You are on page 1of 26

ITEM WISE

TECHNICAL SPECIFICATIONS
(Anganvadi)
ITEM NO. 1
Excavation for foundation up to 1:50 mt. Depth including sorting out and stacking of useful materials and
depositing of the excavated stuff up to 50 meter lead. (A) Loose or soft soil.
a) 0.00 to 1.50 M. depth
General:
Any soil which generally yields to the application of pickaxes and shovels, phawaras, rakes or any such ordinary
excavation implement or organic soil, gravel, silt, sand turf loam this category.
Clearing the site:
The site on which the structure is to be built shall be cleared and all obstructions, loose stone, materials and
rubbish of all kind, bush; wood and trees shall be removed as directed. The materials so obtained shall be
property of the Government and be conveyed and stacked as directed within 50 M. lead. The roots of the trees
coming in the sides shall be cut and coated with hot asphalt.
The rate of site clearance is deemed to be including in the arte of earthwork for which no extra will be paid.
Setting out:
After clearing the site, the centre lines will be given by the Engineer-in-charge. The contractor shall assume full
responsibility alignment, elevation, and dimension of each and all part of the tractor shall assume full
responsibility for alignment elevation of each and all parts of the work. Contractor shall supply labourers,
materials, etc. required for setting out the reference marks and shall maintain them as long as required and
directed.
Excavation:
The excavation in foundation shall be carried out in thru line and level and shall have the width and depth as
shown in the drawing or as directed. The contractor shall do the necessary shoring and shutting or providing
necessary slopes to a safe angle, at his own cost. The payment for such precautionary measures shall be paid
separately if not specified. The bottom of the Excavated area shall be levelled both longitudinally and
transversely as directed by removing and watering as required. No earth filling will be allowed for bringing it to
level, if by mistake or any other reason excavation is made deeper or wider that shown on the plan or directed.
The extra depth or width shall be made up with contractor of same proportion as specified for the foundation
concrete at the cost of the contractor. The excavation up to 1.5 m. depth shall be measured under this item.
Disposal of the excavation stud:
The excavated stuff of the selected type shall be used in filling the trenches and plinth or leveling the ground in
layers including ramming and watering etc.
The balance of the excavated quantity shall be removed by the contractor from the site of work to a place as
directed with lade up to 50 m. and all lift.
Mode of measurement of payment:
The measurement of excavation in trenches for foundation shall be made according to the section of trenches
shown on the drawing as per section given by the Engineer-in-charge. No payment shall be made for surplus
excavation made in excess of above requirements or due to slopping and slopping back as found necessary on
account of condition of soil and requirement of safety.
The rate shall be for a unit of one cubic meter.
ITEM NO. 2
Filling with available earth (excluding rock) in trenches plinth, sides of foundations etc. in layers not
exceeding 20 cm in depth including consolidating each depo sited layer by ramming and watering.
with available earth
Filling in foundation and plinth with murrum or selected soil in layers of 20 cm thickness including watering,
ramming, consolidating and dressing etc. complete.
All fill material will be subject to the Engineers approval. If any material is rejected by the Engineer, the
Contractor shall remove the same forth with from the site at no extra cost to the Owner. Surplus fill material
shall be deposited / disposed off as directed by the Engineer after the fill work is completed.
No earth fill shall commence until surface water discharges and streams have been properly intercepted or
otherwise dealt with as directed by the Engineer.

Borsad Nagar Sevasadan

61

The Contractor shall not commence the placement of any fill or backfill at any location without the approval of
the Engineer.
Material
If any selected fill material is required to be borrowed, the Contractor shall make arrangements for bringing
such material from outside borrow pits. The material and source shall be subject to prior approval of the
Engineer. The approved borrow pit area shall be cleared of all bushed, roots of trees, plants, rubbish etc. top
soil containing salts / sulphate and other foreign material shall be removed. The materials so removed shall
be burnt or disposed off as directed by the Engineer. The Contractor shall make necessary access roads to
borrow areas and maintain the same, if such access road does not exist, at his cost.
Filling in pits and trenches around foundations of structures, walls etc.
As soon as the work in foundations has been accepted and measured, the spaces around the foundations,
structures, pits, trenches etc. shall be cleared of all debris, and filled with earth in layers not exceeding 15
cm., each layer being watered, rammed and properly consolidated, before the succeeding one is laid. Each
layer shall be consolidated to the satisfaction of the Engineer. Earth shall be rammed with approved
mechanical compaction machines. Usually no manual compaction shall be allowed unless the Engineer is
satisfied that in some cases manual compaction by tampers cannot be avoided. The final backfill surface shall
be trimmed and leveled to proper profile as directed by the Engineer.
The compacted surface shall be properly shaped, trimmed and consolidated to an even and uniform gradient.
All soft spots shall be excavated and filled and consolidated.
MEASUREMENT AND PAYMENT
The earth work in filling shall be measured in length, breadth and depth as specified on drawing or as
directed, correct up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of cubic meters.
ITEM NO. 3
Providing and laying cement concrete 1:4:8 (1 cement : 4 course sand: 8 hand broken stone aggregate 40mm
nominal size) and curing complete excluding cost of form work in (A) foundation and plinth.
For Wall
Materials:
Water shall conform to M-1. Sand shall conform to M-6 cement shall conform to M-3 stone aggregate 40 mm.
nominal size shall conform to M- 12.
Workmanship:
General:
Before starting concrete bed of foundation stretches shall be cleared of all loss materials, levelled, watered
and rammed as directed.
Proportion of mix:
The proportion of cement sand and coarse aggregate shall be one part of cement; 3pats of send 6 parts of
stone aggregates and shall so measured by volume.
Mixing:
The concrete shall be mixed in mechanical mixer at the site of work. Hand mixing may however be allowed for
smaller quantity of work if approved by the Engineer-in-charge. When hand mixing is permitted by the
Engineer-in-charge in case of breakdown of machineries and the interest of the work. It shall be carried out on
a watertight platform and care shall be taken to ensure that mixing is continued until the mass is uniform of
colour and consistency. However in such case 10 % more cement then otherwise required shall have to be
used without any extra cost. The mixing in mechanical mixer shall be done for a period 1 to 2 minutes. The
counted of water shall be sufficient to produce a dense concrete of required workability for the purpose.
Transporting & placing the concrete:
The concrete shall be handled from the place of mixing to the final position in not more then 15 minus by the
methods as directed and shall be pleased into its final position, compacted and finessed within 30 minutes of
mixing with water i.e. before the setting commences.
The concrete shall be laid in layers of 15cms to 20cms.
Compacting:
The concrete shall be rammed with heavy iron rammers and ratidiy to get the required compaction and to
allow all the interstices to be filled with mortar.
Curing:
After the final set, the concrete shall be kept continuously wet, if required by pending for a period of less then
the 7 days from the date of placement.
Borsad Nagar Sevasadan

62

Mode of measurement of payment


The concrete shall be measured for its length breadth and depth, limiting dimensions to those specified on
plan or directed.
The rate shall be for a unit of one cubic metre.
ITEM NO. 4
Providing and laying cement concrete 1 : 3 : 6 (1 cement : 3 coarse sand : 6 Crushed stone aggregates 20mm
nominal size) and curing complete including cost of form work in (A) Wall caps / Coping.
for R.C.C. Coping
And
ITEM NO. 5
Providing and laying ordinary cement concrete 1 : 2 : 4 (1 cement : 2 coarse sand : 4 graded stone aggregates
20mm nominal size) for R.C.C Lintel including finishing smooth with curing etc. complete including the cost
of formwork but excluding the cost of reinforcement :.
for R.C.C. Lintel
And
ITEM NO. 6
Providing and laying controlled cement concrete M-200 exposed work with curing etc. complete including the
cost of formwork but excluding the cost of Reinforcement for R.C.C work in
(i) Having cross-sectional area 0.05 to 0.08 sq. m
for R.C.C. Plinth Beam
And
ITEM NO. 7
Providing & laying controlled cement concrete M-200 and curing complete including the cost of form work
and reinforcement for reinforced concrete work in :
for R.C.C. Slab
for R.C.C. Weather Shed
for R.C.C. Loft Slab
And
ITEM NO. 8
Providing and laying controlled cement concrete M-200 exposed work with curing etc. complete including the
cost of formwork but excluding the cost of Reinforcement for R.C.C work in
(ii) Having cross-sectional area 0.08 to 0.12 sq. m
for R.C.C. Beam
GRADES OF CONCRETE:
The compressive strength of various grades of designation concrete shall be given below:
Grades
Compressive strength specified for
Designation
15 cm cubes min at
2
28 days (N/mm )
M 7.5
7.5
M 10
10
M 15
15
M 20
20
M 25
25
M 30
30
NOTE: In the designation of a concrete mix letter M refer to the mix and the number to the specified
2
characteristic compressive strength of 15 cm-cube at 28 days expressed in N/mm
Minimum cement content required in reinforced cement concrete to ensure
durability under specified
3
condition of exposure, will be in accordance with IS : 456-2000. However it shall not be less than 300 Kgs/m
of concrete for all grade cement.
BATCHING:
In proportioning concrete, the quantity of both cement and aggregate should be determined by mass. Cement
shall be used on the basis of mass and should be weighed separately from the aggregate. Water should be
Borsad Nagar Sevasadan

