Professional Documents
Culture Documents
Applied Energy
journal homepage: www.elsevier.com/locate/apenergy
Aalto University, School of Engineering, Dept. of Energy Technology, PO Box 14400, FI 00076 Aalto, Finland
University of Sao Paulo, Sao Paulo, Brazil
c
Aalto University, School of Chemical Technology, Dept. of Biotechnology and Chemical Technology, PO Box 16100, FI 00076 Aalto, Finland
b
h i g h l i g h t s
Process comparison of three CHP-integrated biomass upgrading processes.
Integration of biomass upgrading increases the exergetic efciency.
Integration of biomass upgrading decreases the plants fuel and product price dependency.
Fast pyrolysis integration is most protable followed by wood pellets.
a r t i c l e
i n f o
Article history:
Received 20 February 2015
Received in revised form 15 June 2015
Accepted 17 June 2015
Keywords:
Biomass
Combined heat and power (CHP)
Exergoeconomic analysis
Fast pyrolysis
Wood pellets
Wood torrefaction
a b s t r a c t
The objective of this work is to assess the exergoeconomic performance of three biomass upgrading
processes, namely wood pellets, torreed wood pellets and pyrolysis slurry (a mixture of pyrolysis char
and oil), integrated with a municipal combined heat and power plant. The work is a continuation of work
published earlier (Kohl et al., 2013) and the same simulation model results are used as input for the
calculation of the exergy ows within the system. Economic data of the assessed processes has been
obtained from the literature and has been combined with the exergy data following the specic exergy
costing approach in order to perform the exergoeconomic analysis. The highest exergy destruction is
caused in the combustion equipment, whereas the upgrading processes appear highly efcient. The systems exergetic efciency can be improved by 22%, 26% and 31% for the integration with pyrolysis slurry,
torreed wood pellets and wood pellets, respectively, making wood pellets the most efcient integration
option. However, the integration of pyrolysis slurry production yields the highest prot under the
projected price scenario. In addition it also reacts moderately on possible price uctuations as is shown
in a sensitivity analysis. Considering the generally acknowledged future technical potential of pyrolysis
products for replacing fossil oil-based products transport fuel production as well as the commonly
expected further price increase for fossil oil, pyrolysis slurry constitutes as the best option to be
integrated with the municipal combined heat and power plant.
2015 Elsevier Ltd. All rights reserved.
1. Introduction
It has been shown in our previous work [1] that integration of
wood- and torreed wood pellets as well as of fast pyrolysis slurry
has the potential to substantially improve the energetic and environmental performance of a municipal combined heat and power
(CHP) plant. The motivation for the accomplished study was to
point out potential pathways for municipal CHP plants to mitigate
the adjunct district heating (DH) networks CO2 emissions and, at
the same time, also add a new product to the companys portfolio
allowing it to benet from the currently emerging bio-economy.
Recent research shows the growing interest in the mentioned
upgrading processes and their integration with CHP plants. The
torrefaction process and its economic feasibility have been discussed by Batidzirai et al. [2] and van der Stelt et al. [3]. Both
afrmed the improved fuel and transport properties of torreed
wood pellets (TWP) and stated good economic potential. Adams
et al. [4] compared wood pellets (WP) and TWP production when
produced in Norway and delivered to a power station in UK.
They concluded that the system based on TWP has a lower environmental impact but requires more harvesting area. Starfelt
et al. [5] studied the integration of TWP production, with a CHP
291
Nomenclature
Abbreviations
CELF
constant-escalation levelisation factor
CEPCI
chemical engineering plant cost index
CHP
combined heat and power
DH
district heating
DHEX
district heat exchanger
ECO
economiser
EVA
evaporator
FWT
feedwater treatment
HFO
heavy fuel oil
IC
installation cost
LHV
lower heating value
PEC
purchased equipment cost
PS
pyrolysis slurry
SH
superheater
SPECO
specic exergy cost
TOC
total onsite cost
TCI
total capital investment
TWP
torreed wood pellets
WP
wood pellets
Symbols
b
C
c
cp
E
e
e
EC
El.
f
h
i
j
k
l
n
m
p
q_
R
r
S
s
T
t
W
x
y
z
Z
b
process unit
factor used for calculation of the CELF
lifetime of the plant (y)
chemical component
pressure (Pa)
heat ux (kW)
gas constant (kJ/kg K)
relative cost difference (%)
characteristic dimension ()
specic entropy (J/kg K)
temperature (K)
operation time (h)
work (kW)
molar fraction ()
exergy destruction rate ()
mass fraction ()
z-factor, cost of unit operation (/h)
factor for biomass chemical exergy calculation
efciency ()
Subscripts
0
reference state (15 C, 1013 mbar)
D
destruction
E
evaporation
el
electrical
exe
exergetic
F
fuel according to the F and P rules
L
losses
P
product according to the F and P rules
ph
physical
rel
relative
S
sulphur
th
thermal
W
water
w
work
292
Boiler evaporator
Superheater 1
Superheater 2
14
Economiser
Turbine
Feedwater treatment
Flue gas
15
7
6 5
Power
8
Wet
Biomass
10
9
B
Wet Biomass
12
District
Heat
11
13
16
Water
Steam
Air
Air
17
Flue gas
23
1
2
3
4
5
Air Ambient
Air Boiler In
BM Boiler In
ECO Water Out
Steam EVA Out
6
7
8
9
Steam SH 2 In
Steam Turbine In
Turbine Exhaust
DH Return
10
11
12
13
DH Supply
DH Condensate
Turbine Bleed
ECO Water In
14
15
16
17
FG SH 1 In
FG SH 1 Out
FG Air pre-heater In
FG Air pre-heater Out
Fig. 1. Simplied process owsheet of the stand-alone CHP plant. The units as evaluated in the exergoeconomic analysis are highlighted in grey. Abbreviations:
ECO: Economiser, EVA: Evaporator, SH: Superheater, DH: District Heating, FG: Flue Gas.
