Professional Documents
Culture Documents
25
Discussion
26
DISCUSSION
ON
Fig. 22
SEPTEMBEIL 1934
10th
17th
OCTOBER )P34
NOVEMaER 191+
DECEMBER I934
24th
W
P
Stel fixing
Concreting
Scheduler
Formwork
Sreel flxing
Coneretlng
Preparationof forms
and working drawings
Erearon of formwork
Steel fixing
Concreting
offormwork
Steel fming
Total contract
'W
PICTORILLL
REFRESENTATION
OF -E
SCEEDULB
JANUARY 1935
28
DISCUSSION
ON
29
supported, therefore, directly from t,he walings. With regard to the support of the walings, four angles were shown in Pigs 16. The objection to
that was that itinvolved a rigid arrangement. The walings were S cured
by bolts orscrews to theangles, and i t was almost a physical imposslbility
t o make any adjustment t o the forms a,s work proceeded.
Nr Snow had referred to walls varying in thickness. Walls did not
vary in thickness when the man concerned knew his job, because he corrected t,he forms as work proceeded. That was done by hanging walings
of the yoke, so that thetension went direct to the nut.
straight to the top
Mr Broughton was not certain, from reading the Paper, whether the
or not. Ruskin had
Author believed in havingarchitecturalfeatures
remarked that he would rather have been born blind than live to see some
of them.
Fig. 25 (facing p. 27) showed the type of yoke which was now used.
It had pressed steel legs. The clutch was shown clearly, andthe jack
screw. The wedgesgoing completely round the form wouldbe noted.
Concreting had not pet commenced ; something had happened, and the
draw of t,he staves had had t o be corrected by means of those wedges,
a
Wit,hout pilasters, the building shown in Fig. 26 wouldlooklike
packing case. That building had t,o be in close contact with an existing
building, and had been constructed using the wall of the existing building
as the outside shuttering until reaching the level AB, where the higher
part began. At that point a cut-off hadtaken place. Half theforms
had been left behind, a new side form had been introduced, and concreting had then continued. That was a silo of 17,000 tons capacity ; the bins
were 109 feet deep and there was 30.4 cubic yards of concrete per foot of
heighb-a total of 3,300 cubic yards. The tall building on the right was
172 feet high. The contact surface of the formsfor the concrete was
10,400 square feet ; the wall perimeter, therefore, was 2,600 feet. So far
as labour costs were concerned, it. was a pre-war job. For the forms,
fabricating, erecting, maintaining.anddismantling,the
whole of the
labour costs had been 23.4d. per square foot of form. If 23.4 uses could be
got out of the timber,it,would be seen that the form cost for labour had
been only Id. per square foot. The figureswhich he gave werecertified
costs on which payments had been made.
The jacking costs for the lower part of the building had been 4.4d. per
jack-rodfoot. On reaching the higher part t,he work had become more
difficult ; it wa,s a four-storey building, and the jacking cost had been
6-85d. per foot. The steel hoisting and placing had cost 39s. 10d.-about
S2 per ton. The, concrete had come on the site ready mixed. The hoisting
and placing had cost 2s. 6Bd. per cubic yard. The average progress had
been a t the rate of 11 feet per day, and the bins had been constructed in
10 days, whilst everything shown in the picture had been completed in
about 3 weeks.
The subject of moving formwork was of sufficient importance to justify
e.
30
DISCUSSION
ON
THE DESIGN
AND
CONSTRUCTION
more consideration than had been given to it in the past. The equipment
might be rather costly, but to those who were interested i n construction,
he suggested that the contractors should establish a pool among themselves. Theremight be a poolof,
say,six-hundredjacksandother
fittings necessary, and those who got contracts would draw on thg. pool,
instead of having so much dead material in store year after year.
Mr G. P. Mannings first commentrelated to Airys formula. If
careful regard were givento the premises on which Airy based his results,
it would be seen that therewas a serious discrepancy, and it was surprising
to find that anyone still used Airysresults.