63

either measured by volume in calibrated tanks or weighed. Any solid admixture that may be added may be
measured by mass liquid and paste admixture by volume or mass. Batching plant where used should conform
to IS: 4925 1968. All measuring equipment should be maintained in a clean serviceable condition and their
accuracy periodically checked.
Except where it can be shown to the satisfaction of Engineer that supply of properly graded aggregate of
uniform quality can be maintained over the period of work, the grading of aggregate should be controlled by
obtaining the coarse aggregate in different sizes and blending them in the right proportions hen required, the
different sizes being stocked in separate stock piles. The material should be stocked in separate stock piles.
The material should be stock piles for several hours preferably a day before use. The grading of coarse and
fine aggregate should be checked as frequently as possible, the frequency for a given job being determined
by Engineer to ensure that the specified grading is maintained.
It is important to maintain the water-cement ratio constant at its correct value. To this end, determination of
moisture contents in both fine and coarse aggregate shall be made as frequently as possible, the frequency
for a given job being determined by the Engineer in charge according to weather conditions. The amount of
the water to be added shall be adjusted to compensate for any observed variations in the moisture content in
the aggregates, IS 2386 (Part-3) 1963 may be referred to. To allow for the variation in mass of aggregate
due to variation in their moisture content, suitable adjustments in the masses of aggregates shall also be
made. In the absence of exact data only in the case nominal mixes, the amount of surface water may be
estimated from the values given in the table.
STRENGTH REQUIREMENT OF CONCRETE
At least 4 week before commencing any concreting in the work the contractor shall make trial mixes using
samples of coarse aggregates, sand, water and cement typical of those to be used in the works. A clean dry
mixer shall be used and the first batch discarded.
CONTROL OF CONCRETE:
(I)
PRELIMINARY TESTS: The contractor may be called upon to submit representative samples of
materials to be used for concrete in order that they may be tested at a recognized laboratory and the
suitability of materials established. These tests are to be carried out in accordance with IS 456-2000.
All expenses in connection with the above mentioned tests shall be borne by the contractor.
(ii)
WORKS CUBE TESTS: during the progress of the work, 15 cm. Cubes shall be made and tested in
accordance with IS: 456 2000 and IS: 516 amended up to date.
TEST SAMPLES AND ACCEPTABILITY CRITERIA:
For both preliminary testing as well as day to day works cube testing, the number of test specimens required,
the frequency of sampling and criteria for acceptance of a concrete as conforming to the specified grade shall
be in accordance with IS 456-2000, except that the minimum compressive strength for each grade or
concrete shall be as provided in the above table.
The cubes shall be made, cured, stored, transported and tested in accordance with IS 516 1959 and IS
1199-1959. The test shall be carried out in the laboratory approved by the engineer. Whenever there is a
significant change in the quantity of any of the ingredients for concrete, the engineer may at his discretion
order the carrying out of fresh preliminary trial mixes. All cost for trial mixes and tests shall be paid by the
contractor.
CONSISTENCY OF CONCRETE:
Only sufficient water shall be added to the cement and aggregate during mixing to produce a mixture of
sufficient workability to enable it to be well consolidated, to be worked into the corners of the shuttering and
around the reinforcement, to give the specified surface finish, and to have specified strength.
If difficulty be experienced in placing the concrete of specified mix and approved consistency between and
below the reinforcement bars in the bottom of beams and similar units, the bars shall be embedded in a
concrete of improved workability by increasing the proportion of cement by an approved amount and using
aggregate of approved smaller maximum size than specified for which nothing extra shall be paid.
Whenever it is not possible to concrete the full height of the columns in one operation, at least 1st, ft. depth of
the upper height of the column when concreted at a later state shall be concreted with a richer mix next higher
to the mix specified for the member. This also applied to the top part of the column to be concreted along with
the roof beam or slab. However, nothing extra shall be admissible for this and the contractor is deemed to
have taken into account the excess cost involved in complying to this at the time of quoting his/there rates for
the item.
MEASUREMENT OF CONSISTENCY:
The consistency shall be determined by making trial mixers with dried aggregates, or when so instructed by
laboratory made test cubes as herein after shall be specified. The consistency of the trial mixer of the
approved consistency shall be measured as instructed.

Borsad Nagar Sevasadan

64

The slump of the approved trial mixture shall be measured and this slump shall not be exceeded throughout
all batches of concrete made from the same materials mixed in the same proportions as the trial mixtures and
used in those parts of the works as instructed. In no case, however, shall the slump exceed 50 mm for
concrete in slab or exceed 25 mm for concrete consolidated by mechanical vibration.
The slump test shall be made on concrete actually being placed in the works at the commencement of each
period of concrete placing and at such other times as instructed.
The apparatus used for the slump test shall be a standard cone. When the cone is filled, it shall be raised
vertically clear of the concrete and the measurement of the slump shall be 30 mm minus the height of the
slumped cone of concrete. Care shall be taken to prevent vibration of the sample being tested.
If the engineer requires the use of other means for testing the consistency of the concrete this clause must be
rewritten.
a.
The maximum slump for concrete used in various parts of the buildings shall be as given below
unless specified otherwise.
Sr. No.
Item
Max. Slump
1.
Foundations
3 Cm
2.
Retaining Walls
8 Cm
3.
Concrete Walls
5 Cm
4.
Columns with smaller dimension
a.
12 or less
5 Cm
b.
More than 12
5 Cm
5.
Slabs, beams, parapets, ribs & stairs
5 Cm
DISTRIBUTION OF CONCRETE:
The concrete shall be distributed from the mixers to the position of placing in the works by approved means
that do not cause separation or otherwise impair the quality of the concrete.
PREPARATIONS FOR PLACING CONCRETE:
Before the concrete is placed the shuttering shall be trued-up and any water accumulated therein shall be
removed. All saw dust, chips.
Nails and other debris shall be washed out or otherwise removed from within the shuttering. The
reinforcement shall then be inspected for accuracy of fixing. Immediately before placing the concrete the
shuttering shall except in frosty weather be well wetted and inspection shall be closed.
CURING AND PROTECTION OF CONCRETE:
Newly placed concrete shall be protected from rain and during hot, dry or windy weather approved coverings
shall be used to prevent premature drying out. The concrete shall also be protected from frost as hereinbefore
specified. All exposed faces of concrete shall be kept moist by approved means for fifteen days after placing
or for three days if Rapid Hardening Portland Cement be used, except when there be danger of the curing
water getting frozen. Concrete in foundations and other underground work shall be protected from admixture
with falling earth during and after placing. Concrete placed in ground containing deleterious salts shall be kept
free from contact with such waters during placing and for a period of three days thereafter. The ground water
around basements, underground tanks, and similar constructions shall be kept down to an approved level by
pumping, or the works shall be flooded or other approved means taken to prevent floatation.
Approved means shall be taken to protect immature concrete from damage by floating debris, ice and similar
material in works in water. Arrangements shall be made to restrict traffic loads and speeds in the vicinity of
bridge work for an approved period.
Slabs, stairs, and other work shall be protected from damage from workmen, equipment, over load, or any
other cause.
FINISHES:
Honeycombed surfaces shall be made good immediately upon removal of the shuttering and superficial water
and air holes shall be filled. Unless instructed to the contrary, the face of exposed concrete placed against
shuttering shall, after removal of the shuttering, be rubbed with carborandum stone with cement grout
lubricant or similar to remove fins and other irregularities. This however, is not substitution for plaster, which
may be required to be carried out for purpose of finishing.
The surface of non-shuttered faces of concrete work other than slabs shall be smoothed with a wooden float
(or if approved with a steel trowel) to give a finish equal to that of the rubbed down shuttered faces.
Concealed concrete faces shall be left as from the shuttering except that honey combed surfaces shall be
made good.
The top faces of slabs not intended to be surfaces shall be leveled and floated to a smooth finish at the levels
or falls shown on the drawings or elsewhere. The floating's shall not be executed to the extent of bringing
excess fine material to the surface.
Ribbed surface of slabs shall where instructed be formed at the time of tamping and leveling. Indentations in
slab or stair surfaces shall be formed by approved implements giving the depth and patterns instructed.
Borsad Nagar Sevasadan

65

The top faces of slabs intended to be covered with screened granolithic or similar surfacing shall be left with a
speed finish.
The soffits of slabs and faces of walls intended to be rendered shall be roughened by approved means to
form a key.
Concrete surfaces to take finishes other than those specifically referred to herein shall be prepared in an
approved manner to suit the finish as instructed.
VIBRATION:
i) APPEARANCE: The concrete that is to be compacted by vibration should appear anything from earth dry
to slightly glistening. The mix should have the appearance of lacking in fines.
ii) PLACING: Segregation is likely to take place when the concrete is tipped into the form work and this
should be avoided.
The concrete mix should not contain surplus water and sand which will develop segregation under
influence of vibratory compaction. The distribution of new concrete should be uniform for the whole
section and the surface kept horizontal the whole time, thus ensuring that the movement of concrete is
downward only. Vibrators should not be used as a spreading or distributing agent.
iii) The vibrators shall be of rotary out of balance immersion type or the electromagnetic type and operate at
a frequency of not less than 4,000 cycles per minutes. The vibration shall be of such a power input as to
produce an accelerating of 4g to 10f/sec 2 in the mass of the compacted concrete. The vibrators shall be
designed for continuous operation.
iv) DISPOSITION OF VIBRATORS: Internal vibrators shall be disposed within the mix when placed, so as to
maintain the whole of the concrete under treatment in an adequate state of agitation such that de-aeration
and effective compaction attained at a rate commensurate with the supply of concrete from the mixers.
Insertion of the vibrators at about 45 cm center is considered sufficient.
v) PERIOD OF VIBRATION: Vibration shall continue during the whole period occupied by placing the
concrete, the vibrators being adjusted so that the center of vibration approximates to center of the mass
being compacted at the time of placing. The concrete should not be over-vibrated and the period of
insertion of internal vibrator should be about 15 second at any one point.
vi) COMPACTNESS: The concrete shall be judged to be compacted when the mortar fills the spaces
between the coarse aggregate so as to form a glistening and even surface except for slight irregularities
where the coarse aggregate breaks this smooth surface. When this condition has been attained the
vibrators shall be withdrawn slowly.
vii) The vibrator must not be placed against the steel or the shuttering, the minimum distance being 75 mm.
The compressor must be placed in such a position that shuttering, reinforcement and recently laid
concrete are subjected to the minimum amount of vibration.
MEASUREMENT AND PAYMENT
The Concrete work shall be measured in length, breadth and depth as specified on drawing or as directed,
correct up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of cubic meters.

ITEM NO. 9
Providing TMT Fe 415 bar reinforcement for RCC work including, bending, binding and placing in position
complete up to floor two level..
Reinforcement bars shall be bent by approved means producing a gradual and even motion. Bars shall
comply with the dimensions of bending or the like shall be within a tolerance of +6 mm. Any discrepancies or
inaccuracies found by the contractor in the drawings or other documents shall be immediately reported to the
Engineer, whose interpretation and requirements relating thereto shall be accepted.
The internal radius of bends shall be not less than twice the size of the bar unless described to the contrary
on the bending lists or elsewhere or in the following. Hooks and other and anchorage bends shall be bent to
an internal radius of twice the diameter of the bar. This internal radius of the bends at corners of binders or
stirrups or links shall be half the size of the bar embraced by the binder, stirrup or ink.
FIXING OF REINFORCEMENT:
Reinforcement shall be accurately fixed and by approved means maintained in the position described. Bars
intended to be in contact shall be securely wired together at all such points with No. 16 gauge annealed soft
iron tying binding wire. Binders, stirrups and links shall tightly embrace the bars with which they are intended
to be in contact and shall be securely wired or, if approved, spot-welded thereto.
Reinforcement shall be lapped, joined, or spliced only at the positions described. Splices and the like found to
be necessary elsewhere shall be formed only if and as instructed.