Boiler evaporator
Superheater 1
Superheater 2
Economiser
Turbine
15
Flue gas
24
22
8
16
19
Power
6 5
Feedwater treatment
Dryer
Pelletising
23
3
WP
Wet Biomass
Steam
13
District
Heat
12
14
17
Wet
Biomass
Dried Biomass
Water
11
10
A
Air
1
18
Air
20
21
Flue gas
Wood Pellets
1
2
3
4
5
6
Air Ambient
Air Boiler In
BM Boiler In
ECO Water Out
Steam EVA Out
Steam SH 2 In
7
8
9
10
11
12
Live Steam
Steam Turbine In
Turbine Exhaust
DH Return
DH Supply
DH Condensate
13
14
15
16
17
18
Turbine Bleed
ECO Water In
FG SH 1 In
FG SH 1 Out
FG ECO Out
FG Air pre-heater Out
19
20
21
22
23
24
Steam Dryer In
Dryer Condensate Out
BM Dryer In
BM WP In
WP
FG Out
Fig. 2. Simplied process owsheet of the CHP plant integrated with WP production. The units as evaluated in the exergoeconomic analysis are highlighted in grey.
Abbreviations: ECO: Economiser, EVA: Evaporator, SH: Superheater, DH: District Heating, FG: Flue Gas, BM: Biomass, WP: Wood Pellets.
is described by two full load periods (differing in their DH temperature prole) and 5 isochronous part load periods. All integration
options allow for longer annual operation time and the time extension is represented by an additional subload period. For more
information on the multiperiod model please refer to Refs. [1,14].
2.1.1. Description of the stand-alone CHP plant (case CHP)
As can be observed from Fig. 1, the stand-alone CHP plant consists of a uidised bed boiler with evaporator (B) and superheater
293
Boiler evaporator
Superheater 1
Superheater 2
Economiser
Turbine
15
25
Feedwater treatment
Dryer
Torrefaction
16
22
Power
6 5
26
3
TWP
G
11
10
13
4
19
Wet
Biomass
17
18
Dried Biomass
Water
Steam
District
Heat
12
14
Wet Biomass
27
Flue gas
28
20
A
Air
1
21
Air
23
24
Flue gas
Torrefaction product
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Air Ambient
Air Boiler In
BM Boiler In
ECO Water Out
Steam EVA Out
Steam SH 2 In
Live Steam
Steam Turbine In
Turbine Exhaust
DH Return
DH Supply
DH Condensate
Turbine Bleed
ECO Water In
15
16
17
18
19
20
21
FG SH 1 In
FG SH 1 Out
FG TWP In
FG TWP Out
FG ECO Out
FG Air pre-heater In
FG Air pre-heater Out
22
23
24
25
26
27
28
Steam Dryer In
Dryer Condensate Out
BM Dryer In
BM TWP In
TWP
Torrefaction Gas
FG Out
Fig. 3. Simplied process owsheet of the CHP plant integrated with TWP production. The units as evaluated in the exergoeconomic analysis are highlighted in grey.
Abbreviations: ECO: Economiser, EVA: Evaporator, SH: Superheater, DH: District Heating, FG: Flue Gas, BM: Biomass, TWP: Torreed Wood Pellets.
Boiler evaporator
Superheater 1
Superheater 2
Economiser
Turbine
Feedwater treatment
25
C
17
Pyrolysis
15
16
22
6 5
Power
19
26
27
Flue gas
28
18
Pyrolysis
Slurry
13
District
Heat
12
14
c
20
Wet
Biomass
A
1
Dried Biomass
11
10
B
2
Wet Biomass
21
Water
Air
Steam
23
24
Air
Flue gas
Pyrolysis Product
1
2
3
4
5
6
7
Air Ambient
Air Boiler In
BM Boiler In
ECO Water Out
Steam EVA Out
Steam SH 2 In
Live Steam
8
9
10
11
12
13
14
Steam Turbine In
Turbine Exhaust
DH Return
DH Supply
DH Condensate
Turbine Bleed
ECO Water In
15
16
17
18
19
20
21
FG SH 1 In
FG SH 1 Out
FG BFP In
FG BFP Out
FG ECO In
FG ECO Out
FG Air pre-heater Out
22
23
24
25
26
27
28
Steam Dryer In
Dryer Condensate Out
BM Dryer In
BM BFP In
Pyrolysis Slurry
Pyrolysis Gas
FG Out
Fig. 4. Simplied process owsheet of the CHP plant integrated with PS production. The units as evaluated in the exergoeconomic analysis are highlighted in grey.
Abbreviations: ECO: Economiser, EVA: Evaporator, SH: Superheater, DH: District Heating, FG: Flue Gas, BM: Biomass, BFP: Biomass Fast Pyrolysis.
294
boiler and thus its energy content is subtracted from the boiler
input. The power consumption of the added equipment has been
estimated to 123 Wel/kWch of the chemical energy contained in
the wet wood (based on the LHV) that enters the process. This
power consumption is subtracted from the net power generation
as calculated by the simulation software. In continuation, char
and gas are separated with a hot cyclone and the liquid fraction
is condensed with a spray cooler applying cooled pyrolysis oil (section K). In order to avoid ageing, liquid and char are stored separately and are only mixed prior to transport, forming PS [1,14].
2.2. Exergy analysis
Although energy is always conserved in any process, its useful
part (exergy) is not conserved due to the existence of irreversible
phenomena, such as heat transfer with nite temperature gradient,
mixing, chemical reactions and expansion. These irreversibilities
can be identied and quantied by exergy analysis, which takes
into account the entropy generated. Exergy analysis can reveal
the margin available to design more efcient energy conversion
systems. Although the maximum efciency in energy conversion
systems corresponds to an ideal process (no entropy generation
and reversibility), all real processes are, to some extent, entropy
generators. Exergy analysis can point out how far from ideality a
process is, and thus, indicate the potential for improvements.
2.2.1. Exergy balance calculations
For material streams, there are two main components of
exergy: physical and chemical (neglecting kinetic and gravitational
portion). The former takes into account the departure of the system
from environmental temperature and pressure (T0, p0), while the
chemical exergy takes into account the differences between the
systems chemical composition and the standard chemical composition of the environment. For each process stream, the specic
physical and chemical exergy values (kJ/kg) were calculated as
follows:
Steam and water
Physical exergy:
cp
X
xm cp;m T
ech
X
m
xm ech;m RT 0
X
xm lnxm
m
295
50.64
6.1
42.22
0.16
0.08
Ash
M
0.8
50
LHV (MJ/kg)
7.89
Power output
Condenser pressure
5.21 MWel
1.55 bar
DH return temp.
