Professional Documents
Culture Documents
MAINTENANCE,
AND
REHABILITATION
RESEARCH PROGRAM
TECHNICAL
REPORT
REMR-CO-3
Report
PACIFIC
by
SION
January 1988
Report 1 of a Series
Approved
Release; Distribution
Unlimited
Prepared
Under
For Public
for
Unclassified
ACCESSION NO
This report is the first in a series of case histories of US Army Corps of Engineers
(Corps) breakwater and jetty structures at nine Corps divisions. Herein, case histories are
presented for 28 breakwater and jetty structures located within the US Army Engineer Division, South Pacific (SPD), which encompasses the entire California shoreline. Presently,
there are approximately 171,870 lin ft of breakwater and jetty structures managed by SPD.
These structures are predominantly of rubble-mound construction. Twenty-one of the projects
have undergone repair and/or modification during their lifetimes. A variety of repair
methods have been utilized including replacement and/or addition of armor stone, placement
of concrete armor units, and use of concrete and concrete caps.
LO DISTRIBUTION IAVAILABILITY
[XIUNCLASSlFlEDIUNLIMlTED
OF ABSTRACT
SAME AS RPT
0 DTIC
Unclassified
USERS
I
SECURlTV CLASSIFICATION OF THIS PAGE
Unclassified
Unclassified
ECURITY CLASSIFICATION OF THIS PAGE
IO.
.I
Unclassified
SECURITY CLASSIFICATION OF THIS PAGE
PREFACE
This report was prepared as part of the Coastal Problem Area of the Repair, Evaluation, Maintenance, and Rehabilitation (REMR) Research Program.
The work was carried out jointly under Work Unit 32278, "Rehabilitation of
Rubble-Mound Structure Toes," of the REMR Program and Work Unit 31269, "Stability of Breakwaters," of the Civil Works Coastal Area Program. For the REMR
Program, Problem Area Monitor is Mr. John H. Lockhart, Jr., Office, Chief of
Engineers (OCE), US Army Corps of Engineers (Corps).
CONTENTS
.................................................................
CONVERSION FACTORS. NON-SI TO SI (METRIC) UNITS OF MEASUREMENT ...........
PART I:
INTRODUCTION ...................................................
Background .........................................................
Purposes ...........................................................
PART 11: SUMMARY OF CORPS BREAKWATERS AND JETTY STRUCTURES IN SPD .......
REFERENCES ...............................................................
PREFACE
Page
1
3
4
4
4
6
61
By
cubic yards
feet
miles (US s t a t u t e )
pounds (force)
square f e e t
t o n s (2,000 l b f o r c e )
0.7645549
0.3048
1.609347
4.448222
0.09290304
8896.443353
To O b t a i n
cubic metres
metres
kilometres
newtons
square metres
newtons
PART I:
INTRODUCTION
Background
1.
2. The purposes of this report are to provide insight into the scope,
magnitude, and history of coastal breakwaters and jetties under CE jurisdiction; to determine maintenance and repair history; to determine methods of
construction; to make this information available to CE personnel; and to
address objectives of the Repair, Evaluation, Maintenance, and Rehabilitation
(REMR) research program. To accomplish these objectives, case histories of CE
breakwaters and jetty structures have been developed to quantify past and
present problem areas (if any), to take steps to rectify these problems, and
to subsequently evaluate the remedial measures. General design guidance can
be obtained from the solutions that have been most successful. Information in
this report should be of particular value to CE personnel in the US Army
4
3.
A table of factors for converting non-SI units of measurement to SI (metric) units is presented on page 3 .
+,
S311W NI 3 1 V 3 S
6
WOB8VH h383LNOMI
.
83AIW OhON
i
i
6
l
UORRO BAY H A
GO
'L.
-1
PORT SA
.--
--*--
VI
'4O
Ob1
.Lt3
SANTA BARBARA
CHANNEL 1
T'
SAN BERNARDINO
TURA MARINA
d
.ANDs HARBOR
x
LOS ANGELES-LO!
