You are on page 1of 9

Using BPN Method for Estimating Cement Take of Grouting

Chau-Ping, Yang
Department of Civil Engineering and Engineering Informatics, Chung-Hau University,
30 Tung Shiang, Hsinchu, Taiwan, 30067, E-mail address: ycp@chu.edu.tw
Keywords: Dam foundation; Grouting; Cement take; BPN

Abstract
Using cement grout to improve bedrock has been quite common. However, the cost for cement grout is the
most difficult one to estimate. This study adopted the Back-Propagation Neural network (BPN) to analyze the
grouting construction data of the Li-Yu-Tan dam, in order to estimate the cement take needed. The samples
analyzed included data from 3,532 grout sections. The data from the first half of the grouting construction were
used to derive the parameters of the predictive schemes, and then the second half of the grouting constructions
data were used to test the accuracy of those schemes. The accuracy level estimated by BPN on gross cement
take was 75.3%. It was higher than the original design level of 43.4%.

1. Introduction
The bedrock inherently has discontinuities such as
faults, folds, beddings, joints, and fractures, which
are the major factors that affect the engineering
properties of rock foundations such as permeability,
shear strength, and deformation. When a dam is
located on bedrock that has unknown discontinuities,
the underlying foundation needs to be improved to
raise its engineering properties and ensure a
watertight reservoir. Using cement grout to improve
bedrock has been quite common, and there are
numerous examples of its application in foundation
improvement [1, 2, 3, 4, 5, 6]. However, since the
dam foundation is below the surface of the ground,
the cost for cement grout is the most difficult one to
estimate. The cost of cement grout mainly includes
the operational part and the material part. The cost of
materials is calculated based on the cement take.
Then the cost of the grouting operation is determined
based on the materials cost. Therefore, it is
necessary to study various methods to estimate the
cement take of the grouting based on actual
construction data. The methods commonly used are
mean method and linear regression method [7, 8].
In general, the status of the discontinuities in the
dam foundation is indirectly expressed by the
Lugeon value determined from the Lugeon
tests. This information can also be used to design the
water to cement ratio and the injection pressure used
in the grouting process. Eq. (1) is the definition of the
Lugeon value .
Lugeon value = Lu =

VPs
(l / m / min) (1)
TPi L

Where V is the water take ( l ), Ps is the


standard injection pressure (981 kPa ), T is the
injection time ( min . ), Pi is the injection pressure

used ( kPa ), L is the length of grout section ( m


). Generally speaking, if a dam foundation has a high
Lugeon value , it will have more discontinuities
with high permeability and more cement take is
needed for the grout improvement.
The Lugeon value is the best physical
parameter to express the status of discontinuities in a
dam foundation. Theoretically, it is quite difficult to
define the relationship between cement take and the
Lugeon value [7, 8]. Additionally, when
researchers estimate the cement take needed for a
new dam foundation from past experiences, they still
encounter the problems of different geological
properties for the proposed dam site. For example,
the cement take designed for the improvement of the
foundation of the Li-Yu-Tan dam, Miao-Li County,
Taiwan, was 50 kgf / m . However, the average
reading of cement take from the construction records
was 115 kgf / m [9]. This difference resulted in a
doubling of the amount of gross cement take from
what was required in the stage of original design.
This experience illustrates the difficulty in cement
take estimation.
This study adopted the Back-Propagation Neural
network (BPN) to analyze the construction data from
the grout-curtain improvement of the Li-Yu-Tan
dams foundation, and indicate how to estimate the
cement take needed. The dam is located at the upper
stream of the Jing-San brook, a tributary of the DaAn river. The dam is a zone-type-earth-dam with a
height of 96 m , a bottom width along the foundation
of the river of about 500 m and a gross volume of
3,700,000 m 3 . The major terrain includes gravelly
terra rossa and some riverbank outcrops. There are
no faults or obvious folds on either side of the river.
The major discontinuities in the foundation of the
dam site are dozens of developed shear zones. Most
shear zones are distributed in the right side of the
abutments of the dam with slips of more than 2 cm

~5 cm [10].

