You are on page 1of 473

VOLUME 2

SECTION 3.1

PAGE 1 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

SECTION 3.1

SCOPE OF
WORKS

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 2 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

1.

SCOPE OF WORKS ........................................................................................................ 6

2.

BRIEF SCOPE OF WORKS ............................................................................................. 7

3.

DETAILED SCOPE OF WORKS .................................................................................... 16


3.1

PACKAGE S-1.......................................................................................................... 18

3.1.1

220/132/11kV AL SHAHHANIYAH SUPER SUBSTATION ............................ 18

3.1.2

132/11kV AL SHAHHANIYAH SOUTH SUBSTATION ................................... 26

3.1.3

132/11kV LEBSAYYER SUBSTATION .......................................................... 30

3.1.4

220/66/11kV DOHA SUPER SUBSTATION (UPGRADE) .............................. 34

3.1.5

220/132/66/11kV AL WAAB SUPER SUBSTATION (UPGRADE) ................. 43

3.1.6

220/66/11kV ABU HAMOUR SUPER SUBSTATION (UPGRADE) ................ 50

3.1.7

400/220/132/66/11kV AL WAJBAH SUPER SUBSTATION (UPGRADE) ...... 55

3.2

PACKAGE S-2.......................................................................................................... 58

3.2.1

132/66/11kV UMM EBAIRIYA SUBSTATION ................................................. 58

3.2.2

66/11kV UMM AL AMAD-1 SUBSTATION ..................................................... 65

3.2.3

132/11kV UMM GARN SUBSTATION ............................................................ 69

3.2.4

66/11kV ABU THAILAH SUBSTATION (UPGRADE) ..................................... 76

3.3

PACKAGE S-3.......................................................................................................... 90

3.3.1

132/11kV AL JAHHANIYA 2 SUBSTATION ................................................... 90

3.3.2

132/11kV IZGHAWA NORTH SUBSTATION ................................................. 98

3.3.3

132/33/11kV MESAIEED INDUSTRIAL-A SUBSTATION ............................ 104

3.3.4

132/11kV WAKRAH 3 SUBSTATION ........................................................... 121

3.4

PACKAGE S-4........................................................................................................ 129

3.4.1

66/11kV NEW ASSIRI SUBSTATION (REPLACEMENT) ............................ 129

3.4.2

66/11kV SALWA ROAD SUBSTATION (REPLACEMENT) .......................... 134

3.4.3

66/11kV BIN MAHMOUD NORTH SUBSTATION ........................................ 140

3.4.4

66/11kV MUSHERIB SUBSTATION (REFURBISHMENT) ........................... 146

3.5

PACKAGE S5 ...................................................................................................... 151

3.5.1

66/11kV MURRAH SOUTH SUBSTATION .................................................. 151

3.5.2

66/11kV UMM AL SENEEM 2 SUBSTATION ............................................... 157

3.5.3

66/11kV AL WAAB SUBSTATION (UPGRADE) ........................................... 164

3.5.4

66/11kV AL WAAB 2 SUBSTATION ............................................................. 175

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 3 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.6

REV. 0

PACKAGE S6 ...................................................................................................... 181

3.6.1

132/66/11kV MAITHER CENTRAL SUBSTATION (UPGRADE) .................. 181

3.6.2

66/11kV MUSEUM ROAD SUBSTATION (UPGRADE) ............................... 187

3.6.3

132/11kV AIN SINAN SUBSTATION ............................................................ 196

3.6.4

132/11kV JERYAN JENAIHAT 1 SUBSTATION .......................................... 202

3.7

PACKAGE S7 ...................................................................................................... 210

3.7.1

66/11kV NEW DOHA E SUBSTATION (REPLACEMENT) .......................... 210

3.7.2

66/11kV SALATA SUBSTATION (REPLACEMENT) .................................... 218

3.8

PACKAGE S8 ...................................................................................................... 226

3.8.1

132/11kV MASHAF 1 SUBSTATION ............................................................ 226

3.8.2

132/11kV MASHAF 2 SUBSTATION ............................................................ 230

3.8.3

132/11kV MASHAF 3 SUBSTATION ............................................................ 234

3.8.4

132/11kV AL WUKAIR 10 SUBSTATION ..................................................... 239

3.9

PACKAGE S9 ...................................................................................................... 245

3.9.1

132/11kV AL WUKAIR 9 SUBSTATION ....................................................... 245

3.9.2

132/11kV AL WUKAIR 8 SUBSTATION ....................................................... 250

3.9.3

132/11kV AL WUKAIR 7 SUBSTATION ....................................................... 255

3.9.4

132/11kV AL WUKAIR 6 SUBSTATION ....................................................... 259

3.10

PACKAGE S10 ................................................................................................ 265

3.10.1

132/11kV AL WUKAIR 5 SUBSTATION ....................................................... 265

3.10.2

132/11kV AL WUKAIR 4 SUBSTATION ....................................................... 269

3.10.3

132/11kV AL WUKAIR 3 SUBSTATION ....................................................... 274

3.10.4

132/11kV AL WUKAIR 2 SUBSTATION ....................................................... 278

3.11

PACKAGE S11 ................................................................................................ 284

3.11.1

66/11kV ABU HAMOUR WEST S/S ............................................................. 284

3.11.2

66/11kV RAWDAT AL KHAIL 2 S/S.............................................................. 289

3.11.3

66/11kV LUAIB S/S ...................................................................................... 293

3.11.4

33/11kV ABU SAMRA SUBSTATION (UPGRADE)...................................... 298

3.12

PACKAGE S-12 .................................................................................................. 304

3.12.1

220/132/11kV FRAMEWORK SUBSTATION ............................................... 304

3.12.2

220/66/11kV FRAMEWORK SUBSTATION ................................................. 308

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 4 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.12.3
3.13

REV. 0

REMOTE END WORKS TYPICAL ............................................................ 313

PACKAGE S-13 .................................................................................................. 320

3.13.1

132/11kV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11kV SWG) 2


Nos ............................................................................................................... 320

3.13.2

132/11kV FRAMEWORK TYPE B SUBSTATION (Single 11kV SWG) 2 Nos .


...................................................................................................................... 323

3.13.3

132/11kV FRAMEWORK TYPE C SUBSTATION (Single 11kV SWG) ........ 326

3.13.4

REMOTE END WORKS TYPICAL ............................................................ 330

3.14

PACKAGE S-14 .................................................................................................. 336

3.14.1

132/11kV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11kV SWG) 2


Nos ............................................................................................................... 336

3.14.2

132/11kV FRAMEWORK TYPE B SUBSTATION (Single 11kV SWG) 2 Nos .


...................................................................................................................... 339

3.14.3

132/11kV FRAMEWORK TYPE C SUBSTATION (Single 11kV SWG) ........ 342

3.14.4

REMOTE END WORKS TYPICAL ............................................................ 346

3.15

PACKAGE S15 ................................................................................................ 351

3.15.1

66/11kV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11kV SWG) 2


Nos ............................................................................................................... 351

3.15.2

66/11kV FRAMEWORK TYPE B SUBSTATION (SINGLE 11kV SWG) 2 Nos


...................................................................................................................... 355

3.15.3

66/11kV FRAMEWORK TYPE C SUBSTATION (SINGLE 11kV SWG) ....... 358

3.15.4

REMOTE END WORKS TYPICAL ............................................................ 361

3.16

PACKAGE S16 ................................................................................................ 367

3.16.1

66/11kV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11kV SWG) 2


Nos ............................................................................................................... 367

3.16.2

66/11kV FRAMEWORK TYPE B SUBSTATION (SINGLE 11kV SWG) 2 Nos


...................................................................................................................... 370

3.16.3

66/11kV FRAMEWORK TYPE C SUBSTATION (SINGLE 11kV SWG) ....... 374

3.16.4

REMOTE END WORKS TYPICAL ............................................................ 377

3.17

PACKAGE S17 ................................................................................................ 382

3.17.1

66/11kV FRAMEWORK TYPE A SUBSTATION (CONVENTIONAL, DOUBLE


11kV SWG CIVIL WORKS DONE BY DEVELOPER) ............................... 382

3.17.2

66/11kV FRAMEWORK TYPE B SUBSTATION (CONVENTIONAL, SINGLE


11kV SWG - CIVIL WORKS DONE BY DEVELOPER) ................................ 386

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 5 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

3.17.3

66/11kV FRAMEWORK UNDERGROUND TYPE A SUBSTATION (DOUBLE


11kV SWG CIVIL WORKS DONE BY DEVELOPER) ............................... 390

3.17.4

66/11kV FRAMEWORK UNDERGROUND TYPE B SUBSTATION (SINGLE


11kV SWG - CIVIL WORKS DONE BY DEVELOPER) ................................ 394

3.17.5

66/11kV FRAMEWORK UNDERGROUND TYPE A SUBSTATION (DOUBLE


11kV SWG)................................................................................................... 398

3.17.6

66/11kV FRAMEWORK UNDERGROUND TYPE B SUBSTATION (SINGLE


11kV SWG)................................................................................................... 401

3.17.7

REMOTE END WORKS TYPICAL ............................................................ 405

3.18

PACKAGE S-18 TELECOMMUNICATION SYSTEM .......................................... 410

3.18.1

INTRODUCTION .......................................................................................... 410

3.18.2

SCOPE OF WORKS FOR SUBSTATIONS PACKAGE................................ 411

3.18.3

SCOPE OF WORKS FOR FRAMEWORK CABLES / SUBSTATIONS ........ 427

3.18.4

OPTIONAL SCOPE OF WORK .................................................................... 434

3.19

PACKAGE S19 ................................................................................................ 434

3.19.1

INSTALLATION OF CAPACITOR BANKS ................................................... 434

4.

NOTES TO BIDDERS .................................................................................................. 443

5.

NOTES APPLICABLE FOR FRAMEWORK PACKAGES ............................................ 451

6.

IMPORTANT NOTES APPLICABLE FOR ALL PACKAGES........................................ 454

7.

EXTENT OF SUBSTATION CONTRACT ..................................................................... 455

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 6 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

1. SCOPE OF WORKS
Description of works
Kahramaa intends to expand the existing Power transmission network under the project entitled
Qatar Power Transmission System Expansion Phase 13 - Substations to meet with the
increased Power demand due to the developmental works in the State of Qatar. Details of the
complete project are summarized in the Section 2 below.
The following tenders are issued at the same time, and the contractor should be also aware of the
influence of the works covered by the other Tenders:
GTC 735/2015 Substations (This tender);
GTC 736/2015 Cables
The works of the Project are spread all over the State of Qatar including both newly and already
developed areas. The details which are available at the time of preparation of this Tender
Documents are shown on the Location maps enclosed. The exact coordinates and ground
elevation shall be coordinated with the concerned Authorities during the project execution stage.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 7 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

2. BRIEF SCOPE OF WORKS


PACKAGE S-1 (Works on 220kV and associated S/Ss)
220/132/11kV Al Shahhaniyah Super: New Transmission Substation incorporating 220kV GIS,
132kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 220/132kV, 315MVA and 2 x
132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, 2 x 220kV, 60MVAR
Shunt Reactors and other associated equipment and works as required and indicated elsewhere in
the Tender document.
132/11kV Al Shahhaniyah South: New Transmission Substation incorporating 132kV GIS, 11kV
metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
132/11kV Lebsayyer: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
220/66/11kV Doha Super (Upgrade): Existing 220/66/11kV Transformer Feeder Substation (built
under Phase 8 Project) shall be expanded by addition of new 220kV GIS, 1 x 220/66kV, 200MVA
Power Transformer and other associated equipment and works as required and indicated
elsewhere in the Tender document.
220/132/66/11kV Al Waab Super (Upgrade): Existing 220/132/66/11kV Transformer Feeder
Substation (built under Phase 7 Project) shall be expanded by addition of new 220kV GIS, 1 x
220/132kV, 315MVA Power Transformer and other associated equipment and works as required
and indicated elsewhere in the Tender document.
220/66/11kV Abu Hamour Super (Upgrade): Existing 220/66/11kV GIS substation (built under
Phase 10 Project by Hyosung) shall be extended by adding new 1 x 220/66kV, 200MVA Power
Transformer and other associated equipment and works as required and indicated elsewhere in
the Tender document.
400/220/132/66/11kV Al Wajbah Super (Upgrade): Existing 400/220/132/66/11kV GIS substation
(built under Phase 7 Project) shall be expanded by addition of new 2 x 220kV GIS bays and other
associated equipment and works as required and indicated elsewhere in the Tender document.
PACKAGE S-2 (WORKS RELATED to AL SHAKHAMA AREA)
132/66/11kV Umm Ebairiya: New Transmission Substation incorporating 132kV GIS, 66kV GIS,
11kV metal enclosed switchgear (GIS/AIS), 2 x 132/66kV, 160MVA and 2 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers and other associated equipment and
works as required and indicated elsewhere in the Tender document.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 8 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66/11kV Umm Al Amad - 1: New Transmission Substation incorporating 66kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Umm Garn: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 2 x 132kV, 15MVAr
Shunt Reactors, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
66/11kV Abu Thailah (Upgrade): Existing 66/11kV substation (built under Phase 7 Project) shall
be expanded by addition of new 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA
Power Transformers and other associated equipment and works as required and indicated
elsewhere in the Tender document.
PACKAGE S-3 (NEW 132KV S/S)
132/11kV Al Jahhaniya 2: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Izghawa North: New Transmission Substation incorporating 132kV GIS, 2 x 11kV metal
enclosed switchgears (GIS/AIS), 4 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Mesaieed Industrial-A: Existing 132/33/11kV substation shall be completely
refurbished with the new equipment incorporating 132kV GIS, 33kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/33kV, 100MVA and 2 x 132/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document.
132/11kV Wakrah 3: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-4 (REFURBISHMENT/REPLACEMENT OF THE EXISTING S/S and NEW 66KV
S/S)
66/11kV New Assiri (Replacement): Existing 66/11kV substation shall be completely replaced
with the New Transmission Substation incorporating 66kV GIS, 11kV metal enclosed switchgear
(GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other
associated equipment and works as required and indicated elsewhere in the Tender document.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 9 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66/11kV Salwa Road (Replacement): Existing 66/11kV substation shall be completely replaced
with the New Transmission Substation incorporating 66kV GIS, 11kV metal enclosed switchgear
(GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other
associated equipment and works as required and indicated elsewhere in the Tender document.
66/11kV Bin Mahmoud North: New 66/11kV Transmission Substation incorporating 66kV GIS,
11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Musherib (Refurbishment): Existing 66/11kV substation shall be completely refurbished
with the new equipment incorporating 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV,
40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and
works as required and indicated elsewhere in the Tender document.
PACKAGE S-5 (UPGRADE OF THE EXISTING S/S and NEW 66kV S/S)
66/11kV Murrah South: New 66/11kV Transmission Substation incorporating 66kV GIS, 2 x 11kV
metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Umm Al Seneem 2 New 66/11kV Transmission Substation incorporating 66kV GIS, 11kV
metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Al Waab (Upgrade): Existing 66/11kV transformer feeder substation (built under Phase 6
Project by M/s Siemens) shall be expanded by addition of new 66kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers and other associated equipment and works as required and indicated elsewhere in
the Tender document.
66/11kV Al Waab 2: New 66/11kV Transmission Substation incorporating 66kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-6 (UPGRADE OF THE EXISTING S/S and NEW 132kV S/S)
132/66/11kV Maither Central (Upgrade): Existing 132/66/11kV transformer feeder substation
(built under Phase 5 Project) shall be expanded by extension of the existing 66kV GIS, addition of
new 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers and other associated equipment and works as required and
indicated elsewhere in the Tender document.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 10 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66/11kV Museum Road (Upgrade): Existing 66/11kV substation (built under Phase 6 Project by
M/s ABB) shall be expanded by extension of the existing 66kV GIS, addition of new 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers and other associated equipment and works as required and indicated elsewhere in
the Tender document.
132/11kV Ain Sinan: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Jeryan Jenaihat-1: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-7 (REPLACEMENT OF THE EXISTING 66KV S/S)
66/11kV New Doha E (Replacement): Existing 66/11kV substation shall be completely replaced
with the New Transmission Substation incorporating 66kV GIS, 2 x 11kV metal enclosed
switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
66/11kV Salata (Replacement): Existing 66/11kV substation shall be completely replaced with the
New Transmission Substation incorporating 66kV GIS, 11kV metal enclosed switchgear (GIS/AIS),
2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Transformers, other associated
equipment and works as required and indicated elsewhere in the Tender document.
PACKAGE S-8 (NEW 132KV S/S at Wukair/Mashaf area)
132/11kV Mashaf 1: New Transmission Substation incorporating 132kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Mashaf 2: New Transmission Substation incorporating 132kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Mashaf 3: New Transmission Substation incorporating 132kV GIS, 11kV metal enclosed
switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 11 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

132/11kV Al Wukair 10: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-9 (NEW 132KV S/S at Wukair area)
132/11kV Al Wukair 9: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 8: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 7: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 6: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
PACKAGE S-10 (NEW 132KV S/S at Wukair area)
132/11kV Al Wukair 5: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 4: New Transmission Substation incorporating 132kV GIS, 2 x 11kV metal
enclosed switchgear (GIS/AIS), 4 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 3: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
132/11kV Al Wukair 2: New Transmission Substation incorporating 132kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 12 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-11 (NEW 66KV S/S)


66/11kV Abu Hamour West: New 66/11kV Transmission Substation incorporating 66kV GIS,
11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV
Auxiliary Transformers, other associated equipment and works as required and indicated
elsewhere in the Tender document.
66/11kV Rawdat al Khail 2: New 66/11kV transformer feeder Substation incorporating 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
66/11kV Luaib: New 66/11kV Transmission Substation incorporating 66kV GIS, 11kV metal
enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary
Transformers, other associated equipment and works as required and indicated elsewhere in the
Tender document.
33/11kV Abu Samra (Upgrade): Existing 33/11kV transformer feeder substation (built under
earlier Kahramaa Projects) shall be expanded by addition of new 33kV GIS, 11/0.415kV auxiliary
transformers and other associated equipment and works as required and indicated elsewhere in
the Tender document.
PACKAGE S-12 (NEW 220KV FRAMEWORK S/S)
220/132/11kV Framework Substation: New Transmission Substation incorporating 220kV GIS,
132kV GIS, 11kV metal enclosed switchgears (GIS/AIS), 3 x 220/132kV, 315MVA and 2 x
132/11kV, 40MVA Power Transformers, 11/0.415kV Auxiliary Service Transformers, other
associated equipment and works as required and indicated elsewhere in the Tender document.
220/66/11kV Framework Substation: New Transmission Substation incorporating 220kV GIS, 66kV
GIS, 11kV metal enclosed switchgears (GIS/AIS), 2 x 220/66kV, 200MVA and 2 x 66/11kV,
40MVA Power Transformers, 11/0.415kV Auxiliary Service Transformers, other associated
equipment and works as required and indicated elsewhere in the Tender document.
PACKAGE S-13 (NEW 132KV FRAMEWORK S/S)
Two Nos. of 132/11kV Framework Substation Type A: New Transmission Substation
incorporating 132kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
Two Nos. of 132/11kV Framework Substation Type B: New Transmission Substation
incorporating 132kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 13 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

One No. of 132/11kV Framework Substation Type C: New Transmission Substation incorporating
132kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-14 (NEW 132KV FRAMEWORK S/S)
Two Nos. of 132/11kV Framework Substation Type A: New Transmission Substation
incorporating 132kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
Two Nos. of 132/11kV Framework Substation Type B: New Transmission Substation
incorporating 132kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
One No. of 132/11kV Framework Substation Type C: New Transmission Substation incorporating
132kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 132/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-15 (NEW 66KV FRAMEWORK S/S)
Two Nos. of 66/11kV Framework Substation Type A: New Transmission Substation incorporating
66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
Two Nos. of 66/11kV Framework Substation Type B: New Transmission Substation incorporating
66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document.
One No. of 66/11kV Framework Substation Type C: New Transmission Substation incorporating
66kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-16 (NEW 66KV FRAMEWORK S/S)
Two Nos. of 66/11kV Framework Substation Type A: New Transmission Substation incorporating
66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 14 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two Nos. of 66/11kV Framework Substation Type B: New Transmission Substation incorporating
66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document.
One No. of 66/11kV Framework Substation Type C: New Transmission Substation incorporating
66kV GIS with Single busbar, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
PACKAGE S-17 (NEW 66KV FRAMEWORK S/S without civil works or underground)
One No. of 66/11kV Framework Substation: New Transmission Substation incorporating 66kV
GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Framework Substation: New Transmission Substation incorporating 66kV
GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power Transformers,
11/0.415kV Auxiliary Transformers, other associated equipment and works as required and
indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document. Civil works shall be done by others.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 2 x 11kV metal enclosed switchgear (GIS/AIS), 4 x 66/11kV, 40MVA
Power Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works
as required and indicated elsewhere in the Tender document.
One No. of 66/11kV Underground Framework Substation: New Transmission Substation
incorporating 66kV GIS, 11kV metal enclosed switchgear (GIS/AIS), 2 x 66/11kV, 40MVA Power
Transformers, 11/0.415kV Auxiliary Transformers, other associated equipment and works as
required and indicated elsewhere in the Tender document.
PACKAGE S-18 TELECOMMUNICATION
Telecommunication System: New telecommunication equipment shall be provided for
connection of new and refurbished substations to Kahramaa Telecommunication System including
all works necessary to connect these substations to NCC/ENCC/DCC and to keep existing
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 15 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

connections of existing substations being modified, replaced or upgraded under the scope of this
Tender - as per Detailed Technical Specification in Volume 3.
PACKAGE S-19 INSTALLATION OF CAPACITOR BANKS
New Capacitor banks installation at the existing 11kV switchgear of several primary substations.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 16 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

3. DETAILED SCOPE OF WORKS


BIDDER shall note that:
Remote end modifications: The Scope of Works identifies remote end substations and type of
circuit, e.g. OHL/ cable, involved as connecting link between the two substations. If the remote end
substations are existing substations, the scope of substation Contractor includes all modifications
in Protection, Station Control System, etc., related to the Contractors main Scope of Works, precommissioning checks, end to end tests and all commissioning activities as appropriate at the
remote end stations as well.
EHV and HV Cables: It is general approach that all EHV and HV cables for connections within
substations and between SWG and OHL terminal gantry / cable compound are in the substation
Contractor Scope of Works. The scope of substation Contractor also includes required coordination with the Contractor(s) of other end substation(s), underground Power cable Contractors
and OHL Contractors, for pre-commissioning checks, end to end tests and all commissioning
activities as appropriate. Each Contractor shall be responsible for the works (including his share of
interface points) as per the Scope of the Works. In the case of dispute, if any, Kahramaas decision
in this regard shall be final and binding to all concerned parties.
The following is under the Scope of work for substation Contractor when it is required to dismantle
oil filled cable to install new XLPE cable:
Excavation, backfilling and all other related civil work
Removing oil tank
Disconnect Gauge/manometer panels and control/alarm cables
Cut and cap existing oil filled cables after draining the oil from cables.
Remove the existing terminations
Delivery of dismantled material to Kahramaa store
Dismantling works: Where substation Contractor Scope of the Works includes replacement of
existing substation, dismantling works of the existing facilities, generally, are not included in the
Scope of substation Contractor unless specified otherwise. However, site clearance of the area
dedicated / required for the substation Contractor Scope, including existing structures, if any, is
obligation of substation Contractor.
Future development: In the detailed scope of works below, planned future development for each
substation is clearly specified. Bidder should note all requirements for spare bays, space for future
bays, future Transformers, capacitor banks, etc. Those should be considered during the tendering
and later in design stage in order to allocate sufficient space, to properly plan and size cable
corridors / ducts, common services such as uninterrupted Power supply, HVAC and other related
facilities.
Pricing for civil works: Volume 7 of this Tender document includes site plot layout drawings and
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 17 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

general arrangement drawings for the substation buildings. Commercial offer shall be based on the
subject drawings, considering specified minimum clearances and operation distance requirements
specified in Section 6.3 of this document and related specification, considering actual Scope of
Works and offered equipment. Bidder is obliged to ensure that buildings are properly sized and to
provide relevant layout drawings within the Technical offer. Accordingly, no price variations will be
allowed for change of the building size in the later stage of Contract. Part of civil works such as
perimeter wall/fence, access road and filling works will be measured and paid as per actual
quantities.
Remote end modifications: Specifications enclosed with the Contract shall be applicable for all
modification works at remote end substations constructed under all earlier Kahramaa projects and
which will be connected to substations, subject of this Contract. Therefore protection relays (Main
relays, Trip relays and TCS relays) need to be changed if required under new scheme. Also
replacement of CTs is anticipated, and for this work separate unit price shall be provided. However
for detailed scope please refer under remote end modification works for the concerned remote end
substations.
It shall be noted that many of the substations considered as Remote End Substations are
currently under construction and all the equipment/systems will be under warranty for a period of 2
years from its date of Taking Over. Hence, in case the equipment/system is still under warranty
during modification under the scope of this project, the Contractor shall execute the works in such
a way as not to dilute or nullify existing warranties in any way, whatsoever. All details of work such
as, method statements, interface requirements, intended subcontractors, etc. shall be discussed
and agreed with Kahramaa well in advance of the scheduled commencement date of such works
and full clarity shall be established. The same is applicable for modification on the cable lines
which are part of this Contract.
Connection to NCC/ENCC/DCC: All modification works at Kahramaa control centers
NCC/ENCC/DCC to include new and modified / upgraded / refurbished existing substations will be
covered under a separate Contract. The scope of substation Contractor under this project includes
all interfacing works with the above Contractor, necessary to include new substations and
modifications to existing substations into the NCC, ENCC and DCC, including interoperability and
end-to-end testing. This includes co-ordination works with above Contractor during all stages until
commissioning and end to end test.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 18 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-1

3.1

3.1.1

220/132/11KV AL SHAHHANIYAH SUPER SUBSTATION


220/132/11kV Al Shahhaniyah Super substation is intended to cater Power supply to the
new growing demands in Al Shahhaniyah and the surrounding areas. Al Shahhaniyah
Super S/S will be connected to network by 220kV double cable circuits from Umm Al
Amad Super substation. The cables will be installed under separate Contract
(GTC/736/2015, Package C2).
The principal elements of new 220/132/11kV Al Shahhaniyah Super substation shall be
as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 220/132kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Two (2) Nos. Shunt Reactor bays suitable for cable connection as per the
approved connection arrangement;
- Six (6) Nos. cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. incoming Transformer bays for 220/132kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Eight (8) Nos. Cable feeder bays (four (4) Nos. spare);
- Two (2) Nos. 132kV, 315MVA bus duct between 220/132kV Power
Transformers and 132kV GIS;
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 19 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- One (1) No. Bus section bay rated 2500A;


- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers (Auto) 220/132kV, 189/236/315MVA,


YNa0(d1) ONAN/ONAF/OFAF cooling, 10% on load taps in steps of 1.25%,
13.6% impedance on ONAN (189 MVA), provided with AVR, terminal CTs, neutral
CTs etc.

