Professional Documents
Culture Documents
j
Proposal
p
for EPCIC NN-WHP,
Associated Pipelines and Receiving
Facilities on EE-WHP
Presentation Outlines :
Project Brief
Project Name : Pad-Thai Field
Development
p
Field Location : 100 NM, east of
Chumporn Province,
Province GOT
Water Depth : 60 meter
Type of Contract : Lumpsum
Client : AIT Exploration & Production Ltd
Project Location
Scope of Work
HUC Completion
p
: 30 Nov 2014
Project
j
Execution Plan
Project Management
Detailed Engineering (Process, Structure,
Mechanical/Piping, E/I and Pipeline)
Procurement (Contractor Supplied and Client
Supplied)
pp )
Fabrication (Jacket, Piles & Conductors and Topsides)
Transportation (Pipeline, Jacket and Pile & Conductor,
Topsides)
Installlation, Hook Upp & Commissioningg (Pipeline,
( p
Jacket, Piles and Conductors, Topsides and Tie-in to
Receiving Facilities E-WHP)
Project
j
Organization
g
Chart
ProjectManager
ProjectControland
Risk
Interface
Manager
QAManager
ProjectEngineer
HSEManager
Engineering
Manager
Procurement
Manager
Fabrication
Manager
T&IManager
HUCManager
Structure
Buyer
Structure
Fieldengineer
Hookup Eng
Mechanical/Piping
Procurement
Mechanical/Piping
MarineCoordinator
CommisiongEng
Electrical/Instrument
Electrical/Instrument
Safety
Project Schedule
No
Task Name
Contract Award
Detailed Engineering
Stuctural
Mechanical/Process
Electrical
Instrumentation
Duration
May Jun
(month)
m
m
1d
Jul
m
Year 2013
Year 2014
Aug Sep Oct Nov Dec Jan
Feb
Mar
Apr
May
Jun
Jul
m
m
m
m
m
m wwwwwwwwwwwwwwwwwwww m
6m
6m
6m
6m
Procurement
Client Supplied
Primary Steel
Crane
Coated line pipes & bends
Contractor Supplied
Low grade steel
CS piping material
Duplex piping
Valves, SP items
Vessels, Pump, Tanks
Safety equipment
E/I and Telecom equipment
E/I and
d Telecom
T l
bulks
b lk material
t i l
Fabrication
Topsides incl. deck extension/pig receiver
Testing and pre-commissioning for Topsides
Jacket
Testing for jacket
Piles/Conductors
Loadout and seafastening
N-WHP sailaway
Transportation and Installation
Transportation
Pipeline
Jacket
Topsides
Piles/Conductors
Deck Extension and pig receiver
Installation
Pipeline
Jacket
Topsides
Piles/Conductors
Installation Completion
Hook-up and Commissioning
Install Deck extension @ E-WHP
Install Pig receiver @ E-WHP
Tie-in to existing E-WHP and commissioning
HUC Completion
Drilling Campaign on N-WHP
3m
6m
10m
1m
2m
6m
6m*
6m
3m
6m*
4
4m
7m
1m
6m
1w
3m
2w
Early Facility
Readiness
Description
Engineering
Procurement
Structural Material
Piping Material
Mechanical Material
E&I and Telecom. Material
Procurement Services (Expedite/TPI/FAT)
Fabrication
Topside
Jacket & Appurtenances
Piles & Conductor
LoadOut & Seafastening
QA/QC HSE,
QA/QC,
HSE Final
Fi l Documentation
D
t ti
Transportation & Installation
Mob/Demob
- DP Vessel
Operations
- DP Vessel
Barge & Tug
- Platform (2 nos)
- Pipelines
Crew Boat
Unit Price
(USD/unit)
Quantity
17
months
Lump Sum
PRICE (USD)
90,000
1,530,000
Lumpsum
2,000,000
1
1
1
1
1
LS
LS
LS
LS
LS
600,000
2,600,000
1,700,000
1,400,000
600,000
2,600,000
1,700,000
1,400,000
315,000
6 615 000
6,615,000
137,500
56,000
20,000
1
MH
MH
MH
LS
20
20
20
300,000
2,750,000
1,120,000
400,000
300,000
100 000
100,000
4,670,000
time
6,200,000
31.5
Days
300,000
9,450,000
49
15
14
Days
Days
Days
18,000
18,000
10,000
882,000
270,000
140,000
16,942,000
1
1
1
1
1
LS
LS
LS
LS
LS
2,500,000
2,500,000
34,257,000
41,108,400
4
5
Fabrication
Loadout and seafastening
Transportation and Installation
Cost
(x1000 USD)
1836
2400
131
400
131
400
131
400
131
400
131
400
131
400
131
131
756
378
168
252
315
84
231
94.5
378
168
252
315
84
231
94.5
168
252
315
84
231
94.5
168
252
315
168
252
315
231
94.5
231
583
583
583
583
583
756
756
1008
1512
1890
252
1386
378
168
252
315
231
5244
360
20330
Month
8
10
11
12
13
14
131
131
131
131
131
131
583
583
583
583
360
