Professional Documents
Culture Documents
Conditions of Contract
Ioannes Tang
Senior University Teaching Fellow
Department of Civil Engineering
Faculty of Engineering
Room: B1C16, Telephone: 03-8924 8346
Email: Ioannes.Tang@nottingham.edu.my
Introduction
Construction projects involve a number of companies
(parties) doing work they are responsible for
Links between parties identify the roles and
responsibilities and have a legal context
Explicit links are contracts or agreements
Some legal rights exist when no contract exists
Contracts often use standard clauses and terms
expressed in standard forms of contract
The contract must fit into the prevailing legal system
We will look at two standard contracts
2
Parties to Contract
The key parties to a main construction
contract are:
client (or Employer)
contractor
Conditions of Contract I
Particular clauses will be examined in:
New Engineering Contract Engineering and
Construction Contract Edition 3 (NEC ECC)
ICE Conditions of Contract (7th ed) (ICE 7)
Conditions of Contract II
Others include:
JCT,
FIDIC,
Design and Construct,
Small Works,
Subcontracts,
Framework contracts,
Terms of engagement
7
ICE7 Clauses
71 specific clauses
5-7
Contract documents
8-35 General obligations
12 Adverse physical conditions and artificial obstructions
14 Programme to be furnished
17 Setting out
32 Fossils etc
41-46 Commencement time and delays
51-53 Alterations additions and omissions
55-57 Measurement system
60-61 Certification and payment
66
Avoidance and settlement of disputes
8
13 - Work to be to satisfaction of
Engineer
13(1)
Save insofar as it is legally or physically impossible
Contractor shall construct and complete in strict
accordance with the Contract to the satisfaction of the
Engineer (whether mentioned in the Contract or not).
13(3) covers Delay and extra cost and in addition to the
above refers to clauses 5, 44, 51, 53, 60
44 - Extensions of time
51-53 Variations
51 - allows for any variation necessary with a
variation defined as additions, omissions,
substitutions, alterations to quality, form,
character, kind, position, dimension, level or
line
52 - covers the valuation of ordered variations
53 - covers procedure for additional payments
11
12
66 Disputes
66(2) - If the Contractor or Employer are dissatisfied
with anything the matter shall be referred to the
Engineer who shall notify his decision to the
Employer and Contractor within one month
66(3)&(4) - mentions decision of Engineer and/or
adjudicator
66(5) - covers conciliation procedure
66(6)-(8) - cover adjudication procedure
66(7)-(11) - covers arbitration procedure
THIS IS A KEY RISK SHARING CLAUSE
13
14
NEC3 Structure
Contains core clauses 1-9
And 6 option clauses A-F
And 18 secondary option clauses X-Z (X17, X12-18, X20,
Y(UK)2, Y(UK)3, Z
And dispute resolution clauses W1, W2
It includes a partnering option (X12)
17
Choosing NEC3
Firstly choose either:
A priced contract (with activity schedule or bill of
quantities) (A or B)
A target contract (with activity schedule or bill of
quantities) (C or D)
A cost reimbursable contract (E)
A management contract (F)
18
General
Contractors main responsibilities
Time
Testing and defects
Payment
Compensation events
Title
Risks and insurance
Termination
19
NEC3
Clause 1
10.1 shall act in a spirit of mutual trust and cooperation
NEC3
Clause 3
31 Programme to be submitted [cf. ICE 7 clause 14]
Clause 5
50 Assessment of amount due [cf. ICE 7 clause 52, 55-57]
51 Payment of amount due [cf. ICE 7 clause 53, 60]
21
NEC3
Clause 6
60 Compensation events [cf. several ICE 7 clauses]
61 Notification
[cf. ICE 7 clauses 51-53]
62 Price quotations
[ditto]
63 Assessing
[ditto]
64 Project managers assessments [ditto]
65 Implementing
[ditto]
22
26