Professional Documents
Culture Documents
PUNJAB
The Punjab State Electricity Board was constituted as an integrated
power utility under the Electricity (Supply) Act 1948. It continued
discharging the generation, transmission and distribution functions up to
April 2010. The government of Punjab was required to unbundle the Punjab
State Electricity Board (PSEB) under the provisions of the Electricity Act
2003.
Box 2: Milestone in Power Sector Reforms in Punjab State
Sr. No
1
2
3
4
5
6
7
8
9
Key Development
The Punjab State Electricity Board (PSEB) was a statutory body formed
Re-organization of the erstwhile State of Punjab under the Punjab Reorganization Act 1966
PSERC was constituted under the provisions of Electricity Regulatory
Commissions Act,1998
MoU on power sector reforms signed between Ministry of Power, Govt of
India and Govt of Punjab
The Commission passed its first (tetail) tariff order on the proposal of PSEB
Submission of the Report of the Expert Group on Power Sector Reforms in
Punjab (Gajendra Haldea Report)
These Regulations may be called the Punjab State Electricity Regulatory
Commission (Conduct of Business) Regulations, 2005
Punjab State Electricity Regulatory Commission (Forum and Ombudsman)
Regulations, 2005.
Unbundling of Punjab State Electricity Board (PSEB)
PSPCL has filed its first ARR Petition for FY 2011-12
Date
Feb 01, 1959
May 01, 1967
March 3, 1999
March 30, 2001
Sept 6, 2002
March 06, 2003
March 07, 2005
August 17, 2005
April 16, 2010
Nov 30, 2010
Reforms and Transfer Scheme, 2010 and has notified two successor entities
of the erstwhile PSEB. The Punjab State Power Corporation Limited
(PSPCL) is one of the successor entities and is entrusted with the functions
of generation, distribution, wheeling and retail supply of electricity in the
state. The other successor entity, the Punjab State Transmission Corporation
Limited (PSTCL) is assigned with the functions of transmission of
electricity in the State, including functions of State Load Dispatch Centre
(SLDC).
The Punjab State Electricity Regulatory Commission (PSERC) was
established on 31.3.1999 under the Electricity Regulatory Commissions Act,
1998, a Central Act which was superseded by the Electricity Act, 2003. The
Commission is assigned various functions, such as determination of tariff for
generation, transmission and wheeling of electricity, supply to wholesale,
bulk or retail consumers etc. under Section 86 of the Act. Other major
functions of the Commission include regulating electricity purchase and
procurement process of Distribution Licensees; issue Licenses for
Transmission, Distribution and Trading of electricity and promote
generation /co-generation of electricity from renewable sources of energy. It
has also advisory role to make suggestions to the State Government on key
issues such as promotion of competition, efficiency and economy in
activities of the electricity supply system; promotion of investment and restructuring of electricity supply industry in the state.
Therefore, one of the major functions of the PSERC is to make a
balance between the interests of consumers and utilities promoting economic
efficiency in the sector. Like other Electricity Regulatory Commissions of
the country, PSERC has adopted Rate of Return (RoR) approach for the
regulation of power sector business in the state.
Under the RoR approach, the regulated utility is required to make exante proposals of the revenue requirement and get it approved from the
regulator on periodical basis. Ideally, there should be no significant
difference between the targets approved by the Commission and actual
achievements by the utilities. However, this was not a reality in the case of
Punjab. Many times, there were significant differences observed between the
actual performance of PSEB and the targets fixed by the Commission. The
Commission had to initiate true-up exercises to make adjustments between
the approved amounts and actual performance for various expenses, at later
dates when more reliable data was available.