Two (2) Nos. 220kV, 60MVAr Shunt Reactors with terminal CTs, neutral CTs etc.

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 2000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to UAAS substation. The new relays to be installed at 220/132/11kV Al
Shahhaniyah Super substation shall match the protection at UAAS substation end.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 20 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- Partial discharge online monitoring system for 220kV GIS;
- Online condition monitoring system for new 220/132kV, 315MVA Transformers;
- Online condition monitoring system for new 220kV, 60MVAr Shunt Reactors;
- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 21 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
 LV Power Cables, Control Cables with all accessories
 Earthing & Lightning Protection
 Small Power & Lighting
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 220/132/11kV substation including building services.
Note: The architectural appearance of the Substation buildings and boundary wall shall
aesthetically match with the structures in the surrounding area and is subject to approval
of concerned authorities. All design approvals in this regard shall be coordinated with the
concerned authorities.
 220kV and 132kV GIS and Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers

Fire Pumping Station & Fire Water Tanks.

Fire hydrant and ring main piping (all around the substation buildings perimeter).

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers & Shunt Reactors. All Transformers & Shunt Reactors shall be
manufactured with the necessary provision of connection points for installation of
TEP System (if Kahramaa decides to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 22 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

220kV, 1x1600mm2, XLPE, 315MVA, double circuit, single point earthed with
earth continuity conductor cable links between 220kV GIS and 220/132kV
Transformers, laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.

220kV, 1x500mm2, XLPE, 60MVA, double circuit, solid bonded cable links
between 220kV GIS and 220kV Shunt Reactors, laid in unfilled concrete troughs
with all accessories. Approx. route length: 100m.

132kV, 1x2000mm2, XLPE, 315MVA, double circuit, single point earthed with
earth continuity conductor cable links between 132kV GIS and 220/132kV Power
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m. (alternative to 132kV GI bus duct in case of layout difficulty)

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 2000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 23 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
 REMOTE END WORKS AT UAAS S/S
400/220/66/11kV Umm Al Amad Super is an existing substation with 400kV GIS, 220kV
GIS, 66kV GIS and 11kV Switchgear built by Alstom under Phase 8 Project. UAAS will be
connected to Al Shahhaniyah Super by the new 220kV Double Circuit cable connection.
All required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project. Modification
works at UAAS shall be arranged in a way not to affect the Warranty Period, if still valid at
the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Alstom under Phase 8 project to


include changes to 2x220kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x220kV existing bays to be connected to Al Shahhaniyah Super substation are with
Protection Relays/Equipments under GTC/144A/2006 Phase-8 project.

The relay provided at UAAS for Main-1 protection is Alstom make P545 and for
Main-2 Protection is Siemens make 7SD5. The new Relays/Equipment to be
installed at Al Shahhaniyah Super substation should match the protection at 220kV
UAAS Substation end (supplied under Phase-8 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 24 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT AL THUMAMAH SUPER S/S


220/132/11kV Al Thumamah Super is a new substation with 220kV GIS, 132kV GIS and
11kV Switchgear, being constructed by Siemens under Phase 11 Project. This substation
will be under warranty period.
Al Thumamah Super S/S shall be connected to Old Airport S/S by new 1x132kV cable
circuit. The cables will be installed under separate Contract (GTC/736/2015, Package C3).
All necessary modifications, End to End test, testing and commissioning and putting into
service of the new circuit shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and re-commissioning of two number of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control

Required Modifications to SCS supplied by Siemens under Phase 11 project to


include changes to 1x132kV cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Protection

1x132kV existing bay to be connected to Old Airport substations is supplied with


protection relays/equipment under GTC/488C/2012 Phase-11 project.

The relays provided at Al Thumamah Super for Main-1 protection is Siemens make
7SD5 and for Main-2 protection is Alstom make P545. The new relays/equipment
to be installed at Old Airport substation should match the protection at 132kV Al
Thumamah Super substation end (supplied under Phase-11 project).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 25 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Retesting of the relays/equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT OLD AIRPORT S/S


132/11kV Old Airport is an existing substation with 132kV GIS and 11kV Switchgear,
being refurbished by L&T under Phase 11 Project. This substation will be under warranty
period.
Al Thumamah Super S/S shall be connected to Old Airport S/S by new 1x132kV cable
circuit. The cables will be installed under separate Contract (GTC/736/2015, Package C3).
All necessary modifications, End to End test, testing and commissioning and putting into
service of the new circuit shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and re-commissioning of one number of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control

Required Modifications to SCS of ABB make supplied by L&T under Phase 11


project to include changes to 1x132kV cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Protection

1x132kV existing bay to be connected to Al Thumamah Super substation is


supplied with protection relays/equipment under GTC/488C/2012 Phase-11
project.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 26 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.1.2

REV. 0

The relays provided at Al Old Airport for Main-1 protection is ABB make RED670
and for Main-2 protection is Siemens make 7SD522. Relays shall match protection
at Al Thumamah Super.

Retesting of the relays/equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

132/11KV AL SHAHHANIYAH SOUTH SUBSTATION


132/11kV Al Shahhaniyah South substation is intended to cater Power supply to the new
growing demands in Al Shahhaniyah area. Al Shahhaniyah South S/S will be connected to
network by 132kV double cable circuits from Al Shahhaniyah Super substation under the
separate Contract (GTC/736/2015, Package C3).
The principal elements of new 132/11kV Al Shahhaniyah South substation shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bas bar
GIS consisting of following bays:
- Two (2) Bus section bays;
- Two (2) Bus coupler bays;
- Two (2) 40MVA outgoing Transformer feeder bays for 132/11kV Transformers;
- Six (6) cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on either side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 27 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bays for future capacitor banks feeders;


- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on either side of the switchgear;
Alternatively 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided for
11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear Substation (A
& B) there shall be two load shedding panels.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 28 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Earthing & Lightning Protection
 Small Power & Lighting
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services.
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 29 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 Power cables

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Remote End S/S Works: Al Shahhaniya Super S/S


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 30 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The remote end substation, Al Shahhaniya Super, is also to be built under the same
package and will be connected to the new Shahhaniya South S/S with 2x132kV cable
circuits. The cables will be installed under separate contract (GTC/736/2015, Package
C3). The substation contractor shall coordinate with cable contractor and complete all
necessary works for putting these feeders into service.

3.1.3

132/11KV LEBSAYYER SUBSTATION


132/11kV Lebsayyer substation is intended to cater Power supply to the new growing
demands in surrounding area. Lebsayyer S/S will be connected to network by 2x132kV
cable circuits from Al Shahhaniyah Super substation. The cables will be installed under
separate Contract (GTC/736/2015, Package C3).
The principal elements of new 132/11kV Lebsayyer substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bas bar
GIS consisting of following bays:
- Two (2) Bus section bays;
- Two (2) Bus coupler bays;
- Two (2) 40MVA outgoing Transformer feeder bays for 132/11kV Transformers;
- Six (6) cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on either side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A;
- Two (2) Nos. Bays for future capacitor banks feeders;
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on either side of the switchgear;
Alternatively 11kV GIS is also acceptable.

 Power Transformers, NERs

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 31 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 32 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Earthing & Lightning Protection
 Small Power & Lighting
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services.
Note: The architectural appearance of the Substation buildings and boundary wall shall
aesthetically match with the structures in the surrounding area and is subject to approval
of concerned authorities. All design approvals in this regard shall be coordinated with the
concerned authorities.
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 33 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 Power cables

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Remote End S/S Works: at Al Shahaniya Super S/S


The remote end substation, Al Shahhaniya Super, is also to be built under the same
package and will be connected to the new Lebsayyer S/S with 2x132kV cable circuits. The
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 34 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

cables will be installed under separate contract (GTC/736/2015, Package C3). The
substation contractor shall coordinate with cable contractor and complete all necessary
works for putting these feeders into service.

3.1.4

220/66/11KV DOHA SUPER SUBSTATION (UPGRADE)


220/66/11kV Doha Super is the existing substation built by M/s Alstom under Phase 8
project (GTC 144A/2006). Existing transformer feeder substation shall be upgraded by
addition of 220kV GIS and one new 220/66kV, 200MVA transformer. Doha Super
substation shall remain connected to Airport Super S/S by diverting the existing 2x220kV
cables, currently connected at 220/66kV transformer to the new 220kV GIS. Installation of
the new equipment as well as diversion of the existing 2x220kV cables are in the scope of
this project.
In addition, Doha Super will be connected to Naeeja Super substation by 1x220kV,
515MVA circuit. The cables will installed under separate Contract (GTC/736/2015,
Package C2).
The principal elements for the upgrade of the 220/66/11kV Doha Super substation shall
be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. outgoing Transformer bays for 220/66kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Six (6) Nos. cable feeder bays (three (3) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Existing 66kV GIS:


- Addition of 1x 66kV, 2500A, 200MVA incoming Transformer Feeder Bay with
twin cable head for connecting two runs of 2000 sq.mm 66kV cables. All civil
works required for the new bays to be considered.
- Re-testing and Re-commissioning of 66kV Transformer LV B18 & B28 bays,
including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels,
inscription of additional Alarm facia as required, replacing of Switchgear Name
plates and any required works including, wiring, testing & complete recommissioning of the above switchgear bays.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 35 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power Transformers

An additional 220/66kV Power Transformer 120/150/200MVA, YNyn0(d1),


ONAN/ONAF/OFAF cooling, +10% -10% on load taps in steps of 1.25%,
impedance as the existing Transformers on ONAN provided with AVR, terminal
CTs, neutral CTs etc. Existing Transformers are having 20.76% impedance at
OFAF. Matching of Percentage impedance of new Transformer with the existing
Transformers shall be ensured by Contractor based on the site survey and Factory
acceptance test reports of the existing Transformers. Electrical parameters of the
new transformer shall be identical to the existing Transformers to meet the
conditions of parallel operation of all three units LV cable boxes of the new
transformer shall have suitable arrangement to enable termination of two runs (two
cables per phase) of 66kV, 2000 sq.mm cables from the new bay in the existing
66kV GIS.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with the existing
equipment and with remote ends (in line with remote end protection scope) shall be
provided for the new feeders. However, the following specific requirements shall be
considered:

For 2x220kV Cable Feeders to be connected to Airport Super substation and


1x220kV Cable Feeders to be connected to Naeeja Super substation, new relays
and equipment shall be installed at Doha Super substation. End to End test,
Testing and commissioning and putting into service of these three circuits shall be
substation Contractor's responsibility.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 220kV control room
to complete the necessary connection and end-to-end test of protection for the said
links (New control room in Doha Super to Airport Super).

One new 66kV transformer LV bay shall be provided as detailed in Main Scope of
the Work. New protection relays based on Phase 13 specifications shall be
provided.

New protection relays based on Phase 13 specifications shall be provided for


existing two 220/66kV Power Transformer protections and one new 220/66kV
Power Transformer protection. All modification on the 220kV and 66V sides of the
220/66kV Power Transformer protection shall be done to make it compatible with
220kV side protection. Contractor shall ensure all the required modifications
including provision of any trip/auxiliary relays, cabling/wiring to achieve Interlocks
and Intertrips between 220kV HV side (new 220kV Building) and existing 66kV LV
switchgears and protection. Presently, transformer mechanical protections relays
are provided in the 220kV HV panels as per old protection philosophy. However,
new provision of transformer mechanical protections relays based on new
200/66kV, 200MVA transformer protection philosophy shall be contractors
responsibility. Existing HV side panels shall be converted to LV side protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 36 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

panels and exact details shall be decided during detail engineering. Existing Cable
Differential relays provided 220kV HV panels and any other relays shall be
dismantled and returned to Kahramaa store according to the standard procedure.
Contractor shall ensure that the relays provided in 220kV Transformer HV Bays
protection panels and those installed in 66kV LV bay protection panels are
complete so as to achieve a complete functional protection for the Transformers.
Testing and commissioning of the new 200/66kV Transformers shall be done in
order to provide complete protection.

Existing AVR equipments shall be used which are connected to 220kV side. It is
not be required to shift to new 220kV Control room; however, it shall be decided
during detailed engineering. Existing AVR equipment shall be tested and its proper
functioning shall be ensured by the Contractor. Third AVR of new 200/66kV,
200MVA transformer may not be required to be integrated with two existing AVRs.
However, all other features which are not dependent on existing AVR schemes
shall be incorporated in accordance to specification requirement.

Modification of the existing 66kV bus bar protection, including conducting bus bar
stability and addition of modules required shall be the responsibility of the
Contractor.

Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.

All modification, testing and commissioning, relay setting calculation, relay testing
on final setting, Transformer differential and REF stability etc. and putting in service
is included in the scope.

 SCS & Associated Equipment

Required Modifications in SCS of Alstom make supplied under Phase 8 project by


Alstom to incorporate all substation modifications in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Additional hardware servers/gateways, if required, to be added to accommodate


new 220kV voltage level BCUs/IEDs and future capacity.

GPS upgrade shall be carried out to accommodate CMS Time Synchronization for
SCS, CMS, Telecom, etc. The existing GPS shall be handed over to KM.

For new common alarms contractor will use additional BCUs to maintain 20%
spare availability.

SCS software upgrade to the latest stable version shall be carried out.

One HMI shall be provided in new 220kV relay room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 37 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Redundant Multimode FO cables shall be provided between existing control room


to new 220kV relay room.

Min. 24 port Ethernet switch with VLAN capability shall be provided in NCC to
enable the PMR service.

Works necessary to shift the PMR server and existing Telecom link to new
switches in coordination with Telecom contractor. New CAT6 Ethernet cables shall
be laid from new switch to PMR servers and all Telecom ports.

 Online Monitoring System

Condition monitoring system comprising of:


- Partial discharge online monitoring system for 220kV GIS;
- Online condition monitoring system for new 220/66kV, 200MVA Transformer;
- Existing TMS can be modified/upgraded to integrate new transformer.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Existing transformers monitoring shall be shifted from Engineering PC to new
TMS/ IMS PC.
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.

 LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be proposed from existing LV
services to the new building.
 FO cable links to connect existing OTP to new OTP to maintain existing telecom
connectivity
 Earthing & Lightning Protection including connection to the existing system
 Small Power & Lighting
 LV Service Equipment and Works comprising of:

The new LVAC Sub Distribution Board, for the new 220kV GIS building, 220/66kV
transformer and HVAC units, and will be connected to the existing LVAC
switchboard. Spare feeders are available in the existing LVAC Board.
Modifications, if any, required for the above connections shall also be carried out.

The existing LVAC switchboard shall be extended to enable connection of the new
LVAC Sub Distribution Board.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 38 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The new LVDC Board, Battery and battery charger for the 220kV GIS & associated
protection systems accommodated in the new building and for the new 220/66kV
transformer.

New UPS to cater the additional load requirements in the new building.

 Security Management System according to specification enclosed in section 3.3.15.

Security management system shall cover both existing and new substation building
and open areas. If due to bidders design there are more than one control rooms,
the bidder shall be bound to provide additional SMS material, if required, for both
control rooms.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Civil works:

All civil works related to new 220kV GIS, the new 220/66kV transformer including
building services and modifications of the existing building basement to enable
cable routing.

Part of the existing boundary wall to be removed and re-constructed in new


location as shown in the tender drawing.

220kV and 66kV Cable troughs for laying cables between new GIS/Transformers
to existing transformers/GIS including duct banks and cross over arrangement with
existing cable corridors.

LV cable troughs/duct banks for routing LV power & control cables, FO cables of
SCADA/ Telecom etc between new and existing buildings.

New 220kV GIS building shall have space for 220kV GIS, 220kV Relay Panels
and LV AC/DC Sub Distribution Boards and Battery room.

Existing 4m wide road to be demolished and reconstructed with 8m wide road as


shown in the tender drawing.

 Air-conditioning and ventilation systems to cover the new GIS.


 220kV GIS room Cranes
 Fire Fighting System

Deluge Water Spray System for Power Transformer including related civil works
such as trenches (@ road crossing for deluge pipes as & where required).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 39 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformer. Transformer shall be manufactured with the necessary provision of
connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Fire Detection & Alarm System for the Transformer, GIS building, other areas and
tie-in (connection/interfacing with existing fire detection & alarm system)

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all new cables (EHV, HV, MV &
LV including cable trays) for the entire length of the cable.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc. in the existing Fire Detection &
Alarm System (which must be verified during commissioning) are included in the
present scope of works.

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH8 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.

Introduction of loop card, interface modules & provision of required number of


relays in the existing Fire Alarm Control Panel for transmitting signals to SCS. In
case of there is no space in the existing FACP to introduce loop card for serving
new 220KV GIS Fire alarm system, existing FACP shall be upgraded or replaced
with new FACP.

Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated. Connection to the existing Underground Remote Oil Containment
Tank, if available OR new underground Remote Oil Containment Tank shall be
constructed nearby to the 200MVA Transformer.

 Power cables

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 40 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

220kV, 1x1200mm2, XLPE, 200MVA, double circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the existing
220/66kV Transformers, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m.

220kV, 1x1200mm2, XLPE, 200MVA, single circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the new 220/66kV
Transformer, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.

66kV, 1x2000mm2, XLPE, 200MVA, single circuit, single point earthed with earth
continuity conductor, two (2) cables per phase cable link between 220/66kV
Transformers and 66kV GIS, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m.

Diversion of the existing 220kV, 1x1200mm2, XLPE, 210MVA, double circuits,


from 220/66kV Transformer into the new 220kV GIS, laid in unfilled concrete
troughs with all accessories. Approx. route length: 150m. Existing cables are laid
under Phase 8 project (GTC142D/2006) by M/s Prysmian / Nexans Consortium.

Diversion of the existing DTS FO cables of approximately 2 x 150m related to


diversion of the existing 220kV cables from diversion point to 220KV GIS,
including splicing with existing DTS Cable. Re-commissioning of existing DTS Unit
of SENSA make, model DTS 800 M12-6 (located at Airport Super).

 Sequence of Construction Works

Milestone A
Complete 220kV GIS, 220/66kV Transformer, remote end works at Naeeja Super
and energize substation from Naeeja Super.

Milestone B
Diversion of the existing 220kV Incoming Cables from the existing 220/66kV
transformers into new 220kV GIS and connect the existing 220/66kV transformers
on to new 220kV GIS. Remote end works at Airport Super.

 REMOTE END WORKS AT AIRPORT SUPER S/S


220/66/11kV Airport Super is an existing substation with 220kV GIS, 66kV GIS and 11kV
Switchgear constructed under Phase 4 Project and further upgraded during Phase 5
project by M/s Siemens. Airport Super will remain connected to Doha Super by the
diversion of the existing Double Circuit cable connection to the new GIS. All modifications,
End to End test, testing and commissioning and putting into service of the two circuits
required shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 41 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Minor Modifications to SCS supplied by Siemens to include changes to 2x220kV


cable bays in the SCS.

Minor modification to TMMC/TDB/RTU to incorporate the changes on the 220kV


feeders in including NCC/ENCC end to end testing. The existing spare capacity in
the RTU shall be maintained.

Alarms no more required shall be deleted and those related to modifications are to
be included in SCS and TMMC/TDB/RTU.

 Protection

Two 2x220kV existing (D30 and D40) bays to be connected to new GIS at Doha
Super substation are already equipped with the Protection Relays/Equipments
under GTC/144A/2006 Phase-8 project.

The relay provided at Airport Super for Main-1 protection is Alstom make P545 and
for Main-2 Protection is Siemens make 7SD5. The new Relays/Equipment to be
installed at Doha Super substation should match the protection at 220kV Airport
Super Substation end (supplied under Phase-8 project).

All the required modifications in existing bays with provision of additional auxiliary
relays, BCU/TMMC panels wiring etc. to meet the Phase-13 protection requirement
shall be responsibility of contractor.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 DTS

Re-commissioning of existing DTS Unit of SENSA make, model DTS 800 M12-6.

 REMOTE END WORKS AT NAEEJA SUPER

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 42 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

220/132/66/11kV Naeeja Super is an existing Substation with 132kV GIS, 66kV and 11kV
Switchgear constructed by Siemens under Phase 6 and further upgraded with addition of
220kV GIS by Hyosung under Phase 10 Project. Naeeja Super will be connected with
Doha Super by 1x220kV Cable circuit under separate Contract (GTC/736/2015, Package
C2).
All required modifications, End to End test, Testing & Commissioning and putting into
service of the single new single circuit shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing switchgear bay,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Required Modifications to SCS supplied by Siemens under Phase 6 project and


further updated in the Phase 10 project to include changes to 1x220kV Cable
feeders in the SCS including Gateway Data mapping to NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x220kV existing spare D30 bay to be connected to Doha Super Substation is with
Protection Relays/Equipments under GTC/371/2010 Phase-10 Project.

The Relay provided at Naeeja Super for Main-1 Protection is Siemens make
7SD522 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Doha Super substation should match the
protection at 220kV Naeeja Super Substation end (supplied under Phase-10
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 43 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.
3.1.5

220/132/66/11KV AL WAAB SUPER SUBSTATION (UPGRADE)


220/132/66/11kV Al Waab Super is the existing substation built by M/s Siemens under
Phase 7 project (GTC 123B/2006). Existing transformer feeder substation shall be
upgraded by addition of 220kV GIS and one new 220/132kV, 315MVA transformer. Al
Waab Super substation shall remain connected to Mehairja Super S/S by diverting the
existing 2x220kV cables, currently connected to 220/132kV transformer to the new 220kV
GIS. Installation of the new equipment as well as diversion of the existing 2x220kV cables
are in the scope of this project.
The principal elements for the upgrade of the 220/132/66/11kV Al Waab Super substation
shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. outgoing Transformer bays for 220/132kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Four (4) Nos. cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Existing 132kV GIS:


- Convert the existing 1 x 132kV feeder bay to incoming Transformer bay for
220/132kV Transformer suitable for connection as per the approved connection
arrangement;
- Re-testing and Re-commissioning of 132kV Transformer LV C18 & C28 bays,
132kV Cable bay converted to Transformer LV bay including required
modifications in the existing switchgear bays along with Local Control Panels
including Indicating Meters in the Local Control Panels, inscription of additional
Alarm facia as required, replacing of Switchgear Name plates and any required
works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

 Power Transformers

An additional 220/132/33kV Power Transformer (Auto) 189/236/315MVA, YNa0


(d1), ONAN/ONAF/OFAF cooling, +10% -10% on load taps in steps of 1.25%,
impedance as the existing Transformers on ONAN provided with AVR, terminal
CTs, neutral CTs etc. Existing Transformers are having 13.44% impedance at

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 44 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

ONAN. Matching of Percentage impedance of new Transformer with the existing


Transformers shall be ensured by Contractor based on the site survey and Factory
acceptance test reports of the existing Transformers. Electrical parameters of the
new Transformer shall be identical to the existing Transformers to meet the
conditions of parallel operation of all three units.
 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with the existing
equipment and with remote ends (in line with remote end protection scope) shall be
provided for the new feeders. However, the following specific requirements shall be
considered:

For 2x220kV Cable Feeders to be connected to Mehairja Super substation, new


relays and equipment shall be installed at Al Waab Super substation. End to End
test, Testing and commissioning and putting into service of these three circuits
shall be substation Contractor's responsibility.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 220kV control room
to complete the necessary connection and end-to-end test of protection for the said
links (New control room in Al Waab Super to Mehairja Super).

One existing 132kV cable spare bay shall be converted to 132kV Auto transformer
LV bay as detailed in Main Scope of the Work. Contractor has to do proper CT
sizing calculation and check the adequacy of existing CTs. Existing Cable bay
protection panel shall be modified with provision of new 132kV transformer LV
protection based on Phase 13 specifications. Existing Cable differential relays, Trip
relays, TCS relays TBs, etc. shall be dismantled and returned to Kahramaa store
according to the standard procedure.

New protection relays based on Phase 13 specifications shall be provided for


existing two 220/132kV Auto Transformer protections and one new 220/132kV
Power Transformer protection. All modification on the 220kV and 132V sides of the
220/132kV Auto Transformer protection shall be done to make it compatible with
220kV side protection. Contractor shall ensure all the required modifications
including provision of any trip/auxiliary relays, cabling/wiring to achieve Interlocks
and Intertrips between new 220kV HV side (new 220kV Building) and existing
132kV LV switchgears and protection.

