Professional Documents
Culture Documents
Keywords:
Ethiopia.
construction
delay,
delay
causes,
BACKGROUND
A construction project is commonly acknowledged as
successful, when it is completed on schedule, within the
agreed budget, conforming to quality specifications in the
safest manner and to stakeholders satisfaction.
Functionality, profitability to contractors, absence of
claims and court proceeding and fitness for purpose for
occupiers have also been used as measures of project
success (Takim & Akintoye, 2002).
Public construction projects in Ethiopia are parts of the
countrys development initiative. It shares considerable
amount of the countrys scarce financial resources. In
Ethiopia, the construction industry is the highest recipient
of government budget in terms of government
development program. Consequently, public construction
projects consume an average annual rate of nearly 60%
of the governments capital budget (MoWUD ,2006).
Project success is the ultimate goal of every construction
project. To determine whether the project is completed as
expected, final project performance must be evaluated.
Completion time is one of the performance criteria of
construction projects, along with cost, quality, safety, and
no-dispute etc.
The government of Ethiopia and its
development partners continue to allocate huge financial
resources to finance infrastructure development, but still
the projects face considerable low schedule performance.
Chan & Kumaraswamy (1995) defines construction delay
as late accomplishment of planned work.
A number of studies have been conducted to examine
causes of delay in public construction projects in
developing countries. However, in Ethiopia there is no
thorough and adequate study on causes of delay in public
construction projects.
Fung et al. (2006) opined low speed in construction
causes delay. Delay in decision making by project
RESEARCH METHOD
After critically reviewing the existing literature, related to
causes of construction delay (CCD) in construction
projects, 88 CCD factors were identified and grouped in to
eight broad categories which are related to: client,
consultant/supervisor,
contractor,
designer,
labour,
material, equipment, and external. The questionnaire was
designed to assess the opinion of clients, design
engineers, consultants, and contractors on the relative
importance of causes of delay in Ethiopian public building
construction. The identified 88 causes of delay factors
were adopted in the design of questionnaire for the study.
Responses were collected from respondents and
importance index were used to analyze the data
gathered.
Characteristics of respondents.
The scope of this research includes public building
construction in Ethiopia and the population of the study
consists of all owners, consultants, and contractors
participating in execution of public building construction
projects. A total of 110 questionnaires were distributed to
respondents and 56 responses were collected. Out of
these responses only 51 were valid. This is because 5
respondents were not properly filled the questionnaire.
The response rate of respondents having different
experience is shown in the Chart 1. Maximum responses
have come from respondents with work experience of 510 years (35.29%) and 10 15 years (35.29%). The
average experience of the respondents was about 12
years.
Chart 1: Working experience of the respondents.
i=1
a n
a n
is
is
)
( 5
N
i=1
100
F .I S .I
100
RESULTS
Ranking of delay factors.
As it is shown in Tabe-1 the top 10 causes of delay from
clients, consultants/supervisors, and contractors' point of
view were identified and ranked according to Importance
Index (I.I). Among the listed top ten causes of delay, the
most frequent and critical delay factors are difficulties in
financing project by contractors, escalation of material
prices, ineffective project planning and scheduling, delay
in progress payment for completed works, and lack of
skilled professional in contractor organization.
Table 1: Top ten ranking of construction delay factors.
Consulta Contract
nts
ors
Combine
d
Ran
k
DF32
Difficulties in
financing
project by
contractor
Contract 74.7 2
or
4
75.0 1
9
65.3 4
5
68.7 1
5
DF67
Escalation of
Material 78.8 1
material prices
7
62.9 4
63.0 7
9
65.5 2
7
DF30
Ineffective
project
planning and
scheduling
Contract 71.7 6
or
5
70.4 2
60.1 12
9
64.5 3
3
DF14
Delay in
progress
payment for
completed
works
Clients
62.7 5
77.0 1
4
63.0 4
5
DF29
Lack of skilled
professional in
contractor
organization
Contract 72.7 5
or
2
62.7 6
2
60.0 13
5
62.5 5
7
DF55
Fluctuating
labours
availability
season to
season
/Seasonal
labours
availability
Labour
56.7 8
1
74.1 2
2
60.5 6
9
DF68
Late delivery
of materials
Material 56.6 23
4
54.7 10
6
68.5 3
2
58.4 7
6
DF58
Low
productivity of
labour
Labour
55.7 27
8
65.0 3
3
52.1 25
5
54.9 8
3
DF63
Unqualified /
inadequate
experienced
labour
Labour
65.9 9
54
51.2 26
1
46.8 9
9
DF49
Insufficient
Designer 71.7 6
data collection s
5
and survey
before design
50.5 27
6
46.8 10
5
44.8 50
4
57.4 19
9
11
70.4 2
Frequency of
occurrence
Degree of Importanc
severity
e Index
F.I.