83 C
where ECnew is the cost of the scaled equipment, ECold is the known
cost, j is the scaling factor and Snew/Sold is the ratio of two characteristic equipment dimensions. In the case of power plants either
power output or fuel input is used as characteristic dimension
and the scaling factor was set to 0.6. Applying Eq. (8) on both characteristic dimensions the cost can estimated to be between 25.6 M
and 28.9 M at 2008 prices. With the CEPCI (Chemical Engineering
Plant Cost Index) known prices of a reference year 1 can be adjusted
to prices of reference year 2 according to Eq. (10):
_ T 0 =T
e_ heat q1
24.7 MWch
16.5 MWth
60 bar/510 C
110 C
Fuel input
DH output
Live steam
DH supply temp.
Under consideration of the CEPCI the TCI in 2013 prices was set to
26 M. Therefore the calculated equipment cost considers the inuence of ination and price escalation. In order to determine the
detailed equipment cost, the single equipment units cost contributions have been adapted from AC Caputo et al. [19]. The boiler cost
has been broken down to costs for the evaporator, the superheaters,
the economizer and the air pre-heater by rating them with the
transferred heat in the specic unit. The cost for efuent treatment
has been distributed to the other equipment based on the weighted
average of their cost contribution. By that the purchased equipment
cost (PEC) were calculated to represent 39% of the TCI. All costs as
used in the following are given in Table 2.
Investment cost for WP, TWP and PS
TCI costs calculations for production of WP, TWP and PS were
carried out by rst sizing the equipment. The equipment was
designed for the maximum ow rate, typically reached at 70%
DH-load. The owrate through the upgrading equipment increases
at constant boiler load since more heat needs to be utilised in the
upgrading equipment in order to match the DH load. The condensate leaving the steam tube dryer is rejected to the feedwater tank
and for high dryer loads this would drive the feedwater beyond the
saturation point. Thus, at loads below 70%, the boiler load must be
decreased in order to avoid the saturation state in the feedwater
tank (please see [1] for more details). For the sizing, no overdesign
was included in the equipment design. After sizing the equipment,
the PEC for a specic unit was extracted from references. If needed,
an exchange rate of 1.35 US $/ was used. All costing details including the used references can be found in Tables 3ac. If the PEC for
the required capacity was not directly available from the literature
source the PEC was scaled applying Eq. (8). The scaling factors are
given in Tables 3a3c. In order to determine the total onsite costs
(TOC), installation cost factors have been estimated to range from
10% to 25% based on the purchased equipment cost. All prices and
costs have been adjusted to 2013 values by applying the CEPCI (see
Eq. (9)). The CEPCI of the reference year 2013 is 567.6.
As no detailed cost data for the processes described is available,
it has been assumed that the TOC represent 35% of the TCI costs
which is a typical value for chemical plant design [20]. In order
to consider start-up cost and the costs for connecting the CHP plant
with the upgrading equipment 10% of the TCI costs was added as
contingency.
296
Table 2
Investment cost calculation for CHP plantb.
Cost position
Biomass pre-treatment
Evaporator
Superheater 2
Superheater 1
Economiser
Air pre-heater
Turbine and alternator
DH exchanger
Feedwater system
% of PEC
677.0
2649.5
644.6
433.7
1060.8
1236.1
2116.0
912.0
481.7
6.6
25.9
6.3
4.2
10.4
12.1
20.7
8.9
4.7
PEC
Installation
Piping
Instrumentation
Electrical
Civil works
Land
Service facilities
Engineering
Start up
10211.4
3063.4
919.9
1021.1
2432.2
3552.6
1021.1
1531.7
1225.4
1021.1
30.0
9.0
10.0
23.8
34.8
10.0
15.0
12.0
10.0
TCI
26000.0
CELF 1 l =1 l 1 i =1 i 1;
11
with
l 1 b=1 i
cin e_ in k Z_ k :
10
12
Table 3a
Investment cost calculation for WP.
Equipment
Silo
Belt conveyor
Crusher
Steam tube dryer
Mill
Belt conveyor
Pelletiser
Blower
Belt conveyor
Silo
Capacity
3
2100 m
15.73 t/h
15.73 t/h
15.73 t/h
8.75 t/h
8.75 t/h
8.75 t/h
8.75 t/h
1050 m3
Scaling factor s
Reference year
PEC (k)
IC (% PEC)
CEPCI
TOCa (k)
Ref.
NA
NA
0.65
0.58
NA
NA
0.61
NA
NA
NA
2006
1991
2013
2011
2013
1991
2013
1991
1991
2006
1573.2
59.3
109.2
1134.8
76.7
37.0
1521.5
22.2
37.0
194.4
10
25
10
10
10
25
10
10
25
10
499.6
361.3
567.6
585.7
567.6
361.3
567.6
361.3
361.3
499.6
1966.1
116.4
120.2
1209.7
84.4
72.7
1673.7
38.4
72.7
243.0
[21]
[20]
[2]
[22]
[2]
[20]
[2]
[20]
[20]
[21]
Sum TOC
TCI
a
5597.2
17591.1
297
Capacity
3
2070 m
15.52 t/h
15.52 t/h
15.52 t/h
9.11 t/h
9.11 t/h
8.07 t/h
8.07 t/h
8.07 t/h3
830 m3
Scaling factor s
Reference Year
PEC [k]
IC (% PEC)
CEPCI
TOCa (k)
Ref.
NA
NA
0.65
0.58
NA
NA
0.61
NA
NA
NA
NA
2006
1991
2013
2011
1991
2013
2013
2013
1991
1991
2006
1551.6
58.4
108.3
1076.9
59.3
5931.9
72.5
1448.1
22.2
37.0
207.5
10
25
10
10
10
10
10
10
10
25
10
499.6
361.3
567.6
585.7
361.3
567.6
567.6
567.6
361.3
361.3
499.6
1939.1
114.8
119.1
1148.0
102.4
6525.1
79.7
1592.9
38.4
72.7
259.3
[21]
[20]
[2]
[22]
[20]
[2]
[2]
[2]
[20]
[20]
[21]
Sum TOC
TCI
a
11991.5
37687.5
Table 3c
Investment cost calculation for PS.