Q
0
t U
A+-----
OCEANSIDE HARBOR
SAN /DIEGO
I
I
aD
-
Figure 2.
I
I.
<
Curren 1983; Dai and Jackson 1966; Davidson 1969; Davidson 1971; Jackson 1961;
Markle 1983; Senter 1971; Senter and Brasfeild 1968; US Army Engineer Waterways Experiment Station 1953, 1956; Wilson 1965, 1966, 1967).
6. Case histories for SPD's breakwater and jetty structures are shown in
Tables 1-28. Structure alignments and cross sections are included also as
Figures 1-35 accompanying the various tables. General characteristics of
these structures are shown in the following tabulation:
Table
1
2
3
4
5
6
7
8
9
10
Location
Crescent City Harbor
Humboldt Harbor and
Bay
Noyo River and Harbor
Bodega Harbor
Richmond Harbor
Berkeley Marina
Oakland Harbor
San Leandro Marina
Fisherman's Wharf
Harbor
Gas House Cove
12
Halfmoon Bay
Santa Cruz Harbor
13
14
Moss Landing
Monterey Harbor
15
11
16
Cumulative
Structure
Length, ft
6,270
9,600
Date
of
Origin
Improvementt
1920
1889
M, R
M, R
579
4,048
1924
1943
R
M, R
10,000
1923
1965
1921
1977
1985
R
M
N
N
N
1975
1961
1963
1947
1932
1943
1913
1,165
21,500
700
1,917
117
8,090
1,975
1,230
1,700
3,717
2,400
M
R
R
M
M, R
R
(Continued)
**
Table
17
18
Location
Santa Barbara Harbor
Ventura Marina
Cumulative
Armor Structure
Type** Lenath , ft
S
2 ? 365
S,Tr
4,075
Date
of
Origin
1928
Improvemen tt
M
1963
4,870
1959
20
Channel Islands
Harbor
Port Hueneme
1,800
1940
21
5 ? 090
1965
N
M
22
4 ? 885
1958
M? R
43 ? 002
1898
M,
24
25
26
4 ? 480
7,750
1,350
1934
1968
1961
N
R
M
27
9 ? 620
7 ? 500
1949
1894
M? R
R
19
23
28
7. These tables (Tables 1-28) summarize the construction and rehabilitation histories of SPD's structures. Current and more specific data at a
particular site may be obtained from the latest complete summary condition
survey report through SPD's district offices for readers who need additional
information.
10
Table 1
Crescent City Breakwater
Crescent City Harbor, California
Date( s )
1920-
1926
19281930
1931
1939
1946
1948
19481949
1950
19501951
1952
(Continued)
Table 1 (Continued)
Date(s)
1957
1957-
1964
1973
1974
1974
1979
1983
1984
1986
XI
SCALE IN FEET
F i g u r e 3.
C r e s e n t C i t y Harbor, C a l i f o r n i a
13
HARBOR
OCEAN
HARBOR
OCEAN
HARBOR
OCEAN
CONC CAP
5TON STONE
ELt200
10 TON STONE
I TON STONE
(CORE)
CROSS SECTION
STA. O+OO TO STA. 29+00
5 TON STONE
OUTER BREAKWATER
__
OCEAN
HARROR
/
A
&
CROSS SECTION
STA. 29+00, T O STA 34t70
CROSS SECTION
STA 34+70 TO STA 37+00
OUTER BREAKWATER
OUTER BREAKWATER
HARBOR
STA 36+70T039+70
STA 39+70TO 41+20
I
CROSS SECTION
STA 3 7 + 0 0 TO STA 41+20
OCEAN
.20.$
OCEAN
HARBOR
(4T06TONSI
5 TON STONE
I.-'
TON STONE
ISPALLS TO 4 TONS)
CROSS SECTION
SAND BARRIER
CROSS SECTION
STA. 41t20 TO STA. 46+70
OUTER BREAKWATER
OUTER BREAKWATER
OCEAN
22'
HARBOR
OCEAN
EXISTING DOLOSSE
HARBOR
-/
EL.290
CROSS SECTION
SECTION A-A
INNER BREAKWATER
(400' EXT E NSI0N)
Figure 4.