With this background, this chapter targets to analyse the physical and
financial performance in the light of regulatory observations made by
PSERC during the last ten years. It may be noted that reform process was
initiated with formation of the regulatory commission in 1999. However, the
generation, transmission and distribution functions continued to be vested in
the Punjab State Electricity Board, a single entity. The PSEB was
reorganized quite recently on 16.04.2010 in to two separate companies, one
for generation and distribution functions and the other for transmission and
load dispatch centre which was a statutory requirement. Therefore, Panjab
study is an exercise in examining the changes in performance of the PSEB,
if any under the direction of the regulatory commission (PSERC) during the
last 10 years i.e. from 2001-02 to 2009-10. In Section I, we examine the
physical and financial performance of the utility taking into consideration
some performance parameters such as plant load factor, energy losses,
the demand
Energy
Peak Demand
Available
Demand
Deficit
Demand
Demand
Deficit (%)
(MU)
(MU)
(%)
Met (MW)
(MW)
27577
28780
4.2
4936
5420
8.9
2001-02
28313
30082
5.9
5455
5849
6.7
2002-03
30520
31420
2.9
5622
5922
5.1
2003-04
30383
33393
9.0
5559
7122
21.9
2004-05
32591
35682
8.7
6158
7731
20.3
2005-06
34839
38641
9.8
6558
8971
26.9
2006-07
38795
42372
8.4
7340
8672
15.4
2007-08
37238
41635
10.6
7309
8690
15.9
2008-09
39408
45731
13.8
7407
9786
24.3
2009-10
Source: Central Electricity Authority, Monthly Reports (various issues)
It is shown in the Table 3.1 that over time since 2001-02, the gap
between demand and supply has widened over time. In 2001-02, the energy
and peak demand deficits were reported as 4.2% and 8.9 % which increased
to 13.4% and 24.3% respectively in 2009-10. The widening of gap is due to
failure in adding the planned generation capacity at the state as well central
levels. Another important reason is the faster increasing demand for
electricity across various sectors. In the FY 2009-10, the reported energy as
well as peak shortages were the highest, i. e. 13.8% and 24.3% respectively.
Table 3.2: Thermal-Hydro Mix in Installed Capacity Owned by the
State
Source (Fuel Type)
1990-91
1998-99
Thermal
1280 (42)
2130 (54)
Hydro
1769 (58)
1799 (46)
Total State Capacity
3049 (100)
3929 (100)
Source: Central Electricity Authority, Monthly Reports (various issues)
(Capacity (MW)
2010-11
2620 (70)
1142 30)
3762 (100)
01.50
01.00
00.80
00.80
999.00
1.50
1.00
0.80
0.80
999.00
1260.00
440.00
420.00
10.00
2130.00
3129.00
24484.15
1260.00
440.00
420.00
10.00
2130.00
3129.00
6284.07
However, over time, the relative share of thermal power has increased
rapidly. The relative share of thermal power in the total owned capacity has
increased from 42% in 1990-91 to 70% in 2010-11 (Table 3.2). The detailed
break up of sources of power and the total installed capacity dedicated to the
state as on 31.03.2010 is presented in the Table 3.3.
The Commission has approved the estimates of available power in the
state taking into consideration various performance parameters such as Plant
Load Factor (PLF) and auxiliary consumption of thermal power stations etc.
Table 3.4: Power Generation from Hydro and Thermal Sources
(Million
Units)
Thermal
Year
Generation
Hydro
Moving* Average
Generation
Total
Moving
Average
Generation
Moving*
Average
1990-91
5939
8679
14618
1991-92
5934
8742
14677
1992-93
7105
8613
15718
1993-94
8854
7468
16322
1994-95
8439
7254
8736
8448
17175
15702
1995-96
8232
7713
8667
8445
16899
16158
1996-97
9778
8482
8677
8432
18455
16914
1997-98
10274
9115
7626
8235
17900
17350
1998-99
10914
9527
9966
8734
20880
18262
1999-00
13831
10606
8732
8734
22563
19339
2000-01
14457
11851
7977
8596
22434
20446
2001-02
14669
12829
8334
8527
23003
21356
2002-03
13650
13504
8691
8740
22341
22244
2003-04
14236
14169
9812
8709
24048
22878
2004-05
14384
14279
7293
8421
21678
22701
2005-06
14834
14355
10414
8909
25248
23264
2006-07
15435
14508
8673
8977
24107
23484
2007-08
16457
15069
9044
9047
25501
24116
2008-09
18066
15835
8785
8842
26851
* Moving 5 year average Source: Centre for Monitoring of India Economy (CMIE) and Power Finance
Corporation Report, 2010
24677
Sr. No
Station
Energy Available
1.
Thermal Station
18128
2.
Hydel Stations
3902
3.
BBMB
4349
4. =2+3
Total Hydro
8251
5. =1+4
Total own Availability
26379
6.
Outside purchase
17595
7.
