Professional Documents
Culture Documents
06 October 2015
Effective date:
06 October 2015
Subject:
Formation
This technical note is issued by the Asset Standards Authority as a notification to remove from
use the RailCorp standard ESC 410 Earthworks and Formation, Version 2.0.
ESC 410 is a legacy document and shall be used for reference purposes only. ASA standard
T HR CI 12110 ST Earthworks and Formation, Version 1.0 supersedes this document.
Authorisation:
Technical content
prepared by
Checked and
approved by
Interdisciplinary
coordination
checked by
Authorised for
release
Name
Sarath Fernando
Richard Hitch
John Paff
Graham Bradshaw
Position
Principal Engineer
Geotech
Director Network
Standards and
Services
Signature
Date
Page 1 of 1
Superseded by T HR CI 12110 ST
11 June 2015
Effective date:
11 June 2015
Subject:
This technical note supersedes TN 009: 2013 and is issued by the Asset Standards Authority as
a temporary update to the standards listed in Table 1.
Table 1 RailCorp engineering standards
Reference No
Title
Version
Issue date
ESC 410
2.0
01/07/2010
ESC 540
2.2
01/07/2010
TMC 411
Earthworks
2.0
01/07/2010
The SMS document reference on CTN 13/04 has changed to SMS-06-GD-3066 Guide to
managing construction hazards.
Documents listed in Table 1 are presented as legacy RailCorp documents and shall be read in
conjunction with this technical note and interpreted according to the interpretation guides listed in
Table 2.
Table 2 Interpretation guides
Reference no
Title
Version
Issue date
TS 10762
1.0
28/06/2013
TS 10760
1.0
17/06/2013
TS 10760 - SMS
1.0
17/06/2013
Page 1 of 4
Superseded by T HR CI 12110 ST
1.
Page 2 of 4
Superseded by T HR CI 12110 ST
Figure 3 - Vertical toe cut with high risk for slip failure
Page 3 of 4
Superseded by T HR CI 12110 ST
Figure 4 - Cable trench left open at top of soil/soft rock cutting allowed ponding water to enter slope
leading to failure (see Figure 5)
Figure 5 - Failure due to cable trench left open at top of soil/soft rock cutting
Authorisation:
Technical content
prepared by
Checked and
approved by
Interdisciplinary
coordination
checked by
Authorised for
release
Name
Sarath Fernando
Richard Hitch
John Paff
Graham Bradshaw
Position
Principal Engineer
Geotech
Principal Manager
Network Standards
and Services
Signature
Page 4 of 4
ESC 410
EARTHWORKS AND FORMATION
Version 2.0
Issued July 2010
Owner:
Approved by:
John Stapleton
A/Principal Engineer
Technology & Standards
Authorised by:
Jee Choudhury
Principal Engineer
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document users sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes
any liability which arises in any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced, altered,
stored or transmitted by any person without the prior consent of RailCorp
Page 1 of 16
Engineering Standard
Superseded by T HR CI 12110 ST
Engineering Standard
Geotechnical
Superseded by T HR CI 12110 ST
ESC 410
Document control
Revision
Date of Approval
2.0
July, 2010
1.2
December, 2009
1.1
October, 2007
1.0
September, 2006
Summary of change
Changes detailed in Summary table below
Change of format for front page, change history and table of
contents; Minor editing and formatting throughout
New section 11 on ground anchors to be consistent with ESC 350.