CROSS SECTION
SECTION B-B
INNER BREAKWATER
EXISTING
MA?ERIAL
Figure 5.
15
Table 2
Humboldt Bay J e t t i e s
Humboldt Harbor and Bay, C a l i f o r n i a
Date( s )
18891899
C o n s t r u c t i o n and R e h a b i l i t a t i o n History
The i n i t i a l c o n s t r u c t i o n o f t h e n o r t h and s o u t h j e t t i e s was comp l e t e d a t t h e s i t e ( F i g u r e 6 ) during t h i s time frame. The s o u t h
j e t t y was 4,000 f t long w i t h a +lO-ft m l l w crest e l . The oceans i d e s l o p e was 1 V : 2.658, and t h e channel- side s l o p e was 1V:2.25H.
The n o r t h j e t t y was c o n s t r u c t e d t o a l e n g t h o f 1,500 f t w i t h a
crest e l o f +12 f t m l l w . The ocean- side s l o p e was 1V:2.42H, and
t h e channel- side s l o p e was l V : 1 . 8 5 H .
S t o n e s used i n t h e j e t t i e s
were composed of rock up t o 8 t o n s i n weight. The j e t t i e s termin a t e d a t approximately t h e 18-ft contour.
1goo1907
191 11915
1915
19251927
T a b l e 2 (Continued)
Date( s )
19311932
Construction and R e h a b i l i t a t i o n H i s t o r y
Extensive r e p a i r s were made t o t h e o u t e r ends o f both j e t t i e s .
Precast c o n c r e t e blocks ( 4 by 9 f t ) were used i n l i e u o f s t o n e and
p i l e d one on t o p of a n o t h e r f o r c o n s t r u c t i n g t h e forms f o r c o n c r e t e
monoliths. North j e t t y r e p a i r s u s i n g 1,200 cu yd of c o n c r e t e * were
completed i n 1931 a t a Cost of $53,246. I n 1932 n o r t h j e t t y rep a i r s u s i n g 266 cu yd of c o n c r e t e and s o u t h j e t t y r e p a i r s u s i n g
15,986 cu yd o f c o n c r e t e were completed f o r $247,038.
1933
1935
1936
1937
1939
1940
1941
1942
1943
(Continued)
17
Table 2 (Continued)
Date(s)
1944
$56,740.
1945
1950
The south jetty was breached over a 70-ft span on the sea side.
Side slopes were reconstructed with mass concrete to conform to
existing adjacent slopes to el of +18 ft mllw.
1951
1952
1957
19571958
1958
Major damage was sustained on the channel side of the north jetty.
The total length of damage on the jetty was 410 lin ft at five
locations. Also, the concrete monolith at the outer end of the
structure was completely devoid of stone or concrete protective
side slopes at this time. Major damage to the south jetty had
similarly occurred. Breaches through the center section had occurred at two locations with major loss of side slopes at three
locations. The concrete monolith at the outer end was exposed in a
manner similar to that of the north jetty. The condition of the
jetties at this point was not due to a specific storm but represented deterioration over a period of years. Tetrapods weighing
25 tons were placed on the north jetty and 15 tons on the south
jetty, all on a slope of 1V:1.5H. North jetty repairs using
611 cu yd of concrete and 1,540 tons of stone were completed for
$100,418.
Severe winter storms deteriorated the north and south jetties to
such an extent that repair work constituted a major construction
project.
Mass concrete was poured to fill eroded areas on crests, and armor
stones were replaced in areas that were breached and washed out.
Concrete blocks (11 by 1 1 ft) weighing 100 tons and 12-ton tetrahedrons were placed on the heads of both jetties.