Total Available in the state
43974
Source: Tariff Order issued by PSERC for the FY 2010-11
The Table 3.5 brings out that thermal power plants are the major
source of electricity supply in the state. The share of hydropower including
the energy received from BBMB sources will be 19% of the total power
generated. The commission has also approved 17595 MU to be purchased
from Central Power Undertakings such as NTPC, NHPC etc. Therefore,
about 40% of the total power is outsourced from out of the state power
stations.
As per provisions of the Electricity Act 2003, the tariff rates of power
supply from CPUs and BBMB are to be approved by the CERC. As the
choice of source of supply is limited, the PSERC has effectively little control
over the cost of power purchase from the outside sources. However, through
efficient purchase and demand side management, the utility can reduce the
power purchase bill from outside sources. This important issue is yet to
receive due attention from the utility as well as the commission.
It has been noted that the rates of power purchased from Central as
well as shared utilities are determined by CERC while the state commission
has discretion to fix the rates for the stations owned by PSEB. Since, the
generation business in Punjab is still associated with distribution and retail
supply business; it may not be possible to compare the internal power
generation cost of PSEB with the other sources available to state. However,
taking some performance parameters into account, one can examine the
2008-09
85
2009-10
88
Source: Central Electricity Authority, and the Planning Commission Reports
NA
The plant wise PLF is given in the Table 3.7. It may be noted over
time, except for GNDTP, Bhatinda, other thermal power stations have
shown significant improvement in their performance.
Table 3.7: Plan Load Factor Across Various Power Plants in the State
(in %age)
Years
GNDTP, Bhatinda
GGSSTP, Ropar
1997-98
65.11
70.34
1998-99
66.70
70.01
1999-00
68.79
74.11
2000-01
72.49
76.44
2001-02
71.70
80.20
2004-05
51.69
82.28
2005-06
57.84
84.52
2006-07
56.8
88.52
2007-08
77.83
88.54
2008-09
73.83
87.07
2009-10
70.66
91.11
Source: Basic Statistics issued by PSERC
3.I.2:
Overall
69.10
69.40
74.70
77.90
79.20
77.5
79.9
83.1
87.65
85.48
88.43
Description
1980-81
1997-98
2008-09
Domestic
Commercial
Industrial
Agricultural
148.50
(68.37)
276.33
(127.22)
241.75
(111.30)
FS
380.78
(91.88)
491.00
(118.48)
430.19
(103.80)
FS
Others
32.70
(89.69)
51.8
(142.07)
25.44
(69.78)
20.40
(55.95)
15.50
(42.51)
23.29
(63.87)
36.46
236.60
(108.93)
147.79
(68.04)
217.20
453.34
(109.48)
405.28
(97.79)
414.43
8.94
9.16
10.35
5.36
8.36
14.16
5.38
10.63
17.39
4.77
12.26
11.48
9.60
10.74
Average Revenue
from sale with state
7
11.07
6.05
9.07
Average cost of
supply
Note: (i) FS- Free Supply (ii) Figures in brackets are the average revenue as a percentage of average cost of
electricity supply in a particular year. Sources: (i) Planning Commission, Annual Report on the working
of State Electricity Boards and ED, 1994,1997, and 2002 (ii) Statistical Abstract of Punjab, 2001-02.
(iii) PSERC: Tariff Orders for various financial years.
PSEB shows that there was discrimination in price being charged from various
categories of consumers regardless of cost of supply. The rationale provided for
subsidised supply to agriculture as well as domestic sectors has been to
promote social welfare of the peoples. But in actual practice, there has been
significant intra- category variations regarding their capacity to bear the cost.
In this regard, some independent studies (Ghose, 1998; Garg & Jain, 1998;
GOI, 2000 and World Bank 2001) depicted that most of the benefits of the
subsidies were being cornered by the big farmers, particularly in agricultural
sector. This implies that tariff rates do not have any systematic relationship
with the cost of supply. Mainly political considerations appear to have played a
dominant role in tariff setting. Obviously, State Governments compelled the
SEBs to follow certain pricing policy but abdicated from their responsibility to
compensate the SEBs keeping them in a perpetual financial crisis (Surinder
Kumar, 1999). This requires a reconsideration of the relationship between
electricity undertakings and the state governments on the one side and the
rationale for a pricing policy and subsidisation of certain consumers on the
other.
The analysis of financial loss or surplus from the sale of electricity to
various categories has been presented in Table 3.10.
