Scope:

The scope of this document is to describe the procedure for rectification of the Liner plate
( in 6 places) of Stack pipe 4.
1.1.1 CUT THE DAMAGED LINER PLATE OF THE STACK PIPE BY CUT-OFF WHEEL.
1.1.2 LEVELING OF THE LINER PLATE WHERE THE DENT HAS OCCURRED.
1.1.3 FITUP AND WELD THE RECTIFIED PIECE ON TOP LINER SHEET AND CLEAN.
2.0

SAFETY

2.1

All safety precautions and procedures according to GSE Safety Manual (Submitted)
shall be followed during all erection.