Equipment
Silo
Belt conveyor
Crusher
Steam tube dryer
Belt conveyor
Mill
Pyrolysis reactor
Quench
Colloid mixer
Tank and silo
Capacity
3
1800 m
13.72 t/h
13.72 t/h
13.72 t/h
7.63 t/h
7.63 t/h
7.63 t/h
6.58 t/h
5.5 m3/h
430 m3
Scaling factor f
Reference year
PEC (k)
IC (% PEC)
CEPCI
TOCa (k)
Ref.
NA
NA
0.65
0.58
NA
0.65
0.7
0.7
NA
NA
2006
1991
2013
2011
1991
2013
2003
2003
1990
2006
1371.6
51.7
99.9
1048.0
37.0
68.3
1244.0
506.1
711.5
1148.0
10
25
10
10
499.6
361.3
567.6
585.7
10
10
10
15
10
567.6
402
402
357.6
499.6
1714.1
101.5
109.9
1117.2
72.7
75.1
2718.3
1105.1
27.0
370.2
[21]
[20]
[2]
[22]
[20]
[2]
[23]
[23]
[20]
[21]
Sum TOC
TCI
a
7411.1
23292.1
Different prices and escalation rates can be expected for the different products power, DH, WP, TWP and PS, respectively, and also
for the wood fuel. It is assumed that TWP and PS can be sold at the
same price per thermal unit as coal and heavy fuel oil (HFO),
respectively. In order to estimate the price development of wood,
WP, coal and HFO over the investment period, the historical price
development in Finland based on data available from Statistics
Finland [26] and the Finnish Customs [27] has been used.
Likewise common practise in the energy business, the price
increase rate of the different fuels has been recorded and has been
averaged over the available data history. This average price
increase rate has been used for future price projection for the years
20142032 applying a linear correlation. Based on that, the average price over the whole investment period (comparable to the
annuity) was used in the economic assessment. All input data used,
as well as the estimated time-averaged future commodities unit
price is presented in Table 4 and further information is given in
the following:
Power: It is assumed that the power produced can be sold
locally and hence the Finnish yearly average net prices
(obtained from Ref. [26], excluding all taxes and charges) for
private users (provided in 4 different categories based on the
users total annual consumption) were averaged for the years
20042013. Based on this data the average price increase over
this 10 years period was calculated and used for price
projection.
DH: It is assumed that all heat produced can be sold to small
private consumers and hence the Finnish yearly average net
prices (obtained from Ref. [26], excluding all taxes and charges)
for private users (provided in 5 different categories after 2010
Table 4
Price projection for energy commodities.
Price in 2013
(/MW hch)
Data availability (y)
Average annual price
increase (%)
Projected average price
during investment
period (/MW hch)
Power
DH
Wood
chips
WP
TWP/Coal
PS/HFO
92.3
61.3
20.7
57.0
40.4
60.5
10
1.47
10
1.65
7
1.78
6
1.09
10
1.74
10
1.84
137.0
89.3
32.6
72.3
62.4
95.7
298
gexe EP =EF
13
ED Ein Eout EL
180
160
140
120
/MWh
100
80
60
40
20
0
2004
2008
2012
Wood Chips
Wood Pellets
15
yD is calculated with the data given in Tables A2A5 and by applying the F and P rule as dened in Table A1.
Accordingly, using the same data as for the exergy destruction
rate, the relative rate of exergy destruction is calculated according to Eq. (16). It describes the exergy destruction in process
unit relative to the total exergy destruction of the process.
16
2024
2028
2032
Power
Torrefied Wood Pellets
District Heat
Pyrolysis Slurry
The specic product costs, cproduct, are calculated in the same manner according to Eq. (17).
In order to estimate the cost of exergy destruction the values of
annual exergy destruction are multiplied with the fuel cost as
presented in Eq. (18).
18
In the same manner the cost for exergy losses, CL, can be determined. In here, losses have been accounted only for the ue gas
leaving the stack.
The so-called r-factor describes the relative cost difference
between fuel and product according to:
19
f Z=Z C D C L
Based on the value for the annual exergy destruction, the exergy
destruction per unit and for the whole process can be calculated
according to Eq. (15).
2020
Year
14
2016
17
20
299
A: Pre-heat
B: EVA
C: SH 1
D: SH 2
E: ECO
F: Turbine
G: DHEX
H: FWT
Overall
CEl. (/h)
Z (/h)
gE (%)
ED (GW h)
yD (%)
yDrel (%)
cfuel (/MW h)
cproduct (/MW h)
CD (/h)
CD + Z (/h)
r (%)
f (%)
0.19
23.3
0.25
22.9
6.0
781
8.4
767
67
144
24
35
57
115
49
26
517
72.8
28.6
60.8
37.0
46.9
82.0
84.5
89.5
24.2
3.7
60.2
4.4
8.7
8.9
5.1
2.4
0.1
93.6
27.2
71.4
39.2
63.0
53.1
18.0
15.5
5.5
62.7
4.0
64.4
4.7
9.4
9.5
5.5
2.6
0.1
100.0
32
30
30
30
30
117
118
171
25
81
134
66
115
137
173
287
914
174
23
352
26
51
52
117
57
2
461
90
496
49
86
109
232
106
28
1197
156
352
123
286
361
48
142
436
595
53
58
66
63
68
66
65
93
72
Z (/h)
gE (%)
ED (GW h)
yD (%)
yDrel (%)
cfuel (/MW h)
cproduct (/MW h)
CD (/h)
CD + Z (/h)
r (%)
f (%)
57
122
20
30
49
97
42
22
314
201
954
73.7
28.6
61.3
36.7
47.6
81.1
83.1
86.7
93.6
98.0
54.9
4.7
78.1
5.6
11.4
11.2
6.0
2.9
0.2
7.1
2.9
130.1
26.7
71.4
38.7
63.3
52.4
18.9
16.9
7.1
4.8
2.1
40.6
3.6
60.0
4.3
8.8
8.6
4.6
2.3
0.1
5.5
2.2
100.0
31
29
29
29
29
110
110
165
31
43
25
69
122
62
111
139
161
265
1163
42
49
58
23
356
26
52
51
103
51
4
34
19
511
80
478
46
82
100
201
93
27
348
221
1673
125
318
112
282
376
46
141
607
36
15
133
50
57
64
61
66
66
65
86
81
92
77
Table 5b
WP plant exergoeconomic analysis.
