STUDY OF COST AND TIME IN ACCELARATION OF HOUSES CONSTRUCTION

PROJECT TYPE 79 AT ANUGERAH DIAN REGENCY


By
Dimas Jaya Septhialdy
Coordinator
Ir. Retna Hapsari Kartadipura, MT

ABSTRACT
On the implementation of houses projects often occurs various demand from owner.
As a professional developer, fulfilling owners demans is absolute as long as there are deal
between them. One of the demand is accelarating houses construction project so that the
house can be use as soon as possible. One way to anticipate it is to accelerate the construction
project. Houses construction project type 79 at Anugerah Dian Regency.
In the process of accelerating the constructions schedjule, began with identifiying
works item with the sequences to justify the schedjule in that project. Accelarations
alternative that used is increasing the working hours method and adding more workers. The
calculation began with justify the critical path using Preseden Diagram Method (PDM) then
later crashing to obtain time acceleration which are desired and which method that show
optimal result.
In normal time, a house can be built within 120 days with 7 orang workers dan 8
hour/day of time work with the required cost is Rp.63.321.105,-From research, obtained
adding 3 hours of work per day takes 97 days duration of work with the required cost is
Rp.98.019.438,- . Meanwhile for adding 3 more workers method obtained 99 days duration of
work with the required cost is Rp.92.666.105,-

Keyword : Time Accelaration, Construction, Housing, overtime costs analysis, Analysis of


additional workers.