Development of

Kalyan Dombivli
Solar City
Final Master Plan

Supported by

Ministry of New and Renewable Energy


Government of India, New Delhi

ABBREVIATIONS AND ACRONYMS


AC:
BEE:
BIPV:
BMS:
BOOT:
BOT:
CAGR:
CDM:
CDP:
CERC:
CFA:
CFL:
CHP:
CNG:
CO2:
CPWD:
CSP:
DG Sets:
DISCOM:
DSM:
DTS:
ECBC:
eCO2:
EE:
ESCo:
FITM:
FTL:
GDP:
GHG:
GLS:
GRIHA:
HH:
HPSV:
Hrs/day:
HVAC:
Hz:
ICLEI SA:

Air-conditioner
Bureau of Energy Efficiency
Building Integrated Photovoltaics
Building Management System
Build, Operate, Own and Transfer
Build, Operate and Transfer
Compound Annual Growth Rate
Clean Development Mechanism
City Development Plan
Central Electricity Regulatory Commission
Central Financial Assistance
Compact Fluorescent Light
Combined Heat and Power
Compressed Natural Gas
Carbon Dioxide
Central Public Works Department
Concentrating Solar Power
Diesel Generator Sets
Distribution Company
Demand Side Management
Decentralized Waste Water Treatment System
Energy Conservation Building Code
Equivalent Carbon Dioxide
Energy Efficiency
Energy Service Company
Feed in Tariff Mechanism
Fluorescent Tube Light
Gross Domestic Product
Green House Gases
Global Light Source
Green Building Integrated Habitat Assessment
House Hold
High Pressure Sodium Vapour
Hours per Day
Heating, Ventilation and Air-conditioning
Hertz
International Council for Local Environmental
Initiatives South Asia
IEA:
International Energy Agency
IEO:
International Energy Outlook
IREDA: Indian Renewable Energy Development Agency
ISES:
International Solar Energy Society
JnNURM: Jawaharlal Nehru National Urban Renewal Mission
KDMC: Kalyan Dombivli Municipal Corporation
Kg:
Kilogram
kHz:
Kilo Hertz
kL:
kilo litre
kL:
Kilo Litre
kT/yr:
Kilo Tonnes per Year
kW:
kilo Watt

kWe:
kWh:
kWp:
L:
LED:
LEED:
LPD:
LPG:
m/s:
M:
MNES:

Kilo Watt Equivalent


kilo watt-hour
Kilo Watt Peak
Litre
Light Emitting Diode
Leadership in Energy and Environmental Design
Litres per day
Liquefied Petroleum Gas
Metres per Second
Metre
Ministry of Non-conventional Energy Sources (now
the MNRE)
MNRE: Ministry of New and Renewable Energy
MSEDCL: Maharashtra State Electricity Distribution Company
MSW:
Municipal Solid Waste
MT:
Metric Tonnes
MU:
million units
MW:
Mega Watt
MWe: Mega Watt Equivalent
MWh: Mega Watt-hour
MWp: Mega Watt Peak
NGO:
Non-governmental Organization
O&M:
operations and Maintenance
PDD:
Project Design Document
PNG:
Piped Natural Gas
PPP:
Public-Private Partnership
R&D:
Research and Development
RE:
Renewable Energy
REC:
Renewable Energy Certificate
RET:
Renewable Energy Technology
SCADA: Supervisory Control and Data Acquisition
SCP:
Solar Cities Project
SERC:
State Electricity Regulatory Commission
Sft:
Square Feet
SNA:
State Nodal Agency
SPV:
Solar Photo Voltaic
Sqm:
Square Metre
STP:
Sewage Treatment Plant
SWH:
Solar Water Heater
SWM:
Solid Waste Management
T/yr:
Tonnes per Year
T:
Tonne
TeCO2: Tonnes of Equivalent Carbon Dioxide
TERI:
The Energy and Resources Institute
ULB:
Urban Local Body
UNFCCC: United Nations Framework Convention on Climate
Change
W:
Watt
Wh:
Watt-hour
WTP:
Water Treatment Plant

ACKNOWLEDGEMENT
This Master Plan is an outcome of the Ministry of New and Renewable Energys (MNREs) Solar City
Programme as part of the 11th Five year plan. Their initiatives have led to the collaboration of the Kalyan
Dombivli Municipal Corporation (KDMC) with ICLEI-South Asia for the preparation of the Solar City Master
Plan for Kalyan Dombivli city, as part of this Programme. We gratefully acknowledge the support of Kalyan
Dombivli Municipal Corporation and Maharashtra Energy Development Agency (MEDA) for providing
assistance in primary and secondary data collection in the initial phase of master plan preparation.
We would like to thank Secutech Automation (India) Pvt. Ltd Mumbai, for data collection and sample survey
for Kalyan Dombivli city. The report benefited enormously from peer review process by a gamut of experts
from ICLEI South Asia and most importantly the Kalyan Dombivli Municipal Corporation (KDMC), Maharashtra
Energy Development Agency (MEDA) and the stakeholders of Kalyan Dombivli Solar City Programme. We
acknowledge their contributions and suggestions which streamlined the structure and composition of the
master plan.
The report would have not been possible without the generous support of the Ministry of New & Renewable
Energy, Government of India. We extend our gratitude to the honorable secretary of MNRE, Mr. G. B.
Pradhan for his time and advice to make this report better. We specially thank Dr. Bibek Bandyopadyay,
Advisor, MNRE and Dr. Arun Kumar Tripathi, Director, MNRE for their valuable advice and guidance during
the preparation of this report. We also extend our thanks to the other officers and staff of the MNRE for their
consistent support in preparing and finalizing the report.

CONSULTED ORGANISATIONS:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.

Kalyan Dombivli Municipal Corporation, Kalyan Dombivli


Maharashtra Energy Development Agency (MEDA)
Officials and Councilors of Kalyan Dombivli Municipal Council
Maharashtra State Electricity Distribution Company Limited (MSEDCL)
District Supply Officer (DSO),
State Oil Coordinator for Maharashtra
Hotels and restaurants
Small Scale Industries Association
Tourism Department
Education Department
Department of Health
Members of the civil society
Secutech Automation Pvt Ltd
Local suppliers of RE and EE devices
Local Media

MNRE TEAM:
Dr. Bibek Bandyopadhyay, Advisor & Head, MNRE
Dr. Arun Kumar Tripathi, Director, MNRE
Mr. Hiren Borah, Scientist B, MNRE

KALYAN DOMBIVLI MUNICIPAL CORPORATION AND NODAL AGENCYS TEAM:


Mr. R. K. Sonawane, Commissioner, Kalyan Dombivli Municipal Corporation
Mr. Yashwant Sonawane, Executive Engineer, Kalyan Dombivli Municipal Corporation
Mr. Prashant Bhagwat, Engineer, Kalyan Dombivli Municipal Corporation
Shri Anand Limaye (IAS), Director General, MEDA
Mr. H. M. Kulkarni, General Manager, Rural Energy, MEDA

ICLEI SOUTH ASIA TEAM:


Emani Kumar
Dwipen Boruah
Ravi Ranjan Guru
Ashish Verma
Laasya Bhagvatula

EXECUTIVE SUMMARY
The Development of Solar Cities programme by the Ministry of New and Renewable Energy (MNRE),
Government of India, is an immense opportunity for contributing towards a sustainable India in the coming
years. This programme is a crucial step towards supporting Indian cities for the development of renewable
energy and energy efficiency projects and curbing conventional energy demand by 10% in the next five years.
This master plan is the outcome of the programmes objective to develop a road map for the city to envision
and implement renewable energy and energy conservation strategies. The master plan approach is in tandem
with the requirements of the MNRE guidelines.
The master plan begins with the introductory city profile which encapsulates the citys current energy
demands and also the municipal corporation services which are intrinsic to the citys growing energy demand.
The 2nd chapter provides the Current Energy Scenario of Kalyan Dombivli. Detailed analysis of the trend and
pattern of electricity, petrol, diesel, kerosene and LPG consumption has been discussed and thoroughly
analyzed to base the strategy development of the city. The main sources of energy in the city are electricity,
petrol, diesel, LPG and kerosene.
The 3rd Chapter Energy Demand Forecast of Kalyan Dombivli estimates the future conventional energy
demand interpolating the past data of energy consumption as well as population growth data. However other
key aspects detrimental to energy demand like population growth and city economic growth has also been
considered for ascertaining the citys future conventional energy
Kerosene
SWH
6.38%
0.35%
demands.
Electricity has the largest share in the makeup, accounting for 58% of
the energy supply, with LPG at 12%, petrol at 7%, diesel at 16% and
kerosene at 6%. The present penetration of SWH in Kalyan- Dombivli
is approximately 1%.
Sector wise, a majority of energy consumption is within the residential
sector (81%), followed by the commercial sector. During the last five
years, the residential and commercial sectors have shown higher
growth in electricity consumption as compared to the municipal and
industrial sectors.

Diesel
15.51%

Petrol
7.31%
LPG
12.41%

Electricity
58.04%

Goal for Year 2013:


Studying the historical growth in consumption levels and population growth projections until the year 2013,
it has been assessed that the energy consumption in Kalyan-Dombivli in 2013 can be ascertained under the
highest growth scenario as 1680 MU.
This gives the city a 10% reduction goal of 168 MU.
The success of renewable energy technology projects can only be assured with an accurate resource
assessment and its potential in the city. Hence the 4th Chapter Renewable energy and Energy Efficiency

Strategies for KDMC begins with the resource availability and intensity of renewable energy resources like
solar, wind, hydro- and geothermal in the city. This chapter is the most substantial part of the master plan as
it delineates the specific strategies for the city. For ease of study the city has been divided into residential,
commercial, municipal and industrial sectors and both renewable energy and energy efficiency initiatives
are enlisted within it. Case studies have been highlighted in the city which are 4-5 specific sites within the
city where RE and EE technologies can be showcased.
A minimum of 5% of the energy reduction achieved is aimed to be met through renewable energy measures.
The primary or the most feasible actions for which the techno-economics have been developed under
renewable energy measures are solar water heater and solar home light systems. Considering the high
upfront/ capital costs of solar equipments in India SWH has proved to be the least cost option compared to
other solar equipments for KDMC. As KDMC is primarily an urban residential area, the potential for
investment lies more in/from individual households.
The table below summarizes the year wise energy savings goal with RE and EE strategies in different sectors:

RE and EE Strategy for Kalyan


Dombivli City

Energy Savings target over 5 years period of


implementation (MU per year)
2nd year 3rd year
4th year
5th year
1st
Cumulati Cumulati Cumulati Cumulati
Year
ve
ve
ve
ve

% of
savings
target to
achieve

Emission
reduction/
year

RE for Residential Sector

8.30

20.75

37.36

58.11

83.02

49.41%

69231

RE for Commercial & Inst. Sector

0.50

1.25

2.25

3.50

5.00

2.98%

3187

RE for Industrial Sector

1.17

2.93

5.27

8.20

11.71

6.97%

9747

RE for Municipal Sector

0.10

4.70

6.50

13.16

13.46

8.01%

10903

Total for RE strategy

11.32

28.30

50.93

79.23

113.18

67.37%

93068

EE for Residential Sector

6.61

16.54

29.77

46.30

66.15

39.37%

53580

EE for Commercial Sector

2.51

6.27

11.28

17.55

25.08

14.93%

20312

EE for Industrial Sector

0.33

0.82

1.47

2.28

3.26

1.94%

2643

EE for Municipal Sector

1.46

3.65

6.58

10.23

14.61

8.70%

11838

Total for EE Strategy

10.91

27.28

49.10

76.37

109.10

64.94%

88372

RE and EE Combined Strategy

22.23

55.57

100.03

155.60

222.28

13%

33%

60%

93%

132%

181440

The table below summarizes the total budget and year wise expenses for implementation of solar city
development programme shared among MNRE, state/ city and private users.
Sharing of fund

Year 1
(Crore)

Year 2
(Crore)

Year 3
(Crore)

Year 4
(Crore)

Year 5
(Crore)

Total (Crore)

State / City Share

3.10

4.65

6.20

7.75

9.30

30.99

MNRE Share

21.58

34.48

43.53

55.80

64.44

219.83

Private Share

40.98

64.37

83.00

106.63

122.93

417.90

Total Budget

65.66

103.49

132.72

170.17

196.67

668.71

Guidebook for development of Solar City:


The Guidebook for development of Solar City is an integral part of the Master Plan. The guidebook provides
generic information about general energy scenario, renewable energy scenario and energy efficiency
initiatives in India, evolution of solar city concept, international solar city initiatives and local renewable
network in its first two chapters. The third chapter describes the solar city programme in India and its
objectives, targets and guidelines. Indicative renewable energy devices and energy efficiency measures are
described in chapter 4 & 5. Financial models have been suggested in the 6th Chapter Financial Schemes and
Business Models to enable the city to implement the strategies listed here. The implementation phase under
this programme will be the key indicator to determine the level of success for this MNRE programme. The 6th
Chapter cites numerous schemes available in India as well as various business models which can be emulated
for successful implementation of RE & EE projects.
Not only financing but capacity building and awareness generation go hand in hand to ensure sustainability of
the MNRE programme. All activities from developing a Solar City Cell to workshops and training have been
discussed in the 7th Chapter Implementation Strategy for Solar City Programme.
8th Chapter Risk Analysis describes the risks involved in developing renewable energy projects in the Indian
context and suggests mitigation methods for the cities. A generic approach has been taken to provide the
preventive measures however risks are city-specific and requires intrinsic detailing for individual projects.
The master plan provides a framework to compare and analyze alternative strategies and policies, in order to
facilitate Councils review and the decision-making process. Achieving significant reduction in energy
consumption requires collective effort by all City departments, other government departments, businesses,
industries and citizens. The City needs to become a bolder leader in its policies, planning, programs, advocacy
and its own operations there is a tremendous opportunity and need to demonstrate Community
Leadership. The investigation showed that the biggest energy saving potential is in the residential sector and
most significant RES potential is for solar energy projects. It is the responsibility of leaders in all tiers of
government, commerce, industry and civil society to promote action towards more efficient and renewable
energy use.

Table of Contents

ACKNOWLEDGEMENT ..................................................................................................................................... 2
CONSULTED ORGANISATIONS: ........................................................................................................................ 3
ICLEI SOUTH ASIA TEAM: ................................................................................... Error! Bookmark not defined.
EXECUTIVE SUMMARY..................................................................................................................................... 4
1.

INTRODUCTION ..................................................................................................................................... 15

1.1.

Kalyan Dombivli City Profile .............................................................................................................. 15

1.2.

City Urban Services ............................................................................................................................ 15

1.2.1.

Administrative Setup ..................................................................................................................... 15

1.2.2.

Water Supply ................................................................................................................................. 15

1.2.3.

Municipal Solid Waste ................................................................................................................... 15

1.2.4.

Sewage Treatment Plant ............................................................................................................... 16

1.2.5.

Streetlights .................................................................................................................................... 16

1.2.6.

Storm Water Drains ....................................................................................................................... 16

1.2.7.

Roads, Traffic and Transportation ................................................................................................. 17

1.2.8.

e- Governance ............................................................................................................................... 17

1.3.

Developing Kalyan Dombivli as Solar City ....................................................................................... 17

1.3.1.
2.

Preparation of Master Plan for Kalyan Dombivli Solar City......................................................... 17

ENERGY BASELINE STATUS OF KALYAN DOMBIVLI CITY........................................................................ 19

2.1.

Overall Energy Status ........................................................................................................................ 19

2.1.1.

Energy Consumption ..................................................................................................................... 19

2.1.2.

Supply Side Energy Balance ........................................................................................................... 21

2.2.

Residential Sector .............................................................................................................................. 22

2.2.1.

Energy consumption ...................................................................................................................... 22

2.2.2.

Results of sample survey ............................................................................................................... 23

2.3.

Commercial Sector ............................................................................................................................ 26

2.3.1.

Energy consumption ...................................................................................................................... 26

2.3.2.

Results of sample survey ............................................................................................................... 27

2.4.

Industrial Sector ................................................................................................................................ 30

2.4.1.

Energy consumption ...................................................................................................................... 30

2.4.2.

Results of sample survey ............................................................................................................... 30

2.5.

Municipal Sector ................................................................................................................................ 31

2.6.

City Wide Green House Gas Inventory .............................................................................................. 32

2.6.1.

City level Emissions........................................................................................................................ 32

2.6.2.

Government Emissions .................................................................................................................. 32

3.

ENERGY DEMAND FORECAST FOR KALYAN DOMBIVLI ......................................................................... 34

3.1.

Forecasting Based on Population Growth ......................................................................................... 34

3.2.

Goal for the year 2013....................................................................................................................... 36

4.

RENEWABLE ENERGY STRATEGIES FOR KALYAN DOMBIVLI.................................................................. 37

4.1.

Renewable Energy Resource Assessment ......................................................................................... 38

4.1.1.

Solar Radiation............................................................................................................................... 38

4.1.2.

Wind Energy .................................................................................................................................. 39

4.1.3.

Biomass Resource .......................................................................................................................... 39

4.1.4.

Waste generation .......................................................................................................................... 40

4.1.5.

Liquid Waste from Sewage Treatment Plant................................................................................. 40

4.2.

RE Strategy for Residential sector ..................................................................................................... 40

4.3.

RE Strategy for Commercial and Institutional Sector ........................................................................ 46

4.3.1.

RE Strategy for Hotels .................................................................................................................... 46

4.3.2.

Renewable Energy Systems for Restaurants ................................................................................. 48

4.3.3.

Renewable Energy Systems for Hospitals...................................................................................... 51

4.3.4.

Renewable Energy Systems for Educational Institutes ................................................................. 55

4.3.5.

RE Strategy for Industrial Sector.................................................................................................... 56

4.3.6.

RE Strategy for Municipal Sector ................................................................................................... 57

10

4.3.7.

Waste to Energy Potential in Kalyan Dombivli .............................................................................. 61

4.3.8.

Application of biogas plants .......................................................................................................... 64

4.3.9.

Solar Thermal for cooling .............................................................................................................. 66

5.

ENERGY EFFICIENCY STRATEGIES FOR KALYAN DOMBIVLI.................................................................... 67

5.1.

EE Strategy for Residential sector ..................................................................................................... 68

5.2.

EE Strategy for Commercial Sector.................................................................................................... 71

5.3.

EE Strategy for Industrial Sector ........................................................................................................ 75

5.4.

EE Strategy for Municipal Sector ....................................................................................................... 77

5.4.1.
6.

EE measures in Street Lighting ...................................................................................................... 77

ACTION PLAN AND BUDGET .................................................................................................................. 83

6.1.

Year-wise Goals of Energy Savings .................................................................................................... 83

6.2.

Physical Target and Action Plan......................................................................................................... 86

6.3.

Implementation Strategy................................................................................................................... 88

6.3.1.

Establishment of the Solar City Cell............................................................................................... 88

6.3.2.

Awareness and Publicity ................................................................................................................ 88

6.3.3.

Implementation of RE Strategy ..................................................................................................... 89

6.3.4.

Renewable Energy Pilot Projects ................................................................................................... 91

6.4.

Financial outlays and sharing of fund ................................................................................................ 93

6.5.

Potential Carbon Market Benefit ...................................................................................................... 98

7.

Annexure I Pilot Project I .................................................................................................................... 99

8.

Annexure II Pilot Project II ................................................................................................................ 106

9.

Annexure III Pilot Project III .............................................................................................................. 113

10.

Annexure IV Pilot Project IV ......................................................................................................... 120

11.

Annexure V - Pilot Project V ............................................................................................................ 128

12.

Annexure VI - References & Bibliography ....................................................................................... 134

11

List of Figures
Figure 1 :
Figure 2 :
Figure 3 :
Figure 4 :
Figure 5 :
Figure 6 :
Figure 7 :
Figure 8 :
Figure 9 :
Figure 10 :
Figure 11 :
Figure 12 :
Figure 13 :
Figure 14 :
Figure 15 :
Figure 16 :
Figure 17 :
Figure 18 :
Figure 19 :
Figure 20 :
Figure 21 :

Growth in Electricity Consumption ........................................................................................................................................20


Sector Wise Break-Up of Electricity Consumption ...........................................................................................................20
Shares of Fuels in Supply Side Energy Balance ..................................................................................................................22
Supply Balance in residential sector ......................................................................................................................................23
Household Classification .............................................................................................................................................................23
Lighting Inventory and Usage ..................................................................................................................................................25
Awareness and Usage of RE & EE Technologies ................................................................................................................25
Share Of Fuels In Energy Balance ...........................................................................................................................................26
Consumer classification (kWh/month).................................................................................................................................27
Lighting Technology Used by Consumers.............................................................................................................................29
Awareness and Usage of Energy Efficient Lighting Technologies ..............................................................................29
Share of GHG Emissions by Sector...........................................................................................................................................32
Share of GHG emission in Government sector ....................................................................................................................33
Forecasting for Energy Consumption (MU) based on population growth ..............................................................35
Forecasting of Energy Consumption (MU) based on historical data ........................................................................35
Annual Solar Radiation profile in Kalyan Dombivli.........................................................................................................39
Year wise energy savings targets for Kalyan Dombivli Solar City .............................................................................84
Sharing of total budget for development of solar city Kalyan Dombivli .................................................................94
Sharing of RE Strategy Budget for Kalyan Dombivli Solar City .................................................................................94
Sharing of EE Strategy Budget for Kalyan Dombivli Solar City ..................................................................................94
Year wise sharing of budget for Kalyan Dombivli Solar City Programme ..............................................................95

12

List of Tables
Table 1 :
Table 2 :
Table 3 :
Table 4 :
Table 5 :
Table 6 :
Table 7 :
Table 8 :
Table 9 :
Table 10 :
Table 11 :
Table 12 :
Table 13 :
Table 14 :
Table 15 :
Table 16 :
Table 17 :
Table 18 :
Table 19 :
Table 20 :
Table 21 :
Table 22 :
Table 23 :
Table 24 :
Table 25 :
Table 26 :
Table 27 :
Table 28 :
Table 29 :
Table 30 :
Table 31 :
Table 32 :
Table 33 :
Table 34 :
Table 35 :
Table 36 :
Table 37 :
Table 38 :
Table 39 :
Table 40 :
Table 41 :
Table 42 :
Table 43 :
Table 44 :
Table 45 :
Table 46 :
Table 47 :
Table 48 :
Table 49 :
Table 50 :

Electricity consumption in Kalyan Dombivli City .............................................................................................................19


LPG Consumption Data in KDMC ............................................................................................................................................20
Petrol Consumption Data in KDMC ........................................................................................................................................21
Diesel Consumption Data in KDMC ........................................................................................................................................21
Kerosene Consumption Data in KDMC..................................................................................................................................21
Supply Side Energy Balance in KDMC for 2007-2008.....................................................................................................22
Residential Sector Energy Consumption ..............................................................................................................................22
Energy Balance for Residential Sector .................................................................................................................................22
Summary of Sample Survey ......................................................................................................................................................24
Commercial Sector Energy Usage...........................................................................................................................................26
Energy Balance for the Sector for the Year 2007-08 ......................................................................................................26
Summary of Commercial establishments/institutes in the city ..................................................................................27
Household appliances inventory .............................................................................................................................................28
Interest Shown By Consumers for Solar Water Heater Installation .........................................................................30
Industrial Sector Energy Consumption ................................................................................................................................30
Energy Balance for Industrial Sector ....................................................................................................................................30
Overall Municipal Sector Energy Consumption (MU) .....................................................................................................31
Energy Consumption for Street lighting(kWh) .................................................................................................................31
Electricity Consumption in Water Pumping (MU) ...........................................................................................................31
Energy Consumption in waste water treatment plant (MU) .......................................................................................31
Population Projection till 2020 ...............................................................................................................................................34
Energy Consumption Projection (MU) ..................................................................................................................................34
Energy Consumption Projection for KDMC (MU) .............................................................................................................35
Energy consumption projection for KDMC (MU) ..............................................................................................................36
Forecasting of Energy Consumption for KDMC .................................................................................................................36
Monthly Averaged Insolation Incident on a Horizontal Surface (kWh/M2/Day)................................................38
Monthly averaged wind speed above earth surface for terrain similar to airports (m/s) ..............................39
Biomass Resource .........................................................................................................................................................................39
Solid Waste Generation Data ...................................................................................................................................................40
Target for SWHs installation in Kalyan Dombivli City ...................................................................................................41
Target for introducing solar cooker in Kalyan Dombivli City .....................................................................................41
Target for introducing solar lanterns in Kalyan Dombivli City ..................................................................................42
Target for introducing solar home system in Kalyan Dombivli City .........................................................................43
Target for introducing Solar PV for Home Inverters in Kalyan Dombivli City .....................................................44
Target for replacement of diesel generator sets with PV Power Pack in Kalyan Dombivli City ....................44
RE system for residential apartments ...................................................................................................................................45
Summary of RE Strategy for Residential sector in Kalyan Dombivli City ...............................................................46
Case Study of Budget Hotel cum Bar & Restaurant .........................................................................................................47
Case Study of Restaurant ...........................................................................................................................................................49
Summary of RE strategy for Restaurants ............................................................................................................................51
Case Study of 50 bedded hospital............................................................................................................................................51
Case Study for 20 bed hospital .................................................................................................................................................53
Summary of RE systems for Hospitals ...................................................................................................................................54
Target for Introducing Solar Cookers in Primary Schools............................................................................................55
Summary of RE strategy for educational institutes ........................................................................................................56
RE Strategy for Commercial and Institutional Sector ....................................................................................................56
RE Strategy for industrial sector in KDMC..........................................................................................................................57
RE Strategy for KDMC municipal sector ..............................................................................................................................58
RE Systems for Shopping Complexes .....................................................................................................................................59
RE Systems for Outdoor lights, Road safety ........................................................................................................................59

13

Table 51 :
Table 52 :
Table 53 :
Table 54 :
Table 55 :
Table 56 :
Table 57 :
Table 58 :
Table 59 :
Table 60 :
Table 61 :
Table 62 :
Table 63 :
Table 64 :
Table 65 :
Table 66 :
Table 67 :
Table 68 :
Table 69 :
Table 70 :
Table 71 :
Table 72 :
Table 73 :
Table 74 :
Table 75 :
Table 76 :
Table 77 :
Table 78 :
Table 79 :
Table 80 :
Table 81 :
Table 82 :
Table 83 :
Table 84 :
Table 85 :
Table 86 :
Table 87 :
Table 88 :
Table 89 :
Table 90 :
Table 91 :
Table 92 :
Table 93 :
Table 94 :
Table 95 :
Table 96 :
Table 97 :
Table 98 :
Table 99 :
Table 100 :

Summary of RE Strategy for outdoor light and road safety ........................................................................................60


Renewable Energy Systems for Parks ...................................................................................................................................60
Summary of RE Strategy for Kalyan Dombivli Corporation Parks ............................................................................60
Summary of RE Strategy for Municipal Sector in Kalyan Dombivli ..........................................................................61
Municipal Solid Waste Characterization (2006) ..............................................................................................................61
Waste to Energy through thermo-chemical conversion ................................................................................................62
Waste to Energy through bio-methanation .......................................................................................................................62
Waste to Energy from Sewage Treatment Plant ..............................................................................................................63
Summary of waste to energy potential in Kalyan Dombivli City ................................................................................64
Replacement of incandescent lamps with fluorescent....................................................................................................68
T5 tube light + Electronic Ballast to replace T12/T8 tube light+ Magnetic Ballast ..........................................69
Efficient Ceiling Fans to Replace Conventional Ceiling Fans .......................................................................................69
Replacement of conventional air-conditioners with EE star rated ACs ..................................................................70
Replacement of Conventional Refrigerators with EE Star Rated Refrigerators ..................................................70
Replacement of conventional water pumps with EE star rated water pumps .....................................................71
Summary of EE Strategy in Residential Sector .................................................................................................................71
Replacement of incandescent lamps with fluorescent....................................................................................................72
Replace T12/T8 tube light by T5 tube light .......................................................................................................................72
Replacement of Conventional Fans ........................................................................................................................................73
Replacement of Conventional Air-Conditioners with EE Star Rated ACs ................................................................73
Replacement of Conventional Refrigerators with EE Star Rated Refrigerators ..................................................74
Replacements of Conventional pumps with EE Star Rated pumps ............................................................................74
Summary of EE Strategy in Commercial & Industrial Sector ......................................................................................75
Replacement of incandescent with CFLs in Industrial sector ......................................................................................75
Replacement of T8/T12 tube lights .......................................................................................................................................76
Replacement of conventional fans by EE star rated fans ..............................................................................................76
Replacement of Conventional ACs with EE Star Rated ACs ..........................................................................................77
Summary of EE Strategy for Industrial Sector ..................................................................................................................77
Replacement of 150 watt HPSV with LED ...........................................................................................................................78
Replacement of 40 watt T8/T12 tube lights with T5 tube lights ...............................................................................78
Proper pump-system design (efficient Pump, pumps heads with system heads) .................................................79
Variable Speed Drivers................................................................................................................................................................80
Power saver installation in pump house ..............................................................................................................................80
Proper pump-system design (efficient pump, pumps heads with system heads) .................................................80
Variable Speed Drivers................................................................................................................................................................81
Power saver installation in pump house ..............................................................................................................................81
Summary of EE Strategy for municipal sector ..................................................................................................................82
Energy savings goal over 5 years solar city implementation period ........................................................................83
Year wise Goal of Energy Savings ...........................................................................................................................................85
Physical target of RE systems and EE devices....................................................................................................................86
Physical Target and Action Plan .............................................................................................................................................87
Pilot Projects in Residential Sector ........................................................................................................................................91
Pilot Projects in Commercial and Institutional Sector ...................................................................................................92
Pilot Projects in Industrial Sector ...........................................................................................................................................92
Pilot Projects in Municipal Sector ..........................................................................................................................................92
Summary of Pilot Projects and indicative project cost implication ..........................................................................93
Sharing of budget for development of Kalyan Dombivli Solar City ...........................................................................93
Sector wise total budget and annual expenses ..................................................................................................................96
Budget and Sharing of fund ......................................................................................................................................................97
Potential Carbon Market Benefit ..........................................................................................................................................98

14

CHAPTER 1
1. INTRODUCTION
1.1.