1959
Major side slope losses on the south sides of both the north and
south jetties occurred.
19601963
18
Table 2 (Continued)
Date( s )
1963-
Winter storm waves washed away most of the newly placed 100-ton
concrete blocks.
The concrete monolith at south jetty was undermined and broken.
Heads of both jetties were totally destroyed.
Rehabilitation of both jetties was completed. Concrete monoliths
were reconstructed, and 42-ton dolosse were placed around the seaward quadrant of both jetty heads. Four unreinforced, 1,271 steelreinforced, and 17 steel-fiber-reinforced dolosse were placed on
the north jetty; and 22 unreinforced and 1,423 steel-reinforced
dolosse were placed on the south jetty head. Dolosse (43-ton) also
were placed on the shoreward transition sections o f both jetty
heads. Two layers of dolosse were placed using a concentration of
1 1 dolosse per 1,000 sq ft of Slope. Cost of this work was
$10,108,764. Model testing was conducted prior to these repairs
(Davidson 1971).
South jetty repairs using concrete and stone were completed at a
cost of $20,400.
An earthquake of 5.2 magnitude on the Richter scale occurred near
the site. Inspection trips subsequent to the earthquake revealed
fresh cracks along the south jetty running along the edges of the
crest and slope for a distance of about 800 ft on the channel side
and 300 ft on the seaward side. Blowout holes also were observed
at several locations on the south jetty. On the north jetty, three
of the dolosse had moved about 50, 100, and 150 ft from the placement area, respectively. Only minor settling of the remaining
dolosse had occurred, and no cracking or unraveling of the dolos
units was apparent.
South jetty repairs using concrete and rock were completed. Approximately 15,000 tons of stone ranging from 1 to 20 tons were
used for these repairs.
The jetties were subjected to severe storms combined with high
tides and winds. On occasion, waves covered both jetties over
their entire lengths. Waves also were observed breaking over the
dolosse and concrete monoliths of the jetty heads. North jetty
repairs using stone were completed at a cost of $450,000.
1965
19691970
19711972
1973
1975
1977
19771978
(Continued)
19
Table 2 (Concluded)
Date( s )
1978
1983
1984
1985
q50
c,(->
,1
iP <
,%.
20
Figure 6.
21
Table 3
Noyo Jetties
Noyo River and Harbor, California
Date(s)
1924
1931
1945
1954
1961
1962
1970
1983
1986
was authorized
(Figure 7). This structure has not been constructed.
The two outer breakwaters authorized by the Acts of 1945 and 1962
were reclassified from an active to inactive category. They were
not economically feasible because of the high cost of construction
and maintenance. Model testing of the structures was conducted
(Wilson 1967).
Restoration of the north jetty head was completed. Materials used
consisted of approximately 2,500 tons of capstone, 10 cu yd of concrete, 1,500 cu yd of sandfill, and 4,100 tons of quarrystone fill.
The jetties are presently in good condition. Model testing currently is being conducted to optimize the location of a structure in the immediate area of the River entrance (Bottin, in
preparation).
A 500-ft-long outer rubble-mound north breakwater
22
Table 4
Bodega Harbor Jetties
Bodega Bay, California
Date( s )
1943
1961
1985
1986
24
Table 5
Richmond Harbor BreaKwaLer
Richmond Harbor, San Francisco Bay, California
Date(s)
19231931
1967
1985
Construction
and Rehabilitation
History
Construction
of a lO,OOO-ft-long breakwater (also referred to as a
training
wall) was completed (Figure 10) during this time frame.
The seaward 3,000-ft-long
portion of the breakwater had a IO-ft
Side slopes were lV:1.5H.
crest width and a lo-ft mllw crest el.
The remaining portion of the breakwater entailed a IO-ft mllw crest
el and a 4-ft crest width.
Side slopes were lV:2H on the bay side
and lV:1.5H on the channel side.
Rehabilitation
of the breakwater was performed.