With regard t o sliding shutter work, the method described in the Paper
was not the only one. For example, in one contract the contractor had
a lot of old steel scaffold tubes and a large number of chain blocks, and
had built the scaffold tubes into the walls as he went up, hanging the
chain blocks from them and hoisting the shutters up continuously by that
means. The Author had said that theformwork was constructed for both
sides of the walls. That was not necessarily the case with moving shutter
work, and the inside shutters could be slid and the outside ones brought
up hand over hand. It was possible to slide a single-sided shutter.
The Author had suggested 4-6 feet for the spacing of the jack rods.
In Mr Mannings view, a normal spacing on a straight-forward job would
be about 7 feet, in which case each jack rod supported 56 square feet of
shutters, in addition to a certain amountof decking. It was stated in the
Paper that the shape of the silo should be designed to suit the formwork.
That was so, but it was also necessary to arrange the steel, if sliding shuttering were to be used, so that it could be easily passed underneath the
yokes. That was onedrawback to the hexagonalshape, where the bar
came up the side and turned a t a n angle. So far as the rate of sliding
was concerned, the figures given in the Paper appeared to be on the low
side. A fairly low average for a big job was 9 feet in 24 hours.The
fast,est slide of which he had any personal knowledge was 12g inches in
1 hour and 16 feet in 24 hours. Under really good conditions i t should
be possible to maintain a rate of 1 foot per hour. The
largest figure of
mhich he knew was 72 cubic yards of concrete per footof height, but there
should be no difficulty in sliding jobs two 01three times that capacity.
The highest slide of which he knew was 140 feet, but there should be no
difficulty in reaching 200 feet,. He was not thinking of chimney work but
of silo work as such. The thickest
wallwas 18 inches, and the thinnest
silowall 5 inches. TheAmericansdid notfavour sliding anything less
than 7 inches ; in Britain one should certainly not slide anything less than
6 inches. Mr Snow had already raised the question of how thick a 6-inch
wall was. Those who had seen sliding work could perhaps give a guess.
Mr Snow had also asked whether anybodyhad triedusing steel shutters
on sliding work. Mr Manning said that it had been done, but the application had not been of sufficient interest to give details of it.
31
On the question of the design of silo bottoms, all silo bottoms were
really the same type of design, as shown in Pig. 27, the shaded space being
filled withmassconcrete.Theonlyvariation
was in the height, h. In
a very small silo it p i d to drop the slab so that the small hopper disappeared, but in a very large one it might pay to lift itso that the filling
disappearedand it was practically all hopper. For the normal bin of
12-14 square feet it usually paid to put the slab abouthalf way down.
It was stated in the Paper that the circular shape was more costly to
construct than the hexagonal. That statement was only partly true, over
a restricted range of sizes. In Britain the size of each individual bin in a
battery of silos was fixed by the miller and by milling considerations. The
miller wanted to handle his wheat in batches of 100, 200, or 300 tons, and
Fig. 21
so the engineer made the bins of the size required. In countries such as
Canada,however,whereenormousquantities
of grain were merelystored
until a ship arrived to take the grain away, the circular necked-out shape
was undoubtedly the cheapest.
The American and Canadian silo installations were all very large circular bins.
Mr I. Hey said that he had found a reluctance, particularly in Britain,
t o apply the sliding-form methodt o jobs equivalent to the Authors 3,000ton bunker. The
casewas clearly made out for sliding forms for large
grain-storage silos as used in North and South America. The Author had
stated that the hexagon was the best shape if a number of compartments
for diameters
were required to form a honeycomb inplan, but admitted that
larger than about 18 feet the circular bin was preferable, where the interspace silos could be used. Why should not the inter-space be used in all
cases ? Strangely enough, it was in Britain that engineers questioned the
desirability or advisability of using the inter-space in a run of circular
silos. Jn grain-storage silos where the loads ran up to 1,000 tons in big
bins, there was, as Mr Broughton said, 20 per cent. of the load in the interspace bins, and half that in theend bins. That was the universal practice ;
32
it was only in Brit'ain-or with materials other than grain-that the interspace was not being used, and then it was said that square or hexagonal
bins were more economic than round bins. It was a matter of simple
arithmetic.