Kalyan Dombivli City Profile

Kalyan Dombivli is an important satellite township of Mumbai city. It is an important railway junction. The
city of Kalyan Dombivli forms one of the important urban agglomerations of Maharashtra state. Owing to
large urbanizable zone and its proximity to greater Mumbai, Kalyan Dombivli is trying to enhance the quality
of services, expand the infrastructure and accelerate its economic growth.
Kalyan Dombivli, being close to Mumbai, the demographic profile of the city reveals that the population has
increased continuously. As per census reports the population in the year 1961 was 1, 49,894 which is
increased to 10, 47,297 in the year 2001. KDMC has projected population up to year 2020 which is assessed
to be 20, 52,060. On the basis of proposed land use as provided in development plan and area available for
future development to absorb additional population of approximately 16,55,550 souls in the year 2016
which can called as Carrying Capacity of the City up to year 2016.
The demographic profile shows continuous increase in population of the city. The deletion of Ambarnath &
Badlapur area including surrounding villages affected the economy of the city adversely.

1.2. City Urban Services


1.2.1. Administrative Setup
Kalyan Dombivli Municipal Corporation (KDMC) is the main organization which is responsible for urban
governance and civic management in the city of Kalyan Dombivli. The corporation has a democratically
elected leadership from the constituencies within the geographic jurisdiction of the corporation boundaries.
1.2.2. Water Supply
The total potable water supply in Kalyan Dombivli is sourced from Ulhas and Kalu River. The water supply
was 238 MLD for a population 12.63 lakhs in the year 2006. Surface water is available to a significant extent
as Ulhas and Kalu Rivers are perennial sources. As both the rivers flow within KDMC limits, the cost of
transmission is comparatively less. The KDMC purifies water at its treatment plants located at Barave, Kalyan
Dombivli and along the bank of Kalu River, Titwala. Additional requirement is being purchased from agencies
like MIDC, NRC & ZP. The purification capacity of Barave Treatment Plant is 144 MLD and that of Titwala
Treatment Plant is 7.5 MLD. The present installed distribution system covers all of the 107 wards in the cities
of Kalyan and Dombivli.
1.2.3. Municipal Solid Waste
The KDMC carry out the collection and transportation of the solid waste within the Kalyan Dombivli
Municipal City Limits through its vehicle fleet, machinery and laborers. Out of 7 Administrative Municipal

15

Wards, 2 wards are selected for secondary collection and transportation of the solid waste through
privatization. The department is headed by Deputy Municipal Commissioner who is assisted by 7 ward
officers, 2 Assistant Public Health Officers, 36 sanitary inspectors, 90 Mukadams and 1468 sanitation staff.
The city generates approximately 600 M.T. of municipal solid waste every day which comprises biodegradable and non bio- degradable solid waste components. The solid waste is generated by households,
hotels and restaurants, markets, fruit vendors, construction activities.
Waste segregation at all collection points and at storage is primarily done by rag pickers. The sweepers of
the department collect the waste at the dustbin sites. KDMC endeavors to increase the private sector
participation in solid waste management. KDMC has taken initiatives to direct house owners and
establishments to store waste in 2 different containers at source and not to throw it on the streets.
The waste is collected and transported from each corner of the Corporation by the man & machinery of
KDMC 61 wards and by a private partner in rest of the 46 wards.. The solid waste so collected is presently
transported to the solid waste disposal site located at Adharwadi, Kalyan Dombivli which is in close proximity
to habitation.
1.2.4. Sewage Treatment Plant
Sewage collected from individual house sewer connection is conveyed through sewer lines to the relevant
pumping stations and sent to the sewage pumping plants at different locations for the treatment. The
treated water is discharged finally to the creek. The performance standard benchmarked against standard
requirements in terms of sewage collection system coverage is found to be very low, inadequate in terms of
sewage treatment plants & function characteristics and adequate in terms of Revenue/ O & M ratio.
1.2.5. Streetlights
KDMC is responsible for provision and maintenance of streetlights within the Corporation limits. The
corporation handles material procurement; installation and maintenance through qualified technical staff of
KDMC and approved/ registered Electrical Contractors.
Private sector participation in maintenance of street lighting is being introduced in the year 2000 in the
corporation. As per 2006 data, 13310 nos. of street lights on KDMC owned poles are maintained by Electrical
Contractor appointed by KDMC and 2356 nos. of street lights on MSEDC poles are maintained by Electrical
Departmental Staff of the corporation. Other general lighting service fitments includes 29 nos. of 20 mtr / 16
mtr, high mast at major intersections and roundabouts of the city.
1.2.6. Storm Water Drains
The general elevation of Kalyan Dombivli city is 6.0 m above Mean Sea Level. Overall topography of the area
slopes towards The North and West. The river Kalu, Ulhas and Kalyan Dombivli creek runs along the North
and West side boundaries and cover 60% of the periphery of the corporation. There exists a network of
major and minor nallas in the significant parts of the paved areas of the old municipal council limits of these
towns.
Major part of KDMC is divided into different storm water drainage zones. There are 8 major drains flowing
from South- East to North West. Out of these 8 drains, 7 are primary and major parts of the drains are

16

constructed. These drains also receive and convey sullage water from residential/ habituated areas besides
storm water drainage up to different disposal locations in the creek. These drains are constructed and
maintained by KDMC.
1.2.7. Roads, Traffic and Transportation
The surface transport of the city is mainly divided into railways & roads. Kalyan Dombivli Municipal
Corporation is an important satellite township of Mumbai city. It has an extensive road network. As per the
development plan, the total length is 576 km. within the municipal limit. The figure includes state highways
& Major District Roads, major arterial and internal roads.
Kalyan Dombivli is an important railway junction and entry point of Mumbai city. Trains run between
Dombivli, Thakurli, Kalyan Dombivli, Shahad, Ambivali, Titwala & Kopar railway stations. Besides this, on the
periphery of corporation limits there is 1600 hectare and belongs to civil aviation Department and Airport is
likely to be developed in near future.
1.2.8. e- Governance
Kalyan Dombivli Municipal Corporation has initiated its journey in e Governance in 1999 with an aim of
creating a solid, system driven corporation with highest levels of Transparency, Accountability and Citizen
Servicing Standards. It creates hassle free interactions for citizens. Payment of taxes, application for newer
water connection, application for birth/ death certificate, and application for any other service or simply the
registration of a civic complaint can be done with ease. The project has received accolades/ awards at State,
National & International level.

1.3.

Developing Kalyan Dombivli as Solar City

The Ministry of New and Renewable Energy (MNRE), Govt. of India has launched a Scheme on Development
of Solar Cities under which a total of 60 cities/towns are proposed to be supported for development as
Solar/ Green Cities during the 11th Plan period. The program aims at minimum 10% reduction in projected
demand of conventional energy at the end of five years, which can be achieved through a combination of
energy efficiency measures and enhancing supply from renewable energy sources. Out of this 5% will be from
renewable energy source. MNRE has been providing financial support to Kalyan Dombivli Municipal
Corporation for preparing a Master Plan for developing Kalyan Dombivli as a Solar City.
1.3.1. Preparation of Master Plan for Kalyan Dombivli Solar City
The master plan preparation process is divided into six steps:
(i) Preparing energy base-line for year 2008
Energy base-line for the city is a detailed documentation of the existing energy demand and supply scenario
for the city. Among other things, it consists of sector-wise energy consumption matrix and energy supplymix for the base year. The city is divided into four sectors vis. Residential, commercial/ Institutional,
Industrial and Municipal sector.
(ii) Demand Forecasting for 2013/2018
This step involves predicting the energy demand for 5 year and 10 year periods. To estimate the demand,

17

growth in energy use in different sectors has been established. These growth rates are established based on
immediate past trends and future growth plans. Based on the past time-series data and information on
growth plans, growth rate in energy demand for different sectors has been estimated. These growth rates
are used for making future projection of energy demand in each sector for year 2013 (five year) and 2018
(10 year).
(iii) Sector wise strategies
This step involves carrying out techno-economic feasibility of different renewable energy and energy
efficiency options for each sector based on techno-economic feasibility for such application to the concerned
sectors. A renewable energy resources assessment has been done to identify the potential renewable energy
sources for the city. This includes assessment of solar radiation, wind power density and availability, biomass
resources and municipal/industrial wastes. A strategy has been prepared for use of techno economically
feasible renewable energy technology options in each sector.
(iv) Year-wise goals of savings
Year wise goals have been set to achieve targeted energy savings through demand side management by
energy conservation and energy efficiency measures in different sectors & supply side measures based on
renewable energy applications.
(v) Action Plan
A five-year action plan has been prepared to achieve the set goals & expected GHG abatements. This
includes establishment of solar city cell, capacity building and awareness generation.
(vi) Financial Outlay and sharing of fund
An indicative financial outlay has been prepared for implementation of the proposed five-year action plan
and potential sources of funding from respective sources (both public and private) has been indicated.

18

CHAPTER 2
This chapter gives details of energy consumption for the Kalyan Dombivli city for past 3-5 years. The
consumption has been shown based on the energy sources such as electricity, LPG, petrol, diesel and
kerosene. Further, sectoral break up (i.e. residential, commercial, industrial and municipal) of
consumption for each fuel is also presented. The chapter also provides the findings of the primary sample
survey, including monthly fuel consumptions, ownership of appliances and their usage, present usage of
renewable energy, awareness and usage of energy efficient technologies etc.

2. ENERGY BASELINE STATUS OF KALYAN DOMBIVLI CITY


2.1.

Overall Energy Status

2.1.1. Energy Consumption


Based on the information gathered from survey, the energy consumption scenario is presented here. The
main sources of energy are electricity, petrol, diesel, LPG and kerosene.
Electricity: Electricity distribution in the city is done through five main stations viz. Kalyan E Section 1, Kalyan
Rural (Titwala), Kalyan E Section 2, Dombivli division and Kalyan Urban/West. Based on the information
available, sector wise electricity consumption data is compiled for last 4 years (Please refer to Annexure- I
for details).
Table 1 :

Electricity consumption in Kalyan Dombivli City

Electricity Consumption (MU)


2005-06

2006-07

2007-08

No. of
Consumers
(2007-08)

Residential

635

694

780

305289

Commercial

106

116

124

62976

Industrial

26

26

33

1985

Municipal
Total

26.7

29.0

30.7

794

865

968

370250

Year

Growth trend for the electricity can be seen in the figure given below. The compound annual growth rate
(CAGR) based on 2005-06 & 2007-08 data comes as 10%, which is much higher than the population growth
rate (3.82%) in the city.

19

Figure 1 :

Growth in Electricity Consumption

Figure 2 : below gives the break up of electricity consumption for different sectors. Residential sector
dominates (81%) in electricity consumption and hence should be targeted for Demand Side Measures (DSM).
During last five years, the residential and commercial sectors have shown higher growth in electricty
consumption as compared to the the municipal and industrial sectors.

Industrial
3%

Municipal
3%

Commercial
13%

Residential
81%

Figure 2 :

Sector Wise Break-Up of Electricity Consumption

LPG: Based on the available data, LPG consumption is summarized in Table given below.
Table 2 :
Sectors

LPG Consumption Data in KDMC

Residential

2005-06
(MT)
12149

2006-07
(MT)
12951

2007-08
(MT)
13849

Commercial

349

324

378.9

12505

13281

14234.9

Industrial
TOTAL

20

Petrol: Based on the available data, petrol consumption is summarized in Table given below. Most of the
consumption would be in transportation sector; however, sectoral break up of petrol consumption is not
available.
Table 3 : Petrol Consumption Data in KDMC
Petrol Consumption (kL)

2005-06

2006-07

2007-08

11086

11558.79

13199.5

Diesel: Based on the available data, diesel consumption is summarized in Table given below. Most of the
consumption would be in transportation & industrial sector. There would also be some diesel consumption
in residential sector for DG sets. However, sector-wise break up of diesel consumption is not available. Also,
diesel consumption data might include the supply to industries which are not falling under KDMC area.
Table 4 :

Diesel Consumption Data in KDMC

Diesel Consumption (kL)

2005-06

2006-07

2007-08

16508

18660

22727.5

Kerosene: Based on the available data, kerosene consumption is summarized in Table given below. Most of
the consumption would be in industrial sector; however, it might include the supply to industries which are
not falling under KDMC area. Sectoral break up of kerosene consumption is not available.
Table 5 :

Kerosene Consumption Data in KDMC

Kerosene consumption
(kL)

2005-06

2006-07

2007-08

10373

10474

10574

2.1.2. Supply Side Energy Balance


Based on the available data for these 5 energy sources, the supply energy scenario for year 2007-08 is
developed. It is assumed that the SWH penetration in the city is 1%, i.e. 1% of the households use SWH in
the city. Other renewable sources have very low penetration and are too small a percentage to be reflected
here. The table below gives contribution of these energy sources in the overall energy supply.

21

Table 6 :

Supply Side Energy Balance in KDMC for 2007-2008

Source
Electricity
LPG
Petrol
Diesel
Kerosene
SWH

Consumption

Unit

968
14234.9
13199.5
22727.5
10574
3053

MU
MT
kL
kL
kL
No.
Total

Consumption
(MU)
968
207
122
259
106
5.8
1667

The pie-chart below gives the break up in percentage for supply side energy balance for the 2007-08.

Kerosene
6.38%

SWH
0.35%

Diesel
15.51%

Petrol
7.31%

Electricity
58.04%

LPG
12.41%

Figure 3 :

Shares of Fuels in Supply Side Energy Balance

Residential Sector
2.2.1. Energy consumption
2.2.

Residential sector dominates the overall energy consumption. Energy usage pattern for this sector is shown
in Table below.
Table 7 :
Sources
Electricity (MU)
LPG (MT)

Residential Sector Energy Consumption


2005-06

2006-07

2007-08

635

694

780

12149

12951

13849

Energy balance for the sector for the year 2007-08


Table 8 :
Source
Electricity

Energy Balance for Residential Sector


Consumption
780 MU

Consumption (MU)
780 MU

LPG

13849 MT

201 MU

Total

Total

981 MU
22

Electricity is the main source of energy in residential sector as it contributes 79% of the total whereas LPG
contributes 21%.

LPG
21%

Electricity
79%

Figure 4 :

Supply Balance in residential sector

2.2.2. Results of sample survey


It should be noted that numbers given in the summary are specific to the surveyed households only.
In order to understand the end uses of energy, and consumer behavior patterns consumer survey has been
conducted. The survey questionnaire has been developed to gather information such as monthly fuel
consumption, ownership of appliances and their usage, present usage of renewable energy, awareness and
usage of energy efficient technologies, etc. The survey data has been analyzed and the summary has been
shown below.
Household classification and general details
Household class: Based on the monthly electricity consumption households have been classified under 4
categories.

Figure 5 :

Household Classification

23

Building type:
Bungalow / independent house-18%
Housing Scheme
-8%
Apartment building / Flat
- 44%
Slum pocket
-7%
Other
-23%
Family size: Less than 5 61%, 5-10 38%
House area varies from 100 to 3600 ft2 and the average size is 560 ft2 per household.
Energy Consumption Pattern:
As the data show that the primary sources of energy consumption in the residential sector are: Electricity,
LPG and Kerosene, we will try to find out the consumption behavior of these energy sources in the residential
sector.
Table 9 :
End Use

Type of Appliances

Lighting

Incandescent
CFLs
Fluorescent long
Fluorescent short
Others
Air Conditioner
Room heater
Fans Ceiling, Table Pedestal
Desert cooler
Electric Water Pump
Geyser
Refrigerator
Television
Others

Space
Conditioning

Water Pumping
Water Heating
Refrigeration
Others

Summary of Sample Survey


% of surveyed
HHs owning
the appliance

Average
Usage/day

Average
Wattage

41%
65%
83%
8%
4%
18%
0%
99%

Average
number of
appliances
per surveyed
HHs
0.9
2.5
2.1
0.2
0.5
0.24
0
3

3
3
3
3
5
5
0
8

60
15
36
20
10
1500
0
70

3%
5%
32%
84%
95
82

0.03
0.05
0.35
1.1
1.01
1.34

6
1
2
24
6
5

200
1000
1500
200
100
15

24

Figure 6 :
Lighting Inventory and Usage
Fuel usage:
Primary fuel used for cooking:
LPG/PNG
- 95%
Kerosene
- 15%
Fuel wood - 4%
Electricity
- 12% (total is more than 100 due to multiple fuel usage)
Primary fuel used for water heating
LPG/PNG
- 61%
Kerosene
-11%
Fuel wood -6%
Electricity
-24%
Other
-3% (total is more than 100 due to multiple fuel usage)

Figure 7 :

Awareness and Usage of RE & EE Technologies

25

2.3.

Commercial Sector
2.3.1. Energy consumption
Commercial sector energy usage pattern is shown in Table below. The main sources are electricity
and LPG.
Table 10 : Commercial Sector Energy Usage
Source

2005-06

2006-07

2007-08

Electricity (MU)

106

116

124

LPG (MT)

349

324

379

Table 11 : Energy Balance for the Sector for the Year 2007-08
Source
Electricity
LPG

Consumption
124
379

Unit
MU
MT

Consumption
124025208
5508259

Unit
kWh
kWh

Total

129533467

kWh

LPG
4%

Electricity
96%

Figure 8 :

Share Of Fuels In Energy Balance

26

Electricity is the main source of energy in commercial sector.


Table 12 : Summary of Commercial establishments/institutes in the city
Educational Institutes
Primary Schools/ Nursery

306

Intermediate & High schools

41

Universities/ colleges/ Technical Institutes

Hospitals
Small hospitals and nursing homes with less than 50 beds
Hospitals with 50-100 beds

190
30

Hotels
Budget hotels

Restaurants
Large Restaurants

50

Medium Restaurants

100

Small Restaurants

350

Food Cart

225

2.3.2. Results of sample survey


Similar to the residential sector, a survey questionnaire has been prepared for commercial sector to
understand the energy usage. The summary of the survey is given below. The data shown below are
specific to the surveyed consumers only. Commercial consumers are classified in three categories
based on the energy consumption.

Figure 9 :

Consumer classification (kWh/month)

27

Table 13 : Household appliances inventory


End Use

Type of Appliances

Lighting

Incandescent
CFLs
Fluorescent Tube
Fluorescent Tube
Others
Space
Air Conditioner
Conditioning
Fans Ceiling, Table,
Pedestal
Refrigeration
Refrigerator
Cooking
Cooking Equipment
Laundry
Laundry Equipment
Office Equipments Office Equipment
Computers

% of surveyed
establishment
owning the
appliance
41.38%
66.01%
83.25%
7.9%
4.92%
47.00%
100.00%
63.00%
13.85%
6.98%
10.77%
34.88%

Average
number of
appliances per
surveyed HHs
1
2
2
2
3
5
2.9

Average
Usage/day

1
NA
NA
NA
NA

Average
Wattage

6
3
3
6
5
6.02
7.08

60
16
40
30
20
1800
100

24
NA
NA
NA
NA

400
NA
NA
NA
NA

Fuel usage:

Electricity
LPG
Diesel
Other

- 98.8%
- 21.3%
- 20.0%
- 3.8% (total is more than 100 due to multiple fuel usage)

Average monthly fuel consumption:


Electricity consumption varies from 69 to 22462 kWh and the average consumption is 2147
per consumer.
Electricity bill varies from Rs.200 to 223670 and the average bill is Rs.17400 per consumer.
LPG consumption is 3.7 cylinders per consumer (considering 80 consumers).
Diesel consumption 45 liters per consumer (considering 80 consumers).

28

Figure 10 :

Figure 11 :

Lighting Technology Used by Consumers

Awareness and Usage of Energy Efficient Lighting Technologies

Cooking and other appliances:


Consumers having cooking appliances in their premises: 44.7%
Appliances used for cooking (%age of consumer using):
LPG/PNG stove
39.6%
Microwave
6.4%
Steam cooking
4.3%
Any other
4.3% (total is more than 44.7% due to multiple appliances)
Average LPG consumption is 3.7 cylinders per month.
Consumer having water heating equipment in their premises 19%
Hot water is mainly used for kitchen and bathroom. The fuel used for water heating is electricity
and LPG. Central boiler and storage heaters are used for getting hot water.

29

Interest shown for SWH installation:


Table 14 : Interest Shown By Consumers for Solar Water Heater Installation
Yes
No, it would be too expensive
No, it would be impractical for this facility
No, it is too risky and unproven

39%
37%
21%
3%

2.4. Industrial Sector


Type of Industry
Electrical Equipment
Chemical Manufacturing
Rayon
Dyes
Textile based cottage industry
Others
Total number of industries registered with MSEDL

Number
NA
NA
NA
NA
NA
NA
1985

2.4.1. Energy consumption


Table 15 : Industrial Sector Energy Consumption
2005-06

2006-07

2007-08

Electricity (MU)

26

26

33

LPG (MT)

Table 16 : Energy Balance for Industrial Sector


Source
Electricity
LPG

Consumption
33
7

Unit
MU
MT

Consumption
33
0.1

Unit
MU
MU

Total

33.1

MU

2.4.2. Results of sample survey


There were only three industries operating during the time of survey and the data is collected only from
them.

30

2.5.

Municipal Sector

The major energy end-uses under the Municipal sector include streetlights, water supply and sewage
treatment plant. Energy consumption data for these three segments is shown in the Table below. Energy
consumption for the Govt. buildings and facilities is considered to be falling under commercial sector.

Overall Municipal Sector Energy Consumption:


Table 17 : Overall Municipal Sector Energy Consumption (MU)
2005-06

2006-07

2007-08

2008-09

Street light

7.59

6.78

7.60

6.97

Water Supply

18.63

21.61

21.50

23.19

Sewage Treatment Plant

0.49

0.58

1.63

1.42

TOTAL

26.71

28.97

30.73

31.57

Table 18 : Energy Consumption for Street lighting(kWh)


2003-2004
560154
1375286
1694312
1264605
1280000
829000
1042000
8045357

A - Ward
B - Ward
C - Ward
D - Ward
F - Ward
G - Ward
H -Ward
Total

2004-2005
595325
1484190
1861769
1268401
1033000
771000
982000
7995685

2005-2006
632981
1317136
2419524
1141844
655000
553000
869000
7588485

2006-2007
663030
1277391
1460280
1272099
682000
599000
830000
6783800

2007-2008
784220
1377950
1617534
1430598
896000
588000
904000
7598302

Water Pumping:
Table 19 : Electricity Consumption in Water Pumping (MU)
2003-2004

2004-2005

2005-2006

2006-2007

2007-2008

Barave Water
Treatment Plant
Dombivali (E)
Kalyan (E)
Kalyan (Rural)
Dombivali (W)

14741558
1385298
152000
566333

15660710
1559426
319300
560556

15914849
1480239
226100
512559
498385

17623560
1523660
209000
525652
1726848

17350336
1430916
312660
628941
1781914

Total

16845189

18099992

18632132

21608720

21504767

Waste Water Treatment Plant:

Table 20 : Energy Consumption in waste water treatment plant (MU)


2003-04
G.K. Pumping
Kolsewadi Pumping
Sewage Treatment plant
Ganesh Ghat Pumping

119738
54638
32299
18000

2004-05
251136
65384
23328
44147

2005-06
122073
66340
16405
30473

2006-07
177691
57940
13650
49459

2007-08
1302859
43422
17721
27625
31

Retibunder Pumping
LalChowki Pumping
P.S-I Pumping
PS-II Pumping
P.S-III Pumping
STP

17628
82800
21520
127844
21520
16594

15043
86609
23420
133525
23420
13512

24417
67378
20081
97200
20081
25010

34628
70632
23516
110180
23516
20311

26695
63248
16385
96098
16385
17223

Total

512581

679524

489458

581523

1627661

2.6. City Wide Green House Gas Inventory


2.6.1. City level Emissions
The citys inventory was conducted by compiling the best available data on energy consumption. The ICLEI
SA study reveals that all activities in Kalyan Dombivli city contribute to 954923.8 T e CO2 in 2007-08. The Per
capita emission for Kalyan Dombivli city is 0.70 T/ Year in 2007-08. The corporation level emission is about
2.65 % to the total city level emissions. The GHG emission has gone up by 21.57% in last three years, which is
raising serious environmental sustainability concern and also energy security in near future. As per the study,
the total electricity consumption has gone up by 21.92% in last three years.

7%

3%

3%
5%

82%

Electricity

Figure 12 :

LPG

Petrol

Diesel

Kerosene

Share of GHG Emissions by Sector

Above fig summarizes the city GHG emission by source. The electricity consumption accounts for 82% of the
Citys total carbon emissions. The diesel consumption produces 7% of the Citys total carbon emissions. The
LPG consumption in the city accounts for 5% of total emission and the Petrol & kerosene has another 3%
each.
2.6.2. Government Emissions
Greenhouse gas emissions from City of Kalyan-Dombivli government operations totaled 28107 metric tons of
CO2e in the year 2008-09, which is approximately 3.28% of the Citys total emissions. Figure presents the
distribution of greenhouse gas emissions from City government by sector. Buildings account for 8% of the City

32

governments CO2e emissions. The Citys water supply system represents 68 % of the City governments CO2e
emissions. Electricity used to power streetlights represented 20% of the emissions.

Figure 13 :

Share of GHG emission in Government sector

33

CHAPTER 3
This chapter forecasts the future consumption of Kalyan Dombivli based on baseline energy consumption,
past data and population growth. The forecasts figures gives us a clear view of the future conventional
energy demands in the city based on which the strategies have been developed and substantiated.

3. ENERGY DEMAND FORECAST FOR KALYAN DOMBIVLI


There are two scenarios for which the projections have been done. First is based on the population growth
and the second is based on the time-series data on energy use during last five years.

3.1. Forecasting Based on Population Growth


Population projection for Kalyan Dombivli Municipal Area has been done in city development plan (CDP)
under JNNURM scheme. The table gives the data population data as per the CDP. Based on this data,
population for year 2008, 2013 & 2018 has been interpolated considering linear growth between relevant
years e.g. for calculating the population in year 2008, linear growth is considered between year 2006 & 2011
and then interpolation is done.
Table 21 : Population Projection till 2020
Base year population (2001)

10,47,297

Projection @3.82% for year 2005

12,16,729

For year 2010

14,67,570

For year 2015

17,70,125

Projection @3% for year 2020

20,52,060

Forecasting for the year 2013/2018


The projections for fuel consumption have been done assuming that they fuel consumption will grow at the
same rate as population. The table given below summarizes projections for year 2013 and 2018.
Table 22 : Energy Consumption Projection (MU)
Population
Electricity
LPG

2008
1367234
968
207

2013
1649103
1167
250

2018
1939286
1373
294

34

Figure 14 :

Forecasting for Energy Consumption (MU) based on population growth

Forecasting Based on Past Data


The table given below gives the projected values for the year 2013 and 2018. Based on the past data, a linear
growth has been considered and the projection has been done.
Table 23 : Energy Consumption Projection for KDMC (MU)
Year
Electricity consumption
LPG

Figure 15 :

2008

2013

2018

968
207

1410
269

1856
332

Forecasting of Energy Consumption (MU) based on historical data

35

Forecasting based on national average of 25 cities data


The Table 24 : given below gives the projected values for the year 2013 and 2018. Based on the 25 cities
past data from ICLEI South Asias Carbon and Emissions Profiles of 54 South Asian Cities report, a linear
growth has been considered and the projection has been done.
Table 24 : Energy consumption projection for KDMC (MU)
Energy Sources
Electricity consumption
LPG

3.2.

2008

2013

2018

968
207

1265

1562

Goal for the year 2013

Since, transportation sector is not included in this study and petrol, diesel and kerosene consumption data is
not available for different sectors, the energy usage for electricity and LPG is considered for defining the
energy target. Based on this data, the targeted reduction in energy consumption (10% of the total based on
past data projection) for the year 2013 would be 168 MUs.
Table 25 : Forecasting of Energy Consumption for KDMC
Energy Sources

Electricity (MU)
LPG (MU)
Total (MU)

Based on
population growth
(MU)
1167
250
1417

Based on
past data
(MU)
1410
269
1680

Based on
25 cities data
(MU)
1265

36

CHAPTER 4
This chapter delves into renewable energy resource assessment and strategy for introducing different
Renewable Energy Technologies in residential, commercial, industrial and municipal sector of Kalyan
Dombivli city. Renewable energy resource availability and potential is a key criterion for suitable
renewable energy technology installations and success. The chapter later develops the strategies for
Kalyan Dombivli city based on the renewable energy available in the city and the baseline energy
consumption and future energy demands of the city.