The extent of the
work is not known, however.
The breakwater again underwent repairs and is considered to be in
good condition.
San
25
Table 6
Berkeley Marina Breakwater
Berkeley Marina, San Francisco Bay, California
Date(s)
1936
1965
19'75
1980
1986
CROSS SECTION
SHEETPILE BREAKWATER
2
g p
- -
100
S A400
L L 6W 8 9 0 F
26
Table 1
Oakland Harbor Jetties
Oakland Harbor, San Francisco Bay, California
Date( s )
1921-
1927
1962
1986
A L A M E D A
_.
ISLAND
rJ
90
5000
SCALE IN FEET
0
I
5000
&
27
Table 8
San Leandro Marina Breakwater
San Leandro Marina, San Francisco Bay, California
Date( s )
1963
1966
1977
1986
r
1'
o
,*"
TOP SOIL
MITERUL
100 LB STONE
NOT T O SCALE
BREAKWATER CROSS SECTION
TRUE SCALE
28
Table 9
Fisherman's Wharf Breakwaters
Fisherman's Wharf Harbor, San Francisco Bay, California
Date(s)
19851986
110'-
OLIO S H E E T P I L E
BREAKWATER WITH
WALKWAY I 5 0 9 - F T - U ) N t
- N-
T Y P I C A L BREAKWATER
CROSS SECTION
WEST SIDE
SEGMENTED
BREAKWfiiER
258-Fi~LONG
SCALE IN FEET
IW 0
200
400
29
Table 10
Gas House Cove Breakwater
Gas House Cove, San Francisco Bay, California
Date(s)
1965
1975
1986
SAN
FRANCISCO
- N-
BAY
[NEW
117' BREAKWATER
610, BREAKWATER
SCALE IN FEET
JOO
200
100
390
Table 1 1
Halfmoon Bay Breakwaters
Halfmoon Bay, California
Date(s)
1961
19611964
1967
1986
31
Seoword Side
-. .._
7
L1~15.U
~
.-
Horbor Side
MLLW
Seoword Side
\ 1.5
F I-16n
r , A,.
I
Seoword Side
,*$I.
15.0'
IOTon Stone
Elt3.0
Horbor Side
ORIGINAL BREAKWATERS
II
F i g u r e 16.
MLLW
5Ton Stone
Horbor Side
Seaword Side
Horbor Side
Halfrnoon Bay, C a l i f o r n i a
32
Table 12
Santa Cruz Jetties
Santa Cruz Harbor, California
Date( s )
1963
1983
1986
.'
33
Figure 17.
Figure 18.
34
Table 13
Moss Landing Jetties
Moss Landing Harbor, California
Date(s)
1947
1949
19491965
19661967
1975
1976
1986
A basis for design of repairs to the jetties and revetment was prepared. Estimated cost of these repairs was $290,000, and approximately 7,400 tons of stone would be required.
Work is still required at the jetty heads. Except for the erosion
at these locations, the jetties historically have performed satisfactorily and suffered relatively minor damages.
35
CHANNE
500
500 -
36
lOq0
Table 14
Monterey Breakwater
Monterey Harbor, California
Date(s)
1932
1934
1960
1969
1974
1986
37
MONTEREY HARBOR
CALIFORNIA
500
500
I---u
1000
I
4 TON STONE
CROSS SECTION
O t O O TO 1 3 t O O
OCEAN
HARBOR
4 TO 12 T O N S T O N E = ~ ~ ~ + I ~
ELT16
2 TO 4 TON STONE
C R O S S SECTION
43t0O TO 17+00
38
Table 15
Morro Bay Breakwaters
Morro Bay Harbor, California
Date(s)
1942
1943
19431944
1945
1946
1948
19491960
1964
1983
1985
1986
A 1,000-ft-long north breakwater was constructed, and a 1,832-f~long south breakwater was completed at the site (Figure 21) to
serve as a base for naval patrol craft. The structures were
rubble-mound and built at an el of +16 ft mllw with 1V:1.5H side
slopes and a crest width of 16 ft.
