In this process, first the shearing machine operators takes the sheets
required according to the work ordered issued by the planning department. The
machine operator enters the program for further operations as per the schedule.
In this process if the operator found any damage of goods or repair of machinery
he informs to the shift supervisor and supervisors issues the maintenance note
for the department and inform the quality control department for quality check.
After quality checking the materials pass to the next stage.
The next stage of raw production is punching or flanging. In this process,
as per the work order. The necessary punching and bending has to be done by
the machine operators. If the machine operator finds any repairs of the
machinery, he will informs to the shift supervisors and the shift supervisors issues
the maintenance note. After the quality check in this stage the materials passes
to the next stage.
The next process of raw production is welding. In this process necessary
welding has done as per the work order issued by the planning department. After
the quality check, the semi finished goods pass to the next stage of production
process.
Degreasing and painting
Degreasing and painting process has two different lines.
Line1
Line1 is a manual powder coating, which has to pass through 5 stages of
degreasing process.
Pretreatment stage 1 (Degreasing 1)
In this stage raw water is heated up to 40c-50c and 5% of chemical protobond
40/87 is added to the raw water.
Pretreatment stage 2 (Degreasing 2)
In this stage the raw water is maintained at an ambient temperature.
Pretreatment stage 3 (Water rinse)
In this stage the dematerialized water is maintained at an Room temperature.