4. RENEWABLE ENERGY STRATEGIES FOR KALYAN DOMBIVLI


The main objective of this chapter is to identify available renewable energy resources in Kalyan Dombivli city
and carry out techno-economic feasibility of different renewable energy options for residential, commercial,
industrial and municipal sector and making a priority listing of the options.
A renewable energy resources assessment has been done to identify the potential renewable energy sources
for the Kalyan Dombivli city. This includes assessment of solar radiation, wind power density and availability,
biomass resources and municipal/industrial wastes etc. The strategy has been prepared for each sector
identifying most techno economically viable renewable energy options considering wide range of potential
consumers in the particular sector. An implementation target for development of solar city project in 5
years period has been set with an objective to meet at least 5% energy consumption from renewable energy
on completion of the solar city project in Kalyan Dombivli.
For the residential sector, potential for introducing the following renewable energy devices has been worked
out based on present energy use pattern of the residents, economic level, availability of such products and
economic feasibility.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)

Solar Water Heaters


Solar Cookers
Solar Lanterns
Solar Home System
Solar PV system for Home Inverters
PV for replacement of DG/ Kerosene Generator sets
Renewable Energy Systems for Residential Housing Complexes

Commercial and Institutional Sector has been divided in to four broad categories as below and these
categories again sub divided into further categories based on their capacity and functional differences.
(i)
(ii)
(iii)

RE Strategy for Hotels budget hotels


RE Strategy for Restaurants Large, medium, small, food cart
RE Strategy for Hospitals 250-1000 bedded, 100-250 bedded, 50-100 bedded, Dispensaries/
37

dental clinic/ microsurgery


(iv) RE Strategy for Educational Institutes Primary, intermediate, colleges, engineering colleges,
medical colleges, Computer Institute, Polytechnics, ITI
On the spot assessment have been carried out visiting each of these sub categories to identify present
energy demand, energy and fuel used, load shedding occurs, standby power supply provision, space
available for installation of solar arrays and collectors etc. Based on the site visit and energy demand
assessment, preliminary design/sizing of appropriate renewable energy devices have been worked out for
each category establishment. An indicative budgetary financial implication, energy savings, payback period
and GHG emission reduction has been estimated for each renewable energy option that has been suggested.
Industrial sector is broadly divided into five categories. Suitable renewable energy technologies have been
prepared for each of the category.
(i)
Electrical Equipment
(ii)
Chemical Manufacturing
(iii)
Rayon
(iv)
Dyes
(v)
Textile based cottage industry
Municipal Sector is divided into seven categories and options for appropriate renewable energy options have
been recommended based on the assessment made on each category of the sector.
(i)
(ii)
(iii)
(iv)
(v)
(vi)

Buildings - Municipality building and other Office Buildings


Markets General markets, vegetable markets
Parks Municipality Parks
Outdoor lighting Road safety- Street light, monuments, road blinkers,
Municipal Solid Waste
Sewage Treatment Plant

4.1. Renewable Energy Resource Assessment


A preliminary assessment has been done for solar, wind and biomass resources and energy recovery
potential from municipal solid waste and sewage treatment plant. While biomass data is for entire Kalyan
Dombivli district, there is no hydro potential in the city.
4.1.1. Solar Radiation
Kalyan Dombivli (Latitude 27.18 N, Longitude 78.02 E) receives good amount of solar radiation as the average
annual solar radiation for Kalyan Dombivli is presented in the below table.
Table 26 : Monthly Averaged Insolation Incident on a Horizontal Surface (kWh/M2/Day)
Source
NASA SSE Satellite

Jan
4.97

Feb
5.66

Mar
6.4

Apr
6.72

May
6.56

Jun
4.62

Jul
3.54

Aug
3.49

Sep
4.3

Oct
5.18

Nov
4.94

Dec
4.58

Annual
5.08

MNRE Solar

4.60

5.41

6.18

6.62

6.49

4.86

3.74

4.03

4.54

5.00

4.61

4.29

5.07

38

Figure 16 :

Annual Solar Radiation profile in Kalyan Dombivli

4.1.2. Wind Energy


Wind data18 for Kalyan-Dombivli is presented in the table below. Generally, average annual wind speeds of at
least 4.0-4.5 m/s are needed for a wind turbine to produce enough electricity to be cost-effective. From the
wind data, there seems to be less potential for wind energy in Kalyan- Dombivli. Detailed Study is required
for assessment of energy generation potential from wind resource
Table 27 : Monthly averaged wind speed above earth surface for terrain similar to airports (m/s)
Height
10 m
50 m

Jan
2.39
3.02

Feb
2.84
3.6

Mar
3.14
3.97

Apr
3.48
4.41

May
3.8
4.8

Jun
3.93
4.98

Jul
4.26
5.39

Aug
3.86
4.88

Sep
2.64
3.34

Oct
2.19
2.77

Nov
2.13
2.7

Dec
2.17
2.75

4.1.3. Biomass Resource


Biomass resource for Kalyan Dombivli is not available separately. However, the data is available at district
level and presented below in the Table. Major agricultural products of the district are Paddy, Nagli, Pulses,
Oilseeds, Spices and Flowers. Though the potential of power generation for biomass is estimated to be
93MWe for the entire district, apparently there is no potential of power generation from biomass within the
Kalyan Dombivli city.
Table 28 : Biomass Resource
District

Thane
Thane

Area
(kHa)
149.7
593

Crop
Production
(kT/Yr)
356.5
NA

Biomass
Generation
(kT/Yr)
591
854

Biomass
Surplus
(kT/Yr)
105.4
577.2

Power
Potential
(MWe)
12.5
80.8

Biomass Class

Agro
Forest & wasteland

39

4.1.4. Waste generation


Waste generation data for Kalyan Dombivli Municipal area for the last 5 year is presented in the table given
below.
Table 29 :
Year

Solid waste
Generation
(MT/day)

2002-2003
2003-2004
2004-2005
2005-2006
2006-2007
2007-2008

500
520
540
560
580
600

Solid Waste Generation Data

Paper
Products
39.5
41.08
42.66
44.24
45.82
47.4

Food
300
312
324
336
348
360

Waste Composition
Wood /
Plant debris
Textiles
35
10
36.4
10.4
37.8
10.8
39.2
11.2
40.6
11.6
42
12

% Other Waste
(inorganic)
115.5
120.12
124.74
129.36
133.98
138.6

4.1.5. Liquid Waste from Sewage Treatment Plant


Kalyan Dombivli has two Sewage Treatment Plants. The first sewage treatment plant has a capacity of
treating 14 MLD and the second one has the capacity of 16 MLD.

RE Strategy for Residential sector

4.2.

With projected population of 14.67 lakh (2010) and 3.05 lakh households, the residential sector is the major
energy consumer in the Kalyan Dombivli city. The residential sector consumes 81% of total electricity
consumption of 968MU in Kalyan Dombivli city. The sector consumed 981MU of energy, which includes
primarily electricity and LPG. Electricity is the major fraction (79%) of energy consumed by the residential
sector. Use of renewable system to cater a part of energy demand in residential sector can substantially
reduce fossil fuel consumption and green house gas emission. Different renewable energy options have
been proposed based on technology available and economic feasibility. Only those renewable energy
devices are recommended which are technically proven, commercially available and attractive in terms of
financial benefit from energy savings.
(i)

Installation of Solar Water Heating System

In 2006, Kalyan Dombivli Municipal Corporation (KDMC) made it compulsory for all the newly constructed
buildings to install solar energy system for heating water as geysers and water heaters consume lots of
electricity. Since then, no building in the suburb has been issued No Objection Certificate (NOC) and
Occupancy Certificate on completion unless the solar system is installed.
The target in 5 years for introduction of SWHs is set at 10% of residential consumers who are already using
electric geysers for their daily hot water requirement. Introduction of solar water heating system could save
up to 15.4 MU energy per year. Cost implication and energy savings potential is presented in the table below.

40

Table 30 : Target for SWHs installation in Kalyan Dombivli City


Single Household

Unit

Average size of domestic SWH (2 sqm collector area)

100/125

LPD

Total energy saved per year

1575

kWh

Indicative cost of installation

20000

INR

MNRE Subsidy @Rs.1100.00 per sqm

2200

Cost of energy savings


Payback period

5512.5

INR

Years

305289

Nos.

Target for entire city


Total Residential household
Residential household using geysers
Target to replace electric geyser by SWH in 5 years
Average size of domestic SWH (2 sqm collector area)

32%
10%
100/125

LPD

Number of SWH to be installed in 5 years plan

9769

Nos.

Total collector area in sqm

19538

Sqm

Total energy saved per year

15.4

MU

Indicative cost of installation

1953.85

Lakh

MNRE Subsidy @Rs.1100.00 per sqm

214.92

Lakh

Cost of energy savings

538.53

Lakh

Years

12463

Tonnes

Payback period
Emission reduction per year

(ii) Use of Solar cookers (Box and dish type)


Both box type solar cooker and dish type solar cooker can be promoted in the urban areas. Box type solar
cooker is an ideal device for domestic cooking during most of the year, except for the monsoon season and
cloudy days. It however cannot be used for frying or chapatti making. It is durable and simple to operate. On
the other hand, dish type solar cooker can be used for indoor cooking. The stagnation temperature at the
bottom of the cooking pot could be over 300oC depending upon the weather conditions. The temperatures
attained with this cooker are sufficient for roasting, frying and boiling. Regular use of a box type solar cooker
may save 3-4 LPG cylinders per year. The use of solar cooker to its full capacity may result in savings up to 10
LPG cylinders per year at small establishments. Setting a target of 5% residential consumer to adopt solar
cooker (75% box type and 25% dish type) in the 5 years period, a total of 0.43 million kg of LPG could be
saved by reducing 1491 tonnes of GHG from Kalyan Dombivli City (considering specific emission from LPG as
0.24 kg CO2 per kWh).
Table 31 : Target for introducing solar cooker in Kalyan Dombivli City
Solar Cooker for residential use
Total Residential household
Household having facility to install a solar cooker
Target for introducing of solar cooker in 5 years
Number of Solar Cooker to be installed in 5 years plan
Average savings of LPG domestic cylinder per year (14kg)

305289
40%
5%
6106
5

Unit
Nos.

Nos.
Nos.

41

Total LPG saved per year


Total energy saved per year
Indicative cost of installation (75% box type & 25% SK-14)
MNRE subsidy for solar cooker @30%
Cost of energy savings
Payback period
Emission reduction per year

427405
6.21
160.28
48.08
106.85
1.05
1491

kg
MU
Lakh
Lakh
Lakh
Years
Tonnes

(iii) Solar lanterns to replace kerosene lamps


Solar lantern has the average capacity of providing three hours of continuous light from a single charge per
day, and can work as source of light for poor families without electricity. Kerosene is the main source of
burning light in poor families in Kalyan Dombivli particularly during load shedding hours and survey results
reveal that 14% of population use kerosene lanterns during load shedding to illuminate their houses.
Average consumption of kerosene per household is 9 litres per month. Assuming a household uses 3-4
lanterns, consumption of one lantern will be about 3 litres per month. Targeting 10% of population to
replace at least one kerosene lantern with solar lantern out of 14% of total population who uses kerosene
lamps a 0.46 million litres of kerosene could be saved reducing 1172 tonnes of GHG per year. Detailed
techno commercial is provided in the table below.
Table 32 : Target for introducing solar lanterns in Kalyan Dombivli City
Capacity of residential Solar Home System
Number lights per Solar Lantern
Number of Kerosene lamp replaced by SL
Consumption of kerosene per lanterns/month
Cost of kerosene per litre in the market
Cost of kerosene per year per household
Indicative cost of installing a SL
MNRE subsidy @50%
Payback period when replacing the kerosene lamps
Total Residential household
Residential household use kerosene lamps
Target to replace kerosene lamp in 5 years
Number of SL to be installed in 5 years plan
Total kerosene lamp replaced
Indicative cost of installation
Kerosene saved
Savings in terms of Electricity
Cost of kerosene savings
MNRE subsidy @50%
Payback period
Emission reduction per year

10
1
1
3
20
720
3000
1500
2.1
305289.00
14%
10%
12822
12822.1
384.66
461597
4.64
92.32
192.33
2.1
1172

Unit
Wp
Nos.
Nos.
Litres
INR
INR
INR
INR
years
Unit
Nos.

Nos.
Nos.
Lakh
Litres
MU
Lakh
Lakh
years
Tonnes

42

(iv) Use Solar Home Systems (SHS)


A Solar Home System is a fixed indoor lighting system and consists of solar PV module, battery and balance of
systems. Capacity of such system could be of 18Wp, 37Wp and 74Wp for different configuration. The
luminaries used in the above systems comprise compact fluorescent lamp (CFL) of 7 W / 9 W / 11 W capacity
respectively. The fan is of DC type with less than 20 W rating. One Battery of 12 V, 40 / 75 Ah capacity is also
provided with SPV modules of 37Wp / 74Wp as required. The system will work for about 4 hours daily, if
charged regularly. The Solar Home Lighting systems have been proposed to replace kerosene lamps used by
14% population in Kalyan Dombivli Municipality area during load shedding hours. A 74Wp Solar Home
System can replace 3-4 kerosene lamps with 4-5 hours backup hence replacing entire need of kerosene,
which is estimated at an average of 9 litres per month per household. Assuming 10% replacement in the
planned 5 years period an estimated amount of 0.67 million litres of kerosene could be saved reducing 1707
tonnes of GHG emission from the city. The potential of kerosene replacement with Solar Home Systems and
financial implication thereon is indicated in the table below.
Table 33 :

Target for introducing solar home system in Kalyan Dombivli City

Single residential household

Unit

Capacity of residential Solar Home System

74

Wp

Number lights per Solar Home System

Nos.

Number of Kerosene lamp replaced by SHS

Nos.

Consumption of kerosene per household/month (survey result)

13

Litres

Cost of kerosene per litre in the market

20

INR

Cost of kerosene saved per year per household

3144

INR

Indicative cost of installing a SHS

16000

INR

MNRE subsidy @50%

8000

INR

2.5

Years

Payback period when replacing the kerosene lamps


Target for the Entire City
Total Residential household
Residential household use kerosene lamps

Unit
305289

Nos.

14%

Target to replace kerosene lamp in 5 years

10%

Number of SHS to be installed in 5 years plan

4274

Nos.

Total kerosene lamp replaced

17096.2

Nos.

Indicative cost of installation

683.85

Lakh

672

KL

MU

Cost of kerosene savings

134

Lakh

MNRE Subsidy @50%

342

Lakh

2.5

Years

1707

Tonnes

Kerosene saved
Savings in terms of Electricity

Payback period
Emission reduction per year

(v) Using Solar PV for Home Inverters


Use of solar panels to charge Home Inverter system could be an attractive option as standby power supply
system during load shedding hours. The power supply situation in Kalyan Dombivli is very poor. About 5-6
43

hours load shedding occurs per day in most of the places of Kalyan Dombivli city. About 58% of residential
consumer use inverters during load shedding hours. Assuming that 15% of HH who are already using inverters
will adopt the 250 Wp solar PV systems to charge their inverter battery, an aggregate of 6.64MWp solar PV
systems could be installed in the residential buildings, which will generate 9.96 MU green energy per year and
reduce the load demand and emission by 8067.64 tonnes per year. It is assumed that MNRE will provide 50%
subsidy for these system. The potential of energy savings, green house gas emission reduction and
budgetary financial implication is indicated in the table below.
Table 34 : Target for introducing Solar PV for Home Inverters in Kalyan Dombivli City
Solar PV for Home Inverters

Unit

Capacity of solar PV system for Home Inverter

250

Wp

Indicative cost of incorporating Solar PV to Home Inverter

30000

INR

Total Residential household

305289

Nos.

Residential household use Inverter during load shedding

58%

Target to introduce solar charger for inverter in 5 years

15%

Number of solar inverter to be installed in 5 years plan

26560

Nos.

Total PV capacity installed

6640

kWp

Energy generated by PV arrays per year

9.96

MU

Cost of energy saved

349

Lakh

Indicative cost of installation

7968

Lakh

MNRE subsidy @50%

3984

Lakh

11

Years

8067.64

Tonnes

Payback period
Emission reduction per year

(vi) Using Solar PV for replacement of DG/ Kerosene Generator sets


Due to poor power supply situation, about 20% of resident of Kalyan Dombivli use typically 5-10kW DG/
kerosene generator sets during the load shedding hours. Solar PV power packs can be used to replace those
polluting generator sets with high operating cost. A 1000 Wp solar PV power pack has been considered for
an average household in Kalyan Dombivli. For 5-year framework 10 % households have been taken into
consideration for replacement of DG /kerosene sets with solar PV systems with a target to save 7.33 million
litres of diesel per year reduce GHG in the tune of 18610 tonnes per year.
Table 35 : Target for replacement of diesel generator sets with PV Power Pack in Kalyan Dombivli City
Solar PV for replacement of DG/ Kerosene Generator sets
Capacity of solar PV system
Indicative cost of Solar power pack
Total Residential household

Unit
1

kWp

2.00

Lakh

305289

Nos.

Residential household use generators during load shedding

20%

Target to introduce solar power pack in 5 years

10%

Number of solar power pack to be installed in 5 years plan

6106

Nos.

Total PV capacity installed

6106

kWp

Energy generated by PV arrays per year

9.16

MU

44

Typical generator set used


Average fuel consumption per day for 4-6 hours load shedding
Amount of diesel saved per year for entire city
Cost of Diesel saved
Indicative cost of installation
MNRE subsidy @50%, subject to maximum of Rs.1.00 Lakh per kWp
Payback period

5-10
6
7327

litres
KL

2930.77

Lakh

12211.56

Lakh

6105.78

Lakh

2.08

Emission reduction per year for replacement of diesel

kW

18610

Years
Tonnes

(vii) RE systems for residential Apartments/ housing complexes


Kalyan Dombivli has more than 8000 registered residential apartment building societies in the city with
average number of 25 families in each society. Solar water heaters and solar PV power plants are
considered to be most viable renewable energy devices for the existing and well as new residential
complexes.
Table 36 : RE system for residential apartments
Number of residential apartment complex society

8000

Number of residential apartment per society

10%

Number of Residential Apartments Blocks to Introduce RE system

800

Average number of Residence in each apartment Block

25

Solar Water Heater System


Average size of Solar water heaters
Total capacity of SWH to be installed in 5 years plan

2000

LPD

1600000

LPD

Total collector area in sqm

32000

Sqm

Total energy saved per year

18.9

MU

Indicative cost of installation

1600.00

Lakh

MNRE subsidy @Rs.1900.00 per sqm

608.00

Lakh

Beneficiary/ State/ KDMC share

992.00

Lakh

Cost of energy savings

661.50

Lakh

1.50

years

16000

Tonnes

12.5

kWp

15

Lakh

Total capacity of PV systems for targeted apartments for 5 years

10000

kWp

Energy generated by PV arrays per year

15.00

MU

Payback period
Emission reduction per year
Solar PV Power Plant for Back up power
Capacity of solar PV system for single apartment of 50 Residence
Indicative cost of incorporating Solar PV to Home Inverter

Cost of energy saved

525

Lakh

Indicative cost of installation

12000

Lakh

MNRE subsidy @50%

6000

Lakh

Beneficiary/ State/ KDMC share

6000

Lakh

11

years

12150

Tonnes

Payback period
Emission reduction per year

45

(viii)

Summary of RE strategy for Residential Sector

Implementation of renewable energy projects as proposed above will save 83.02MU energy per year, which
will reduce GHG of 69231 tonnes per year. When achieved the target, residential sector strategy will meet
49.41% of total target for energy savings for the city as per mandate of development of solar city. The entire
target could be achieved with a total investment of about Rs.345.62 in the 5 years period where contribution
from MNRE will be about Rs.163.00cr with existing schemes and balance fund could be met from users, state
or other funding agencies. It is recommended that promotion of solar water heaters in residential sector
should be given higher priority, as energy savings from solar water heaters is the highest.
Table 37 : Summary of RE Strategy for Residential sector in Kalyan Dombivli City
RE Strategy for residential sector

Units
of
Target

Target
Capacity

Investment
(Lakh)

Installation of Solar water Heaters

Nos.

9769

1953.85

Use of solar cookers

Nos.

6106

Use of Solar Lantern

Nos.

Use of Solar Home Lighting System

Nos.

Use of Solar Home inverter

Nos.

Use of PV for replacing DG sets

Nos.

Solar Water Heaters for Residential

LPD

Solar PV Power Pack for Residential

kWp

MNRE
subsidy
(Lakh)

Users
contribu
tion
(Lakh)

Energ
y
Saved
per

214.92

1738.93

15.39

Emission
s
Reductio
ns
(T
)
12463

160.28

48.08

112.19

6.21

1491

12822

384.66

192.33

192.33

4.64

1172

4274

683.85

341.92

341.92

6.76

1707

26560

7968.04

3984.02

3984.02

6106

6105.78

6105.78

9.16

8068
18610

1600000

608.00

992.00

18.90

9.96
1861
16000

8000

4800.00
34562.24

4800.00
16295.0
6

12.00
18267.1
8

0
9720
83.02

16000
12150
69231

4.3. RE Strategy for Commercial and Institutional Sector


The commercial and institutional sector is the second highest consumer of energy in Kalyan Dombivli city. The
sector consumes about 13% of total electricity consumed in the city with its 354 educational institutes, 220
medical service facilities, 5 hotels and 725 odd restaurants. Different strategies are prepared for different
categories of consumers based on type and quantum of energy consumed and availability of resource and
space to generate renewable energy in their premises. While preparing the strategy, only techno
economically viable and commercially available renewable energy options are considered.
4.3.1. RE Strategy for Hotels
Kalyan Dombivli city does not have much of the big hotels. The city has 5 budget hotels and other
commercial accommodations facilities. Some case studies are made to assess renewable energy and energy
conservation measures in hotels. Major energy requirement such as hot water and electricity during load
shedding hours could be met by solar energy. Solar thermal system can be used to generate hot water or
steam for cooking. Solar PV power plant can be used to reduce or eliminate use of diesel generators which
are being used during load shedding hours. Apart from that hotels also generate bio waste which can be

46

used to produce biogas through bio-methanation process. Solar pumps and solar garden lights can be used
for sprinkling water and beautification.
(i)
Renewable Energy Systems for Budget Hotels cum Bar & Restaurant
Hotel Raja has been chosen as the case study site for a budget hotels energy consumption portfolio. The
tables below give us the energy appliances utilized by a typical budget hotel in Kalyan Dombivli. Based on the
energy baseline scenario specific renewable energy systems have been proposed which can help in energy
saving at the case study site. The occupancy of the hotel has been taken to be 50% for the calculations
mentioned below.
Table 38 : Case Study of Budget Hotel cum Bar & Restaurant
Location of the Hotel

Kalyan Dombivli

No of rooms

16

Nos.

Roof Area available

150

sqm

Shadow free open space at ground

15

sqm

Average Load Shedding

Hours/day

1620

kg

82.5

KVA

48

liters/ day

Monthly LPG consumption for cooking


Standby Power Supply System:
Diesel Generator 1 (off peak load)
Average consumption of diesel per day
Electrical Energy Demand:
Electrical Appliances

No

Ope
ratin
g
Hou
rs

Wattage
of the
device
(in watt)

Load
(kW)

Energy
consumpti
on /day at
50%
occupancy
(kWh)

Ceiling Fans (throughout the year)

16

12

60

0.96

5.76

Air Conditioner (throughout the year)

16

10

1800

28.8

144.00

Electric Geyser (throughout the year)

16

1750

28

28.00

Television

16

10

100

1.6

8.00

Incandescent (light Bulb)

16

10

60

0.96

4.80

Compact Fluorescent

32

15

0.48

1.44

Fluorescent (Long, 4 Feet Tube)

16

10

55

0.88

4.40

Ceiling fans

14

12

60

0.84

10.08

Air conditioner

16

10

1800

28.8

288.00

168

15

2.52

15.12

Fluorescent (Long, 4 Feet Tube)

10

55

0.22

2.20

Incandescent (Light Bulb)

10

60

0.24

2.40

Refrigerators/ Freezer

560

2.24

17.92

Television

100

0.1

0.80

Water pump

3750

7.5

30.00

Computers

24

100

0.1

2.40

Printer

10

100

0.1

1.00

104

566.00

Guest Rooms

Common area and other facilities

Compact Fluorescent

Total energy consumption

47

The renewable energy systems proposed for the budget hotel in Kalyan Dombivli are enlisted in the tables
below. The techno economics of installing the RE systems has also been provided.
Solar Water Heating system to replace geysers and preheating of water for
Approximate area required for installation
Indicative cost of the system
MNRE subsidy @1400.00 per m2
Energy savings per day average
Considering 4 months use of geyser (using 75% of water) & 12 months of hot
water for cooking (using 25% of water) savings per year will be
Savings of electricity per year
Savings of LPG per year
Annual cost savings from saving electricity
Annual cost savings from saving LPG
Total savings
Payback period
Emission reduction
Rooftop PV system for diesel abetment
Approximate area required
Indicative cost of the system with 1 day battery backup
MNRE Subsidy @Rs.1.00lakh per kWp
Approximate annual energy generation
Fraction of DG power replaced
Amount of diesel saved per year
Cost savings from diesel per year
Annual O&M Cost of DG sets
Payback period
Emission reduction
Biogas system
Organic Waste from kitchen and other services per day
Biogas plant recommended
Investment
MNRE subsidy @50%
Users share
LPG saved per year
Energy in terms of MU savings per year
Cost savings per year
Payback period
Emission Reduction per year

2000
60
350000
84000
70
12688

LPD
sqm
INR
INR
kWh
kWh

6300
6388
439.38
31500
17575
49075
5
10
30
30
7500000
3000000
45000
47%
8182
327273
75000
11
36

kWh
kWh
kg
INR
INR
INR
years
tones
kWp
sqm
INR
INR
kWh
litres
INR
INR
years
tonne

30
3
0.5
0.25
0.25
438
0.00636
0.1752
1.43
0.267

kg
CuM
Lakh
Lakh
Lakh
kg
MU
Lakh
Years
Tonn

4.3.2. Renewable Energy Systems for Restaurants


Kalyan Dombivli has a number of restaurants and eateries. The city has more than 700 restaurants and which
are categorised as large restaurant, medium restaurants/Dhabas and small restaurants. Solar water heaters
can easily be introduced in these restaurants to meet their hot water demand for cooking and utensil
48

cleaning. Since all the restaurants are using DG sets as standby power supply source during load shedding,
PV power plant will be an attractive and profitable option for the restaurants
Cart food is very popular in Kalyan Dombivli. These carts serve piping hot traditional North Indian food and
hence are preferred by all. There are hundreds of food cart which use kerosene or gas operated lights for
illumination. Solar Lanterns will be a profitable and attractive option for these food cart operators.

(i)

RE strategy for Restaurants

Restaurants have been separately taken up for case studies as innumerable such establishments are found
across India which are huge energy guzzlers. Kalyan Dombivli city also has innumerable restaurants of which
Gurudev restaurant has been chosen as a case study site.
Table 39 : Case Study of Restaurant
Location of the Restaurant

Kalyan Dombivli

Roof Area available

150

Connected load

50

kW

Average Load Shedding

Hours/day

2700

kg

100-120

Kg/day

65

KVA

11.52

kL

Monthly LPG consumption for cooking


Organic waste generated

sqm

Standby Power Supply:


Diesel Generator
Average consumption of diesel per year
Electrical Energy Demand:
Electrical Appliances
Ceiling Fans (12 months)
Air Conditioner (12 months)
Micro oven
Milk Chiller
Deep Freezer
Compact Fluorescent
Air conditioner for cold
Television
Water pump 1
Water pump 2
Computers
Printer
OTG
Total

Nos.

Operati
ng

5
4
5
1
1
123
2
3
2
1
12
1
1

12
10
6
8
8
12
10
8
4
4
24
3
4

Load
(W)
60
2000
1000
740
560
20
1500
100
1500
1000
100
100
800

Total
Load
0.30
8.00
5.00
0.74
0.56
2.46
3.00
0.30
3.00
1.00
1.20
0.10
0.80
26.46

Energy
consump
3.60
80.00
30.00
5.92
4.48
29.52
30.00
2.40
12.00
4.00
28.80
0.30
3.20

Use
per
365.00
365.00
365.00
365.00
365.00
365.00
365.00
365.00
365.00
365.00
365.00
365.00
365.00

Energy
Consumpt
1314
29200
10950
2161
1635
10775
10950
876
4380
1460
10512
110
1168
85490

Based on the portfolio of energy consumption in the restaurant following renewable energy systems have
been recommended to save energy. The techno economics of installing the PV system is provided below.

49

Solar Water Heating system to replace LPG for preheating of water for cooking:

1000

LPD

30

sqm

150000

INR

MNRE subsidy @1400.00 per m

42000

INR

Energy savings per day average


Savings of LPG per year

35
12775

kWh
kWh

878.76

kg

Approximate area required for installation


Indicative cost of the system
2

Annual cost savings from saving LPG

35150

INR

3.07

years

Emission reduction

tonnes

Rooftop PV system for diesel abetment

20

kWp

Approximate area required

20

sqm

Indicative cost of the system with 1 day battery backup

4500000

INR

MNRE Subsidy @Rs.75.00 per Wp

1500000

INR

30000

kWh

Payback period

Approximate annual energy generation


Fraction of DG power replaced

40%

Amount of diesel saved per year

4552

litres

Cost savings from diesel per year

182086

INR

Annual O&M Cost of DG sets

50000

INR

Payback period

13

years

Emission reduction

24

tonnes

100-120

kg

Biogas plant recommended

10

CuM

Investment

0.5

Lakh

MNRE subsidy @50%

0.25

Lakh

Users share

0.25

Lakh

LPG saved per year

1460

kg

Energy in terms of MU savings per year

0.02

MU

Cost savings per year

0.58

Lakh

Payback period

0.43

Years

Emission Reduction per year

0.89

Tonnes

Biogas system
Organic Waste from kitchen and other services per day

(ii)

Summary of RE strategy for Restaurants

Introduction of RE system in 25% of restaurants in Kalyan Dombivli city as described in the table below will
save 1.85MU of energy per year and reduce GHG emission by 1518.81 tonnes. Introduction of solar water
heater system should be given prime importance followed by biogas system and solar PV system for diesel
abatement.

50

Table 40 : Summary of RE strategy for Restaurants


Restaurants

Numbers

RE System Proposed
SWH/SC PV system Biogas/
system
kWp
Biomass
LPD/
system
Nos.
(cum)

Energy
Savings (MU)

Total Emission
reduction
Tonnes/ year

Large Restaurants
Medium Restaurants/ Dhabas
Small Restaurants
Food Cart
Aggregate

50
100
350
225
725

250000
100000
70000
0
420000

1250
50.00
87.50
0.02
1388

500
500
1050
0.00
2050

4.83
1.26
0.96
0.34
7.39

4069.50
1105.50
900.20
0.02
6075.22

Target 25% for 5 years


Total investment (Lakh INR)
MNRE subsidy (Lakh INR)
Beneficiarys contribution (Lakh INR)

181

105000
105
29
76

347
780
347
434

513
51.25
25.63
25.63

1.85

1518.81

* Replacing kerosene by using 2 lanterns in one cart

4.3.3. Renewable Energy Systems for Hospitals


The Kalyan Dombivli city has 220 health care facilities, which includes two hospitals owned by Municipal
Corporation with more than 100 beds each, a railway hospital with 50 beds, one maternity with 30 beds and
some small hospitals with 15-20 beds capacity each. Apart from that the city has other health care facilities
like dispensaries, dental clinic, microsurgery, day care centre and pathological laboratories.
To portray the energy consumption scenario in these facilities a 50 and 20 bed Hospitals have been chosen
in Kalyan Dombivli city. Detailed energy consumption data have been collected and specific
recommendations for renewable energy systems have been made. An average occupancy of 75% has been
considered for making all calculations.