Borsad Nagar Sevasadan

66

Where practicable, bars in each member shall be assembled and fixed in the form of a rigid cage or skeleton
before placing in the moulds or shuttering.
Immediately before concreting, the reinforcement shall be checked for position, cleanliness, freedom from
rust, damaging liquids. Means shall be taken to ensure that reinforcement remains correctly in position with
required cover during the placing and consolidating of the concrete.
Reinforcement projecting from work being concreted or already concreted shall not be bent out of its correct
position for any reason unless approved and shall be protected from deformation or other damage.
Reinforcement left projecting for bending with future extensions shall be thoroughly coated with cement grout
wash or encased in concrete or otherwise protected from corrosion as instructed.
COVER:
Cover of concrete and spacing of bars:
Unless otherwise described the cover of concrete over the reinforcement shall be follows
The cover shall be provided in accordance with IS : 456-2000.
Nominal cover
Minimum Nominal cover
1)
Walls, Slabs and Others Members
15 mm
2)
Beam
25 mm
3)
Column
25 mm
4)
Foundation / Footing
50 mm
WELDING OF BARS
Wherever facility for electric arc welding is available, welding of bars shall be done in lieu of overlap. The
location and type of welding shall be got approved by the Engineer. Welding shall be as per IS: 2751-1979 for
mild steel bars and for cold worked bars.
PLACING IN POSITION:
Fabricated reinforcement bars shall be placed in position as shown in the drawing or as directed by the
Engineer. The bars crossing one another shall be tied together at every intersection with two stands of
annealed steel wire 0.9 to 1.6 mm thickness twisted tight to make the skeleton of the steel work rigid so that
the reinforcement does not get displaced during deposition of concrete.
Tack welding in crossing bars shall also be permitted in lieu of binding with steel wire if approved by Engineer.
The bars shall be kept in correct position by the following methods.
a) In case of beam and slab construction precast cover blocks of the same grade of concrete about 4 X 4
cm section and of thickness equal to the specified cover shall be placed between the bars and shuttering,
so as to secure and maintain the requisite cover of concrete over reinforcement.
b) In case of cantilevered and doubly reinforced beams or slabs, the vertical distance between be horizontal
bars shall be maintained by introducing chairs, spacers or support bars of steel at 1.0 meter or at shorter
spacing to avoid sagging.
c) In case of columns and walls, the vertical bars shall be kept in position by means of timber templates with
slots accurately cut in them; or with block of the same grade of cement of required size suitably tied to the
reinforcement to ensure that they are in correct position during concreting.
d) In case of other R.C.C. structure such as arches, domes, shell, storage tanks etc. a combination of cover
blocks, spacers and templates shall be used as directed by Engineer.
TOLERANCE ON PLACING OF REINFORCEMENT:
Unless otherwise specified by the Engineer, reinforcement shall be placed within the following tolerances.
Tolerance in spacing
a. For effective depth, 200 mm or less
+ 10 mm
b. For effective depth, more than 200 mm
+ 15 mm
The cover shall in no case be reduced by more than one third of specified cover or 5 mm whichever is less.
BENDING AT CONSTRUCTION JOINTS
Where reinforcement bars are bent aside at construction joints and afterwards bent back into their original
position care should be taken to ensure that at no time the radius of the bend is less than 4 bar diameters for
plain mild steel or 6 bar diameters for deformed bars. Care shall also be taken when bending back bars to
ensure that the concrete around the bar is not damaged.
EXPANSION JOINTS
Expansion joints shall be provided as shown in the structural drawings or as directed by Engineer, for the
purpose of general guidance. However it is recommended that structures exceeding 45 m in length shall be
divided by one or more expansion joints. The filling of these joints with bitumen filler, bitumen felt or any such
material and provision of copper plate, etc. shall be paid for separately in running meter. The measurement
shall be taken up to two places of decimal stating the depth and width of joint.

Borsad Nagar Sevasadan

67

MEASUREMENT AND PAYMENT


The rate for reinforcement includes cost of steel binding wires.
The rate shall be for a unit of kilogram basis.
ITEM NO. 10
Brick work using common burnt building bricks having crushing strength not less than 35 Kg./sq. cm in
foundation & plinth in cement mortar 1:6 (1 Cement, 6 fine sand). (B) Conventional.
Up to GL
And
ITEM NO. 11
Brick work using common burnt building bricks having crushing strength not less than 35 Kg./sq. cm in
foundation & plinth in cement mortar 1:6 (1 Cement, 6 fine sand). (B) Conventional.
Extra for brick work in super structure above plinth level up to floor two level.
Above Plinth
The contractor shall provide all labour, materials, scaffolding operations, equipment and incidentals necessary
required for the completion of all brickwork called for in the drawings and documents and that which is fairly
intended for smooth completion of the work.
BRICKS:
The bricks shall be well burnt locally available from good brick earth and shall be of uniform size unless
otherwise specified. They shall be of uniform deep red, cherry or copper colour, thoroughly well burnt without
being verified, regular in shapes and size, and shall have sharp and square sides and edges and parallel
faces to ensure uniformity in the thickness of the courses of brick work. The bricks shall be free from cricks,
chips, flaws, stones or humps of any kind. They shall not show appreciable signs of efflorescence either dry
or subsequent to soaking in water. The bricks shall be sound, hard homogeneous in texture and emit a clear
ringing sound when struck with a trowel. In no case, the minimum crushing strength of bricks shall be less
than 50 kg/sq. cms. The bricks shall be provided with frogs, all bricks which absorb water more than onesixth of their own dry weight after being socked for one hour by immersion in water shall be rejected.
BRICKBATS:
Brickbats shall be well burnt and shall be obtained only from the bricks specified under 1 above.
MORTARS:
All brick work shall laid with C.M. (1:6) of good workable consistency.
SOAKING OF BRICKS:
All bricks required for masonry in cement or composite lime mortars shall be thoroughly soaked in clean water
for at least one hour in advance of sufficient size immediately before use. The cessation of bubbles when the
bricks are immersed in water is an indication of thorough soaking of bricks. Bricks required for masonry with
fat lime mortar shall not be soaked.
LAYING:
a)

Brick shall be laid in English bond, unless otherwise specified. Half or cut bricks shall not be used
except where necessary to complete the bond. Closers in such cases shall be cut to the required size
and used near the ends of the walls.

b)

The walls shall be taken up truly plumb. All courses shall be laid truly horizontal and all vertical joints
join shall be truly vertical. Vertical joints in alternate courses shall come directly one over the other.
The thickness of brick courses shall be kept uniform and for this purpose straight edge with
graduations showing the thickness of each brick course including joint shall be used. Bricks shall be
laid with frogs upwards.

C)

The walls of a structure shall be carried up regularly and nearly at one level and no portion of the
work shall be left more than 3 ft. below the rest of the work. Where this is not possible the work shall
o
be raked back according to bond (and not left toothed) at an angle not exceeding 45 .

d)

All iron fixtures, pipes, outlets of water, holdfasts of doors and windows, etc. which are required to be
built in walls, shall be embedded in cement mortar or in cement concrete as specified, in their correct
positions as the work proceeds. Nothing extra shall be paid for such extra cement mortar or of the
nature stated above.

Borsad Nagar Sevasadan

68

JOINTS:
Bricks shall be so laid that all joints are quite full of mortar. The thickness of the bed joints shall in no case
exceed 3/8" unless otherwise specified. The face of joints shall be raked to a minimum depth of 0.5 by
raking tool daily during the progress of work when the mortar is still green, so as to provide proper key for the
plaster or pointing to be done. Where plastering or pointing is not required to be done, the joints shall be
struck flush and finished at the time of laying. The face of brick work shall be cleaned daily and all mortar
droppings removed.
BRICK IN EDGE COPING
The top course of all plinths, parapets, steps and tops of walls below R.C.C. slabs or beams shall be laid with
brick on edge, unless otherwise specified. Proper care shall be taken that the bricks forming the top corners
and ends of walls shall be properly radiated and keyed in to position.
CURING:
Green work shall be protected from rain by suitable covering. Brick masonry with cement or composite mortar
shall be kept constantly moist on all faces for a minimum period of 7 (seven) days. In case of fat lime mortar,
curing shall commence two days after the laying of masonry and shall continue for 7 (seven) days.
SCAFFOLDING:
Double scaffolding having two sets of vertical supports shall be provided. The supports shall be sound and strong.
Tied together with horizontal pieces over which the scaffolding planks shall be fixed. In building up to two stories,
single scaffolding shall be allowed. In this case, the inner end of the horizontal scaffolding pole shall rest in a hole
provided in the header course only. Only one header or each pole shall be left out. The holds left in masonry work
for supporting the scaffoldings shall be filled and made good, before plastering. The contractor shall be
responsible for providing and maintaining sufficiently strong scaffolding so as to withstand all loads likely to come
upon it.
MEASUREMENT AND PAYMENT
The Brick masonry work shall be measured in length, breadth and depth as specified on drawing or as
directed, correct up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of cubic meters.
ITEM NO. 12
Half brick masonry in common brunt clay building brick having crushing strength not less than 35 Kg./sq.cm.
in cement mortar 1:4 (1 cement :4 coarse sand ) in foundation and plinth.
(b) Conventional
The work shall be done exactly similar to the specification BRICK WORK except that all courses shall be laid
with stretchers.
Cement Mortar 1:4 (1 cement: 4 coarse or fine sand) shall be used unless otherwise specified in the
description of the item.
The description of the item shall mention whether or not, reinforcement is to be provided. When the brick work
is to be reinforced, hoop iron band 1 x 1/16 (2.5 c.m. x 1.6. mm) shall be embedded in the cement mortar at
every fourth course or as described in the description of the item. The hoop iron shall be hooked (given a
double lap) with minimum of 9 hooks at all angles and junctions. At either end of the wall, 2 (5 c.m.) length of
the hoops shall be bent up or down so as to take a firm grip of the brick work. When hoop iron is not available
the Consultant may allow equivalent reinforcement in the form of mild steel.
MEASUREMENT AND PAYMENT
The half brick masonry shall be measured in length, breadth/depth as specified on drawing or as directed,
correct up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.