First issue as a RailCorp document. Replaces C 1100, TS 3421, TS
3422
Summary of change
Version control updated
Old section 4 Width of property deleted; new Section 4 with additional requirements for
design, assessment and documentation including design flood level and requirements for
multiple tracks
New Section on design flood level
8
9
More detailed requirements for embankments including for sampling & testing; drainage
blanket; embankment profile and rock facing of embankments
Additional design requirements for earthworks near structures
10
11
Minor changes to design requirements for capping; update reference to TMC 304 to SPC 301
16
Appendix 1
Appendix 2
Rail Corporation
Issued July 2010
Title changed for clarity; note added re minimum dimension from edge of cutting face to top
drain
Title changed for clarity; note added re minimum dimension from edge of cutting face to top
drain
Page 2 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
Contents
1
References ................................................................................................................................................ 4
2.1
2.2
2.3
Definitions ................................................................................................................................................. 4
Cuttings ..................................................................................................................................................... 7
5.1
5.2
General .......................................................................................................................................... 6
Design investigation ...................................................................................................................... 6
Design flood level .......................................................................................................................... 6
Formation....................................................................................................................................... 7
Documentation .............................................................................................................................. 7
Excavation ..................................................................................................................................... 7
Batter Slopes ................................................................................................................................. 8
Embankments ........................................................................................................................................... 8
6.1
6.2
6.3
6.4
6.5
6.6
Embankment Material.................................................................................................................... 8
Compaction Standards .................................................................................................................. 9
Sampling and Testing.................................................................................................................... 9
Drainage Blanket ........................................................................................................................... 9
Embankment Profile ...................................................................................................................... 9
Rock Facing of Embankments....................................................................................................... 9
Capping Layer........................................................................................................................................... 9
General ........................................................................................................................................ 10
Construction................................................................................................................................. 10
Excavation ................................................................................................................................... 11
Vertical Tolerances...................................................................................................................... 11
Horizontal Tolerances.................................................................................................................. 12
10
Drainage .................................................................................................................................................. 12
11
12
13
Walkways ................................................................................................................................................ 13
14
Rehabilitation of Formation................................................................................................................... 13
Rail Corporation
Issued July 2010
Page 3 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
References
2.1
2.2
2.3
AS 1289
AS 4678
RailCorp Documents
ESC 215
Transit Space
ESC 350
ESC 420
Track Drainage
SPC 301
Structures Construction
SPC 411
Earthworks Materials
Other References
Nil
Definitions
Borrow Pit:
Capping Layer:
CBR:
Cohesionless Soil:
Cohesive Soil:
Collapsible Soil:
Compaction:
Contaminated Material:
Cutting:
An earth or rock excavation within the works site that is made below an
existing surface to create the railway formation.
Dispersive soil:
Soil that has the ability to pass rapidly into suspension in the presence
of water
Earthworks:
Rail Corporation
Issued July 2010
Page 4 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
Earthworks Level:
Embankment:
Expansive Soil:
Soil that will suffer a high volume change when in contact with
water. Any increase or decrease in the moisture content of such soil,
would cause swelling or shrinkage, respectively. This type of soil is also
called Reactive Soil and Swelling Soil.
Formation:
Formation Level:
Formation Width:
Foundation Treatment:
General Fill:
Geosynthetics:
Geotechnical Engineer:
Rail Level:
Relative Compaction:
For cohesive soils, the dry density ratio determined in accordance with
AS 1289.5.4.1, or the Hilf density ratio determined in accordance with
AS 1289.5.7.1.
For cohesionless soils, the density index determined in accordance
with AS 1289.5.6.1.
Relative Density:
Right of Way:
Rockfill:
Shoulder Distance:
Soluble Soil:
Stockpile:
Structural Zone:
The upper zone of the embankment. Its thickness varies from 500 mm
to 1000 mm, depending on the CBR of the general fill.
Tolerance:
Top Soil:
Unsuitable Material:
The material that occurs in the borrow site or below the foundation level
of embankment and is not considered as suitable due to its adverse
Rail Corporation
Issued July 2010
Page 5 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
Design Requirements
4.1
General
Earthworks and formation design includes:
cuttings
embankments
capping layer.
New lines shall be constructed on a corridor wide enough to accommodate earthworks and
formation designed and constructed in accordance with the requirements in this document. The
corridor shall also accommodate associated drainage and access roads as detailed in relevant
RailCorp engineering standards.
4.2
Design investigation
Before any earthwork activity is undertaken, necessary assessment and investigation shall be
carried out to determine the nature, elements and extent of the work.
In the preliminary assessment, planning and design of earthworks, the following items shall be
considered:
4.3
Site investigation
Adjoining property
Preservation items
Rehabilitation
Drainage
Sloping ground
Slope stability
Retaining walls
Surcharging of slopes
Calculation of quantities
Construction vibrations
Contamination
Rail Corporation
Issued July 2010
Page 6 of 16
Version 2.0
Superseded by T HR CI 12110 ST
4.4
ESC 410
Formation
Formation is the earthworks structure including all foundation, structural treatment and capping
layer on which ballast is laid.