Rank
S.I.
Ran
k
I.I.
Ran
k
Contractors related
factors
65.97
69.73
46.0
1
65.15
70.10
45.6
7
65.23
66.84
43.6
0
63.89
65.52
41.8
6
66.16
41.5
9
Designers related
factors
62.44
66.58
41.5
7
Equipment related
factors
57.45
63.33
36.3
9
52.13
54.81
28.5
7
Ran
k
Current
study
(2015),
Ethiopia
Mohammed
and Isah
(2012),
Nigeria.
Difficulties in
financing
project by
contractor
Design
changes
Finance and
payments of
completed work
by owner
Improper
planning
Escalation of
material
prices
Delays in
payment to
contractors,
Variation
orders/changes of
scope by owner
during
construction
Lack of
effective
communicatio
n
Ineffective
project
planning and
scheduling
Information
delays
Low productivity
level of labours
Design errors
Delay in
progress
payment for
completed
works
Funding
problems
Effects of
subsurface
conditions (e.g.,
soil, high water
table, etc.)
Shortage of
supply like
steel,
concrete
Ineffective
planning and
scheduling of
project
Slow decision
making
Fluctuating
labours
availability
season to
season
/Seasonal
labours
availability
Compensation Difficulties in
issues
financing project
by contractor
Late delivery
and shortage
of materials
Disagreement
on the
valuation of
work done
Type of project
Shortage of
bidding and award materials
(negotiation,
lowest bidder)
Low
productivity
of labour
Conflicts
among the
involved
Shortage of
construction
materials in
Financial
issues
Cash-flow
problems
during
parties
market
Project
schedule
changes
Late in revising
Increase in
and approving
quantities
design documents
by owner
Unqualified /
inadequate
experienced
labour
10
Insufficient
Supply /
data
procurement
collection and problems
survey before
design
Unqualified
workforce
construction
Mismanageme
nt by the
contractor
(financial,
supplier
support, subcontractor)
Lack
of
skilled
organization
professional
in
contractor
to
CONCLUSIONS
This study is focused on delay of construction of public
building projects in Ethiopia. The study sought the views
of clients, consultants, and contractors on the relative
importance of the factors that cause delays in building
construction projects. Moreover, it was observed that all
the three groups of respondents generally agreed that out
of a total of 88 factors the top ten influencing factors are:
contractors financial difficulty, escalation of material
prices, ineffective project planning and scheduling, delay
in progress payment for completed works, lack of skilled
professional in contractor organization, fluctuating labours
availability, late delivery of materials, low productivity of
labour, unqualified / inadequate experienced labour,
insufficient data collection and survey before design. The
88 factors were categorized into eight major groups and
were ranked accordingly. The result shows that clients,
consultants, and contractors all agreed that the contractor
group of delay factors was the most influential factor.
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul A. (2008).
Delays in Construction Projects: The Case of Jordan.
International Journal of Project Management, 26:665674.
Tabish, S. Z. S., & Jha, K. N. (2012). Success Traits for a
Construction
Project. Journal of Construction
Engineering and Management, 138 (10): 1131-1138.
Takim, R., & Akintoye, A. (2002). Performance Indicators
for Successful Construction Project Performance. 18th
Annual ARCOM Conference, 2: 545-555.
Thornton, G. (2007). Surety Credit Survey for
Construction Contractors:
The Bond Producers
Perspective.
[Online].
Available
at
www.grantthornton.com [Retrieved September 5,
2015]
Wong, K., and Vimonsatit, V. (2012). A study of the
Factors Affecting Construction Time in Western
Australia. Scientific Research and Essays, 7(40):
3390-3398.
Yaw, F., Oluwoye, J., & Crawford, L. (2003). Causes of
Delay and Cost Overruns in Construction of
Groundwater Projects in a Developing Countries:
Ghana as a Case Study. International Journal of
Project Management, 21: 321326.
Zagorsky, J.L. (2007). Do You Have To Be Smart To Be
Rich? The Impact of IQ on Wealth, Income and
Financial Distress. Intelligence 35(5): 489-501.