Professional Documents
Culture Documents
No. 10-1375
Appeal from the United States District Court for the Eastern
District of Virginia, at Alexandria.
Anthony J. Trenga,
District Judge. (1:09-cv-00861-AJT-TCB)
Argued:
Decided:
PER CURIAM:
This appeal concerns an action brought by a subcontractor
against a surety under the Miller Act (the Act), 40 U.S.C.
3131 through -3134.
payment
bond
for
the
protection
of
all
persons
40 U.S.C. 3131(b)(2).
contractor
subcontractors work.
within
90
days
of
40 U.S.C. 3133(b)(1).
completing
the
I.
We review the facts in the light most favorable to Aarow,
the non-moving party in the district court.
Hooven-Lewis v.
In 2007, Syska
prime
contract)
by
the
United
2
States
government
(the
Army
project).
National
Guard
at
Fort
Belvoir,
Virginia
(the
awarded
Aarow
Equipment
&
Services,
Inc.
(Aarow)
subcontract, which set forth the work that Aarow was required
to perform on the project.
Section 11.1 of the subcontract stated that Syska may make
changes in the [w]ork covered by this [s]ubcontract, and that
any
changes
must
be
made
in
writing.
The
subcontract
also
to
the
subcontract,
any
such
change
in
price
or
work
described
in
the
subcontract
included
several
plan
standard[s].
erosion
plan
Aarow
was
Aarow
ceased
drawings,
implementing
working
which
was
until
required
not
it
the
up
to
received
new
construction
of
In September 2007,
not issue a change order for the pond work at that time.
Aarow completed the pond work, with the understanding that Syska
would issue a change order at some point in the future.
Upon
Syskas
determination
that
the
pond
work
was
not
months
later,
neither
invoice
to
Syska
for
the
modification
nor
pond
work.
Syska
Aarow to list the pond work under a line item designated for
certain finishing work on the project that had not yet been
completed. 3
to
the
government
identifying
$484,980,
which
included
the
the
pond
work
as
invoice
in
the
amount
of
pond work.
modification
and
issued
change
order,
Aarow
could
reallocate the funds received for the pond work to the proper
line
item.
Shortly
after
the
government
paid
Syska
the
Accordingly, the
the
response,
funds
Syska
previously
withheld
paid
payment
for
from
the
pond
work.
In
Aarow
for
other
work
Aarow under the terms of the demand, Aarow ceased work on the
project.
On July 17, 2009, Syska sent Aarow a letter notifying Aarow
that
failing
to
In
that
it
was
letter,
in
default
Syska
of
the
instructed
subcontract
Aarow
to
for
correct
and
complete
On
July 23, 2009, Syska sent another letter to Aarow stating that
because Aarow had not cured the defaults, Syska was terminating
the subcontract as provided in Section 12.1 of that agreement.
Section 12.1 of the subcontract stated, in relevant part:
If, in the opinion of [Syska], [Aarow] shall at any
time . . . fail in any respect to prosecute the Work
according to the current schedule. . . then, after
serving three (3) days written notice, unless the
condition specified in such notice shall have been
eliminated within such three (3) days, [Syska] may at
its option . . . terminate the Subcontract for default
. . . . [Aarow] shall not be entitled to receive any
further payment until the Work shall be fully
completed and accepted by [the government].
Under
Section
12.2
of
the
subcontract,
however,
if
Syska
Aarow
payment
monthly,
from
the
provided
that
government.
Syska
This
already
had
pay-when-paid
received
provision
to
pay
Aarow
series
briefs
addressing
numerous
issues.
In
Travelers first
maintained
pay-when-paid
that
because
the
terms
of
the
pay
Syska
for
several
months,
Syska
did
not
breach
its
Travelers
Travelers
argued
alternatively
that
even
if
Syska
than Aarow was due under the subcontract and, therefore, Aarow
was not entitled to additional payment.
Two months after the hearing, but before the district court
entered its judgment, Travelers requested leave to supplement
its motion for summary judgment to discuss a new decision issued
by this Court.
his
performance
may
not
take
advantage
of
that
to
the
prime
contract,
and
by
its
failure
to
weeks
later,
summary
the
judgment
district
in
favor
court
of
entered
Travelers.
an
order
In
its
for
[w]ork
several
stoppage
months,
based
on
Aarow
was
Syskas
unable
to
failure
to
justify
pay
its
Aarow.
in this court.