Existing 220/132kV Auto Transformer protection panels (D11 & D21) are provided
with one low impedance (7UT613) and one high impedance (DADN) differential
protection, also, no tertiary winding earth fault protection is provided. New
protection relays based on Phase 13 specifications (including two low impedance
differential protections from different manufacturers and REF protection) shall be
provided for existing 220/132kV Auto Transformer protection. The tertiary winding
shall be protected separately against earth faults (1ph O/C relay-51N/50N),
additional 1ph Ring CT on the neutral connection of the delta winding shall be
provided. In addition to existing bushing neutral CT, additional ring type CT (of the
similar characteristics) shall be provided on the neutral of the Auto-transformers.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 45 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

This Ring type CT shall be used for Protection applications and Bushing NCT shall
be kept shorted. Presently, transformer mechanical protections relays are provided
in the 220kV HV panels as per old protection philosophy. However, new provision
of transformer mechanical protections High Impedance relays based on new
200/132kV, 315MVA transformer protection Phase 13 philosophy shall be
contractors responsibility. Existing HV side panels shall be converted to LV side
protection panels and exact details shall be decided during detail engineering.
Existing Cable Differential relays provided 220kV HV panels and any other relays
shall be dismantled and returned to Kahramaa store according to the standard
procedure.

Contractor shall ensure that the new relays provided in 220kV Transformer HV
Bays protection panels and those installed in 132kV LV bays protection panels are
complete so as to achieve a complete functional protection for the existing and new
Auto Transformers. Testing and commissioning of the three 200/132kV Auto
Transformers shall be done in order to provide complete protection.

Existing AVR equipments shall be used which are connected to 220kV side. It is
not be required to shift to new 220kV Control room; however, it shall be decided
during detailed engineering. Existing AVR equipment shall be tested and its proper
functioning shall be ensured by the Contractor. Third AVR of new 200/132kV,
315MVA Auto transformer may not be required to be integrated with two existing
AVRs. However, all other features which are not dependent on existing AVR
schemes shall be incorporated in accordance to specification requirement.

Modification of the existing 132kV bus bar protection, including conducting bus bar
stability and addition of modules required shall be the responsibility of the
Contractor.

Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.

All modification, testing and commissioning, relay setting calculation, relay testing
on final setting, Transformer differential and REF stability etc. and putting in service
is included in the scope.

 SCS & Associated Equipment

Required Modifications in SCS of Siemens make supplied under Phase 7 project


by Siemens to incorporate all substation modifications in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

Additional hardware servers/gateways, if required, to be added to accommodate


new 220kV voltage level BCUs/IEDs and future capacity.

GPS upgrade shall be carried out to accommodate CMS Time Synchronization for
SCS, CMS, Telecom, etc. The existing GPS shall be handed over to KM.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 46 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For new common alarms Contractor will use additional BCUs to maintain 20%
spare availability.

One HMI shall be provided in new 220kV relay room.

Redundant Multi mode FO cables, including OTBs, shall be provided between


existing control room to new 220kV relay room.

 Online Monitoring System

Condition monitoring system comprising of:


- Partial discharge online monitoring system for 220kV GIS;
- Online condition monitoring system for new 220/132kV, 315MVA Transformer;
- Existing TMS to be modified/upgraded to integrate new transformer.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Existing transformers shall be integrated to new TMS/IMS PC.
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.

 LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be proposed from existing LV
services to the new building.
 Earthing & Lightning Protection including connection to the existing system;
 Small Power & Lighting
 LV Service Equipment and Works comprising of:

The new LVAC Sub Distribution Board, for the new 220kV GIS building, 220/132kV
transformer and HVAC units, connected to the existing LVAC switchboard. Spare
feeders are available in the existing LVAC Board. Modifications, if any, required for
the above connections shall also be carried out.

The existing LVAC switchboard shall be extended to enable connection of the new
LVAC Sub Distribution Board.

The new LVDC Board, Battery and battery charger for the 220kV GIS & associated
protection systems accommodated in the new building and for the new 220/132kV
transformer.

New UPS to cater the additional load requirements in the new building.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 47 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Security Management System according to specification enclosed in section 3.3.15.

Security management system shall cover both existing and new substation building
and open areas. If due to bidders design there are more than one control rooms,
the bidder shall be bound to provide additional SMS material, if required, for both
control rooms.

All SMS equipment at existing substation shall be decommissioned and


dismantled, and handed over to KM.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Civil works:

All civil works related to new 220kV GIS, the new 220/132kV transformer including
building services and modifications of the existing building basement to enable
cable routing.

New 220kV GIS building shall have space for 220kV GIS, 220kV Relay Panels
and LV AC/DC Sub Distribution Boards and Battery room.

220kV and 132kV Cable troughs for laying cables between new GIS/Transformers
to existing transformers/GIS including duct banks and cross over arrangement with
existing cable corridors.

LV cable troughs/duct banks for routing LV power & control cables, FO cables of
SCADA/ Telecom etc. between new and existing buildings.

Existing 6m wide road (from proposed transformer to existing gate) shall be


demolished and re-constructed with 8m wide road.

Existing Fire shelter to be relocated (re-construction) to suitable location.

Existing duct bank edge to be extended to beyond the road edge.

 220kV GIS room Cranes


 Air-conditioning and ventilation systems to cover the new GIS.
 Fire Fighting System

Deluge Water Spray System for Power Transformer including related civil works
such as trenches (@ road crossing for deluge pipes as & where required).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 48 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformer. Transformer shall be manufactured with the necessary provision of
connection points for installation of TEP System (if Kahramaa decides to adopt this
system in future).

Fire Detection & Alarm System for the Transformer, GIS building, other areas and
tie-in (connection/interfacing with existing fire detection & alarm system).

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all new cables (EHV, HV, MV &
LV including cable trays) for the entire length of the cable.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH7 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.

Introduction of loop card, interface modules & provision of required number of


relays in the existing Fire Alarm Control Panel for transmitting signals to SCS. In
case of there is no space in the existing FACP to introduce loop card for serving
new 220KV GIS Fire alarm system, existing FACP shall be upgraded or replaced
with new FACP.

Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.

 Underground Remote Oil Containment Tank, if available OR new underground


Remote Oil Containment Tank shall be constructed nearby to the 315MVA
Transformer.
 Power cables
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 49 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

220kV, 1x1600mm2, XLPE, 315MVA, double circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the existing
220/132kV Transformers, laid in unfilled concrete troughs with all accessories.
Approx. route length: 150m.

220kV, 1x1600mm2, XLPE, 315MVA, single circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and the new 220/132kV
Transformer, laid in unfilled concrete troughs with all accessories. Approx. route
length: 150m.

132kV, 1x2000mm2, XLPE, 315MVA, single circuit, single point earthed with
earth continuity conductor, one (1) cable per phase cable link between 220/132kV
Transformer and 132kV GIS, laid in unfilled concrete troughs with all accessories.
Approx. route length: 125m.

Diversion of the existing 220kV, 1x2500mm2, XLPE, 515MVA, double circuits,


from 220/132kV Transformer into the new 220kV GIS, laid in unfilled concrete
troughs with all accessories. Approx. route length: 150m. Existing cables are laid
under Phase 7 project (GTC124B/2006) by M/s Mitsubishi Corporation.

Diversion of the existing DTS FO cables of approximately 2 x 250m related to


diversion of the existing 220kV cables from diversion point to 220kV GIS, including
splicing with existing DTS Cable. Re-commissioning of existing DTS Unit of J
Power make, model SUT-15/12 (located at Al Wajbah Super) shall be also done.

 Sequence of Construction Works

Milestone A
Complete 220kV GIS, 220/132kV Transformer with corresponding cable
connections, convert one 220kV Incoming Cable from the existing 220/132kV
transformers into new 220kV GIS and the corresponding remote end works at
Mehairja Super.

Milestone B
Convert the remaining 220kV Incoming Cable from the existing 220/132kV
transformers into new 220kV GIS and connect the existing 220/132kV transformers
on to new 220kV GIS. Remaining remote end works at Mehairja Super.

 REMOTE END WORKS AT MEHAIRJA SUPER


220/66/11kV Mehairja Super is a new Substation with 220kV, 66kV GIS, and 11kV
Switchgear being constructed under Phase 11 Project by M/s L&T. Al Waab Super will be
connected to Mehairja Super (upon its completion) by loop-in/loop-out of the existing Al
Wajbah Super Al Waab Super double circuit cable lines. Mehairja Super will remain
connected to Al Waab Super by the diversion of the existing Double Circuit cable
connection from the 220/132kV transformers to the new 220kV GIS.
All required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project. Modification
works at Mehairja Super shall be arranged in a way not to affect the Warranty Period, if
still valid at the time of new works.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 50 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS of ABB make supplied under Phase 11 project by M/s
L&T to include changes to 2x220kV Cable feeders in the SCS including Gateway
Data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:
2x220kV existing bays to be connected to Al Waab Super Substation are with Protection
Relays/Equipments under Phase-11 Project.

The relay provided at Mehairja Super for Main-1 protection is ABB make RED670
and for Main-2 Protection is Siemens make 7SD52. The new Relays/Equipment to
be installed at Al Waab Super substation should match the protection at 220kV
Mehairja Super Substation end (supplied under Phase-11 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection operation
are to be made available between the Stations based on requirement.

3.1.6

220/66/11KV ABU HAMOUR SUPER SUBSTATION (UPGRADE)


220/66/11kV Abu Hamour Super substation is the existing Super substation built by
Hyosung under phase 10 project. This substation shall be upgraded with the addition of
one new 220/66kV, Power Transformer. Abu Hamour Super is connected to DSS by

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 51 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

double circuit 220kV cable lines and with Abu Hamour North by double circuit 220kV cable
lines. In addition to the existing connections, Abu Hamour Super S/S will be connected to
DSS by 1x220kV cable circuit. The cables will be installed under separate Contract
(GTC/736/2015, Package C2).
The scope of works shall be as follows:

An additional 220/66kV Power Transformer 120/150/200MVA, YNyn0 (d1),


ONAN/ONAF/OFAF cooling, +10% -10% on load taps in steps of 1.25%,
impedance as the existing Transformers on ONAN provided with AVR, terminal
CTs, neutral CTs etc. Existing Transformers are having 12.28% impedance at
ONAN. Matching of Percentage impedance of new Transformer with the existing
Transformers shall be ensured by Contractor based on the site survey and Factory
acceptance test reports of the existing Transformers. Electrical parameters of the
new Transformer shall be identical to the existing Transformers to meet the
conditions of parallel operation of all three units.

Existing 220kV GIS D31 bay and 66kV GIS B38 bay shall be used for connecting
the additional Transformer.

Existing 220kV GIS D50 bay shall be used for connecting the new 220kV feeder
from DSS.

One (1) no. 66kV, 200MVA SF6 Gas Insulated bus duct between 220/66kV Power
Transformers & 66kV GIS including testing and commissioning.

Re-testing and Re-commissioning of one numbers of the existing switchgear D50


bay, 220kV Transformer HV D31 & LV B38 bays, including required modifications
in the existing switchgear bays along with Local Control Panels including Indicating
Meters in the Local Control Panels, inscription of additional Alarm facia as
required, replacing of Switchgear Name plates and any required works including,
wiring, testing & complete re-commissioning of the above switchgear bays.

 Protection Systems modification


Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main Scope
of the Work shall be provided as per standard specification, Protection SLD and Technical
Schedules. However, the following specific requirements shall be considered:

1x220kV existing spare D50 bay to be connected to DSS Substation is with


Protection Relays/Equipments under Phase-10 Project.

The Relay provided at Abu Hamour Super substation for Main-1 Protection is
Siemens make 7SD522 and Main-2 Protection is ABB make RED670 relays. The
contractor shall ensure that the same Relays/Equipment installed at Abu Hamour
Super substation shall match the protection at 220kV DSS Substation end. At both
ends, existing relays shall be used. Retesting of the Relays/Equipment, all
modifications, End to End test, testing and commissioning and putting into service
of these two circuits is included in the Present Scope.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 52 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

All modification on the existing 220kV spare Transformer bay (D31 & B38)
protection as per standard specification, Protection SLD and Technical Schedules,
testing and commissioning, relay setting calculation, relay testing on final setting,
Transformer differential and REF stability test and putting in service are included in
the present Scope.

Contractor shall ensure all the required modifications including provision of any
trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips between
220kV HV side and 66kV LV switchgears and protection. Provision of additional
transformer mechanical protections relays based on new 200/66kV, 200MVA
transformer shall be contractors responsibility. Contractor shall ensure that the
existing relays provided in 220kV Transformer HV Bays protection panels and
those installed in existing relays 66kV LV bay protection panels are complete so
as to achieve a complete functional protection for the Transformers. Testing and
commissioning of the new 200/66kV Transformers shall be done in order to
provide complete protection.

Third AVR of new 200/66kV, 200MVA transformer may not be required to be


integrated with two existing AVRs. However, all other features which are not
dependent on existing AVR schemes shall be incorporated in accordance to
specification requirement.

Modification of the existing 220kV and 66kV bus bar protection, including
conducting bus bar stability and addition of modules required shall be the
responsibility of the Contractor.

Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

All modification, testing and commissioning, relay setting calculation, relay testing
on final setting, Transformer differential and REF stability etc. and putting in
service is included in the scope.

 SCS & Associated Equipment

Required Modifications in SCS of Siemens make updated under Phase 10 project


by Hyosung to incorporate all substation modifications in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Online Monitoring System

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 53 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Required Modifications in the existing Partial discharge online monitoring system


for 220kV and 66kV GIS;

Online condition monitoring system for new 220/66kV, 200MVA Transformer;

Existing TMS shall be modified/upgraded to integrate new transformer.

 LV Service Equipment - Spare feeder outlets available in the existing LVAC board,
LVDC Board and UPS are to be utilized for the new equipment. If required additional
MCCB/MCBs are to be provided in the vacant blocks,
 LV Power Cables, Control Cables with all accessories for the new equipment as
well as for the connections to the existing equipment/systems.
 Earthing & Lightning Protection shall be extended.
 Small Power & Lighting
 Fire Fighting System

Deluge Water Spray System for Power Transformer including related civil works
such as trenches (@ road crossing for deluge pipes as & where required).

Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station

Fire Detection & Alarm System for the Transformer


(connection/interfacing with existing fire detection & alarm system).

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformer. Transformer shall be manufactured with the necessary provision of
connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes all new
cables.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas related to the
installation of the new transformer.

Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH10 Contract during the tie-in works with the existing Fire

GTC-735 SCOPE OF WORKS R0

and

tie-in

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 54 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.

Introduction of loop card (if requires), interface modules & provision of required
number of relays in the existing Fire Alarm Control Panel for transmitting signals to
SCS.

Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.

Connection to the existing underground Remote Oil Containment Tank.

 Civil Works

All required civil Works for the installation of the new Transformer.

 Power cables

220kV, 1x1200mm2, XLPE, 200MVA, single circuit, single point earthed with
earth continuity conductor cable link between 220kV GIS and 220/66kV
Transformer, laid in unfilled concrete troughs with all accessories. Approx. route
length: 50m.

66kV, 1x2000mm2, XLPE, 200MVA, single circuit, single point earthed with earth
continuity conductor, two (2) cables per phase cable link between 220/66kV
Transformers and 66kV GIS, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m (alternative to 66kV GI bus duct in case of layout
difficulty).

 REMOTE END WORKS AT DOHA SOUTH SUPER (DSS) SUBSTATION


400/220/132/11kV Doha South Super is an existing substation, built under 3 separate
projects, where 220kV GIS is installed by Schneider under Phase 4 Project.
DSS shall be connected to Abu Hamour Super by 1x220kV cable circuit.
All required modifications, End to End test, testing and commissioning and putting into
service of the new circuit shall be carried out under the scope of this project. The SOW
includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing GIS D10 bay,
including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 55 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Required modifications to the SCS supplied by ABB to include changes on the


220kV bay in the SCS. Three bays that were connected to Al Thumamah Super
and Al Baraha Super are converted to spare bays through Phase 12 project and
ready to be utilized for the connection to Abu Hamour Super.

Required modifications to existing Microsol RTU/TDB/TMMC equipment include


changes to 1x220kV spare feeder D10 bay and S/S work necessary for
NCC/ENCC end to end testing. Old Transducers shall be replaced and all related
testing shall be done.

Alarms no more required shall be deleted and those related to modifications are to
be included in the conventional control panels and S/S work necessary for remote
signaling to NCC/ENCC.

 Protection

3.1.7

Relay Protection Equipment for the spare bay (D10 bay) as per standard
specification, Protection SLD and Technical Schedules.

The Relay provided at two bays connected to Al Thumamah Super at DSS are
Main-1 Protection is Siemens make 7SD522 and for Main-2 Protection is ABB
make RED670. The contractor shall ensure that the same Relays/Equipment
installed at Abu Hamour Super substation should match the protection at 220kV
DSS Substation end. Both end substations, existing shall be used.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

400/220/132/66/11KV AL WAJBAH SUPER SUBSTATION (UPGRADE)


400/220/132/66/11kV Al Wajbah Super substation is the existing Super substation built by
ABB under phase 7 project and further upgraded with 400kV GIS under GTC318B/2009
project. This substation shall be expanded with the addition of two new 220kV GIS bays.
The scope of works shall be as follows:

Two (2) Nos. of 220kV GIS feeder bays.

Extend the existing double bus bar.

 Protection Systems modification


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 56 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Relay Protection Equipment for new Bays as detailed in Main Scope of Work shall
be provided as per standard specification, Protection SLD and Technical
Schedules.

1x220kV new extended bay will be connected to 220/66/11kV Mehairja Super


being constructed by L&T under Phase 11 Addendum Project. The Relay provided
at Mehairja Super for Main-1 Protection is ABB make RED670 and for Main-2
Protection is Siemens make 7SD522. The new Relays/Equipment to be installed
at Al Wajbah Super substation should match the protection at 220kV Mehairja
Super Substation end (supplied under Phase 11 Addendum project).

Existing Distributed ABB make Low Impedance 220kV Bus bar protection is
provided. Modification of the existing distributed 220kV bus bar protection,
including conducting bus bar stability and addition of modules required shall be the
responsibility of the Contractor. Direct inter-trip for breaker failure, Pole
discrepancy and Bus bar protection operation are to be made available between
the stations based on requirement.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Direct inter-trip for breaker failure, Pole discrepancy and Bus bar protection
operation are to be made available between the stations based on requirement.

 SCS & Associated Equipment

Required Modifications in SCS of ABB make updated under GTC318B/2009


project by ABB to include addition of new 220kV bays in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 LV Service Equipment shall be extended,


 LV Power Cables, Control Cables with all accessories shall be extended,
 Earthing & Lightning Protection shall be extended.
 Civil Works

All required civil Works for the installation of the new bays.

 REMOTE END WORKS AT MEHAIRJA SUPER


220/66/11kV Mehairja Super is a new Substation with 220kV, 66kV GIS, and 11kV
Switchgear being constructed under Phase 11 Project by M/s L&T. Al Wajbah Super will
be connected to Mehairja Super (upon its completion) by single circuit cable line.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 57 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

All required modifications, End to End test, testing and commissioning and putting into
service of one circuit shall be carried out under the scope of this project. Modification
works at Mehairja Super shall be arranged in a way not to affect the Warranty Period, if
still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing switchgear bay,


including required modifications in the existing switchgear bay along with Local
Control Panel including Indicating Meters in the Local Control Panel, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS of ABB make supplied under Phase 11 project by M/s
L&T to include changes to 1x220kV Cable feeder in the SCS including Gateway
Data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:
1x220kV existing bays to be connected to Al Wajbah Super Substation are with Protection
Relays/Equipments under Phase-11 Project.

The relay provided at Mehairja Super for Main-1 protection is ABB make RED670
and for Main-2 Protection is Siemens make 7SD52. The new Relays/Equipment to
be installed at Al Wajbah Super substation should match the protection at 220kV
Mehairja Super Substation end (supplied under Phase-11 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection operation
are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 58 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-2

3.2

3.2.1

132/66/11KV UMM EBAIRIYA SUBSTATION


132/66/11kV Umm Ebairiya substation is intended to cater Power supply to the new
growing demands in the surrounding Al Sakhama area. Umm Ebairiya will be connected to
Al Sakhamah Super by 132kV double circuit cables. Also, Umm Ebairiya substation will be
connected to Umm Al Amad-1 substation at 66kV level by 2x66kV Cable feeders. These
cable circuits will be installed under separate Contract (GTC/736/2015, Package C4).
Besides, existing 2x66kV OHL feeders from Abu Thailah-Umm Salal will be diverted to
Umm Ebairiya to have final configuration 2x66kV OHL Abu-Thailha- Umm Ebairiya
feeders. All the works related to diversion of these OHL feeders are part of this scope
The principal elements of the new 132/66/11kV Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus Section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Outgoing Transformer bays for 132/66kV Transformers;
- Six (6) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear.

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus Section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. incoming Transformer bays for 132/66kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. Outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) spare bays);
- Two (2) nos. 66kV, 160MVA SF6 Gas Insulated bus duct between 132/66kV
Power Transformers & 66kV GIS.
- Space for four future bays, two on each side of the switchgear.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 59 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- One (1) No. Bus section bay rated 2500A;


- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future capacitor bank;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/66kV, 96/120/160MVA, YNyn0 (d1)


ONAN/ONAF/OFAF cooling, 10% on load taps in steps of 1.25%, 13%
impedance on ONAN (96 MVA), provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV 32/40MVA Power Transformer.

Space for four (4) future capacitor banks along with space for four (4) vacuum
contactor panels for the future capacitor banks shall be provided for in the
substation layout.

Two 2 Nos. Auxiliary Transformers 11/0.415kV, 1600kVA, with ONAN cooling,


Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.

The rated Power of the Auxiliary Transformer mentioned here is provisional.


Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, load for two future 66/11kV Transformers, future 11kV
switchgear B & associated equipment with additional capacity of 30%. The
capacity of the Transformer is to be justified by calculation note which shall be
subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
shall be provided for feeders connected to Al Sakhamah Super and Abu Thailah
substations (in line with remote end protection scope of works).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 60 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided for
11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear Substation (A
& B) there shall be two load shedding panels.
Note: OHL between new TC near Umm Ebairiya and Abu Thailah is equipped with
one OPGW (24fibres).

 SCS & Associated Equipment


Substation Control System Including Gateway data mapping to NCC/ENCC/DCC
and s/s works necessary for NCC/ENCC/DCC End to End testing.
 Online Monitoring System

Condition monitoring system comprising of:


- Online condition
Transformers

monitoring

system

for

132/66kV,

96/120/160MVA

- 132kV and 66kV GIS shall be equipped with the internal UHF couplers so the
retrofitting can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 61 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
 LV Power Cables, Control Cables with all accessories.
 Small Power & Lighting
 Earthing & Lightning Protection.
 LV Service Equipment with all accessories, sized for the 132/66/11kV substation
including future 11kV (B) switchgear and future 2 x 66/11kV Transformers.
 Security Management System according to specification enclosed in section 3.3.15.
 Civil works:

All civil works related to new 132/66/11kV substation including building services,

The substation layout shall have space for future 11kV (B) switchgear and space
for future 2 x 66/11kV Transformers.

Control & relay room building shall be sized to accommodate the requirements of
the above future equipment such as control and relay panels, LV Service
equipment etc.

 132kV and 66kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 62 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment


 Power Cables:

132kV, 1x800 mm2, XLPE, 160MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/66kV Transformers laid in unfilled concrete troughs
with all accessories. Approx. route length: 50m.

66kV, 1x2000mm2, XLPE, 160MVA, double circuit, single point earthed with
earth continuity conductor cable links between 66kV GIS and 132/66kV Power
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m (alternative to 66kV GI bus duct in case of layout difficulty).

66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.

11kV, 1x500mm2, XLPE, 1600kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 63 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 REMOTE END WORKS AT AL SAKHAMAH SUPER


400/132/11kV Al Sakhamah Super is a new Substation, being constructed under Phase
12 Project. Umm Ebairiya shall be connected to Al Sakhamah Super by double circuit
132kV Cable Line.
All required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project. Modification
works at Al Sakhamah Super shall be arranged in a way not to affect the Warranty Period,
if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including replacing of feeder Name Plates in the front and rear side of GIS, Local
Control Panels, and any required works including, wiring, testing & complete recommissioning of the above switchgear bays as applicable for establishing the
connection with Umm Ebairiya Substation.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 2x132kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

2x132kV existing bays to be connected to Umm Ebairiya Substation are with


Protection Relays/Equipments under Phase-12 Project.

The new Relays/Equipment to be installed at Umm Ebairiya substation should


match the protection at 132kV Al Sakhamah Super Substation end (supplied under
Phase-12 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 64 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 REMOTE END WORKS AT ABU THAILAH S/S


66/11kV Abu Thailah substation is the existing substation built by M/s Siemens under
phase 7 project and updated by M/s Hyosung under Phase 9 project. Existing OHL
connection Abu Thailah Umm Salal S/S shall be diverted from Umm Salal S/S to Um
Ebairiya S/S. Construction of the new Terminal Compound (TC), dismantling of the
existing OHL from TC to Umm Salal S/S shall be done under this project. Laying of the
new 66kV double circuit from TC to Um Ebairiya S/S shall be done under this project.
All modifications, End to End test, testing and commissioning and putting into service of
the two OHL circuits required shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the exiting GIS bays,


including required modifications in the existing GIS bays along with Local
Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of GIS name plates
and any required works including, wiring, testing & complete re-commissioning
of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Existing Substation Control System supplied by Siemens under phase 7 project


shall be updated Including Gateway data mapping to NCC/ENCC/DCC and S/S
works necessary for NCC/ENCC/DCC End to End testing

Alarms no more required shall be deleted and alarms related to modifications


are to be included in the SCS.

 Protection

2x66kV existing OHL bays to be connected to Umm Ebairiya Substation are with
Protection Relays/Equipments under Phase-7 Project.

The relay provided at Abu Thailah substation for Main-1 protection is Siemens
make 7SD5 an Existing 7SD532 relay shall be upgraded and new relay shall
be installed in place of existing P543 relay at Abu Thailah substation to match
the protection provided at Umm Ebairiya Substation.

