You are on page 1of 7

INTRODUCTION:

Estimation is the approximation of a result which is usable in business and


economics. Estimation in project planning can be particularly significant,
because plans for the distribution of labor and for purchases of raw materials
must be made, despite the inability to know every possible problem that may
come up. Furthermore, such plans must not underestimate the needs of the
project, which can result in delays while unmet needs are fulfilled, nor must they
greatly overestimate the needs of the project, or else the unneeded resources
may go to waste.
The purpose of this activity is that we will learn on how to estimate our building
plan in such time it will not be hard for us to make estimation when we will be in
the field. This will help me in my chosen field because this is one of the important
things like getting the contract when we are already professionals.

PROCEDURE:
Building plan is prepared for estimates especially the sections of important
points.
Necessary specifications are required for the steel bars and lateral ties
used in the columns.
Study the building plan specifically the foundation plan and floor framing
plans.
Get the height of the column and also for the depth of footing and
ground spacing.
Determine the number of steel reinforcing bars for each group and its
sizes.
Make an estimate of the main bars in each column and footing details
and slab using different methods in obtaining the estimates.

DATA GATHERED:
Estimating Square Concrete Column by Linear Method:
Computations for column 1 and 2 are the same since they have the same
dimension. So, the total number of columns in the ground floor is 16.

Total length of the column 1 and 2 in ground floor


No. of columns x height

16 columns x 3 meters = 48 meters


Refer to Table 1-4 in Estimate book by Max B. Fajardo Jr. page 23. Along
30 x 30 cm. column, using 40 kg cement class A concrete, multiply:
Cement
Sand
Gravel

:
:
:

48 x 0.810 = 38.88 bags say 39 bags


48 x 0.45 = 21.60 cu. m.
48 x 0.90 = 43.2 cu. m.

Total length of the column 1 and 2 in 2nd floor


No. of columns x height
16 columns x 3.15 = 50.40 meters
Refer to Table 1-4 in Estimate book by Max B. Fajardo Jr. page 23. Along
30 x 30 cm. column, using 40 kg cement class A concrete, multiply:
Cement
Sand
Gravel

:
:
:

50.40 x 0.810 = 40.824 say 41 bags


50.40 x 0.45 = 22.68 cu. m.
50.40 x 0.90 = 45.36 cu. m.

The total number of columns 1 and 2 in 3rd floor is 11

Total length of the column 1 and 2 in 3rd floor


14 columns x 2.70 meters = 37.80 meters
Refer to Table 1-4 in Estimate book by Max B. Fajardo Jr. page 23. Along
30 x 30 cm. column, using 40 kg cement class A concrete, multiply:
Cement
Sand
Gravel

:
:
:

37.80 x 0.810 = 30.618 say 31 bags


37.80 x 0.45 = 17.01 cu. m.
37.80 x 0.90 = 34.02 cu. m.

Estimating Foot Slab by Volume Method:


Since there is only one footing in the foundation plan;
Volume of 16 footing slab

V = 16 (0.25 x 1.20 x 1.20)


V = 5.76 cubic meters
Refer to Table 1-2 in Estimate book by Max B. Fajardo Jr. page 8. Using 40
kg. cement class A concrete, multiply:
Cement
Sand
Gravel

:
:
:

5.76 x 9.0 = 51.84 say 52 bags


5.76 x 0.5 = 2.88 cu. m.
5.76 x 1.0 = 5.76 cu. m.

Estimating Main bars and Lateral ties in Columns:


Main Bars for Column 1

At Ground floor

= (height of column + footing depth + ground floor spacing) x No. of main bars x
No. of column 1
= (3 + 1 + 0.20)(6)(4) = 100.80 m.

At 2nd floor

= height of column x no. of main bars x no. of column1


= 3.15 x 6 x 4 = 75.60 m.

At 3rd floor

= height of column x no. of main bars x no. of column1


= 2.70 x 6 x 2 = 32.40 m.
The combined column for C1: 100.80 + 75.60 + 32.40 = 208.80 m.
208.80/6.00 meters = 34.80 say 40 pieces
Main Bars for Column 2

At Ground floor

= (height of column + footing depth + ground floor spacing) x No. of main bars x
No. of column 2
= (3 + 1 + 0.20)(8)(12) = 403.20 m.

At 2nd floor

= height of column x no. of main bars x no. of column 2


= 3.15 x 8 x 12 = 302.40 m.