(Rs. in Crore)
S. No.
Description
1980-81
1997-98
2008-09
ACGR
1980-81
To
1997-98
ACGR
1997-98
to
2008-09
ACGR
1980-81
to
2008-09
Domestic
-1.87
-231.38
-314.19
32.77
2.82
18.66
Commercial
+2.14
+42.46
+150.61
19.22
12.20
16.41
Industrial
-17.78
+176.98
+174.08
-0.15
Agricultural
-29.71
-1314.06
-2014.50
24.97
3.96
16.25
Others
-2.86
+9.87
+29.59
10.50
Total
-55.80
-1239.25
-264.03
20.01
-13.11
5.71
Source (i) Computed from the data collected from Annual Report on the Working of State Electricity
Boards and EDs, 1994, 2002. (ii) Statistical Abstract of Punjab, 2001-02. (iii) PSERC: Tariff
Orders for various financial years
The Table 3.10 reveals that revenue loss due to subsidised power supply
in 1980-81 was Rs. 55.80 crores and it increased to Rs. 1239.25 crores in 199798. During the year 2008-09 it was reduced to Rs. 264.03 crores. The reduction
in revenue loss is due to subvention paid by the state government on account of
free power to agriculture sector. It needs to be noted that subsidy per unit of
supply for domestic consumers increased from 3.76 paise per unit in 1980-81 to
68.70 paise in 1997-98. It reduced to 54.87 paise per unit in the year 2008-09.
Hence, total quantum of subsidy to domestic consumers has increased from Rs.
1.87 crores in 1980-81 to Rs. 231.38 crores in 1997-98 and further to Rs.
314.19 crores in 2008-09 mainly due to significant increment in electricity
consumption by the concerned category of consumers. Average revenue
realised from commercial consumers was higher than the average cost of
supply, so there was surplus. Per unit surplus increased from 15.34 paise to
59.13 paise during the period 1980-81 to 1997-98. It was recorded as 86.34
paise per unit in 2008-09. Therefore, the total quantum of the surplus has
increased from Rs. 2.14 crores to Rs. 42.46 crores and to Rs 150.61 crores
during the same period. It is pertinent to note that commercial consumers were
never subsidised and this category always contributed to the surplus to PSEB.
As far as industrial consumers were concerned, the comparison between
average revenue realised and average cost of supply shows that since after
1990-91, this category was also being overcharged and consequently
contributed surplus to the Boards revenue. Per unit revenue gap between cost
of supply and revenue realised has been recorded as -11.02 paise in 1980-81
and 24.55 paise in 1997-98. During the year 2008-09 it turned out to be 33.17
paise per unit. Subsequently, the total quantum of surplus has increased from
Rs.-17.78 crores to Rs.176.98 crores during the period 1980-81 to 1997-98. It
was calculated to be Rs. 174.08 crores in 2008-09. The analysis of the financial
performance of agricultural consumers presented a very interesting picture.
The pricing policy for the agricultural sector in Punjab consists of two types of
tariff and consumers could opt for any one of these. One system was a flat rate
system, which was levied according to the horsepower rating of the sanctioned
load of the motor used by the tube wells per month. The other was metered
supply where tariff was charged per unit of electricity consumed. The average
revenue did not keep pace with the increase in the cost of supply over the
period under consideration. Thus, total quantum of subsidy to this category
increased from Rs.29.71 crores in 1980-81 to Rs.1314 crores in 1997-98 and
further to Rs. 2014 crores in 2008-09. Being very low recovery rate of the cost
of supply through the revenue realised and significant amount of electricity sale
to this category, the quantum of subsidy kept on increasing consistently during
the period under consideration. Further, the Table 3.10 depicts that in case of
the category of other consumers (bulk supply & public lighting etc.) it was
noted that since after 1990-91 this category was also contributing to the surplus
of the Board. The total quantum of surplus from this category has been
recorded as Rs. 29.71 crores in 2008-09 as against to Rs. 2.86 crores in 198081 and Rs.9.87 crores in 1997-98.
It is clear from the above analysis that there were elements of
subsidisation and cross subsidisation in the tariff structure without any rational
justification. This implies that tariff rates do not have any systematic
relationship with the cost of supply and mainly political considerations appear
to have played a dominant role in tariff setting.