The formation for single track mainlines and single track sidings shall comply with the appropriate
dimensions shown in Appendix 1.
The formation for double track mainlines and double track sidings shall comply with the appropriate
dimensions shown in Appendix 2.
The formation for multiple track mainlines and multiple track sidings shall comply with the
appropriate dimensions shown in Appendix 2, subject to the requirement that the water from one
track shall not cross another track to get away. For example, if there are three tracks, there shall be
at least one subsurface centre drain.
Shoulder distances shall comply with Appendix 3.
Track centres shall be in accordance with ESC 215 Transit Space.
Where reduced shoulder distances exist due to physical constraints, an assessment is to be made
of the need for safety refuges, handhold devices and limited clearance signs. The requirements are
specified in ESC 350 Retaining Walls and Platforms.
4.5
Documentation
All activities of earthworks shall be documented. Appropriate documents should be prepared in the
following stages:
Construction.
Cuttings
Design of cuttings shall provide for excavation of material within the limits of the batters including
benching and terracing of cut batters; cleaning of batter surfaces; treatment of cutting floors; and
foundation treatment below the embankment. Cuttings in both soil and rock should provide a
stable, safe foundation for the structure.
Benching in cuttings will be provided in both soil and rock as necessary.
5.1
Excavation
Excavation shall be carried out to the lines, levels, dimensions and slopes shown on the Drawings.
The excavated faces shall be neatly trimmed and the top edges of the cuttings neatly rounded.
Under cutting of the slopes shall not be permitted under any circumstances.
Excavation shall be carried out in such a manner as to prevent erosion or slip; working faces shall
be limited to safe height and slopes, and surfaces shall be drained to avoid ponding and erosion.
Batters will generally require fattening at the ends of cuttings owing to the presence of less stable
material. In all cuttings, undulations in the general plane of the batter shall not be permitted.
Overhanging and loose or unstable materials likely to slip shall be cut back, removed or stabilised.
Rock cuttings and exposed surfaces shall be excavated so as to obtain smooth, uniformly trimmed
surface.
Rail Corporation
Issued July 2010
Page 7 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
Excavation at the base of cutting shall be finished at a level to suit the capping thickness, with
cross falls and cess drains provided.
Prior to placing formation materials and carrying any designed foundation treatment, the cutting
floor shall be tested and inspected by the Geotechnical Engineer.
5.2
Batter Slopes
Batter slopes in soil and rock cuttings in excess of 3 m high and closer than 6 m from the track
centreline, shall be determined on the advice of the Geotechnical Engineer.
Unless shown otherwise on the Drawings or as advised above, cutting slopes should be in
accordance with the following guidelines:
Material
Slope
Horizontal
Vertical
Sand
2 2.5
1.0
2.0
1.0
1.75
1.0
1.5
1.0
5*
1.0
1.0
6*
Ordinary rock
1.0
1.0
7*
0.25
1.0
Embankments
6.1
Embankment Material
Embankment materials shall comply with Engineering Specification SPC 411 Earthworks Materials.
Embankments are earthfill or rockfill structures above an existing and/or excavated surface to
create the rail track formation.
The embankment shall consist of two zones of embankment material:
General Fill
Structural Zone.
Page 8 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
Material for use in the structural zone shall comply with SPC 411.
6.2
Compaction Standards
To achieve a stable and durable embankment, the material shall be prepared and compacted as
specified below.
The Compaction standards shall be as follows:
Compaction A:
Compaction B:
6.3
General Fill:
Compaction B
Structural Zone:
Compaction A
6.4
Drainage Blanket
Where specified or directed by the Geotechnical Engineer, a free draining filter layer consisting of
hard durable crushed rock, river gravel or slag which is called drainage blanket, shall be provided
under the embankment.
6.5
Embankment Profile
Embankment batter slopes up to a height of 3 meters, shall be 2:1 (horizontal: vertical). For higher
embankments, the batter slopes shall be determined by stability analysis taking into account of
materials properties, height, foundation conditions, static and dynamic loading, and potential
seepage forces. Advice shall be sought from the Geotechnical Engineer if there is any doubt
concerning the embankment stability.