He was pleased that Mr Manning had called attention to the type of
hopperconstruction shown in Pig. 27, even though i t meant building
columns from the main slab and st,arting thesliding shuttering higher up,
rather than building the columns and going right through. It was not
possible to go ahead and complete the plan, because the contractor came
back t o build his hoppers and was a long time on those hoppers. With
the slabformation.that difficulty was avoided. Mr Hey thought that
7 metres was an economical size for circular bins of up to 30 metres in
height. In the design, the fact,ors relating to the progress of the job had
to be takeninto consideration. The basis of theadvantage, of sliding
formwork was that by a fair amount of preparation and organization time
was saved on construction. The steel mouth-pieces were easily fitted, but
should not be fitt'ed t o ternplated bolts.
I n Figs 2 a type of construction of hopper bottoms for sticky materials
was shown. It was known from experience that the best answer to the
problem o i handling st,icky materials was t o have t'wo vertical sides. With
two vertical sides he would not say t,hat arching would not occur, but
t,here would be no archingoff a vertical side ; vertical sides would guarantee
the best natural flow. That gave rise to a problem in the slope, but it
was the most st'raight-forward answer and was far better than hanging
the hopper on big bins from the direction of the top of the column. He
had seen building formwork done in record time, 12 feet a day, and then
it had been necessary to wait many months before the floor was free to
start placing the machinery.
It was stated in the Paper that the design had to be correlated with
the machinery and equipment'. Mr Hey looked on storage as compensabion between two systems of transport, from rail to ship or ship back t o
mil, or as compensation between sect'ions of a process, but always in the
sense of compensation. The Canadian and American grain siloswere
compensation as between producer and user and those forms of transport.
The second factor was that, even when use was made of the best methods
of constructing silos or bunkers, they were st.ill very expensive ; therefore
the mechanical handling or machinery process should be the first consideration, because storage was really a secondary function ; i t was the
machinery and plant and process which deteImined the earning capacity.
Simplicity of design for the use of sliding forms would give a good line
and contrast and a good-looking job.
So far as the thickness of the walls was concerned, he advocated a
thickness of 6 inches to give protection against t,he weather, but they had
to Fe good walls. He did not like t o go down lower than 5 inches, because
i t was not possible to ensure a proper cover on the steel ; but it coruld be
i
I
Fig. 30
//
33
time, and there were numerous jobs where it had been done and which
were very satisfactory. How Mr Snow came to have so great a variation
in the thickness of the wall he did not know ; that had not been his own
experience. Perhapsthe formwork had beenweak somewhere inthat
design.
Sliding fornlwork applied to the construction of big grain silos was
well illustrated by the example shown in Fig. 28, which was in the Argentine, and had a storage capacity of 140,000 t,ons, was 92 feet high, with
bins of 18 feet in diameter. It had been done in three lifts, and each of
those two blocks had taken S days to build. The receiving house on the
right was part of the big building. There were bins in between the main
floors, which had been stopped for several hours because they introduced
bin bottoms for dividing t.he bins, bottoms for elevator legs which did not
runrightthrough,andthere
were small walls for the elevators. The
at,oppages had been quite frequent,, but the 60 feet of those bins had been
carried out,fromMonday
afternoon toFriday morning, working with
squads of men of t,wenty-two different nationalities. Since 1932, when it
had been h i l t , i t had handled 1,000,ooOtons of grain a year,andin
October 1947 it received and shipped 200,000 tons of grain in thecalendar
month, which he thought was a record.
Fig. 29 showed a 150,000-ton silo in Buenos Aires ; it was possible to
feedfive ships simultaneously from that plant. Pig. 30 was an example
of moving formwork for a 60,000-ton silo, and Fig. 31 was another view
of the same elevator.
Mr F. G. Etches, dealing with the aesthetics of design, observed that
i t was inferred in the Paper that engineers did not consider sufficiently
the appearance of their structures. Whereas that might have been true
20 years ago, he did not think that it
applied to-day. It was certainly
t,rue that both bunkers and silos needed special thought and care in planning, because large surfaces, unbroken by window or door openings, and
usually without an interesting surface texture, presented certain problems.
