Professional Documents
Culture Documents
Application
Application
Triple-country protection
OMICRONs CPC 100 + CP CU1 measures complex
three-terminal HV lines for protection settings
Hoheneck
123.8 km
(77.4 mi)
112.5 km
(70.3 mi)
132.4 km
(82.8 mi)
Herbertingen
Tiengen
CH
Measurement setup at the 220 kV three-terminal
line in Southern Germany, connecting the Hoheneck,
Tiengen and Brs substations (Depicted with the section
Tiengen-Herbertingen off grid and without grounding).
Brs
AT
Application
35
overhead lines.
line has remained in operation throughout the measurement process, therefore the induced voltage in the
in typical cases.
on a three-terminal line is typically supplied by multiple power sources. This effect also causes additional
36
Application
500 V
CPC 100
CP CU1
500 V
CPC 100
CP CU1
Conventional
measurement
CP GB1
CP GB1
1 000 V
1000 V
CPC 100
con mayor
CPC 100
CP CU1
CP CU1
proteccin contra
CP GB1
with sobretensiones
increased
surge protection
Adjusted measurement
Series connection of the outputs from two CP CU1 systems for induced voltages of up to 1 000 V.
Time-saving measurement
ditional fault current, in-feed via the third terminal, has on the
protection scheme.
Due to the length of the power lines and the resulting distances
was made to place a team with one CPC 100 and two CP CU1s at
each of these points. This allowed the duration of the measurement to be significantly reduced because the travel time did not
be eliminated.
scheduled maintenance.
Application
37
Constant use
The OMICRON testing equipment has proven its value
lines and the ground, and also metallic conductors such as rails or
tinue to play
role at Amprion in future.
mkan
5,21important
1
)im 8,28(
negnit rebreH
)im 3,07(
optimum protection.
TA
HC
srB
Magazine | Volume 3 Issue 2 2012