Contractor shall change Communication Module in 7SD532 relay and make


them suitable for Dual Fiber Optic Communication.

Separate Three Phase Auto recloser relays and Auto recloser scheme shall be
provided in the 2x66kV existing OHL bays.

Existing trip relays / TCS relays shall be replaced with new relays.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 65 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.2.2

REV. 0

Note: OHL between new TC near Umm Ebairiya and Abu Thailah is equipped
with one OPGW (24fibres).

Existing telecommunication equipments at Abu Thailah shall be dismantled by


telecom contractor. However, all the required scheme and wiring changes shall
be done under this Contract.

Retesting of the Relays/Equipment, all modifications, End to End test, testing


and commissioning and putting into service of these two circuits is included in
the Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule
4.5 will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this
Contract. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

66/11KV UMM AL AMAD-1 SUBSTATION


66/11kV Umm Al Amad-1 substation is intended to cater Power supply to the new growing
demands in the surrounding Al Sakhama area along with Al Sakhamah Super and Umm
Ebairiya S/Ss. Umm Al Amad-1 will be connected to Umm Ebairiya by 66kV double circuit
cable lines under the separate Contract (GTC/736/2015, Package C4).
The principal elements of the new 66/11kV Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus Section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Outgoing Transformer bays for 66/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 66 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;


- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future capacitor bank;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C rated
for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV 32/40MVA Power Transformer.

Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.

The rated Power of the Auxiliary Transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
shall be provided for feeders connected to Umm Ebairiya substation.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 67 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided for
11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear Substation (A
& B) there shall be two load shedding panels.

 SCS & Associated Equipment


Substation Control System Including Gateway data mapping to NCC/ENCC/DCC
and s/s works necessary for NCC/ENCC/DCC End to End testing.
 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All Civil works related to new 66/11kV substation including building services,
 66kV GIS & Fire Pump room Cranes
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 68 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment


 Power Cables:

66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 69 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Remote End S/S Works at Umm Ebairiya S/S


The remote end substation is also to be built under the same package and will be
connected to the new UAA-1 S/S with 2x66kV cable circuits. The cables will be installed
under separate contract (GTC/736/2015, Package C4). The substation contractor shall
coordinate with cable contractor and complete all necessary works for putting these

feeders into service.

3.2.3

132/11KV UMM GARN SUBSTATION


132/11kV Umm Garn substation is intended to cater power supply for the surrounding
area. Umm Garn S/S will be connected by 2x132kV cable circuits Al Sakhama Super and
Semaisma substations. Both these cable circuits will be installed under separate Contract
(GTC/736/2015, Package C4):
The principal elements of new 132/11kV Umm Garn substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Shunt Reactor bays suitable for Double bus bar system with
single pole Circuit breakers
Note: Controlled switching device to be included and CB shall be capable for
reactor switching
- Alternatively, Two numbers of 132kV GIS Bay for Shunt Reactor without
Switching Device
Note: Contractor shall make study and confirm suitability of the proposed GIS
Bay without controlled switching device. This alternative item will be applicable
subject to such confirmation
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 70 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Two (2) Nos. 132kV, 15MVAr Shunt Reactors with terminal CTs, neutral CTs etc.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 71 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

(in line with remote end protection scope of works) shall be provided for feeders
connected to Al Sakhamah Super and Semaismah substations. The new relays to
be installed at 132/11kV Umm Garn substation shall match the protection at Al
Sakhamah Super and Semaismah substation ends.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV incomer bays and each of
the Auxiliary Transformer bays. Separate load shedding panel shall be provided
for 11kV outgoing feeders of each Switchgear, i.e., for a two Switchgear
Substation (A & B) there shall be two load shedding panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- Online monitoring system for 15MVAr Shunt Reactors;
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 72 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 Civil works:

All civil works related to new 132/11kV substation including building services,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 73 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Note: The architectural appearance of the Substation buildings and boundary wall shall
aesthetically match with the structures in the surrounding area and is subject to
approval of concerned authorities. All design approvals in this regard shall be
coordinated with the concerned authorities.
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers & Shunt Reactors. All Transformers shall be manufactured with the
necessary provision of connection points for installation of TEP System (if
Kahramaa decides to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 74 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

132kV, 1x500mm2, XLPE, 15MVA, double circuit, solid bonded cable links
between 132kV GIS and 132kV Shunt Reactors laid in unfilled concrete troughs
with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT SEMAISMAH S/S


132/11kV Semaismah is an existing substation built by Hyosung under Phase 9 Project.
Semaismah will be connected to Umm Garn by 2x132kV, cable circuits. All modifications,
End to End test, testing and commissioning and putting into service of the two circuits
required shall be carried out under the scope of this project. Modification works at
Semaismah shall be arranged in a way not to affect the Warranty Period, if still valid at the
time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Siemens make supplied by Hyosung under


Phase 9 project to include changes to 2x132kV Cable feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 75 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Protection
2x132kV existing bays to be connected to Umm Garn substation are with Protection
Relays/Equipments under GTC/240B/2008 Phase-9 project.

The relay provided at Semaismah for Main-1 protection is Siemens make 7SD5
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Umm Garn substation should match the protection at 132kV
Semaismah Substation end (supplied under Phase-9 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT AL SAKHAMAH SUPER


400/132/11kV Al Sakhamah Super is a new Substation, being constructed under Phase
12 Project. Umm Garn shall be connected to Al Sakhamah Super by 2x132kV cable
circuits.
All modifications, End to End test, testing and commissioning and putting into service of
the two circuits required shall be carried out under the scope of this project. Modification
works at Al Sakhamah Super shall be arranged in a way not to affect the Warranty Period,
if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including replacing of feeder Name Plates in the front and rear side of GIS, Local
Control Panels and any required works including, wiring, testing & complete recommissioning of the above switchgear bays as applicable for establishing the
connection with Umm Garn Substation.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 2x132kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 76 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

3.2.4

2x132kV existing bays to be connected to Umm Garn Substation are with


Protection Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope. The new Relays/Equipment to be installed at Umm Garn
substation should match the protection at 132kV Al Sakhamah Super Substation
end (supplied under Phase-12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

66/11KV ABU THAILAH SUBSTATION (UPGRADE)


66/11kV Abu Thailah substation is existing substation built by M/s Siemens under phase 7
project and modified by M/s Hyosung under Phase 9 project. Existing substation shall be
upgraded by addition of two new 66/11kV transformers and 11kV switchgear (11kV-B).
Existing OHL connection Abu Thailah Umm Salal S/S shall be diverted from Umm Salal
S/S to Um Ebariya S/S. Construction of the new Terminal Compound (TC), dismantling of
the existing OHL from TC to Umm Salal S/S shall be done under this project. Laying of the
new 66kV double circuit from TC to Um Ebariya S/S shall be done under this project. All
required modifications, End to End test, testing and commissioning and putting into
service of the two OHL circuits shall be carried out under the scope of this project.
In addition, the existing OHL connection Umm Al Ghahab Umm Salal S/S shall be
diverted from Umm Salal S/S to Umm Al Amad Super S/S. Construction of the new
Terminal Compound (TC), dismantling of the existing OHL from TC to Umm Salal S/S
shall be done under this project. Laying of the new 66kV double circuit from TC to Umm Al
Amad Super S/S shall be done under this project.
The principal elements of the upgraded 66/11kV Abu Thailah substation shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Modification of the existing 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz,
double bus bar GIS to connect the new transformers on the existing bays:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 77 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Convert the existing 2 x 66kV OHL feeder (B30 and B40) bay into the outgoing
Transformer bay for 66/11kV Transformer suitable for connection as per the
approved connection arrangement;

The SOW includes but is not limited to the following:


- Re-testing and Re-commissioning of two numbers of the existing (B30 and B40)
GIS bays converted to 66/11kV Transformer HV side bays, including required
modifications in the existing GIS bays along with Local Control Panels including
indicating meters in the local control Panels, inscription of additional alarm facia
as required, replacing of GIS name plates and any required works including,
wiring, testing & complete re-commissioning of the above GIS bays.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
- Existing switchgear shall be named Switchgear A;

11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Existing Auxiliary transformers shall remain in function.

 Protection:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 78 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main Scope
of the Work shall be provided as per standard specification, Protection SLD and Technical
Schedules. However, the following specific requirements shall be considered:

Two existing cable spare bays (B30 and B40 bays) shall be converted to 66kV
transformer bays as per above SOW. The Contractor shall provide complete
66/11kV transformer, HV side protection as per Phase-13 specification. CT
adequacy shall be checked. Contractor shall ensure all the required modifications
including provision of any trip/auxiliary relays, cabling/wiring to achieve Interlocks
and Intertrips between existing 66kV HV side and new 11kV LV switchgears and
protection. Contractor shall ensure that the new relays provided in 66kV
Transformer HV Bays protection panels and those installed in new 11kV LV bay
protection panels are complete so as to achieve a complete functional protection
for the Transformers. Testing and commissioning of the new 66/11kV
Transformers shall be done in order to provide complete protection.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection and end-to-end test of protection for the
said links (New control room in Abu Thailah to Umm Ebairiya).

Modifications of the existing Siemens make centralized Low Impedance Busbar


protection, including conducting bus bar stability and addition of modules, if
required shall be provided under this Contract.

Existing 11kV Switchgear shall be marked as 11kV Switchgear A with appropriate


name plates and indications in SCS/NCC. Any required changes to existing
protection relay settings, testing and re-commissioning of existing 25MVA
transformer, 11kV Switchgear and earthing transformer shall be the responsibility
of the Contractor.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

All required modifications in SCS of SIEMENS make supplied under Phase 7


project by SIEMENS to incorporate all substation modifications in the SCS
including Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End to End testing.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 79 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Additional hardware servers/gateways, if required, to be added to accommodate


new 11kV voltage level BCUs/IEDs and future capacity.

For new common alarms the contractor shall use additional BCUs to maintain 20%
spare availability.

One HMI shall be provided in new 11kV relay room.

Redundant Multimode FO cables, including OTBs shall be provided between


existing control room to new 11kV relay room.

New transformer related mechanical protection signals shall be configured in


Transformer LV feeders.

 Online Monitoring System

Condition monitoring system comprising of:


- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be provided from existing LV
services to the new building;
 Small Power & Lighting
 Earthing & Lightning Protection for new equipment and integration with existing
earthing system.
 LV Service Equipment and Works for the newly installed equipment

The new LVAC Sub Distribution Board, for the new switchgear building, 66/11kV
transformers and HVAC units and will be connected to the existing LVAC

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 80 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

switchboard. Spare feeders are available in the existing LVAC Board,


modifications, if any, required for the above connections shall also be carried out.

The new LVDC Board, Battery and battery charger for the 11kV switchgear &
associated protection systems accommodated in the new building and for the new
transformers

New UPS to cater the additional load requirements in the new building.

Existing LV Service Equipment shall remain in function.

 Security Management System according to specification enclosed in section 3.3.15.

 Security management system shall cover both existing and new substation building

and open areas. If due to bidders design there are more than one control rooms,
the bidder shall be bound to provide additional SMS material, if required, for both
control rooms.

 All SMS equipment at existing substation shall be decommissioned and


dismantled, and handed over to KM.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Civil works

All civil works related to new building for 11kV switchgear B & relay panels and
66/11kV transformers including building services,

 Air-conditioning and ventilation systems to cover new 11kV switchgear and Control
& Relay buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers
including related civil works such as trenches (@ road crossing for deluge pipes
as & where required).

Tie-in works for connection with the existing deluge system / fire mains / fire
pumping station

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformer. Transformer shall be manufactured with the necessary provision of
connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 81 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Detection & Alarm System for the Transformer, SWGR Room and tie-in
(connection/interfacing with existing fire detection & alarm system)

Passive fire protection system Cable Coating for all new cables (EHV, HV, MV &
LV including cable trays) for the entire length of the cable.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc. in the existing Fire Detection &
Alarm System (which must be verified during commissioning) are included in the
present scope of works.

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH7 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.

Introduction of loop card (if requires), interface modules & provision of required
number of relays in the existing Fire Alarm Control Panel for transmitting signals to
SCS. In case of there is no space in the existing FACP to introduce loop card for
serving new SWGR & Transformer areas Fire alarm system, existing FACP shall
be upgraded or replaced with new FACP.

Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated. Deluge Water Spray System for Power Transformers & Auxiliary
Transformers

 Connection to the Underground Remote Oil Containment Tank, if available OR


new underground Remote Oil Containment Tank shall be constructed nearby to the
Transformers.
 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 82 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 66 KV OH/Line Double Circuit OH/Line Abu Thailah S/S / Umm Salal S/S
diversion to Umm Ebairiya S/S
This is an existing 66kV double circuit Overhead Transmission Line on Steel Lattice
towers with single Conductors per phase type ZEBRA and one earthwire type OPGW
(24 fibres) with an approximate total length of 13km and total number of 42 towers (to
be operated on 66kV level).
The Contractor shall install a cable compound near existing tower no. 10 close to new
Umm Eberia S/S in order to enable connection of the subject 66kV OHL and Umm
Eberia substation. The works shall include (but not be limited to) design, supply,
installation and commission of:

New Terminal Tower with foundation, earthing, etc.,

Two single circuit 66kV OHL gantries with their foundations,

Cable Compound Palisade Fence complete with gate, foundations,


earthing, kerb stone etc.,

RTV coated OHL insulators and insulator/conductor fittings to match


insulators on the existing OHL,

OHL down droppers between the terminal tower and gantries,

OHL jumpers between OHL gantries and cable sealing ends & lighting
arresters,

All necessary OHL conductor branches and OHL conductor connectors and
links,

Installation/Replacement of Tower/Line identification plates as required,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 83 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Cable compound earthing and earthing connections to cable compound


equipment shall be with no more than 5 resistance to earth for each
structure,

All related civil works (foundation, grading, levelling, backfilling, gravelling,


etc.),

Dismantling of the complete 66kV OHL portion between Umm Salal S/S and
Umm Eberia S/S (10 OHL towers, two single gantries, conductors, OPGW,
insulators and cable compound in front Umm Salal S/S, completely together
with foundations to 2m depth under the ground).

Include installation of OPGW hood closure at new cable compound near Umm
Eberia S/S, OPGW suspension and tension fittings sets. After completion of
OPGW diversion work, the Contractor shall perform End to End testing of the
complete optical link.

The handling of the dismantled materials shall be in accordance with the


Environmental requirements and any benefit (e.g. payment for scrap material) shall be
to the Contractors account. Accordingly, the Bidder shall provide the price (Disposed
Material for OHL of Price schedules) which will be compensated to Kahramaa, i.e.
deducted from the corresponding item in Price schedule.
The Contractor shall submit detailed method statement for the above works, with
clearly indicated outage schedule, which shall be subject of final Kahramaa approval.
All required modifications at Abu Thailah S/S, Umm Salal S/S, LCC, SCS, etc. shall be
covered under this SOW Item.
 66kV OH/Line Double Circuit OH/Line Umm Salal S/S / Umm Al Ghahab S/S
diversion to Umm Al Amad Super S/S
This is an existing 66kV double circuit Overhead Transmission Line on Steel Lattice
towers with single Conductors per phase type ACSR RACOON and one earthwire (1x
Steel 7/12) with an approximate total length of 14.75km and total number of 63 towers.
The Contractor shall install a cable compound near existing tower no. 29 close to
existing Umm Al Amad S/S in order to enable connection of the subject 66kV OHL and
Umm Al Amad substation. The works shall include (but not be limited to) design,
supply, installation and commission of:

New Tower with foundation, earthing, etc.,

Two single circuit 66kV OHL gantries with their foundations,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 84 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Cable Compound Palisade Fence complete with gate, foundations, earthing, kerb
stone etc.,

RTV coated OHL insulators and insulator/conductor fittings to match insulators on


the existing OHL,

OHL down droppers between the terminal tower and gantries,

OHL jumpers between OHL gantries and cable sealing ends & lighting arresters,

All necessary OHL conductor branches and OHL conductor connectors and links,

Installation/Replacement of Tower/Line identification plates as required,

Cable compound earthing and earthing connections to cable compound equipment


shall be with no more than 5 resistance to earth for each structure,

All related civil works (foundation, grading, levelling, backfilling, gravelling, etc.),

Dismantling of the complete 66kV OHL portion between Umm Salal S/S and Umm
Al Amad S/S (27 OHL towers, two single gantries, conductors, OPGW, insulators
and cable compound in front Umm Salal S/S, completely together with foundations
to 2m depth under the ground).

Replacement of existing earthwire (1x Steel 7/12) with new OPGW (48 fibres) on the
OHL portion between Umm Al Amad S/S and Umm Al Ghahab S/S, installation of
OPGW splice and hood closures, OPGW suspension and tension fittings sets, etc.
After completion of OPGW diversion work, the Contractor shall perform End to End
testing of the complete optical link.
The handling of the dismantled materials shall be in accordance with the
Environmental requirements and any benefit (e.g. payment for scrap material) shall be
to the Contractors account. Accordingly, the Bidder shall provide the price (Disposed
Material for OHL of Price schedules) which will be compensated to Kahramaa, i.e.
deducted from the corresponding item in Price schedule.
The Contractor shall submit detailed method statement for the above works, with
clearly indicated outage schedule, which shall be subject of final Kahramaa apprval.
All required modifications at Umm Al Amad S/S, Umm Al Ghahab S/S, LCC, SCS, etc.
shall be covered under this SOW Item.
 Laying of new Cables
Lying of the new 66kV double circuit from TC to Um Ebariya S/S shall be done under
this project.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 85 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

In addition, laying of the new 66kV double circuit from TC to Umm Al Amad Super S/S
shall be done under this project.
Contractor should make all necessary arrangements to connect cable circuits at
Terminal Compounds near Umm Ebariya & Umm Al Amad Super substations.

Surge Arrestors for 4 x 66kV OHL feeders

66kV, 1x2000mm2, XLPE, 120MVA, double circuit underground power cables


and the associated communication cables (48 fiber optic pilot) between terminal
compound at TC-point to 66KV GIS at Um Ebariya substation. Approximate route
length: 600 m.

2 x 66kV, Cable Sealing Ends suitable for terminating above UG Cables and 66kV
OHL feeders from Abu Thailah substation.

66kV, 1x2000mm2, XLPE, 120MVA, double circuit underground power cables


and the associated communication cables (48 fiber optic pilot) between terminal
compound at TC-point to 66KV GIS at Umm Al Amad Super substation.
Approximate route length: 300 m.

2 x 66kV, Cable Sealing Ends suitable for terminating above UG Cables and 66kV
OHL feeders from Umm Al Ghahab substation.

All required co-ordination with Telecom contractor as per the responsibility matrix
included in this scope of work.

 Sequence of Construction Works

Milestone A
Complete Substation extension, complete one new 66kV cable Um Ebariya to TC
and one new 66kV cable Umm al Amad Super to TC and the remote end works at
Umm al Amad Super, Umm AL Ghalab and Umm Salal S/Ss.

Milestone B
Complete the second new 66kV cable Um Ebariya to TC and second new 66kV
cable Umm al Amad Super to TC and the corresponding remote end works.

 REMOTE END WORKS AT UMM SALAL S/S


132/66/11kV Umm Salal is an existing 132/66/11kV substation with 132kV GIS, 66kV GIS
and 11kV Switchgear built by Siemens under Phase 6 Project. Umm Salal is presently
connected to Abu Thailah and Umm Al Ghahab S/Ss by OHL double circuits. Through the
specified OHL circuit modifications under this package, the connection to Abu Thailah will
be changed to Umm Ebairiya & connection to Umm Al Ghahab will be changed to Umm Al
Amad Super Substations. With these changes the OHL bays at Umm Salal S/S will

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 86 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

become spare. All modifications to convert these existing OHL bays into spare bays shall
be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Required modifications in the existing GIS bays into spare bays along with Local
Control Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 6 project to


include changes to 4x66kV OHL feeders into spare feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

 Protection
Four 4x66kV existing bays to be disconnected from Abu Thailah and Umm Al Ghahab
S/Ss are with Protection Relays/Equipments under Phase-6 project.

All modifications to change the OHL bays into spare are included in the Present
Scope.

 REMOTE END WORKS AT UMM AL GHAHAB S/S


66/11kV Umm Al Ghahab is an existing 66/11kV substation with 66kV GIS and 11kV
Switchgear built by Siemens under Phase 10 Project. Umm Al Ghahab will be connected
to Umm Al Amad Super S/S by diverting the existing 2x66kV, OHL, Umm Salal Umm Al
Ghahab into 66kV GIS at Umm Al Amad Super S/S. Construction of the new Terminal
Compound (TC), dismantling of the existing OHL from TC to Umm Salal S/S shall be done
under this project along with the laying of the new 66kV double circuit from TC to Umm Al
Amad Super S/S.
All required modifications, End to End test, testing and commissioning and putting into
service of the two OHL circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 87 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 10 project to


include changes to 2x66kV OHL feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Gateway communication shall be changed from IEC-101 to IEC-104. All necessary


testing shall be carried out after change over.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Umm Al Amad Super substation are with
Protection Relays/Equipments under Phase-10 project.

The relay provided at Umm Al Ghalab for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The relay provided at
UAA Super substation for Main-1 protection is Alstom make P545 and for Main-2
Protection is make 7SD5 relays. The new Relays/Equipment (mainly, Main-2RED670 relay) to be installed and Main-1 as 7SD53 relay at Umm Al Amad
substation should match the protection at 66kV Umm Al Ghahab Substation end
(supplied under Phase-10 project).

The existing main relays provided at Umm Al Ghalab are not connected to any
fibre Optic/ OPGW and hence, new provision of fibre optic patch cords is included
in present scope.
Note: OHL between new TC near Umm Al Ghahab and Umm Al Ghahab shall be
equipped with one OPGW (48fibres).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT UAAS S/S


400/220/66/11kV Umm Al Amad Super is an existing substation with 400kV GIS, 220kV
GIS, 66kV GIS and 11kV Switchgear built by Alstom under Phase 8 Project. UAAS will be
connected to Umm Al Ghahab by diverting the existing 2x66kV, OHL, Umm Salal Umm
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 88 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Al Ghahab into 66kV GIS at Umm Al Amad Super S/S. Construction of the new Terminal
Compound (TC), dismantling of the existing OHL from TC to Umm Salal S/S shall be done
under this project along with the laying of the new 66kV double circuit from TC to Umm Al
Amad Super S/S.
All modifications, End to End test, testing and commissioning and putting into service of
the two circuits required shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays for new
OHL connection, including required modifications in the existing GIS bays along
with Local Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of GIS name plates and
any required works including, wiring, testing & complete re-commissioning of the
above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Alstom under Phase 8 project to


include changes to 2x66kV OHL feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Umm Al Ghalab substation are with
Protection Relays/Equipments under GTC/144A/2006 Phase-8 project.

The relay provided at Umm Al Ghalab for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The relay provided at
UAA Super substation for Main-1 protection is Alstom make P545 and for Main-2
Protection is make 7SD5 relays for UGC cable protection. All the modifications at
UAA Super substation shall be carried out to have OHL protection with new Auto
recloser relay and associated Autocloser scheme. The new Relays/Equipment
(mainly, Main-2-RED670 relay) to be installed and Main-1 as 7SD53 relay at Umm
Al Amad substation should match the protection at 66kV Umm Al Ghahab
Substation end (supplied under Phase-10 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.
Note: OHL between new TC near Umm Al Ghahab and Umm Al Ghahab shall be
equipped with one OPGW (48fibres).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 89 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 90 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-3

3.3

3.3.1

132/11KV AL JAHHANIYA 2 SUBSTATION


132/11kV Al Jahhaniya 2 substation is intended to cater power supply for the surrounding
area including temporary power feed for Rayyan Stadium. Al Jahhaniya 2 S/S will be
connected to network by looping in looping out (LILO) following existing single 132kV
cable circuits:

Bani Hajer Super Barzan Camp 1,


Bani Hajer Super Al Jahhaniya 1 and
Al Jahhaniya 1 Barzan Camp 1.

LILO of the cable circuits Bani Hajer Super Al Jahhaniya 1 and Al Jahhaniya 1
Barzan Camp 1 into Jahhaniya 2 are the scope of this project, while LILO of the cable
circuit Bani Hajer Super Barzan Camp 1 into Jahhaniya 2 shall be done through
separate cable contract (GTC-736/2015 Package C5).
The principal elements of new 132/11kV Al Jahhaniya 2 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Eight (8) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 91 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, load for two future 132/11kV Transformers, load for future
11kV switchgear B with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bani Hajer Super, Barzan Camp 1 and Al Jahhaniya 1 substations.
The new relays to be installed at 132/11kV Al Jahhaniya 2 substation shall match
the protection at Bani Hajer Super, Barzan Camp 1 and Al Jahhaniya 1 substation
end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 92 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories, sized for the 132/11kV substation
including future 11kV switchgear-B and future 2 x 132/11kV, 32/40MVA Transformers.
 Security Management System according to specification enclosed in section 3.3.15.
 Civil works:

All civil works related to new 132/11kV substation including building services,

The substation layout shall have space for future 11kV switchgear-B and space
for future 2 x 132/11kV, 32/40MVA Transformers.

Control & relay room building shall be sized to accommodate the requirements of
the above future equipment such as control and relay panels, LV Service
equipment etc.

 132kV GIS & Fire Pump room Cranes

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 93 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 94 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits listed below shall be diverted into the Al Jahhaniya 2 substation
under the present Scope of Work:

1 x 132kV Bani Hajer Super Al Jahhaniya 1 and

1 x 132kV Al Jahhaniya 1 Barzan Camp 1.

The substation Contractor should make all necessary arrangements to connect cable
circuits at Al Jahhaniya 2 substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion. Refer to attached drawing no. TRANS-52015.