(i)

Renewable Energy Systems for 50 bedded Hospital

Wockhardt Hospital has been chosen as the case study site for a 50 bed hospital in Kalyan Dombivli. The
general details and the energy consumption pattern of the hospital are mentioned in the tables below.
Table 41 : Case Study of 50 bedded hospital
Location of the Hospital
No of beds
Roof Area available
Connected Load
Average Load Shedding
Average electricity bills per month
Average occupancy
Standby Power Supply:
Diesel Generator 1 (off peak load)
Diesel Generator 2 (peak load)
Average consumption of diesel per day

Kalyan Dombivli
50
Nos.
200
sqm
150
KVA
4
Hours/day
1.00
Lakh
75%
75
125
72

KVA
KVA
Liters/ day

51

Electrical Energy Demand:


Electrical
Nos.
Appliances

Opera
ting
Hours

Watt/
unit

Load
(kW)

Energy
consumption
/day at 100%
occupancy
(kWh)

Energy
consumption
/day at 75%
occupancy
(kWh)

Utilizatio
n /year

Energy
Consump
tion per
year

Ceiling Fans

70

12

60

4.2

50.40

37.80

270

10206

Air Conditioner

20

10

1800

36

360.00

270.00

150

40500

Electric Geyser

30

1750

52.5

210.00

157.50

120

18900

200

10

55

11

110.00

82.50

365

30113

Fluorescent tube
Water pump

8820

17.64

70.56

70.56

365

25754

Computers

24

100

0.6

14.40

14.40

365

5256

Printer

100

0.2

0.60

0.60

365

219

Auto clave

5000

10

20.00

20.00

365

7300

132

836.00

653.00

138248

Based on the energy demand in this building the following renewable energy systems have been
recommended for the 100 bedded hospitals.
Solar Water Heating system to replace geysers and preheating of
Approximate area required for installation
Indicative cost of the system
MNRE subsidy @1400.00 per m2
Energy savings per day average
Electricity savings per year
Annual cost savings from saving electricity
Payback period
Emission reduction
Rooftop PV system for diesel abatement
Approximate area required
Indicative cost of the system with 1 day battery backup
MNRE Subsidy @Rs.75 per Wp
Approximate annual energy generation
Fraction of DG power replaced
Amount of diesel saved per year
Cost savings from diesel per year
Annual O&M Cost of DG sets
Payback period
Emission reduction

(ii)

3000
90
750000
126000
157.5
57488
287437.5
2.17
47
30
30
67.50
22.50
45000
51%
13500
5.40
0.75
7
36

LPD
sqm
INR
INR
kWh
kWh
Lakh
years
tonnes
kWp
sqm
Lakh
Lakh
kWh
litres
Lakh
Lakh
years
tonnes

Renewable Energy Systems for 20 bedded Hospital

Shivam General Hospital has been chosen as the case study site for a 20 bedded hospital in Kalyan Dombivli.
It is one of the primary medical facilities in Kalyan Dombivli. The energy baseline scenario of the Hospital
reveals huge energy consumption on daily basis, supplemented by a high capacity diesel generator back-up
of 150 KVA. An average occupancy of 75% has been taken to provide the calculations given below.

52

Table 42 : Case Study for 20 bed hospital


Location of the Hospital
No of beds
Roof Area available
Premise area
Connected Load
Average Load Shedding
Average electricity bills per annum
Average occupancy
Standby Power Supply:
Diesel Generator 1
Diesel Generator 2
Average consumption of diesel per day

Kalyan Dombivli
20
200
450
80
5
10.00
75%

Nos.
sqm
sqm
kW
Hours/day
Lakh

50
100
52

KVA
KVA
Liters/ day

Electrical Energy Demand:


Electrical Appliances

Nos.

Operatin
g Hours

Watt/
unit

Load
(kW)

Energy
consumpti
on /day at
100%
occupancy
(kWh)

Energy
consumpti
on /day at
75%
occupancy
(kWh)

Utilizat
ion
/year

Energy
Consump
tion per
year

Table Fans

10

10

60

0.60

6.00

4.50

365

1643

Ceiling Fans

50

18

60

3.00

54.00

40.50

365

14783

Air Conditioner

15

10

1800

27.00

270.00

202.50

365

73913

Television

25

100

2.50

17.50

13.13

365

4791

Refrigerator

10

250

1.25

12.50

9.38

365

3422

Autoclaves

8820

17.64

105.84

79.38

365

28974

Water Pump

1000

2.00

12.00

9.00

365

3285

Incandescent 60 watt

20

20

60

1.20

24.00

18.00

365

6570

Incandescent 100 watt

20

20

100

2.00

40.00

30.00

365

10950

Compact Fluorescent

40

20

11

0.44

8.80

6.60

365

2409

Fluorescent Tube, Long

20

20

40

0.80

16.00

12.00

365

4380

Computers

15

20

150

2.25

45.00

33.75

365

12319

100

0.40

1.60

1.20

365

438

61.08

613.24

459.93

Printers
Total

167874

Recommended Renewable Energy Systems


The energy consumption baseline assessment of the 50 bedded hospital in Kalyan Dombivli, lead to the
recommendation of Solar water heater to address the daily hot water requirement and PV systems for diesel
abatement.

53

Solar Water Heating system to replace geysers and preheating


of water for cooking:
Approximate area required for installation
Indicative cost of the system
2
MNRE subsidy @1400.00 per m
Energy savings per day average
Electricity savings per year
Annual cost savings from saving electricity
Payback period
Emission reduction
Rooftop PV system for diesel abatement
Approximate area required
Indicative cost of the system with 1 day battery backup
MNRE Subsidy @Rs.75 per Wp
Approximate annual energy generation
Fraction of DG power replaced
Amount of diesel saved per year
Cost savings from diesel per year
Annual O&M Cost of DG sets
Payback period
Emission reduction

(iii)

2000
60
400000
84000
105
23625
118125
2.68
19

LPD
sqm
INR
INR
kWh
kWh
INR
years
tonnes

20
20
4500000
1500000
30000
67%
12653
506133
150000
5
24

kWp
sqm
INR
INR
kWh
litres
INR
INR
years
tonnes

Summary of RE strategy for Hospitals

The analysis of the above two case studies of a 50 bedded hospital and a 20 bedded hospital in Kalyan
Dombivli has revealed the huge energy consumption patterns in sector. Hospitals are a growing
infrastructure need of any developing city. Hence the source to future energy consumptions lies in the
proper streamlining of energy consumption patterns in these building sectors. Policy mandates and
programmes for facilitating the adoption/installation of renewable energy technology in these building type
will be a milestone for future energy savings. Adoption of Renewable energy systems in 25% of the hospitals
will save 1.80MU energy per year reducing GHG emission by 1507 tonnes per year. The payback period for
solar water heater system for hospitals is about one year only due maximum use of hot water in health care
facility.
Table 43 : Summary of RE systems for Hospitals
Hospitals
Small hospitals and nursing homes < 50 beds
Hospitals with 50-100 beds
Aggregate
Targeting 25% implementation
Investment (Lakh)
MNRE subsidy @Rs.1400.00 per sqm
Beneficiary/state/KDMC contribution

Nos.
190
30
220
55

RE System
SWH/SC
PV
380000
90000
470000
117500
117.5
33
85

190
900
1090
273
613
273
341

Energy
4.77
2.41
7.19
1.80

Total
4031.80
1998.00
6029.80
1507.45

54

4.3.4. Renewable Energy Systems for Educational Institutes


Educational institutes are major establishments in the commercial sector of a city. Although they are not
major source of energy consumption in the city yet they account for a substantial degree of energy
utilization. The official website of Kalyan Dombivli gives the following figures of educational institutes in
Kalyan Dombivli. The city has 308 primary/ nursery schools, 41 intermediate and high schools, two
engineering colleges, five degree colleges. The government primary schools provide free mid-day meal to its
students. Community solar cookers can be used to cook mid-day meal in these schools. The institutes
having hostels can use solar water heater to supply hot water to the bath rooms and the kitchen thereby
providing bathing comfort to the students and hot water for cooking.

(i) Use of Solar cookers for cooking mid-day meals in primary schools
Solar Cookers can have an apt utilization for cooking mid-day meals in primary schools. Assuming 50% of the
schools in Kalyan Dombivli have a mid-day meal programme a target of 50% for the framework of 5 years has
been considered.
Table 44 : Target for Introducing Solar Cookers in Primary Schools
Total no of schools
Schools providing mid day meal for students
Target for introducing of solar cooker in 5 years
Number of Solar Cooker to be installed in 5 years plan
Average savings of LPG domestic cylinder per year (14kg)
Total LPG saved per year
Total energy saved per year
Indicative cost of installation
MNRE subsidy for solar cooker @30%
Beneficiary/ State/ KDMC share
Cost of energy savings
Payback period
Emission reduction per year

306
62%
50%
95
10
13280
0.19
18.97
5.69
13.28
3.32
4.00
46

Unit
Nos.

Nos.
Nos.
kg
MU
Lakh
Lakh
Lakh
Lakh
years
Tonnes

(ii) Summary of RE strategy for Educational Institutes


The two renewable energy options can effectuate a considerable energy saving in educational institutes are
the solar water heaters and solar PV systems. The potential for energy savings in different educational
institutes in Kalyan Dombivli is tabulated below. The figures give a gross idea about the financial implications
and emission reductions rendered by installation of the aforementioned renewable energy systems.

55

Table 45 : Summary of RE strategy for educational institutes


RE System Proposed
Educational Institutes

Numbers

Primary Schools/ Nursery


Intermediate & High schools
Engineering Colleges
Degree Colleges
Aggregate
Target 25% in 5 years
Investment (Lakh INR)
MNRE subsidy @Rs.1750.00 per sqm
Beneficiary/state/KDMC contribution

306
41
2
5
354
89

SWH/SC
system

PV system

LPD/ Nos.
95
0
10000
2500
12500
3125
22
11
12

kWp

Biogas/
Biomass

Energy
Savings

0
0
0
0
0
0
0
0
0

0.19
0.02
0.13
0.07
0.41
0.10

77
10
10
25
122
30
68
30
38

Total
Emission
Tonnes/
46.34
12.51
112.20
55.50
226.54
56.64

(iv)
Summary of RE strategy for Commercial and Institutional Sector
The target of RE strategy for commercial and institutional sector is to achieve about 3% of total energy
savings requirement. The strategy, once implemented fully will save 5MU of energy per year and reduce GH
of 3187.33 tonnes per year. The primary focus should be given to introduction of solar water heaters for
hotels, restaurants, hospitals and other residential institutes, which will save 1.80MU per year. Solar PV
power plant should be introduced for diesel abatement in the establishment that are using diesel sets as
standby power supply source. The restaurants and hotels that has considerable amount of food and organic
waste, should introduce biogas system. Use of solar cooker for preparing mid-day meal in primary schools
will be an attractive option to save LPG for cooking and creation of awareness and demonstration about use
of renewable energy devices among school children.
Table 46 : RE Strategy for Commercial and Institutional Sector
RE Strategy for Commercial
and Institutional sector

Solar Cooker for mid-day


meal in schools
Solar Water Heaters for
Hotels, Restaurants,
Solar PV Power Plant for
Hotels, Restaurants,
Biogas for Hotels and
Restaurants

Pote
ntial
User
s

Target
Users
(Nos.)

Units
of
Target

Target
Capaci
ty

Total
Investm
ent
(Lakh)

MNRE
subsid
y
(Lakh)

Sate/
KDMC/
Benefici
ary's

Amou
nt of
Energ
y

Emission
s
Reductio
ns per

18.97

5.69

13.28

0.19

46.34

247.60

73.72

173.88

2.70

2286.25

153

95

Nos.

1304

326

LPD

95
24362
5

1304

326

kWp

662

1490.20

662.31

827.89

0.99

808.02

730

183

CuM

525

52.50

26.25

26.25

1.11

46.73

1809.27

767.97

1041.30

5.00

3187.33

4.3.5. RE Strategy for Industrial Sector


The industry sector in Kalyan Dombivli consumes 3.40% of total electricity and considerable amount of coal,
diesel and LPG for its different manufacturing and process industries. Kalyan Dombivli City has about 1985
odd small and medium scale industries. On the eastern side of the Kalyan city, there is a large industrial

56

complex where electrical equipment, rayon, and dyes and other chemicals are manufactured. There are also
a large number of textile-based cottage industries. Dombivli is the home to many chemical manufacturing
units. Target should be made to introduce solar water heaters and PV power plants in the industries in
Kalyan Dombivli as shown in the table below. The system capacity assumed is average capacity and will vary
based on the size of the industry and energy requirement. Introducing proposed systems in 25% of the
industries will save 11.71MU of energy per year reducing 9747 tonnes of GHG emission.
Table 47 : RE Strategy for industrial sector in KDMC
RE System Proposed
Small Scale Industries

Nos.

SWH system

Energ
y
Savin
gs

Total
Emissio
n
reductio

0.12

97

Electrical Equipment

159

PV system
159x0.5kWp

Chemical Manufacturing

794

794x2000LPD

794x10kWp

30.67

25567

Rayon

496

496x1000

496x10kWp

13.30

11011

Dyes

397

198500

199

2.64

2227

Textile based cottage industry

139

139x0.5kWp

0.10

85

1985

2282500LPD

13248kWp

46.83

38987

496

570625

3312

11.71

9747

570.63

7451.72

94.15

3311.88

476.47

4139.84

Aggregate
Targeting 25% implementation
Investment (Lakh)
MNRE subsidy @Rs.1400.00
Beneficiary/state/KDMC
ib i

4.3.6. RE Strategy for Municipal Sector


The municipal sector of Kalyan Dombivli city consumes 3.10% of total electrical energy in the city. The
primary consumers in this sector are street lights, outdoor lights in parks and monuments, markets, office
buildings of the Municipal Corporation, water supply, sewerage treatment plant etc. Renewable energy
devices are suggested to all categories of consumers depending upon the energy demand. The sector has
ample opportunity to save energy through introducing renewable energy and energy conservation measures
and could show case these initiatives to encourage people to adopt further.
(i) Renewable Energy System for Municipality building and other Office Buildings
The main administrative building of the municipal corporation consumes about 0.55 MU of electricity per
year. The loads consume most of the energy are air conditioners, fans and lighting loads. A 70kWp PV Power
plant is recommended for the building to supply power during load shedding hours.

57

Table 48 : RE Strategy for KDMC municipal sector


Main Administrative Building, Municipal Corporation, KDMC

Name of the Building


Total premise area

23400

sqm

Built up area

3375

sqm

hours/day

Average Load Shedding


Electrical appliances in
municipal building

Total
Nos.

Table fans
Ceiling Fans
Exhaust fans
Wall Fans
Air Conditioner I
Air Conditioner II
Air Conditioner III
Air Conditioner IV
Air Conditioner V
Television
Refrigerator
Electric Water Pump
Water Cooler
Incandescent
CFLs
Fluorescent Long
36 watt CFLs
Computers
TOTAL

34
241
44
10
42
2
4
6
2
2
2
2
5
38
30
766
80
250

Load
(W)
60
60
300
100
1800
9000
6000
3600
2400
100
200
11250
300
60
11
55
36
100

Total
Load
(kW)
2.04
14.46
13.20
1.00
75.60
18.00
24.00
21.60
4.80
0.20
0.40
22.50
1.50
2.28
0.33
42.13
2.88
25.00
271.92

Hours of
Operation

Consumption
/ Day (kWh)

9
9
9
9
6
6
6
6
6
4
1
4
4
4
5
8
4
10

18
130
119
9
454
108
144
130
29
1
0
90
6
9
2
337
12
250
1597

Annual
Utilization
(days)
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300

Annual
Consumpti
on (kWh)
5508
39042
35640
2700
136080
32400
43200
38880
8640
240
120
27000
1800
2736
495
101112
3456
75000
554049

Recommended Renewable Energy System:


Rooftop PV system for diesel abatement
Approximate area required
Indicative cost of the system with 1 day battery backup
MNRE subsidy for diesel abetment @75.00/Wp
Approximate annual energy generation
Fraction of DG power replaced

70

kWp

70

sqm

157.50

Lakh

52.50

Lakh

105000

kWh

27%

Amount of diesel saved per year

18981

Ltrs.

Cost savings from diesel per year

7.59

Lakh

Annual O&M Cost of Generator sets

2.00

Lakh

Payback period

11

years

Emission reduction

53

tonnes

58

(ii) Renewable Energy System for Markets


Kalyan Dombivli city does not has any particular market as such. The shops are scattered around. But there
are some shopping complexes in the city like one is Jhojhwaala shopping complex in the main city. These
kind of shopping complexes can be chosen in the city for installation of RE technologies like Solar PV and can
be replicated in other establishments as well.
Table 49 : RE Systems for Shopping Complexes
Unit
Capacity of solar PV system for Shops
Indicative cost of incorporating Solar PV to Shop's
inverter
Total no of shops in eight markets
Shops uses Inverter during load shedding

500

Wp

60000

INR

200

Nos.

100%

Target to introduce solar charger for inverter in 5 years

50%

Number of solar inverter to be installed in 5 years plan

100

Nos.

Total PV capacity installed

50

kWp

0.08

MU

Lakh

Indicative cost of installation

60

Lakh

MNRE subsidy @50%

30

Lakh

User's share

30

Lakh

years

61

Tonnes

Energy generated by PV arrays per year


Cost of energy saved

Payback period
Emission reduction per year

(iii)

RE System for Outdoors lighting (Streets, Traffic, Road safety etc.)

The city has about 10322 outdoor lights, which have been fixed for illumination streets, wards, etc. The
objective is to introduce one solar PV outdoor light in every three conventional lights so that minimum
illumination level is maintained during load shedding hours. The tables below indicate targets, investment
thereon and energy savings potential etc.
Table 50 : RE Systems for Outdoor lights, Road safety
Street Light Details

Existing SL
(Nos.)

Solar SL
(Nos.)

250/70 watt sodium points


40 watt tube light point
Simple Bulb Point
High Mast
400 watt flood light point

7011
454
2391
184
198

2337
151
797
61
66

Total

10238

3413

Targeting 50% in 5 years


PV module capacity (Wp)
Total PV Module capacity (kWp)
Total Investment (Lakh INR)

1706
40
68
256
59

MNRE subsidy @50% (Lakh INR)


KDMC/ State/ Beneficiary share (Lakh INR)
Energy Generated (MU per year)
Emission reduction (Tonnes per year)
Payback period (Years)

128
128
0.10
83
25

Table 51 : Summary of RE Strategy for outdoor light and road safety


RE Strategy for Kalyan Dombivli City Street and Road Safety
LED based solar Street Light in every 3 alternative existing

Total

Road Stud @ 1 stud in 2m for 50% of 91km main road

Investment

3413

1706

255.95

13

3.25

120

60

9.00

7500

1875

22.50

Solar PV Traffic Lights (2x74Wp) @


Solar Blinkers (37Wp) @

Target

Total Investment required (Lakh INR)

290.70

MNRE subsidy @50% (Lakh INR)

145.35

KDMC/States share(Lakh INR)

145.35

Energy saved (MU per year)

0.12

Emission reduction (Tonnes per year)

93.63

(iv)
Renewable Energy Systems for Parks
Kalyan Dombivli City has 16 Municipal Parks where electrical energy is consumed for outdoor lighting and
water pumping for sprinkling irrigation. Solar PV outdoor lights and solar pumps are recommended for these
parks.
Table 52 : Renewable Energy Systems for Parks
No. of

Unit load (W)

Total

Hours of

Energy

Flood light

250

2.25

10

22.5

CFL outdoor light

50

20

1.00

10

10

Water Pump

1000

1.00

10

10

1270

4.25

30

42.5

Nos.

Capacity

Unit

Investme

30

74

Wp

6.64

kWp

1.75

Total
RE Options:
Options
Converting 50% of
Providing solar pump for

Table 53 : Summary of RE Strategy for Kalyan Dombivli Corporation Parks


Total Number of Parks in Kalyan Dombivli
Targeting 50% in 5 years
Total PV system capacity per park
Total investment
MNRE Subsidy @50%
KDMC/ state/ Park Operator

16
8
3.18
53.10
26.55
26.55

Nos.
Nos.
kWp
Lakh
Lakh
Lakh

60

Energy saved per year


Emission reduction per year
Cost of electricity saved per year
Payback period

(v)

0.04
30.94
1.91
14

MU
Tonnes
Lakh
Years

Summary of RE Strategy for Municipal Sector

The Municipal sector can contribute 0.98MU energy savings per year through introducing RE devices in the
different municipal utilities and services reducing GHG emission by 795.44 tonnes per year.
Table 54 : Summary of RE Strategy for Municipal Sector in Kalyan Dombivli
RE Strategy for Municipal Sector

Units
of
Target

Target
Capacit
y

Total
Investme
nt (Lakh)

MNRE
subsidy
(Lakh)

Sate/
KDMC/
User's
Share
(Lakh)

Amount
of
Energy
Saved
(MU)

Emissions
Reductions
per year
(Tonnes)

70kWp PV Power Plant for


Municipal and other Office

Nos.

10

1575.00

788

787.50

0.75

610

LED based Solar Street Light

Nos.

1706

255.95

127.98

127.98

0.10

83

Solar PV Traffic Lights

Nos.

3.25

1.63

1.63

0.00

Solar Blinkers (37Wp)


Road Stud @ 1 stud in 2m for
50% of 30 km main road
Outdoor lights for Parks

Nos.

60

9.00

4.50

4.50

0.00

Nos.

1875

22.50

11.25

11.25

0.01

Nos.

236

53.10

26.55

26.55

0.03

21

Solar Pumps for Parks


PV system for Inverters in the
k h

Nos.

14.00

7.00

7.00

0.01

10

Nos.

100

60

30

30

0.08

61

1992.80

996.40

996.40

0.98

795.44

4.3.7. Waste to Energy Potential in Kalyan Dombivli


Discussion with MSW department in the KDMC, reveals the waste characterization for Municipal Solid waste
in Kalyan Dombivli to be as indicated in Table 55 :. Based on 2006 figures, the total waste quantity at
dumpsites and at the dustbins aggregated to 600 MT/day. The total waste generated can be classified as
biodegradable and non - biodegradable.
Table 55 : Municipal Solid Waste Characterization (2006)
Waste Composition
Bio-degradable
Non-biodegradable (Inert)
Total Waste
Per capita waste (Kg/capita/day)

Percentage Waste
45.00%
55.00%
100%
300 gms/day/person

Quantity (MT/Day)
270
330
600

A rough assessment of the potential of recovery of energy from MSW through different treatment methods
can be made from knowledge of its calorific value and organic fraction, as under. Since relevant details are
not available for Kalyan Dombivli, widely used estimates for municipal solid waste in India have been used.

61

(i)

Waste to Energy Potential through thermo-chemical conversion

In thermo-chemical conversion all of the organic matter, biodegradable as well as non-biodegradable,


contributes to the energy output. Total electrical energy generation potential is estimated to be 0.73MWe
and savings per year with 70% PLF is estimated as 4.46 MU.
Table 56 : Waste to Energy through thermo-chemical conversion
Unit
Total waste generated
Net Calorific Value (conservative estimate)
Energy recovery potential ( NCV x W x 1000/860)
Power generation potential

(ii)

25

Tonnes

2400

kcal/kg

69767

kWh

2907

kW

Conversion efficiency

25%

Net Power generation potential

0.73

Plant Load Factor

70%

MWe

Net electrical energy savings potential @70% PLF

4.46

MU

Emission reduction per year

3610

Tonnes

Total Investment

509

Lakh

MNRE subsidy @ 50% subject to maximum of Rs.300.00 per MW

218

Lakh

State/City/Private Power Producer

291

Lakh

Cost savings

201

Lakh

Payback period

1.45

Years

Waste to Energy Potential through bio-methanation

In bio-chemical conversion, only the biodegradable fraction of the organic matter can contribute to the
energy output. It is estimated that a 0.26MWe electrical energy generation is possible from this process
which could save about 1.60 MU of energy every year assuming a 70% of PLF.
Table 57 : Waste to Energy through bio-methanation
Unit
Total waste generated

25

Tonnes

Total biodegradable volatile solid (VS)

30%

Typical digester efficiency

60%

Typical bio-gas yield (m3 / kg. of VS destroyed)

0.80

CuM/kg

Biogas yield

3600

CuM

calorific Value of bio-gas

5000.00

Energy recovery potential

20930.23

Power generation potential

872

Conversion efficiency

30%

Net Power generation potential

0.26

kcal/CuM
kWh
kW
MWe

Plant Load Factor

70%

Net electrical energy savings potential

1.60

MU

Emission reduction per year

1299

Tonnes

Total Investment
MNRE subsidy @ R.200.00 lakh per MW

157

Lakh

52

Lakh
62

State/City/Private Power Producer


Cost savings
Payback period

(iii)

105

Lakh

72

Lakh

1.45

Years

Liquid Waste to Energy Potential from Sewage Treatment Plant (STP)

Kalyan Dombivli City has two sewage treatment plants through which approximately 30 MLD of wastewater
being treated every day. Energy consumption in these sewage treatment plants is about 1.63 MU per year
(2007-08). The produce of waste water treatment can be used as a raw material for anaerobic distention
and subsequent power generation. A very preliminary assessment shows that there is potential of
generating 1.05MWe power which could deliver 6.42 MU of electrical energy per year with 70% PLF. Surat
Municipal Corporation has established three such power plants with aggregate capacity of 3.50MWe with
financial support from MNRE which have been running successfully since several years. A detailed study has
to be made for Kalyan Dombivli to generate power from STPs.
Table 58 : Waste to Energy from Sewage Treatment Plant
Unit
Total waste water generated

30

MLD

Total biodegradable organic/ Volatile Solid available for Biomethanation

30

Tonnes/day

Typical Digestion Efficiency


Typical Biogas yield
Biogas yield
Electricity (kWh)

60%
0.8

cum / kg

14400

cum

83720.93

kWh

Capacity of the plant

3488.37

KW

Conversion Efficiency

30%

Total Electricity Generated

1.05

MWe

Plant Load Factor

70%

Net electrical energy savings potential

6.42

MU

Emission reduction per year

5198

Tonnes

Total Investment

627.91

Lakh

MNRE subsidy @40% subject to maximum of Rs.200.00 lakh/MW

209.30

Lakh

State/City/Private Power Producer

418.60

Lakh

Cost savings

288.77

Lakh

1.45

Years

Payback period

(iv)

Summary of Waste to Energy Potential in Kalyan Dombivli City

Total solid waste generated in Kalyan Dombivli is 600MT/day and capacity of two waste treatment plants is
30 MLD. A very preliminary assessment for energy recovery from MSW and STPs has been done based on
the widely used assumptions and presented in the table below.

63

Table 59 : Summary of waste to energy potential in Kalyan Dombivli City


RE Strategy for Municipal
Sector

Units
of
Target

Targ
et
Capa
city

Total
Investm
ent
(Lakh)

MNRE
subsidy
(Lakh)

Amount
of Energy
Saved
(MU)

Emissions
Reductions
per year
(Tonnes)

218

Sate/
KDMC/
User's
Share
(Lakh)
291

Waste to Energy Potential


for thermo-chemical
conversion
Waste to Energy Potential
for bio-methanation
Liquid Waste to Energy
Potential from Sewage
Treatment Plant (STP)

MWe

0.73

509

4.46

3610

MWe

0.26

157

52

105

1.60

1299

MWe

1.05

628

209

419

6.42

5198

1293.60

479.65

813.95

12.48

10107.10

4.3.8. Application of biogas plants


Biogas from Kitchen Waste:
Using bio-methanation technology all domestic bio waste including wastewater
from the kitchen can be used to produce biogas. Use of domestic waste to produce
biogas will help in reducing consumption of cooking fuel and better waste
management in the cities. The municipal corporation will also save energy and
expenses in collection and disposal of such waste.
The biodegradable waste material and wastewater from the kitchen is fed into the
plant through the inlet chamber of the plant. This waste is converted into biogas
with the help of a special type of anaerobic bacteria. The main component of the
gas produced is methane. The space required for a domestic plant is about one
square meter. The portable plant developed by M/s Biotech can be installed in a day
depending upon the model of the plant. The gas generated from the waste of a
family of 3 -5 members is sufficient to operate for 2 hours per day in a single burner
stove. Typical payback period of such plant is about 2 years. The slurry in liquid form
can be used as fertilizer.
Biogas from Institutional Waste:
Conversion of bio waste generated in the iinstitutions like hostels,
hospitals, hostels, old age-homes, could be a highly attractive way
of reducing waste disposal hassle and save fuel for cooking and
making hot water. In the same time the cooking fuel consumption
of these Institutions is also very high. The solid Bio Manure /
Organic fertilizer generated from the pre digesters can be utilized as
a fertilizer.

64

Toilet attached Biogas Plant:


Like any other bio waste, human excreta can be treated through biomethanation process to produce biogas.
The night soil bas biogas plant can replace the conventional septic tank. Treated slurry coming out from the
plant can be utilized as liquid fertilizer. All other easily biodegradable waste can also be treated together
with human excreta in the same plant. Apart from residential apartments, the public institutions like hostels,
hostels, hospitals etc the toilets can be attached with large sized plants for treating the human wastes for
the production of biogas. The size of such plants is determined in accordance with the total number of
inmates of those institutions. The treatment plant can be installed either as a single unit or more units in
different locations. The installation of a night soil based biogas plant is more convenient during the building
construction time.
Sl.
No.

Plant Size
(CuM)

1
2
3
4
5

1
2
3
4
6

Production of
gas per day
(CuM)
1
2-3
3-5
4-6
6-10

Suitable for
Family
Members
1-5
5-7
7-10
10-15
15-20

Max
Treatable
Waste (Kg)
2
3-5
5-8
8-12
10-20

Organic
Waste Water
(Litre)
20-25
25-40
40-50
50-60
60-70

Reference: http://www.biotech-india.org/

65

4.3.9. Solar Thermal for cooling


Introduction:
Solar energy can be used for the cooling purposes in place of conventional air conditioners used in large
commercial buildings now a day. The commercial establishments particularly hospitals, hotels and other
institutional buildings use huge amount of conventional energy to power the air conditioners used for the
cooling purposes in these commercial premises. Application of renewable energy for the cooling purposes
can save a substantial amount of energy and the resultant emissions. As per an independent energy audit
conducted by civic authorities, the compressor based central AC system had a specific energy consumption
of 1.19 kilo watt per tonne, whereas a new AC system would have specific energy consumption of 0.89 kilo
watt per tonne. Now a days air conditioners are used in almost all the commercial and industrial
establishments. In a city like Kalyan Dombivli having more than 1,500 number of big commercial
establishments, an estimation of total energy savings by use of solar cooling facilities can be made.
How it works?
The installation of solar cooling system is an unique
combination of parabolic reflecting mirrors, heat receivers,
insulated plumbing, boilers for storing the steam and
vapour absorption machine (VAM). The mirrors with high
reflectivity are focused on receivers containing water
through a tracking system. The parabolic mirrors are
capable of generating steam. The steam is routed through
boilers for storage and getting the desired pressure to be
fed in to the Vapour Absorption Machine. The VAM with lit
hium bromide absorbers chills the water and steam which
separates the absorbent from the water. The chilled water is circulated through the ducts cooling the air
flowing in it. The circulation of steam, air and water can be ensured with a pump.
As hot water is generated as a by-product it can be used for drinking, bathing and laundry. The steam which
is generated can also be used for disinfecting the linen in the laundry and sterilise surgical equipments.
A centralized solar AC system is being implemented in Chhatrapati Shivaji Maharaj Hospital at Kalwa in
district Thane. The entire project cost of this 160 tonne solar air conditioning system is apprx INR 3.99. It is
expected to save electricity worth INR 40 lakh per annum.
Application and usage:
The solar air conditioning systems introduced by Sharda Inventions are useful for large scale centralized
applications with capacities of 10 TR and above. In near future the solar air conditioning system will be
introduced for household applications as well.