El. (GW hel)
A: Pre-heat
B: EVA
C: SH 1
D: SH 2
E: ECO
F: Turbine
G: DHEX
H: FWT
I: Dryer
K: Pellets
Overall
CEl. (/h)
0.25
6.2
25.7
0.34
0.63
2.89
21.6
646
8.9
29.7
71.5
530
Table 5c
TWP plant exergoeconomic analysis.
A: Pre-heat
B: EVA
C: SH 1
D: SH 2
E: ECO
F: Turbine
G: DHEX
H: FWT
I: Dryer
K: TWP
Overall
CEl. (/h)
Z (/h)
gE (%)
ED (GW h)
yD (%)
yDrel (%)
cfuel (/MW h)
cproduct (/MW h)
CD (/h)
CD + Z (/h)
r (%)
f (%)
0.26
26.0
0.35
0.57
3.95
20.9
6.3
657
9.1
28.0
91.1
522
56
119
20
29
48
95
41
22
253
660
1343
73.8
27.8
61.9
35.4
47.7
81.0
82.6
91.1
93.9
94.9
50.1
4.1
80.9
5.7
11.9
11.6
6.1
3.1
0.1
6.6
7.4
137.5
26.2
72.2
38.1
64.6
52.3
19.0
17.4
4.7
4.5
5.1
42.3
3.0
58.8
4.2
8.7
8.5
4.4
2.2
0.1
4.8
5.4
100.0
32
30
31
30
30
115
114
172
31
42
26
77
135
63
115
129
167
273
880
41
65
68
20
374
27
55
54
107
53
3
31
48
543
76
494
46
84
102
202
94
25
284
708
2115
139
342
107
279
324
46
140
412
31
52
160
50
57
63
60
65
65
64
89
77
94
80
Table 5d
PS plant exergoeconomic analysis.
A: Pre-heat
B: EVA
C: SH 1
D: SH 2
E: ECO
F: Turbine
G: DHEX
H: FWT
I: Dryer
K: PS
Overall
CEl. (/h)
Z (/h)
gE (%)
ED (GW h)
yD (%)
yDrel (%)
cfuel (/MW h)
cproduct (/MW h)
CD (/h)
CD + Z (/h)
r (%)
f (%)
0.26
26.3
0.36
1.42
1.99
22.3
5.9
633
9.1
67.6
43.4
507
53
114
19
28
46
91
39
21
238
342
991
73.7
28.0
48.7
43.0
48.6
80.4
82.4
89.9
93.0
89.8
46.0
4.6
87.3
6.7
11.3
10.2
6.4
3.2
0.1
8.6
14.5
153.0
26.3
72.0
51.3
57.0
51.4
19.6
17.6
5.3
6.1
10.2
46.0
3.0
57.0
4.4
7.4
6.7
4.2
2.1
0.1
5.6
9.5
100.0
32
30
30
30
30
116
115
178
33
46
26
74
132
83
94
139
171
274
945
44
61
66
21
378
29
49
44
106
52
3
40
94
568
75
492
47
77
90
197
91
24
279
436
1808
130
335
174
207
358
46
138
431
33
34
152
48
57
62
61
67
65
64
88
75
82
76
Abbreviations: EVA: Evaporator, SH: Superheater, ECO: Economiser, DHEX: district heat exchanger, FWT: feedwater treatment, TWP: torreed wood pellets, PS: pyrolysis
slurry,
Represented by the Z-value it can be observed that the integration has a strong inuence on the plants TCI. The cost per operation hour is highest for TWP as a result of the expensive
torrefaction reactor which results from the large size (due to the
long residence of 20 min) and, to some extent, also from the less
operation hours when compared to PS.
300
high efciencies can be linked to two main reasons. First, the used
biomass fuel is broken down chemically to a much less extent as
when combusted. In the case of WP, no chemical reaction occurs
which basically conserves the chemical exergy. Second, the process
temperatures are much lower than for combustion which means
that less high temperature heat is converted to low-temperature
heat as it is the case in the boiler. This heat quality conversion
from high- to low-temperature naturally decreases the exergetic
efciency as it does decrease the Carnot efciency of the cycle.
This fact is also represented by the exergy destruction rates yD
and yDrel, which represent the exergy destruction in each unit
and relative to the whole process, respectively. For the CHP plant,
the evaporator and the superheater 2 which are both situated in
the combustion boiler show very high rates of exergy destruction.
In general, the units destruction rates yD, with the exemption of
the superheater 1 in the PS case, do not show signicant changes
which can be interpreted as a sign that the integration does not
hamper the plant operability. In the PS case the superheater 1
experiences heavily reduced mass ows which decrease the heat
exchanger efciency. The effect of the integration on the CHP
plants process parameters has been discussed in more detail in
previous work [1]. The relative exergy destruction yDrel for the different units is reduced slightly as a result of the additional (small)
exergy destruction within the additional equipment.
The specic fuel costs, cfuel, do not show large variations. The
same accounts for the specic product costs cproduct. For all integrated cases the specic cost for electricity increase somewhat,
but the specic cost for DH can be reduced by 7.7%, 4.9% and
4.5%, respectively. The obviously high prices for the product of
the feedwater treatment block can be related to the denition of
product and fuel in that unit as shown in Table A1. The product
is the increase in exergy which is achieved by pump work, steam
extraction and dryer condensate recovery of which the rst two
fuels have a high price. In addition the equipment cost (Z) is also
rather high for the small change in exergy that is achieved. The
overall product cost for the integrated cases are naturally lower
due to the high amount of exergy in the products which can also
be seen in the overall efciencies.
The values of the cost of exergy destruction, CD, do not differ
much among the different cases and are highest for the boiler
(evaporator and superheater 2) and the turbine. Compared to
those, the CD of the new equipment (I and K) appears moderate
and, regarding the value, reects inversely the exergetic efciency
of the upgrading processes. For the integration, the higher overall
cost of exergy destruction can be explained simply by the fact that
more fuel is handled in the plant and thus also more exergy is
destructed.