Diversion (Loop in / Loop out) of existing single circuit 132kV, 1x2000mm2,


XLPE, 250MVA underground cable line with fiber optic cable (24 Fibers) between
Bani Hajer Super S/S and Al Jahhaniya 1 S/S into Al Jahhaniya 2 S/S.
Approximate route length: 500m. The Contractor shall include all necessary
modification works and equipment including all link boxes and earth continuity
conductors in the earthing arrangement (cross bonding, single point bonding or
mixed bonding) in order to ensure that required current rating of diverted circuit is
maintained. Necessary details, schematic drawings etc., with accurate lengths
shall be submitted for approval during detailed engineering stage. The terminations
shall be 132kV GIS type in Al Jahhaniya 2 S/S and cable joints at diversion point.
Refer to attached drawings. The circuits were installed by M/s Elsewedy under
Phase 11 project (GTC/450C-2011).

Diversion (Loop in / Loop out) of existing single circuit 132kV, 1x2000mm2,


XLPE, 250MVA underground cable line with fiber optic cable (24 Fibers) between
Al Jahhaniya 1 S/S and Barzan Camp 1 S/S into Al Jahhaniya 2 S/S. Approximate
route length: 500m. The Contractor shall include all necessary modification works
and equipment including all link boxes and earth continuity conductors in the
earthing arrangement (cross bonding, single point bonding or mixed bonding) in
order to ensure that required current rating of diverted circuit is maintained.
Necessary details, schematic drawings etc., with accurate lengths shall be
submitted for approval during detailed engineering stage. The terminations shall be
132kV GIS type in Al Jahhaniya 2 S/S and cable joints at diversion point. Refer to
attached drawings. The circuits were installed by M/s Elsewedy under Phase 11
project (GTC/450C-2011).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 95 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Sequence of Construction Works

Milestone A
Complete Al Jahhaniya 2 substation, diversion of 1x132kV cable circuit between Al
Jahhaniya 1 S/S and Barzan Camp 1 S/S into Al Jahhaniya 2 and related remote
end works at Jahhaniya 1 S/S and Barzan Camp 1 S/S substations.

Milestone B
Diversion of 1x132kV cable circuit between Bani Hajer Super S/S and Al Jahhaniya
1 into Al Jahhaniya 2 and related remote end works at Bani Hajer Super S/S and Al
Jahhaniya 1 substations.

Milestone C
Remote end works at Bani Hajer Super S/S and Barzan Camp-1 substations
related to diversion of 1x132kV cable circuit between Bani Hajer Super S/S and
Barzan Camp-1 into Al Jahhaniya-2 by cable contractor

 REMOTE END WORKS AT BANI HAJER SUPER S/S


220/132/66/11kV Bani Hajer Super is an existing substation with 220kV GIS, 132kV GIS,
66kV GIS and 11kV Switchgear built by Alstom under Phase 8 Project. Bani Hajer Super
will be connected to Al Jahhaniya 2 by diverting (LILO) the existing 1x132kV, Single
Circuit, Bani Hajer Super Barzan Camp 1 into Al Jahhaniya 2 and by diverting (LILO) the
existing 1x132kV, Single Circuit, Bani Hajer Super Al Jahhaniya 1 into Al Jahhaniya 2.
All required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project. Modification
works at Bani Hajer Super shall be arranged in a way not to affect the Warranty Period, if
still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Alstom under Phase 8 project to


include changes to 2x132kV Cable feeders in the SCS including Gateway data

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 96 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing bays to be connected to Al Jahhaniya 2 substation are with
Protection Relays/Equipments under GTC/144A/2006 Phase-8 project.

The relay provided at Bani Hajer Super for Main-1 protection is Alstom make P545
and for Main-2 Protection is Siemens make 7SD5. The new Relays/Equipment to
be installed at Al Jahhaniya 2 substation should match the protection at 132kV
Bani Hajer Super Substation end.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT BARZAN CAMP 1 S/S


132/11kV Barzan Camp 1 is an existing substation with 132kV GIS and 11kV Switchgear
built by L&T under Phase 10 Project. Barzan Camp 1 will be connected to Al Jahhaniya 2
by diverting (LILO) of the existing 1x132kV, Single Circuit, Bani Hajer Super Barzan
Camp 1 into Al Jahhaniya 2 and by diverting (LILO) of the existing 1x132kV, Single Circuit,
Barzan Camp 1 Al Jahhaniya 1 into Al Jahhaniya 2. All required modifications, End to
End test, testing and commissioning and putting into service of the two circuits shall be
carried out under the scope of this project. Modification works at Barzan Camp 1 shall be
arranged in a way not to affect the Warranty Period, if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 97 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS and Power Control Scope

Required Modifications to SCS of Alstom make supplied by L&T under Phase 10


project to include changes to 2x132kV Cable feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing bays to be connected to Al Jahhaniya 2 substation are with
Protection Relays/Equipments under GTC/371A/2006 Phase-10 project.

The relay provided at Barzan Camp 1 feeder connected to Bani Hajer Super for
Main-1 protection is Alstom make P545 and for Main-2 Siemens make 7SD5
relays.

The relay provided at Barzan Camp 1 feeder connected to Al Jahhaniya 1 for Main1 protection is Alstom make P545 and for Main-2 Protection Siemens make
7SD52.

The new Relays/Equipment to be installed at Al Jahhaniya 2 substation should


match the protection at 132kV Barzan Camp 1 Substation end (supplied under
Phase-10 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT AL JAHHANIYA 1 S/S


132/11kV Al Jahhaniya 1 is a new substation being constructed by Siemens under Phase
11 Project. Al Jahhaniya 1 will be connected to Al Jahhaniya 2 by diversion (LILO) of the
existing 1x132kV, Single Circuit, Bani Hajer Super Al Jahhaniya 1 into Al Jahhaniya 2
and by diverting (LILO) of the existing 1x132kV, Single Circuit, Barzan Camp 1 Al
Jahhaniya 1 into Al Jahhaniya 2. All required modifications, End to End test, testing and
commissioning and putting into service of the two circuits shall be carried out under the
scope of this project. Modification works at Al Jahhaniya 1 shall be arranged in a way not
to affect the Warranty Period, if still valid at the time of new works.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 98 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Siemens make supplied by Siemens under


Phase 11 project to include changes to 2x132kV Cable feeders in the SCS
including Gateway data mapping to NCC/ENCC and S/S works necessary for
NCC/ENCC End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing bays to be connected to Al Jahhaniya 2 substation are with
Protection Relays/Equipments under GTC/488C/2012 Phase-11 project.

3.3.2

The relay provided at Al Jahhaniya 1 feeder connected to Barzan Camp 1 for Main1 protection is Alstom make P545 and for Main-2 Siemens make 7SD5.

The new Relays/Equipment to be installed at Al Jahhaniya 2 substation should


match the protection at 132kV Al Jahhaniya 1 Substation end (supplied under
Phase-11 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

132/11KV IZGHAWA NORTH SUBSTATION


132/11kV Izghawa North substation is intended to cater power supply for the surrounding
area. Izghawa North S/S will be connected to network by 132kV double cable circuits from

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 99 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Doha North Super S/S substation. The double circuit cable lines will be installed under
separate Contract (GTC/736/2015, Package C5).
The principal elements of new 132/11kV Izghawa North substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.

11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 100 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Four (4) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 101 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 102 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 132kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between
132/11kV Power Transformers and 11kV switchgear, laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 103 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT DOHA NORTH SUPER S/S


220/132/66/11kV Doha North Super is an existing substation built under Phase 4 project
and upgraded with 132kV GIS by ABB under Phase 6 Project. Doha North Super
substation will be connected to Izghawa North substation by 2x132kV, cable circuits. The
cables will be installed under separate project (GTC/736/2015, Package C5). All required
modifications, End to End test, testing and commissioning and putting into service of the
two circuits shall be carried out under the scope of this project. Modification works at Doha
North Super shall be arranged in a way not to affect the Warranty Period, if still valid at the
time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of ABB make supplied by ABB under Phase 4


project to include changes to 2x132kV Cable feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Minor modification to TMMC/TDB/RTU to incorporate the changes on the 2x132kV


Cable feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained.

Existing BCUs in 2 x 132kV bays utilized for connection towards Izghawa North
substation shall be replaced with new BCUs. New BCUs shall be integrated with
the existing SCS. All wiring modifications in the relay panel, testing and
commissioning to make new BCU fully operational shall be Contractors
responsibility.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 104 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing spare bays to be connected to Izghawa North substation are with
Protection Relays/Equipments under Phase-4 project.

3.3.3

For those 132kV Cable feeders connected to Izghawa North S/S, complete
functional protection system as per standard specification shall be provided. The
new relays/equipment shall be installed at Doha North substation to match the
(new) protection at Izghawa North substation end.

Existing trip relays / TCS relays need to be replaced.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

132/33/11KV MESAIEED INDUSTRIAL-A SUBSTATION


Existing 132/33/11kV Mesaieed Industrial-A substation shall be completely refurbished
with the new equipment. Mesaieed Industrial-A S/S will remain connected to network by
132kV cable circuits to:

QASCO S/S,
MPCL,
MIB S/S and
QVC & QAPCO S/S.

And by 33KV Cable Circuits to:

Container Berth Terminal-7 SS ( CBT-7),


NGL SS and

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 105 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The principal elements of new 132/33/11kV Mesaieed Industrial-A substation shall be as


follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. Shunt Reactor bays suitable for Double bus bar system with
single pole Circuit breakers
Note: Controlled switching device to be included and CB shall be capable for
reactor switching
- Alternatively, Two numbers of 132kV GIS Bay for Shunt Reactor without
Switching Device
Note: Contractor shall make study and confirm suitability of the proposed GIS
Bay without controlled switching device. This alternative item will be applicable
subject to such confirmation
- Two (2) Nos. outgoing Transformer bays for 132/33kV Transformers;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Twelve (12) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 33kV, 2500A at 40C, 31.5kA / 1 sec, double bus bar GIS, consisting
of the following:
- Two (2) Nos. Bus section bay rated 2500A;
- Two (2) Nos. Bus coupler bay rated 2500A;
- Two (2) Nos. Incomers for 132/33kV Transformers rated 2500A;
- Ten (10) Nos. Outgoing feeder bays rated 1250A (four (4) Nos. spare);
- Space for four future bays, two on each side of the 33kV switchgear.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 106 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Eighteen (18) Nos. Outgoing feeder bays rated 630A;


- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
Note: 3 Nos. 132kV Cable feeder bays connected to bulk consumer (QASCO
extension and QAPCO) and 3 Nos. 33kV Outgoing feeder bays connected to bulk
consumer (NGL) shall be provided with Tariff metering CT and VTs cores.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/33kV, 60/75/100 MVA, Dyn1


ONAN/ONAF/OFAF cooling, +5% -15% on load taps in steps of 1.25%, 13%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 33kV Metallic Neutral Earthing Resistors 25.40 ohm @ 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/33kV 100MVA Power transformer.

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Two (2) Nos. 132kV, 15MVAr Shunt Reactors.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1600kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 107 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for:
- 132kV feeders connected to QASCO extension, MESAC (MPCL), MIB and
QAPCO substations.
- 33kV feeders connected to NGL and Container Terminal Berth substations

Metering system: Tariff meters shall be provided on the 3 Nos. 132kV Cable
feeder bays connected to bulk consumer (QASCO extension and QAPCO
substation) and 3 Nos. 33kV Outgoing feeder bays connected to bulk consumer
(NGL substation). Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.

For 33kV outgoing feeders Numerical relay with fibre optic interphase (for Fibre
optic cable) and Numerical relay with fibre optic to pilot converter (for Pilot wire
cable) shall be provided which shall be decided during detail design. Other
protection and schemes as applicable in specification shall be provided.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

Any modifications at TMMC/TDB/RTU, for NCC/DCC communication of existing


substation, required due to sequence of activities, shall be included in the scope of
works.

Some of existing bulk consumer substation signals are hardwired to and


configured in existing RTU at MIA (e.g. QAPCO, NGL, etc,) these signals shall be
shifted to new SCS. Necessary gateway configuration will also be done for
communication to NCC.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 108 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- Online condition monitoring system for new 132/33kV, 100MVA Transformer;
- Online condition monitoring system for 132kV, 15MVAr Shunt Reactor;
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Integrated HMI shall include the existing TMS installed on the existing
transformers;
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/33/11kV substation including building services,

Removal of existing palisade fence and construction of new Boundary wall.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 109 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 132kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:
 132kV, 1x630 mm2, XLPE, 100MVA, double circuits, special bonded cable
links, single point earthed with earth continuity conductor, the links between new
132/33kV transformers and new 132kV GIS switchgear laid in unfilled concrete
troughs with all accessories Approx. route length: 100m.
 33kV, 1x500 mm2, XLPE, 100MVA, double circuits, special bonded cable links,
single point earthed with earth continuity conductor (four (4) cables per phase), the

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 110 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

links between new 132/33kV transformers and new 33kV GIS switchgear laid in
unfilled concrete troughs with all accessories Approx. route length : 50m
 33kV, 1x500 mm2, XLPE, two singlecable links between 33kV NER and
132/33kV, 100 MVA Power Transformers. Approx. route length: 20 m.
 132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bondedcable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.
 11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.
 11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.
 132kV, 1x500mm2, XLPE, 15MVA, double circuit, solid bondedcable links
between 132kV GIS and 132kV 15MVAr Shunt Reactor laid in unfilled concrete
troughs with all accessories. Approx. route length: 150m.
 11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.
 11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
 Diversion of the existing 132kV, 1x1000mm2, XLPE, 174MVA, double circuits,
from the existing 132kV GIS into new 132kV GIS, connected to MPCL S/S, laid in
unfilled concrete troughs with all accessories, including one FO cable per circuit.
Approx. route length: 150m. Existing cables are laid under separate project 2006
by M/s LC Cable.
 Dismantling of the existing 132kV, 1x1600mm2, oil filled, 160MVA, double
circuits, from the existing 132kV GIS into new 132kV GIS, connected to QASCO
S/S, laid in unfilled concrete troughs with all accessories (with a necessary
transition joint), including single core Pilot Wire cable. Approx. route length: 200m.
Existing cables are laid under separate project.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 111 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Diversion of the existing 132kV, 3Cx350mm2, oil filled, 71MVA, single circuit,
from the existing 132kV GIS into new 132kV GIS, connected to QAPCO S/S, laid in
unfilled concrete troughs with all accessories (with a necessary transition joint),
including single core Pilot Wire cable. Approx. route length: 150m. Existing cables
are laid under separate project.
Necessary modification of oil pressure feeding system for the existing cable shall
be done according to the oil profile details of the existing cables. Design and
arrangement shall be submitted for approval (oil tank, alarm panel, oil pressure
gauge manometer, oil pipe feeding, all test required for oil filled cable and concrete
manhole for oil tank). Technical specification of the existing 3-core oil filled cable
circuits will be provided after award of works.
The correct phasing identification (R-Y-B) shall be done after cable is opened,
isolated and earthed for spiking. All required works for laying of new XLPE cable
shall include cutting and capping of redundant section of cable to prevent draining
of oil to the ground. The exact location of cutting cable or diversion points and
details design shall be responsibility of the Contractor and shall be covered by
Contract prices.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.
 Diversion of the existing 132kV, 3Cx350mm2, oil filled, 71MVA, single circuit,
from the existing 132kV GIS into new 132kV GIS, connected to QVC S/S, laid in
unfilled concrete troughs with all accessories (with a necessary transition joint),
including single core Pilot Wire cable. Approx. route length: 150m. Existing cables
are laid under separate project.
Necessary modification of oil pressure feeding system for the existing cable shall
be done according to the oil profile details of the existing cables. Design and
arrangement shall be submitted for approval (oil tank, alarm panel, oil pressure
gauge manometer, oil pipe feeding, all test required for oil filled cable and concrete
manhole for oil tank). Technical specification of the existing 3-core oil filled cable
circuits will be provided after award of works.
The correct phasing identification (R-Y-B) shall be done after cable is opened,
isolated and earthed for spiking. All required works for laying of new XLPE cable
shall include cutting and capping of redundant section of cable to prevent draining
of oil to the ground. The exact location of cutting cable or diversion points and
details design shall be responsibility of the Contractor and shall be covered by
Contract prices.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 112 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Diversion of the existing 132kV, 1x1200mm2, XLPE, 209MVA, double circuits,


from the existing 132kV GIS into new 132kV GIS, connected to MIB S/S, laid in
unfilled concrete troughs with all accessories, including one FO cable per circuit.
Approx. route length: 150m. Existing cables are laid under Kahramaa project
(1995) by M/s Alcatel Cable.
 Diversion of the existing 132kV, 1x1200mm2, XLPE, 209MVA, single circuit,
from the existing 132kV GIS into new 132kV GIS, connected to MIB S/S, laid in
unfilled concrete troughs with all accessories, including one FO cable. Approx.
route length: 150m. Existing cables are laid under Kahramaa project (2008) by M/s
Saudi Cable.
 Diversion of the existing 132kV, 1x1200mm2, XLPE, 160MVA, single circuit,
from the existing 132kV GIS into new 132kV GIS, connected to QASCO S/S, laid in
unfilled concrete troughs with all accessories, including one FO cable. Approx.
route length: 150m. Existing cables are laid under Kahramaa project (1995) by M/s
Alcatel Cable.
 Dismantling of oil filled three core cable to the 132kV, 15MVAr Shunt Reactors.
 Two numbers each of existing 132kV and 33kV cables are to be re-arranged to
make available free space for new substation. If more cables are found upon
survey, contractor shall carry out diversion of such cables.
 Diversion of the existing 33kV, 1x400mm2, 21MVA, double circuits, from the
existing 33kV GIS into new 33kV GIS, connected to CTB7 S/S, laid in unfilled
concrete troughs with all accessories, including one FO cable per circuit. Approx.
route length: 150m.Existing cables are laid under separate project.
 Diversion of the existing 33kV, XLPE, 2x3Cx240mm2, 18MVA, single circuit,
from the existing 33kV GIS into new 33kV GIS, connected to NGL S/S, laid in
unfilled concrete troughs with all accessories,including single core Pilot Wire cable.
Approx. route length: 150m.Existing cables are laid under separate project.
 Diversion of the existing 33kV, oil filled, 2x3Cx240mm2, 12.5MVA, double
circuit, from the existing 33kV GIS into new 33kV GIS, connected to NGL S/S, laid
in unfilled concrete troughs with all accessories (with a necessary transition
joint),including single core Pilot Wire cable. Approx. route length: 150m. Existing
cables are laid under separate project.
Necessary modification of oil pressure feeding system for the existing cable shall
be done according to the oil profile details of the existing cables. Design and
arrangement shall be submitted for approval (oil tank, alarm panel, oil pressure
gauge manometer, oil pipe feeding, all test required for oil filled cable and concrete
manhole for oil tank). Technical specification of the existing 3-core oil filled cable
circuits will be provided after award of works.
The correct phasing identification (R-Y-B) shall be done after cable is opened,
isolated and earthed for spiking. All required works for laying of new XLPE cable
shall include cutting and capping of redundant section of cable to prevent draining
of oil to the ground. The exact location of cutting cable or diversion points and

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 113 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

details design shall be responsibility of the Contractor and shall be covered by


Contract prices.
Decommissioning (dismantling of termination) and draining of oil of the remaining
portion of cable is also a part of the Contractors Scope of Works as well as the
laying and termination of control cables from the oil pressure monitoring system to
the new MIA S/S control room.
 Diversion of the existing DTS FO cables of approximately 1 x 100m related to
diversion of the existing 132kV cables to MIB from diversion point to 132KV GIS,
including splicing with existing DTS Cable. Re-commissioning of existing DTS Unit
of SENSA make, model DTS 800 M8-6 (located at Mesaieed Industrial B).
 Diversion of the existing DTS FO cables of approximately 2 x 100m related to
diversion of the existing 132kV cables to MPCL from diversion point to 132KV GIS,
including splicing with existing DTS Cable. Re-commissioning of existing DTS Unit
of SENSA make, model DTS 800 S15-4(located at Mesaieed Industrial-A).
 Sequence of Construction Works

Milestone A
Complete Substation, divert one cable from MIB from the existing 132kV GIS to the
new 132kV GIS, divert one cable from MPCL from the existing 132kV GIS to the
new 132kV GIS and the remote end works at MIB and MPCL.

Milestone B
Divert the other cables to the new 132kV GIS and the corresponding remote end
works.

 REMOTE END WORKS QASCO EXTENSION S/S


Existing 132/66/1kV QASCO Transformer feeder substation built under phase 4 projects
has been upgraded with new 220/66/11kV substation constructed by Siemens. Existing
2x132kV oil filled cables connected to the 150MVA 132/66kV transformers will be no
longer connected to QASCO SS. Whereas, existing 1x132kV, 160MVA, XLPE feeder
connected to the 132/66kV, 160MVA transformer of QASCO extension substation will
remain in service.
All required modifications, End to End test, testing and commissioning and putting into
service of the one circuit shall be carried out under the scope of this project.
For 1x132kV Cable transformer feeder bay connected to bulk consumer QASCO
extension, all the requirements as per Kahramaa standard specification for the bulk
consumers shall apply. Contractor is required to obtain all the necessary permits to work
inside the bulk consumer premises.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing GIS bay, including
required modifications in the existing GIS bays along with Local Control Panels
including indicating meters in the local control Panels, inscription of additional

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 114 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Minor modification to TMMC/TDB/RTU to incorporate the changes on the 132kV


feeders in including NCC/ENCC end to end testing. The existing spare capacity in
the RTU shall be maintained.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
1x132kV existing cable transformer bays to be connected to Mesaieed Industrial-A
substation is with Protection Relays/Equipments as per the earlier Kahramaa projects.

For the 132kV Cable transformer feeder connected to Mesaieed Industrial-A S/S,
complete functional protection system as per standard specification shall be
provided.

The new relays/equipment shall be installed at QASCO Extension substation to


match the (new) protection at MIA substation end.

Existing trip relays / TCS relays need to be replaced.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT MPCL S/S


Mesaieed A IPP is an existing substation with Gas insulated switchgears constructed by
Mesaieed Power Company Ltd. MPCL is connected to Mesaieed Industrial-A by 2x132kV
cable circuits. These cable circuits will be diverted to the new 132kV GIS at Mesaieed
Industrial-A. All required modifications, End to End test, testing and commissioning and
putting into service of the two circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 115 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Siemens make to include changes to 2x132kV


Cable feeders in the SCS including Gateway data mapping to NCC/ENCC and S/S
works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing bays to be connected to Mesaieed Industrial-A substation are with
Protection Relays/Equipments under separate project.

For those 132kV Cable feeders connected to MPCL S/S, complete functional
protection system as per standard specification shall be provided. The bays are
fully equipped with protection relays/equipment.

The relay provided at MESAC (MPCL) substation for Main-1 protection is Siemens
make 7SD5 and for Main-2 Protection is ABB make RED670 relays. The new
Relays/Equipment to be installed at Mesaieed Industrial-A substation should match
the protection at MESAC (MPCL) Substation end (supplied under Phase-9 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

All modifications, testing and commissioning, relay setting calculations, relay


testing on final setting, end to end test, overall stability etc. and putting into service
is included in the Present Scope

 REMOTE END WORKS QAPCO & QVC S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 116 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

QAPCO & QVC will remain connected to Mesaieed Industrial-A by 132kV, Double Circuit,
Oil filled cables QAPCO Mesaieed Industrial A and QVC- MIA, associated with pilot wire.
All modifications, End to End test, testing and commissioning and putting into service of
two circuits required shall be carried out under the scope of this project.
For 2x132kV Cable transformer feeder bay connected at bulk consumer QAPCO, all the
requirements as per Kahramaa standard specification for the bulk consumers shall apply.
Contractor is required to obtain all the necessary permissions to work inside the bulk
consumer premises.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of One number of the existing switchgear bay,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Minor modification to TMMC/TDB/RTU to incorporate the changes on the 132kV


feeders in including NCC/ENCC end to end testing. The existing spare capacity in
the RTU shall be maintained.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per earlier Kahramaa specification.

For the 132kV Cable transformer feeders connected to Mesaieed Industrial-A S/S,
complete functional protection system as per standard specification shall be
provided, for cable with pliot wire and associated protection.

The new relays/equipment shall be installed at QAPCO substation to match the


(new) protection at MIA substation end.

Existing trip relays / TCS relays need to be replaced.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 117 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS MIB S/S


220/132/33kV Mesaieed Industrial B is an existing 220/132/33kV substation built under
Phase 4 project. Mesaieed Industrial B will remain connected to Mesaieed Industrial-A by
132kV, Triple Circuit, Mesaieed Industrial B Mesaieed Industrial-A. All required
modifications, End to End test, testing and commissioning and putting into service of the
three circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of three numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required modifications in the existing SCS of ABB make to include changes


related to 132kV feeders.

Minor modification to TMMC/TDB/RTU to incorporate the changes on the 3x132kV


Cable feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained.

Existing BCUs in 3 x 132kV bays utilized for connection towards MIA substation
shall be replaced with new BCUs. New BCUs shall be integrated with the existing
SCS. All wiring modifications in the relay panel, testing and commissioning to make
new BCU fully operational shall be Contractors responsibility.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS and TMMC/TDB/RTU.

 Protection
Three 3x132kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per earlier Kahramaa specifications.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 118 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For those 3x132kV Cable feeders connected to Mesaieed Industrial-A S/S,


complete functional protection system as per standard specification shall be
provided.

MIB MIA 132kV Cable Circuit#1 and Circuit#2, the bays are fully equipped with
one main protection relays/equipments supplied under Phase-4 project. The new
relays/equipment shall be installed at MIB substation to match the (new) protection
at MIA substation end.