II.
We review the district courts award of summary judgment de
novo.
as
Anderson
v.
Liberty
(construing
matter
former
of
law.
Lobby,
Rule
Fed.
Inc.,
56(c)
R.
477
of
the
Civ.
U.S.
P.
242,
Federal
56(a);
247
Rules
see
(1986)
of
Civil
Procedure).
A.
Aarow argues on appeal that the district court erred in
failing to apply the prevention doctrine in determining whether
Travelers was entitled to judgment as a matter of law.
Aarow
make
the
requested
payment
under
the
prime
contract.
response,
granted
Travelers
summary
argues
judgment
that
in
its
the
district
favor.
court
Initially,
asserted
timely
and
should
not
be
considered
in
the
Syska
to
withhold
the
11
requested
payment
to
Aarow.
Travelers
therefore
Travelers
did
not
maintains
owe
any
that,
payment
as
to
matter
of
law,
under
the
bond
Aarow
wrongfully
abandoned
the
project.
We
disagree
with
Travelers arguments.
We find no merit in Travelers assertion that Aarow failed
to preserve its prevention doctrine argument in the district
court.
the
first
time
in
later-filed
supplemental
pleading,
the
in
the
judgment.
record
three
Furthermore,
weeks
in
before
the
Aarows
court
initial
rendered
brief
its
opposing
summary judgment, Aarow set forth the factual predicate for its
prevention doctrine argument by asserting that Syska directed
Aarow to complete the pond work before issuing a change order
for that work, and that Syska acted in bad faith by attempting
to back charge Aarow for the pond work.
that
Aarows
adequately
to
prevention
the
district
doctrine
court
Thus, we conclude
argument
and
was
was
not,
as
presented
Travelers
See Evans v.
Metro. Life Ins. Co., 358 F.3d 307, 310 n.2 (4th Cir. 2004)
(explaining that although appellants argument was not raised in
district court until oral argument on the motion for summary
judgment, the argument was preserved for appellate review).
12
B.
We turn to examine the present record to determine whether
Travelers was entitled to judgment as a matter of law at the
summary judgment stage of the proceedings.
argument
before
the
district
court,
Based on Aarows
we
give
particular
In Moore Brothers, we
subcontractors
general
contractor
seeking
asserted
payment
as
There, in response to
for
completed
defense
the
work,
the
pay-when-paid
Id. at 724-25.
the
general
contractor
materially
contributed
to
the
Id. at 725-26.
the
was
its
general
contractor
liable
13
to
subcontractors
for
payment
notwithstanding
subcontract.
Brothers
Id.
to
reasonably
at
the
725.
pay-when-paid
Applying
our
the
present
case,
we
could
find
that
Syskas
provision
analysis
consider
in
whether
actions
in
the
Moore
jury
materially
condition
in
the
subcontract
in
defense
of
deposition
president
in
testimony
charge
of
of
Robert
F.
construction,
Geremia,
who
Syskas
stated
that
vice
the
however,
asserts
that
Syskas
actions
materially
Aarow
points
to
evidence
in
the
record
that
Syska
directed Aarow to perform the pond work even though Syska had
not issued a change order or received a modification to the
prime contract.
completed
the
work,
relying
14
on
Syskas
promise
that
change
order,
Syska
Aarow
to
remove
its
on
these
facts,
jury
reasonably
could
return
Aarow
to
perform
the
pond
work
before
issuing
the
subcontract,
governments
later
Syska.
Syskas
If
materially
decision
to
actions
contributed
withhold
certain
materially
to
payments
contributed
to
the
to
the
to
subcontract.
provision
pay
of
Aarow
the
for
subcontract
its
work
to
excuse
performed
Syskas
under
the
government
instructed
billing procedure.
of
any
Syska
to
employ
the
questionable
responsibility
for
the
arguably
improper
billing
The
raises
credibility
issues
and
other
issues
of
fact
that
are
in
these
reasons,
granting
we
conclude
that
summary
judgment
in
the
favor
district
of
court
Travelers.
16