2. Factors affecting cement take


Theoretically, there are many factors that affect the
cement take needed for improving dam foundations.
Moreover, since some factors may have combined
effects, it is not possible to clearly define the role of
each factor. Some factors that can be categorized or
quantified are the strata, zone of dam foundation,
depth of grout section, injection pressure, and the
Lugeon value .
2.1 Strata
This category covers properties such as the rock
layers, the nature of discontinuities, the rock strength,
the mineral components, and the cementation.
Shallow bedrock tends to have a high density of
cracks or openings and is subjected to grout leakage
and holes collapse. If a rock foundation has little
strength, the grout hole will be less independent. The
disadvantages of bedrock mentioned above increase
the amount of cement take needed for grout
improvement.
As shown in Fig. 1, the strata in the dam site
vicinity are northeastwards and meet the river valley
vertically at 28~34 degrees. All the strata are leaning
towards the upper stream at 30~34 degrees. The
strata of the Li-Yu-Tan dams foundation include
clean sandstone (CS), mudstone (MS), and
alternations with sandstone and shale (AL). The
major formation of clean sandstone contains quartz
sand, which has a tensile strength of about 1,050
kPa and a hydraulic conductivity of about
6.5 10 5 cm / sec . However, since quartz sand
has a poor cementation quality, the seepage paths are
more likely to cause a loss of fine material. Mudstone
contains different amounts of mud; therefore, its
tensile strength ranges from 1,140 kPa to 2,010
kPa , and the average hydraulic conductivity is
Alternations
with
3.4 10 6 cm / sec .
sandstone and shale have intertwined clean sandstone
and shale or mudstone and shale in small alternating
thickness. The thickness of mud accumulation
between layers can reach 30 cm . On the surface
layer, seepage paths can form that cause deterioration
of the shale into fragments or even seams.
2.2 Zone of dam foundation
When the overburden of ground is relieved,
riverbanks will move inwards, and tensile fractures
will occur in the banks. This phase results in more
cracks on the upper half of the dams abutments and
induces greater permeability. For this reason, the
cement takes needed for the grout improvement in
the right zone, left zone, and the valley are different.
This research has divided the dam foundation into the

riverbed, the left upper zone, the left lower zone, the
right upper zone and the right lower zone, as shown
in Fig.2 and Fig. 3, according to the tunnel locations
for the grout-curtain construction. However, because
the riverbed has been dug to the level of fresh
bedrock with a permeability lower than 10 Lugeon
, there are only a few in-place grout holes. Thus, the
analytical extent of this research covers only the left
upper zone, the left lower zone, the right upper zone,
and the right lower zone. The shaded part in Fig. 3 is
the outcome of the grout-curtain in the Li-Yu-Tan
dams foundation. For the shallower parts, grouting
can be performed from the top, but, in the deeper
areas, the grouting will have to be performed from
tunnels.
2.3 Depth of grout section
In a rock layers deeper into the underground, the
cracks are narrow and comparatively do not take in
grout because of the greater tectonic stresses in lower
elevation. When the tectonic stress is taken into
consideration, the depth of the grout section is
considered as one of the factors that affect cement
take. As to the grout-curtain construction in the LiYu-Tan dam, the diameter of the grout holes was 3.8
cm and the greatest vertical depth of a grout hole
was limited to 50 m . Inside of each grout hole, there
were several grout sections, and the grout process
was conducted from the bottom to the top of the
grout hole. If the depth of the grout section was
smaller than 30 m , the grout section length was 5
m . When the depth of a grout section was greater
than 30 m , the section length was 10 m .
2.4 Injection pressure
The injection pressure is the major technical factor
affecting cement take. Theoretically, the injection
pressure should be smaller than the tectonic stress
corresponding to the depth of a grout section, which
is obtained from the hydraulic fracturing test.
Moreover, the injection pressure should be smaller
than the tensile strength of the rocks [11, 12]. In
Taiwan, dam engineers consider that the injection
pressure is determined based on the principle of
additional pressure increasing about 30 kPa per
meter depth. The injection pressure adopted for the
grout-curtain construction of the Li-Yu-Tan dam was
150 kPa to 1200 kPa from top to the bottom of
the grout hole [13].
2.5 Lugeon value
The Lugeon value is the only physical
parameter that the researcher could obtain to evaluate
the multiple factors that affect cement take. This
value shows the degree of permeability in the dam
foundation. Basically, in grout improvement, a dam

foundation that has a high


requires more cement take.

