Professional Documents
Culture Documents
DAM NAME: UPPER SPRING CREEK T: 060N R: 0840W S: 9 COUNTY: ROUTT DATE OF INSPECTION: 5/26/2016
DAM ID: 580304 YRCompl: 1960 DAM HEIGHT(FT): 21.0 SPILLWAY WIDTH(FT): 12.0 PREVIOUS INSPECTION: 6/18/2014
CLASS: Significant hazard DAM LENGTH(FT): 170.0 SPILLWAY CAPACITY(CFS): 464.0 NORMAL STORAGE (AF): 4.0
DIV: 6 WD: 58 CRESTWIDTH(FT): 8.0 FREEBOARD (FT): 8.0 SURFACE AREA(AC): 1.0
EAP: 7/16/1997 CRESTELEV(FT): 6950.0 DRAINAGE AREA (AC.): 4943.0 OUTLET INSPECTED: 10/21/2015
CURRENT RESTRICTION: -- NONE --
OWNER: CITY OF STEAMBOAT SPRINGS OWNER REP.: JOHN OVERSTREET; PARKS, OPEN SPACE, & REC D
ADDRESS: P.O. BOX 775088 CONTACT NAME: CRAIG ROBINSON, OPEN SPACE SUPERVISOR
STEAMBOAT SPRINGS CO 80477- CONTACT PHONE: (970) 871-7034X
INSPECTION PARTY : Brad Setter Dana Miller
REPRESENTING : City of Steamboat Springs State Engineer's Office
FIELD
WATER LEVEL: BELOW DAM CREST 4.5 FT. Above Spillway 3.5 FT. GAGE ROD READING
CONDITIONS
OBSERVED GROUND MOISTURE CONDITION: DRY WET SNOWCOVER OTHER
DIRECTIONS: MARK AN X FOR CONDITIONS FOUND AND UNDERLINE WORDS THAT APPLY
UPSTREAM SLOPE
PROBLEMS NOTED (0)NONE (1)RIPRAP - MISSING, SPARSE, DISPLACED, WEATHERED (2) WAVE EROSION - WITH SCARPS
(3) CRACKS WITH DISPLACEMENT (4) SINKHOLE (5) APPEARS TOO STEEP (6) DEPRESSIONS OR BULGES (7) SLIDES
(8) CONCRETE FACING - HOLES, CRACKS, DISPLACED, UNDERMINED (9) OTHER Rodent activity
PREVIOUS REQUIRED ACTIONS:
- Increase vegetation control efforts on the upstream slope
In light of anticipated dam rehabilitation, recommendation is to not spend too much effort at this point on vegetation removal, but to maintain
the current condition and not allow vegetation to become more prominent.
(1) Some rocks, but no real protection provided; (2) significant scarping/erosion at and above the high water line; (5) too steep to walk across
the upper portion of the slope; (9) handful of smaller, active rodent burrows on the upper slope, one or two larger burrows above high water
line.
CONDITIONS OBSERVED: Good X Acceptable X Poor
CREST
PROBLEMS NOTED (10) NONE (11 RUTS OR PUDDLES (12) EROSION (13) CRACKS - WITH DISPLACEMENT (14) SINKHOLES
(15) NOT WIDE ENOUGH (16) LOW AREA (17) MISALIGNMENT (18) IMPROPER SURFACE DRAINAGE (19) OTHER
DOWNSTREAM SLOPE
PROBLEMS NOTED (20) NONE (21) LIVESTOCK DAMAGE (22) EROSION OR GULLIES (23) CRACKS - WITH DISPLACEMENT (24) SINKHOLE
(25) APPEARS TOO STEEP (26) DEPRESSIONS OR BULGES (27) SLIDE (28) SOFT AREAS (29) OTHER
Page 1 of 4
ENGINEER'S INSPECTION REPORT DATE. 5/26/2016
DAM NAME: UPPER SPRING CREEK DAM I.D.: 580304
SEEPAGE
PROBLEMS NOTED (30) NONE (31) SATURATED EMBANKMENT AREA (32) SEEPAGE EXITS ON EMBANKMENT
(33) SEEPAGE EXITS AT POINT SOURCE (34) SEEPAGE AREA AT TOE (35) FLOW ADJACENT TO OUTLET (36) SEEPAGE INCREASED / MUDDY
(33) (39) Point source in the right hillside just downstream of the right groin about 9 feet below the dam crest, currently flowing about 2-3
gpm, reported by Brad Setter to have been flowing about 4 times that amount previously after heavy rain and runoff with similar reservoir
level; likely has some groundwater connection; also sits below the diversion ditch around the right side of the reservoir and is likely fed by
this as well; recommended to continue to visually monitor, especially for any sediment in the flow, or deposits below where the flow is
exiting the hillside; saturated area below the right toe, source could be the hillside flow, and/or additional seepage exiting the toe.
