You are on page 1of 10

ALL INTERVIEW

1 Cement-concrete ratio:

1:4

Calculation for the cutting length of


10,12,16,20 and so on iron bars for 45
15 digree and 90 digree bents.

for example if any steel take 1.0 meter cutting


length
density= weight / volume
density of steel is 7850kg/m3
volume of steel = areaXlength=3.14xD2/4*1.0
weight of steel for 1m is= density X volume
=
3.14D2x1000*7850/1000*1000*1000
=D2/162 (square of D/162)
where D is the dia of bar in mm
for 45degrres =cutting length-1 * dia of bar* no of
bends
for 90 degrees= cutting length-2 * dia of bar*no of
bends

The answer posted should some reference from


any of IS code.
It has to be justified.
As i refered code IS 2502 BS 4466 the deductions
followed are
0 for 45 bends
d<= 16 dia for 90 bends
2d>=20 dia for 90 bends
there is a formula for finding out the extra length
required for one bent. i.e. 0.42d where d is the
effective depth of the member.
To calculate the bending Deduction formula given
Below.
Bend Deduction = 1.25*Dia of Steel*No of Bend
15 What is the unit weight of concrete?.
Rcc -25kn/m or 2500kg/m
Pcc- 24 kn/m or 2400kg/m
2 how to calculate the weight of 6mm dia rod
Weight of reinforcement per meter

= area of bar*unit weight of steel


=22/7*1/4*(D)^2*(7850)/10^6
=0.0061678*(D)^2
= (1/0.0061678)*D^2
= D^2/162.13
(D*D)/162

Roughly calculated by the formula


Now,
weight (kg) = length * (d*d/162)
= metre * (kg/m)
= kg
Area of steel
Length of steel
volume of steel = areaXlength

m2
m
m3

density= weight / volume


Density of steel is

kg/m3

weight of steel for 1m is= density X volume

kg

0.0028285714
1
0.0028285714
=input
7850
22.2042857143

what"s the formula find the cement


consumption for brick work
23 thick wall 1 m3?
Brick work volume per cum with motor
Size: 0.2 X 0.1 X 0.1
Brick work without motor
Size: 0.19 X 0.09 X 0.09
Mortor volume per cum

Cum
Per Cum
Cum
Cum

0.002
500
0.7695
0.2305

4 Unit weight of fine concrete

Kg/m3

2400

5 What is the density of Cement

Kg/m3

1440

6 Ratio of Grades M10,M15,M20,M25,M30,M35,M40.


M10-1:3:6
M15-1:2:4
M20-1:1.5:3
that rattio is nominal mix basis.above M20,than
mix design
is preford.basically M25 consider is 1:1:2
after M25 we have to control the strength
acoording to
garde, so it will be disigned

4 Binding wire is required for one tone reinforcement


It should be 5 Kg to 6 Kg for one tone
reinforcement.
approximate 8kg, it is based upon thumb
rule.
Upto 16mm dia = 6.90/7.20kgs
20mm to 32mm = 8.00/8.30kgs

CALCULATION OF LABOUR COST FOR


6 CONCRETE WORK PER CUBIC METER
For M20 Grade conc.
Head mason
Mason
Labour
Total Amount
Add 1% for watering

Rate
200
190
90

This is the only Labour cost of RCC not Machinary


and
pouring
7 estimation of the # of bags of cement, sand & gravel.. if only given the volume of the project..
Volume of concrete
Cum
=input
Loose volume of 1 cum concret.
1.57
mix proportion is 1:1.5:3
5.5
Cement
1
Fine Aggregate
1.5
Coarse Aggregate
3
5.5
Cement : Fine Aggregate : Coarse Aggregate
a. Cement
Quantity of the
cement required = X
we know that one cubic metre =
1 cubic metre
Cement content for X Cubic meter
b. Fine Aggregate
Add 5% of voids
c. Coarse Aggregate
Add 1% of voids

