Professional Documents
Culture Documents
ANSWERS
PUTRAJAYA CAMPUS
Test No. 1
2nd Semester, Year 2015 / 2016
PROGRAMME
SUBJECT CODE
: CEPB 323
SUBJECT
DATE
TIME
INSTRUCTIONS TO CANDIDATES:
1. This paper contains THREE (3) questions in TWO (2) pages.
2. Answer ALL questions in the answer sheets that are provided.
3. Total marks = 45 marks
0
0
A
2
2
2
6 D 14
2 8 10
[8 marks]
24 C 30
14 6 20
14 E 24
14 10 24
2 F 14
2 12 14
30
30
H 32
2 32
24 G 30
24 6 30
[1 mark]
[1 mark]
[2 marks]
[1 mark]
a) The CPM arrow (AOA) diagram is shown in Figure 2. Note that the diagram was
created / drawn based on the vertical event numbering system.
b) The critical path is shown by bold arrows in Figure 2.
[10 marks]
[2 marks]
[1 mark]
[1 mark]
e) The latest time that activity D must start to avoid any delay in the project is at the
beginning of the 9th month.
[1 mark]
Page 2 of 4
4
2
B
4
8
6
8 D 10
6 2 8
0
0
A
2
2
2
10
10
2 C
2 6
8
8
8
8
F 16
6 16
16 G 18
16 2 18
E 10
2 10
Successor
Activity A
Activity B
If the predecessor (activity A) were delayed and completed behind schedule therefore the
successor (activity B) will have to start behind schedule.
Lag and lead can be introduced in the successor / predecessor relationship. For F-S
relationship, lag is the duration that a successor is purposely delayed from the finish of its
predecessor. Lead is the opposite of lag which is the duration that a successor purposely
precedes the finish of its predecessor.
End of questions
Page 4 of 4