6777
6777
6777
3000
41108
3000
531
531
1497
3392
2636
2258
1774
1680
714
714
714
7851
6908
9908
531
1062
2559
5952
8588
10846 12621
14300
15014
15728
16442
24293
31200
41108
Notes :
1) Projects monthly performance cost will be the basis for
Client payment
2) Monthly equal cost basis is assumed
15
Project Cost
756
756
1008
1512
1890
252
1386
378
10
11
12
13
14
15
531
531
1497
3392
2636
2258
1774
1680
714
714
714
7851
6908
9908
-131
-131
-131
-131
-131
-131
-131
-131
-131
-131
-131
-131
-131
-131
-400
-400
-400
-400
-400
-400
30% order,
d 40% on site,
i
30% commissioning
-756
756
-756
-1008
-454
-605
-454
-567
-756
-567
-252
-277 2
-277.2
-693
-76
d) Fabrication
f) HUC
-583
-583
-113
-583
-583
-583
-583
-583
-360
18780
1550
-9390
-9390
-1550
3000
-583
360
-416
-189
-583
-3000
531
531
1497
3392
2636
2258
1774
1680
714
714
714
7851
6908
9908
-531
-1829
-1363
-1870
-1366
-1303
-3776
-714
-714
-2264
-10104
-10104
-2042
-3131
-1298
134
1523
1271
956
-2001
966
-1550
-9390
-2253
4866
6777
2000
1523
0
0
966
956
134
0
1
1271
4
-1298
0
5
-2000
9
-2001
10
11
12
13
-1550
-2253
-4000
-6000
-8000
-9390
-10000
14
15
16
Thank You
Backupp Slides
Procurement Cost
Vendor
V d A vs Vendor
V d B
Item
Description
1
2
3
4
5
6
7
8
Lowgradesteel
CSPipingmaterials
DuplexPiping
E&I and Telecom equipment
E&IandTelecomequipment
E&IandTelecombulksmaterials
Vessels,Pumps,Tanks
Valves,SPItems
SafetyEquipment
Total
Item
Description
Price
Leadtime
Month(s)
600,000
600,000
800,000
1 000 000
1,000,000
300,000
1,500,000
1,000,000
200,000
6,000,000
Price
1
2
3
4
Lowgradesteel
CSPipingmaterials
DuplexPiping
E&I and Telecom equipment
E&IandTelecomequipment
700,000
700,000
1,000,000
1 000 000
1,000,000
5
6
7
E&IandTelecombulksmaterials
Vessels,Pumps,Tanks
Valves,SPItems
300,000
1,500,000
1,000,000
SafetyEquipment
Total
200,000
6,400,000
1
2
6
8
4
6
8
3
Term
CIFFabYard
CIFFabYard
CIFFabYard
CIF Fab Yard
CIFFabYard
CIFFabYard
CIFFabYard
CIFFabYard
CIFFabYard
Leadtime
Month(s)
h( )
Term
1
2
6
CIFFabYard
CIFFabYard
CIFFabYard
6
4
6
ExWork
CIFFabYard
CIFFabYard
1,100,000
6
3
ExWork
CIFFabYard
1,200,000
,
,
CIF Fab
yard
ard Price
Fabrication Cost
MT
MH/MT
MH
USD/MH
USD
Topside Steel
350
150
52 500
52,500
20
1 050 000
1,050,000
Mech/Piping
150
300
45,000
20
900,000
E/I
100
400
40,000
20
800,000
Jacket
700
80
56 000
56,000
20
1 120 000
1,120,000
1,000
20
20,000
20
400,000
Piles/Conductors
2,300
213,500
4,270,000
T and I Cost
DerrickLayBarge(DLB)
Opt1:8pointmooring,comeswith2AHTs,noSATsystem
5MMUSDLumpSummob/demob(onto/fromSite)
250,000USD/dayDayRate
PipelayRate:1km/day
JacketInstallation7days
Pile/ConductorInstallation7days
TopsidesInstallation3days
PostinstalledRiserInstallation4days
PipelineHydrotest2days
p
DLBspeed3knots
Opt2:DPVessel,withSATsystem
6.2MMUSDLumpSummob/demob(onto/fromSite)
300,000USD/dayDayRate
PipelayRate:2km/day
JacketInstallation6days
Pil /C d t I t ll ti 7 d
Pile/ConductorInstallation7days
TopsidesInstallation2days
PostinstalledRiserInstallation3days
SubseaTiein2dayseachend
PipelineHydrotest2days
DPspeed3knots
DiverSupportVessel(DSV)DP2,withROVandSATsystem
2MMUSDLumpSummob/demob(onto/fromSite)
150,000USD/dayDayRate
SubseaTiein4daysbothends
PipelineHydrotest2days
Day
USD
5,000,000
250,000
15
3,750,000
1,750,000
1,750,000
750,000
1,000,000
500,000
38
14,500,000
,
,
6,200,000
300,000
7.5
2,250,000
6.0
1,800,000
70
7.0
2 100 000
2,100,000
2.0
600,000
3.0
900,000
4.0
1,200,000
2.0
600,000
32
15,650,000
2,000,000
150,000
4
2
600,000
300,000
2 900 000
2,900,000
Barge&TugareonlyavailableinJurong,Singapore
BareBargeTowSpeed5knots
BargewithfullloadTowSpeed3knots
Dayrateat18,000USD/day
15
270,000
18,000
30
540,000
19
extension
CrewBoat&SupplyBoatareonlyavailableinSingapore
Dayrateat10,000USD/day
AverageSpeed10knots
Remark
Supply boat
342,000
1,152,000
-
10,000
14
140,000
16,942,000
Selected