On basis of the analysis of technical as well as financial performance of
the Board it may be highlighted that the PSEB has played an important role in
creating an extensive network of electricity supply in the state. However, lower
level of operational efficiencies coupled with an irrational tariff structure has
led to increasing losses taking it to the verge of bankruptcy. It is in this
background that reform measures were initiated. Thus it may be concluded that
the reforms in Power Sector of Punjab did not lead to any significant
improvement in technical as well as financial performance of PSEB.
3. II. 1: Collection Efficiency
The collection efficiency in Punjab has increased in the recent year
(Table 3.11). It may be noted that 100% collection efficiency does not mean
that no dues is pending towards consumers. It simply represents the
collection in the relevant year. The collection may be the deferred amounts
pending towards consumers in past.
Table 3.11: Collection Efficiency in Punjab
Year
2004-05
2005-06
2006-07
2007-08
Collection efficiency
99.61
98.01
97.66
100.44
93.63
2008-09
Source: PFC Report for the respective years
Punjab
24
26
25
19
19
(FY 2011-12)
Source
Total Cost (Rs. Million)
21677.1
NTPC
4548
NHPC
2127
NPC
10073
Short-term Purchase
57512
Overall
Source: Tariff order issued by PSERC for FY 2011-12
Cost (Rs./Unit)
2.75
1.76
2.66
4.85
3.11
(Rs.
Million)
Sr. No
Particular
1.
Salary
Projections
and
other
2231
Approval
1504
Percentage
approval
of
52%
total
expenses
1139
Terminal and Pension
Benefits
3.
-Arrears
4.
3370
Total Expenses
Source: Tariff order issued by PSERC for FY 2011-12
2.
1169
40%
245
2917
8%
100%
The Graph 3.1 highlights that employee cost per unit of sale of energy
was almost stable for the period from 2004-055 to 2008-09. The Employee
cost was reported to be Rs. 0.5 per unit of sale in 2004-05. Afterwards, there
was little decrease in the cost for the next two years and it was reported as
0.55 in the FY 2008-09. It implies that there was no significant change in the
per unit employee cost. One important reason for little increase in the
employee cost was the ban on new recruitments. PSERC had pointed out
that the PSEB has enough manpower and it should improve the labor
productivity before making any fresh appointment in the Board.
3. III.2: Repair and Maintenance cost
The PSERC has been following its Tariff Regulations while
approving the Repair and Maintenance Cost (R&M). The commission links
the current year cost with the base year value though Wholesale Price Index
(WPI). Then, if required, certain directions are issued to the utility so that
the funds are utilized properly. For the FY 2011-12, the licensee had
proposed Rs. 414.74 crore for R&M. This amount also included Rs. 38.52
crore as expenses on the assets to be added during 2011-12. The commission
observed that this claim as a part of R&M expenses was not justified.
Therefore, the Commission disallowed this item while approving the R&M
expenses. Finally, it allowed Rs. 376 crore as R&M expenses. The
commission followed the same approach for the approval of administration
and general expenses. The actual expenditures on R&M are given in the
Table 3.15.
Table 3.15: Repair and Maintenance Cost
Year
R&M Cost (Rs. Crore)
2004-05
207
2005-06
223
2006-07
268
2007-08
274
2008-09
295
Source: PFC Report for the respective years
It is indicated in the Table 3.15 that the growth rate for FY 2006-07
was reported highest. The main reason for this hike was approval of the
deferred amount during this year. However, during the FY 2007-08 it grew
at 2%. So, taking the average inflation rate into account, the increase in
R&M expenses is reasonably acceptable except for the FY 2006-07.
3. III. 3: Depreciation
The depreciation amount is approved to compensate the utility for the
wear and tear of capital employed in the business. According to the standard
practices, a company should recover the capital cost of the assets during the
useful life of the assets. The commission has approved the depreciation
amount for the year 2011-12 on the basis of audited accounts for the FY
2009-10. As required by standard accounting practices, the Commission has
applied different rates for the different type of assets. The rates and amounts
of depreciation approved by the commission are given in the Table 3.16.
Table 3.16: Depreciation Charges for the FY 2011-12
Crore)
(Rs.
Sr.
Item
Assets (Approved as on
Depreciation rate
Depreciation Amount
No
April 1, 2011)
1.
5689
5.17%
294
Thermal
2.
5985
2.28%
136
Hydro
3.
66
4.81%
3.19
Transmission assets
4.
7168
5.65%
405
Distribution assets
5.