The factor r decribes the relative cost difference between fuel
and product. It also considers the equipment cost factor Z as well
as the exergetic efciency or destruction. According to the the F
and P rules, all cost resulting from required equipment and exergy
destruction are allocated to the product and increase its price.
This means that, for instance in the case of the evaporator all
exergy losses and the equipment cost are charged to the generated
steam which explains the high relative cost difference. Despite the
high equipment costs, the upgrading processes clearly benet from
the exergetic efciencies achieved.
The exergoeconomic factor f and describes the ratio of the
equipment cost (Z) to the cost of exergy destruction (CD) and loss
(CL). As a relative gure of merit it gives an indication whether it
is worth to optimise the unit for higher efciency at the detriment
of higher cost. High values indicate that a cheaper less efcient
component could be used in order to achieve lower total processing costs. Vice versa for low values the equipments efciency
should be improved at higher unit costs. Different equipment has
different optimal values as can be found for e.g. in Ref. [25].
CHP
WP
TWP
PS
1.54
1.27
3.48
48.7
6.30
178.57
31.26
22.9
70.8
1.54
1.46
4.51
63.1
1.04
0.99
3.51
49.2
13.05
173.67
28.35
57.66
21.6
79.6
122.3
1.54
1.49
4.49
62.9
2.24
1.54
3.44
48.1
14.73
184.36
29.30
73.25
20.9
80.6
116.4
1.54
1.55
4.66
65.2
1.38
1.28
3.27
45.7
13.68
178.22
29.39
70.55
22.3
82.8
103.2
32.60
137.00
89.30
3.13
6.33
9.46
3.16
1.26
29.0
32.60
137.00
89.30
72.30
2.96
7.11
8.84
18.90
5.85
3.72
22.4
32.60
137.00
89.30
62.40
2.86
7.20
7.26
17.32
2.59
0.43
21.7
32.60
137.00
89.30
95.70
3.05
7.40
9.88
20.32
6.64
4.42
One reason for that the higher price of WP might be that WP are
not a typical fuel for medium- to large sized biomass power plants
in Finland and Sweden. They usually use wood chips as a fuel,
which is much cheaper. WP are sold rather to small-scale applications and private customers that are subjected to higher prices.
Energy companies might be willing to pay a higher price if they
were compensated for instance by means of the European emission
trading system.
In summary, integration of WP and PS increase the yearly prot
by 85% and 110%, respectively. The protability calculated as the
ration of revenues to prot can be almost doubled for WP and
PS. The integration of TWP is found to not increase the prot due
to high investment costs and the low coal price. For the sake of
completeness, results are also presented for the case that the plant
owner would need to pay a transmission fee for construction and
maintenance of the DH network. A value of 30% of the DH turnover
has been assumed reasonable. However, transmissions losses have
been neglected. Then prots are certainly lower.
Regarding the price development it can be calculated that the
PS-integrated systems will provide the same prot as WP when
the average price over the investment period is assumed to be
88.06 /MW hch and is the same as for TWP if assumed to be
56.43 /MW hch. This corresponds with the PS price being 8% and
42% lower than projected. In turn, in order to make TWP competitive with, the cost of using coal as fuel (thereby considering the
actual fuel and the cost for the emission trading certicates) would
need to be as high 97.22 /MW hth, which is a 48% higher price
than projected in this work.
As could be observed, the results presented above are heavily
dependent on the price assumptions and hence the projected fuel
and product market prices have been varied independently by
50%. As a matter of fact also the TCI cost, especially for the
upgrading bear a high amount uncertainty and have been varied
as well. The results are presented in Fig. 6.
All cases show that the dependency on the electricity market
price is minor when compared to the variation of DH and
bio-product
prices,
respectively.
Prot
variations
are
301
302
160%
160%
120%
120%
80%
40%
0%
-40%
-80%
-120%
-160%
-50%
80%
40%
0%
-40%
-80%
-120%
-25%
0%
25%
-160%
-50%
50%
-25%
Price variation
Variation Power Price
Variation Feedstock Price
Variation DH Price
Variation Investment Cost
25%
50%
Variation DH Price
Variation Investment Cost
Variation WP Price
160%
160%
120%
120%
80%
40%
0%
-40%
-80%
80%
40%
0%
-40%
-80%
-120%
-120%
-160%
-50%
0%
Price variation
-25%
0%
25%
50%
-160%
-50%
-25%
Variation DH Price
Variation Investment Cost
0%
25%
50%
Price Variation
Price Variation
Variation TWP Price
Variation DH Price
Variation PS Price
Fig. 6. Inuence of investment cost and fuel and product market price on the plant prot.
4. Conclusions
An exergoeconomic analysis has been carried out for the integration of WP, TWP and PS with a CHP plant. The results are compared to the CHP stand-alone plant and among each other. The
integration causes the annual cost to rise considerably.
The highest investment is required for the TWP integration and
is mainly caused by the large reactor volume required due to the
long residence time of approximately 20 min. Results also show
that for all cases the gross electricity generation can be increased
by 1013% due to longer operation hours, but that the net power
output decreases by 2.68.7% due to the additionally installed
equipment.
The combustion process in the boiler and the ue gaswater
heat exchangers cause the highest rates of exergy destruction.
This can be attributed to the high rate of irreversible chemical
break-down in the combustion and also to the heat exchange from
hot ue gas to the moderate-tempered steam. Conversely, the integrated processes show very low rates of exergy destruction which
results in high exergetic efciencies. The total systems exergetic
efciencies show, compared to the stand-alone CHP plant, that
those can be improved substantially from 24% to 55%, 50% and
46% for WP, TWP and PS, respectively. This is well in line with
results gained by a primary energy efciency assessment carried
out previously [1].
In order to evaluate the economic feasibility of the systems
studied, future prices for fuel and products were projected based
on historical price data. The economic results reveal that the
investment and operation cost only provide a relatively small share
on the total annual production cost; i.e. all systems are fuel-cost
dominated. Based on the cost allocation based on the exergy content of the products it has been shown that electricity and TWP
303
x4 = 0.859
e_ 20 e_ 21 El:
x4 (e2 e15 e17 + e3)
e15 e16
(1 x4) (e2 e15 e17 + e3)
e19 e20
e8 e9 e13
e9 e12
El. + e13 + e23
e22 e23 + e21 e28 + e24 + El.
e17 e18a + El. + e25
e_ 2 e_ 1
e5 e4
e6 e5
e7 e6
e4 e14
El.
e11 e10
e14 e12
e25
e26 + e27
Table A2
Stand-alone CHP plant: annual Z-values, exergy- and cost uxes.
