
0.09
0.07
2689
2545
7883
41
46
69
0.02
0.02
0.01
13444
12726
39413
964
985
2200
0.07
0.08
0.06
Fig. 5. CNPV after 25 years for different Ta for three MHP schemes in the Spilinga-Ricadi
irrigation system.
[1] T. Abbasi, S.A. Abbasi, Small hydro and the environmental implications of its
extensive utilization, Renew. Sustain. Energy Rev. 15 (2011) 2134e2143.
[2] G.A. Aggidis, E. Luchinskaya, R. Rothschild, D.C. Howard, The costs of smallscale hydro power production: impact on the development of existing potential, Renew. Energy 35 (2010) 2632e2638.
[3] T. Caloiero, R. Coscarelli, E. Ferrari, M. Mancini, Precipitation change in
Southern Italy linked to global scale oscillation indexes, Nat. Hazards Earth
Syst. Sci. (11) (2011) 1683e1694.
[4] C. Dragu, T. Sels, R. Belmans, Small hydro power e state of the art and applications, in: International Conference on Power Generation and Sustainable
ge (Belgium), 8e9 October 2001, pp. 265e270.
Development (AIM). Lie
[5] ESHA., Guide on How to Develop a Small Hydropower Plant, European Small
Hydropower Association, 2004. Available at: URL, http://www.esha.be/
leadmin/esha_les/documents/publications/GUIDES/GUIDE_SHP/GUIDE_
SHP_EN.pdf. Last access on 02.23.15..
[6] J.L. Gordon, A.C. Penman, Quick estimating techniques for small hydro potential, J. Water Power Dam Constr. 31 (1979) 46e55.
[7] S.M.H. Hosseini, F. Forouzbakhsh, M. Rahimpoor, Determination of the optimal
installation capacity of small hydro-power plants through the use of technical,
economic and reliability indices, Energy Policy 33 (2005) 1948e1956.
[8] J.K. Kaldellis, D.S. Vlachou, G. Korbakis, Techno-economic evaluation of small
hydro power plants in Greece: a complete sensitivity analysis, Energy Policy
33 (2005) 1969e1985.
[9] A.D. Karlis, D.P. Papadopoulos, A systematic assessment of the technical
feasibility and economic viability of small hydroelectric system installations
(Technical note), Renew. Energy 20 (2000) 253e262.
[10] V. Milano (Ed.), Acquedotti. Hoepli, 1996, p. 643. Milano, Italy (in Italian).
[11] R. Montanari, Criteria for the economic planning of a low power hydroelectric
plant, Renew. Energy 28 (2003) 2129e2145.
[12] B. Ogayar, P.G. Vidal, Cost determination of the electro-mechanical equipment
of a small hydro-power plant, Renew. Energy 34 (2009) 6e13.
[13] O. Paish, Small hydro power: technology and current status, Renew. Sustain.
Energy Rev. 6 (2002) 537e556.
[14] D. Papantonis, Small Hydro Power Stations, Simeon, Athens, 2001.
[15] P. Vijaya Kumar, M. Bindi, A. Crisci, G. Maracchi, Detection of variations in
precipitation at different time scales of twentieth century at three locations of
Italy, Weather Clim. Extrem. (2) (2013) 7e15.
[16] N.G. Voros, C.T. Kiranoudis, Z.B. Maroulis, Short-cut design of small hydroelectric plants, Renew. Energy 19 (2000) 545e563.