19106
4.40
841
Total
So, applying the differential rates of depreciations, the total depreciation amount comes out to be Rs. 841
crore. The overall weighted average depreciation is 4.40% for the FY 2011-12.
(Rs.
Crore)
Sr. No Particular
1.
Loan Amount (on April 1, 2011)
2.
Borrowing for FY 2011-12
3.
Repayment of loan during FY 2011-12
4.
Loan on the closing of FY 2011-12
5.
Interest payment
Source: Tariff order FY 2011-12 for PSPCL
Proposal
8013
2990
676
10328
985
Approval
6003
885
676
6213
656
The Commission has reduced the interest expenses by Rs. 329 crore
from the amount proposed by licensee. Though the commission has not
questioned the rate of interest applicable to the approved loans, however, the
commission has reduced the loan amount proposed by licensee. It was
reduced because the commission observed that the loans were being utilized
to meet out the current expenses. It may be noted from the Table 11, there
are wide differences in the loan amounts proposed by licensee and approval
given by the commission. Now, the question arises that what would happen
to the loan amount over and above the commissions approval. Since, it
stands on the balance sheet of the PSPCL and being a public sector unit, the
public has to bear this burden in future unless the same is not paid by the
state government. Therefore, under-approval of the interest expenses is not a
desirable solution unless the commission is able to ensure financial viability
of the utility. Responsibility of the erring officials may be fixed and suitable
action initiated as per the Act.
3. III. 4 (a): Observations of the Commission on the fund management
The Commission has observed that the utility has not utilized its funds
properly. The money which was approved to strengthen the distribution
system has been spent out to meet the current expenditure. This reflects poor
financial management on behalf of the utility. The money should be used to
create assets to reduce the AT& C losses in the system. The Commission has
estimated that the liability on account of fund diversion is Rs. 2459 crore
and should not be passed on to the consumers. The present consumers
should not be asked to pay for the mismanagement of funds by erstwhile
PSEB. Therefore, the Commission has also required Govt of Punjab (GoP)
to pay Rs. 454 core interest payment on the account of diversion of capital
funds for current purposes by PSEB.
3. III. 5: Return of Equity
The utility had claimed the Return on Equity (ROE) at the rate of
15.5% for the FY 2011-12.
Table 3.18: Annual Revenue Requirement for FY 2011-12
1
Particular
Cost of fuel
Cost of power purchase
Employee cost
R&M expenses
A&G expenses
Depreciation
Interest charges
Return on Equity
Transmission charges payable to PSTCL
Charges payable to GoP on Power RSD
Total Revenue Requirement
Less Non Tariff Income
Net Revenue Requirement
Less Revenue from Existing Tariff
Gap for FY 2011-12
Add Consolidated Gap upto FY
Consolidated Gap up to FY 2011Add Carrying Cost of Revenue
Total Gap for FY 2011-12
Energy Sales(MU)
PSERC - Tariff Order FY 2011-12
2
Proposal
3
Approval
4066.43
6349.74
3607.75
414.74
87.95
891.92
2203.27
598.86
712.03
17.71
18950.4
502.77
18447.62
14214.81
4232.81
5423.72
9656.53
3588.17
5751.26
2916.98
376.22
87.95
841.04
1066.86
366.47
491.45
17.71
15504.11
579.11
14925
14682.03
242.97
2116.69
2359.66
291.85
2651.51
35676
9656.53
36165
(Rs. Crore)
4= 3/2
Approval as a
Percentage of
proposal
88%
91%
81%
91%
100%
94%
48%
61%
69%
100%
82%
115%
81%
103%
6%
39%
24%
NA
27%
99%
(FY
2011-12)
Sr.
Category
Projections by Company
No
1
Domestic
8836
2
Commercial
2618
3
Industry
11187
4
Agriculture (Mainly Un-metered)
12253
5
Others*
1271
6
Total
36165
Source: PSERC Tariff Order for FY 2011-12 for PSPCL
Others includes common pool and outside states sales
Approval by
Commission
8854
2623
12197
10843
1159
35676
Relative shares
(approval)
25%
7%
34%
30%
3%
100%
3.V:
CONCLUSIONS
AND
POLICY
RECOMMENDATIONS
Poor technical and financial performance was the main problems
faced by PSEB in the pre-reforms period. The Plant load factor of the plants
operated by PSEB was very low. At the same time, the auxiliary
consumptions and energy losses were reported unreasonably high. Further,