Lugeon value

3. Data analysis
In the Li-Yu-Tan dams grout-curtain construction,
the grout holes were of the split-spacing type. Splitspacing means that the grout holes were arranged in
the sequence of primary holes, secondary holes,
tertiary holes, and quaternary holes. Supplementary
holes may be added to enhance the locations with
more discontinuities in the bedrock or near the holes
that required more cement take. Basically, the
arrangement of grout holes was based on the quality
of bedrock. The grout holes were arranged at
intervals of 1 m to 3 m . When the grouting process
of a specific hole lasts for 60 minutes, but the amount
of cement take does not reach 70 l , the grouting for
this section should be stopped. Finally, the drill
inspection holes used for performing the Lugeon test
to check the permeability of the dam foundation were
improved. The process of grouting in each grout
section was arranged in the following sequence:
drilling, washing, water testing, and grouting. During
water testing, the Lugeon tests need to be performed
to obtain Lugeon value .
Table 1 lists the data analyzed for 469 grout holes
and 3,532 grout sections. Each grout section had data
such as zone, sequence, hole depth, length of grout
section, rock nature, Lugeon value , injection
pressure, and cement take. All of the data were
collected from the inspection chart of the groutcurtain construction for the Li-Yu-Tan dam in 1993.
Then, all the data were entered into an Excel
application program for calculations before the BPN
analysis began.
For the convenience of analysis, this study has
adopted the symbol Lu to represent the Lugeon
value of a specific grout section. In addition,
because the lengths of the grout sections analyzed
were not the same (between 5 m and 10 m ), the
cement take of a grout section was divided by its
length to obtain the cement take per unit length Lg
( kgf / m ). There were three reasons to use cement
take instead of cement mortar take to define Lg .
First, the voids in the cracks were filled by solid
cement. Secondly, the major material expense in
grout construction is the quantity of cement. Thirdly,
many documents related to grouting refer to cement
take in place of cement mortar take [14, 15].

4. BPN method
The BPN is a branch of artificial neural networks
(ANN). The growing interest in ANN among
researchers is due to its excellent performance in
learning ability, fault tolerance, pattern recognition,
and the modeling of nonlinear relationships
especially involving a multitude of non-digital

variables in place of conventional techniques.


Generally, a complex domain is characterized by a
number of interacting factors. Yet, such factors are
often incomplete or unreliable. If ANN is used to
analyze complex engineering systems, it can alleviate
noise interference and raise the accuracy level of the
analysis. ANN has been widely applied to research in
the field of geotechnical engineering in recent years
[16,17,18].
Huang and Wanstedt [19] applied BPN to the
categorization of rocks and found that the
categorizing ability of BPN was much better than
statistical methods. Additionally, a conventional
method for modeling the stress-strain behavior of soil
is the constitutive law. However, it is characterized
by the difficulties in obtaining correct parameters,
conducting mathematical calculations, and the
oversimplification of the hypothesis. In a quite
different way of research thinking the constitutive
law was replaced with BPN to simulate the stressstrain behavior of soils [20, 21, 22].
4.1 Mechanism of BPN
The typical architecture of BPN used in this study
is shown in Fig. 4. The input layer uses linear
transfer functions to handle the input variables in the
network. The number of processing elements in the
input layer depends on the problem. In the hidden
layer, it learns how each processing element in the
input layer affects the others through association of
the connection weights. In the output layer, an Sshaped sigmoid transfer function is used to handle
output variables to make the domain to be [0, 1]. The
number of processing elements in the output layer
depends on the problem. BPN learns by modifying
the connection weights of the elements in response to
the errors between the actual output values and the
target output values. This is carried out through the
gradient descent on the sum of squared error for all
the training patterns.
The learning algorithm of BPN requires the
following steps:
a. Use the connection weight W to show the
correlation between the input variable X and
each processing element. Meanwhile, biases
and activity function net value will come out.
Then, convert the net value to either the target
output value H in the hidden layer and to the
target output value Y in the output layer.
b. As to the processing elements in the output
layer, use Y and the actual output value T to
calculate the offset y . The calculation of the
processing elements in the hidden layer also
adopts W , H and y to calculate the offset
c.

h.
In the input layer and the hidden layer, use the
learning rate , h and X to calculate the

d.

correction value of the connection weight W .