That was especially t.rue of silos which were situated near a dock or on
the banks of a waterway, which t,ended to exaggerate their height and to
makc then1 appear out of proport,ion to their surroundings.
One solution was to attempt to create a simple self-contained and
balanced structure which did notdominate its neighbours. Mr Etches
described a nledium-sized silo in which small projecting piers, which were
nladc visihle by the shadows they cast, wereused to give form to the
building. In t.ha,t building there wasno wasted space, and 90 per cent.
of the area, and therefore the volume, was available for useful storage.
Another silo, of the same general arrangement and overall size, had eight
octagonal bins. The shadows on the elevation gave a broken and rather
rest,l(:ss surfacc, whichhe thought was also shown by Figs 17-19 in the
lapt:r----thelatter were hexagord bins, but the sitme point was illustrated.
Rather less than 80 per cent. was available for storage, and that included
3
Downloaded by [] on [06/07/16]. Copyright ICE Publishing, all rights reserved.
34
the small square bins which, for grain storage, were often an advantage.
They stored about one-quarterof the quantity held by the large bins, and
qualities of binned
gavemore flexibilit,y for differentquantitiesand
material,
A circular bin gave probably the most interesting surface, as revealed
byshadows. One such lay-out had 70 per cent. of useful storagearea,
althoughagainsmallbins
were used.Another was a variation of the
square bin, but was improved by the addition of semi-circular piers. If
some justification had to be made for those piers, apart from appearance,
they could enclose rainwaterdown-pipes.
Almost the whole area was
available for storage ; in addition, there was the advantage of small bins,
and the plan cut down the large span of morJtof the walls, cxcept the
outside walls, as shown in Fig. 32.
With regard to the quantity of steel necessary in the bin walls, which
was influenced by the bin shape, the cconomics of any particular lay-out
of bins had to be investigated for each case, but the quantity of steel
mcessary lent itself to somegeneral conclusions. Fig. 33 showed an
dealised curve for a bin of given size, with the quantity of steel plotted
gainst the number of bin sides. The lower part of the curve showed the
tee1 required for ring tension, and was constant for all regular shapes of
in. Mr Broughton had made the point that all bins tended to become
rcular. The upper part of the curve from the dotted line upwards, to
e same scale, showed the steel required to resist bending stresses. That
tuld be maximum for a squarebin,and
was reducedinversely as
.
: square of the bin size ; it, was equal to zero for a circular bin.
The
11 of the t w o ordinates (the total vertical ordinate) would be a measure
;he total quantity of steel needed for any given set of conditions. The
:l required in the hexagonal bin was considerably less than thatfor the
are bin of the same overall size ; in other words, the curve was steep
35
to the left ; but the saving 'was likely to bo very much less for a greater
number of sides.
Fig. 33
COMPARISONOF HOBIZONTAL
WALLSTEELBEQUIBED IOR A GIVEN SIZEOF
BIN FOR VARIOUS GEOMETRIOAL FORME
+ +'
1+&4
were forces andnot pressures, and so the dotted line represented the
resultant (P), PN being the normal and PT the tangential component.
In the Paper there
was no mention of PT, but it was not possible to
ignore it.
By inspection of Fig. 34,
PT=PVSh8-PpaCOS8
PN=PVCOs8+PH8h8
substituting p1 sin 8 and p cos 8 in those equations forP, and
P T = (p-pl) sin 8 COS 8 ; and
PN= p cos2 8 f p sin2 8.
4
Downloaded by [] on [06/07/16]. Copyright ICE Publishing, all rights reserved.
P,,
36
DISCUSSION ON THE
DESIGN
AND CONSTRUCTION
The latter was the expression given in the Paper, and the former was the
expression for the tangential component.
He emphasized the fact that the tangential force had to be t,aken up
somewhere, and the only point where it could be taken up was by friction
being the
on the bottom, so that the angle M could not exceed #-that
friction angle betweenthe material and the bottom. Therefore formula(3)
PT
+ tan$'.