66

CHAPTER 5
This chapter delves into Energy Efficiency strategy for residential, commercial, industrial and municipal
sector of Kalyan Dombivli city. The chapter later develops the strategies for Kalyan Dombivli city based
on the Energy conservation and Energy Efficiency measures in the city and the baseline energy
consumption and future energy demands of the city.

5. ENERGY EFFICIENCY STRATEGIES FOR KALYAN DOMBIVLI


While renewable energy technologies would provide clean energy, EE and DSM measures would help in
reducing the energy demand. Energy Efficiency (EE) initiatives are the most financially feasible energy saving
options in India today. In this report the EE measures have been thoroughly analyzed for all the four sectors,
i.e. residential, commercial, industrial as well as municipal. The financial and technical analysis is provided
for each strategy suggested in all the sectors. The list of EE and DSM measures suggested for different
sectors is given below:
Residential Sector:

Replace Incandescent Lamps with Fluorescent


T5 tube light + Electronic Ballast to replace T12/T8 tube light+ Magnetic Ballast
Efficient ceiling fans to replace conventional ceiling fans
Replacement of conventional air-conditioners with EE star rated ACs
Replacement of conventional refrigerators with EE star rated refrigerators
Replacement of conventional water pumps with EE water pumps
Reduce energy consumption in existing private buildings
Reduce energy consumption in all new construction

Commercial and institutional building Sector:

Replace Incandescent Lamps with Fluorescent


T5 tube light + Electronic Ballast to replace T12/T8 tube light+ Magnetic Ballast
Efficient ceiling fans to replace conventional ceiling fans
Replacement of conventional air-conditioners with EE star rated ACs
Replacement of conventional refrigerators with EE star rated refrigerators
Replacement of conventional water pumps with EE water pumps
Industrial Sector:
Replace Incandescent Lamps with Fluorescent
T5 tube light + Electronic Ballast to replace T12/T8 tube light+ Magnetic Ballast
67

Efficient ceiling fans to replace conventional ceiling fans


Replacement of conventional air-conditioners with EE star rated ACs
Energy efficiency in motors, furnaces, boilers, etc.
Municipal Sector:

Replacement of 150 watt HPSV with LEDs


Replacement of 40 watt T8/T12 tube lights with T5 tube lights
Sensors for automatic on/off of street lights
Proper pump-system design (efficient Pump, pumps heads with system heads
Installation of variable speed drivers
Power saver installation in pump house
Plugging of leakages in the water supply system and use of efficient pumps and motors
Energy Efficiency Measures in WTP

A sector-wise techno-economic analysis of potential energy efficiency and DSM measures has been carried
out.

5.1.

EE Strategy for Residential sector

Residential sector consumes largest amount of energy. Important proven and cost effective measures for
the sector are described in this section. Based on the survey, it was found that incandescent lights are still
used a lot in the residential sector. Utilizing the survey data the savings due to replacement of incandescent
lamps with CFL are calculated and are presented in the table below.
(i)
Replace Incandescent Lamps with Fluorescent
Incandescent bulbs are the major and the most common source of high energy consumption in the residential
area. Replacement of incandescent lamps has acquired a substantial precedence in all the energy efficiency
strategies as the most feasible option. The techno commercial for replacement of incandescent bulbs with
CFL is given below. An assumption of 80% households utilizing CFLs has been considered as target group for
replacements and an 80% replacement is assumed for the calculations below.
Table 60 : Replacement of incandescent lamps with fluorescent
Total Residential household
Household using incandescent bulb
Target to replace incandescent bulb with CFL
Number of incandescent bulb to be replaced per household
Total number of incandescent bulb to be replaced
Indicative cost of installation
Energy saved by replacing 60W bulb with 15W CFL
Cost of electricity savings
Payback period
Emission reduction per year

305289
41%
80%
1
100135
150
9868284
345
0.43
7993

Unit
Nos.

Nos.
Nos.
Lakh
kWh
Lakh
years
Tonnes

68

(ii)

T5 tube light + Electronic Ballast to replace T12/T8 tube light+ Magnetic Ballast

A conventional tube light (with magnetic ballast consuming 15W) consumes around 55 watts. It can be
replaced with T5 tube (28W) with electronic ballast (4W) which will require around 32W. The calculations
have been done for a period of 5 years assuming 80 % replacement of T 12 /T8 tube lights can be possible in
83% of the households using T12/T8 tube lights.
Table 61 : T5 tube light + Electronic Ballast to replace T12/T8 tube light+ Magnetic Ballast

Total Residential household


Household using T8/T12 tube lights
Target to replace T8/T12 by T5 tube lights
Number of incandescent bulb to be replaced per household
Total number of T8/T12 tube lights to be replaced
Indicative cost of installation
Energy saved by replacing T8/T12(with magnetic ballast) with T5 (with electronic ballast)
Cost of electricity savings
Payback period
Emission reduction per year

(iii)

305289
83%
80%
2
405424
2027
13614131
476
4.25
11027

Unit
Nos.

Nos.
Nos.
Lakh
kWh
Lakh
years
Tonnes

Efficient ceiling fans to replace conventional ceiling fans

Replacing conventional fans with star rated fans can save substantial amount of electrical energy and money.
The financial and technical analysis for replacement of conventional ceiling fans in residential sector of Kalyan
Dombivli city assumes that 25% replacement should be possible in almost 100% of the households.
Table 62 : Efficient Ceiling Fans to Replace Conventional Ceiling Fans
Unit
Total Residential household

305289

Household using Conventional Fans

99%

Target to replace CF by EE Fans

25%

Number of Conventional fan to be replaced per household


Total number of Conventional Fans to be replaced
Indicative cost of installation
Energy saved by replacing Conventional Fans by EE Fans
Cost of electricity savings
Payback period
Emission reduction per year

Nos.

Nos.

226677

Nos.

3400

Lakh

7344337

kWh

257

Lakh

13

years

5949

Tonnes

(iv)
Replacement of conventional air-conditioners with EE star rated ACs
Survey results in Kalyan Dombivli reveal that approximately 18% of residential households had 1.5 ton air
conditioners on average. The energy consumption by a 1.5 ton unit is approximately 7.2 kWh per day. For
calculating the energy savings by switching to more energy efficient air conditioners it is assumed that 66%

69

households in Kalyan Dombivli owns an air conditioner and 25% air conditioners can be assumed as
potential target for replacement with energy efficient ACs.
Table 63 : Replacement of conventional air-conditioners with EE star rated ACs
Total Residential household
Household using Conventional AC
Target to replace Conventional Acs by EE star rated AC
Number of Conventional ACs to be replaced per household
Total number of Conventional ACs to be replaced
Indicative cost of installation
Energy saved by replacing Conventional ACs by EE Star Rated ACs
Cost of electricity savings
Payback period
Emission reduction per year

(v)

305289
18%
25%
1
13738
2061
4.70
164
13
3806

Unit
Nos.

Nos.
Nos.
Lakh
MU
Lakh
years
Tonnes

Replacement of conventional refrigerators with EE star rated refrigerators

One of the most common appliance used in homes are the refrigerators. With increasing affordability
refrigerators have become an indispensable item in most Indian households. They come in the capacity
range of 200-400 litres. These days many BEE star rated energy efficient refrigerators are available in the
Indian market. A conventional refrigerator of 200 watts has been taken to provide the calculations below.
An assumption of 25 % households with conventional refrigerators is taken to show the energy savings.
Table 64 : Replacement of Conventional Refrigerators with EE Star Rated Refrigerators
Total Residential household
Household using Conventional Refrigerators
Target to replace Conventional Refrigerators by EE Star one
Number of Conventional Refrigerators to be replaced per household
Total number of Conventional Refrigerators to be replaced
Indicative cost of installation
Energy saved by replacing Conventional Refrigerators by Star Rated
Cost of electricity savings
Payback period
Emission reduction per year

(vi)

305289
84%
25%
1
64111
3847
30.39
1064
3.6
24615

Unit
Nos.

Nos.
Nos.
Lakh
MU
Lakh
years
Tonnes

Replacement of conventional water pumps with EE star rated water pumps

Survey in Kalyan Dombivli has shown that residential households use water pumps of 1.5 HP capacity which
has an approximate electrical consumption of 2.2 kWh. Assuming 5% households in Kalyan Dombivli use
water pumps, 10% replacement of conventional pumps by energy efficient pumps have been targeted for
energy savings.

70

Table 65 : Replacement of conventional water pumps with EE star rated water pumps
Unit
Total Residential household

305289

Household using Water Pumps

Nos.

5%

Target to replace Conventional Water Pump by EE Pump


Number of Conventional Pumps to be replaced per household

10%
1

Nos.

2137

Nos.

21.37023

Lakh

234004

kWh

Cost of electricity savings

8.19

Lakh

Payback period

2.61

years

Emission reduction per year

190

Tonnes

Total number of Conventional Pumps to be replaced


Indicative cost of installation
Energy saved by replacing Conventional Water Pumps by EE Water
Pumps

(vii)
Summary of EE Strategy in Residential Sector
The estimated potential of energy savings in the residential sector through energy efficiency measures is 66
MU per year which is alone can meet 39.37% of the target of 168MU energy savings per year in Kalyan
Dombivli City. The reduction of emission through EE measures in residential sector is 70323 tonnes per year.
Replacement of incandescent bulbs with CFL, conventional fans, refrigerators and air conditioners with star
rated one is the most potential scope for energy savings.
Table 66 : Summary of EE Strategy in Residential Sector
EE Measures in residential sector

Unit

Target
Capacity

Investm
ent
(Lakh)

Amount
of
Energy
Saved
(MU)

Emissions
Reduction
s (Tonnes)

Indicative cost of replacing 60 watt incandescent with 15 watt CFL

Nos.

100135

150

10

7993

Indicative cost of replacing T12/T8 with T5 FTL


Indicative cost of replacing conventional Fans with EE star rated
fans

Nos.

405424

2027

14

11027

Nos.

226677

3400

5949

Indicative cost of replacing conventional AC with EE star rated AC

Nos.

13738

2061

3806

Indicative cost of replacing conventional refrigerator with EE star


rated refrigerator

Nos.

64111

3847

30

24615

Indicative cost of installing a EE water pump

Nos.

2137

21

190

11506

66

53580

5.2.

EE Strategy for Commercial Sector

The commercial sector comprises primarily of offices, shopping malls, markets, hotels and restaurants and
comprises of a mix of air conditioned and non air-conditioned buildings. The prime load centers in the
sector are air-conditioning, lighting and pumps/equipment. The major share of electricity consumption is
attributed to by air-conditioning in a full conditioned building followed by lighting, whereas the prime energy
consumption in a non-air conditioned building is lighting followed by space conditioning (coolers, fans, etc.).
The energy conservation and efficiency measures targeted for commercial sector thus should be aimed at
enhancing efficiency levels and deploying conservation options for lighting and air conditioning. Thus
71

efficiency and conservation have to be addressed in existing and new buildings to affect overall demand and
consumption reduction.
While retrofit options in existing buildings are restricted to system upgrades (e.g. upgrade to efficient chillers,
air handling units, pumps in HVAC system or upgrade to efficient lighting systems), new buildings offer ample
opportunities for walls & roof, efficient glazing, energy efficient lighting & HVAC system and renewable
energy integration for water heating or power generation)
Energy efficiency in the commercial sector is also hugely dependent on replacement of conventional
equipment with more energy efficient appliances. All kinds of building sectors are available in Kalyan
Dombivli ranging from hotels, hospitals, shops, malls, hostels, educational institutes and restaurants. The
strategies here target all these building types in Kalyan Dombivli.

(i)

Replace Incandescent Lamps with Fluorescent

CFL usage has been widespread in the last few years and it is high time that all commercial establishments
should voluntarily replace the high energy consuming incandescent lamps with CFLs. From survey results we
have assumed that 11% of the commercial sector establishments use incandescent bulbs and 72% of
establishment use T8/T12 tube lights. A target to replace 80% of the incandescent bulbs in this household is
assumed to give the calculations below.
Table 67 : Replacement of incandescent lamps with fluorescent
Total Commercial Consumers
Consumers using incandescent bulb
Target to replace incandescent bulb with CFL
Number of incandescent bulb to be replaced per consumer
Total number of incandescent bulb to be replaced
Indicative cost of installation
Energy saved by replacing 60W bulb with 15W CFL
Cost of electricity savings
Payback period
Emission reduction per year

Unit
Nos.

62976
11%
80%
10
55419
83
4488929
224
0.37
3636

Nos.
Nos.
Lakh
kWh
Lakh
years
Tonnes

Table 68 : Replace T12/T8 tube light by T5 tube light


Unit
Total Commercial Consumers

62976

Consumers using T8/T12 tube lights

72%

Target to replace T8/T12 by T5 tube lights

80%

Number of incandescent bulb to be replaced per consumer

Nos.

Nos.

72548

Nos.

Indicative cost of installation

363

Lakh

Energy saved by replacing T8/T12(magnetic ballast) with T5 (electronic ballast)

2.00

MU

Cost of electricity savings

100

Lakh

Total number of T8/T12 tube lights to be replaced

Payback period

3.62

years

Emission reduction per year

1622

Tonnes
72

(ii)

Replacement of inefficient fans

Analysis of the sample survey of Kalyan Dombivli city reveals that maximum commercial establishments in
Kalyan Dombivli city have fans. Conventional fans have an average energy consumption of 1.03kWh per day.
Assuming 25% of the conventional fans in the commercial sector of Kalyan Dombivli can be replaced with
more energy efficient fans the following techno-commercials have been calculated.
Table 69 : Replacement of Conventional Fans

Total Commercial Consumers


Consumers using Conventional Fans
Target to replace CF by EE Fans
Number of Conventional fan to be replaced per consumer
Total number of Conventional Fans to be replaced
Indicative cost of installation
Energy saved by replacing Conventional Fans by EE Fans
Cost of electricity savings
Payback period
Emission reduction per year

(iii)

62976
100%
25%
3
42509
638
0.59
30
21.43
482

Unit
Nos.

Nos.
Nos.
Lakh
MU
Lakh
years
Tonnes

Replacement of conventional air-conditioners with EE star rated ACs

Commercial establishments are usually equipped with air conditioners. Survey in Kalyan Dombivli city reveals
that 1.5 tons air conditioners are more popular in the commercial buildings. Assuming that 47% of the
commercial establishments own an air conditioner, 10% target replacement of inefficient air-conditioners
with more efficient conditioners are taken into consideration for the below mentioned calculations.
Table 70 : Replacement of Conventional Air-Conditioners with EE Star Rated ACs
Total Commercial Consumers
Consumers using Conventional ACs
Target to replace Conventional ACs by EE star rated ACs
Number of Conventional ACs to be replaced per household
Total number of Conventional ACs to be replaced
Indicative cost of installation
Energy saved by replacing Conventional ACs by EE Star Rated ACs
Cost of electricity savings
Payback period
Emission reduction per year

(iv)

62976
47%
25%
5
36998
5550
12.65
633
8.77
10249

Unit
Nos.

Nos.
Nos.
Lakh
MU
Lakh
years
Tonnes

Replacement of conventional refrigerators with EE star rated refrigerators

Refrigerators in commercial sector are restricted to the food outlets, restaurants, hotels, guest houses, and
ice-cream parlors. General trend reveals that the refrigerators of the range of 200-400 W are found in the

73

commercial sector of Kalyan Dombivli City. Approximately 63% of the consumers own a refrigerator and a
target of replacing 25% refrigerators has been taken to show the energy saving potential of replacing
conventional refrigerators in commercial sector of Kalyan Dombivli city.
Table 71 : Replacement of Conventional Refrigerators with EE Star Rated Refrigerators
Unit
Total Commercial Consumers

62976

Nos.

63%
25%
1

Nos.

9919

Nos.

Indicative cost of installation

670

Lakh

Energy saved by replacing Conventional Refrigerators by EE Star Rated one

4.70

MU

Cost of electricity savings

235

Lakh

years

3808

Tonnes

Consumers using Conventional Refrigerators


Target to replace Conventional Refrigerators by EE Star Rated Refrigerators
Number of Conventional Refrigerators to be replaced per consumer
Total number of Conventional Refrigerators to be replaced

Payback period
Emission reduction per year

(i)

Replacement of conventional water pumps with EE star rated pumps

Replacement of 10% conventional pumps by energy efficient pumps in the commercial and institutional
sector will save 0.63 MU energy per year and reduce 514 tonnes of GHG emission per year.
Table 72 : Replacements of Conventional pumps with EE Star Rated pumps
Unit
Total Residential household

62976

Consumers using Water Pumps

80%

Target to replace Conventional Water Pump by EE Pump

10%

Number of Conventional Pumps to be replaced per household


Total number of Conventional Pumps to be replaced
Indicative cost of installation

Nos.

Nos.

7053

Nos.

71

Lakh

0.63

MU

22

Lakh

Payback period

3.17

Years

Emission reduction per year

514

Tonnes

Energy saved by replacing Conventional Water Pumps by EE Water Pumps


Cost of electricity savings

(ii)

Summary of EE Strategy in Commercial & Institutional Sector

The estimated energy savings potential from commercial and industrial sector through energy efficiency
measures is 3.26MU per year, which is 1.94% of total target to achieve. Potential for GHG reduction is 2643
tonnes per year.

74

Table 73 : Summary of EE Strategy in Commercial & Industrial Sector


EE Measures

Units

Targets
12155

Investment
(INR)
24

Electricity
Saved
2.63

Emissions
Saved
2127

Indicative cost of replacing 100 watt incandescent with 15 watt CFL

Nos.

Indicative cost of replacing T8/T12 tube lights with T5 FTL

Nos.

10085

50

0.36

288

Indicative cost of replacing conventional fans with EE fans

Nos.

7320

110

0.14

114

Indicative cost of replacing conventional AC with EE star rated AC

Nos.

413

64

0.14

115

248

3.26

2643

5.3. EE Strategy for Industrial Sector


Kalyan Dombivli has around 1985 industrial units a registered customer of MSEDCL. They are also
contributing a lot towards the huge energy consumption in Kalyan Dombivli city. Energy efficiency measures
are the most financially feasible option in this sector too.

(i) Replacement of incandescent with CFLs


Industrial sector survey in Kalyan Dombivli city reveals that almost all of them use incandescent bulbs as
lighting appliances. A 50 % target of replacing incandescent bulbs with CFLs is taken to provide the energy
savings calculations below.
Table 74 : Replacement of incandescent with CFLs in Industrial sector
Total Industrial Consumers
Consumers using incandescent bulb
Target to replace incandescent bulb with CFL
Number of incandescent bulb to be replaced per consumer
Total number of incandescent bulb to be replaced
Indicative cost of installation
Energy saved by replacing 100W bulb with 20W CFL
Cost of electricity savings
Payback period
Emission reduction per year

1985
89%
50%
9
7597
15
1640865
82
0.19
1329

Unit
Nos.

Nos.
Nos.
Lakh
kWh
lakh
years
Tonnes

(ii) Replacement of T8/T12 by T5 tube lights


The T12 and Tt8 tube lights are also frequently used in the industrial sector in Kalyan Dombivli city. Survey
results show that almost 87% consumers use these appliances. The energy saving potential by replacement
of T12 and T8 with more efficient T5 tube lights is calculated below assuming a replacement of 50%
appliances in target households. The financial and technical details of the replacement in Kalyan Dombivli
city industrial units are given below.

75

Table 75 : Replacement of T8/T12 tube lights


Unit
Total Industrial Consumers
Consumers using T8/T12 tube lights
Target to replace T8/T12 by T5 tube lights
Number of incandescent bulb to be replaced per consumer
Total number of T8/T12 tube lights to be replaced
Indicative cost of installation
Energy saved by replacing T8/T12(with magnetic ballast) with T5
Cost of electricity savings
Payback period
Emission reduction per year

1985
87%
50%
7
6303
32
222250
11
2.84
180

Nos.

Nos.
Nos.
Lakh
kWh
Lakh
years
Tonnes

(iii) Replacement of Conventional Fans by EE Star Rated Fans


Conventional fans are other energy guzzlers in industrial units of Kalyan Dombivli city. They are used for
longer hours in this sector hence the replacement of conventional energy efficient fans with more efficient
ones would bring about a lot of energy savings. 53% of industrial units have installed a conventional fan
which can be targeted for replacement. Assuming a replacement of 25% of the conventional fans with
energy efficient fans the economics and technical details of replacement are tabulated below.
Table 76 : Replacement of conventional fans by EE star rated fans
Total Commercial Consumers
Consumers using Conventional Fans
Target to replace CF by EE Fans
Number of Conventional fan to be replaced per consumer
Total number of Conventional Fans to be replaced
Indicative cost of installation
Energy saved by replacing Conventional Fans by EE Fans
Cost of electricity savings
Payback period
Emission reduction per year

1985
100%
25%
15
7320
110
140538
7
16
114

Unit
Nos.

Nos.
Nos.
Lakh
kWh
Lakh
Years
Tonnes

(iv) Replacement of Conventional ACs with EE Star Rated ACs


Almost 50 % of the surveyed industrial units in Kalyan Dombivli City had the ownership of air conditioning
units in their office premises. Assuming the replacement of 10% of the air-conditioning units with star rated
air conditioning units the figures related to installments and energy savings are given below.

76

Table 77 : Replacement of Conventional ACs with EE Star Rated ACs


Total Industrial Consumers
Consumers using Conventional ACs
Target to replace Conventional ACs by EE star rated ACs
Number of Conventional ACs to be replaced per household
Total number of Conventional ACs to be replaced
Indicative cost of installation
Energy saved by replacing Conventional ACs by EE Star Rated ACs
Cost of electricity savings
Payback period
Emission reduction per year

1985
49%
10%
2
165
26
56550
3
9
46

Unit
Nos.

Nos.
Nos.
Lakh
kWh
Lakh
years
Tonnes

(v) Summary of EE Strategy in Industrial Sector


Energy Efficiency measures with mere replacement of incandescent bulbs, inefficient fans, ac and
refrigerators in industrial sector of Kalyan Dombivli city can save at least 2.06MU energy per year reducing
GHG emission by 1669 tonnes per year.
Table 78 : Summary of EE Strategy for Industrial Sector
EE Measures

Unit
s

Indicative cost of replacing 100 watt incandescent with 15 watt CFL


Indicative cost of replacing T12/T8 tube lights with T5 tube lights
Indicative cost of replacing conventional fans with EE star rated

Nos.
Nos.
Nos.
Nos.
Nos.

Indicative cost of replacing conventional AC with EE star rated AC

Target

7597
6303
7320
165

Invest
ment
(INR)

Electrici
ty
Saved
(MU)

Emission
s Saved
(Tonnes)

15
32
110
26
182

1.64
0.22
0.14
0.06
2.06

1329
180
114
46
1669

5.4. EE Strategy for Municipal Sector


Municipal services annually incur huge expenditures on electricity consumption to cater to the local public
services. Hence energy efficiency has become the call of the day for municipal organizations in India, owing
to growing city needs. The Bureau of Energy Efficiency in India has already come out with the Manual for
development of Municipal Energy Efficiency Projects. Energy conservation drives in the municipal
corporations and councils will become an exemplary initiative for similar activities in eth city. As a high
visibility and administration center Municipal bodies across India should go ahead in implementing the
strategies and replicating the success stories.
5.4.1. EE measures in Street Lighting
Street lighting is one of the major sources of energy consumption in municipal area. The different lighting
appliances used for municipal lighting are the 150W HPSV lamps, 250W HPSV lamps, and T12 and T8 tube
lights.

77

(i)
Replacement of 250 watt HPSV with LEDs
250 watts high pressure sodium vapor lamps are frequently used in street lighting fixture in municipal area.
They can be replaced with more energy efficient LEDS available in the Indian market today. A 100% target to
replace 250W HPSV lamps with LEDs is taken for Kalyan Dombivli city, to provide the techno-economics of
implementing the replacement and bringing about energy savings.
Table 79 : Replacement of 150 watt HPSV with LED

Total number of 250 watt HPSV


Target to replace HPSV lamp with LEDs
Total number of 112 watt LEDs needed
Indicative cost of installation
Energy saved by replacing 250 watt HPSV with 112 watt LED
Cost of electricity savings
Payback period
Emission reduction per year

5142
100%
5142
2828
3108030
155
18.20
2518

Unit
Nos.
Nos.
Lakh
kWh
Lakh
years
Tonnes

(ii)
Replacement of 40 watt T8/T12 tube lights with T5 tube lights
In Kalyan Dombivli city T12 and T8 tube lights are frequently used in street lighting and survey results have
revealed approximately 454 tube lights in municipal street lighting. 100% replacement of tube lights with in
municipal street lighting should be targeted to bring about energy savings.
Table 80 : Replacement of 40 watt T8/T12 tube lights with T5 tube lights
Unit
Total number of 40 watt Tube lights
Target to replace incandescent bulb with CFL
Total number of 112 watt LEDs needed
Indicative cost of installation
Energy saved by replacing 250 watt HPSV with 112 watt LED
Cost of electricity savings
Payback period
Emission reduction per year

(iii)

454

Nos.

100%
454

Nos.

Lakh

45736

kWh

Lakh

0.99

years

37

Tonnes

Sensors for automatic on/off of street lights

Automatic street lights ensure that energy is not wasted by lights turned on during day time. Many
streetlights in India face this predicament due to faulty manually controlled street lights. Manual control
involves labor costs, energy wastes and poor efficiency , hence Municipal street lights should hasten the
process of installing automatic sensors. Solar sensors are the new and upcoming products in the market
today and should be applied by municipalities for higher efficiency in the operation and maintenance of
municipal street lights. Kalyan Dombivli city showed predominantly manual control of municipal street

78

lights and hence it is highly recommended for switch over to automatic sensors preferably solar automatic
sensors.

(iv)

Energy Efficiency Measures in Water Pumping

Water pumping is one of the major utility practices which consume high energy. The energy efficiency
initiatives for water pumping in India have been going on for quite some time. BEE state in its Manual for
Development of Municipal Energy Efficiency Projects states that 25% energy savings can be obtained from
initiatives in water systems alone. In Karnataka Municipal energy efficiency Improvement initiatives, water
pumping has been addressed. This has been further taken up as a Municipal Energy efficiency CDM project.
The effort can be replicated throughput other municipalities sin India. This would bring about a lot of energy
savings in water pumping utilities.
The Table 19 : shows the electricity consumption in supplying water to different areas in the city.

(v)

Proper pump-system design (efficient Pump, pumps heads with system heads

Proper water pumping design can bring about lots of energy savings in the running and maintenance cost of
water pump systems. Careful designing is required to assess the volume of water to be pumped and the
height it needs to be raised to. Fluid piping softwares can be utilized for designing water pumps in Municipal
bodies. A 20% saving is assumed for design based energy efficiency of water pumping systems. The technoeconomics given below for this initiative is based on this assumption.
Table 81 : Proper pump-system design (efficient Pump, pumps heads with system heads)
Standard/Recommended Condition
Annual Energy Consumption in MU
Annual Energy Cost in Rs. (lacs)
Saving %
Total Annual Saving in MU
Annual Saving in Rs. (lacs)
eCO2 (Tonne) Reduction

(vi)

Value
21.5
752.5
20%
4.3
150.5
3483

Installation of variable speed drivers

Dimension and adjustment losses are two of the major energy loss sources in pumping processes. Adjusting
pump speed or using Variable Speed Driver to adjust speed is one way to decreasing both the
aforementioned losses in pumping processes. An assumption of 5% savings is taken to provide the financial
and technical details of installing variable speed drivers in municipal water pumping systems in Kalyan
Dombivli City.

79

Table 82 : Variable Speed Drivers


Standard/Recommended Condition

Value

Annual Energy Consumption in MU

21.5

Annual Energy Cost in Rs. (lacs)

752.5

Saving %

(vii)

5%

Total Annual Saving in MU

1.075

Annual Saving in Rs. (lacs)

37.625

eCO2 (Tonne) Reduction

870.75

Power saver installation in pump house

An assumption of 15% savings is taken as the energy saving potential for installing power saver in municipal
pump houses. The following techno-economics is based on this assumption.
Table 83 : Power saver installation in pump house
Standard/Recommended Condition
Annual Energy Consumption in MU
Annual Energy Cost in Rs. (lacs)
Saving %
Total Annual Saving in MU
Annual Saving in Rs. (lacs)
eCO2 (Tonne) Reduction

(viii)

Value
21.5
752.5
15%
3.225
112.875
2612.25

Energy Efficiency Measures in STP

Pumping systems are utilized in water treatment plants of the municipal corporations whose energy
efficiency can also be determined through efficient system design. A considerable amount of energy can be
saved taking suitable measures in STP. KDMC should initiate energy audit in all its utility services and
installations to take a stalk of the energy consumption and potential savings.