In the hidden layer and the output layer, use the
learning rate , y and H to calculate W .
Then, update the W in each processing element
to complete the learning of one cycle.
Repeat the computation described above until
convergence or approximately 3,000 learning
cycles are reached.

The BPN software used in this research was PCNeuron, written in C language [23]. With the
assistance of the original programmer, a new
subprogram was written to return to the target output
value from the original domain [0, 1]. Then, this
value was converted to a data file that Excel software
can treat.
4.2

Architecture of B PN f or esti ma tin g


c emen t tak e

The input variables which needed to be fed into


the BPN program were the zone of the dam
foundation, the type of rock layers, the injection
pressure, the depth of grout section, and Lu . The
output variable was the Lg of each grout section.
Among these variables, both Lu and Lg are
measured digital data and the others are represented
by the classification codes. The codes of these input
variables are listed in Table 2.
The learning algorithm of BPN can be divided into
the training phase and the testing phase. The learning
samples for these phases were collected from the first
half of the grout construction in the four zones. The
samples were randomly categorized into the training
set and testing set in the first phase of data
processing. The initial learning rate, the initial
inertial factor, and the initial connection weight were
set to be 5.0, 0.5 and 0.3 respectively. After a number
of different hidden layers were tried, one hidden
layer was used in the BPN model employed here. In
the preliminary task, a network with different
elements ranging from 2 to 8 in the hidden layer was
trained for the same number of 3,000 cycles. It was
found that the value of the average sum squared error
( SSE ) would reach the minimum value of 0.11
when the number of elements was equal to 5. Eq. (2)
is used to calculate SSE :
M

SSE

(T
p

p
j

Y jp ) 2

(2)

M N

p
Where T j is the actual output value of processing
p
element j in example p, Y j is the target output

value of processing element j in example p, M is


the number of example, N is the number of

processing element in the output layer.


So, a 5 5 1 network was set up as shown in
Fig.5. The learning process was performed with a
Pentium 586 computer, which took about 110 min. of
CPU time. Finally, BPN was applied to the training
set and produced the connection weights and biases.
Then, the architecture of BPN for estimating cement
take was built (see Fig.5). The accuracy for the
training and testing data sets are described by the
degree of correlation between output target values
and actual values. The scatter of the target output
Lg values versus the actual output Lg values
were assessed using regression analysis and its
degree of correlation of 0.82 was an acceptable one

5. Estimated results of cement take


According to the different zones of the dam
foundation, use the data of grout sections in the
second half of the grout-curtain construction as the
input variables. Key the input variables of each grout
section into the BPN program with the architecture as
shown in Fig. 5 to predict the Lg value of that
grout section and further to obtain its cement take.
Repeat the prediction process described above one by
one until all of the grout sections have been covered.
Then, calculate the sum of cement take for all the
grout sections to get the estimated gross cement take.
The estimated accuracy levels of BPN method are
78.2%, 81.4%, 71.9% and 75.6% for the left upper
zone, the left lower zone, the right upper zone, and
the right lower zone respectively. The average
estimated accuracy for the four zones is 75.3% (see
Table 3).

6. Summary and conclusions


This study adopted the BPN method to estimate
the cement take needed for the grout improvement on
the Li-Yu-Tan dams foundation. The level of
average estimated accuracy on gross cement take is
75.3%. This level is higher than the designed level of
43.4% calculated in Table 3. Because the BPN
method takes into consideration the effects of factors
on Lg , such a structure, which naturally increases
the level of estimated accuracy. However, the
construction of the network, testing and data input
process still tend to be more time-consuming.
Moreover, its estimation tool is a network program
instead of just a regression equation. It must be
declared that the coefficients in Fig. 5 are only
suitable to the Li-Yu-Tan dam. The method
mentioned above can be applied in other situations
only when using the data collected from the
completed parts of the grouting to estimate the rest of
the grout take at the same site.
Acknowledgements

Thanks are expressed to the National Science


Council, Taiwan (NSC85-2211-E-216-004), for
research funding and to the Water Resources Agency,
Ministry of Economic Affairs, Taiwan, for the data
collection.