The completed batter must be free of rills running down the face of batter. Any loose material on
the batter shall be promptly removed as the work progresses.
6.6
Capping Layer
Capping is a compacted layer from selected materials that provides seal to the earthwork
underneath. The capping layer shall be constructed in a single layer having a compacted thickness
of minimum 150 millimetres.
Rail Corporation
Issued July 2010
Page 9 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
The material shall be spread in uniform horizontal layer so as to achieve the specified compacted
thickness for the full width of the capping layer. Capping is to be laid on subgrade with a minimum
CBR of 8%.
Capping material shall comply with Engineering Specification SPC 411 Earthworks Materials.
Compaction shall achieve a minimum dry density of 95 per cent Maximum Dry Density as
determined by AS 1289, Test 5.2.1.
The capping material shall be well mixed throughout the layer so that all voids are filled. The top of
the final layer shall be graded and trimmed, and material shall be added as necessary to produce
an even sealing layer.
8.1
General
For the purpose of this Clause, structures include bridge piers and abutments, wing walls, box
culverts, pipe culverts, headwalls, tunnels, retaining walls, platform walls, overhead wiring
structures, signal gantries and towers.
8.2
Construction
Care shall be exercised in constructing earthworks within 5m of structures to avoid damage to the
structures.
Non-vibratory compaction equipment shall be used within this distance and adjacent to the
structure as defined in the following table:
Structure
Compaction Method
Pipe Culverts
Structure Type
Width
Height
Bridge Abutments
2m
H/3
H + 300 mm
0.5 m
H + 500 mm
Retaining Walls
H/3
Rail Corporation
Issued July 2010
Page 10 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
Compaction shall start at the wall and proceed away from it.
The existing slope behind the structures shall be cut in the form of successive horizontal terraces,
each terrace being at least 1 meter in width and 600 mm in height.
In case of spill-through abutments, rocks shall not be dumped against the columns or retaining
walls but shall be built up evenly by hand placing around or against such structures.
In the case of framed structures, embankments at both ends of the structure shall be brought up
simultaneously and the difference between the levels of the embankments at the respective
abutments shall not exceed 500 mm unless otherwise specified in the Drawings or within the
specifications.
Adjacent to weep holes, free draining filter material encapsulated in a suitable geotextile fabric
should be placed, horizontally for at least 300 mm from, and vertically for 450 mm above the weep
- hole. Free draining material must be provided by broken stone or river gravel consisting of clean,
hard, durable particles graded from 50 mm to 10 mm such that:
8.3
Excavation
Care should also be exercised when excavating within 5m of structures (for example near
overhead wiring structures when benching into slopes for embankment widening or when
excavating for track reconditioning).
When excavating adjacent to structures, there is a risk that the footings may be undermined or the
structure destabilized, resulting in structural failure and potential collapse.
Excavations in the vicinity of structure footings are therefore not permitted unless documented
engineering advice and approval are obtained.
No excavation should be made within this 5m distance without prior analysis of structure stability
with respect to the effects of the excavation.
No excavation shall be made below the base of the footings of any structure (for example bridges,
retaining walls and station platform walls) without prior analysis of structure stability with respect to
the effects of the excavation.
The approval will be in the form of a certification by a competent geotechnical/structural engineer
with relevant engineering authority, based on the results of an appropriate geotechnical and/or
structural investigation.
9.1
Vertical Tolerances
9.1.1
In embankments
9.1.2
In cuttings
Rail Corporation
Issued July 2010
Page 11 of 16
Version 2.0
Superseded by T HR CI 12110 ST
9.1.3
9.1.4
Capping layer
9.2
9.1.5
ESC 410
The finished surface of the capping shall be within 25mm of the level shown on the drawings
and:
The algebraic difference of the deviations from the correct level for any two points
20 metres apart on the centreline shall not exceed 15mm.
The deviation from a three (3) metre straight edge laid on the surface parallel to the
centreline shall not exceed 10mm.