Storm waves during this period damaged the north breakwater. The
south breakwater received no appreciable damage.
The north breakwater was repaired and extended to 1,800 ft in
length. This work also included widening the crest from 16 to 20
ft. The project was adopted and completed under the supervision of
the CE using funds provided by the US Navy.
The north breakwater again suffered damage from storm waves.
Maintenance work was performed on the north breakwater. Damaged
sections of the structure were restored, and the cap was bound with
concrete across the crest to an el of -2 ft mllw on both sides.
The north breakwater continued to deteriorate, and shoaling occurred in the channels. The south breakwater still had suffered no
observable damage since its construction in 1943.
The north breakwater was reconstructed at a cost of $1,561,882.
The new rubble-mound structure was built at an el of +18 ft mllw,
with a 20-ft-wide crest and 1V:2.5H side slopes. The structure was
rebuilt about 100 ft bayward of the original north breakwater location and extended to 1,885 ft in length (Figure 21). The breakwater included larger armor stone than the original structure.
Also included was a concrete monolithic breakwater head. Model
tests were conducted (Jackson 1961).
Major storms resulted in approximately $1,430,000in damages to the
breakwaters.
Maintenance repair of the north and south breakwaters was completed
which included the placement of approximately 18,000 tons of
capstone. Capstones ranged in weight from 6-21 tons each.
The structures presently are in good condition.
39
IW
f
W
bi
40
Table 16
Port San Luis Breakwater
Port San Luis, California
Date( s )
18881913
1924
1927
1931
1935
1976
1983
1984
1986
41
-N-
dccoUNTY
HARBOR SIDE
OCEAN SIDE
'UNION OIL
COMPANY
PIER
PORT SAN
LUIS WHARF
5
\
WHALER
ISLAND
F i g u r e 22.
Port San L u i s , C a l i f o r n i a
--
?FEET
Table 17
Santa Barbara Breakwaters
Santa Barbara Harbor, California
Date(s)
1928
1929
1930
1962
1969
1986
HARBOR SIDE
EXISTING BREAKWATER
SCALEO
' -~FEET
&
&
SCALE IN FEET
5 0 0 0
1000
Table 18
Ventura Marina Structures
Ventura Marina, California
Date(s)
1963
1968
1971
1972
1986
45
OCEAN SIDE
CHANNEL SIDE
.o
9
...
c
0
A
/
..
0
..
ch
._'
.. .
I -'
F i g u r e 24.
Ventura Marina, C a l i f o r n i a
Table 19
Channel Islands Structures
Channel Islands Harbor, California
Date( s 1
1959
1960
1986
Figure 25.
47
Table 20
Port Hueneme Jetties
Port Hueneme, California
Date( s)
19391940
1968
1986
" A .
-\
'
'2,
PACIFIC
OCEAN
SCALE I N F E E T
200
Figure 26.
48
YO
Table 21
Marina Del Rey Structures
Marina Del Rey, California
Date( s )
1965
1986
49
Table 22
Redondo Beach Breakwaters
Redondo Beach King Harbor, California
Date( s)
1938
1950
1958
1960
1963
1964
19781980
1982
1983
1986
50
HARBOR SIDE
O C E A N SIDE
13 TON CAPSTONE
S T I 36+00-52+00
(NORTH BREdlXWATER1
OCEAN SIDE
PACIFIC OCEAN
\.:
F i g u r e 28.
51
Table 23
Los Angeles and Long Beach Breakwaters
Los Angeles and Long Beach Harbors, California
Date( s )
18981910
19301938
19421960
1947
1983
1986
52
Table 24
Newport Bay Jetties
Newport Bay Harbor, California
Date( s )
1934
1986
.-...
SCALE
1000
-.-
1000 2000
4000FT
\
\
Figure 31.