Stream data
Stream no.
1. Air ambient
2. Air boiler in
3. Biomass boiler in
4. Economiser water out
5. Steam evaporator out
6. Steam superheater 2 in
7. Live steam
8. Turbine exhaust
9. DH return water
10. DH supply water
11. Condensate out
12. Turbine bleed
13. Economiser water in
14. FG Superheater 1 in
15. FG Superheater 1 out
16. FG air pre-heater in
17. FG air pre-heater out
x3 = 0.8589
x2 = 0.8587
x1 = 0.8585
For TWP and PS, the losses due to re-mixing of stream 18 with the main ue gas ow has been accounted for in section K.
a
e_ 20 e_ 21 El:
x3 e_ 2 e_ 15 e_ 3
e15 e16
(1 x3) (e2 e15 + e3)
e16 e19
e8 e9 e13
e9 e12
El. + e13 + e23
e22 e23 + e21 e28 + e24 + El.
e17 e18a + El. + e25
e_ 17 e_ 18 El:
x2 e_ 2 e_ 15 e_ 3
e15 e16
(1 x2) (e2 e15 + e3)
e16 e17
e8 e9 e13
e9 e12
El. + e13 + e20
e19 e20 + e18 e24 + e21 + El.
El. + e22
A: Air pre-heating
B: EVA
C: SH 1
D: SH 2
E: ECO
F: Turbine
G: DH Exchanger
H: FWT
I: dryer
K: Upgrading
e_ 16 e_ 17 El:
x1 e_ 2 e_ 14 e_ 3
e14 e15
(1 x1) (e2 e14 + e3)
e15 e16
e7 e8 e12
e8 e11
El. + e12
e_ 2 e_ 1
e_ 5 e_ 4
e6 e5
e7 e6
e4 e13
El.
e10 e9
e13 e11
e_ 2 e_ 1
e_ 5 e_ 4
e6 e5
e7 e6
e4 e14
El.
e11 e10
e14 e12
e22
e23
e_ 2 e_ 1
e_ 5 e_ 4
e6 e5
e7 e6
e4 e14
El.
e11 e10
e14 e12
e25
e26 + e27
P
PS
F
P
F
P
TWP
WP
F
P
F
CHP
Flowsheet section
Table A1
Denition of fuel (F) and product (P) according to (Lazzareto) for the process units. Please refer to Figs. 14. e_ i denotes the exergy ux of the stream i and El. stands for power. The variable xi describes the amount of the combustion heat
transferred in the boiler that is utilised for evaporation. The remaining heat is used for superheating (1 xi).
186.71
730.67
177.77
119.61
292.53
340.89
583.55
251.51
132.84
2816.08
Operation time
(h)
Exergy ux
(GW h/y)
Cost ux
(/h)
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
5088
0.37
10.28
138.83
9.71
33.81
40.67
45.82
17.09
10.62
23.88
1.40
0.31
1.90
50.90
39.62
22.95
9.51
151.42
720.48
229.01
865.61
955.16
1071.35
397.71
414.87
32.28
7.18
73.98
297.66
231.62
134.08
55.61
Table A3
CHP plant integrated with WP production: annual Z-values, exergy- and cost uxes.
Z-values/annual equipment cost (k)
Biomass pre-treatment
Evaporator
Superheater 2
Superheater 1
Economiser
Air pre-heater
Turbine
DH exchanger
FW treatment
Dryer
Pelletising
Annual plant operation cost
Stream data
Stream no.
1. Air ambient
2. Air boiler in
3. Biomass boiler in
4. Economiser water out
5. Steam evaporator out
6. Steam superheater 2 in
7. Live steam
8. Steam turbine in
9. Turbine exhaust
10. DH return water
11. DH supply water
12. Condensate out
13. Turbine bleed
14. Economiser water in
198.97
778.65
189.44
127.46
311.74
363.27
621.86
268.03
141.56
1239.19
793.46
2033.36
Operation time
(h)
Exergy ux
(GW h/y)
Cost ux
(/h)
6384
6384
6384
6384
6384
6384
6384
6384
6384
6384
6384
6384
6384
6384
0.30
13.50
179.82
12.88
44.20
53.10
59.71
50.82
18.92
10.88
25.31
1.55
0.19
2.69
143.48
737.07
221.24
841.42
927.48
1039.13
877.07
325.55
341.02
26.51
3.15
74.88
304
Table A3 (continued)
Stream data
Stream no.
15. FG Superheater 1 in
16. FG superheater 1 out
17. FG economiser out
18. FG air pre-heater out
18a. FG dryer in
18b. FG to stack at full load
19. Steam dryer in
20. Dryer condensate
20a. Time domain 1
21. Biomass dryer in
22. Biomass WP in
23. Wood pellets
24. FG out wet
24a. Dryer dry fg out
24b. Dryer wet fg Out
Table A5
CHP plant integrated with PS production: annual Z-values, exergy- and cost uxes.
Operation time
(h)
Exergy ux
(GW h/y)
Cost ux
(/h)
6384
6384
6384
6384
3944
6384
3944
3944
6384
3944
3944
3944
6384
3944
3944
65.94
51.44
30.04
12.37
6.81
5.56
8.89
0.78
0.78
140.16
139.78
139.78
11.90
6.33
8.81
300.35
234.26
136.74
56.34
50.50
65.78
262.33
22.97
14.19
890.60
1477.42
1750.06
103.32
65.35
46.98
Table A4
CHP plant integrated with TWP production: annual Z-values, exergy- and cost uxes.
Z-values/annual equipment cost (k)
Biomass pre-treatment
Evaporator
Superheater 2
Superheater 1
Economiser
Air pre-heater
Turbine
DH exchanger
FW treatment
Dryer
Torrefaction
Annual plant operation cost
Stream data
Stream no.