ITEM NO. 13
Providing and fixing 35 mm thick shutters for door, window and clerestory window including Indian teak
wood frame of 10cm X 7 cm size including black enameled iron oxidized fixtures and fastening including
primer coat of approved quality and two coat of oil painting etc. complete.(ii) Fully paneled.
Teakwood shall be second class Indian Teakwood conforming to IS: 4021 of good quality, well seasoned and
free from defects such as cracks, dead knots, sapwood etc. No individual and sound knot shall more than15
sq.cm. in size and the aggregate area of such knots shall not exceed 2% of the areas of the piece. The timber
shall be fairly close grained having not less than 2 growth rings per cm. width in cross-section.
Borsad Nagar Sevasadan

69

Wooden door/window frame shall be made of specified wood as per item description and shall be in
accordance with detailed drawings.
The wooden members of the frame shall be planed smooth and accurate to the full dimensions. Rebats,
rounding, moulding etc. shall be done before the members are jointed into frames. Joints in the frame work
shall be perfect with square edges and shall be pinned with hard wood/bamboo pins of 10 to 15mm dia.
Wood work shall be pained/polished or otherwise treated as specified. All exposed portions shall be coated
with wood primer and concealed surface by bituminous paints as per clause No.6.8 of specification No.6.
Before any surface treatment is applied, the wood work shall be got approved by the Engineer. The frames
shall be fixed only after acceptance by the Engineer. The frames shall be fixed to the masonry by 300 mm x
25mm x 6 mm MS hold fasts embedded in M-15 grade concrete block of 350 mm x 100 mm x 100 mm in the
hole of the masonry. In case of concrete, frames shall be fixed by 96 mm long 12 mm dia metallic dash
fasteners.
Joints in the frame work shall be perfect with square edges and shall be pinned with hard wood/bamboo pins
of 10 to 15mm dia.
Wood work shall be pained/polished or otherwise treated as specified. All exposed portions shall be coated
with wood primer and concealed surface by bituminous.
Before any surface treatment is applied, the wood work shall be got approved by the Engineer. The frames
shall be fixed only after acceptance by the Engineer. The frames shall be fixed to the masonry by 300 mm x
25mm x 6 mm MS hold fasts embedded in M-15 grade concrete block of 350 mm x 100 mm x 100 mm in the
hole of the masonry. In case of concrete, frames shall be fixed by 96 mm long 12 mm dia metallic dash
fasteners.
MEASUREMENT AND PAYMENT
The Wood work shall be measured in length, breadth/depth as specified on drawing or as directed, correct up
to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.
ITEM NO. 14
Providing and fixing glazed louvered glass windows and ventilators with teak wood frame 10 cm. x 7cm. Size
including the cost of oil painting to wood work etc. complete.
Glass sheets for glazing shall be
i)
ii)
iii)
iv)

4 mm thick plain glass (wt. 7.2 kg./m ) conforming IS : 2835, or


5.5 mm thick wired glass conforming to IS : 5437 or
6.3 mm thick laminated glass conforming to IS : 2553 as the case may be as per item
description or
5.5 mm thick toughened glass.

Glass sheets shall be free from flaws, scratches, cracks, bubbles etc.
Teakwood stiles and rails of size as specified in item description shall be cut accurately and planed smoothly
to required dimensions as per drawings. The stiles and rails shall be provided with rebates for fixing the
glazing and shall be joined together to form the profile of the shutter as per drawings. The joinery work shall
be as approved by Engineer. Only after such approval, the joints shall be coated with white lead, pressed and
secured by hardwood pins of about 6 mm dia. All the four edges of the shutter shall be square. In case of
double leaf doors, rebates shall be provided at the meeting of stiles. Rebates shall be splayed type and one
third the thickness of the stiles.
The glass sheets for glazing shall be fixed by teak wood beading having mitred joints as per drawings and
shall be fixed by means of approved neoprene based adhesive and nailing, the spacing between the nails
being no more than 300 mm.
All wooden surfaces shall be coated with 2 coats of approved make polyurethane with stainer mixed to
achieve desired shade.
The shutter shall be fixed to the door frame, by means of hinge @ minimum 3 hinges per leaf, maximum
spacing of hinges being 600 mm or as per drawing with suitable sized screws.
The shutter when fitted to the frame shall satisfy all operational aspects of the door like smooth movement,
proper closing against the door frame etc.
MEASUREMENT AND PAYMENT
The Wood work shall be measured in length, breadth/depth as specified on drawing or as directed, correct up
to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.

Borsad Nagar Sevasadan

70

ITEM NO. 15
Providing and fixing M.S. grills of required paten to wooden frames of windows etc. with M.S. flats at required
spacings and frame around square or round bars with round headed bolt and nuts or by screws. (A) plain
grill. (Window).
Materials:
The structural steel conforms to M-22.
Workmanship:
The M.S. grill shall be prepared as per the drawings or as directed for fixing to wooden frames of windows etc.
The grill shall be fabricated to the designs and pattern shown in the drawings and the weight shall be riveted or
welded as shown in the plan or is directed. The grill so formed shall be fixed in to the frames of the windows etc.
before they are erected in position. The outside strip frame of the grill shall be housed to its full thickness in to
the recess cut in to the frames of the window etc. the grill shall be fixed to the frames with number of bolts and
nuts of screws viz. bolts nuts/crews per 30 cm. Of the length of outer strip subject to a minimum of 12 Nos. on
each side of the frame or as indicated in the drawing or as directed.
The bolts nuts and screws shall be counter sunk and shall be fixed with the top of their heads flush with the race
of frames strips.
Mode of measurements & payment:
No payment shall be made for weight of screws, bolts; nuts etc. only weight of grill shall be paid.
The rate shall be for unit of one Kg.

ITEM NO. 16
10 mm thick cement plaster in single coat on brick/concrete walls for interior plastering up to floor two level
finishing even and smooth in (II) cement mortar 1:3
Extra over above item for finishing with a floating coat of neat cement slurry for Wall
Extra over above item for paltering on ceilings and soffits of stair above floor two level for every additional
storey height finishing with a floating coat of neat cement slurry for Ceiling
The Contractor shall furnish all labour, materials scaffolding, equipment, tools, plants and incidentals
necessary and required for the completion of all plaster work.
GENERAL:
Plaster as herein specified shall be applied to all internal surface where called for. All plaster work shall be
executed by skilled workmen in workmen like manner and shall be of the best workmanship and in strict
accordance with the dimensions on drawings subject to the approval of the Consultant/Owner.
The primary requirement of plaster work shall be to provide dense, smooth and hard enclosure and devoid of
any cracks of the interior and/or exterior.
SCAFFOLDING:
Double scaffolding having two seats of vertical supports shall be provided. The supports shall be sound and
strong, tied together with horizontal pieces over which scaffolding planks shall be fixed. The contractor shall
get the scaffolding approved from the Consultant well in advance.
CHASING AND BREAKAG:
All fixing of door and window frame shall be completed before any plaster work is commenced on a surface.
No chasing or cutting of plaster shall be permitted normally. However, If the same is felt unavoidable at
places, written permission shall be obtained from the Consultant before cutting any such plaster. Broken
corners shall be cut back out less than 150 mm on sides and patched with cement mortar as directed. All
corners shall be rounded to a radius of 80 mm or as directed by the consultant.
PREPARATION:
Masonry and concrete surfaces which call for application of plaster shall be clean, free from dust and loose
mortar. Efflorescence if any shall be removed by brushing and scrapping. For masonry surfaces the joints
shall be raked out properly, while the concrete surfaces shall be roughed by wire brushing and hacking to
provide the key, thereby ensuring proper bond to the satisfaction of the consultant. The surface shall then be
thoroughly washed with water, cleaned and kept wet before plastering is commenced.
CHICKEN WIRE MESH:
Galvanized chicken mesh (22 gauge, 12 mm size) shall be provided at junctions of brick masonry and
concrete members, to be plastered and other locations as called for, properly stretched and nailed with
galvanized wire nails, ensuring equal thickness of plaster on both sides of the mesh. The width of the mesh
Borsad Nagar Sevasadan

71

shall be as approved by the Consultant. The chicken mesh wherever specified, shall be fixed in place before
plastering.
Samples of each type of plaster shall be prepared well in advance of undertaking the work for the approval of
the Consultant/Owner.
MORTAR:
The mortar of the 1:4 shall be used. Mortar shall be prepared as specified under Brick Work. It shall be
made in small quantities, as required, and applied within 15 minutes of adding water to the plaster mix.
CEMENT:
Cement shall be as per specifications under Concrete Work.
WATER:
Water shall be as per specifications under Concrete Work.
SAND:
For plaster work normally clean fine river sand shall be used. However, if specified in the drawing or schedule
of finishes, coarse sand conforming to the specifications under concrete work shall be mixed with fine river
sand in proportion specified or directed by the consultant.
FINISH:
The plaster shall be finished to a true and plumb surface and to the proper degree of smoothness as required.
The work shall be tested frequently as the work proceeds with a true straight edge not less than 2.5 m long
and with plumb bobs. All horizontal lines and surfaces shall be tested with a level and all jambs and corners
with a plumb bob as the work proceeds.
CURING:
Curing shall be started as soon as the plaster has hardened sufficiently not to be damaged when watered.
The plaster shall be kept wet for a period of at least 7 days. During this period, it shall be suitably protected
from all damages.
PRECAUTION:
Any cracks which appear in the surface and all portions, which sound hollow when tapped or are found to be
soft or otherwise defective, shall be cut out in rectangular shape and redone as directed by the consultant.
FLOATING COAT OF NEAT CEMENT:
Where finishing with a floating coat of neat cement is specified in the drawings or directed by the Consultant,
specification for this item of work shall be same described above except for the additional floating coat which shall
be carried out as below. When the plaster has been brought to a true surface with the wooden straight edge, it
shall be uniformly treated over its entire area with a paste of neat cement and rubbed smooth, so that the whole
surface is covered with neat cement coating. The quantity of cement applied for floating coat shall 1 kg. per sq.
mt. smooth finishing shall be completed with trowel immediately and in no case later than half an hour of adding
water to the plaster mix.
MEASUREMENT AND PAYMENT
The Plaster work shall be measured in length, breadth/depth as specified on drawing or as directed, correct
up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.
ITEM NO. 17
20mm thick sand face cement plaster on walls up to 10meter height above ground level consisting of 12 mm
thick bracking coat of C.M. (1:3) (1 Cement, 3 sand) and 8mm thick finishing coat of C.M. (1:1) (1 Cement, 1
sand) etc. complete..
Materials:
Water shall conform to M-12. Cement mortar shall conform to M-11.
Workmanship:
Scaffolding: wooden bellies, bamboos, planks, treat less and other scaffolding shall be sound. These shall be
properly examined before erection and use. Stage scaffolding shall be provided for ceiling plaster which shall
be independent of the walls.
The rate shall be carried out in the coats. The backing coat (base coat) shall be 12 mm. thick in C.M. 1:3 the
relevant specifications shall be followed except that the thickness or back coat shall be 12 mm. averages.
Borsad Nagar Sevasadan