If
Fig. 35
parts of the walls, according to whether or not a deep bin or deep silo
formula was being used, but if, having taken Rankine's or some other value
for the horizontal pressure and the friction on the bottom into consideration, the material still wanted to slide down, it wouldbe necessary t o
increase the lateral pressure ; that could make a considerable difference.
A solution couldbe obtained graphically by makingthe angle tc equal to $'
and getting a revisedvalue for P,, or by equating
37
If the friction angle was going to hold the material against sliding, there
wouldbe a very sluggish discharge, if there were any discharge a t all.
Reference was made in the Paper to the use of glass or similar lining for
the bottom to improve the discharge. In that case, he thought that the
normal pressure which would be taken on the bottom of the bin would not
be the same as if it were a concrete surface.
*** Mr Adolf Fruchtlander thought that the remarks in the Paper
regarding the pressure calculations and two standard formulae of Janssen
and Airy gave the impression that those formulae were more of an
empirical than a theoreticalnature ; that was not so. The basicconstants hadbeen determined, as in all theories of structures, byexperiment.
Jansscns formula had beendeveloped about 50 years agoon a purely
theoretical basis ; it had later been checked on models and buildings by
In Pigs
36,
3,
***
38
Therefore
9dh -
IO
- pp1-U
A " " " "
(2)
P1
a24
U
- = kw - p*.k-p1
. . . . . .
A
&l
(3)
. . . . . .
(1)
. . . . . . . (5)
where
= e-#hulA,
and
U pkh
log N = - __
A ' 2.303'
Fig. 37
'B
V
III practice, for a depth h more than 10-15 feet, N was a large number
approached unity.
Equations (4)and ( 5 ) therefore reduced to :
Aw
Maximum p - -
. . . . . .
39
general, be practicable to use the two straight lines for the design of the
walls ; that greatly simplified calculations, gave a good margin of safety,
and scarcely affected the economy of the design.
The Author, in reply, said that he very much regretted his inability,
due to illness, to introduce the Paper personally, and expressed his sincere
appreciation to Mr Leopold Brook for undertaking the task and
for showing
the lantern slides.
The Suthor was glad that theChairman hadcalled attention to failure
a
of the foundationsof a silo constructed inAlgiers. That typeof failure was
usually dueto thelack of consideration of the pressures on the stratabelow
the surface. Inthe case of isolated foundations a t a fairly generous
spacing, that was not of great importance, but in thecase of silo or bunker
foundationswhereahigh-intensitypressureoccurredoveracomparatively large area, the intensity of pressure on any weak strata below the
surface could be ten or twenty times higher than it would be under any
normal fourldation condition.
The thickness of a silo wall was arrived a t by the ordinary methods of
design against flexure combined with direct tension,in the case of straight
walls, and by limiting the overall tensile stress (ignoring reinforcement)
to 200 lb. per square inch. It was essential to provide sufficient reinforcement to take the whole of the tensile stresses. If the silowallswere
designed on that principle, no difficulty would arise in making them
weather-tight.
With regard t o formula (3), it would be noticed in an earlier paragraph
that that formula was intended to refer only to shallow silos and would
not be applicable to a deep silo.
Mr Snows remarks regarding timber construction were quite true and
well recognized.
Steel formwork had been used for continuously moving forms,but they
had the disadvantage that, in general, they weighed and cost more than
wooden forms. They had the advantageof not being affected by changing
moisture and climatic conditions.
in
There was, as Mr Snow had suggested, arisk of distortion taking place
wooden forms, but that was usually taken care of by constructing a rigid
framework a t decking-level between the inner forms of the outer walls.
Provided that that framework was held rigid and kept vertical, the outer
forms couldbe lined up by adjustment of the yoke tie-bolts. Triangulated
tie-bolts were very useful in overcoming any distortion difficulties.
A loud-speakersystem on acontinuouslymoving
job was agreat
advantage, but the Author had notexperienced the necessity of correcting
the levels of the forms by as.much as 1 foot. That would, in most cases,
be a very difficult thing to do, and the forms
should not be allowed to get
so far out of level.
It was agreed that the removal of the formwork from a silo roof was a
difficult and dangerous job. In many cases, the use of steel joists as the
40
41
MADE ANDPRINTEDIN