13.

References

14.

1.

Baker, W.H. (1982), Grouting in geotechnical


engineering, American Society of Civil
Engineers.
2. Jaroslavl, I. (1989), Rock grouting and
diaphragm wall construction, Elsevier Ltd..
3. Houlsby, A.C. (1990), Construction and design
of cement grouting a guide to grouting in
rock foundations, John Wiley & Sons, Ltd..
4. JSIDRE (1994), The fundamental knowledge on
grouting, Japanese Society of Irrigation,
Drainage and Reclamation Engineering,
Tokyo. (Japanese)
5. Ewert, F.K. (1985), Rock grouting with
emphasis on dam sites, Springer-Verlag Ltd.,
Berlin, Heidelberg, Germany.
6. Weaver, K. (1991), Dam foundation grouting,
Library of Congress Catalog, Card No. 9134635, American Society of Civil Engineers.
7. Yamaguchi, Y. and Matsumoto, N. (1989),
Permeability and Lugeon values of dam
foundation, Journal of Japan Society of Civil
Engineering, 12(412), 51-60.
8. Hirota, Y., Takebayasi, S. and Shibata, I. (1990),
Prediction of grout take in dam
foundation
grouting - a case of Granite -, Journal of Japan
Society of Civil Engineering, 13(421), 195-202.
9. Taiwan Water Resources Agency (1993),
Construction completion report of foundation
grouting on Li-Yu-Tan Dam, Water Resources
Agency, Ministry of Economic Affairs, Taiwan,
Ch.4.
10. Taiwan Water Resources Agency (1986a),
Report of fundamental design on Li-Yu-Tan
Dam construction, Water Resources Agency,
Ministry of Economic Affairs, Taiwan, Ch.3.
11. Kutzner, C. (1985), Consideration on rock
permeability and grouting criteria, 15 th
International Congress on Large Dams,
Lausanne, Q.58, R.17.
12. Shibata, I. (1989), The determination of a
rational injection pressure related to in-situ stress

15.

16.

17.

18.

19.

20.

21.

22.

23.

in dam foundation grouting, Journal of Japan


Society of Civil Engineering, 16(436), 121-130.
Taiwan Water Resources Agency (1986b),
Construction and design of grouting, Water
Resources Agency, Ministry of Economic
Affairs, Taiwan, Ch.4.
Ennto, M. (1988), Foundation grouting and cutoff in IRIHATA dam, The Dam Digest, Japan
Dam Foundation Society, No. 520-2, 9-26.
(Japanese)
Tano, S. (1988), Foundation grouting in
TENZAN dam. The Dam Digest, Japan Dam
Foundation Society, No. 520-4, 53-83.
(Japanese)
Goh, A.T.C. (1994), Seismic liquefaction
potential assessed by neural networks, Journal of
Geotechnical Engineering, American Society of
Civil Engineers, 120(9), 1467-1480.
Goh, A.T.C. (1995), Back-propagation neural
networks for modeling complex systems, Journal
of Artificial Intelligence in Engineering, Elsevier
Ltd., 9, 143-151.
Schaap, M.G., Leij, F.J. and van Genuchten,
M.T. (1998), Neural network analysis for
hierarchical prediction of soil hydraulic
properties, Journal of Soil Science Society of
America, 62( 4), 847-855.
Huang, Y. and Wanstedt, S. (1998), The
introduction of neural network system and its
application in rock engineering, Engineering
Geology, Elsevier Ltd., 49, 253-260.
Ellis, G.W., Yao, C., Zhao, R. and Penumadu, D.
(1995), Stress-strain modeling of sands using
artificial
neural
networks,
Journal
of
Geotechnical Engineering, American Society of
Civil Engineers, 121(5), 429-435.
Zhu, J.H., Zaman, M.M. and Anderson, S.A.
(1998), Modeling of shearing behavior of a
residual soil with recurrent neural network,
Journal of Numerical and Analytical Methods in
Geomechanics, John Wiley & Sons Ltd., 22,
671-687.
Yang, C.P. (2002), Modeling of shear behavior
of saturated OTTAWA sands with backpropagation networks, Journal of Chinese
Institute of Civil and Hydraulic Engineering,
14(2), 175-180.
Yeh, I. C. (1997), Application of artificial neural
network. Ju-lin Ltd., Taiwan, Ch.1~Ch.4.