72

Before the first coat hardens its surface shall be beaten up by edges of wooden tapers and close dents shall
be made on the surface.
The subsequent coat shall be applied after this coat has been allowed to set for 3 to 5 days depending upon
the weather conditions. The surface shall not be allowed to dry during this period.
The second coat shall be completed to 8 mm. thickness in C.M. 1:1 as described above, including raising
sand facing by bushing. The sample of sand face shall be go approved before the work is started. The whole
work shall be carried out uniformly as per sample approved.
Preparation of back-ground:
The surface shall be cleaned of all dust, loose mortar droppings, traces of algae, efflorescence and other
foreign matter by water or by brushing. Smooth surface shall be roughened by wire brushing if it is not hard
and by racking if it is hard. In case of concrete surface, if a chemical retarded has been applied to the form
work, the surface shall be roughened by wire brushing and all the resulting dust and loose particle cleaned off
and care shall be taken than none of the retarders is left on the surface. Trimming of the projections on
brick/concrete surface where necessary shall be carried out to get an even surface.
Raking of joints in case of masonry where necessary shall be allowed to dry out for sufficient period before
carrying out the plaster work.
The work shall be not be soaked but only damped evenly before applying the plaster. If the surface becomes
dry such area shall be moistened again.
For external plaster, the plastering operation shall be started from top floor and carrier downwards. For
internal plaster. the plastering operation may be started wherever the building frame and cladding works are
ready and the temporary supporting ceiling resting on the wall of the floor have been removed. Ceiling plaster
shall be completed before starting plaster to walls.
Application of Plaster:
The plaster about 15 X 15 Cms. shall be first applied horizontally and vertically at not more than 2 meters
intervals over the entire surface to serve as gauge. The surface of the gauges shall be truly in plane of the
finished plastered surface. The mortar shall than be applied in uniform surface slightly more than the specified
thickness, then brought to a true surface by working a wooden straight edge reaching across the gauges with
small upward and sideways movement at a time. Finally, the surface shall be finished of true with a trowel or
wooden float according as a smooth or a sandy granular texture is required. Excessive towelling or
overworking the float shall be avoided. All corners, arises, angles and junctions be truly vertical or horizontal
as the case may be and shall be carefully finished, Rounding or chamfering corners, arise junctions etc. shall
be carried out with proper templates to the size required.
Cement plaster shall be used within half an hour after addition of water. Any mortar or plaster, which is
partially set, shall be rejected and removed forthwith from the site.
In suspending the work at the end of the day, the plaster shall be left out clean to the line both horizontally
and vertically. When recommending the plaster, the edge of the old work shall be scraped clean and wetted
with cement putty before plaster in applied to the adjacent areas to enable the two to properly join together.
Plastering work shall be closed at the end of the day on the body of the wall and nearer than 15 cm. To any
corners or arises. Horizontal joints in plasterwork shall not also occur on parapet tops and copings as these
invariably lead to leakage. No portion of the surface shall be left out initially to be packed up later on.
Each coat shall be kept damp continuously till the next coat is applied or for a minimum period of 7 days.
Moistening shall commence as soon as plaster is hardened sufficiently. Soaking of walls shall be avoided and
only as much water as can be readily absorbed shall be used, excessive evaporation on the sunny or
windward side of building in hot air or dry weather shall be prevented by handing matting or gunny bags on
the outside of the plaster and keeping them wet.
Mode of Measurement & Payment:
The rate shall include the cost of all materials, labours and scaffolding etc. involved in the operations
described under workmanship.
All plastering shall be measured in square meters unless, otherwise specified. Length breadth or height shall
be measured correct to a centimeter.
Thickness of the plaster shall be exclusive of the thickness of the sky i.e. grooves or open joints are
brickwork, stonework etc. or space between laths. Thickness of the plaster shall be average thickness with
minimum 10 mm. at any point on this surface.
This item includes plastering up to floor two levels.
The measurement of wall plastering shall be taken between the walls or partition (dimensions before a
plastering being taken) for length and from the top of floor or skirting to ceiling for height. Depth of cover of
cornices if any shall be deducted.
Soffits of stairs shall be measured as plastering on ceilings. Followings soffits shall be measured separately.
For jams, soffits, sills etc. for opening not exceeding 0.5 sq. mt. each in area for ends of joins, beams, posts,
girders, steps, etc. not exceeding 0.5 sq. mt. each in area and for opening exceeding 0.5 sq. mt. and not
exceeding 3.00 Sq.m. in each area deductions and additions shall be made in the following manner:
Borsad Nagar Sevasadan

73

(a)

No deductions shall be made for ends of joints, beams, posts etc. and openings not exceeding 0.5
Sq.m. each and no addition shall be made for reveals, jambs, soffits, sills etc. of these opening for
finish to plaster around ends of joints, beams posts etc.
(b) Deduction for openings exceeding 0.5 Sq.m. but not exceeding 3 Sq.m. each shall be made as
follows and no addition shall be made for reveals, jambs, soffits, sills etc. of these openings.
(i)
When both faces of all walls are plastered with same plaster, deduction shall be made for one
face only.
(ii)
When two faces of wall are plastered with different types of plasters or if one faces is
plastered and the other pointed, deductions shall be made from the plaster or pointing on the
side of frame for door, window etc. on which width of reveals is less than that on the other
side but no deductions shall be made on the other side. Where width of reveals on both faces
of all is equal, deductions of 50 % of area of opening on each face shall be made from area
of plaster and/or pointing as the case may be.
For openings having doorframes equal to projecting beyond the thickness of wall, full deduction for
opening shall be made from each plastered face of the wall.
In case of openings of area above 3 Sq. m. each, deduction half shall be made for opening but jambs,
soffits and sills shall be measured.
The rate shall be for a unit of 1 Sq. m.
ITEM NO. 18
Distempering (two coats) with oil bound distemper of approved brand and manufacture and of required shade
on wall surface to give an even shade over and including a priming coat with distemper primer of approved
brand and manufacture after thoroughly brushing the surface free from mortar dropping and other foreign
matter and also including preparing the surface even and sand prepared smooth..
for Wall
Extra over above item with oil bound washable distemper on ceiling and sloping roofs for Ceiling
And
ITEM NO. 19
Providing, applying and finishing with 2 coats of water proofing cement paint on under coated wall surface of
an approved brand, manufacturer and of required even shade after brushing the surface to remove all dirt
and remains of house power materials including scaffolding, curing etc. complete as directed by Engineer-incharge.
GENERAL:
All materials required for the execution of painting work shall be obtained direct from approved manufacturers
and shall be brought to the site in makers drums, kegs etc. with seals unbroken.
If in case of ready mixed paints, thinning if necessary, the brand of thinner shall be as per recommendations
of the manufacturer.
Paint shall be applied by brushing or spraying. The brushing operations are to be adjusted to the spreading
capacity advised by the manufacturer. During painting, every time after the paint has been worked out of the
brush bristles, the bristles shall be opened up by striking the brush suitably.
Spray machine used may be of high pressure type or low pressure depending on the nature and location of
work. After work, the brushes shall be completely cleaned off paint and shall be hung in a thinner if intended
to be used afterwards. The spray guns shall be cleaned thoroughly after every break in work. The paint
containers, when not used shall be kept close and free from air.
After the finishing of work, the adjacent surfaces not intended to be washed/distempered/painted/polished,
shall be thoroughly cleaned of all paint patches and shall be finished in accordance with surface finishing of
such surfaces.
White washing:
White washing in general shall confirm to IS 6278.
Scaffolding:
Wherever scaffolding is necessary, it shall be erected in such a way that as far as possible no part of
scaffolding shall rest against the surface to be white / colour washed. For white washing of ceiling, proper
stage scaffolding shall be erected.
Preparation of surfaces:
The surface shall be thoroughly cleaned of all dirt, dust mortar dropping and other foreign matter before white
wash is to be applied.

Borsad Nagar Sevasadan

74

Surface already white/colour washed shall be boomed down to remove all dust, dirt, loose scales of lime
wash or other foreign matters.
All damaged portions of the surface plaster shall be removed to full depth of plaster in rectangular patches
and plastered again after raking the joints in masonry properly. Such portions shall be wetted and allowed to
dry before any operation.
All holes, cracks, patches etc. not exceeding 0.1 sqm in area shall be made good with material similar to that
of the surface. Surfaces affected by efflorescence, moss, fungi, algae, lichen etc. shall be treated in
accordance with IS 2395.
Preparation of white wash:
The fat lime conforming to IS 712 shall be slaked at site and shall be mixed and stirred with about 5 liters of
water for 1 kg. of unslaked lime to make thin cream. This shall be allowed to stand for a period of 24 hours
and then shall be screened through a clean coarse cloth. 4kg of gum dissolved in hot water shall be added to
each cubic meter of lime cream. Approved quality ultramarine blue conforming to IS 55 @ 3 grams per kg. of
lime shall also be added to the solution. The whole solution shall be stirred thoroughly before use.
Application:
White wash shall be applied with 'MOONJ' brush to the specified number of coats. The operation for each
coat shall consist of stroke of the brush from the top to down wards, another from the down to upwards over
the first stroke, similarly one stroke horizontally from right and another stroke from the left. Each coat shall be
allowed to dry before the next coat is applied.
The white washing on ceiling should be done prior to that on walls.
Protective measures:
Surface of doors, windows, floors etc. which are not to be white washed shall be protected from being
splashed upon. such surfaces shall be cleaned of white wash splashed.
Waterproof cement paint
Preparation of surface
Preparation of surface shall be in accordance with clause no. 6.2.1.2. The surface so prepared shall be
thoroughly wetter with clean water before the paint is applied.
Preparation of paint
Waterproof cement paint of approved make shall be mixed with water and stirred to obtain a thick paste which
shall then be diluted to brush able consistency. The proportion of mixture shall be as manufactures
recommendation .The paint shall be mixed in such quantity which can be used up within an hour of mixing to
avoid setting and thickening of the paint.
Application of paint
The surface shall be treated with minimum two coats of waterproof cement paint. No less than 24 hours shall
be allowed between two coats and the subsequent coats shall be applied only after the preceding coat has
become hard to resist marking by subsequent brushing.
The finished surface shall be even and uniform in shade without patches brush marks, paint drops, etc.
Cement paints shall be applied with a brush with relatively short stiff hog of fiber bristles.
Curing
Curing shall be started after the paint has hardened. Curing shall be done by sprinkling with water two or
three times a day. This shall be done between coats and for at least two days following the final coat.
MEASUREMENT AND PAYMENT
The Color work shall be measured in length, breadth/depth as specified on drawing or as directed, correct up
to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.

ITEM NO. 20
Providing and laying polished kota stone slab flooring over 20mm (average) thick base of cement mortar 1:6
(1 cement, 6 coarse sand) or L.M. 1:1:5 laid and jointed with gray cement slurry including rubbing and
polishing complete. (A) 25mm thick.
The contractor shall furnish all labour, materials, tools, equipment, machinery operations and related items
necessary and required for the full performance of the contract under this section, as shown on the drawings
or as specified or reasonably implied or incidental to the construction.