At 3rd floor

= height of column x no. of main bars x no. of column 2


= 2.70 x 8 x 12 = 259.20 m.
The combined column for C2: 403.20 + 302.40 + 259.20 = 964.80 m.
964.80/6.00 meters = 160.80 say 161 pieces
Lateral ties
Number of ties required in each typical column by using this formula:
Length of Column
Spacing of ties

= Number of ties per column

At Ground floor

(C-1 with 10 mm dia.): 3.00 m. ht. = 20 ties


0.15 m
No. of Lateral ties: 20 + 1 = 21 pieces
Total ties: 21 pieces x 4 columns = 84 pieces
(C-2 with 12 mm dia.): 3.00 m. ht. = 20 ties
0.15 m
No. of Lateral ties: 20 + 1 = 21 pieces
Total ties: 21 pieces x 12 columns = 252 pieces

At Second floor

(C-1 with 10 mm dia.): 3.15 m. ht. = 21 ties


0.15 m
No. of Lateral ties: 21 + 1 =22 pieces
Total ties: 22 pieces x 4 columns = 88 pieces
(C-2 with 12 mm dia.): 3.15 m. ht. = 21 ties
0.15 m

No. of Lateral ties: 21 + 1 = 22 pieces


Total ties: 22 pieces x 12 columns = 264 pieces

At Third floor
(C-1 with 10 mm dia.): 2.70 m. ht. = 18 ties

0.15 m
No. of Lateral ties: 18 + 1 = 19 pieces
Total ties: 19 pieces x 2 columns = 38 pieces
(C-2 with 12 mm dia.): 2.70 m. ht. = 18 ties
0.15 m
No. of Lateral ties: 18 + 1 = 19 pieces
Total ties: 19 pieces x 12 columns = 228 pieces
The Length of one lateral tie by getting the perimeter multiplied by two is:
L = 2 (a + b) = 2 (0.3 + 0.3) = 1.20 meters
The commercial length of steel bars that we chose is 6.00 meters. Therefore,
6.00 meters/1.20 meters = 5.0 ; exactly 5 pieces could be derived from a 6.0
meters long steel bar.

Total Number of ties in Column 1 and 2:


Column 1 84 + 88 + 38 = 210 ties with 10 mm diameter
Column 2 252 + 264 + 228 = 744 ties with 12 mm diameter

ORDER:

(C-1 with 10 mm) 210/5.0 = 42 pieces


(C-2 with 12 mm) 744/5.0 = 148.8 say 149 pieces

DISCUSSION, ANALYSIS AND INTERPRETATION OF RESULTS:


First, I studied all the relevant project drawings like elevations, framing plan,
footing and column details. Different methods were used in obtaining the values
needed for the computation. In getting the estimates for the concrete I used
the volume method which is the area multiplied by its thickness. The result
obtained is multiplied by the number of columns so that I can get the estimate
for cement, sand and gravel. For the reinforcement, the number of columns to
be erected is studied. The length of columns and sizes of vertical bars are

classified. The assumed length of commercial bars to be ordered is 6 meters.


And for the concrete, the class A with 40 kg will be used.

CONCLUSION:
Therefore, I learned that estimation is very significant in projects like making a
building plan because it is a method of calculating various quantities to be
incurred on a particular work or project. In estimating the steel bar
reinforcement the first thing that must be considered is the length and quantity
of a particular reinforcement.

REFLECTION:
Its importance is that it decides whether the proposed plan matches the funds
available or not. In case, the available funds doesnt suit the estimated cost of
work we can reduce it. It will also give an idea of the time required for the
completion of work.

CAPITOL UNIVERSITY
COLLEGE OF ENGINEERING
Cagayan de Oro City
BUILDING DESIGN
Activity No. 2

ESTIMATING BILL OF MATERIALS


TITLE
EVALUATION RATING:
DATE PERFORMED :
July 4, 2012
DATE DUE

I. Hand-on Performance (25 pts.)


Criteria

:
Manifestations of skills in manipulating
equipments, apparatuses,
materials etc. (5pts.)
Observance of class hours (5 pts.)

July 9, 2012
GROUP NO. :

SUBMITTED BY

Following procedures correctly (5 pts.)


Working closely and sharing ideas with
group-mates (5 pts.)
Observing laboratory rules and
maintaining order in laboratory
premises (5 pts.)
II. Laboratory Report (25 pts.)

Bethel Princess T. Flores

STUDENT

SUBMITTED TO

Engr. Genevieve A. Gabule


INSTRUCTOR

Correctness of data and


computations (5 pts.)
Analysis of Results (5 pts.)
Appropriateness of conclusions (5
pts.)
Presentation of figures and report
write-ups (5 pts.)
Promptness (5 pts.)

Total Score (50 pts.)

REMARKS :
1st SEMESTER SCHOOL YEAR 2012 - 2013

Actual
Score

You might also like