54
Table 25
Dana Point Breakwaters
Dana Point Harbor, California
Date( s)
1968
1983
1984
1986
55
Table 26
Oceanside Jetties
Oceanside Harbor, California
Date(s)
1958
1961
1968
1986
56
Table 27
Mission Bay Jetties
Mission Bay Harbor, California
Date( s )
1949
1955
1959
1970
1986
57
58
Table 28
Zuniga Jetty
San Diego Harbor, California
Date(s)
18941902
1942
19431969
1970
1984
1986
59
PAC/NC
OCEAN
60
REFERENCES
Baumgartner, R. C., Carver, R. D., and Davidson, D. D. 1985. "Breakwater
Rehabilitation Study, Crescent City Harbor California; Coastal Model Investigation," Technical Report CERC-85-8, US Army Engineer Waterways Experiment
Station, Vicksburg, Miss.
Baumgartner, R. C., Carver, R. D., Davidson, D. D., and Herrington, C. R.
1986. "Stability Test of Modified Repair Options for San Pedro Breakwater,
Los Angeles, California; Coastal Model Investigation," Miscellaneous Paper
CERC-86-8, US Army Engineer Waterways Experiment Station, Vicksburg, Miss.
Bottin, Robert R., Jr., Sargent, Francis E., and Mize, Marvin G. 1985.
"Fisherman's Wharf Area, San Francisco Bay, California, Design for Wave
Protection; Physical and Numerical Model Investigation, "Technical Report
CERC-85-7, US Army Engineer Waterways Experiment Station, Vicksburg, Miss.
Bottin, Robert R., Jr., and Acuff, H. F . 1985. "Mission Bay Harbor, San
Diego County, California, Design for Wave and Surge Protection; Coastal Model
Investigation," Technical Report CERC-65-11, US Army Engineer Waterways
Experiment Station, Vicksburg, Miss.
Bottin, Robert R., Jr. In preparation. "Noyo River and Harbor, California,
Design for Wave and Surge Protection; Coastal Model Investigation," Technical
Report, US Army Engineer Waterways Experiment Station, Vicksburg, Miss.
Brasfeild, C. W. 1965. "Selection of Optimum Plan for Reduction of Wave
Action in Marina Del Rey, Venice, California; Hydraulic Model Investigation,"
Technical Report No. 2-671, US Army Engineer Waterways Experiment Station,
Vicksburg, Miss.
Brasfeild, C. W., and Ball, J. W. 1967. "Expansion of Santa Barbara Harbor,
California; Hydraulic Model Investigation," Technical Report No. 2-805, US
Army Engineer Waterways Experiment Station, Vicksburg, Miss.
Carver, Robert D. 1984. "San Pedro Breakwater Repair Study, Los Angeles,
California; Hydraulic Model Investigation," Miscellaneous Paper CERC-64-11, US
Army Engineer Waterways Experiment Station, Vicksburg, Miss.
Chatham, C. E. 1968. "Wave and Surge Conditions after Proposed Expansion of
Monterey Harbor, Monterey, California; Hydraulic Model Investigation," Technical Report H-68-9,US Army Engineer Waterways Experiment Station, Vicksburg,
Miss.
Curren, Charles R. 1983. "Mission Bay Harbor, California, Design for Wave
and Surge Protection and Flood Control; Hydraulic Model Investigation,"
Technical Report HL-83-17, US Army Engineer Waterways Experiment Station,
Vicksburg, Miss.
Dai, Y. B., and Jackson, R. A. 1966. "Designs for Rubble-Mound Breakwater,
Dana Point Harbor, California; Hydraulic Model Investigation," Technical
Report No. 2-725, US Army Engineer Waterways Experiment Station, Vicksburg,
Miss.
Davidson, D. D. 1969. "Stability and Transmission Tests of Tribar Breakwater
Section Proposed for Monterey Harbor, California; Hydraulic Model Investigation," Miscellaneous Paper H-69-11, US Army Engineer Waterways Experiment
Station, Vicksburg, Miss.
61
62