MIB MIA 132kV Cable Circuit#3, the bays are fully equipped with protection
relays/equipments supplied under Phase-7 project. The relay provided at MIB
substation for Main-1 protection is Siemens make 7SD5 and for Main-2 Protection
is ABB make RED670 relays. The 87C relays are to be replaced to get Dual FO
port communication wherever applicable as per latest Kahramaa specifications.
Existing trip relays / TCS relays need to be replaced. The new Relays/Equipment
to be installed at Mesaieed Industrial-A substation should match the protection
upgraded at MIB Substation end, circuit-3 (supplied under Phase-7 project).

Existing trip relays / TCS relays need to be replaced in all three MIB MIA 132kV
Cable feeders.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS NGL S/S


33/11kV NGL is an existing 33/11kV substation with 33kV and 11kV Switchgear built
under separate project. NGL will remain connected to Mesaieed Industrial-A by 33kV,
Triple Circuit, NGL Mesaieed Industrial-A associated with pilot wires. All required
modifications, End to End test, testing and commissioning and putting into service of the
three circuits shall be carried out under the scope of this project. For 2x33kV Cable feeder
bay connected to bulk consumer NGL, all the requirements as per Kahramaa standard
specification for the bulk consumers shall apply. Contractor is required to obtain all the
necessary permissions to work inside the bulk consumer premises.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of three numbers of the existing switchgear


bays, including required modifications in the existing switchgear bays along with
Local Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of switchgear name

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 119 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

plates and any required works including, wiring, testing & complete recommissioning of the above switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Minor modification to TMMC/TDB/RTU to incorporate the changes on the 33kV


feeders in including NCC/ENCC end to end testing. The existing spare capacity in
the RTU shall be maintained.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Three 3x33kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per the earlier Kahramaa specification.

For the 33kV Cable feeder connected to Mesaieed Industrial-A S/S, complete
functional protection system as per standard specification shall be provided for
cable with pliot wire and associated protection. For 33kV outgoing feeders
Numerical relay with fibre optic to pilot converter (for Pilot wire cable) shall be
provided which shall be decided during detail design. Other protection and
schemes as applicable in specification shall be provided.

Existing trip relays / TCS relays need to be replaced.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS CTB7 (Container Terminal Berth 7) S/S


33kV CTB7 is an existing substation with 33kV Switchgear built under separate project.
CTB7 will remain connected to Mesaieed Industrial-A by 33kV, Double Circuit, CTB7
Mesaieed Industrial-A. All required modifications, End to End test, testing and
commissioning and putting into service of the two circuits shall be carried out under the
scope of this project. For 2x33kV Cable feeder bay connected to bulk consumer CTB7, all
the requirements as per KM standard specification for the bulk consumers shall apply.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 120 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor is required to obtain all the necessary permissions to work inside the bulk
consumer premises
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of ABB make to include changes to 2x33kV Cable


feeders in the SCS including Gateway data mapping to NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x33kV existing bays to be connected to Mesaieed Industrial-A substation is with
Protection Relays/Equipments as per the earlier Kahramaa specification.

For the 33kV Cable feeder connected to Mesaieed Industrial-A S/S, complete
functional protection system as per standard specification shall be provided.

The relay provided at CTB7 substation for Main protection is ABB make RED670
relay and Back O/C ABB make REF615 relay. The new Relays/Equipment to be
installed at Mesaieed Industrial-A substation should match the protection at CTB7
substation end (supplied under bulk consumer project).

Tairff metering provided at Bulk consumer end CTB7 shall be remain connected as
per present arrangement.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 121 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.3.4

REV. 0

132/11KV WAKRAH 3 SUBSTATION


132/11kV Wakrah 3 substation is intended to cater power supply for Wakrah area. Wakrah
3 S/S will be connected to network by single 132kV cable circuit from RAF South and from
132kV FACILITY D (QEZ-3) substations. The cables will be installed under separate
Contract (GTC/736/2015, Package C5).
In addition, single 132kV cable circuit from 132kV FACILITY D (QEZ-3) to Wakrah North
substations shall be installed under separate Contract (GTC/736/2015, Package C5).
The principal elements of new 132/11kV Wakrah 3 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 122 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to RAF South and 132kV FACILITY D (QEZ-3) substations. The new
relays to be installed at 132/11kV Wakrah 3 substation shall match the protection
at RAF South and 132kV FACILITY D (QEZ-3) substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 123 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- 40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 124 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT 132kV FACILITY D (QEZ-3) S/S


FACILITY D is a new generation project including 400kV, 220kV and 132kV Gas insulated
switchgear which will be constructed under IWPP project. The 400kV GIS at FACILITY D
Substation shall be owned, operated and maintained by the IWPP. 220kV and 132kV GIS
at FACILITY D being constructed under IWPP project shall be owned, operated and
maintained by Kahramaa

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 125 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Facility D 132kV GIS (QEZ-3) will be connected by 132kV single circuit cables to Wakrah
3 and Wakrah North substations. The cables will be installed under separate contract
(GTC/736/2015, Package-C5).
All required modifications, End to End test, testing and commissioning and putting into
service of two circuits shall be carried out under the scope of this project. Modification
works at 132kV FACILITY D (QEZ-3) shall be arranged in a way not to affect the Warranty
Period.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of the existing switchgear bay, including


required modifications in the existing switchgear bays along with Local Control
Panels including Indicating Meters in the Local Control Panels, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under IWPP project to include changes


to 2x132kV Cable feeder (Wakra North and Wakra-3) in the SCS including
Gateway Data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing spare bay to be connected to Wakrah 3 Substation and 1x132kV


existing spare bay to be connected to Wakrah North Substation are with Protection
Relays/Equipments under IWPP Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Wakrah 3 and Wakrah North
substations should match the protection at 132kV FACILITY D (QEZ-3) Substation
end (supplied under IWPP project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 126 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 REMOTE END WORKS AT RAF SOUTH S/S


132/11kV RAF South is a new Substation, being constructed under Phase 12 Project.
Wakrah 3 shall be connected to RAF South by single circuit 132kV Cable Line.
All required modifications, End to End test, testing and commissioning and putting into
service of one circuit shall be carried out under the scope of this project. Modification
works at RAF South shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing switchgear bay,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to Wakrah 3 Substation are with Protection


Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of this circuit is included in the Present
Scope. The new Relays/Equipment to be installed at Wakrah 3 substation should
match the protection at 132kV RAF South Substation end (supplied under Phase12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 REMOTE END WORKS AT WAKRAH NORTH S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 127 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

132/11kV Wakrah North is a new Substation, being constructed under Phase 12 Project.
Wakrah North shall be connected to 132kV FACILITY D by single circuit 132kV Cable
Line.
All required modifications, End to End test, testing and commissioning and putting into
service of one circuit shall be carried out under the scope of this project. Modification
works at Wakrah North shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing switchgear bay,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to 132kV FACILITY D (QEZ-3) Substation


are with Protection Relays/Equipments under Phase-12 Project.

The new Relays/Equipment to be installed at Wakrah North substation should


match the protection at 132kV FACILITY D (QEZ-3) Substation end (supplied
under IWPP project).

If there is mismatch between the Main Relays provided at Wakrah North substation
under Phase-12 project, to the relays already provided in 132kV FACILITY D
(QEZ-3) Substation, Swapping or changing with new relays at Wakrah North
substation is included in the Present Scope.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of this circuit is included in the Present
Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 128 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 129 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-4

3.4

3.4.1

66/11KV NEW ASSIRI SUBSTATION (REPLACEMENT)


66/11kV New Assiri substation is intended to replace the existing 66/11kV transformer
feeder substation. The substation is to be built at a new plot and will be connected to
network by diverting the existing cable circuits from Ali Bin Abu Talib S/S.
The principal elements of new 66/11kV New Assiri substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (four (4) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 130 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Ali Bin Abu Talib substation.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 131 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 Civil works

All civil works related to new 66/11kV substation including building services,
Note: The architectural appearance of the Substation buildings and boundary wall
shall aesthetically match with the structures in the surrounding area and is subject
to approval of concerned authorities. All design approvals in this regard shall be
coordinated with the concerned authorities.

 66kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 132 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits from Ali Bin Abu Talib substation shall be diverted from the
existing GIS into the new GIS at New Assiri substation under the present Scope of
Work. Refer to attached drawing no. TRANS-14-2015.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 133 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The substation Contractor should make all necessary arrangements to connect cable
circuits at New Assiri substation. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.

Diversion of the existing 66kV, 1x240mm2, XLPE, 25MVA, double circuit, from
the existing 66/11kV Transformer into new 66kV GIS, connected to Ali Bin Abu
Talib S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 500m.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Sequence of Construction Works

Milestone A
Complete Substation, divert the existing 66kV cable from Ali Bin Abu Talib S/S into
new 66kV GIS and the remote end works at Ali Bin Abu Talib S/Ss.

Milestone B
Divert the second cable from Ali Bin Abu Talib S/S into the new 66kV GIS and the
corresponding remote end works.

 REMOTE END WORKS AT ALI BIN ABU TALIB S/S


66/11kV Ali Bin Abu Talib is an existing substation with 66kV GIS and 11kV Switchgear
built by Siemens under Phase 5 Project. Ali Bin Abu Talib will be connected to New Assiri
by diverting the existing 2x66kV, Double Circuit, Ali Bin Abu Talib New Assiri cables into
new 66kV GIS. All required modifications, End to End test, testing and commissioning and
putting into service of the two circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Modification of existing bays connected to New Assiri SS by installing new VTs

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 134 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Required Modifications to SCS supplied by Siemens under Phase 5 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to New Assiri substation are with Protection
Relays/Equipments under Phase-5 project.

3.4.2

VTs are not available in 66kV GIS bays. New GIS 66kV VT shall be provided at Ali
Bin Abu Talib substation. The Contractor shall be fully responsible for all
associated works, Synchro. Functionality and extension of Local Sync. Scheme,
interlocks and required interfaces.

For those 66kV Cable feeders connected to New Assiri substation, complete
functional protection system as per standard specification shall be provided.
Existing main relay and trip relays / TCS relays need to be replaced with new one.
The new Relays/Equipment to be installed at Ali Bin Abu Talib substation should
match the new protection at New Assiri substation.

Existing Trip relays / TCS relays need to be replaced with new one.

All the required modifications in existing bays with provision of additional auxiliary
relays, BCU panels wiring etc. to meet the the new VT provisions and Phase-13
protection requirement shall be responsibility of contractor.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

66/11KV SALWA ROAD SUBSTATION (REPLACEMENT)


66/11kV Salwa Road substation is intended to replace the existing 66/11kV transformer
feeder substation. The substation is to be built at a new plot and will be connected to
network by diverting the existing cable circuits from Ali Bin Abu Talib S/S.
The principal elements of new 66/11kV Salwa Road substation shall be as follows:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 135 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 136 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Transformer is to be justified by calculation note which shall be subject to


approval.
 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Ali Bin Abu Talib substation.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 137 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 Civil works

All civil works related to new 66/11kV substation including building services,
Note: The architectural appearance of the Substation buildings and boundary wall
shall aesthetically match with the structures in the surrounding area and is subject
to approval of concerned authorities. All design approvals in this regard shall be
coordinated with the concerned authorities.

 66kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 138 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits from Ali Bin Abu Talib substation shall be diverted from the
existing Transformers into the new GIS at Salwa Road substation under the present
Scope of Work. Refer to attached drawing no. TRANS-107-2014.
The substation Contractor should make all necessary arrangements to connect cable
circuits at Salwa Road substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion.

Diversion of the existing 66kV, 1x240mm2, XLPE, 25MVA, double circuit, from
the existing 66/11kV Transformer into new 66kV GIS, connected to Ali Bin Abu

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 139 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Talib S/S, laid in unfilled concrete troughs with all accessories. Approx. route
length: 600m.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Sequence of Construction Works

Milestone A
Complete Substation, divert the existing 66kV cable from Ali Bin Abu Talib S/S into
new 66kV GIS and the remote end works at Ali Bin Abu Talib S/Ss.

Milestone B
Divert the second cable from Ali Bin Abu Talib S/S into the new 66kV GIS and the
corresponding remote end works.

 REMOTE END WORKS AT ALI BIN ABU TALIB S/S


66/11kV Ali Bin Abu Talib is an existing substation with 66kV GIS and 11kV Switchgear
built by Siemens under Phase 5 Project. Ali Bin Abu Talib will be connected to Salwa
Road by diverting the existing 2x66kV, Double Circuit, Ali Bin Abu Talib Salwa Road
cables into new 66kV GIS. All required modifications, End to End test, testing and
commissioning and putting into service of the two circuits shall be carried out under the
scope of this project.
The SOW includes but is not limited to the following:

Modification of existing bays connected to New Assiri SS by installing new VTs

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.

Required Modifications to SCS supplied by Siemens under Phase 5 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 140 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Salwa Road substation are with Protection
Relays/Equipments under Phase-5 project.

3.4.3

For those 66kV Cable feeders connected to Salwa Road substation, complete
functional protection system as per standard specification shall be provided. The
new Relays/Equipment to be installed at Ali Bin Abu Talib substation should match
the new protection at New Assiri substation.

VTs are not available in 66kV GIS bays. New GIS 66kV VT shall be provided at Ali
Bin Abu Talib substation. The Contractor shall be fully responsible for all
associated works, Synchro. Functionality and extension of Local Sync. Scheme,
interlocks and required interfaces.

Existing Trip relays / TCS relays need to be replaced with new one.

All the required modifications in existing bays with provision of additional auxiliary
relays, BCU panels wiring etc. to meet the new VT provisions and Phase-13
protection requirement shall be responsibility of contractor.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

66/11KV BIN MAHMOUD NORTH SUBSTATION


66/11kV Bin Mahmoud North is a new substation intended to cater power supply to the
surrounding area. Bin Mahmoud North S/S will be connected to network by looping in
looping out (LILO) existing 66kV cable circuit from Al Sadd Super Musherib.
The principal elements of new 66/11kV Bin Mahmoud North substation shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 141 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for four (4) vacuum
contactor panels for the future capacitor banks shall be provided for in the
substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, load for two future 66/11kV Transformers & for future 11kV

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 142 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

switchgear-B with additional capacity of 30%. The capacity of the Transformer is to


be justified by calculation note which shall be subject to approval.
 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. All the necessary coordination with Al Sadd Super
Contractor for the compatibility of the relay and equipment (in line with remote end
protection scope of works) shall be provided for feeders connected to Al Sadd
Super substation. The new relays to be installed at 66/11kV Bin Mahmoud North
substation shall match the protection at Al Sadd Super substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 143 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories, sized for the 66/11kV substation including
future 11kV (B) switchgear and future 2 x 66/11kV Transformers.
 Security Management System according to specification enclosed in section 3.3.15.
 Civil works:

All civil works related to new 66/11kV substation including building services,

The substation layout shall have space for future 11kV (B) switchgear and space
for future 2 x 66/11kV Transformers.

Control & relay room building shall be sized to accommodate the requirements of
the above future equipment such as control and relay panels, LV Service
equipment etc.

 66kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 144 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing 66kV double cable circuit Al Sadd Super Musherib shall be diverted into the
Bin Mahmoud North substation under the present Scope of Work:
The substation Contractor should make all necessary arrangements to connect cable
circuits at Bin Mahmoud North substation. The Contractor shall be responsible to
maintain rating of the existing circuits after diversion.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 145 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Diversion (Loop in / Loop out) of existing 66kV, 1x2000mm2, XLPE, 120MVA


underground cable line with fiber optic cable (24 Fibers) between Al Sadd Super
and Musherib S/S into Bin Mahmoud North S/S. Approximate route length: 500m.
The Contractor shall include all necessary modification works and equipment
including all link boxes and earth continuity conductors in the earthing arrangement
(cross bonding, single point bonding or mixed bonding) in order to ensure that
required current rating of diverted circuit is maintained. Necessary details,
schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage. The terminations shall be 66kV GIS type in Bin
Mahmoud North S/S and cable joints at diversion point. Refer to attached drawing
no. TRANS-13-2015.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Sequence of Construction Works

Milestone A
Complete Substation, LILO of the one existing 66kV cable circuit Al Sadd Super
and Musherib into Bin Mahmoud North S/S and the remote end works at Al Sadd
Super S/Ss.

Milestone B
LILO of the second existing 66kV cable circuit Al Sadd Super and Musherib into
Bin Mahmoud North S/S and the corresponding remote end works.

 REMOTE END WORKS AT AL SADD SUPER SUBSTATION:


AL-SADD SUPER is a 220/66/11kV underground substation which will be constructed
under a separate project.
Bin Mahmoud North substation shall be connected to AL-SADD SUPER by 2x66kV
Double Cable Line. All required modifications, End to End test, testing and commissioning
and putting into service of the two circuits shall be carried out under the scope of this
project. Modification works at AL-SADD SUPER shall be arranged in a way not to affect
the Warranty Period, if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 146 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Minor Modifications to SCS to be supplied under separate project to include


changes to 2x66kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

3.4.4

2x66kV existing bays to be connected to Bin Mahmoud North are with Protection
Relays/Equipments under separate Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope. The new Relays/Equipment to be installed at Bin Mahmoud North
substation should match the protection at 66kV AL-SADD SUPER Substation end
(supplied under separate contract).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

66/11KV MUSHERIB SUBSTATION (REFURBISHMENT)


66/11kV Musherib transformer feeder substation is intended to replace the existing
66/11kV substation. Musherib S/S will remain connected to network by diverting the
existing cable circuits from Al Sadd Super S/S to the new 66/11kV transformers.
The principal elements of new 66/11kV Musherib substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 147 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bays for future Capacitor bank;


- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. All the necessary coordination with Al Sadd Super
Contractor for the compatibility of the relay and equipment (in line with remote end
protection scope of works) shall be provided for feeders connected to Al Sadd
Super substation. The new relays to be installed at 66/11kV Musherib substation
shall match the protection at Al Sadd Super substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 148 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

Any modifications at TMMC/TDB/RTU, for NCC/DCC communication of existing


substation, required due to sequence of activities, shall be included in the scope of
works.

 Online Monitoring System

Condition monitoring system comprising of:


- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 66/11kV substation including building services,
 Fire Pump Room Cranes
 Air-conditioning and ventilation systems to cover the Switchgear and Control &
Relay buildings and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 149 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Fire hydrant and ring main piping (all around the substation buildings perimeter).

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the Switchgear buildings, Transformer Yards
(Power & Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 150 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits from Al Sadd Super substation shall be diverted from the
existing transformers into the new transformers at Musherib substation under the
present Scope of Work. Refer to attached drawing no. TRANS-64-2013.
The substation Contractor shall make all necessary arrangements to divert the above
cable circuits at Musherib substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion.

Diversion of the existing 66kV, 1x2000mm2, XLPE, 120MVA, double circuit,


from the existing 66/11kV Transformer into new 66/11kV Transformer, connected
to Al Sadd Super S/S, laid in unfilled concrete troughs with all accessories. Approx.
route length: 100m.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Dismantling/Demolition Works:
De-commissioning and dismantling of the existing 66/11kV Transformers, 11kV
Switchgears and all associated equipment, existing palisade fence etc. and handover
all the dismantled materials to Kahramaa stores or approved location. The existing
buildings and unused structures shall be demolished and all the debris, waste material,
garbage etc. shall be removed from the substation site and shifted to Municipality
designated/ approved location.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 151 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S5

3.5

3.5.1

66/11KV MURRAH SOUTH SUBSTATION


66/11kV Murrah South is a new substation intended to cater power supply to the
surrounding area. Murrah South S/S will be connected to network by 66kV double cable
circuits, under the separate Contract (GTC/736/2015, Package C6):

from Doha Industrial B (DIB) S/S and


from Doha Industrial Super (DIS) S/S.

The principal elements of new 66/11kV Murrah South substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Eight (8) Nos. Cable feeder bays (four (4) spare);
- Space for four future bays, two on each side of the switchgear;

Establish two 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgear with vacuum circuit breakers, consisting of the following:

Switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.

Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 152 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bays for future Capacitor bank;


- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to DIB and DIS substations. The new relays to be installed at 66/11kV
Murrah South substation shall match the protection at DIB and DIS substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 153 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 66/11kV substation including building services,
 66kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 154 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 155 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT DOHA INDUSTRIAL B S/S


66/11kV Doha Industrial B is an existing substation upgraded under Phase 11 project by
M/s L&T with 66kV GIS of Siemens make and 11kV Switchgear. Doha Industrial B will be
connected to Murrah South by new 2x66kV, Double Circuit cable lines. All required
modifications, End to End test, testing and commissioning and putting into service of the
two circuits shall be carried out under the scope of this project. Modification works at Doha
Industrial B shall be arranged in a way not to affect the Warranty Period, if still valid at the
time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS (B30 and
B40) bays, including required modifications in the existing GIS bays along with
Local Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of GIS name plates and
any required works including, wiring, testing & complete re-commissioning of the
above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Siemens make supplied by L&T under Phase 11


project to include changes to 2x66kV Cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing spare (B30 and B40) bays to be connected to Murrah South
substation are with Protection Relays/Equipments under GTC/488D/2006 Phase-11
project.

The relay provided at Doha Industrial B for Main-1 protection is Siemens make
7SD5 and for Main-2 Protection is Alstom make P545. The new Relays/Equipment
to be installed at Murrah South substation should match the protection at 66kV
Doha Industrial B Substation end (supplied under Phase-11 project).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 156 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT DOHA INDUSTRIAL SUPER S/S


220/132/66/11kV Doha Industrial Super is an existing substation built under Phase 10
project by M/s L&T with 220kV GIS, 132kV GIS, 66kV GIS of Hyosung make and 11kV
Switchgear. Doha Industrial Super will be connected to Murrah South by new 2x66kV,
Double Circuit cable lines. All required modifications, End to End test, testing and
commissioning and putting into service of the two circuits shall be carried out under the
scope of this project. Modification works at Doha Industrial Super shall be arranged in a
way not to affect the Warranty Period, if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Alstom make supplied by L&T under Phase 10


project to include changes to 2x66kV Cable feeders in the SCS including Gateway
data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Murrah South substation are with Protection
Relays/Equipments under GTC/488D/2006 Phase-11 project.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 157 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.5.2

REV. 0

The relay provided at Doha Industrial Super for Main-1 protection is Alstom make
P545 and for Main-2 Protection is Siemens make 7SD5. The new
Relays/Equipment to be installed at Murrah South substation should match the
protection at 66kV Doha Industrial Super Substation end (supplied under Phase-11
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

66/11KV UMM AL SENEEM 2 SUBSTATION


66/11kV Umm Al Seneem 2 is a new substation intended to cater power supply to the
surrounding area. Umm Al Seneem 2S/S will be connected to network by looping in
looping out (LILO) existing 66kV cable double circuit Vegetable Market Ain Khalid North.
The principal elements of new 66/11kV Umm Al Seneem 2 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 158 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bays for future Capacitor bank;


- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Ain Khalid North and Vegetable Market substation. The new relays to
be installed at 66/11kV Umm Al Seneem 2 substation shall match the protection at
Ain Khalid North and Vegetable Market substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 159 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 66/11kV substation including building services,
 66kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 160 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 161 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing 66kV double circuit cable lines between Vegetable Market and Ain Khalid
North substations shall be diverted (LILO) into the Umm Al Seneem 2 substation under
the present Scope of Work:
The substation Contractor shall make all necessary arrangements to divert the cable
circuits to Umm Al Seneem 2 substation. The Contractor shall be responsible to
maintain rating of the existing circuits after diversion.

Diversion (Loop in / Loop out) of existing double circuit 66kV, 1x500mm2, XLPE,
40MVA underground cable line with fiber optic cable (24 Fibers) between
Vegetable Market and Ain Khalid North S/S into Umm Al Seneem 2 S/S.
Approximate route length: 500m. The Contractor shall include all necessary
modification works and equipment including all link boxes and earth continuity
conductors in the earthing arrangement (cross bonding, single point bonding or
mixed bonding) in order to ensure that required current rating of diverted circuit is
maintained. Necessary details, schematic drawings etc., with accurate lengths
shall be submitted for approval during detailed engineering stage. The terminations
shall be 66kV GIS type in Umm Al Seneem 2 S/S and cable joints at diversion
point. Refer to attached drawing no. TRANS-102-2014.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Sequence of Construction Works

Milestone A
Complete Substation, LILO of the one existing 66kV cable line Vegetable Market
and Ain Khalid North into Umm Al Seneem 2 S/S and the remote end works at
Vegetable Market and Ain Khalid North S/Ss.

Milestone B
LILO of the second existing 66kV cable line Vegetable Market and Ain Khalid North
into Umm Al Seneem 2 S/S and the remote end works at Vegetable Market and
Ain Khalid North S/Ss.

 REMOTE END WORKS AT AIN KHALID NORTH S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 162 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66/11kV Ain Khalid North is an existing substation built under Phase 10 project by M/s
Hyosung. Ain Khalid North will be connected to Umm Al Seneem 2 by diversion (LILO) of
the existing 2x66kV cables between Ain Khalid North & Vegetable Market substations. All
modifications, End to End test, testing and commissioning and putting into service of these
two circuits shall be carried out under the scope of this project. Modification works at Ain
Khalid North shall be arranged in a way not to affect the Warranty Period, if still valid at the
time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Siemens make under Phase 10 project to include


changes to 2x66kV Cable feeders in the SCS including Gateway data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Umm Al Seneem 2 substation are with
Protection Relays/Equipments under Phase-10 project.

The relay provided at Ain Khalid North for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Umm Al Seneem 2 substation should match
the protection at 66kV Ain Khalid North Substation end (supplied under Phase-10
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 163 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 REMOTE END WORKS AT VEGETABLE MARKET S/S


66/11kV Vegetable Market is an existing substation with 66kV GIS and 11kV Switchgear
built by Siemens under Phase 5 Project. Vegetable Market will be connected to Umm Al
Seneem 2 by diversion (LILO) of the existing 2x66kV cables between Ain Khalid North &
Vegetable Market substations.. All modifications, End to End test, testing and
commissioning and putting into service of these two circuits shall be carried out under the
scope of this project
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.