(35) Flow coming from under the left outlet, valve is sealed tight, so flow is either coming from the upstream connection between the pipe
and the valve, or from somewhere else along the pipe, on the order of 2-3 gpm, clear.
CONDITIONS OBSERVED: Good X Acceptable X Poor
OUTLET
PROBLEMS NOTED (40) NONE (41) NO OUTLET FOUND (42) POOR OPERATING ACCESS (43) INOPERABLE
(44) UPSTREAM OR DOWNSTREAM STRUCTURE DETERIORATED (45) OUTLET OPERATED DURING INSPECTION YES NO
INTERIOR INSPECTED (120) NO (121)YES (46) CONDUIT DETERIORATED OR COLLAPSED (47) JOINTS DISPLACED (48) VALVE LEAKAGE
(44) Trash rack on right outlet is torn open, headwall on the left outlet is deteriorated; (120) both outlets inspected in 2015, actual conduits
are quite old, but appeared structurally sound; left pipe invert downstream of the valve has rotted away, leakage/seepage from under the
pipe; (48) minor seepage/leakage around the valve operators; (49) no trash rack on the left outlet pipe.
CONDITIONS OBSERVED: Good X Acceptable X Poor
SPILLWAY
PROBLEMS NOTED (50) NONE (51) NO EMERGENCY SPILLWAY FOUND (52) EROSION WITH BACKCUTTING (53) CRACK - WITH DISPLACEMENT
(54) APPEARS TO BE STRUCTURALLY INADEQUATE (55) APPEARS TOO SMALL (56) INADEQUATE FREEBOARD (57) FLOW OBSTRUCTED
(58) CONCRETE DETERIORATED / UNDERMINED (59) OTHER Damaged but braced concrete wall
(58) (59) Right wall broken and leaning in with voids behind; void behind the left wall as well; questionable capacity; channel obstructed by
large rocks that have fallen in from the left hillside.
CONDITIONS OBSERVED: Good Acceptable X Poor
MONITORING
EXISTING INSTRUMENTATION FOUND (110) NONE (111) GAGE ROD (112) PIEZOMETERS (113) SEEPAGE WEIRS / FLUMES
(114) SURVEY MONUMENTS (115) OTHER
MONITORING OF INSTRUMENTATION (116) NO (117) YES PERIODIC INSPECTIONS BY: (118) OWNER (119) ENGINEER
Monitor rodent activity in upstream face, and seepage from the toe and especially the right hillside.
CONDITIONS OBSERVED: Good X Acceptable Poor
(63) BRUSH ON UPSTREAM SLOPE, CREST, DOWNSTREAM SLOPE, TOE (64) TREES ON UPSTREAM SLOPE, CREST, DOWNSTREAM SLOPE, TOE
(65) RODENT ACTIVITY ON UPSTREAM SLOPE, CREST, DOWNSTREAM SLOPE, TOE (66) DETERIORATED CONCRETE - FACING, OUTLET SPILLWAY
(67) GATE AND OPERATING MECHANISM NEED MAINTENANCE (68) OTHER Upstream slope erosion
(65) Fill large rodent holes in the upstream slope; (66) (67) (68) need addressed as part of rehabilitation project.
Large trees recently cut from the crest and downstream slope (thank you!). Discussed additional vegetation control and waiting on any
significant efforts until we know the direction of the dam rehabilitation project.
CONDITIONS OBSERVED: X Good X Acceptable Poor
Page 2 of 4
ENGINEER'S INSPECTION REPORT DATE. 5/26/2016
DAM NAME: UPPER SPRING CREEK DAM I.D.: 580304
OVERALL CONDITIONS
ADDITIONAL PREVIOUS REQUIRED ACTIONS:
-Update the Emergency Action Plan using a provided template (W.W. Wheeler retained to assist with this and other activities)
Dam rehabilitation alternatives currently under consideration by City staff. Intent is to potentially budget for construction in 2017. It is
anticipated that all items from this inspection report will be addressed as part of that project.
Increased seepage noted this year from the left toe, under the outlet, and the right hillside; spillway capacity still significantly reduced by
large rocks in the channel downstream; and upstream slope erosion is bordering on severe in some areas; efforts towards an overall plan
for this structure are appreciated.
Based on this Safety Inspection and recent file review, the overall condition is determined to be:
(71) SATISFACTORY (72) CONDITIONALLY SATISFACTORY (73) UNSATISFACTORY
(81) LUBRICATE AND OPERATE OUTLET GATES THROUGH FULL CYCLE annually.