Horizontal Tolerances
Base at top of cuts and fills, widths of benches and berms shall not to be less than specified
dimensions. Maximum positive tolerance is 300 mm, unless approved by the Geotechnical
Engineer.
The width of the capping layer from the design centreline to the finished top of embankment slopes
or toe of batters in cuttings shall be not less than the dimensions required by Appendix 3.
When the capping layer is tested with a three (3) metre straight edge laid perpendicular to the
centre line the deviation from design profile shall not exceed 10mm concavity.
10
Drainage
Cess drains; sub-surface drains, top drains and interceptor drains shall be provided for cuttings and
are to comply with the requirements in ESC 420 Track Drainage.
11
Ground Anchors
Ground anchors shall have a design life of 100 years.
Ground anchors shall comply with the requirements of AS 4678 Earth-retaining structures and
Technical Specification S38 Permanent Rock Anchors in RailCorp Engineering Specification SPC
301 Structures Construction.
The design of ground anchors shall include mitigation against the effects of stray currents.
The designer shall specify requirements for testing. Test procedures shall comply with Technical
Specification S38.
The designer shall specify requirements for long term monitoring, if any.
Anchor heads shall be protected so as not to be an obstruction. They shall be recessed or
protected by a continuous smooth surface of shotcrete, concrete etc.
Ground anchors shall not extend under private property without the approval of the Chief Engineer
Civil.
12
Rail Corporation
Issued July 2010
Page 12 of 16
Version 2.0
Superseded by T HR CI 12110 ST
ESC 410
The train examination area is not to be assumed as available for road access purposes.
13
Walkways
Where nominated, walkways are to be provided for staff to walk along the track cess. The
minimum requirement is to cover walkways with a 50mm layer of 10mm single sized aggregate as
in Appendices 1 and 2.
14
Rehabilitation of Formation
In rehabilitating the formation, the following shall be taken into account when preparing the work
plan and design:
Rail Corporation
Issued July 2010
Page 13 of 16
Version 2.0
ESC 410
Appendix 1
Shoulder Distance
Shoulder Distance
Rail Level
1.5 :1
1000 min.
1.5 :1
Ballast
1 in 30
Formation Level
1 in 30
1 in 10
Earthworks Level
Capping Layer
Batter Slope
Natural
Surface
EMBANKMENT
CL
Batter Slope
Shoulder Distance
Shoulder Distance
Batter Slope
Top drain
1.5 :1
1.5 :1
Ballast
1 in 30
1 in 30
Capping Layer
Cess drain
ROCK
EARTH
CUTTING
CL
Superseded by T HR CI 12110 ST
Shoulder Distance
Shoulder Distance
1250
50 min.
Rail Level
1.5 :1
1 in 30
1 in 30
1 in 30
1.5 :1
Formation Level
Earthwork Level
1 in 30
Capping Layer
Rail Corporation
Issued July 2010
Page 14 of 16
Version 2.0
Appendix 2
ESC 410
1000 min.
1 in 10
Shoulder Distance
Track Centres
Rail Level
1.5 :1
1
1.5 :1
Ballast
in
Formation
Earthworks Level
Natural
Capping
Surface
Batter Slope
EMBANKMENT
Batter Slope
Superseded by T HR CI 12110 ST
Shoulder Distance
Track Centres
Shoulder Distance
Batter Slope
1.5
:1
1.5 :1
Ballast
1 in 30
EARTH
ROCK
Top Drain
Capping Layer
Cess Drain
CUTTING
Shoulder Distance
3 :1
1.5 :1
3 :1
1.5 :1
1 in 30
1 in 30
in
Subsurface Drain
Capping
1 in 30
Surface Drain
CENTRE DRAIN
Shoulder
50 min.
1.5 :1
1 in 30
1 in 30
Capping
Typical section where shunters and
guards walkways are required.
Rail Corporation
Issued July 2010
Page 15 of 16
Version 2.0
Superseded by T HR CI 12110 ST
Appendix 3
ESC 410
Shoulder Distance
Shoulder distance
Plain track
mm
4250
Siding (Electrified)
4250
Siding (non-electrified)
3000
6200
5500
Special Requirements
Rail Corporation
Issued July 2010
4250
5500
7750
3000
Page 16 of 16
Version 2.0