Required Modifications to SCS supplied by Siemens under Phase 5 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Umm Al Seneem 2 substation are with
Protection Relays/Equipments upgraded under Phase-10 project.

The relay provided at Vegetable Market Main-1 protection is Siemens make 7SD52
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Umm Al Seneem 2 substation should match the protection at 66kV
Vegetable Market Substation end (supplied under Phase-10 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 164 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.5.3

REV. 0

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

66/11KV AL WAAB SUBSTATION (UPGRADE)


66/11kV Al Waab substation is an existing transformer feeder substation built by M/s
Siemens under Phase 6 project. Existing substation shall be upgraded by addition of the
new 66kV GIS, two 66/11kV transformers and the 11kV switchgear-B. Existing 40MVA
transformers are delta-star type with earthing transformers on LV side.
Al Waab will be connected to the network by loop-in/loop-out (LILO) of the existing 2x66kV
cable circuits between Al Waab Super and Mehairja Super substations. It shall also remain
connected to Vegetable Market S/S by diverting the 2x66kV cables from the existing
transformers to the new 66kV GIS at Al Waab S/S.
The principal elements of the upgraded 66/11kV Al Waab substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays;
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
- Existing switchgear shall be named Switchgear A and connected to the new
66kVGIS;
- Re-testing and re-commissioning of existing transformers and associated
GIS/switchgear bays

11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 165 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Eighteen (18) Nos. Outgoing feeder bays rated 630A;


- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the existing substation as well for the new equipment, with additional
capacity of 30%. The capacity of the Transformer is to be justified by calculation
note which shall be subject to approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Vegetable Market, Al Waab Super and Mehairah Super substation.
However, the following specific requirements shall be considered: Protection at Al
Waab substation for 2x66kV cable feeders to be connected to Al Waab Super
substation shall be provided to be compatible with already installed relays at Al
Waab Super substation. End to End test, Testing and commissioning and putting
into service of these two circuits shall be substation Contractor's responsibility.

Protection at Al Waab substation for 2x66kV Cable Feeders to be connected to


Mehairja Super substation shall be provided to be compatible with already
installed relays at Mehairja Super substation. End to End test, Testing and
commissioning and putting into service of these two circuits shall be substation
Contractor's responsibility.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 166 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Protection at Al Waab substation for 2x66kV cable feeders to be connected to


Vegetable Market substation shall be provided to be compatible with already
installed relays at Vegetable Market substation. End to End test, Testing and
commissioning and putting into service of these two circuits shall be substation
Contractor's responsibility.

New (HV side) protection for existing 66/11kV Power Transformer shall be
provided based on Phase 13 specifications, installed in new control room. All
modification on the 66kV and 11V sides of the 66/11kV Power Transformer
protection shall be done to make it compatible with 66kV side protection.
Contractor shall ensure all the required modifications including provision of any
trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips between
66kV HV side (new control building) and existing 11kV LV switchgears and
protection.

Presently, existing panels (B11 & B21), provided with transformer (HV) side
protection and line differential (F87C and F87C+T) protection shall be dismantled
and returned to Kahramaa store as per standard procedure. Transformer
mechanical protections relays are provided in the 66kV HV panels as per old
protection philosophy. However, new provision of transformer mechanical
protections relays based on new 66/11kV, 40MVA transformer protection
philosophy shall be contractors responsibility. Existing HV side panels shall be
converted to LV side protection panels. Alternatively, new LV protection panels
can be provided and exact details shall be decided during detail engineering.
Contractor shall ensure that the relays provided in new 66kV Transformer HV
Bays protection panels and those installed in existing 11kV LV bay protection
panels are complete so as to achieve a complete functional protection for the
Transformers. Testing and commissioning of the 66/11kV Transformers protection.

AVR panels with AVR relays are provided for existing two number 66/11kV
Transformers, located in existing control room. Existing AVR equipment shall be
tested and its proper functioning shall be ensured by the Contractor; however, any
AVR equipment modifications, testing and commissioning for AVR scheme due to
connection to new 66kV GIS shall be Contractor's responsibility.

All other protections shall be provided as per the standard specification.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection and end-to-end test of protection for the
said links (New control room in Al Waab to Vegetable Market).

Existing 11kV Switchgear shall be marked as 11kV Switchgear A with appropriate


name plates and indications in SCS/NCC. Any required changes to existing
protection relay settings, testing and re-commissioning of existing 40MVA
transformer, 11kV Switchgear and earthing transformer shall be the responsibility
of the Contractor.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 167 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

Additional new BCUs shall be installed on existing 11kV Incomers to transfer the
existing signals and controls to new SCS.

For all signals from existing s/s towards NCC/DCC, integration at gateway level
shall be shall be done to have single channel towards control centers. Currently
NCC communication is on IEC-101 whereas DCC communication is on IEC-104.

One HMI shall be provided in existing relay room.

Redundant Multi mode FO cables, including OTBs, shall be provided between


existing control room to new 220kV relay room.

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 168 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection for new equipment and integration with existing
earthing system
 LV Service Equipment and Works for the new equipment
 Existing LV Service Equipment shall remain in function.
 Security Management System according to specification enclosed in section 3.3.15.

Security management system shall cover both existing and new substation
buildings, control rooms and open areas.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Civil works

All civil works related to new 66/11kV substation and 66/11kV transformers
including building services,

 66KV GIS and Fire Pump Room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the new
Transformers. All new Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the 66KV GIS Building, 11kV SWGR B,
Transformer Yards (Power & Auxiliary), and all other areas.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 169 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH6 Contract during the tie-in works with the existing Fire
Detection & Alarm System. Commissioning works must be carried out only by the
authorized vendor or Fire contractor who has installed the existing system.

Introduction of loop card, interface modules & provision of required number of


relays in the existing Fire Alarm Control Panel for transmitting signals to SCS. In
case of there is no space in the existing FACP to introduce loop card for serving
new 66KV GIS Fire alarm system, existing FACP shall be upgraded or replaced
with new FACP.

 Connection to the existing Underground Remote Oil Containment Tank, or new


underground Remote Oil Containment Tank shall be constructed nearby to the 40MVA
Transformers.
 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 170 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing 66kV double cable circuit Al Waab Super Mehairja Super shall be diverted
into the Al Waab substation under the present Scope of Work.
Existing cable circuits from Vegetable Market substation shall be diverted from the
existing transformer into the new GIS at Al Waab substation under the present Scope
of Work:
The substation Contractor shall make all necessary arrangements to divert cable
circuits to Al Waab substation. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.

Diversion of the existing 66kV, 1x500mm2, XLPE, 40MVA, double circuit


cables, from the existing 66/11kV Transformers into new 66kV GIS, connected to
Vegetable Market S/S, laid in unfilled concrete troughs with all accessories.
Approx. route length: 100m.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

Diversion (Loop in / Loop out) of existing 66kV, 1x2000mm2, XLPE, 120MVA


underground cable line with fiber optic cable (24 Fibers) between Al Waab Super
Mehairja Super into Al Waab S/S. Approximate route length: 300m. The Contractor
shall include all necessary modification works and equipment including all link
boxes and earth continuity conductors in the earthing arrangement (cross bonding,
single point bonding or mixed bonding) in order to ensure that required current
rating of diverted circuit is maintained. Necessary details, schematic drawings etc.,
with accurate lengths shall be submitted for approval during detailed engineering
stage. The terminations shall be 66kV GIS type in Al Waab S/S and cable joints at
diversion point. Cable is laid under phase 11 project. Refer to drawing TRANS-952014.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Sequence of Construction Works

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 171 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Milestone A
Complete Substation extension, LILO of the existing 66kV cable line Al Waab
Super and Mehairja Super into Al Waab S/S and the remote end works at Al Waab
Super and Mehairja Super S/Ss.

Milestone B
Divert one circuit Al Waab S/S - Vegetable Market S/S from the existing 66/11kV
transformer into the new 66kV GIS, connect one existing 66/11kV transformer onto
the new 66kV GIS and the corresponding remote end works at Vegetable Market
S/S.

Milestone C
Divert second circuit Al Waab S/S - Vegetable Market S/S from the existing
66/11kV transformer into the new 66kV GIS, connect second existing 66/11kV
transformer onto the new 66kV GIS and the corresponding remote end works at
Vegetable Market S/S.

 REMOTE END WORKS AT VEGETABLE MARKET S/S


66/11kV Vegetable Market is an existing substation built by Siemens under Phase 5
Project. Vegetable Market will remain connected to Al Waab by 2x66kV cables, diverted
from existing transformers to the new GIS at Al Waab. All modifications, End to End test,
testing and commissioning and putting into service of these two modified circuits shall be
carried out under the scope of this project.
The SOW includes but is not limited to the following:

Necessary modifications on the existing 66kV GIS bays, connected to the


transformers at Al Waab substation, to equip the same as UGC feeder bays with
Line VTs.

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Existing BCUs in 66kV bays may not have necessary spare BI/BO to connect new
signals as per latest specification requirements. Hence Contractor shall install
additional BCU or other suitable device to transfer all the required signals to
SCS/NCC as per specification, including new VT connection and additional spare
BI/BO.

Required Modifications to SCS supplied by Siemens under Phase 5 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 172 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Al Waab substation are with Protection
Relays/Equipments under Phase-5 project.

For those 66kV Cable feeders connected to Al Waab substation, complete


functional protection system as per standard specification shall be provided.

VTs are not available in 66kV GIS bays. New GIS 66kV VT shall be provided at
Vegetable Market substation. The Contractor shall be fully responsible for all
associated works, Synchro. Functionality and extension of Local Sync. Scheme,
interlocks and required interfaces.

For those 66kV Cable feeders connected to Al Waab substation, complete


functional protection system as per standard specification shall be provided. New
main relays/equipment shall be installed at Al Waab to match the protection at
Vegetable Market substation end (supplied under Phase-10 project).

Existing trip relays / TCS relays need to be replaced.

All the required modifications in existing bays with provision of additional auxiliary
relays, BCU panels wiring etc. to meet the new VT provisions and Phase-13
protection requirement shall be responsibility of contractor.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

New main relays/equipment shall be installed at Vegetable Market substation to


match the (new) protection at Al Waab substation end.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

 REMOTE END WORKS AT MEHAIRJA SUPER S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 173 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

220/132/11kV Mehairja Super is a new Substation with 220kV, 132kV GIS, and 11kV
Switchgear being constructed under Phase 11 Project. Mehairja Super is connected by
double circuit 66kV Cable Lines to Al Waab Super S/S S and this cable circuits shall be
diverted (by loop-in/loop-out) to Al Waab.
All modifications, End to End test, testing and commissioning and putting into service of
the two circuits shall be carried out under the scope of this project. Modification works at
Mehairja Super shall be arranged in a way not to affect the Warranty Period, if still valid at
the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS supplied under Phase 11 project to include changes to


2x66kV Cable feeders in the SCS including Gateway Data mapping to NCC/ENCC
and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

2x66kV existing bays to be connected to Al Waab Substation are with Protection


Relays/Equipments under Phase-11 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

The new Relays/Equipment to be installed at Al Waab substation should match the


protection at 66kV Mehairja Super Substation end (supplied under Phase-11
project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 174 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 REMOTE END WORKS AT AL WAAB SUPER S/S


220/132/66/11kV Al Waab Super is the existing substation built by M/s Siemens under
Phase 7 project (GTC 123B/2006). Existing transformer feeder substation will be upgraded
with the addition of 220kV GIS through separate package (S-1) under this project. Al
Waab Super S/S is connected at 66kV level by double circuit cable lines to Mehairja Super
and this cable circuits shall be diverted (by loop-in/loop-out)to Al Waab substation.
All modifications, End to End test, testing and commissioning and putting into service of
the two circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS supplied under Phase 7 project to include changes to


2x66kV Cable feeders in the SCS including Gateway Data mapping to NCC/ENCC
and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

2x66kV existing bays to be connected to Al Waab Substation are with Protection


Relays/Equipments under Phase-11 Project.

The new Relays/Equipment to be installed at Al Waab substation should match the


protection at 66kV Al Waab Super Substation end (supplied under Phase-11
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 175 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

3.5.4

66/11KV AL WAAB 2 SUBSTATION


66/11kV Al Waab 2 is a new substation intended to cater power supply to the surrounding
area. Al Waab 2 S/S will be connected to network by looping in looping out (LILO) the
existing 66kV cable single circuit Abu Hamour North Al Soudan South.
The principal elements of new 66/11kV Al Waab 2 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 176 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Abu Hamour North and Al Soudan South substations. The new
relays to be installed at 66/11kV Al Waab 2 substation shall match the protection
at Abu Hamour North and Al Soudan South substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 177 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 66/11kV substation including building services,
 66kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Fire hydrant and ring main piping (all around the substation buildings perimeter).

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 178 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 179 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Existing 66kV double circuit cable lines between Abu Hamour North and Al Soudan
South substations shall be diverted (LILO) into the Al Waab 2 substation under the
present Scope of Work:
The substation Contractor shall make all necessary arrangements to divert the cable
circuits to Al Waab 2 substation. The Contractor shall be responsible to maintain rating
of the existing circuits after diversion.

Diversion (Loop in / Loop out) of existing single circuit 66kV, 1x2000mm2, XLPE,
120MVA underground cable line with fiber optic cable (24 Fibers) between Abu
Hamour North and Al Soudan South S/S into Al Waab 2 S/S. Approximate route
length: 500m. The Contractor shall include all necessary modification works and
equipment including all link boxes and earth continuity conductors in the earthing
arrangement (cross bonding, single point bonding or mixed bonding) in order to
ensure that required current rating of diverted circuit is maintained. Necessary
details, schematic drawings etc., with accurate lengths shall be submitted for
approval during detailed engineering stage. The terminations shall be 66kV GIS
type in Al Waab 2 S/S and cable joints at diversion point. Refer to attached drawing
no. TRANS-2-2015.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 REMOTE END WORKS AT ABU HAMOUR NORTH S/S


66/11kV Abu Hamour North is an existing substation built under Phase 5 project by M/s
Siemens. Abu Hamour North is being connected with Al Soudan South under ongoing
phase 11 project, under which protection relays shall be upgraded.
Abu Hamour North will be connected to Al Waab 2 by diversion (LILO) of the existing
1x66kV cables between Abu Hamour North & Al Soudan South substations. All
modifications, End to End test, testing and commissioning and putting into service of these
two circuits shall be carried out under the scope of this project. Modification works at Abu
Hamour North shall be arranged in a way not to affect the Warranty Period, if still valid at
the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 180 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Required Modifications to SCS of Siemens make under Phase 5 project to include


changes to 1x66kV Cable feeders in the SCS including Gateway data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
One 1x66kV existing bay to be connected to Al Waab 2 substation are with Protection
Relays/Equipments under Phase-11 project.

The relay provided at Abu Hamour North for Main-1 protection is Siemens make
7SD522 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Al Waab 2 substation should match the
protection at 66kV Abu Hamour North Substation end (supplied under Phase-11
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT AL SOUDAN SOUTH S/S


66/11kV Al Soudan South is an existing substation with 66kV GIS and 11kV Switchgear
built by L&T under Phase 11 Project. Al Soudan South will be connected to Al Waab 2 by
diversion (LILO) of the existing 1x66kV cables between Abu Hamour North & Al Soudan
South substations. All modifications, End to End test, testing and commissioning and
putting into service of these two circuits shall be carried out under the scope of this project
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 181 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Required Modifications to SCS supplied by Siemens under Phase 11 project to


include changes to 1x66kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
1x66kV existing bays to be connected to Al Waab 2 substation are with Protection
Relays/Equipments upgraded under Phase-11 project.

The relay provided at Al Soudan South Main-1 protection is Siemens make 7SD52
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Al Waab 2 substation should match the protection at 66kV Al Soudan
South Substation end (supplied under Phase-11 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

PACKAGE S6

3.6

3.6.1

132/66/11KV MAITHER CENTRAL SUBSTATION (UPGRADE)


132/66/11kV Maither Central substation is the existing transformer feeder substation built
by M/s Siemens under Phase 5 project. Existing substation shall be upgraded by
expansion of the existing 66kV GIS, addition of 66/11kV transformers and addition of the
11kV switchgear.
Maither Central substation shall remain connected to Al Wajbah Super S/S.
The principal elements of the upgraded 132/66/11kV Maither Central substation shall be
as follows:
 Gas Insulated/ Air Insulated Switchgear

Modification (Extension) of the existing 66kV, 2500A at 40C, 31.5kA / 1 sec, 3phase, 50Hz, single bus bar GIS consisting of following bays:
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 182 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Note: expansion of the existing 66kV GIS shall be done by the Original Equipment
Manufacturer.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
- Existing switchgear shall be named Switchgear A;

11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the existing substation as well for the new equipment, with additional
capacity of 30%. The capacity of the Transformer is to be justified by calculation
note which shall be subject to approval.

 Protection:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 183 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main Scope
of the Work shall be provided as per standard specification, Protection SLD and Technical
Schedules. However, the following specific requirements shall be considered:

Two new 66kV transformer HV bays shall be provided as detailed in Main Scope
of the Work. New protection relays based on Phase 13 specifications shall be
provided. Contractor shall ensure all the required modifications including provision
of any trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips
between two new 66kV transformer HV bays and new 11kV LV switchgears and
protection. Contractor shall ensure that the new relays provided in 66kV
Transformer HV Bays protection panels and those installed in new 11kV LV bay
protection panels are complete so as to achieve a complete functional protection
for the Transformers. Testing and commissioning of the new 66/11kV
Transformers shall be done in order to provide complete protection.

Modifications of the existing 66kV Siemens make centralized Low Impedance


Busbar protection, including conducting bus bar stability and addition of modules,
shall be provided under this Contract.

Existing 11kV Switchgear shall be marked as 11kV Switchgear A with appropriate


name plates and indications in SCS/NCC. Any required changes to existing
protection relay settings, testing and re-commissioning of existing 40MVA
transformer, 11kV Switchgear and earthing transformer shall be the responsibility
of the Contractor.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

Minor modifications as required in existing Siemens make SCS HMI screens to


show the new 66/11kV Transformer arrangements.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 184 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Existing SCS Gateways is required to interface with new SCS Gateways.

Existing SCADA room shall be utilized to install new SCS system

Provision of protocol/media converters and fibers to connect all services at new


control room to new SCS system.

Existing furniture to be dismantled.

New furniture shall be supplied to accommodate existing and new SCS system.

For new common alarms the contractor will use additional BCUs to maintain 20%
spare availability.

One HMI shall be provided in new 11kV relay room.

Redundant Multimode FO cables, including OTBs, shall be provided between


existing control room to new 220kV relay room.

 Online Monitoring System

Condition monitoring system comprising of:


- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection for new equipment and integration with existing
earthing system.
 LV Service Equipment and Works comprising of:

New LVAC switchboard for the new equipment;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 185 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

LVDC battery and battery charger for the new equipment.

 Existing LV Service Equipment shall remain in function.


 Security Management System according to specification enclosed in section 3.3.15.

Security management system shall cover both existing and new substation
building and open areas. If due to bidders design there are more than one control
rooms, the bidder shall be bound to provide additional SMS material, if required,
for both control rooms.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Civil works

All civil works related to new 11kV substation B and 66/11kV transformers
including building services,

 Fire Pump Room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the new
Transformers. All new Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the new 11kV switchgear building, Transformer
Yards (Power & Auxiliary) and all other areas.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 186 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH5 Contract during the tie-in works with the existing Fire
Detection & Alarm System (if requires). Commissioning works must be carried out
only by the authorized vendor or Fire contractor who has installed the existing
system.

Introduction of loop card, interface modules & provision of required number of


relays in the existing Fire Alarm Control Panel for transmitting signals to SCS. In
case of there is no space in the existing FACP to introduce loop card for serving
new 11kV SWGR/Control building Fire alarm system, existing FACP shall be
upgraded or replaced with new FACP (if requires).

Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.

 Connection to the existing Underground Remote Oil Containment Tank, or new


underground Remote Oil Containment Tank shall be constructed nearby to the 40MVA
Transformers.
 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 187 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.6.2

REV. 0

66/11KV MUSEUM ROAD SUBSTATION (UPGRADE)


66/11kV Museum Road substation is the existing substation built by M/s ABB under Phase
6 project (GTC 05/2004). Existing substation shall be upgraded by expansion of the
existing 66kV GIS, addition of 66/11kV transformers and addition of the 11kV switchgear.
Museum Road substation shall remain connected to Airport Super S/S. In addition,
Museum Road will be connected to Salata substation by 66kV, 120MVA double circuit
cables. The cables will be installed under the separate Contract (GTC/736/2015, Package
C4).
Existing 66kV, 40MVA double circuit, Muntazah North Museum Road shall be
disconnected from Museum Road and diverted to the Old Ghanem.
The principal elements of the upgraded 66/11kV Museum Road substation shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Modification of the existing 66kV, 1850A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz,
single bus bar GIS consisting of following bays:
- Re-testing and Re-commissioning of two numbers of the existing switchgear
bays(B30 & B40), including required modifications in the existing switchgear
bays along with Local Control Panels including Indicating Meters in the Local
Control Panels, inscription of additional Alarm facia as required, replacing of
Switchgear Name plates and any required works including, wiring, testing &
complete re-commissioning of the above switchgear bays
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
Note: expansion of the existing 66kV GIS shall be done by the Original Equipment
Manufacturer.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
- Existing switchgear shall be named Switchgear A;

11kV Switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 188 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for two (2) vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the existing substation as well for the new equipment, with additional
capacity of 30%. The capacity of the Transformer is to be justified by calculation
note which shall be subject to approval.

 Protection:
Relay Protection Equipment for all Primary Equipment (all new bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. However, the following specific requirements shall be
considered:
 2x66kV Cable connection to New Salata (S7 package):
Two 2x66kV existing (B30 and B40) bays to be connected to New Salata substation
substation are with Protection Relays/Equipments under Phase-13, (S7 package) project.

For those 66kV Cable feeders connected to New Salata substation, complete
functional protection system as per standard specification shall be provided.
Presently Main relays REL316*4 and REL551 are provided. The new
Relays/Equipment to be installed at Museum Road substation should match the
new protection at New Salata substation. Existing relays including Over current
relay shall be dismantled and returned to Kahramaa store according to the
standard procedure.

Existing Trip relays / TCS relays need to be replaced with new one.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 189 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Existing CTs (800/400/1 A) for B30 and B40 bays shall be replaced with new CTs
to match with new 120MVA cable rating and protection/metering requirements.
Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs.

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 Extension of GIS for Two (2) Nos. outgoing Transformer bays for 66/11kV
Transformers:

Two new 66kV transformer HV bays shall be provided as detailed in Main Scope
of the Work. New protection relays based on Phase 13 specifications shall be
provided. Contractor shall ensure all the required modifications including provision
of any trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips
between two new 66kV transformer HV bays and new 11kV LV switchgears and
protection. Contractor shall ensure that the new relays provided in 66kV
Transformer HV Bays protection panels and those installed in new 11kV LV bay
protection panels are complete so as to achieve a complete functional protection
for the Transformers. Testing and commissioning of the new 66/11kV
Transformers shall be done in order to provide complete protection.

Modifications of the existing 66kV ABB make Distributed Low Impedance Busbar
protection, including conducting bus bar stability and addition of modules, shall be
provided under this Contract.

Existing 11kV Switchgear shall be marked as 11kV Switchgear A with appropriate


name plates and indications in SCS/NCC. Any required changes to existing
protection relay settings, testing and re-commissioning of existing 40MVA
transformer, 11kV Switchgear and earthing transformer shall be the responsibility
of the Contractor.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 66kV control room
to complete the necessary connection.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 190 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

Existing BCUs on 66kV feeders (B30 & B40) shall be replaced with the new ones
and connected to the new SCS. New protection relays to be connected to the new
SCS.

Minor modification required in existing ABB make SCS HMI screens to show the
new 66/11kV Transformer arrangements.

Existing SCS Gateways is required to interface with new SCS Gateways.

Provision of protocol/media converters and fibers to connect all services at new


control room to new SCS system.

Existing furniture to be dismantled.

New furniture shall be supplied to accommodate existing and new SCS system.

For new common alarms the contractor will use additional BCUs to maintain 20%
spare availability.

One HMI shall be provided in new 11kV relay room.

Redundant Multimode FO cables, including OTBs, shall be provided between


existing control room to new 220kV relay room.

 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 191 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection for new equipment and integration with existing
earthing system.
 LV Service Equipment and Works for the new equipment.

New LVAC switchboard;

LVDC battery and battery charger for the new Transformers and switchgears;

New UPS;

 Existing LV Service Equipment shall remain in function.


 Security Management System according to specification enclosed in section 3.3.15.

Security management system shall cover both existing and new substation
building and open areas. If due to bidders design there are more than one control
rooms, the bidder shall be bound to provide additional SMS material, if required,
for both control rooms.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Civil works

All civil works related to new 11kV substation B and 66/11kV transformers
including building services,

Demolition of existing boundary wall (one side only, refer tender Drg.) and
construction of new boundary wall as shown in the tender drawing.
Note: The architectural appearance of the Substation buildings and boundary wall
shall aesthetically match with the structures in the surrounding area and is subject

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 192 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

to approval of concerned authorities. All design approvals in this regard shall be


coordinated with the concerned authorities.

Establish parking spaces at grade level on the adjacent plot to the allocated
substation plot once the construction of the substation is finalized.