Borsad Nagar Sevasadan

75

GENERAL:
The flooring shall be laid to the level except where slopes are called for on the drawings, in which case the
slopes shall be uniform and arranged to drain into the indicated outlets. Particular care shall be exercised to
ensure that all flooring, skirting etc. is perfectly matched for colour and finish. The contractor shall pave the
areas indicated on the plans and schedule of finishes with materials therein called for. All work shall be laid to
the best practice known to the trade.
The contractor shall furnish for approval by the consultant, samples of each type of floor, paving etc. The
samples shall be of sizes and thickness as specified.
MATERIALS:
CEMENT:
Ordinary grey Portland cement, white or colored cement conforming to BIS: 269 (latest edition or blast
furnace slag cement conforming to BIS: 455 latest editions.
WHITE CEMENT:
White cement shall be as per BIS:269 or latest edition.
AGGREGATES:
Coarse and fine aggregate shall conform to the requirements of BIS: 383 latest edition.
PIGMENTS:
Pigments shall be from approved manufacturer and be guaranteed to be absolutely colour fast. Black pigment
shall be lamp black as manufactured by m/s. Philips carbon black or approved equal. Other colours shall be of
manufacturer to be approved by the consultant.
WATER:
Water shall be clean, free from oil, acid, alkali, soluble salts etc.
KOTAH STONE SLABS:
The slabs shall be of selected quality, hard, sound dense and homogeneous in texture, free from cracks,
decay, weathering and flaws. They shall be hand or machine cut to the requisite thickness, they shall be of
the colour indicated in the drawings or as instructed by the Engineer.
The slabs shall have the top (exposed) face polished before being brought to site, unless otherwise specified.
The slabs shall conform to the size required. Before starting the work the contractor shall get the samples of
slabs approved by the Engineer.
The thickness of the slabs shall be 20,30 or 40 mm as specified in the description of the item. Tolerance of +
or 2 mm shall be allowed for the thickness. In respect of length and breadth of slabs, a tolerance of + or 5
mm shall be allowed.
DRESSING:
Every kota stone slab shall be machine cut to required size and shape as specified in the drawings. All angles
and edges of the kota slabs shall be true and square and free from chipping and the surface shall be true and
plane. The thickness of the stone shall be as specified in the drawings. No tolerance shall be allowed for
thickness.
Kotah stones for flooring shall be mirror polished and shall be of yellow greenish tint. Kotah stone for terraces
shall be rough dressed kota stone of yellow greenish tint. Kotah stone slabs shall be of approved quality and
shade and shall be free from cracks and flakes and of uniform colour.
The contractor shall ensure that no chisel marks are visible on the surface of the stone before fixing. Stones
with chisel marks shall be rejected.
LAYING OF STONE SLABS OF KOTA STONE:
Sub grade concrete or the RCC slab on which the slabs are to be laid shall be cleaned, wetted and mopped.
The bedding for the slabs shall be with cement mortar 1:4 (1 cement : 4 course sand).
The thickness of the bedding mortar under the slab shall be as specified in the drawings/schedule of finishes.
The slab shall be laid in the following manner.
Mortar of the specified mix shall be spread under the area of each slab, to the thickness specified. The slab
shall be washed clean before laying. It shall be laid on top, pressed, tapped with wooden mallet and brought
to level with the adjoining slabs. It shall then be lifted and laid aside. The top surface of the mortar shall then
be corrected by adding fresh mortar at hollows. The mortar is allowed to harden a bit and cement slurry of
honey like consistency shall be spread over the same at the rate of 4.4 kg of cement per Sq. m. The edges of
the slab already paved shall be buttered with grey cement with admixture of pigment to match the shade of
the slabs. The slab to be paved shall then be lowered gently back in position and tapped with wooden mallet
till it is properly bedded in level with and close to the adjoining slab with as fine a joint as possible.

Borsad Nagar Sevasadan

76

Subsequent slabs shall be laid in the same manner. After each slab has been laid, surplus cement on the
surface of the slabs shall be cleaned off. The flooring shall be cured for a minimum period of seven days.
The surface of the flooring as laid shall be true to levels and slopes as shown in the drawings.
The slabs shall be laid as per the pattern shown in the drawings. Slabs which are fixed in the floor adjoining
the wall shall enter not less than 12 mm under wall finish. The junction between wall finish and floor shall be
finished neatly and without waviness.
A thick bed of saw dust or other approved material shall be spread over the floors as necessary to keep the
floors free of scratches and other damages. This shall be cleared away on completion to leave the floor
scratch free and stain free. Any damaged area or floor shall be replaced to the satisfaction of the consultants
at the contractors own cost.
SAMPLES:
The size and thickness of the stone slabs/stones for flooring and paving shall be as specified in the drawings.
Before proceeding with the setting of stone work the contractor shall prepare samples for the approval of the
consultants. No deviation in the workmanship shall be permitted from the workmanship and appearance of
the accepted sample. The contractor shall also prepare samples of stone work to be provided on the other
parts of the work on site e.g. in landscaping work, boundary wall etc. and shall submit them for approval.
The approval of a typical sample of a finished stone by the consultant implies that the contractor shall finish
and dress the stones as per the approved site sample. The consultant shall however reject any stone on the
site which does not conform to the accepted sample. No payments shall be made for any rejected stone
whether rejected before or after fixing. Only the final, finished, erected and approved stone work shall be
accepted.
WORKMANSHIP:
The work of laying, setting, finishing, polishing etc. shall be carried out by tradesmen fully experienced in the
class of work required. Sub contractors and specialists to be appointed for these items of work shall be got
approved from the consultant before commencing any work.
FINAL POLISH:
WAX POLISH:
When all construction and finishing work is completed, the floor shall be worked clean with dilute oxalic acid
solution and dried. Non slip wax polish shall then be applied with soft linen on the clean and dry surface and
polishing machine fitted with felt or Hessian bobs shall be run over the surface. Clean saw dust shall then be
spread over the surface, polishing machine again applied, mopping up surplus wax and leaving glossy
surface. Care shall be taken that the floor is not left slippery and that ordinary wax is not used under any
circumstances.
MEASUREMENT AND PAYMENT
The Kota stone flooring work shall be measured in length, breadth as specified on drawing or as directed,
correct up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.
ITEM NO. 21
Providing and laying white glazed tiles 6mm thick in flooring, treads and steps and landing laid on 12mm
thick cement motar 1:3 (1cement :3 coarse sand ) and pointing in white cement jointed with white cement
slurry. on flooring.
And
ITEM NO. 22
Providing and laying white glazed tiles 6mm thick in skirtings, risers of steps and dado on 10mm thick
cement motar 1:3 (1cement :3 coarse sand ) and pointing in white cement jointed with white cement slurry.
for dedo
TILES
Glazed tiles shall conform to 1S-777 and shall be of specified shade, size and of approved manufacturer.
PIGMENTS
Pigments to be admixed with mortar or for grouting shall conform to IS 2114.
CEMENT MORTAR
Cement mortar shall be of specified mix and thickness and shall be in accordance with the specification.

Borsad Nagar Sevasadan

77

WORKMANSHIP
The tiles shall be laid over a coating of specified adhesive (as per approved manufacturers specification) laid
on base floor/wall plaster. The joints of the tiles shall be flush pointed with cement paste (white cement and
pigment conforming to IS-2114, ) matching the shade of colours.
CURING
The flooring shall be cured for 7 days by keeping it wet with pending. Heavy traffic on the flooring shall be
permitted only after 14 days.
GLAZED TILES IN RISERS OF STEPS, SKIRTING AND DADO
Ceramic tiles in toilets and other areas where called for shall be non-slip ceramic tiles of approved make and
shade. The tiles shall be laid to the pattern as approved by the consultant. The tiles shall be of uniform colour,
true to size and shape and free from cracks, twists, uneven edges, crazing and other defects. The size and
thickness of the tiles shall be as specified.
The tiles shall be laid as per the pattern shown in the drawings over a bed of specified thickness of cement
mortar leveled to a true surface. The surface of the bedding mortar shall be left rough to provide bond for the
tiles. A floating coat of thick cement slurry shall be laid over the screed to proper levels and the tiles set over
the same firmly to correct line and levels.
The joints shall be filled and finished neat with cement paste pigmented to the shade of the tile. The joints
shall be finished neat as directed and shall be straight, regular and uniform.
On completion, the surface shall be washed with water, rubbed with fine saw dust and left clean.
The finished floor surface shall be true to required levels.
MEASUREMENT AND PAYMENT
The glazed tiles work shall be measured in length, breadth/depth as specified on drawing or as directed,
correct up to nearest centimeter content shall be worked out nearest up to two place or decimal.
The rate shall be for a unit of square meters.
ITEM NO. 23
Providing and fixing wash basin with single hole for pillar tap with C.I. Or M.S. brackers painted white
including cutting holes and making good the same but excluding fittings:
(A) Vitreous china
(ii) In white colour
Materials:
The white glazed earthenware wash basin shall 550 cm. X 400 mm. of 1st quality and make as provided by the
Engineer-in-charge. The wash basin shall conform to M- 59.
Workmanship:
The wash basin shall be fixed on the wall as and where directed. The wash basin shall be supported on a pair
of M.S. or C.I. brackets fixed in C.M. 1:3 (1 cement: 3 sand). The bracket shall conform to I.S. 775 1962. The
wall plaster on the rear be cut to rest the top edge of the wash basin. After fixing the basin, plaster shall be
made good and surface finished to match with the existing one.
The bracket shall be painted white with ready mixed paint.
The C.I. brass trap and union shall be connected to 32 mm. dia. waste pipe which shall be suitably bent towards
the wall and which shall discharge into an open drain leading to a gully trap on the ground floor and shall be
connected to a waste pipe through a floor trap on the upper floor. C.I. brass trap and union may not be provided
where the surface drain or a floor trap is placed directly under the basin and the waste is discharged in to
vertically.
The height of the front edge of the wash basin from the floor level shall be 80 Cms.
The necessary inlet connection and fitting such as pillar cocks. C.P. dress waste trap waste trap waste pipe,
stop cock, chain wish rubber plug etc. shall be fixed.
The payment of fitting shall be made separately under separate item.
Mode of measurement & payment:
The rate includes cost of all labour, materials, tools and plant etc. required for satisfactory completion of this
item as specified in workmanship.
The rate shall be for a unit of one number.
ITEM NO. 24
Providing and fixing Kitchen sink with C.I. Or M.S. brackers painted white including cutting holes and making
good the same but excluding fittings:
(C) Vitreous china sink.
Borsad Nagar Sevasadan

78

(i) 600 mm x 450 mm x450mm size.


Materials:
White glazed vitreous china sink 600 mm. X 450 mm. X 150 mm. size shall conform to M 63.
Workmanship:
The kitchen sink shall be supported on a pair of M.S. or C.I. brackets fixed in cement mortar 1:3 (1 cement: 3
coarse sand). The M.S. or C.I. brackets shall conform to I.S. 775 1972. The wall plaster on the rear shall be
cut to rest over the top edge of the sink. After fixing the sink plaster shall be made good the surface finished to
match with the existing one.
The C.P. brass trap and union shall be connected to 40 mm. dia nominal bore galvanized mild steel waste pipe
which shall be suitably bent towards the wall and which shall discharge into an open drain leading to a gully
trap or direct into the gully trap on the ground floor and shall be connected to a waste pipe through a floor trap
on the upper floors. C.P. brass trap and union may not be provided where surface drain or a floor trap is placed
directly under the sink and the waste is discharged to it vertically.
The height to front edge of the wash basin from the floor level shall be 80 cms.
Mode of Measurement of Payment:
The rate includes cost of labour, materials tools and plant and other equipment required for satisfactory
completion of this item as described in workmanship.
The rate shall be for a unit of one number.