(83) INITIATE RODENT CONTROL PROGRAM AND PROPERLY BACKFILL EXISTING HOLES: Backfill larger holes in the slope to discourage continued activity and to
allow visual monitoring.
(84) GRADE CREST TO A UNIFORM ELEVATION WITH DRAINAGE TO THE UPSTREAM SLOPE:
(87) DEVELOP AND SUBMIT AN EMERGENCY ACTION PLAN: Plan to update/provide an EAP as part of the dam rehabilitation project.
(88) OTHER
(89) OTHER
ENGINEERING - EMPLOY AN ENGINEER EXPERIENCED IN DESIGN AND CONSTRUCTION OF DAMS TO: (Plans and Specifications must be approved by State Engineer prior to construction.
(90) PREPARE PLANS AND SPECIFICATIONS FOR REHABILITATION OF THE DAM:
(95) SET UP A MONITORING SYSTEM INCLUDING WORK SHEETS, REDUCED DATA AND GRAPHED RESULTS:
(98) OTHER:
(99) OTHER:
ACTIONS REQUIRED FOR CONDITIONAL FULL STORAGE OR CONTINUED STORAGE AT THE RESTRICTED LEVEL:
Continue with plans to rehabilitate the dam within the near future.
Owner's
Engineer's
Signature DATE:
Signature INSPECTED BY
OWNER/OWNER'S REPRESENTATIVE
Page 3 of 4
ENGINEER'S INSPECTION REPORT DATE. 5/26/2016
DAM NAME: UPPER SPRING CREEK DAM I.D.: 580304
CONDITIONS OBSERVED - APPLIES TO UPSTREAM SLOPE, CREST, DOWNSTREAM SLOPE, OUTLET, SPILLWAY
GOOD ACCEPTABLE POOR
In general, this part of the structure has a near new Although general cross-section is maintained, surfaces Conditions observed in this area appear to threaten the
appearance, and conditions observed in this area do not may be irregular, eroded, rutted, spalled, or otherwise not safety of the dam.
appear to threaten the safety of the dam. in new condition. Conditions in this area do not currently
appear to threaten the safety of the dam.
OVERALL CONDITIONS
SATISFACTORY CONDITIONALLY SATISFACTORY UNSATISFACTORY
The safety inspection indicates no conditions that appear The safety inspection indicates symptoms of structural The safety inspection indicates definite signs of structural
to threaten the safety of the dam, and the dam is distress (seepage, evidence of minor displacements, etc.), distress (excessive seepage, cracks, slides, sinkholes,
expected to perform satisfactorily under all design loading which, if conditions worsen, could lead to the failure of the severe deterioration, etc.), which could lead to the failure
conditions. Most of the required monitoring is being dam. Essential monitoring, inspection, and maintenance of the dam if the reservoir is used to full capacity. The
performed. must be performed as a requirement for continued full dam is judged unsafe for full storage of water.
storage in the reservoir.
NPH hazard - No loss of life or damage to improved property, or loss of downstream resource is expected in the event of failure
of the dam while the reservoir is at the high water line.
Page 4 of 4
Dam ID: 580304
Dam Name: Upper Spring Creek The terms “left” and “right” in the photograph
Inspection Date: May 26, 2016 descriptions refer to the downstream orientation
PHOTOGRAPHS
Photo #: 1
Description:
Downstream face
Photo #: 2
Description:
Upstream slope
Photo #: 3
Description:
Scarping in the upstream
face
Dam ID: 580304
Dam Name: Upper Spring Creek The terms “left” and “right” in the photograph
Inspection Date: May 26, 2016 descriptions refer to the downstream orientation
PHOTOGRAPHS
Photo #: 4
Description:
Spillway entrance
Photo #: 5
Description:
Crest
Photo #: 6
Description:
Downstream slope
Dam ID: 580304
Dam Name: Upper Spring Creek The terms “left” and “right” in the photograph
Inspection Date: May 26, 2016 descriptions refer to the downstream orientation
PHOTOGRAPHS
Photo #: 7
Description:
Marking the highest
point where seepage
exits the left toe of the
embankment, with
saturated material below
Photo #: 8
Description:
Seepage/leakage coming
from under the left
conduit downstream of
the valve
Photo #: 9
Description:
Left outlet headwall
Dam ID: 580304
Dam Name: Upper Spring Creek The terms “left” and “right” in the photograph
Inspection Date: May 26, 2016 descriptions refer to the downstream orientation
PHOTOGRAPHS
Photo #: 10
Description:
Right outlet operator nut
Photo #: 11
Description:
Seepage from the right
hillside just downstream
of the groin
Photo #: 12
Description:
Close up of point source
seepage in previous
photo