Professional Documents
Culture Documents
REV 4
SAIC NUMBER
SAIC-W-2003
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
31-Mar-10
DATE APPROVED
31-Aug-11
QR NUMBER
WELD-
CONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
A
A1
A2
A3
A4
A5
A6
ACCEPTANCE CRITERIA
REFERENCE
Page 1 of 14
SAES-W-011,
Para. 13.1
SAES-W-011,
Para. 13.1
SAES-W-011,
Para. 13.2
SAES-W-011,
Para. 13.2
PASS
FAIL
N/A
RE-INSP DATE
REV 4
ITEM
No.
A7
A8
A9
SAIC NUMBER
SAIC-W-2003
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
REFERENCE
Carbon & low alloy steel butt welds requiring PWHT for Process
Conditions & Services are as listed in Attachment 1.
A) All caustic soda (NaOH) solutions, incl. conditions
where caustic carryover may occur (e.g. downstream of caustic injection
points).
B) All monoethanolamine (MEA) solutions (all temperatures).
C) All diglycol amine (DGA) solutions above 138C design temp.
D) Rich amino diisoprop (ADIP) solutions above 90C design temp.
E) All lean ADIP solutions above 60C design temperature.
F) Boiler Deaerator serv (ambient temp vacuum deaerator = exempt)
G) Hydrogen service for P-No. 3, 4, and 5A/B/C base materials.
H) All diethanolamine (DEA) solutions.
These reqmts also apply to external welds to attach nonpressure
containing component to piping (e.g., reinforcement pad or sleeve
attached to the pipe) and to seal welds. Seal welds on threaded valves
For applications where PWHT is required by service fluid (Item A7
above) " OR " where hardness limits are specified:
a) Reductions in PWHT temperature or alternative temperatures
below normal holding temps listed in ASME B31.3 are not permitted.
b) Minimum PWHT soak time shall be 1 hour.
c) If hardness limits are specified, production weld soak time shall not be
less than 80% of PQR soak time unless approved by CSD.
Note : A copy of
the CSD approved WPS shall be cross checked
The PWHT heating and cooling rates > 316C shall not exceed 222C/hr
weld thickness in inches, but in no case > 222C/hr.
SAES-W-011,
Para. 13.3
SAES-W-011,
Para. 13.9
SAES-W-011,
Para. 13.4
A10
SAES-W-011,
Para. 13.5
A11
SAES-W-011,
Para. 13.6
A12
SAES-W-011,
Para. 13.6
A13
All temperatures within the heated zone for furnace or localized PWHT
shall exceed the specified minimum holding temperature.
SAES-W-011,
Para. 13.10
A14
The actual temperature range for the soak period, as recorded by TC's,
shall not have a spread of more than 40C.
SAES-W-011,
Para. 13.10
A15
SAES-W-011,
Para. 13.11
A16
PWHT shall be carried out using one or more of the following types:
a) Permanent or semi-permanent furnaces (gas/oil/electric heaters)
b) Electrical resistance heaters.
c) Induction heaters.
SAES-W-011,
Para. 13.12
Thermocouple Requirements
B1
SAES-W-011,
Para. 13.13
B2
Additional TCs are required if multiple heat control zones are used, in
which a control zone is not monitored by any of the primary T/Cs.
SAES-W-011,
Para. 13.13
B3
SAES-W-011,
Para. 13.14
B4
All charts shall be marked with the date and sufficient information to
uniquely identify the joint/component being heat treated.
SAES-W-011,
Para. 13.14
B5
SAES-W-011,
Para. 13.14
B6
SAES-W-011,
Para. 13.15
Page 2 of 14
31-Mar-10
DATE APPROVED
31-Aug-11
QR NUMBER
WELD-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
REV 4
SAIC NUMBER
31-Mar-10
DATE APPROVED
SAIC-W-2003
ACCEPTANCE CRITERIA
REFERENCE
B7
SAES-W-011,
Para. 13.15 &
Sch Q,
M&TE
B8
SAES-W-011,
Para. 13.16.1
B9
SAES-W-011,
Para. 13.16.1
B10
SAES-W-011,
Para. 13.16.2
B11
SAES-W-011,
Para. 13.16.2
B12
SAES-W-011,
Para. 13.16.3
C1
SAES-W-011,
Para. 13.16.3
C2
SAES-W-011,
Para. 13.17
C3
SAES-W-011,
Para. 13.17
C4
SAES-W-011,
Para. 13.18
C5
SAES-W-011,
Para. 13.19
C6
SAES-W-011,
Para. 13.20
WELD-
31-Aug-11
WBS / BI / JO NUMBER
ITEM
No.
