Professional Documents
Culture Documents
1 of 5
http://ecmweb.com/print/shock-amp-electrocution/case-concrete-cutting-c...
print | close
When a rapidly growing packaging plant decided to once again expand its main manufacturing facility, the
company faced a long yet familiar renovation road ahead. Through addition after addition, what was once a
single building had now grown many times over into a large office, manufacturing, and distribution complex. As
is the case with many building expansions, operations in the older sections moved into the new additions, and
their former homes were then repurposed.
In this case, the company wanted to expand its production area into a warehouse section of the complex. A large
extruder, which outputs rolls of plastic sheeting that make up the various packets, bags, and wrappers for the
final product, was required in the new production area. The packaging company coordinated the construction
and hired individual contractors to remodel the warehouse and update the utilities.
The Scene
The extruder weighed several tons, which was much greater than the concrete foundation floor of the warehouse
could handle. A 30-ft 115-ft rectangle of concrete needed to be cut out of the approximately 60-ft 150-ft
warehouse floor to accommodate the footprint of the extruder. The concrete pad section was further divided into
5-ft 5-ft sections that could be removed with a front end loader. The ground below the foundation would then
be dug out to accommodate a thicker, 18-in. reinforced concrete foundation to handle the additional weight of
the extruder.
This particular project required the use of a gas-powered, walk-behind cutting saw with a 38-in. blade. To use
this tool, a constant stream of water jets onto the blade and cutting surface to prevent the otherwise heavy dust
generated by the cutting operation from blowing into the warehouse. As the operator walks along with the
self-propelled saw, another worker follows behind and uses a floor vacuum to remove the slurry. Although the
cutting process doesnt seem complicated, a hidden electrical hazard awaited the unsuspecting workers.
The Accident
Jared had worked for XYZ Heavy Construction, the company hired to replace the foundation below the new
extruder, for about 16 yr prior to this project. He had cut out sections of concrete and asphalt at least 20 to 30
times before, including other areas of the packaging company. Although he never received any specific training,
he was familiar enough with the operation of different types of cutting saws and cutting procedures in general.
The day of the incident was also Jareds first day of work on this particular job. After meeting with the on-site
foreman for XYZ at 7 a.m., the project manager for the packaging company made a rough sketch of the
foundation area to be removed and told the guys to get to work. XYZ employees asked if there were any potential
utility services (water lines, electrical conduits, etc.) in the area they needed to be aware of. According to Jared,
the answer was no.
07-03-15 4:29 PM
2 of 5
http://ecmweb.com/print/shock-amp-electrocution/case-concrete-cutting-c...
Jared and other XYZ workers took a few hours to measure and lay out the extruder footprint, eventually
denoting it with a black marker. It took another hour or two to set up the saw and vacuum equipment. Once they
were ready, Jared began his first cut along one of the 115-ft edges of the extruder footprint.
As he moved along the perimeter with the saw, he moderated the cutting depth based on the resistance on the
blade and the type of material thrown up with the saw (dirt vs. concrete). In this case, the concrete floor was on
average 8 in. to 10 in. thick. Wearing his normal construction outfit of jeans and a T-shirt along with regular
work boots, leather gloves, eye-protection, and a hard hat, Jared walked along the right side of the saw in order
to make sure he was following the cutting line, steering the saw with his left hand.
He had traveled approximately 80 ft during his first cutting pass when the arcing event occurred. After seeing a
blue arc come out of the saw, he felt an electrical shock and was immediately thrown to the floor. Jared later
reported that the saw itself jumped up from the cutting track due to the force of the blast.
Unfortunately, none of the other workers saw the incident. The worker operating the vacuum was several feet
behind Jared and didnt initially notice anything. Once the XYZ foreman saw Jared sitting on the floor 10 ft to 15
ft away from the now non-operating saw, he quickly went over to him. He found Jared pale, shivering, and
shaking. I got zapped, Jared told him.
07-03-15 4:29 PM
3 of 5
http://ecmweb.com/print/shock-amp-electrocution/case-concrete-cutting-c...
Lessons Learned
If further investigation had been done prior to the start of construction, it would have revealed the existence of
electrical plans in the possession of the original electrical contractor. This would have at least given all parties
notice that hazards did exist, which could be further identified by using a circuit tracer and cable locator to
determine the actual path of the conduit runs beneath the concrete.
Even if the electrical plans were not found prior to construction, one could still attempt to determine the
existence of pipes, conduits, cables, etc., using an outside contractor to examine the extruder footprint with
x-ray equipment or ground-penetrating radar. Both of these methods are well known ways of mapping out
unknown underground utilities.