(ix)

Proper pump-system design (efficient pump, pumps heads with system heads)

The same principle of speed adjustment to reduce adjustment and dimension energy losses in water
pumping process applies in water treatment plants. An assumption of 5% saving is taken into consideration
for giving the techno-economics of installing variable
Table 84 : Proper pump-system design (efficient pump, pumps heads with system heads)
Standard/Recommended Condition

Value

Annual Energy Consumption in MU

1.63

Annual Energy Cost in Rs. (lacs)

57.05

Saving %

20%

Total Annual Saving in MU

0.326

Annual Saving in Rs. (lacs)

350

eCO2 (Tonne) Reduction

264
80

(x)

Installation of variable speed drivers

Installation of variable speed drivers for municipal pumps could save at least 5% energy resulting total
savings of 0.8MU per year reducing 648 tonnes of GHG emission.
Table 85 : Variable Speed Drivers
Standard/Recommended Condition

Value

Annual Energy Consumption in MU

1.63

Annual Energy Cost in Rs. (lacs)

57.05

Saving %

5%

Total Annual Saving in MU

0.08

Annual Saving in Rs. (lacs)

2.85

eCO2 (Tonne) Reduction

(xi)

66

Power saver installation in pump house

An assumption of 15% savings has been taken to calculate the energy saving potential and financial
implications of installing power saver in pump houses.
Table 86 : Power saver installation in pump house
Standard/Recommended Condition

(xii)

Value

Annual Energy Consumption in MU

1.63

Annual Energy Cost in Rs. (lacs)


Saving %

57.05
15%

Total Annual Saving in MU

0.2445

Annual Saving in Rs. (lacs)

8.56

eCO2 (Tonne) Reduction

198

Summary of EE Strategy for Municipal Sector

The energy savings potential through energy efficiency measures in municipal sector is 22.60 MU per year
which is about 9% of total target to achieve.

81

Table 87 : Summary of EE Strategy for municipal sector


EE Measures

Water
Supply

STP

Invest
ment
(Lakh)

Electricity
Saved
(MU)

Emissions
Saved
(Tonnes)

454

0.05

37

5142

2828

3.11

2518

10316

84

2.38

1929

NA

NA

4.30

3483

Installation of variable speed drivers

NA

NA

1.08

870.75

Standard/Recommended Condition
Proper pump-system design (efficient Pump,
pumps heads with system heads

NA

NA

3.23

2612.25

NA

NA

0.33

264.06

Installation of variable speed drivers

NA

NA

0.08

66.015

NA

NA

0.24

198.045

2914

14.79

11978

Indicative cost of replacing T8/T12 tube lights


with T5 tube lights
Indicative cost of replacing 250 watt HPSV with
112 watt LED
100% timer based operation and installation of
power saver
Proper pump-system design (efficient Pump,
pumps heads with system heads

Standard/Recommended Condition

82

CHAPTER 6
6. ACTION PLAN AND BUDGET
6.1. Year-wise Goals of Energy Savings
The table below presents a summary of year wise goals for energy savings through introduction of
renewable energy and taking energy efficiency measures. The goal is to minimum 10% reduction in
projected total demand of 1680MU of conventional energy at the end of five years to be achieved through
energy saving from energy efficiency measures and generation from renewable energy installations.
The master plan sets a goal of total savings of 222.28MU with 113.18MU from renewable energy installation
and 109.10MU from energy efficiency measures.
Table 88 : Energy savings goal over 5 years solar city implementation period

RE and EE Strategy for Kalyan


Dombivli City

Energy Savings target over 5 years period of


implementation (MU per year)
2nd year 3rd year
4th year
5th year
1st
Cumulati Cumulati Cumulati Cumulati
Year
ve
ve
ve
ve

% of
savings
target to
achieve

Emission
reduction/
year

RE for Residential Sector

8.30

20.75

37.36

58.11

83.02

49.41%

69231

RE for Commercial & Inst. Sector

0.50

1.25

2.25

3.50

5.00

2.98%

3187

RE for Industrial Sector

1.17

2.93

5.27

8.20

11.71

6.97%

9747

RE for Municipal Sector

0.10

4.70

6.50

13.16

13.46

8.01%

10903

Total for RE strategy

11.32

28.30

50.93

79.23

113.18

67.37%

93068

EE for Residential Sector

6.61

16.54

29.77

46.30

66.15

39.37%

53580

EE for Commercial Sector

2.51

6.27

11.28

17.55

25.08

14.93%

20312

EE for Industrial Sector

0.33

0.82

1.47

2.28

3.26

1.94%

2643

EE for Municipal Sector

1.46

3.65

6.58

10.23

14.61

8.70%

11838

Total for EE Strategy

10.91

27.28

49.10

76.37

109.10

64.94%

88372

RE and EE Combined Strategy

22.23

55.57

100.03

155.60

222.28

13%

33%

60%

93%

132%

181440

83

Figure 17 :

Year wise energy savings targets for Kalyan Dombivli Solar City

84

Table 89 : Year wise Goal of Energy Savings

85

6.2. Physical Target and Action Plan


The Master Plan for developing Kalyan Dombivli as Solar City sets a target of installing 3.38 MLPD capacity
Solar water heater with a collector capacity of 67600 sqm, 25.80MWp cumulative solar PV systems, 525CuM
Biogas systems, 2.03MWe waste to energy projects and 6201 nos. solar cookers. A list of renewable energy
equipments and energy efficient devices has been presented in the table below.
Table 90 : Physical target of RE systems and EE devices
Renewable Energy Devices proposed
Domestic Solar Water Heating System (100/125LPD system)
x 1000LPD solar water heating system
Solar cookers (Box and dish type)
Community Solar Cooker
Solar lanterns
Use Solar Home Systems (SHS)
0.25 - 1.0kWp Solar PV system for inverters
x 10kWp PV Power Plant for diesel abatement
x 10CuM Biogas system from organic/food waste
Solar Street Light
Solar PV Traffic Lights
Solar Blinkers (37Wp)
Road Stud
Solar PV Pumps
Waste to Energy Power Plant
Energy Efficient Devices proposed
CFLs
T5 tube light + Electronic Ballast to replace
Efficient ceiling fans
Star rated Acs
Star rated refrigerators
Star rated water pumps
112 watt LED
Power saver

9769
2399
6106
95
12822
4274
36078
1198
53
1942
7
60
1875
8
3

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

167708
488512
276506
51150
74029
9190
5142
10316

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

86

Table 91 : Physical Target and Action Plan

87

6.3.

Implementation Strategy

6.3.1. Establishment of the Solar City Cell


The Solar City Cell is a very integral component of the MNREs Development of Solar Cities Scheme. The
basic purpose of establishing a Solar City cell is to ensure the parallel set up of a local site for exchange and
collection of relevant data for sustenance, promotion and awareness generation of renewable energy and
energy efficiency at the local level. The solar city cell will be the focal point and critical player for
implementation of the solar city development programme. Solar City Cell will be established within the
Kalyan Dombivli Municipal Corporation and will function under the full administration of the Kalyan Dombivli
Municipal Corporation and the Council Chairman will be the highest level authorizing personnel. A senior
technical officer at the level of executive engineer or above will be the overall in charge of the solar city cell.
The officer in-charge will prepare all strategy and functioning modalities of the solar city cell. A full time
technical expert will be associated to the Solar City Cell for day-to-day activities, documentation,
communication and every other activity under Solar City Cell. The Solar City Cell will provide technical
guidance, expertise and financial analyses of projects for potential investors- individual or companies. It will
also help for customer outreach. It will act as a platform where all relevant stakeholders
(citizens/manufacturers /banks/institutions etc.) can meet and exchange information on RE and EE.
The Ministry of New and Renewable Energy, Government of India will provide Rs.10.00 Lakh (Rupees ten
lakh only) for the establishment and operation the solar city cell for five years. The Kalyan Dombivli
Municipal Corporation will provide space for the cell and depute one senior engineer/ technical person of
the level of executive engineer or above as an overall in-charge of the solar city cell. The detailed functions
and modus operandi of the solar city cell is elaborated in the guidebook for development of solar city, which
is an integral part of this master plan.
6.3.2. Awareness and Publicity
Awareness and Publicity Programme will be taken up to creating awareness among mass and target sectors
in the city about benefits and financial incentive for targeted Renewable Energy systems & devices. Under
these programmes, information on technological developments, financial benefits and cost savings from RE
system and EE measures, government initiatives and incentives for such devices/ measures, availability, price
etc will be disseminated through various media. The Solar City Cell will primarily take up these programmes.
MNRE has earmarked Rs.20.00 lakh (Rupees twenty lakh) for each city for awareness and publicity activities
under the solar city development programme. The following activities are proposed for creation of
awareness and publicity.
(i) Publicity through electronic media

Production and telecast of documentary films, short duration films, TV spots/advertisements etc
through local TV network
Production and broadcast of Radio sponsored programmes, Radio Spots/jingles and Radio Talks etc.
through local FM channels
88

Creating an interactive E-Commerce website exclusively for Kalyan Dombivli Solar City for
awareness campaigns, information sharing and support to the users for submission of online
application for incentives etc.

(ii) Print Media/Publication

Advertisements in colour and black & white in Newspapers/magazines/journals etc.


Printing of booklets/folders/brochures/posters/calendars/Trade Guide/ Compendium/ Newsletters
etc. on different promotional schemes under Kalyan Dombivli Solar City project.
Develop educational programs on energy efficiency, distributed generation, and renewable energy
systems in buildings for homeowners, businesses, government staff, and those in the building
industries.

(iii) Exhibitions, Outdoor Publicity, Campaign

Use of Exhibitions and Outdoor Publicity activities like hoardings, kiosks, bus panels, bus-stop
shelters, wall paintings, computerized animation display systems, etc. in the city.
Display and demonstration of RE and EE equipments in the Solar City Cell.
Organizing runs, debates, seminars, quiz, drawing, model making, poster, essay and slogan writing
competitions among others for school children and others;
Promotion and publicity of RE and EE by displaying models and posters etc in different public places,
institutions/organizations, hospitals, bus stand etc.
Encourage maximum participation by residents and business owners in the Citys energy efficiency
programs through marketing and education.
Educate government purchasing agents in each City department regarding the benefits of Energy
Star rated equipment, including the cost savings to the city.
Encourage community input on strategies for improving energy efficiency in building.

(iv) Workshops and Seminars


It is proposed to organize workshops and seminars on specific technologies for targeted audiences from
residential, commercial, Institutional, Industrial and Municipal Sectors.
6.3.3. Implementation of RE Strategy
The solar city development programme will be implemented through joint participation of the residential
citizens of the Kalyan Dombivli city, industries, commercial and institutional establishment, city municipal
corporation, state government and Ministry of New and Renewable Energy. Financial assistance for
installation of various renewable energy devices and systems will be availed as per the provisions of various
schemes of the Ministry. Support for various other activities will also be availed as per the scheme
provisions of MNRE. The ministry will give priority for support to the cities identified as potential Solar
Cities. The Ministry, IREDA and other implementing institutions for promoting the use of renewable energy
devices/systems, will consider these cities as priority cities. State Nodal Agency may also request the
Ministry to allocate higher targets for installation of various renewable energy devices/systems in these
cities under its different schemes through subsidies. Ministry of Urban Development would also be
89

approached for assistance under their schemes e.g., JNNURM, etc., as well as the Bureau of Energy
Efficiency. The following activities are proposed to promote use of renewable energy and energy efficiency
measures among different section of people, commercial establishment, institutions, municipality and
industries.
(I)

Show casing and promotion of different MNRE programmes through different audiovisual
publicity, workshop, exhibition, campaign etc.

(II)

Establishment of single window clearance mechanism to avail all government incentives. The
Solar city cell can be used as a single point contact and clearance centre for all kinds of
promotional activities and subsidies for RE and EE devices.

(III)

Creation of interactive web based tool for accepting application for availing incentives from
MNRE/ State/ City

(IV)

Providing technical assistance to project developers in site assessment, feasibility and detailed
project report preparation.

(V)

Providing assistance in conducting energy audit

(VI)

Involvement of financial institution/ IREDA for providing soft loan for large scale promotion of
RE projects.

(VII) Setting up of a high level committee including city administration, state nodal agency,
developers, MNRE, RE/ EE experts, Finance institution stakeholders from different sectors to
oversee and review implementation of the Master Plan
(VIII) Provide additional subsidy/ incentives for those systems which have payback period more that 3
years
(IX)

Amend building bye-laws for making the use of solar water heating systems mandatory

(X)

Provide rebate in property tax through Municipal Corporations/ Municipalities & in electricity
tariff though Utilities/ Electricity Boards to the users of solar water heaters especially in
domestic sector.

(XI)

Comply MSW Rules 2000 notified by the MoEF and set up projects of suitable capacity for
generating energy from the waste collected from the city/town.

(XII) Conduct energy auditing of Govt./Public sector buildings, water pumping and street lightings in
the city at regular interval and take necessary steps towards conservation of energy for the
same.
(XIII) Issue G.O as regards to construction of energy efficient solar buildings at least in Govt. /Public
sectors in accordance with ECBC : 2006 and follow up its implementation rigorously.
(XIV) Organize rigorous publicity, and also the training programmes/ business meets for various stake
holders e.g. architects, engineers, builders & developers, financial institutions, NGOs, technical

90

institutions, manufactures/suppliers, RWAs etc. so as to involve them actively in meeting the


objective of solar city.
(XV) Generate necessary funds from State Govt. and other funding organizations for achieving the
objective of making the city as Solar City. Benefits of the schemes of Govt. of India will also be
taken in meeting the objectives.
(XVI) Promote National Rating System for construction of energy efficient Green Buildings in particular
to commercial and institutional buildings
(XVII) Avail financial benefit from Carbon Market

6.3.4. Renewable Energy Pilot Projects


MNRE will provide financial assistance for implementation of pilot projects in all the sectors. Five categories
of projects in different RE technologies are proposed in each sector. It is proposed that MNRE will provide
financial assistance to meet 75% of the project cost, KDMC/ State will support 15% and users will contribute
10% project cost. The total investment for implementation of all proposed pilot projects is estimated as
Rs.311.59Lakh out of which MNRE will contribute Rs.233.69Lakh, City/ Sate will contribute Rs.46.74Lakh and
the users will contribute Rs.31.16Lakh. All the pilot projects shall be executed in the first year of
implementation. All the pilot projects shall be executed in the first year of implementation. The following
tables show pilot projects proposed and financial implication thereon in different sectors in the city.

Table 92 : Pilot Projects in Residential Sector


Sl.
No.

1
2
3
4
5

Proposed Pilot Projects

Solar lanterns for roadside markets/


hawkers to replace kerosene lamps
PV system for Home inverter
PV system to replace Home Generator
Solar Water Heating System for
residential Apartment Complex
PV Power Plant for residential
apartment Complex
Total

Capacity

Unit

Nos.

Cost per
system
(Lakh)

Total
cost
(Lakh)

MNRE
Share
(Lakh)

Users
share
(Lakh)

2.25

City/
State
Share
(Lakh)
0.45

10

Wp

100

0.03

3.00

250
1
5000

Wp
kWp
LPD

10
5
2

0.30
2.00
5.00

3.00
10.00
10.00

2.25
7.50
7.50

0.45
1.50
1.50

0.30
1.00
1.00

25

kWp

30.00

60.00

45.00

9.00

6.00

86.00

64.50

12.90

8.60

0.30

91

Table 93 : Pilot Projects in Commercial and Institutional Sector


Sl.
No.

Project

Community Solar Cooker for mid day


meal in schools
Solar Water hearts for Hospitals
Biogas system for Restaurants
Solar Water Heater for Restaurants
PV system for educational institutes
Total

1
2
3
4
5

Capacity

Unit

Nos.

1
5000
10
5000
6

No.
LPD
CuM
LPD
kWp

10
2
2
2
2

Cost
per
system
(Lakh)

Total
cost
(Lakh)

MNRE
Share
(Lakh)

City/
State
Share
(Lakh
)

Users
share
(Lakh
)

0.20
5.00
0.50
5.00
12.91

2.00
10.00
1.00
10.00
25.82
48.82

1.50
7.50
0.75
7.50
19.36
36.61

0.30
1.50
0.15
1.50
3.87
7.32

0.20
1.00
0.10
1.00
2.58
4.88

Total
cost
(Lakh)

MNRE
Share
(Lakh)

Users
share
(Lakh)

10.00
4.00

7.50
3.00

City/
State
Share
(Lakh)
1.50
0.60

Table 94 : Pilot Projects in Industrial Sector


Sl.
No.
1
2
3
4
5

Project

Biogas system for restaurants


PV System for Leather Industries
Solar Water Heaters for Food
processing
Solar PV system for Garment Industry
Solar steam generator process
heating
Total

Capacity

Unit

Nos.

10
1

CuM
kWp

5
2

Cost
per
system
(Lakh)
2.00
2.00

2000
0.5

LPD
kWp

2
2

2.00
1.00

4.00
2.00

3.00
1.50

0.60
0.30

0.40
0.20

Nos.

1.00

2.00
22.00

1.50
16.50

0.30
3.30

0.20
2.20

Cost
per
system
(Lakh)

Total
cost
(Lakh)

MNRE
Share
(Lakh)

City/
State
Share
(Lakh)

Users
share
(Lakh)

1.00
0.40

Table 95 : Pilot Projects in Municipal Sector


Sl.
No.

1
2
3
4
5

Project

Solar PV power plant for Municipal


building/ bus stand
Solar Streetlights/ traffic lights/
blinkers
Solar PV system for markets
Outdoor PV systems for Municipal
Parks
Solar Hoardings
Total

Capacity

Unit

Nos.

25

kWp

50.00

100.00

75.00

15.00

10.00

74
500

Wp
Wp

100
5

0.20
0.60

20.00
3.00

15.00
2.25

3.00
0.45

2.00
0.30

1
1

No.
No.

2
10

8.39
1.50

16.78
15.00
154.78

12.58
11.25
116.08

2.52
2.25
23.22

1.68
1.50
15.48

92

Table 96 : Summary of Pilot Projects and indicative project cost implication


Sl.
No.
1
2
3
4

6.4.

Project

Total cost
(Lakh)

Pilot Project in Residential Sector


Pilot Projects in Commercial & Institutional Sector
Pilot Projects in Industrial Sector
Pilot Projects in municipal Sector
Total

86.00
48.82
22.00
154.78
311.59

MNRE
Share
(Lakh)
64.50
36.61
16.50
116.08
233.69

City/
State
Share
(Lakh)
12.90
7.32
3.30
23.22
46.74

Users
share
(Lakh)
8.60
4.88
2.20
15.48
31.16

Financial outlays and sharing of fund

The total indicative budget for development of Kalyan Dombivli as Solar City is estimated at Rs.668.71 crore
which will be invested over the 5 years of implementation period of solar city development programme. The
total budget will be shared by the state government/ City authority (5%), MNRE (33%) and the private users
(62%). The budget for implementation of RE strategy and EE strategy is estimated at Rs.463.87 crore and is
Rs.191.43 crore respectively. Budget for establishment of the Solar City Cell and awareness and publicity is
estimated at Rs.48.30 Lakhs which could be enhanced depending upon the requirement. While budget for RE
strategy will be shared among MNRE, state/city and private users, private investors will primarily drive EE
activities. A substantial amount of investment could be recovered or the entire project could be partially
financed through carbon finance mechanism. A suitable methodology will be adopted to avail benefit from
carbon market selling the CER generated from the project.
Table 97 : Sharing of budget for development of Kalyan Dombivli Solar City
Sharing of fund

Year 1
(Crore)

Year 2
(Crore)

Year 3
(Crore)

Year 4
(Crore)

Year 5
(Crore)

Total (Crore)

State / City Share

3.10

4.65

6.20

7.75

9.30

30.99

MNRE Share

21.58

34.48

43.53

55.80

64.44

219.83

Private Share

40.98

64.37

83.00

106.63

122.93

417.90

Total Budget

65.66

103.49

132.72

170.17

196.67

668.71

93

Figure 18 :

Sharing of total budget for development of solar city Kalyan Dombivli

Figure 19 :

Sharing of RE Strategy Budget for Kalyan Dombivli Solar City

Figure 20 :

Sharing of EE Strategy Budget for Kalyan Dombivli Solar City

94

Figure 21 :

Year wise sharing of budget for Kalyan Dombivli Solar City Programme

95

Table 98 : Sector wise total budget and annual expenses


Unit

Total

Year 1

Year 2

Year 3

Year 4

Year 5

MNRE contribution for RE strategy


Establishment of Solar city cell

Lakh

10.00

3.52

1.62

1.62

1.62

1.62

Publicity and awareness

Lakh

28.00

8.15

8.15

5.60

3.05

3.05

RE for residential sector

Lakh

16295.06

1629.51

2444.26

3259.01

4073.77

4888.52

RE for Commercial & Inst. sector

Lakh

767.97

76.80

115.20

153.59

191.99

230.39

RE for Industrial sector

Lakh

3406.03

340.60

510.90

681.21

851.51

1021.81

RE for Municipal sector

Lakh

996.40

99.64

149.46

199.28

249.10

298.92

W2E Project form MSW & STPs

Lakh

479.65

0.00

218.02

52.33

209.30

0.00

21983.12

2158.22

3447.61

4352.64

5580.34

6444.31

10.30

0.70

2.40

2.40

2.40

2.40

MNRE
State/city contribution
Establishment of solar city cell
RE for Institutional sector

Lakh

263.72

26.37

39.56

52.74

65.93

79.12

RE for Municipal sector

Lakh

966.40

96.64

144.96

193.28

241.60

289.92

1843.33

184.33

276.50

368.67

460.83

553.00

14.79

1.48

2.22

2.96

3.70

4.44

3098.54

309.85

464.78

619.71

774.63

929.56

EE measures for Inst. sector


EE measures for Municipal sector
State / City
Private/ Users contribution
RE for residential sector

Lakh

18267.18

1826.72

2740.08

3653.44

4566.79

5480.15

RE for Commercial & Inst. sector

Lakh

777.58

77.76

116.64

155.52

194.39

233.27

RE for Industrial sector

Lakh

4616.32

461.63

692.45

923.26

1154.08

1384.89

RE for Municipal sector

Lakh

30.00

3.00

4.50

6.00

7.50

9.00

EE for Residential sector

Lakh

11506.19

1150.62

1725.93

2301.24

2876.55

3451.86

EE for Commercial & Inst. sector

Lakh

5529.98

553.00

829.50

1106.00

1382.50

1658.99

EE measures for Industrial sector

Lakh

248.40

24.84

37.26

49.68

62.10

74.52

Private Investor for W2E projects

Lakh

813.95

0.00

290.70

104.65

418.60

0.00

41789.59

4097.56

6437.04

8299.78

10662.51

12292.69

66871.25

6687.12

10030.69

13374.25

16717.81

20061.37

Private/ Users
Total

Lakh

96

Table 99 : Budget and Sharing of fund

97

6.5.

Potential Carbon Market Benefit

The RE and EE activities under solar city programme will considerable amount of green house emission per
year. The CER generated under this project can be sold to carbon market under suitable mechanism. It is
estimated that a total of 181440 CER could be sold from the project which will give a revenue of Rs.13.06
crore per year. If project life is considered 10 years, the income from carbon market will recover about 20%
of the project cost.
Table 100 : Potential Carbon Market Benefit
Assumption: Value of CER = 12 Euro;
1Euro= 60 INR

Energy Saved
(MU)

CER
(Tonnes)

Value
(Lakh/ year)

CER from RE strategy

113.18

93068

670.09

CER fro EE strategy

109.10

88372

636.28

CER from entire solar city project

222.28

181440

1306.37

98

7. Annexure I Pilot Project I

Project Proposals
for
Solar Thermal Systems/ Devices
Under
Development of Solar City Programme of MNRE
1.
Title of the Project : Solar Water Heating System for Hospitals in Kalyan Dombivli Municipal Area
2.
Name of the Project Proponent : Kalyan Dombivli Municipal Corporation
3.
Socio- Economic Justification of the Project:
There are many benefits of from solar water heater, and number one is economics. Solar water heater
economics compare quite favorably with those of electric water heaters, while the economics aren't quite so
attractive when compared with those of gas water heaters. Heating water with the sun also means longterm benefits, such as being cushioned from future fuel shortages and price increases, and environmental
benefits.
Economic Benefits
Solar water heaters offered the largest potential savings compared to electric heating, with solar waterheater owners saving as much as 50% to 85% annually on their utility bills over the cost of electric water
heating. Typical simple payback period of a solar water heating system is 2 to 3 years.
Tax Incentives and Rebates
Ministry of New and Renewable Energy (MNRE) offers subsidies on domestic as well as commercial solar
water heating systems installations. Government of India offers 80% depreciation claim in the first two years
itself on installation of commercial solar water heating systems.
Long-Term Benefits
Solar water heaters offer long-term benefits that go beyond simple economics. In addition to having free hot
water after the system has paid for itself in reduced utility bills, it contributes towards future fuel shortages
and price increases and reduce country's dependence on foreign oil.
Environmental Benefits
Solar water heaters do not pollute and contribute in reduction of GHG emission. A 100 LPD solar water
heater system when replaces an electric water heater, the electricity displaced over 20 years represents
more than 30 tons of avoided carbon dioxide emissions alone.
4.
Benefits of the proposed project:
There are 220 hospitals Kalyan Dombivli Municipal area out of which 190 hospitals with intake capcity less
then 50 beds and 30 hospitals with 50-100 beds. in It is proposed to install Solar Water Heating systems in
all hospitals in KDMC area. Total potential for solar water heating systems in the hospital sector is estimated
to be 470000 LPD. Complete installation of solar water heaters in the hospitals will save about 7.20MU
electricity per year and reduce about 6000 tons of GHG per year. The target for the first phase is to install
130000LPD solar water heating systems in 60 hospitals.
99

Ministry of New and Renewbale Energy (MNRE) declared KDMC as a Solar City and a master plan has been
prepared to reduce 10% energy consumption through renewable energy and energy efficiency measures.
The master plan sets a goal to reduce 168MU electricity per year within 5 years period. Implementation of
solar water heating projects in hospitals alone can contribute 4.3% towards the set goal.
Most importantly, hospitals will save considerable amount of electricity and will enjoy free hotwater within
2-3 years of payback on the investment. They will avail subsidy from the MNRE and may avail 80%
depreciation benefit in the first two years.
PART-A: Details of the Project Proponent
I

II

III

IV

Name of the Project Proponent:


Kalyan Dombivli Municipal
a) Renewable Energy Service Providing Corporation, Kalyan Dombivli,
Company (RESCO)
Maharashtra.
b) Financial Institutions (Banks, NBFCs, MFIs)
c) Financial Integrator
Category: Program Administrator.
d) System Integrator
e) Program Administrator
Name, Designation and Address of the Authorized Name: The Commissioner
Representative for correspondence with telephone
Address: Kalyan Dombivli
no, fax & email
Municipal Corporation
KDMC, Shankarrao Chowk,
Kalyan West - 421301
In case of Channel Partner other than Programme
Administrator, the following information will be
provided:
Name and Category of Project Proponent

a) Whether commercial or non-commercial.


b) Copy of Articles of Association, Registration
NA
No. & Date
c) Audited Balance Sheet for last three years
d) Annual Report of previous year
e) Whether MNRE has earlier sanctioned any
Solar
Thermal
project
(s)
for
implementation to the Project Proponent, if
yes, please furnish information
Autonomous Institution set by
In case of 1 (e), Please indicate:
State Government (Urban Local
a) Government Department, Autonomous Body)
Institution set up by Central/ State
Government, State renewable Energy
development agency, Public Sector
Undertaking
b) Others

100

PART-B: Details of the Project


Kalyan Dombivli is an important satellite township of Mumbai city. It is an important railway junction. The city
of Kalyan Dombivli forms one of the important urban agglomerations of Maharashtra state. Owing to large
urbanizable zone and its proximity to greater Mumbai, Kalyan Dombivli is trying to enhance the quality of
services, expand the infrastructure and accelerate its economic growth. It has not only made its presence felt
in terms of overall development and commercialization but also in its many eco drives for a sustainable
future. Kalyan Dombivli has been approved by the Ministry of New and Renewable Energy to be developed as
a solar city. Kalyan Dombivli Municipal Corporation (KDMC) is the main organization which is responsible for
urban governance and civic management in the city of Kalyan Dombivli. The corporation has a democratically
elected leadership from the constituencies within the geographic jurisdiction of the corporation boundaries.
Kalyan Dombivli Municipal Corporation is a very active organization for initiating good practices and it has
also come with the added supportive policy framework from Maharasthra Government for the
implementation of renewable energy initiatives.
There are 220 hospitals in KDMC area out of which 190 hospitals with less then 50 beds and 30 hospitals have
capacity of 50-100 beds. All the hospitals uses electric geysers to fulfill their hot water demand.
It is proposed to install solar water heaters in all the hospitals in phased manner as a part of solar city
activities. In the first phase, 10 hospitals of 50-100 bed capacity will be installed solar water heaters of
capacity 3000LPD each. Similarly, 50 hospitals having less then 50 beds will be installed with 2000LPD solar
water heaters.
1. Details of Project site:
The Kalyan Dombivli city is located at geographical coordinates of 27.18 N and 78.02 E. The administrative
building of Kalyan Dombivli Municipal Corporation is located in the heart of the city. Average annual solar
radiation in Kalyan Dombivli is 5.08kWh/m2/day.
2. Details of Project Beneficiaries:
Kalyan Dombivli Municipal Corporation (KDMC) will be the direct beneficiary of the project. KDMC is
responsible for providing the basic services infrastructure to city dwellers. The services include water supply,
sewage treatment and disposal, solid waste management, disaster management, buildings and roads, street
lighting, maintenance of parks and open spaces, cemeteries and crematoriums, conservation of heritage
sites, and registering of births and deaths.
3.

Details of Proposed Systems :


I.

II.

Proposed capacity of the Solar Water Heating System is as below:


Unit Capcity (LPD)

Proposed Units

Gross Capcity (LPD)

50-100 bedded hospitals

3000

10

30000

20- 50 bedded

2000

50

100000

Availability of shadow free roof area for the power plant : Sufficient area (90 sqm for 3000LPD and
70sqm for 2000LPD system) is available in each hospital.
101

PART C: Implementation Schedule

Major Monitorable Milestones


Sl.
No.
1
2
3
4
5
6
7

Activities

Progress Months
4
5
6
7

Application/ clearance from MNRE


Procurement Process
Site survey & ystem integration layout
Erection of collector mounting Structures
Installation of Collectors & storage tank
Distribution Pipings
Testing and commissioning

Project Commissioning Timeline

Project can be completed within 6 months from the date of finalization of technology partner.
PART D: Performance Monitoring Mechanism:
Performance will be monitored with
facilities for daily, monthly & annual
(Daily, Monthly and Annual energy generation,
power generation. Energy meters and
logging, compilation and sharing with MNRE)
data loggers will be installed accordingly.
Performance Data Monitoring

Monthly
monitoring
of
reduction
in
diesel/electricity/ other fuel consumption, if any.