ITEM NO. 25
Providing and fixing water closet squatting pan (Indian type w. c. pan) size 580mm. (Earth work, Bed concrete
foot rests and trap to be measured and paid for separately)
(A) Vitreous china.
(I) Long paten white colour
Materials:
Water closet squatting pan (India type W.C. Pan) shall conform to M 62. Cement shall conform to M 11.
Workmanship:
The pan shall be sunk in to the floor and embedded in a cushion if average 15 cm. cement 1:5:10 (1 cement: 5
fine sand: 10 graded stone aggregate or brick aggregate 40 mm. nominal size) or as specified. This concrete
shall be left 115 mm. below the top level of the pan so as to allow for flooring and its bed concrete. The floor
should be suitably sloped so that the waste water is drained in to the pan. The pan shall provided with 100 mm.
P or S traps as specified in the item No. 23. 113 with approximately 50 mm. seal. The joints between the pan
the trap shall be made leak proof with cement mortar 1:1 (1cement: 1 fine sand).
Mode of measurement & payment:
The rate shall include the cost of all materials and labours involved in the operations described under
workmanship.
The rate shall be for a unit of one number.
The P or S traps shall be paid separately.
ITEM NO. 26
Providing and fixing (Two level or slopes) and jointing with stiff mixture of cement mortar in proportion 1:1
salt glazed stone ware pipes following nominal internal diameter including testing of pipes and joints etc.
complete.
(A) 100 mm. dia.
(B) 150 mm. dia.
Materials:
(1) Water shall conform to M- 1, (2) Cement mortar proportion 1:1 shall conform to M-11. (3) 100 mm. dia.
glazed stone ware pipe shall conform to M- 71.
Workmanship:
The trenches for stone ware pipe drains shall be carried out as relevant specifications of item No. 23.4 (A)
except that the work id for stone ware pipes of 100 mm. dia.
Laying: The pipes shall be laid accurately and perfectly true to line, levels and gradients. Great care shall be
taken to prevent sand etc. from entering the pipes. The pipe between two manholes shall be laid truly in a
Borsad Nagar Sevasadan

79

straight line without vertical or horizontal undulation. All junctions and changes in direction and diameter shall
be made inside manholes by means of curved tapered channels formed in cement concrete finished smooth
and benched on both side. The body of the pipe shall rest for its entire, on an even level bed grips being made
or left on the bed to receive the sockets o the pipes.
Jointing:
Tarred gaskin or yarn socked in neat cement slurry first be placed around the spigot of each pipe and the spigot
shall then be placed well home into the socket of the pipe previously laid. The pipe shall then be adjusted and
fixed in the correct position and gaskin caulked home so as fill not more than 1/4 th of the total dept or (13 mm.
in depth) of the socket.
The remainder of the socket shall filled with stiff mixture of cement mortar in proportion of one part of cement
and of sharp sand. when the socket is filled, shall be formed round the joints trowel, forming an angle of 45144
with the barrel of the pipe.
The mortar shall be mixed as necessary for immediate use.
After the joint is made, any extraneous materials shall be removed from the inside of the joints with a suitable
scraper of badger. The newly made joints shall be protected. until set, from the sun, dry winds, rain or frost,
sacking or other suitable materials which shall be used for the purpose.
The mortar shall be cured to 10 year.
Testing of joints:
The pipe line shall be tested as directed.
If any leaking is visible, the defective part of the work shall be made good at no extra cost.
A slight amount of sweating which is uniform may be over looked, but excessive sweating form a particular pipe
or joints shall be watched for and taken as indicating a defect to be made good.
Mode of measurement & payment:
Pounding or buttoning of the trenches bed to fit the lower part of the pipe and Grip left to take socket, collars
etc. are included in the rate of laying the pipes.
The measurement shall be net without any allowance for cutting and waste. The length pf bends, junctions and
other connections shall be included in the total length of the drain pipe. Nothing extra shall be paid for the same.
The rate includes necessary excavation refilling trenches etc. complete.
The rate shall be for a unit of one running meter.
ITEM NO. 27
Providing & fixing screw down bib taps of following size.
(A) Brass screw down bib tap polished bright.
(I) 15mm. Dia.
Materials:
15 mm. dia. brass screw down with bright polished finish shall conform to I.S. 781 1977. The bib cock shall be
best Indian make and quality.
Workmanship:
The screw down bib cock 15 mm. dia. as specified above shall be fixed as directed. The threaded portion shall
be smeared with white or red lead and around with a few turns of fine spun yarn round the screwed end of the
pipe. The bib cock shall be than screwed and fixed to water tight position.
Mode of Measurements & Payment:
The rate includes cost of all labour, materials, tools and plant etc. required for satisfactory completion of this
item.
The rate shall be for a unit of one number.
ITEM NO. 28
Providing & fixing pillar tap, capstan head, screw down high pressure with screws, shanks & back nuts.
(A) 15mm dia.
Materials:
The capstan head pillar tap of specified dia. of C.P. cover brass shall be of best quality and shall conform to
I.S.: 1795 1961. The pillar taps shall be tested quality.

Borsad Nagar Sevasadan

80

Workmanship:
The capstan head pillar tap of specified dia. shall be fixed as directed with required washer of selected leather
or rubber asbestos composition or of plastic as directed. The cock shall fix with pipeline with white zink end
spun yarn to make joint watertight. The work shall be carried out in best workman like manner.
Mode of Measurements & Payment:
The rate includes cost of all labour, materials tolls and plant etc. required for satisfactory completion of this item.
The rate shall be for a unit of one number.
ITEM NO. 29
Providing and fixing chromium plated brass half turn flush cock of approved quality including fixing in pipe
line etc. complete.
(ii) 25mm dia.
Materials:
Chromium plated brass half turn flush cock shall conform to M 67.
Workmanship:
The half turn flush cock specified diameter shall be fixed as directed. The flush cock shall be fixed in G.I. pipe
line with necessary fittings. The joints shall be made leak proof by using spun yarn and white zink. The fixing
work shall be carried out as per relevant specifications.
Mode of Measurements & Payment:
The rate includes cost of all materials and labour required for satisfactory completion of this item including
fittings.
The rate shall be for a unit of one number.
ITEM NO. 30
Constructing brick masonry chamber for underground C.I. Inspection chamber and bends with bricks having
crushing strength nor less than 35 kg/cm2. In cm. 1:5 C.I. Cover with frame ( light duty) 455 mm. X 610 mm.
internal dimensions , total weight of cover with frame to be not less than 38 kgs. Weight of cover 23 Kg. And
wt. of frame 15 kg ).
(I) inside dimensions , 455mm x 610mm x 450 mm deep for single pipe line.
Materials:
Water shall conform to M-1. Cement shall conform o M-3. Coarse sand shall conform to M-5. Brick shall
conform to M-15. Stone aggregate shall conform to M-12. Brickbat shaft shall conform to M-14. Bar shall
conform to M-18.
Workmanship:
C.I. inspection chamber with provision of C.I. bends of specified size with bolts, nuts and left washers for
underground drain shall be enclosed in masonry chamber which shall be constructed as under:
The excavation shall be done true to dimensions and level shown on the plans or as directed.
Bed concrete shall be of 15 Cms. thick C.C. 1:5:10 (1 cement: 5 coarse sand: 10 graded brickbat aggregate.)
the projection of bed concrete beyond the masonry walls shall be 7.5 cms.
Masonry walls and plasterwork shall be carried out as per relevant specifications of item 24-40.
The covers slab shall be constructed as per relevant specification of 24.27 (I).
Mode of Measurement and Payment:
The earthwork in excavation providing and laying C.I. Inspection chamber and bends shall be measured and
paid per separately.
The rate shall be for a unit of one number.
ITEM NO. 31
(B) Providing sock pit of 5.00 cu.mt. Volume including excavating sand filling brick bats with dry masonry
work at top for 5 CM high including covering the top with stone including providing vatas in C:M 1:3 with
finishing curing etc. complete.
Materials:
Water conform to M 1. Cement mortar shall conform to M 11. burnt bricks shall conform to M 15. Rough
stone slab 40 X 50 mm. thick shall conform to M 48. Brick bat shall conform to M 14.

Borsad Nagar Sevasadan

81

Workmanship:
The excavation for soak pit shall be carried out as per relevant specifications of item 4.00.1 (A) except that the
size of soak pit shall be such that the clear volume shall remain 2 Cu.m. the diameter and depth shall be as
directed.
The periphery of the soak pit shall be provided with dry masonry with burnt bricks in 23 cm. thick. Masonry wall
be done with best workman like manner in true line and plumb.
The sock pit shall be filled in with brick bats of burnt brick 40 Cms. nominal size in 45 Cms. height. The work of
filling brick bats shall be done in such a way that no dry masonry shall be damaged during filing of brick bats.
The top of the sock pit shall be covered with rough kota stone slab 40 to 50 mm. the length of the stone shall be
in single pieces in length.
The cement mortar 1:3 shall be used t fill up the joints and preparing vata as directed.
The cement work shall be cured for 4 days.
Mode of measurement & payment:
The rate includes coat of all labour and materials required for satisfactory completion of this item as described
above.
The rate shall be for a unit of one number.
ITEM NO. 32
Constructing a cooking platforms 60cm. Width and 70cm. Height resting on B.B Masonry walls 23cm. Thick in
cm.(1:6) with (1) Fixing of pre-cast R.C.C (1:2:4) 8 cm thick slab with marble mosaic chips set in c. m (1:6) 6
mm . Thick (terrazzo ) with plastering on exposed faces of wall in cm. (1;4) etc. complete.
Materials:
Water shall conform to M- 1. Cement shall conform to M- 3. Sand shall conform to M- 6. Burnt shall conform to
M- 15. Marble Mosaic chips shall conform to M- 46. Stone aggregate 20 mm. nominal size shall conform to M18.
Workmanship:
The cooking platform of size as directed shall be constructed in 60 Cms. height the brick masonry wall in C.M.
1:6 shall be constructed in 23 Cms. thickness up to full deth. The relevant specification of item 6.13 (B) shall be
followed for masonry work.
The R.C.C. slab of 8 Cms. thicknesses and of adequate design and size shall be precast and the same shall be
put up on the B.B. masonry work.
The top and exposed sides of the R.C.C. slab shall be finished with marble mosaic terrazzo 8 mm. thick with
required colour pigment. The work of terrazzo shall be carried out as per.
The whole masonry work shall be finished with cement mortar in C.M. 1:4. The relevant shall be followed.
Mode of measurement & payment:
The work of cooking platform shall be measured for finished work.
The rate includes cost of all labour and materials, etc. required for satisfactory completion of this item as
described above.
The rate shall be for a unit of one Running Meter.