QR NUMBER
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
REMARKS:
NOTES: 1. Code exemptions for PWHT for P-No. 4 & P-No. 5 materials are not allowed at Saudi Aramco. PWHT all P-No. 4 & P-No. 5 mat'l
welds & pressure boundary attachments when Sour Service exists or nominal chrome content is above 1.5%. (SAES-W-011, Para. 13.8
2. Condition of PWHT Insulation blankets shall be monitored for deterioration & burn damage. Deteriorated blankets and those without wire
mesh coverings release Ceramic fibers into the immediate work area and are a great health hazard (Safety & Quality Concern).
3. Strict controls for work sequence and work segregation are required.
4. For Recording of Results & Final Acceptance, utilize checklist SAIC-W-2004 R3 to cover any points in the Procedure deemed necessary.
ATTACHMENTS:
Attachment 1 - Requirements for Heat Treatment (ASME B31.3, Table 331.1.1) & SAES-W-011
Attachment 2 - SAEP-1160 DATABASE, PROCESS CONTROL TRACKING (By Weld)
Attachment 3 - SATR-W-2004 - SAMPLE PWHT TABLE (PROCESS CONTROL TRACKING BY WELD)
REFERENCE DOCUMENTS:
1. SAES-W-011, Welding Requirements for On-Plot Piping, (4 Oct 2009)
2. ASME B31.3, Process Piping (Latest Edition)
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
QC Inspector
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
PID Representative
Performed Inspection
T&I Witnessed
Name, Initials and Date:
Page 3 of 14
REV 4
SAIC NUMBER
ITEM
No.
SAIC-W-2003
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
31-Mar-10
DATE APPROVED
REFERENCE
31-Aug-11
QR NUMBER
WELD-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
QC Supervisor
Name, Organization,
Initials and Date:
T&I Witnessed
QC Record Reviewed
Y = YES
Page 4 of 14
Work Verified
N = NO F = FAILED
REV 4
SAIC NUMBER
SAIC-W-2003
31-Mar-10
DATE APPROVED
31-Aug-11
QR NUMBER
WELD-
Attachment 1 - Requirements for Heat Treatment (ASME B31.3, Table 331.1.1) & SAES-W-011, Section 13
Attachment 2 - Requirements for Heat Treatment (ASME B31.3, Table 331.1.1) & SAES-W-011
Attachment 2 - Requirements for Heat Treatment (ASME B31.3, Table 331.1.1) & SAES-W-011
Attachment 2 - Requirements for Heat Treatment (ASME B31.3, Table 331.1.1) & SAES-W-011
Attachment 2 - Requirements for Heat Treatment (ASME B31.3, Table 331.1.1) & SAES-W-011
REV 4
SAIC NUMBER
31-Mar-10
DATE APPROVED
QR NUMBER
REV 4
SAIC NUMBER
SAIC-W-2003
31-Mar-10
DATE APPROVED
31-Aug-11
QR NUMBER
WELD-
Attachment 3 - SATR-W-2004 R-3- SAMPLE PWHT TABLE (PROCESS CONTROL TRACKING BY WELD)
Instructions for PWHT Table (Line List) Use: 1. Perform Heat Treatment in conjunction with SAIC-W-2012 and
SAIC-W-2014 for Brinnell Hardness Testing and the applicable NDE SATIP & Project NDE Specification.
2. Localized PWHT = 100% Brinnell Hardness Testing. Furnace Batch PWHT = 10% Brinnell Hardness Testing.
3. PWHT Crew & QC Responsible utilize this Work Sheet to perform field work under close supervison/Witness.
4. Results are entered into the SAEP-1160 Database for Welds on Projects. Verify Weld ID numbers carefully.
5. Such Databases are not needed when 500 welds or less are in the Project Work Scope (SAEP-1160 Reqmt).
6. PWHT shall be performed per approved Project Welding & PWHT Specification including all notes.
7. Those responsible for work and data entry have been approved by Saudi Aramco to perform work on IK Projects.
8. Rework shall require a new Weld ID Number (suffix added = R 1, etc) per SAEp-1160 Requirements.