Yes

Own Mechanism

In built monitoring system with energy


meter and data logger will installed

Third Party

5 years AMC will be signed with the


supplier
Yes

PART E: Project Cost and Financing Details.


i. Cost of Systems Hardware
ii. Cost of transportation and insurance
iii. Cost of civil works and electrical works
iv. Cost of installation and commissioning
v. Cost of Annual Maintenance for 5 years
vi. Any other cost
Total Cost of the Systems/Project
Total Capacity & Collector Area

211.00Lakh
4.00Lakh
16.00Lakh
16.00Lakh
4.00Lakh
20.00Lakh
251.00Lakh
130000LPD (2600sqm)
102

Means of Finance
a) Contribution of Project Proponent
b) Contribution
of
Beneficiaries
organization
c) Envisaged CFA from MNRE
d) Other Source (s) of Funding (capital
grant)
e) Envisaged Soft Loan assistance, if any
f) Whether funds are in surplus or
deficiency
Details of Project Revenue recurring, if any

NA

Project Duration

6 months

a) Contribution of Project Proponent


b) Contribution from
beneficiaries:
c) CFA from MNRE

165.20Lakh
85.80Lakh

PART F: Operation and Maintenance Arrangements


The supplier will train engineers and technicians of KDMC / hospital authority for day to day operation,
monitoring and scheduled maintenance work such as cleaning, topping up of batteries etc.
- Detail of Operation and Maintenance Arrangements.
The system will be procured with minimum 5 years comprehensive annual maintenance contract service.
During this period engineers and technicians from KDMC/ hospital will be trained for O&M of the system.
- Arrangement for Energy Savings Data Collection
(i)

Flow meter will be installed where in manual recording of the reading will be maintained in a
log. The reading will be taken on a regular periodic basis.

(ii)

Data logging system for recording water temperature would be installed. This system will keep a
log of the cold water and hot water at the inlet and outlet of the SWH system respectively.

(iii)

Energy delivered in kcal by the SWH system will be calculated based on the quantity of the
water consumed and temperature rise of the water (t).

(iv)

The flow meter reading needs to be taken regularly and average from the temperature logging
system needs to be noted regularly.

(v)

Collected data will be reported to MNRE/ designated agencies on regular basis

- Method of monitoring of reduction in conventional fuel consumption, if any. - NA


- Strategy for training of the O&M Personnel of the Beneficiary Organization.
As stated above

103

PART G: Declarations
It is certified that I/we have read the guidelines issued by the Ministry vide 5/23/2009/P&C dated 16th June,
2010 and the related provisions/terms and conditions for availing financial support from the Ministry of New
and Renewable Energy and I agree to abide by these guidelines and related terms and conditions.
I understand that failure to comply by these guidelines may result in denial of financial support by the
Ministry.
I confirm that the present proposal in full or part has not been submitted / has been submitted to any other
agency for seeking support (In case proposal has been submitted to any other agency or under consideration
all details and a copy of the proposal must be submitted along with the present proposal).
I confirm that I will not submit the same proposal or a part thereof to any other funding agency, without
prior knowledge of the Ministry of New and Renewable Energy.
I confirm that the share of project proponent/beneficiaries shall not be lower than 20% in any
circumstances. Projects owned by the Programme Administrators are exempt from this condition.
I confirm that the proposed solar thermal system(s) have not been installed/supplied at the proposed sites
or to the proposed beneficiaries, prior to the receipt of project sanction letter from the Ministry.
There is no duplication in the proposal and the submitted proposal is the only proposal by the proponent
and to the best of my / our knowledge no other organization has submitted any proposal for the systems at
these site(s) to MNRE for financial support.
A detailed site survey has been done/or will be undertaken to identify the beneficiaries before actual supply
and installation takes place.
In case of System Integrators, the beneficiaries will be charged net of MNRE subsidy towards cost of systems
installed by them at their respective places.
I confirm that in case of any dispute, the decision of Secretary, Ministry of New and Renewable Energy,
Government of India will be final and binding on all.

Signature _____________
Name & Designation of Authorized Signatory
Seal

Place:
Date:

104

Annexure
DETAILS OF SYSTEMS TO BE INSTALLED
Sl.
no

Systems
to be
installed

Type
of
systems/
collector to be
used*

Solar
water
heating
systems

Flat plate type

Place(s) of
installation**

No. of
systems

No. of
collecto
rs/
dishes

Total
collector
area
(sq. m)

Applicatio
n

Total cost of
systems/
units
including
AMC
for 5 yrs
(apprx)

Subsidy
sought
from
MNRE @
Rs.3300/s
q. m

50 beded
Hospitals

10

300

600

Hot water

58.00 Lakh

19.80

<50 bedded
hospitals

50

1000

2000

Hot water

193.00 Lakh

66.00

60

1300

2600

251.00

85.80

State
subsidy
to be
availed
if any
@
Rs. ----

Expected
date
of
completion

a) Domestic
b) Others

Sept 2011

ETC type
a) Domestic
b) Others
Storage
collector

cum

type

* Only those systems will be eligible for subsidy which have BIS/MNRE standards/ specifications or have
approval from test centers of MNRE
** For domestic systems, only area of operation/implementation will be mentioned
This is to certify that the various components of the Solar Thermal System (s) conform to the Relevant
Standards, as mentioned in the Guidelines for Off-grid and Decentralized Solar Applications for Solar
Collectors and components under JNNSM. Copies of the Relevant BIS/MNRE Certificates/specifications
should be enclosed.
Note: It is mandatory to provide technical performance specifications of each component of the system(s) to
be installed under the project and for which the performance will be warranted. All technical parameters
and warranty requirements must meet or exceed the requirements mentioned in the guidelines issued by
the Ministry.

(Signature & Seal of Channel partner)


as Head of Organization
105

8. Annexure II Pilot Project II

Project Proposals
for
Solar Thermal Systems/ Devices
Under
Develppment of Solar City Programme of MNRE
1.

Title of the Project : Solar Water Heating System for Hotels and Restaurants in Kalyan Dombivli
Municipal Area
2.
Name of the Project Proponent : Kalyan Dombivli Municipal Corporation
3.
Socio- Economic Justification of the Project:
There are many benefits of from solar water heater, and number one is economics. Solar water heater
economics compare quite favorably with those of electric water heaters, while the economics aren't quite so
attractive when compared with those of gas water heaters. Heating water with the sun also means longterm benefits, such as being cushioned from future fuel shortages and price increases, and environmental
benefits.
Economic Benefits
Solar water heaters offered the largest potential savings compared to electric heating, with solar waterheater owners saving as much as 50% to 85% annually on their utility bills over the cost of electric water
heating. Typical simple payback period of a solar water heating system is 2 to 3 years.
Tax Incentives and Rebates
Ministry of New and Renewable Energy (MNRE) offers subsidies on domestic as well as commercial solar
water heating systems installations. Government of India offers 80% depreciation claim in the first two years
itself on installation of commercial solar water heating systems.
Long-Term Benefits
Solar water heaters offer long-term benefits that go beyond simple economics. In addition to having free hot
water after the system has paid for itself in reduced utility bills, it contributes towards future fuel shortages
and price increases and reduce country's dependence on foreign oil.
Environmental Benefits
Solar water heaters do not pollute and contribute in reduction of GHG emission. A 100 LPD solar water
heater system when replaces an electric water heater, the electricity displaced over 20 years represents
more than 30 tons of avoided carbon dioxide emissions alone.
4.

Benefits of the proposed project:

There are about 720 restaurants and food carts in Kalyan Dombivli Municipal area out of which 100
restaurants are of medium size, 50 are large, 350 are small and 225 are foodcarts. There are 5 budget hotels
in the municipalty area. It is proposed to install Solar Water Heating systems in hotels and restaurants in
KDMC area based on the hot water demand and available area for installation of such systems. Total
potential for solar water heating systems in the hotels and restaurants is estimated to be 432000 LPD.
Complete installation of solar water heaters in the hospitals will save about 7.60MU electricity per year and
reduce about 6460 tons of GHG per year. The target for the first phase is to install 140000LPD solar water
heating systems in 5 hotels, 10 large restaurants, 25 medium restaurant and 50 small restaurant.
106

Ministry of New and Renewbale Energy (MNRE) declared KDMC as a Solar City and a master plan has been
prepared to reduce 10% energy consumption through renewable energy and energy efficiency measures.
The master plan sets a goal to reduce 168MU electricity per year within 5 years period. Implementation of
solar water heating projects in hotels and restaurant can contribute 4.5% towards the set goal.
Most importantly, hotels and restaurants will save considerable amount of electricity and will enjoy free hot
water within 2-3 years of payback on the investment. They will avail subsidy from the MNRE and may avail
80% depreciation benefit in the first two years.
PART-A: Details of the Project Proponent
I

II

III

IV

Name and Category of Project Proponent


a) Renewable Energy Service Providing
Company (RESCO)
b) Financial Institutions (Banks, NBFCs, MFIs)
c) Financial Integrator
d) System Integrator
e) Program Administrator
Name, Designation and Address of the Authorized
Representative for correspondence with telephone
no, fax & email

Name of the Project Proponent:


Kalyan Dombivli Municipal
Corporation, Kalyan Dombivli,
Maharashtra.
Category: Program Administrator.
Name: The Commissioner
Address: Kalyan Dombivli
Municipal Corporation
KDMC, Shankarrao Chowk,
Kalyan West - 421301

In case of Channel Partner other than Programme


Administrator, the following information will be
provided:
a) Whether commercial or non-commercial.
b) Copy of Articles of Association, Registration
No. & Date
NA
c) Audited Balance Sheet for last three years
d) Annual Report of previous year
e) Whether MNRE has earlier sanctioned any
Solar
Thermal
project
(s)
for
implementation to the Project Proponent, if
yes, please furnish information
In case of 1 (e), Please indicate:
Autonomous Institution set by
a) Government Department, Autonomous State Government (Urban Local
Institution set up by Central/ State Body)
Government, State renewable Energy
development agency, Public Sector
Undertaking
b) Others

PART-B: Details of the Project


Kalyan Dombivli is an important satellite township of Mumbai city. It is an important railway junction. The
city of Kalyan Dombivli forms one of the important urban agglomerations of Maharashtra state. Owing to
large urbanizable zone and its proximity to greater Mumbai, Kalyan Dombivli is trying to enhance the quality
of services, expand the infrastructure and accelerate its economic growth. It has not only made its presence
felt in terms of overall development and commercialization but also in its many eco drives for a sustainable
future. Kalyan Dombivli has been approved by the Ministry of New and Renewable Energy to be developed
as a solar city. Kalyan Dombivli Municipal Corporation (KDMC) is the main organization which is responsible
107

for urban governance and civic management in the city of Kalyan Dombivli. The corporation has a
democratically elected leadership from the constituencies within the geographic jurisdiction of the
corporation boundaries. Kalyan Dombivli Municipal Corporation is a very active organization for initiating
good practices and it has also come with the added supportive policy framework from Maharasthra
Government for the implementation of renewable energy initiatives.
There are about 720 restaurants and food carts in Kalyan Dombivli Municipal area out of which 100
restaurants are of medium size, 50 are large, 350 are small and 225 are foodcarts. There are 5 budget hotels
in the municipalty area. It is proposed to install Solar Water Heating systems in hotels and restaurants in
KDMC area based on the hot water demand and available area for installation of such systems. The target
for the first phase is to install 140000LPD solar water heating systems in 5hotels, 10 large restaurants, 25
medium restaurant and 50 small restaurant.
4. Details of Project site:
The Kalyan Dombivli city is located at geographical coordinates of 27.18 N and 78.02 E. The administrative
building of Kalyan Dombivli Municipal Corporation is located in the heart of the city. Average annual solar
radiation in Kalyan Dombivli is 5.08kWh/m2/day.
5. Details of Project Beneficiaries:
Kalyan Dombivli Municipal Corporation (KDMC) will be the direct beneficiary of the project. KDMC is
responsible for providing the basic services infrastructure to city dwellers. The services include water supply,
sewage treatment and disposal, solid waste management, disaster management, buildings and roads, street
lighting, maintenance of parks and open spaces, cemeteries and crematoriums, conservation of heritage
sites, and registering of births and deaths.
6. Details of Proposed Systems :
Proposed capacity of the Solar Water Heating System:
Beneficiaries
Budget Hotels
Large Restaurant
Medium Restaurant
Small Restaurant
III.

Capcity of SWH (LPD)


2000
3000
2000
1000

Target
5
10
25
50
Total

Total Capacity (LPD)


10000
30000
50000
50000
140000

Availability of shadow free roof area for the power plant : Sufficient area (90 sqm for 3000LPD,
70sqm for 2000LPD system and 35sqm for 1000LPD) is available in the proposed hotels and
restaurants.

PART C: Implementation Schedule

Major Monitorable Milestones


No.
1
2
3
4
5
6
7

Activities

Progress Months
4
5
6

Application/ clearance from MNRE


Procurement Process
Site survey & ystem integration layout
Erection of collector mounting Structures
Installation of Collectors & storage tank
Distribution Pipings
Testing and commissioning
108

Project Commissioning Timeline

Project can be completed within 6 months from the date of finalization of technology partner.
PART D: Performance Monitoring Mechanism:
Performance Data Monitoring
Performance will be monitored with
(Daily, Monthly and Annual energy generation, facilities for daily, monthly & annual
logging, compilation and sharing with MNRE)
power generation. Energy meters and
data loggers will be installed accordingly.
Monthly
monitoring
of
reduction
in
Yes
diesel/electricity/ other fuel consumption, if any.
Own Mechanism
In built monitoring system with energy
meter and data logger will installed
Third Party
5 years AMC will be signed with the
supplier
Yes
PART E: Project Cost and Financing Details.

i.
ii.
iii.
iv.
v.
vi.

213.00Lakh
4.00Lakh
16.00Lakh
16.00Lakh
20.00Lakh
4.00Lakh

Cost of Systems Hardware


Cost of transportation and insurance
Cost of civil works and electrical works
Cost of installation and commissioning
Cost of Annual Maintenance for 5 years
Any other cost

Total Cost of the Systems/Project


Total Capacity & Collector Area
Means of Finance

140000LPD (2800sqm)

271.00Lakh

a) Contribution of Project Proponent


b) Contribution
of
Beneficiaries a) Contribution of Project Proponent
organization
c) Envisaged CFA from MNRE
d) Other Source (s) of Funding (capital b) Contribution from
beneficiaries:
178.60Lakh
grant)
c) CFA from MNRE
92.40Lakh
e) Envisaged Soft Loan assistance, if any
f) Whether funds are in surplus or
deficiency
Details of Project Revenue recurring, if any
Project Duration

NA
6 months

PART F: Operation and Maintenance Arrangements


The supplier will train engineers and technicians of KDMC / hotels/restaurant authority for day to day
operation, monitoring and scheduled maintenance work such as cleaning, topping up of batteries etc.
109

- Detail of Operation and Maintenance Arrangements.


The system will be procured with minimum 5 years comprehensive annual maintenance contract service.
During this period engineers and technicians from KDMC/ hotels/restaurants will be trained for O&M of the
system.
- Arrangement for Energy Savings Data Collection
a) Flow meter will be installed where in manual recording of the reading will be maintained in a log.
The reading will be taken on a regular periodic basis.
b) Data logging system for recording water temperature would be installed. This system will keep a log
of the cold water and hot water at the inlet and outlet of the SWH system respectively.
c) Energy delivered in kcal by the SWH system will be calculated based on the quantity of the water
consumed and temperature rise of the water (t).
d) The flow meter reading needs to be taken regularly and average from the temperature logging
system needs to be noted regularly.
e) Collected data will be reported to MNRE/ designated agencies on regular basis
- Method of monitoring of reduction in conventional fuel consumption, if any. - NA
- Strategy for training of the O&M Personnel of the Beneficiary Organization.
As stated above

110

PART G: Declarations
It is certified that I/we have read the guidelines issued by the Ministry vide 5/23/2009/P&C dated 16th June,
2010 and the related provisions/terms and conditions for availing financial support from the Ministry of New
and Renewable Energy and I agree to abide by these guidelines and related terms and conditions.
I understand that failure to comply by these guidelines may result in denial of financial support by the
Ministry.
I confirm that the present proposal in full or part has not been submitted / has been submitted to any other
agency for seeking support (In case proposal has been submitted to any other agency or under consideration
all details and a copy of the proposal must be submitted along with the present proposal).
I confirm that I will not submit the same proposal or a part thereof to any other funding agency, without
prior knowledge of the Ministry of New and Renewable Energy.
I confirm that the share of project proponent/beneficiaries shall not be lower than 20% in any
circumstances. Projects owned by the Programme Administrators are exempt from this condition.
I confirm that the proposed solar thermal system(s) have not been installed/supplied at the proposed sites
or to the proposed beneficiaries, prior to the receipt of project sanction letter from the Ministry.
There is no duplication in the proposal and the submitted proposal is the only proposal by the proponent
and to the best of my / our knowledge no other organization has submitted any proposal for the systems at
these site(s) to MNRE for financial support.
A detailed site survey has been done/or will be undertaken to identify the beneficiaries before actual supply
and installation takes place.
In case of System Integrators, the beneficiaries will be charged net of MNRE subsidy towards cost of systems
installed by them at their respective places.
I confirm that in case of any dispute, the decision of Secretary, Ministry of New and Renewable Energy,
Government of India will be final and binding on all.

Signature _____________
Name & Designation of Authorized Signatory
Seal
Place:
Date:

111

Annexure
DETAILS OF SYSTEMS TO BE INSTALLED
Sl.
no

Systems
to be
installed

Type
of
systems/
collector to be
used*

Solar
water
heating
systems

Flat plate type


a) Domestic
b) Others

Place(s) of
installation**

No. of
system
s

No. of
collecto
rs/
dishes

Total
collector
area
(sq. m)

Applicatio
n

Hotels
Large Restaurants
Med Restaurant
Small Restaurant
Total

5
10
25
50
90

100
300
500
500
1400

200
600
1000
1000
2800

Hot water
Hot water
Hot water
Hot water
Hot water

Total cost of
systems/
units
including
AMC
for 5 yrs
(apprx)

Subsidy
sought
from
MNRE @
Rs.3300/s
q. M

State
subsidy to
be
availed if
any @
Rs. ----

Expected
date
of
completi
on

271.00Lac

92.40Lac

178.60Lac

Sept 2011

ETC type
a) Domestic
b) Others
Storage cum
collector
type

* Only those systems will be eligible for subsidy which have BIS/MNRE standards/ specifications or have
approval from test centers of MNRE
** For domestic systems, only area of operation/implementation will be mentioned
This is to certify that the various components of the Solar Thermal System (s) conform to the Relevant
Standards, as mentioned in the Guidelines for Off-grid and Decentralized Solar Applications for Solar
Collectors and components under JNNSM. Copies of the Relevant BIS/MNRE Certificates/specifications
should be enclosed.
Note: It is mandatory to provide technical performance specifications of each component of the system(s) to
be installed under the project and for which the performance will be warranted. All technical parameters
and warranty requirements must meet or exceed the requirements mentioned in the guidelines issued by
the Ministry.

(Signature & Seal of Channel partner)


as Head of Organization

112

9. Annexure III Pilot Project III

Project Proposals
for
Solar Thermal Systems/ Devices
Under
Develppment of Solar City Programme of MNRE
1. Title of the Project : Solar Water Heating System for Residential Apartment Building in Kalyan
Dombivli Municipal Area
2. Name of the Project Proponent : Kalyan Dombivli Municipal Corporation
3. Socio- Economic Justification of the Project:
There are many benefits of from solar water heater, and number one is economics. Solar water heater
economics compare quite favorably with those of electric water heaters, while the economics aren't quite so
attractive when compared with those of gas water heaters. Heating water with the sun also means longterm benefits, such as being cushioned from future fuel shortages and price increases, and environmental
benefits.
Economic Benefits
Solar water heaters offered the largest potential savings compared to electric heating, with solar waterheater owners saving as much as 50% to 85% annually on their utility bills over the cost of electric water
heating. Typical simple payback period of a solar water heating system is 2 to 3 years.
Tax Incentives and Rebates
Ministry of New and Renewable Energy (MNRE) offers subsidies on domestic as well as commercial solar
water heating systems installations. Government of India offers 80% depreciation claim in the first two years
itself on installation of commercial solar water heating systems.
Long-Term Benefits
Solar water heaters offer long-term benefits that go beyond simple economics. In addition to having free hot
water after the system has paid for itself in reduced utility bills, it contributes towards future fuel shortages
and price increases and reduce country's dependence on foreign oil.
Environmental Benefits
Solar water heaters do not pollute and contribute in reduction of GHG emission. A 100 LPD solar water
heater system when replaces an electric water heater, the electricity displaced over 20 years represents
more than 30 tons of avoided carbon dioxide emissions alone.
4. Benefits of the proposed project:
There are about 8000 residential apartment building Society Kalyan Dombivli Municipal area which
accommodate about 160000 famlies. Generally hot water demand of residents is met from electric geysers.
These electric geysers can be replaced with solar water heating system based on the availability of space to
install such system in the apartment buildings. If 10% of such apartment complex are installed with solar
water heating system of capacity, total solar water heating systems will be 1600,000LPD which will save
about 18.90MU electricity per year and reduce about 15120 tons of GHG per year.

113

Ministry of New and Renewbale Energy (MNRE) declared KDMC as a Solar City and a master plan has been
prepared to reduce 10% energy consumption through renewable energy and energy efficiency measures.
The master plan sets a goal to reduce 168MU electricity per year within 5 years period. Implementation of
solar water heating projects in hotels and restaurant can contribute 11.25% towards the set goal.
Most importantly, hotels and restaurants will save considerable amount of electricity and will enjoy free
hotwater within 2-3 years of payback on the investment. They will avail subsidy from the MNRE and may
avail 80% depreciation benefit in the first two years.
PART-A: Details of the Project Proponent
I

II

III

IV

Name and Category of Project Proponent


a) Renewable Energy Service Providing
Company (RESCO)
b) Financial Institutions (Banks, NBFCs, MFIs)
c) Financial Integrator
d) System Integrator
e) Program Administrator
Name, Designation and Address of the Authorized
Representative for correspondence with telephone
no, fax & email
In case of Channel Partner other than Programme
Administrator, the following information will be
provided:

Name of the Project Proponent:


Kalyan Dombivli Municipal
Corporation, Kalyan Dombivli,
Maharashtra.
Category: Program Administrator.
Name: The Commissioner
Address: Kalyan Dombivli
Municipal Corporation
KDMC, Shankarrao Chowk,
Kalyan West - 421301

a) Whether commercial or non-commercial.


b) Copy of Articles of Association, Registration
No. & Date
NA
c) Audited Balance Sheet for last three years
d) Annual Report of previous year
e) Whether MNRE has earlier sanctioned any
Solar
Thermal
project
(s)
for
implementation to the Project Proponent, if
yes, please furnish information
In case of 1 (e), Please indicate:
Autonomous Institution set by
State Government (Urban Local
a) Government Department, Autonomous Body)
Institution set up by Central/ State
Government, State renewable Energy
development agency, Public Sector
Undertaking
b) Others

114

PART-B: Details of the Project


Kalyan Dombivli is an important satellite township of Mumbai city. It is an important railway junction. The city
of Kalyan Dombivli forms one of the important urban agglomerations of Maharashtra state. Owing to large
urbanizable zone and its proximity to greater Mumbai, Kalyan Dombivli is trying to enhance the quality of
services, expand the infrastructure and accelerate its economic growth. It has not only made its presence felt
in terms of overall development and commercialization but also in its many eco drives for a sustainable
future. Kalyan Dombivli has been approved by the Ministry of New and Renewable Energy to be developed as
a solar city. Kalyan Dombivli Municipal Corporation (KDMC) is the main organization which is responsible for
urban governance and civic management in the city of Kalyan Dombivli. The corporation has a democratically
elected leadership from the constituencies within the geographic jurisdiction of the corporation boundaries.
Kalyan Dombivli Municipal Corporation is a very active organization for initiating good practices and it has
also come with the added supportive policy framework from Maharasthra Government for the
implementation of renewable energy initiatives.
There are about 8000 residential apartment building Society Kalyan Dombivli Municipal area which
accommodate about 160,000 famlies with an average of 20 families per apartment. It is proposed to install
solar water heaters in 800 apartments (10% of total apartment) to provide hot water to about 16000
families using solar water heating systems of 160,000LPD capcity.
1. Details of Project site:
The Kalyan Dombivli city is located at geographical coordinates of 27.18 N and 78.02 E. The
administrative building of Kalyan Dombivli Municipal Corporation is located in the heart of the city.
Average annual solar radiation in Kalyan Dombivli is 5.08kWh/m2/day.
2.

3.
I.

Details of Project Beneficiaries:


Kalyan Dombivli Municipal Corporation (KDMC) will be the direct beneficiary of the project. KDMC is
responsible for providing the basic services infrastructure to city dwellers. The services include water
supply, sewage treatment and disposal, solid waste management, disaster management, buildings and
roads, street lighting, maintenance of parks and open spaces, cemeteries and crematoriums,
conservation of heritage sites, and registering of births and deaths.
Details of Proposed Systems :
Proposed capacity of the Solar Water Heating System:
Beneficiaries
Residential Apartment

II.

No. of
families
20

Capcity of
SWH (LPD)
2000

Target

Total Capacity (LPD)

800

160,000

Availability of shadow free roof area for the power plant : Sufficient area (70sqm for 2000LPD system) is
available in the proposed apartments.

115

PART C: Implementation Schedule

Major Monitorable Milestones


S

No.
1
2
3
4
5
6
7

Activities

Progress Months
4
5
6
7

Application/ clearance from MNRE


Procurement Process
Site survey & ystem integration layout
Erection of collector mounting Structures
Installation of Collectors & storage tank
Distribution Pipings
Testing and commissioning

Project Commissioning Timeline

Project can be completed within 6 months from the date of finalization of technology partner.
PART D: Performance Monitoring Mechanism:
Performance will be monitored with
Performance Data Monitoring
(Daily, Monthly and Annual energy generation, facilities for daily, monthly & annual
power generation. Energy meters and
logging, compilation and sharing with MNRE)
data loggers will be installed accordingly.
Monthly monitoring of reduction in
Yes
diesel/electricity/ other fuel consumption, if any.
Own Mechanism
In built monitoring system with energy
meter and data logger will installed
Third Party
5 years AMC will be signed with the
supplier
Yes
PART E: Project Cost and Financing Details.
i.
ii.
iii.
iv.
v.
vi.

Cost of Systems Hardware


Cost of transportation and insurance
Cost of civil works and electrical works
Cost of installation and commissioning
Cost of Annual Maintenance for 5 years
Any other cost

Total Cost of the Systems/Project


Total Capacity & Collector Area
Means of Finance
a) Contribution of Project Proponent
b) Contribution
of
Beneficiaries
organization
c) Envisaged CFA from MNRE

244.00Lakh
5.00Lakh
19.00Lakh
19.00Lakh
23.00Lakh
5.00Lakh
160,000LPD (3200sqm)

314.00Lakh

a) Contribution of Project Proponent


b) Contribution from
beneficiaries:
208.40Lakh
c) CFA from MNRE
105.60Lakh
116

d) Other Source (s) of Funding (capital


grant)
e) Envisaged Soft Loan assistance, if any
f) Whether funds are in surplus or
deficiency
Details of Project Revenue recurring, if any
NA
Project Duration
6 months
PART F: Operation and Maintenance Arrangements
The supplier will train engineers and technicians of KDMC / housing society for day to day operation,
monitoring and scheduled maintenance work such as cleaning, topping up of batteries etc.
- Detail of Operation and Maintenance Arrangements.
The system will be procured with minimum 5 years comprehensive annual maintenance contract service.
During this period engineers and technicians from KDMC/ housing society will be trained for O&M of the
system.
- Arrangement for Energy Savings Data Collection
(I) Flow meter will be installed where in manual recording of the reading will be maintained in a log.
The reading will be taken on a regular periodic basis.
(II) Data logging system for recording water temperature would be installed. This system will keep a log
of the cold water and hot water at the inlet and outlet of the SWH system respectively.
(III) Energy delivered in kcal by the SWH system will be calculated based on the quantity of the water
consumed and temperature rise of the water (t).
(IV) The flow meter reading needs to be taken regularly and average from the temperature logging
system needs to be noted regularly.
(V) Collected data will be reported to MNRE/ designated agencies on regular basis
- Method of monitoring of reduction in conventional fuel consumption, if any. - NA
- Strategy for training of the O&M Personnel of the Beneficiary Organization.
As stated above

117

PART G: Declarations
It is certified that I/we have read the guidelines issued by the Ministry vide 5/23/2009/P&C dated 16th June,
2010 and the related provisions/terms and conditions for availing financial support from the Ministry of New
and Renewable Energy and I agree to abide by these guidelines and related terms and conditions.
I understand that failure to comply by these guidelines may result in denial of financial support by the
Ministry.
I confirm that the present proposal in full or part has not been submitted / has been submitted to any other
agency for seeking support (In case proposal has been submitted to any other agency or under consideration
all details and a copy of the proposal must be submitted along with the present proposal).
I confirm that I will not submit the same proposal or a part thereof to any other funding agency, without
prior knowledge of the Ministry of New and Renewable Energy.
I confirm that the share of project proponent/beneficiaries shall not be lower than 20% in any
circumstances. Projects owned by the Programme Administrators are exempt from this condition.
I confirm that the proposed solar thermal system(s) have not been installed/supplied at the proposed sites
or to the proposed beneficiaries, prior to the receipt of project sanction letter from the Ministry.
There is no duplication in the proposal and the submitted proposal is the only proposal by the proponent
and to the best of my / our knowledge no other organization has submitted any proposal for the systems at
these site(s) to MNRE for financial support.
A detailed site survey has been done/or will be undertaken to identify the beneficiaries before actual supply
and installation takes place.
In case of System Integrators, the beneficiaries will be charged net of MNRE subsidy towards cost of systems
installed by them at their respective places.
I confirm that in case of any dispute, the decision of Secretary, Ministry of New and Renewable Energy,
Government of India will be final and binding on all.