OSHA statutes require all employers to inform their employees of the risks involved with their job and provide
them with the appropriate PPE. In particular, OSHA 29 CFR 1910 and 29 CFR 1926 regulate safety and health
in general industry and construction, respectively. Section 1910.132(d)(1) states: The employer shall assess the
workplace to determine if hazards are present, or are likely to be present, which necessitate the use of personal
protective equipment (PPE)
The argument against XYZ Construction is that it did not perform this task to the best of its ability. Furthermore,
it did not provide the appropriate PPE to employees performing concrete cutting operations, as provided in the
OSHA statute 29 CFR 1926.29(a), which states: The employer is responsible for requiring the wearing of
appropriate personal protective equipment in all operations where there is an exposure to hazardous conditions
or where this part indicates the need for using such equipment to reduce the hazards to the employees.
In this case, cutting concrete where known or unknown electrical lines may exist is referred to in 29 CFR
1926.416(a)(2): In work areas where the exact location of underground electric power lines is unknown,
employees using jack-hammers, bars, or other hand tools which may contact a line shall be provided with
insulated protective gloves.
Further, protective footwear is also required according to 29 CFR 1910.136(a): Each affected employee shall
wear protective footwear when working in areas where there is a danger of foot injuries due to falling or rolling
objects, or objects piercing the sole, and where such employees feet are exposed to electrical hazards.
07-03-15 4:29 PM
4 of 5
http://ecmweb.com/print/shock-amp-electrocution/case-concrete-cutting-c...
Protective gloves need to be designed and manufactured according to ASTM standard D 120: Specification for
Rubber Insulating Gloves as well as rated for the appropriate voltages that may be encountered. Insulating
footwear should be rated DI, for dielectric shoes, and rated according to ASTM F 1117: Specification for
Dielectric Overshoe Footwear.
According to OSHA standards, employers are also required to train their employees to recognize potential
hazards and determine when PPE is necessary. Because Jared did receive many hours of training during his
work history with XYZ, he probably should have been able to recognize hazardous conditions on his own and
request mitigation and/or PPE. However, his prior history of accident-free concrete cutting and his position in
the company may have discouraged him from questioning the safety of this particular project.
The Outcome
As a result of this incident, XYZ Construction changed its policy and procedures regarding concrete cutting.
Now, it brings in a utility locating company if the building owner states that there are underground conductors
in the area or if the as-built plans show such lines. It also requires workers to wear insulated gloves and boots.
The packaging company hired an electrical contractor to produce electrical drawings of the building systems.
Eventually, the lawsuits against XYZ Construction and the packaging company were settled confidentially out of
court for an undisclosed amount prior to trial. Had OSHA investigated this claim, XYZ could have been fined
based on the violations uncovered during our analysis.
One final note to keep in mind on this case is that you, as electrical professionals, are aware of the hazards
involved when dealing with electricity. Therefore, its critical to coordinate with all parties involved to ensure that
safety is paramount. Keep clear and accurate records/plans of your work, provide the same to your client at the
conclusion of a project, and keep archive copies on-hand in case incidents such as this arise.
Paris is a forensic electrical engineer with Anderson Engineering, New Prague, Minn. He can be reached at
dparis@andeng.net.
The Concrete Sawing and Drilling Association (CSDA), the leading trade group representing concrete sawing
and drilling companies, offers many safety and construction training courses/documents. It has also worked
directly with OSHA to produce a best practices document regarding electrical safety. CSDA-OBP-1004, issued in
2010, lists a variety of electrical safety concerns, involving both underground electrical services and the
electrical components of the saw itself. Below are a few items of significance from its best practices document
that relate to this case.
Electricity is widely recognized as a potential workplace hazard, exposing employees to electric shock, burns,
fires, and explosions. Working on or around electrical conductors and equipment can be particularly dangerous,
because electrical energy often cannot be sensed until contact is made. Apply the following guidelines to
maximize safety:
1. On a daily basis, before starting any task, inspect the work area for possible electrical hazards. Take all
necessary precautions to avoid cutting into electrical lines. In work areas where the exact location of the
electrical power is unknown, power in the general vicinity of the building should be de-energized.
2. Operators should wear ASTM F 1117 dielectric boots and ASTM D 120 rubber insulating gloves. Leather
protector gloves that meet ASTM F 696 should be worn over insulating gloves to prevent damage. Instruct each
employee on how to recognize and avoid unsafe conditions that apply to the work areas.
07-03-15 4:29 PM
5 of 5
http://ecmweb.com/print/shock-amp-electrocution/case-concrete-cutting-c...
07-03-15 4:29 PM