Table 1 Number of grout holes and grout sections at each zone of the grout-curtain
Zone

Sequence

Primary
Secondary
Left upper zone Tertiary
Quaternary
Supplementary
Inspection
Primary
Secondary
Left lower zone Tertiary
Quaternary
Supplementary
Inspection
Primary
Secondary
Right upper
Tertiary
zone
Quaternary
Supplementary
Inspection
Primary
Secondary
Right lower
Tertiary
zone
Quaternary
Supplementary
Inspection
Sum

Number of grout
holes
11
9
20
36
11
14
15
15
30
51
3
14
16
15
30
52
28
20
9
9
17
26
4
14
469

Total length of
grout holes
591
543
1,158
1,869
540
739
828
826
1,655
2,326
166
772
976
987
1,949
3,029
1,422
1,193
480
472
906
879
221
749
25,276

Number of grout
sections
83
76
163
262
76
104
108
108
216
303
22
101
133
134
265
412
194
162
79
78
150
145
37
124
3,532

Table 2 Codes of input variables for BPN analysis.


Zone of dam Code Type of rock layer
foundation
Left upper
1 Clean sandstone
zone
Right upper
2 Mudstone
zone
Left lower
3 Alternation with
zone
sandstone and shale
Right lower
4
zone

Code Injection pressure (


kPa )
1
0~200

Code Depth of grout Code


section ( m )
1
0~20
1

201~400

21~40

401~600

41~60

601~800

61~80

801~1,000
1,001~1,200

5
6

81~100

Table 3 Amount of gross cement take at each zone for the second half of the grout-curtain construction.
Item

Left upper
zone

Left lower
zone

Right upper
zone

Right lower
zone

Sum for
four zones

2,721

3,287

4,778

1,854

12,638

296,126

228,512

670,533

262,223

1,457,393

136,050

164,350

238,900

92,700

631,900

231,570

186,007

482,034

198,156

1,097,767

(3)
(%)
( 2)

45.9

71.9

35.6

35.3

43.4

( 4)
(%)
( 2)

78.2

81.4

71.9

75.6

75.3

Zone

Total length of grout holes (


m)
(1)
Gross cement take ( kgf )
(construction)
(2)
Gross cement take ( kgf )
(1) 50( kgf / m )
(design)
(3)
Gross cement take ( kgf )
(BPN method)
(4)

Estimated
Accuracy
levels

Fig. 1. Longitudinal section of the Li-Yu-Tan dam indicating the rock layers in dam
foundation (CS=clean sandstone, MS=mudstone, AL=alternation of sandstone
and shale).

Fig. 2. Characteristic zones of the grout-curtain in the dam foundation.

Original ground surface

Crest

Grouting tunnel

Design excavation surface

Dam

Grouting tunnel

Grouting hole

Fig. 3. Longitudinal section of the Li-Yu-Tan dam indicating the extent of the grout-curtain.

Input layer

Hidden layer

Output layer

net
c

h3

_
X

1
W

13

13

h3

h3

3
W
W

14

h3

14

23

23

35

net

35
3

45

W
X

W
W

24

45

24

net
c

h4

h4

h4

h4

Fig. 4. Typical BPN architecture.

y5

y5

y5

y5

Input layer
Region

Kind of rock

Injection pressure

Depth of grout hole

Lu

Hidden layer

Ouput layer

10

Lg

Weights and Biases


item
node 5
node 6
node 7
node 8
node 9
node 10

node 0
weight
0.34
0.18
0.23
-0.22
-0.17

node 1
weight
0.59
-0.81
-1.24
2.01
2.32

node 2
weight
0.92
0.50
-0.71
-1.24
0.63

Node3
weight
-0.52
-1.09
-0.14
0.45
-0.16

node 4
weight
1.57
1.74
1.48
1.74
1.36

Fig. 5. Architecture of BPN for estimating Lg

node 10
weight
-0.79
-0.63
-0.35
-0.36
-0.36

biases
0.95
0.04
0.79
0.84
0.36
0.50

You might also like