1. Air ambient
2. Air boiler in
3. Biomass boiler in
4. Economiser water out
5. Steam evaporator out
6. Steam superheater 2 in
7. Live steam
8. Steam turbine in
9. Turbine exhaust
10. DH return water
11. DH supply water
12. Condensate out
13. Turbine bleed
14. Economiser water in
15. FG superheater 1 in
16. FG superheater 1 out
17. FG torrefaction in
18. FG torrefaction out
19. FG economiser out
20. FG air pre-heater in
21. FG air pre-heater out
21a. FG dryer in
21b. FG to stack at full load
22. Steam dryer in
23. Dryer condensate
23a. Time domain 1
24. Biomass dryer in
25. Biomass torrefaction in
26. Torreed wood pellets
27. Torrefaction gas
28. FG out wet
28a. Dryer dry FG out
28b. Dryer wet FG out
200.79
785.75
191.17
128.62
314.58
366.59
627.53
270.47
142.85
1045.36
2729.30
6803.02
Operation
time (h)
Exergy ux
(GW h/y)
Cost ux
(/h)
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
6576
4136
4136
6576
6576
6576
4136
2440
4136
4136
6576
4136
4136
4136
4136
6576
4136
4136
0.27
11.85
187.32
13.31
44.50
53.80
60.32
51.45
19.14
11.74
25.43
1.51
0.19
2.70
68.69
53.67
8.10
4.43
31.41
27.74
12.29
6.73
5.56
8.87
0.77
0.77
137.22
136.88
129.40
7.69
14.72
6.81
9.16
132.70
789.30
225.77
863.91
953.19
1067.44
895.62
331.15
346.41
25.87
3.16
74.73
318.17
248.45
62.70
34.35
145.24
127.41
56.74
51.51
65.61
273.19
23.68
14.89
831.42
1361.04
2020.35
120.04
57.14
52.15
38.73
205.10
802.63
195.27
131.39
321.34
374.46
641.01
276.28
145.92
1093.79
1570.38
5757.58
Operation time
(h)
Exergy ux
(GW h/y)
Cost ux
(/h)
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
7032
4592
7032
4592
7032
7032
7032
4592
2440
0.29
13.30
201.91
12.36
46.32
52.67
61.23
52.46
19.53
10.89
25.72
1.54
0.20
2.75
54.37
41.34
19.63
19.63
9.21
50.55
30.77
13.37
7.81
5.56
134.10
797.86
203.63
842.92
917.48
1031.44
864.38
319.20
333.68
24.81
3.05
72.73
231.39
175.52
136.65
89.23
65.18
218.08
132.87
57.97
54.08
65.29
4592
4592
7032
4592
4592
4592
4592
7032
4592
4592
8.77
0.79
0.79
130.41
130.06
115.76
12.20
14.57
7.72
9.00
255.83
23.05
15.05
711.73
1250.85
1544.92
162.79
57.61
53.53
45.90
Appendix B
In the following Tables A2A5, the Z-values, the exergy uxes
and cost uxes that form the input to exergy and
exergy-economic analysis are presented. It is important to understand that the units analysed differ in their operation time. The
power plant equipment is in operation during the whole operation
time (time domain 1) whereas the dryer and upgrading equipment
(sections I and K in Figs. 14) is only in operation when the CHP
plant does not supply the full DH load of 16.5 MW (time domain
2). Depending on the time domain the denominator for the cost ux
operation varies and thus the nominal values. For instance, in all
integrated cases the ue gas leaving the air-preheater during full
load operation is by-passed to the stack, whereas in part load operation those are led through the dryer as carrying and heating medium. In order to formulate the cost balances the time domain needs
to be considered accordingly. For the sake of visual clarity, the
by-pass of the dryer has not been illustrated in Figs. 14. For the
dryer efciency calculation the enthalpy difference of the dry ue
gas has been considered and hence those values are given as well.
References
[1] Kohl T, Laukkanen T, Jrvinen M, Fogelholm CJ. Energetic and environmental
performance of three biomass upgrading processes integrated with a CHP
plant. Appl Energy 2013;107:12434.
[2] Batidzirai B, Mignot APR, Schakel WB, Junginger HM, Faaij APC. Biomass
torrefaction technology: Techno-economic status and future prospects. Energy
2013;62:196214.
[3] van der Stelt MJC, Gerhauser H, Kiel JHA, Ptasinski KJ. Biomass upgrading by
torrefaction for the production of biofuels: a review. Biomass Bioenergy
2011;35:374862.
[4] Adams PWR, Shirley JEJ, McManus MC. Comparative cradle-to-gate life cycle
assessment of wood pellet production with torrefaction. Appl Energy
2015;135:36780.
[5] Starfelt F, Aparicio ET, Li H, Dotzauer E. Integration of torrefaction in CHP
plants a case study. Energy Convers Manage 2015;90:42735.
[6] Peters JF, Petrakopoulou F, Dufour J. Exergetic analysis of a fast pyrolysis
process for bio-oil prodcution. Fuel Proc Technol 2014;119:24555.
[7] Boateng AA, Mullen CA, Osgood-Jacobs L, Carlson P, Macken N. Mass balance,
energy, and exergy analysis of bio-oil production by fast pyrolysis. J Energy Res
Technol 2012;134(4):19.
[8] Rogers JG, Brammer JG. Estimation of the production cost of fast pyrolysis biooil. Biomass Bioenergy 2012;36:20817.
[9] Fortums Bio-oil plant commissioned in Joensuu - rst of its kind in the world;
2013. <http://www.fortum.com/en/mediaroom/pages/fortums-bio-oil-plantcommissioned-in-joensuu-rst-of-its-kind-in-the-world.aspx>
[Cited
01.30.2015].
[10] Grling M, Larsson M, Alvfors P. Bio-methane via fast pyrolysis of biomass.
Appl Energy 2013;112:4407.
[11] Djuric Ilic D, Dotzauer E, Trygg L, Broman G. Integration of biofuel production
into district heating Part I: An evaluation of biofuel production costs using
four types of biofuel production plants as case studies. J Cleaner Prod
2014;69:17487.
[12] Truong NL, Gustavsson L. Cost and primary energy efciency of small-scale
district heating systems. Appl Energy 2014;130:41927.
[13] Sartor K, Quoilin S, Dewallef P. Simulation and optimization of a CHP biomass
plant and district heating network. Appl Energy 2014;130:47483.
305