Signature _____________
Name & Designation of Authorized Signatory
Seal
Place:
Date:

118

Annexure
DETAILS OF SYSTEMS TO BE INSTALLED
Sl.
no

Systems
to be
installed

Type
of
systems/
collector to be
used*

Solar
water
heating
systems

Flat plate type


a) Domestic
b) Others

Place(s) of
installation**

No. of
system
s

No. of
collect
ors/
dishes

Total
collector
area
(sq. m)

Applica
tion

Total cost
of
systems/
units
including
AMC
for 5 yrs
(apprx)

Subsidy
sought
from MNRE
@
Rs.3300/sq.
m

State
subsidy to
be
availed if
any @
Rs. ----

Expected
date
of
completion

Apartment
complex

800

16000

32000

Hot
water

314.00Lac

105.60Lac

208.40Lac

Sept.2011

ETC type
a) Domestic
b) Others
Storage
cum
collector
type

* Only those systems will be eligible for subsidy which have BIS/MNRE standards/ specifications or have
approval from test centers of MNRE
** For domestic systems, only area of operation/implementation will be mentioned
This is to certify that the various components of the Solar Thermal System (s) conform to the Relevant
Standards, as mentioned in the Guidelines for Off-grid and Decentralized Solar Applications for Solar
Collectors and components under JNNSM. Copies of the Relevant BIS/MNRE Certificates/specifications
should be enclosed.
Note: It is mandatory to provide technical performance specifications of each component of the system(s) to
be installed under the project and for which the performance will be warranted. All technical parameters
and warranty requirements must meet or exceed the requirements mentioned in the guidelines issued by
the Ministry.

(Signature & Seal of Channel partner)


as Head of Organization

119

10. Annexure IV Pilot Project IV

Project Proposal
for
70kWp Stand Alone SPV Power Plant
under
Development of Solar City Programme of MNRE
1. Title of the Project: 70kWp rooftop Solar PV system for Kalyan Dombivli Municipal Corporation Building.
2. Name of the Project Proponent: Kalyan Dombivli Municipal Corporation.
3. Socio- Economic Justification of the Project:
Solar PV power plant generates clean electricity using sunlight thereby off set green house gases
produced by fossil fuel based power generating system. The countrys majority generation capacity is
largely coal based and produces high quantity of carbon dioxide and other harmful gases. If the
untapped solar energy potential is realized carbon dioxide and other toxic gas emissions can be lowered
by significant quantity and thereby saving our environment. Therefore, every kilowatt of solar energy
produced has to be seen from this angle as a small but major step towards mitigation of carbon dioxide
emission and subsequently combat climate change. The proposed 70kWp PV power plant will generate
about 105000 kWh of clean electrical energy per year and will reduce 84 tons of GHG per year. Many
Government and commercial buildings in Kalyan Dombivli use Diesel Generator sets as standby power
supply system during load shedding hours. DG sets create pollution and generation cost of electricity
from DG sets is high which is Rs.15-Rs.20 per kWh based on capacity of DG sets and utilization of
capacity. Solar PV power plant generates electricity at much lower cost then DG sets and use of Solar PV
power plant can replace diesel set completely or reduce fuel consumption. Use of Solar PV power plant
also reduces peak load, air-conditioner load in particular.
4. Benefits of the proposed project:
The proposed 70kWp PV power plant in the KDMC building will generate 105000kWh per year which will
save equivalent amount of electricity consumed from the grid. The power plant will reduce peak load
and will supply power during load shedding hours thereby replace the use of diesel generator sets for
standby power supply.
PV systems are becoming increasingly popular in India however; experience in O&M of such system in is
very low. The first hand experience PV system O&M train engineers and technical staff in Kalyan
Dombivli Municipal Corporation, which will help in developing similar projects in future.

PART-A: Details of the Project Proponent


120

ii

Name and Category of Project Proponent


a) Renewable Energy Service Providing Company
(RESCO)
b) Financial Institutions (Banks, NBFCs, MFIs)
c) Financial Integrator
d) System Integrator
e) Program Administrator

Name of the Project Proponent:


Kalyan Dombivli Municipal
Corporation, Kalyan Dombivli,
Maharashtra.

Name, Designation and Address of the Authorized


Representative for Correspondence with telephone no., fax &
email

Name: The Commissioner


Address: Kalyan Dombivli
Municipal Corporation
KDMC, Shankarrao Chowk,
Kalyan West - 421301

iii In case of Channel Partner other than Programme


Administrator, the following information will be provided:
a) Whether commercial or non-commercial.
b) Copy of Articles of Association, Registration No. & Date;
PAN/TAN No.
c) Audited Balance Sheet for last three years
d) Annual Report of previous year
e) Whether MNRE has earlier sanctioned any SPV projects
for implementation to the Project Proponent, if yes,
please furnish information.
iv In case of 1 (e), please indicate:
a) Government Department, Autonomous Institution set up
by Central/ State Government, State Renewable Energy
Development Agency, Public Sector Undertaking
b) Others

Category: Program Administrator.

NA

Autonomous Institution set by


State Government (Urban Local
Body)

PART-B: Details of the Project


1. Summary of the Proposal:

Kalyan Dombivli is an important satellite township of Mumbai city. It is an important railway


junction. The city of Kalyan Dombivli forms one of the important urban agglomerations of
Maharashtra state. Owing to large urbanizable zone and its proximity to greater Mumbai, Kalyan
Dombivli is trying to enhance the quality of services, expand the infrastructure and accelerate its
economic growth. It has not only made its presence felt in terms of overall development and
commercialization but also in its many eco drives for a sustainable future. Kalyan Dombivli has
been approved by the Ministry of New and Renewable Energy to be developed as a solar city.
Kalyan Dombivli Municipal Corporation (KDMC) is the main organization which is responsible for
urban governance and civic management in the city of Kalyan Dombivli. The corporation has a
democratically elected leadership from the constituencies within the geographic jurisdiction of the
corporation boundaries. Kalyan Dombivli Municipal Corporation is a very active organization for
121

initiating good practices and it has also come with the added supportive policy framework from
Maharasthra Government for the implementation of renewable energy initiatives.
It is proposed to install one 70kWp SPV power plant in Kalyan Dombivli Municipal Corporation as
model Renewable Energy power generating systems to cater the electrical energy demand for the
office and simultaneously to set example and encourage entrepreneurs to invest on such projects.
The system will be installed in the administrative building of KDMC and will be opened to the
interested public and entrepreneurs. Trained manpower will be deployed to explain about the
system and benefits to the interested visitors.
2. Details of Project site:
The Kalyan Dombivli city is located at geographical coordinates of 27.18 N and 78.02 E. The administrative
building of Kalyan Dombivli Municipal Corporation is located in the heart of the city. The building has
sufficient space on its roof for installation of 70kWp PV system. Average annual solar radiation in Kalyan
Dombivli is 5.08kWh/m2/day. The Corporation uses three DG sets (2 nos. 250KVA and 1 no. 100KVA)
alternatively to supply power during load shedding hours. Average load shedding per day reported be 4
hours. Based on the use of DG sets and occurrence of load shedding annual diesel consumption in the
corporation building is about 46.50kL.
3. Details of Project Beneficiaries:
Kalyan Dombivli Municipal Corporation (KDMC) will be the direct beneficiary of the project. KDMC is
responsible for providing the basic services infrastructure to city dwellers. The services include water supply,
sewage treatment and disposal, solid waste management, disaster management, buildings and roads, street
lighting, maintenance of parks and open spaces, cemeteries and crematoriums, conservation of heritage
sites, and registering of births and deaths.
4. Details of Proposed Systems :

I.
II.
III.

Proposed capacity of the SPV Power Plant: 70kWp


Availability of shadow free roof area for the power plant : 1400 Sqm
Details of loads to be energized by Power Plant, calculations and justification for the
proposed capacity and expected annual energy generation

Details of the loads to be energized by Power Plant:-

Table fans
Ceiling Fans
Exhaust fans
Wall Fans
Air Conditioner I
Air Conditioner II
Air Conditioner III
Air Conditioner IV
Air Conditioner V
Television

Total
Annual
Annual
Total Load
Load
Hours of
Consumption Utilisation Consumption
No.s (W)
(kW)
Operation / Day (kWh)
(days)
(kWh)
34
60
2.04
9
18
300
5508
241
60
14.46
9
130
300
39042
44
300
13.20
9
119
300
35640
10
100
1.00
9
9
300
2700
42 1800
75.60
6
454
300
136080
2 9000
18.00
6
108
300
32400
4 6000
24.00
6
144
300
43200
6 3600
21.60
6
130
300
38880
2 2400
4.80
6
29
300
8640
2
100
0.20
4
1
300
240
122

Refrigerator
Electric Water Pump
Water Cooler
Incandescent
CFLs
Fluorescent Long
36 watt CFLs
Computers
TOTAL

2
200
2 11250
5
300
38
60
30
11
766
55
80
36
250
100

0.40
22.50
1.50
2.28
0.33
42.13
2.88
25.00
271.92

1
4
4
4
5
8
4
10

0
90
6
9
2
337
12
250
1597

Standby Power Supply:


DG set I
Diesel consumption @ 75% load
DG Set II
Diesel consumption @ 75% load
DG set III
Diesel Consumption @ 100% load
Power supplied by DG set per year assuming 50% usage of DG I, 50%
usage of DG II and 75% usage of DG III
Diesel consumption per day assuming 50% use of DG I, 50% use of
DG II and 75% use of DGIII
Diesel consumption per year
Rooftop PV system for diesel abetment
Approximate solar array area
Approximate annual energy generation
Fraction of DG power replaced
Amount of diesel saved per year
Emission reduction

300
300
300
300
300
300
300
300

250
40
250
40
100
25

120
27000
1800
2736
495
101112
3456
75000
554049

KVA
Ltrs./hr
KVA
Ltrs./hr
KVA
Ltrs./hr

240000 kWh
235
46500
70
70
105000
44%
20344
84

Ltrs.
Ltrs.
kWp
sqm
kWh
Ltrs.
tonnes

IV. Output Voltage of the Power Plant: 440 V


V. Storage battery capacity: 300 kWh (3 hours backup for entire load except ACs and water pump)
VI. Building for housing the battery bank and plant control systems: Separate rooms within the building
available
VII. Distribution Network (if any): The existing distribution network will be used
VIII. Expected reduction in diesel consumption, if any: 30% (21500 liters per year)
System Components
PV Module

Charge Controller/
Inverter

Make and
Model
Make: MNRE
approved supplier
Mono/ Multi
crystalline
MNRE approved
supplier

Capacity

Numbers

200Wp at
STC

350 nos.

70kW

Integral part of
Power
Conditioning Unit

Indigenous/
Imported
Indigenous

Indigenous

123

Power Conditioning
Unit
Storage Battery Bank
Performance Data
Acquisition System
Other components

MNRE approved
supplier
MNRE approved
supplier
BIS or equivalent

70kW

1 no.

Indigenous

300kWh

1 set.

Indigenous

NA

1 No

Indigenous

BIS approved or
equivalent

As
As required
applicable

Indigenous

124

PART C: Implementation Schedule


o

Major Monitorable Milestones


Sl.
No.

Activities

Application/ clearance from MNRE

Procurement Process

Site survey & Engineering design

Erection of array mounting Structures

Module mounting and cabling

Installation of Power Conditioning Unit

Testing and commissioning

Progress Months
1

Project Commissioning Timeline

Project can be completed within 6 months from the date of finalization of vendor.

PART D: Performance Monitoring Mechanism:


Performance Data Monitoring
(Daily, Monthly and Annual energy
generation , logging, compilation and sharing with
MNRE)
Monthly monitoring of reduction in diesel
consumption, if any
Own Mechanism
Third Party
Remote Monitoring (for SPV power plants
having capacity above 5 kWp)

Performance will be monitored with facilities for


daily, monthly & annual power generation. Energy
meters and data loggers will be installed
accordingly.
Yes
In built monitoring system with energy meter and
data logger will installed
5 years AMC will be signed with the supplier
Yes

PART E: Project Cost and Financing Details.


i. Cost of Systems Hardware
ii. Cost of transportation, insurance
iii. Cost of civil works and electrical works
iv. Cost of installation and Commissioning
v. Cost of Annual Maintenance for 5 years
vi. Any other related costs
Total Cost of Systems

Rs. 168.00
Rs.3.00
Rs. 13.00
Rs.13.00
Rs. 13.00
Rs. 2.00
Rs. 212.00

125

Total kWp SPV Capacity

70kWp

Means of Finance
a) Contribution of Project Proponent
b) Contribution of Beneficiaries organization
c) Envisaged CFA from MNRE
d) Other Source (s) of Funding (capital grant)
e) Envisaged Soft Loan assistance, if any
f) Whether funds are in surplus or deficiency
Details of Project Revenue recurring, if any

NA

Project Duration

6 Months

a) KDMC : Rs. 106.00 Lakh


b) MNRE: Rs. 106.00 Lakh

PART F: Operation and Maintenance Arrangements


The supplier will train engineers and technicians of KDMC for day to day operation, monitoring and
scheduled maintenance work such as cleaning, topping up of batteries etc.
- Detail of Operation and Maintenance Arrangements.
The system will be procured with minimum 5 years comprehensive annual maintenance contract service.
During this period engineers and technicians from KDMC will be trained for O&M of the system.
- Arrangement for Generation Data Collection (applicable for SPV Power Plants having more than 10 kWp
capacity). Details of monitoring equipment proposed to be installed and method of supplying data to MNRE/
designated agency.
As stated above
- Method of monitoring of reduction in diesel consumption, if any. DG set logbook is being maintained in the
KDMC. The same will be maintained to know in reduction of operating time of DG sets after installation of PV
systems. The Solar system will
- Strategy for training of the O&M Personnel of the Beneficiary Organization.
As stated above

126

PART G: Declarations and Certificates


A. It is certified that I/we have read the guidelines issued by the Ministry vide 5/23/2009/P&C dated 16th
June, 2010 and the related provisions/terms and conditions for availing financial support from the Ministry
of New and Renewable Energy and I agree to abide by these guidelines and related terms and conditions.
B. I understand that failure to comply by these guidelines may result in denial of financial support by the
Ministry.
C. I confirm that the present proposal in full or part has not been submitted / has been submitted to any
other agency for seeking support (In case proposal has been submitted to any other agency or under
consideration all details and a copy of the proposal must be submitted along with the present proposal).
D. I confirm that I will not submit the same proposal or a part thereof to any other funding agency, without
prior knowledge of the Ministry of New and Renewable Energy.
E. I confirm that the share of project proponent/beneficiaries shall not be lower than 20% in any
circumstances. Projects owned by the Programme Administrators are exempt from this condition.
F. I confirm that the proposed solar PV system has not been installed/ supplied at the proposed sites or to
the proposed beneficiaries, prior to the receipt of project sanction letter from the Ministry.
G. There is no duplication in the proposal and the submitted proposal is the only proposal by the proponent
and to the best of our knowledge no other organization has submitted any proposal for the system at this
site to MNRE for financial support.
H. A detailed site survey has been done/or will be undertaken to identify the beneficiaries before actual
supply and installation takes place.
I. This is to certify that the various components of the SPV power plant will conform to the Relevant
Standards, as mentioned in the Guidelines for Off-grid and Decentralized Solar Applications (Annexure-3) for
SPV modules and components under JNNSM. Copies of the Relevant IEC/ BIS Certificates should be enclosed.
J. It is mandatory to provide technical performance specifications of each component of the power plant
proposed to be installed under the project. And for which the performance will be warranted.
K. All technical parameters and warranty requirements must meet or exceed the requirements mentioned in
the guidelines issued by the Ministry.
I confirm that in case of any dispute, the decision of Secretary, Ministry of New and Renewable Energy,
Government of India will be final and binding on all.

Place:
Date:

Signature _____________
Name & Designation
of Authorized Signatory
Seal

127

11. Annexure V - Pilot Project V

Project Proposal
for
Stand Alone Solar PV Systems
for
Kalyan Dombivli Municipal Corporation
under
Development of Solar City Programme of MNRE
1. Title of the Project: Solar PV standalone system for Kalyan Dombivli Municipal Corporation
2. Name of the Project Proponent: Kalyan Dombivli Municipal Corporation.
3. Socio- Economic Justification of the Project:
Solar PV power plant generates clean electricity using sunlight thereby off set green house gases
produced by fossil fuel based power generating system. The countrys majority generation capacity is
largely coal based and produces high quantity of carbon dioxide and other harmful gases. If the
untapped solar energy potential is realized carbon dioxide and other toxic gas emissions can be lowered
by significant quantity and thereby saving our environment. Therefore, every kilowatt of solar energy
produced has to be seen from this angle as a small but major step towards mitigation of carbon dioxide
emission and subsequently combat climate change. A cumulative capacity of 105kWp PV power plant
will generate about 157500 kWh of clean electrical energy per year and will reduce 126 tons of GHG per
year. Use of solar streetlights and outdoor lights in the municipal parks will ensure illumination of these
areas during load shedding hours. Reliable traffic lights, blinkers and road studs will increase road
safety. Water pumps in the municipal parks will help in maintaining the parks green. Municipal parks
can avoid use of Diesel Generator sets as standby power supply system during load shedding hours
thereby reduces pollution and generation cost of electricity from DG sets. Use of Solar PV power plant
also reduces peak load, air-conditioner load in particular.
4. Benefits of the proposed project:
The proposed standalone PV systems in the KDMC area will maintain a minimum illumination level in the
roads and parks of the municipal area during load shedding and will save 157500kWh per year which will
save an amount of 7.89 lakh from electricity bill per year. The systems will reduce peak load and will
supply power during load shedding hours thereby replace the use of diesel generator sets for standby
power supply.
PV systems are becoming increasingly popular in India however; experience in O&M of such system in is
very low. The first hand experience PV system O&M train engineers and technical staff in Kalyan
Dombivli Municipal Corporation, which will help in developing similar projects in future.

128

PART-A: Details of the Project Proponent


i

ii

Name and Category of Project Proponent


f) Renewable Energy Service Providing Company
(RESCO)
g) Financial Institutions (Banks, NBFCs, MFIs)
h) Financial Integrator
i) System Integrator
j) Program Administrator

Name of the Project Proponent:


Kalyan Dombivli Municipal
Corporation, Kalyan Dombivli,
Maharashtra.

Name, Designation and Address of the Authorized


Representative for Correspondence with telephone no., fax &
email

Name: The Commissioner


Address: Kalyan Dombivli
Municipal Corporation
KDMC, Shankarrao Chowk,
Kalyan West - 421301

iii In case of Channel Partner other than Programme


Administrator, the following information will be provided:
f) Whether commercial or non-commercial.
g) Copy of Articles of Association, Registration No. & Date;
PAN/TAN No.
h) Audited Balance Sheet for last three years
i) Annual Report of previous year
j) Whether MNRE has earlier sanctioned any SPV projects
for implementation to the Project Proponent, if yes,
please furnish information.
iv In case of 1 (e), please indicate:
c) Government Department, Autonomous Institution set up
by Central/ State Government, State Renewable Energy
Development Agency, Public Sector Undertaking
d) Others

Category: Program Administrator.

NA

Autonomous Institution set by


State Government (Urban Local
Body)

PART-B: Details of the Project


1. Summary of the Proposal:

Kalyan Dombivli is an important satellite township of Mumbai city. It is an important railway


junction. The city of Kalyan Dombivli forms one of the important urban agglomerations of
Maharashtra state. Owing to large urbanizable zone and its proximity to greater Mumbai, Kalyan
Dombivli is trying to enhance the quality of services, expand the infrastructure and accelerate its
economic growth. It has not only made its presence felt in terms of overall development and
commercialization but also in its many eco drives for a sustainable future. Kalyan Dombivli has been
approved by the Ministry of New and Renewable Energy to be developed as a solar city. Kalyan
Dombivli Municipal Corporation (KDMC) is the main organization which is responsible for urban
governance and civic management in the city of Kalyan Dombivli. The corporation has a
129

democratically elected leadership from the constituencies within the geographic jurisdiction of the
corporation boundaries. Kalyan Dombivli Municipal Corporation is a very active organization for
initiating good practices and it has also come with the added supportive policy framework from
Maharasthra Government for the implementation of renewable energy initiatives.
It is proposed to install 1000 solar streetlights, 10 solar traffic lights, 50 solar blinkers, 2000 road
studs, 200 outdoor lights for parks and 8 solar pumps in Kalyan Dombivli Municipal Corporation as
model Renewable Energy systems.
2. Details of Project site:

The Kalyan Dombivli city is located at geographical coordinates of 27.18 N and 78.02 E. Average
load shedding in the city reported be 4 hours per day. The streetlights, traffic lights, solar blinkers
and road studs will be distributed in prime areas of the city. Outdoor lights and solar pumps will be
installed in all the municipal parks.
3. Details of Project Beneficiaries:

Kalyan Dombivli Municipal Corporation (KDMC) will be the direct beneficiary of the project. KDMC
is responsible for providing the basic services infrastructure to city dwellers. The services include
water supply, sewage treatment and disposal, solid waste management, disaster management,
buildings and roads, street lighting, maintenance of parks and open spaces, cemeteries and
crematoriums, conservation of heritage sites, and registering of births and deaths.
4. Details of Proposed Systems:

I.

Proposed capacity of the SPV Systems:


Solar System Proposed No. Proposed system Capacity/unit (Wp) Total capacity (kWp)
Solar Street Light
1000
74
74.00
Solar PV Traffic Lights
10
74
0.74
Solar Blinkers (37Wp)
50
37
1.85
Road Stud
2000
3
6.00
Outdoor lights for Parks
200
74
14.80
Solar Pumps for Parks
8
1000
8.00
105.39

II.
III.

Availability of shadow free roof area for the power plant: Available
Details of loads to be energized by Power Plant, calculations and justification for the
proposed capacity and expected annual energy generation

Details of the loads to be energized by Power Plant:- As stated above


IV.
V.
VI.
VII.
VIII.

Output Voltage of the Power Plant: 12V


Storage battery capacity: 3 days autonomy for all systems except solar pumps
Building for housing the battery bank and plant control systems: Not required
Distribution Network (if any): Not required (Standalone)
Expected reduction in diesel consumption, if any: NA
130

System Components
PV Module

Charge Controller/
Inverter
Power Conditioning
Unit
Storage Battery Bank
Performance Data
Acquisition System
Other components

Make and
Model
Make: MNRE
approved supplier
Mono/ Multi
crystalline
MNRE approved
supplier
MNRE approved
supplier
MNRE approved
supplier
BIS or equivalent
MNRE approved

Capacity

Numbers

100Wp/
74Wp/ 37Wp/
3Wp at STC

3340 nos.

Indigenous/
Imported
Indigenous

As required

As required

Indigenous

Not required

Not required

Indigenous

As required

As required

Indigenous

NA

NA

Indigenous

MPPT required As required


for solar
pumps

Indigenous

PART C: Implementation Schedule


o

Major Monitorable Milestones

Sl.
No.
1
2
3

Activities

Progress Months
3
4

Application/ clearance from MNRE


Procurement Process
Installation and commissioning

Project Commissioning Timeline


Project can be completed within 6 months from the date of finalization of vendor.

PART D: Performance Monitoring Mechanism:


Performance Data Monitoring
(Daily, Monthly and Annual energy
generation , logging, compilation and sharing with
MNRE)
Monthly monitoring of reduction in diesel
consumption, if any
Own Mechanism
Third Party
Remote Monitoring (for SPV power plants
having capacity above 5 kWp)

Performance will be monitored through regular


inspection.

NA
NA
5 years AMC will be signed with the supplier
NA

131

PART E: Project Cost and Financing Details.


Rs. 252.00
Rs.5.00
Rs. 20.00
Rs.20.00
Rs. 20.00
Rs. 3.00
Rs. 320.00

i.
Cost of Systems Hardware
ii.
Cost of transportation, insurance
iii.
Cost of civil works and electrical works
iv.
Cost of installation and Commissioning
v.
Cost of Annual Maintenance for 5 years
vi.
Any other related costs
Total Cost of Systems
Total kWp SPV Capacity
Means of Finance
a) Contribution of Project Proponent
b) Contribution of Beneficiaries organization
c) Envisaged CFA from MNRE
d) Other Source (s) of Funding (capital grant)
e) Envisaged Soft Loan assistance, if any
f) Whether funds are in surplus or deficiency
Details of Project Revenue recurring, if any
Project Duration

105kWp
a) KDMC : Rs. 160.00 Lakh
b) MNRE: Rs. 160.00 Lakh

NA
6 Months

PART F: Operation and Maintenance Arrangements


The supplier will train engineers and technicians of KDMC for day to day operation, monitoring and
scheduled maintenance work such as cleaning, topping up of batteries etc.
- Detail of Operation and Maintenance Arrangements.
The system will be procured with minimum 5 years comprehensive annual maintenance contract service.
During this period engineers and technicians from KDMC will be trained for O&M of the system.
- Arrangement for Generation Data Collection (applicable for SPV Power Plants having more than 10 kWp
capacity). Details of monitoring equipment proposed to be installed and method of supplying data to MNRE/
designated agency.
As stated above
- Method of monitoring of reduction in diesel consumption, if any. NA
- Strategy for training of the O&M Personnel of the Beneficiary Organization.
As stated above

132

PART G: Declarations and Certificates


A. It is certified that I/we have read the guidelines issued by the Ministry vide 5/23/2009/P&C dated 16th
June, 2010 and the related provisions/terms and conditions for availing financial support from the Ministry
of New and Renewable Energy and I agree to abide by these guidelines and related terms and conditions.
B. I understand that failure to comply by these guidelines may result in denial of financial support by the
Ministry.
C. I confirm that the present proposal in full or part has not been submitted / has been submitted to any
other agency for seeking support (In case proposal has been submitted to any other agency or under
consideration all details and a copy of the proposal must be submitted along with the present proposal).
D. I confirm that I will not submit the same proposal or a part thereof to any other funding agency, without
prior knowledge of the Ministry of New and Renewable Energy.
E. I confirm that the share of project proponent/beneficiaries shall not be lower than 20% in any
circumstances. Projects owned by the Programme Administrators are exempt from this condition.
F. I confirm that the proposed solar PV system has not been installed/ supplied at the proposed sites or to
the proposed beneficiaries, prior to the receipt of project sanction letter from the Ministry.
G. There is no duplication in the proposal and the submitted proposal is the only proposal by the proponent
and to the best of our knowledge no other organization has submitted any proposal for the system at this
site to MNRE for financial support.
H. A detailed site survey has been done/or will be undertaken to identify the beneficiaries before actual
supply and installation takes place.
I. This is to certify that the various components of the SPV power plant will conform to the Relevant
Standards, as mentioned in the Guidelines for Off-grid and Decentralized Solar Applications (Annexure-3) for
SPV modules and components under JNNSM. Copies of the Relevant IEC/ BIS Certificates should be enclosed.
J. It is mandatory to provide technical performance specifications of each component of the power plant
proposed to be installed under the project. And for which the performance will be warranted.
K. All technical parameters and warranty requirements must meet or exceed the requirements mentioned in
the guidelines issued by the Ministry.
I confirm that in case of any dispute, the decision of Secretary, Ministry of New and Renewable Energy,
Government of India will be final and binding on all.

Place:
Date:

Signature _____________
Name & Designation
of Authorized Signatory
Seal

133

12. Annexure VI - References & Bibliography


1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.

29.
30.
31.
32.

India Power Scenario, Young India Inc


http://maps.grida.no/go/graphic/natural-resource-solar-power-potential, 11.08.09, map credit: Hugo
Althenius, UNEP/GRID Arendal
http://www.igreenspot.com/solar-powered-city-concept/, 12.08.09
Solar and Sustainable Cities: Renewable Energy Information on Markets, Policy, Investment and Future
Pathways, Eric Martinot, http://www.martinot.info/solarcities.htm, 10.08.09
India: Addressing Energy Security and Climate Change, Ministry of Environment and Forests, Ministry of
Power, Bureau of Energy Efficiency, Government of India
http://www.indiasolar.com/ren-india.htm, 12.08.09
Solar Radiation Handbook 2008, Solar Energy Centre, Ministry of New and Renewable Energy, Indian
Meteorological Institute
http://www.mnre.gov.in/
Source: MSEDCL
Source: State oil Coordinator (HPCL, BPCL, IOCL)
Source: State oil Coordinator (HPCL, BPCL, IOCL)
Source: State oil Coordinator (HPCL, BPCL, IOCL)
http://www.energymanagertraining.com/DesignatedConsumers/main.htm,
http://www.hindustanpetroleum.com/en/UI/AboutLPG.aspx
Source: MSEDCL, state oil Coordinator (HPCL, BPCL, IOCL)
Source: MSEDCL and State Oil Coordinator
Kalyan Dombivli CDP
Source: http://eosweb.larc.nasa.gov/ ; http://www.mnre.gov.in/
Source: http://eosweb.larc.nasa.gov/
Source: Biomass Resource Atlas of India (http://lab.cgpl.iisc.ernet.in/Atlas/Default.aspx)
Source: http://mnes.nic.in/shp-state/maharashtra.htm
(Source: Kalyan Dombivli Report)
http://www.mnre.gov.in/
Case-study booklet on Renewable Energy. 2009
Source:GEDA
Anil Dhussa: Presentation Biogas in India, MeKalyan Dombivli to Markets Partnership Meeting of Agr. SubCommittee April 22, 2004
CII. 2005. Development of small ESCOs to undertake biomass gasification projects for industrial applications.
Report prepared for MNES. Confederation of Indian Industries.
Basic Information Sourced from: Ministry of Urban Development and Poverty Alleviation 2000.
(Biomethanation of Vegetable Market Waste Untapped Carbon Trading Opportunities K. Sri Bala Kameswari,
B. Velmurugan, K. Thirumaran and R.A. Ramanujam. Department of Environmental Technology, Central
Leather Research Institute (CLRI), Adyar, Chennai, India Proceedings of the International Conference on
Sustainable Solid Waste Management,5 - 7 September 2007, Chennai, India. Pp.415-420)
(Energy Revolution, Green Peace International)
Renewable Energy: Economic and Environmental Issues, Pimental et al)
(A roadmap for renewable energy risks, Lloyd).
Source: Green Peace

134

CONTACT
Emani Kumar
Dwipen Boruah
ICLEI South Asia
Ground Floor, NSIC - STP Complex,
NSIC Bhawan, Okhla Industrial Estate
New Delhi - 110020
Phone: 011-41067220
Fax: 011-41067221
www.iclei.org/sa

135