According to reports, the roof had a 100% overload compared to its design safe loading. Further investigation
showed that, in 2002 the roof buckled under heavy snow, and against the regulations the hall was repaired
despite getting a building inspectors clearance. On top of this, the construction was resumed without doing
necessary tests and calculations to determine if the construction was stable and had sufficient strength.
It was also found that two architects involved in the structure made several errors and had brought about
many changes to the initial drawing without getting the approvals from the authorities. The head architect of
the structure was found to have approved the drawings of the design although it was very obvious to have
major errors and deficiencies- investigation done by experts revealed that there were major errors in the
construction of the structure such as steel constructions and reinforced concrete constructions.
CONCLUSION
After careful and thorough investigation, it was clear that the structure failed due to careless mistakes leading
to incorrect design from the construction company MTK, which was found to have been done to make the
construction cheaper. The investigation was formally completed at the end of June 2008 indicting 12 personals
through the investigation including the designer of the hall facing upto 12 years in prison. The result of the
catastrophe lead to the amendment of the Polish Building law in March 2007. The new amendment requires
large buildings must now undergo a technical survey twice every year (before and after winter) to make sure
they are safe and structurally sound, hence avoiding such catastrophic failures. It was also mentioned that
companies which fail to conduct the survey is punishable by a minimum 1,000 zloty fine or a imprisonment for a
specified period of time depending on the case.
It is important to note that this failure was due to improper management and planning by the company and
the responsible authorities, who moved forward with the construction knowing the possible consequences
considering the previous signs shown in the building regarding to its instability. The carelessness resulted in the
loss of 65 people along with other numerous causalities.