ITEM NO. 33
Constructing a sink (chowkdi) with C.C. 1:2:4 12 cm thick B.B. Masonry in front and dwarf wall 1.0 Mt. High
and 23 cm thick cement plaster to masonry in cm. (1:3) and cement concrete flooring in 1:2:4 with 5 cm. dia.
A.C. drain pipe etc. complete.
Materials:
Water shall conform to M- 1. Cement shall conform to M- 3. Sand shall conform to M- 6. Burnt brick shall
conform to M- 15. Stone aggregate 20 mm. nominal size shall conform to M- 12a. and A.C. Drain pipe of pipe of
5 Cms. dia. shall conform to M- 74.
Workmanship:
The chowkadi shall be constructed of specified size and as directed. The slab shall be cost on B.B. masonry
wall 12 Cms. Thick and dwarf wall 1 M. high, and 23 Cms. Thick shall be constructed in proportion of C.M. 1:3
The relevant specifications of item No.6.3 (I) shall be followed for masonry partition work and 5.4.1 (C) shall be
followed for reinforcement concrete work.
The whole masonry work shall be finished with cement mortar 1:6 and finished smooth. The relevant
specifications of item No. 17.59 (I) shall be followed for plastering work.

Borsad Nagar Sevasadan

82

The A.C. pipe of 5 Cms. dia. shall be fixed as drainage pipe. The bottom shall be finished with C.C. 1:2:4
finished with cement slurry.
Mode of measurement & payment:
The work shall be measured for finished work.
The rate includes cost of all materials labour etc. requred for carrying out satisfactory completion of work.
The rate shall be for a unit of one Sq. m.
ITEM NO. 34
Providing light point fitting using 0.12 mm2 copper wire in PVC batten fitting incl. all specials, anchor or
comet make switches, plug point, two/three pin combined half points with switching arrangement, item also
includes to provide wiring from GEB fuse to boards incl. main switch, room fuse & blank sheet with boards
and full ear thing arrangements etc. complete.
Scope
This section covers, definition of point wiring, system of wiring and supply, installation, connection, testing and
commissioning of point wiring for light points, ceiling fan points, exhaust fan points, convenience socket outlet
points, power socket outlet points, bell outlet points etc. including fixing of light fixtures, ceiling fan, exhaust
fan, wall fan, bell etc.
Point Wiring
A point shall consist of the branch wiring from the distribution board together with a switch as required,
including the ceiling rose or pendant holder or swan holder, or ceiling fan box or socket or suitable
termination. A point shall include, in addition, the earth continuity conductor / wire from the distribution board
to the earth pin / stud of the outlet / switch box and to the outlet points.
Supplying and drawing of wires of required size including earth continuity wire.
Supply, installation and connection of flush type switches, sockets, cover plates, switch plates, and fixing fan
regulator etc.
The point shall be complete with the branch wiring from the distribution board to the outlet point, through
switch board, conduit with accessories, junction, pull, inspection boxes, control switch, socket, outlet boxes,
ceiling roses, button / swan holder, connector etc.
Material
PVC Conduits
All non-metallic PVC conduits shall conform to IS: 9537 ( Part 3). The conduit shall be plane and of type as
specified in IS: 9537 and shall be used with the corresponding accessories (Refer IS: 3419 specification for
fittings for rigid non PVC metallic conduits). PVC conduits shall be rigid unplasticised, heavy gauge having 2.0
mm. wall thicknesses up to 20mm. diameter conduits and 2.5 mm. wall thickness for all sizes above 20 mm.
diameter.
Cover Plate
The cover of the boxes to receive outlet points shall be of best anodized sheet cut to shape and size or plate
of approved manufacturers of switches.
Cables
The cables shall conform to IS: 694. For all internal wiring PVC insulated cables of 650 / 1100 volts grade,
single core shall be used.
The conductors shall be plain annealed copper conductors complying with IS: 1554.
The conductors shall be circular copper conductor.
The insulation shall be PVC compound complying with the requirements of IS: 694. It shall be applied by an
extrusion process and shall form a compact homogenous body.
The thickness of PVC insulation shall be as set out in the relevant standards
Point Rate
The rate per point shall include supply, installation, connection, testing and commissioning of point as
described under point wiring. The measurements of the points will be enumerated.
MEASUREMENT
The rate includes cost of all materials, labour includes involved in the operation described under
workmanship.
The Rate shall be for a unit of one Point.

Borsad Nagar Sevasadan

83

ITEM NO. 35
Providing and fixing PVC water storage tank of ISI make including deliver at sites, supply and fixing of inlet,
outlet, air vent over flow, ball cock, drainage sleeves of the specified size, with necessary neo-prene
gasket/packing/washer, GI washer & check nuts etc complete as directed on terrace, loft in bathroom etc any
height. The rate shall include for fixing additional accessories supplied by the supplier accessories.
The polythene water thank shall be best quality should be approved by Engineer-in-charge. The shape and
size of the polythene tank to be fixed shall be as approved by the Engineer-in-charge inlet & out let washout
and over flow arrangement should be provided as per instruction Number and size of tank shall be provided
as per instruction of Engineer-in-charge
The payment under this item shall be on liter basis
The item includes for providing and fixing the same in position with outlet inlet pipes with wash pipe and over
flow pipe and ball cock etc as required.
ITEM NO. 36
Providing and fixing to wall ceiling and floor 6.0 kg. F/cm2 working pressure polyethylene pipes of the
following outside dia. special density, complete with special flange compression type fittings, wall clips etc.
including making good the wall ceiling and floor.
(A) 20mm dia. (6kgf/cm2)
(B) 25mm dia. (6kgf/cm2)
Materials:
The low density polythene pipe of specified diameter with 6 Kg./Sq.cm. working pressure shall conform to I.S.
3076 1968. The specials and fitting required shall be of best quality.
Workmanship:
The P.V.C. Pipes of specified diameter shall be fixed as directed. Due to thermal expansion of rigid P.V.C.
Pipes, due allowed shall be made particularly in over ground pipe lines for any change in length of pipe line
which may occur during installation or when pipe line is in service.
Above ground installation of rigid P.V.C. pipe should be undertaken after preparations are observe for their
protection against direct sun rays and mechanical damage.
The rigid P.V.C. pipe lines should not be kept exposed above ground when if passes through public places,
railway lines, road side and floor paths.
P.V.C. pipes shall be supported at the following intervals:
20 mm. dia. :500 mm. dia.
32 mm. dia.:900 mm. dia.
25 mm. dia. :750 mm. dia.
Closer support spacings shall be provided if recommended by the manufacture.
The guide lines indicated by the manufacture regarding, handling, transportation, storing laying and jointing
pipes shall be kept in view during execution.
P.V.C. pipes shall be fixed on wall with wooden plugs and suitable plastic clamps.
Jointing the pipes:
The pipes and sockets shall be accurately cut. The ends of the pipes and fittings should be absolutely free from
dirt and dust. The outside surface of the pipes and the inside of the fittings shall then be roughened with emery
paper, and then solvent cement joint. Since solvent cement is aggressive to P.V.C., care must be taken to avoid
applying excessive cement to the inside of pipe sockets as any surplus cement cannot be wiped off after
jointing. Empty solvent cement tins, brushes rags, or paper impregnated with cement should not be buried in
the trenches. They should be gathered, not left scattered about, as they can prove to be a hazard to animals,
which may chew them.
If manufacture recommends its own methods of jointing, the same shall be adopted after necessary approval
from the Engineer-in-charge.
Laying pipes in Trenches:
The pipe shall be laid over uniform relatively soft fine grained soil found to be presence of hard object such as
large flints, rockey projection, large tree etc. the width of the trenches shall be minimum width required for
working.
The pipes laid underground shall not be less than one metre from the ground level. The pipe shall be position in
the trenches so as to avoid any induct tresses due to deflection. Any deviation required shall be obtained by
using proper type of rubber ring joints.

Borsad Nagar Sevasadan

84

Mode of measurement & payment:


The relevant specifications of item No. 23.2 (A) shall be followed except that the P.V.C. pipes of specified dia.
shall be paid under this item.
The rate shall be for a unit of one Running meter.
ITEM NO. 37
Providing & laying China mosaic type water proofing treatment on terrace including (a) Applying neat cement
slurry 2.75kg/sq. m of cement admix with water proofing compund after cleaning the surface (b) laying
cement concrete using brick bats 25mm to 100mm size with 50% cement mortar 1:5 admixed mortar proofing
compound over 20mm thick layer of cement mortar 1:5 to required slope including rounded of junctions of
walls and slabs (c) after two days of proper curing applying a second coat of cement slurry (d) finishing the
surface with 20mm thick cement mortar 1:4 and china mosaic tiles & finally finishing the surface with trowel
with white cement slurry (e) after finishing the whole terrace shall be flooded with water for a period of two
day.
Materials :
Cement shall conform to M-3, white glazed tiles shall be of best approved quality as per M-55 & shall be got
approved by Engineer in charge, white cement shall confirm to M-4, sand shall conform to M-3 and pigment
for matching the shade of tiles of best quality and shall got approved by Engineer in charge.
Workmanship:
White glazed tiles shall be broken into pieces of size 12 mm to 20 mm and shall get approved by Engineer in
charge. The surface shall be prepared for laying broken pieces by applying cement mortar. The surface to be
prepared for laying broken pieces in true line and level. After preparing the surface the broken glazed tiles
pieces shall be laid as per design as suggested by architect or
Engineer in charge. The piece shall be laid in white cement slurry. The work
shall be carried out in vertical and horizontal surface including curved surface. After preparing the surface by
broken china pieces, the surface shall be well tempered by wooden template for leveling the surface.
Tempering shall be done in such a manner that the white cement slurry cream shall be come out in upper
portion of the surface. After completion of work, the surface shall be well boomed. The curing shall be done in
such a way that the surface shall be wetted at least seven days. After curing period over, the surface shall be
washed by oxalic acid.
Mode of Measurement and Payment:
The measurement shall be taken on Sq.mt. basis. The payment shall be made on unit of Sq. meter basis. The
visible surface for measurement shall be taken in Consideration. The rate shall include all cost of material,
labour & equipments to complete the job.

Borsad Nagar Sevasadan

85

APPENDIX
APPENDIX I
Details of plants and machinery immediately available with the tenderer for use in this work.
Sr.
No.

Name Of
N0. of Kind or
Equipment
Units
Name
To be attached separately

Capacity

Age And
Condition

DATE:

Present
Location

Remark

SIGNATURE OF CONTRACTOR

APPENDIX - II
LIST OF WORKS ALREADY COMPLETED BY TENDERER
Sr.

Name of work

Place

No.

Cost On
completion

Time taken in months To


complete the work

Remarks

To be attached separately
*

Necessary certificate from the officer concerned shall be attached with the tender.

SIGNATURE OF CONTRACTOR

AUTHORITY

APPENDIX - III

DECLARATION REGARDING WORKS ON HAND WITH TENDERER


Sr.
No
.

Name
of Work

Place

Tender
cost

Works on Hand

Cost of
remaining to
be executed

Estimated
cost

Date
when
decision is
expected

Stipulated
date and
period of
completion

Remarks

Anticipated
date of
completion

To be Attach separately

SIGNATURE OF CONTRACTOR

Borsad Nagar Sevasadan

AUTHORITY

86

You might also like