KG
Bags

0
1450
29
0
0
0.05
0

13 Caculation of cement bag in RCC & PCC in one cubic meter

simple method
calculation for m20 for /1 m3
1.51 is Bulk Density and Specific Gravity cement
powder.
1.54*1/1+ 1.5 + 3(cement+sand+agg.) =0.2745,
0.2745/0.035 =7.84 say 8 bags.
same calculation try for m10,15,25,30
calculation for m20 for /1 m3
Proportion, 1:1.5:3 (Cement: Sand: Aggregate)
Cement
Sand

1
1.5

Aggregate
Total
Bulk Density and Specific Gravity cement powder.

9 what is lap length? why it is required

In the construction of RC buildings, due to the


limitations in available length of bars and due to
constraints in construction, there are numerous
occasions when column bars have to be joined. A
simple way of achieving this is by overlapping the
two bars over at least a minimum specified
length, called lap length. The lap length depends
on types of reinforcement and concrete. For
ordinary situations, it is about 50 times bar
diameter. Further, IS:13920-1993 prescribes that
the lap length be provided ONLY in the middle half
of column and not near its top or bottom

Re: What is standard sand? What is coarse


& fine sand? What is foundation? What is
the seze of hooks in various Reinforced
section? What is the formula of providing
clear cover? What is the basic diff. between
working stress & Limit state design? What is
&cbc and fck? what are the primary &
10 secondary test of water purification?
Standard sand means which obtained from
nature, like river sand. According to IS code sand
which passes lower than 4.75mm
and above 600milimicron and fine sand which
passes 600 mili micro and retained 75 mili micron.
Foundation is the part of structure which transfer
load of the structure to the base of soil on which it
rests.
hooks- semicircular secn.-16d
90' bend- 8d
45' bend- 12d
Clear cover- column-40mm
BEAM - 25MM
SLAB - 15MM
FOOTING - 50MM
lIMIT STATE DESIGN- in this method design based
on limit state concept, the structure shall be
designed to with stand safety of all loads liable on
it throughout its life.
it also satisfy the serviciablity recquirments such
as limitation on deflection and cracking. the
acceptable limit for the safety and serviciable
recquirment before failure
occurs is called limit state.
working stress- when limit state design are not
acceptable working stress method is used. in this
method is based on
elastic theory.
cbc- compressive strength
fck- charterstics strength

11 i have a bar of 36 dia in column, what is the lap length?


as per indiaqn standards the bars above 32mm
dia bars are to be welded not lapped. its a
twisting questions in interviews

14 difference between MS rod & TMT rod?


MS means Mild steel. that means plain rod .
mainly created by CST ( cold tiwsted)
TMT means Thermo mechanically treated. this
method used by now a days.

3
5.5
1.51

MS(Mild Steel) bars have low tensile strength


bars, and are generally preferred for lighter loads,
whereas TMT (Thermo Mechanically Treated ) bars
have high tensile strength and are preferred for
important structures with heavy loads
Diesel deduction
generate units from generator
The fuel consume during the generate x units is
Then average
The cost of diesel 160xrate
The cost of per unit generated

Cum
Lit
Cum/ Liter

=input
=input
#DIV/0!

Total amount/Generated units.

' =22/7*1/4*(D)^2

(0.2*.1*.1)
(1/(0.2*.1*.1))=500
500*(.19*.09*.09)=0.76
=1-.76 = 0.24 mortor volume

qty
0.5
0.3
2.5

me of the project..

=1+1.5+3

a*(1.52/(1+1.5+3))m^3 = x m^3

1.5*X
3*X

Amount
100
57
225
382

MAINTENANCE EVOLUTION
Planned hours for Leyland tipper no.1
Actual worked hours of Leyland tipper no.1
Equipment Utilisation

=
=
=

Calculation
200

184.9
Total working time
Total Shift Hours of working

X 100

92.45

=(184.9/200)*100

You might also like