 Fire Pump Room Cranes


 Air-conditioning and ventilation systems to cover new buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the new
Transformers. All new Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the new 11kV switchgear building, Transformer
Yards (Power & Auxiliary) and all other areas.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in PH6 Contract during the tie-in works with the existing Fire
Detection & Alarm System (if requires). Commissioning works must be carried out
only by the authorized vendor or Fire contractor who has installed the existing
system.

Introduction of loop card, interface modules & provision of required number of


relays in the existing Fire Alarm Control Panel for transmitting signals to SCS. In
case of there is no space in the existing FACP to introduce loop card for serving

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 193 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

new 11kV SWGR/Control building Fire alarm system, existing FACP shall be
upgraded or replaced with new FACP (if requires).

Existing Fire Protection & Fire Detection & Alarm System drawings shall be
updated.

 Connection to the existing Underground Remote Oil Containment Tank, or new


underground Remote Oil Containment Tank shall be constructed nearby to the 40MVA
Transformers.
 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits from Muntazah North shall be disconnected from Museum Road
and diverted to the Old Ghanem.
The substation Contractor should make all necessary arrangements to connect cable
circuits at Old Ghanem substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion. Refer to attached drawing No. TRANS-012015.

Diversion of the existing 66kV, 1x300mm2, XLPE, 40MVA, double circuit, from
the existing 66kV GIS at Museum Road into 66kV GIS at Old Ghanem laid in
unfilled concrete troughs with all accessories. Approx. route length: 500m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 194 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

The remaining existing 66kV up to Museum Road S/S shall be disconnected and
capped at both ends.

 REMOTE END WORKS AT MUNTAZAH NORTH S/S


66/11kV Muntazah North is an existing 66/11kV transformer feeder substation built by
ABB under Phase 6 Project. The existing 2x66kV cable feeders to Muntazah North will be
disconnected from Museum Road and diverted to the existing 66kV GIS at Old Ghanem
substation. All modifications, End to End test, testing and commissioning and putting into
service of these two modified circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing 11kV Switchgear


bays, including required modifications in the existing 11kV Switchgear bays along
with Local Control Panels including indicating meters in the local control Panels,
inscription of additional alarm facia as required, replacing of 11kV Switchgear
name plates and any required works including, wiring, testing & complete recommissioning of the above 11kV Switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by ABB under Phase 6 project to include


changes to 2x66kV Cable transformer feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Old Ghanem substation are with Protection
Relays/Equipments under Phase-9 project.

For those 66kV Cable feeders connected to Old Ghanem substation, complete
functional protection system as per standard specification shall be provided to
match protection system at Old Ghanem substation. Presently Main relays
REL316*4 and REL551 are provided. The new Relays/Equipment to be installed at
Muntazah North substation should match the new protection at Old Ghanem
substation (Main-1 Siemens make 7SD5 shall be used for F87C protection and
Main-2 Protection ABB make RED670 shall be F87C+T protection). Existing Main
relays including over current relay shall be dismantled and returned to Kahramaa
store according to the standard procedure.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 195 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Existing trip relays / TCS relays need to be replaced.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing Partial bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

 REMOTE END WORKS AT OLD GHANEM S/S


66/11kV Old Ghanem is an existing substation with 66kV GIS and 11kV Switchgear built
by Siemens under Phase 9 Project (GTC 240D/2008). Old Ghanem will be connected to
Muntazah North by diverting the existing 2x66kV, Double Circuit, Muntazah North
Museum Road into 66kV GIS at Old Ghanem. All modifications, End to End test, testing
and commissioning and putting into service of the two circuits shall be carried out under
the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes to 2x66kV Cable transformer feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 196 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two 2x66kV existing (B50 & B60) bays to be connected directly to transformer at
Muntazah North substation are with Protection Relays/Equipments under GTC/240D/2008
Phase-9 project.

The relay provided at Old Ghanem for Main-1 protection is Siemens make 7SD5
and for Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Muntazah North substation should match the protection at 66kV Old
Ghanem Substation end (supplied under Phase-9 project). The Main-1 Siemens
make 7SD5 shall be used for F87C protection and Main-2 Protection ABB make
RED670 shall be F87C+T protection.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 Remote end Modification at Salata Substation


Salata is a new 66/11kV substation which will be constructed under Package (S-7) in this
project. The museum road substation will be connected to Salata substation with 2x66kV
cable circuit. The cables will be installed by a cable contractor under separate contract.
The substation contractor shall coordinate with cable contractor and Salata substation
contractor for the successful completion of all necessary works for putting these feeders
into service including end to end test, overall stability, co-ordination with NCC, SCS
modification, etc. All contractors shall mutually agree and co-ordinate the activities. In case
of any disputes in this regard, Kahramaa decision will be final.
3.6.3

132/11KV AIN SINAN SUBSTATION


132/11kV Ain Sinan substation is intended to cater power supply to the surrounding areas.
Ain Sinan S/S will be connected to Madinat Al Kaban by 132kV double circuit OHL under
this project.
The principal elements of new 132/11kV Ain Sinan substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bay;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 197 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;


- Two (2) Nos. OHL bays with SF6-Air bushings for connection with OHL
conductor at OHL landing gantry along with aluminum clamps for connection to
twin bundle AAAC flint conductor;
- Two (2) Nos. Cable feeder bays (spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 198 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Madinat Al Kabaan substation. The new relays to be installed at
132/11kV Ain Sinan substation shall match the protection at Madinat Al Kabaan
substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 199 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 LV Power Cables, Control Cables with all accessories.


 Small Power & Lighting
 Earthing & Lightning Protection
 Surge Arrestors for OHL feeders
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 200 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 All outdoor insulators, cable compound equipment, terminal equipment, etc. shall be
provided with RTV coating.
 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

132kV, XLPE, 250MVA, 1x2000sqmm double circuit underground power cables


and the associated communication cables (fiber optic pilot) between terminal
compound and 132KV GIS at Ain Sinan substation. Approximate route length:
100m. (Alternative to GIB, in case layout difficulty).

132kV Outdoor Cable Sealing Ends suitable for the 2x132kV OHL feeder
terminations with 132kV, XLPE, 250MVA, 1x2000sqmm UG cables including
structures, foundations etc. at Ain Sinan substation Terminal Compound
(Alternative to GIB, in case layout difficulty).

132kV GIS Sealing Ends suitable for the 2x132kV feeder terminations with
132kV, XLPE, 250MVA, 2000sqmm UG cables including necessary material and
accessories and steel structure at Ain Sinan Substation (Alternative to GIB, in
case layout difficulty).

 ESTABLISHMENT OF 132KV OVERHEAD LINE MADINAT AL KABAN S/S / AIN


SINAN S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 201 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The proposed construction of 132kV Double Circuit OH Line with twin bundle AAAC
FLINT conductor per phase for transmission of 250MVA of power of each circuit with a
total length of approximately 14km between the existing substation Madinat Al Kabaan
S/S (132/11kV) and new Ain Sinan S/S (132/11kV) Substation. The basic OH line
characteristics shall be as follows:

Twin bundle AAAC FLINT phase conductor,

Porcelain or toughened glass coated insulators (shall be considered as main offer)


or (HTV, SIR) Composite Insulators (to be proposed as alternative offer), and all
other required OHL accessories,

Steel lattice towers and gantries (with fencing if they are located outside substation
compound) complete with structure earthing,

Two composite earthwires (OPGW) with 48 Fibres each,

OHL termination to the equipment at terminal Substations.

The scope shall also include survey approvals from MMAA, mechanical design
considering the safety of the operation and maintenance of each individual line,
supply, installation testing and commissioning.
At existing Madinat Al Kabaan S/S (132/11kV) and new Ain Sinan S/S (132/11kV), the
132kV OH Line shall be terminated to the new OHL double Gantries which shall be
located within substation fences. Terminal towers, gantries, shall be provided in order
to lead in the lines; down leads to the gantries, down droppers, conductor links and
conductor branching clamps to the Cable Compound equipment shall be provided
also. All earthworks and earthing systems related to the OHL shall be provided also
under this Contract. Refer to attached drawing No. TRANS-13-2014.
Contractor is responsible for all works related to End-to-End testing of FO links (F#1,
F#2) between Madinat Al Kabaan S/S and new Ain Sinan S/S.
The Contractor shall coordinate with GTC 735/2015 Telecom Contractor to complete
the works.
All required modifications at existing Madinat Al Kabaan S/S (132/11kV), LCC, SCS,
etc. shall be covered under this SOW Item.
 REMOTE END WORKS AT MADINAT AL KABAAN S/S
132/11kV Madinat Al Kabaan is an existing substation with 132kV GIS and 11kV
Switchgear built by L&T under Phase 10 Project. Madinat Al Kabaan will be connected to
Ain Sinan by new 132kV, double circuit OHL. All modifications, End to End test, testing
and commissioning and putting into service of the two circuits shall be carried out under
the scope of this project. Modification works at Madinat Al Kabaan shall be arranged in a
way not to affect the Warranty Period, if still valid at the time of new works.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 202 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Alstom make supplied by L&T under Phase 10


project to include changes to 2x132kV Cable feeders in the SCS including
Gateway data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC
End to End testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x132kV existing bays to be connected to Ain Sinan substation are with Protection
Relays/Equipments under GTC/371A/2006 Phase-10 project.

3.6.4

The relay provided at Madinat Al Kabaan for Main-1 protection is Alstom make
P545 and for Main-2 Protection is Siemens make 7SD52. The new
Relays/Equipment to be installed at Ain Sinan substation should match the
protection at 132kV Madinat Al Kabaan Substation end (supplied under Phase-10
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

132/11KV JERYAN JENAIHAT 1 SUBSTATION


132/11kV Jeryan Jenaihat 1 substation is intended to cater mainly Boulevard mall project.
Jeryan Jenaihat 1 S/S will be connected to network by looping in looping out (LILO)
existing single 132kV cable circuit Jeryan Jenaihat Super S/S Al Khissa West S/S into
Jeryan Jenaihat 1 S/S.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 203 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

LILO of the cable circuit Jeryan Jenaihat Super S/S Al Khissa West S/S is scope of this
project.
The principal elements of new 132/11kV Jeryan Jenaihat 1 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 204 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Jeryan Jenaihat Super and Al Khissa West substations. The new
relays to be installed at 132/11kV Jeryan Jenaihat 1 substation shall match the
protection at Jeryan Jenaihat Super and Al Khissa West substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 205 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 206 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuit listed below shall be diverted into the Jeryan Jenaihat 1
substation under the present Scope of Work:

1 x 132kV Jeryan Jenaihat Super Al Khissa West.

The substation Contractor should make all necessary arrangements to divert and
connect cable circuits at Jeryan Jenaihat 1 substation. The Contractor shall be
responsible to maintain rating of the existing circuits after diversion.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 207 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Diversion (Loop in / Loop out) of existing single circuit 132kV, 1x2000mm2,


XLPE, 250MVA underground cable line with fiber optic cable (24 Fibers) between
Jeryan Jenaihat Super and Al Khissa West S/S into Jeryan Jenaihat 1 S/S.
Approximate route length: 700m. The Contractor shall include all necessary
modification works and equipment including all link boxes and earth continuity
conductors in the earthing arrangement (cross bonding, single point bonding or
mixed bonding) in order to ensure that required current rating of diverted circuit is
maintained. Necessary details, schematic drawings etc., with accurate lengths
shall be submitted for approval during detailed engineering stage. The terminations
shall be 132kV GIS type in Jeryan Jenaihat 1 S/S and cable joints at diversion
point. Refer to attached drawing TRANS-14-2015. The circuits of Elsewedy make
were installed by M/s NCC under Phase 10 project (GTC/372F-2010).

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 REMOTE END WORKS AT JERYAN JENAIHAT SUPER S/S


220/132/66/11kV Jeryan Jenaihat Super is an existing substation with 220kV GIS, 132kV
GIS and 11kV Switchgear built by Siemens under Phase 10 Project. Umm Salal Mohamed
Super is renamed as Jeryan Jenaihat Super. Jeryan Jenaihat Super will be connected to
Jeryan Jenaihat 1 by diverting (LILO) of the existing 1x132kV, Single Circuit, Jeryan
Jenaihat Super Al Khissa West into Jeryan Jenaihat 1. All modifications, End to End test,
testing and commissioning and putting into service of the circuit shall be carried out under
the scope of this project. Modification works at Jeryan Jenaihat Super shall be arranged in
a way not to affect the Warranty Period, if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of the existing GIS bay, including required


modifications in the existing GIS bay along with Local Control Panels including
indicating meters in the local control Panels, inscription of additional alarm facia as
required, replacing of GIS name plates and any required works including, wiring,
testing & complete re-commissioning of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes to 1x132kV Cable feeder in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 208 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

One 1x132kV existing bays to be connected to Jeryan Jenaihat 1 substation are with
Protection Relays/Equipments under GTC/240A/2008 Phase-9 project.

The relay provided at Jeryan Jenaihat Super for Main-1 protection is Siemens
make 7SD52 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Jeryan Jenaihat 1 substation should match the
protection at 132kV Jeryan Jenaihat Super Substation end (supplied under Phase9 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT AL KHISSA WEST S/S


132/11kV Al Khissa West is an existing substation with 132kV GIS and 11kV Switchgear
built by Siemens under Phase 10 Project. Al Khissa West will be connected to Jeryan
Jenaihat 1 by diverting (LILO) the existing 1x132kV, Single Circuit, Jeryan Jenaihat Super
Al Khissa West into Jeryan Jenaihat 1. All modifications, End to End test, testing and
commissioning and putting into service of the two circuits required shall be carried out
under the scope of this project. Modification works at Al Khissa West shall be arranged in
a way not to affect the Warranty Period, if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of the existing GIS bay, including required


modifications in the existing GIS bays along with Local Control Panels including
indicating meters in the local control Panels, inscription of additional alarm facia as
required, replacing of GIS name plates and any required works including, wiring,
testing & complete re-commissioning of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS of Siemens make installed under Phase 10 project


to include changes to 1x132kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 209 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Protection
One 1x132kV existing bay to be connected to Jeryan Jenaihat 1 substation are with
Protection Relays/Equipments under GTC/371/2010 Phase-10 project.

The relay provided at Al Khissa West feeder to be connected to Jeryan Jenaihat 1


for Main-1 protection is Siemens make 7SD52 and for Main-2 Protection is ABB
make RED 670.

The new Relays/Equipment to be installed at Jeryan Jenaihat 1 substation should


match the protection at 132kV Al Khissa West Substation end (supplied under
Phase-10 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 210 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S7

3.7

3.7.1

66/11KV NEW DOHA E SUBSTATION (REPLACEMENT)


New Doha E is new substation to be installed in a multi-storey building consisting of
substation (occupying ground and first floor) and Car Parking (other floors). New 66/11kV
substation is intended to replace the existing 66/11kV substation.
The Contractor scope covers construction of the complete multi-storey building and
substation as detailed below including design, obtaining Building Permit, all civil
construction works and building services. QCS 2014 and other relevant standards shall be
applicable for the multistory building. The car park design shall comply with open parking
structure. Standard Kahramaa specifications shall be used for the substation itself.
New Doha E S/S will be connected to network:

by looping in looping out (LILO) existing 66kV single cable circuit from West Bay
Super 2 New Doha A Super into New Doha E S/S,
by diverting the existing single cable circuit from West Bay Super 2 from the
existing 66kV GIS into new 66kV GIS at New Doha E and
by diverting the existing single cable circuit from New Doha A Super from the
existing 66kV GIS into new 66kV GIS at New Doha E.

The principal elements of new 66/11kV New Doha E substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish two 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the following:

11kV switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 211 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bays for future Capacitor bank;


- Space for four future bays, two on each side of the 11kV switchgear.

11kV switchgear B:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.

Alternatively, 11kV GIS is also acceptable.


 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to New Doha A Super and West Bay Super 2 substations. The new
relays to be installed at 66/11kV New Doha E substation shall match the protection
at New Doha A Super and West Bay Super 2 substation end.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 212 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- Partial discharge online monitoring system for 66kV GIS;
- Online condition monitoring system for new 66/11kV, 40MVA power
transformers.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
 Parking Management System
 Civil works

All civil works related to new multi-storey building, 66/11kV substation including
building services, as per relevant specification and drawings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 213 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The substation building shall also be provided with the rooms for the future 11kV
Capacitor Banks, as shown in the layout drawing.

Necessary number of sleeves for all outgoing feeders shall be provided on the
substation building and boundary wall

Outgoing feeder cable routing (66kV and 11kV) inside the basement to be
proposed by the contractor to facilitate convenient installation of future cables
upon requirement.

Independent Fire Fighting System for the multi-storey car parking building shall be
provided including Fire Pumping Station, Fire Pumps & Controllers, Fire Water
Tank, Fire Alarm & Detection System, Fire Hose Reels with cabinets/all
accessories, Dry Riser System and other necessary systems in accordance with
QCDD requirements.

Smoke Control System (Means of Escape & Means of Egress - Exit Access, Exitsstaircases/elevator shafts & exit discharge shall be pressurized) as per the QCDD
requirements & relevant NFPA standards.

 66kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Transformer Explosion Prevention System for Power Transformers.

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 214 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits listed below shall be diverted into the New Doha E substation
under the present Scope of Work:

LILO of the 1 x 66kV New Doha A Super and West Bay Super 2,

1 x 66kV New Doha A Super from the existing 66kV GIS and

1 x 66kV West Bay Super 2 from the existing 66kV GIS.

The substation Contractor should make all necessary arrangements to connect cable
circuits at New Doha E substation. The Contractor shall be responsible to maintain
rating of the existing circuits after diversion.

Diversion (Loop in / Loop out) of existing 66kV, 1x1600mm2, XLPE, 120MVA


underground cable line with fiber optic cable (24 Fibers) between New Doha A
Super and West Bay Super 2 into New Doha E S/S. Approximate route length:
500m. The Contractor shall include all necessary modification works and
equipment including all link boxes and earth continuity conductors in the earthing
arrangement (cross bonding, single point bonding or mixed bonding) in order to
ensure that required current rating of diverted circuit is maintained. Necessary

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 215 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

details, schematic drawings etc., with accurate lengths shall be submitted for
approval during detailed engineering stage. The terminations shall be 66kV GIS
type in New Doha E S/S and cable joints at diversion point. Refer to drawing No.
TRANS-52-2014. The circuits are under installation under Phase 11 project.

Diversion of the existing 66kV, 1x1600mm2, XLPE, 120MVA, single circuit,


from the existing 66kV GIS into new 66kV GIS, connected to New Doha A Super
S/S, laid in unfilled concrete troughs with all accessories. Approx. route length:
100m. Existing 2 x 66kV cables between New Doha A Super and West Bay Super
2 are laid under phase 7 project (GTC124D/2006) by M/s Saudi Cable and one
circuit is LILO into existing New Doha E under Phase 11 project.

Diversion of the existing 66kV, 1x1600mm2, XLPE, 120MVA, single circuit,


from the existing 66kV GIS into new 66kV GIS, connected to West Bay Super 2
S/S, laid in unfilled concrete troughs with all accessories. Approx. route length:
100m. Existing 2 x 66kV cables between New Doha A Super and West Bay Super
2 are laid under phase 7 project (GTC124D/2006) by M/s Saudi Cable and one
circuit is LILO into existing New Doha E under Phase 11 project.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Requirement for Kahramaa distribution S/S:

Contractor shall coordinate with Kahramaa distribution department to get approval


on starting a new project, called a new scheme, required for construction of
Kahramaa distribution S/S.

Contractor shall work in close coordination with Kahramaa distribution department


to get approval for the work and get the material required for completing the work.

For the subject work Contractors scope of work is:

Supply and installation of Two (2) Nos. Transformers 11/0.415kV, of 1000kVA


rating, complete with current transformer on high voltage side with 11 kV air filled
cable box. These transformers shall be for connection to LVAC switchboard for
purpose of power supply to car park building.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and 11/0.415, 1000kVA transformers. Approx.
route length: 30m.

Supply and installation of LVAC switchboard which will be used for power supply to
car park building. The contractor shall provide necessary equipment such as
distribution boards, LV cables, etc. and complete the works as specified and
required..

Supply and installation of 415V cables between 11/0.415kV transformer and LVAC
switchboard.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 216 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Supply & Installation of other required equipment and materials such as battery
chargers, batteries and any other materials as required for the completeness of the
work as per the scheme approved by Kahramaa distribution department ).

 Sequence of Construction Works

Milestone A
Complete Substation, LILO of the existing 66kV cable line New Doha A Super and
West Bay Super 2 into New Doha E S/S and the remote end works at New Doha A
Super and West Bay Super 2 S/Ss.

Milestone B
Divert the cables from the existing 66kV GIS into the new 66kV GIS and the
corresponding remote end works.

 REMOTE END WORKS AT NEW DOHA A SUPER S/S


220/66/11kV New Doha A Super is an existing 220/66/11kV substation with 220kV GIS,
66kV GIS and 11kV Switchgear built by Siemens under Phase 11 Project. New Doha A
Super will be connected to New Doha E by diverting (LILO) of the existing 1x66kV, Single
Circuit, New Doha A Super and West Bay Super 2 into New Doha E and using the existing
1x66kV, Single Circuit, New Doha A Super New Doha E. All modifications, End to End
test, testing and commissioning and putting into service of the two circuits required shall
be carried out under the scope of this project. Modification works at New Doha A Super
shall be arranged in a way not to affect the Warranty Period, if still valid at the time of new
works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 11 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 217 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two 2x66kV existing bays to be connected to New Doha E substation are with Protection
Relays/Equipments under GTC/488B/2006 Phase-11 project.

The relay provided at New Doha A Super are provided under phase 11 project.
The new Relays/Equipment to be installed at New Doha E substation should match
the protection at 66kV New Doha A Super Substation end (supplied under Phase11 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT WEST BAY SUPER 2 S/S


220/66/11kV West Bay Super 2 is an existing substation with 220kV GIS, 66kV GIS and
11kV Switchgear built by Siemens under Phase 7 Project. West Bay Super 2 will be
connected to New Doha E by diverting (LILO) of the existing 1x66kV, New Doha A Super
and West Bay Super 2 cable circuit into New Doha E and using the existing 1x66kV, West
Bay Super 2 New Doha E. All required modifications, End to End test, testing and
commissioning and putting into service of the two circuits shall be carried out under the
scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 7 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 218 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Protection
Two 2x66kV existing bays to be connected to New Doha E substation are with Protection
Relays/Equipments under GTC/488B/2006 Phase-11 project.

3.7.2

The relay provided at West Bay Super 2 feeder connected to New Doha E for Main
protection relays will be replaced during phase 11 project to match protection
equipment at New Doha A Super.

The relay provided at West Bay Super 2 feeder connected to New Doha A Super
for Main-1 protection is Siemens make 7SD5 and for Main-2 Protection is ABB
make RED670.

The new Relays/Equipment to be installed at New Doha E substation should match


the protection at 66kV West Bay Super 2 Substation end (supplied under Phase-11
project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

66/11KV SALATA SUBSTATION (REPLACEMENT)


Salata is new substation to be installed in a multi-storey building consisting of substation
(occupying ground and first floor) and Car Parking (other floors). New 66/11kV substation
is intended to replace the existing 66/11kV substation.
The Contractor scope covers construction of the complete multi-storey building and
substation as detailed below including design, obtaining Building Permit, all civil
construction works and building services. QCS 2014 and other relevant standards shall be
applicable for the multistory building. The car park design shall comply with open parking
structure. Standard Kahramaa specifications shall be used for the substation itself.
Salata S/S will be connected to network by double cable circuits from Museum Road
substation under this project and by diverting the existing cable circuits from (from the
existing 66kV Switchgear to the new 66kV GIS at Salata) Khalifat S/S.
The principal elements of new 66/11kV Salata substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 219 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bus section bays;


- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.

Alternatively, 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation, with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 220 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Khalifat substation. The new relays to be installed at 66/11kV Salata
substation shall match the protection at Khalifat substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- Partial discharge online monitoring system for 66kV GIS;
- Online condition monitoring system for new 66/11kV, 40MVA power
transformers.
- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories.
 Security Management System according to specification enclosed in section 3.3.15.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 221 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Parking Management System


 Civil works

All civil works related to new multi-storey building, 66/11kV substation including
building services, as per relevant specification and drawings.

The substation building shall also be provided with the rooms for the future 11kV
Capacitor Banks, as shown in the layout drawing.

Necessary number of sleeves for all outgoing feeders shall be provided on the
substation building and boundary wall

Outgoing feeder cable routing (66kV and 11kV) inside the basement to be
proposed by the contractor to facilitate convenient installation of future cables
upon requirement.

Independent Fire Fighting System for the multi-storey car parking building shall be
provided including Fire Pumping Station, Fire Pumps & Controllers, Fire Water
Tank, Fire Alarm & Detection System, Fire Hose Reels with cabinets/all
accessories, Dry Riser System and other necessary systems in accordance with
QCDD requirements.

Smoke Control System (Means of Escape & Means of Egress - Exit Access, Exitsstaircases/elevator shafts & exit discharge shall be pressurized) as per the QCDD
requirements & relevant NFPA standards.

 66kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Transformer Explosion Prevention System for the Power Transformers.

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 222 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:
 66kV, 1x2000mm, XLPE, 120MVA, double circuit, single point bonding
system underground cable line between Salata and Museum Road S/S. Each
circuit shall be provided with its own Fiber Optic cable (48 Fibers) with all
accessories. Approx. route length: 0.5km. Necessary details, schematic drawings
etc., with accurate lengths shall be submitted for approval during detailed
engineering stage. The termination is GIS at Salata S/S and GIS at Museum Road
S/S (upgrade under GTC/735/20015 package 6). Refer to attached drawing no.
TRANS-112-2014.

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Modification of Existing Cables


Existing cable circuits from Khalifat substation shall be diverted from the existing
Switchgear into the new GIS at Salata substation under the present Scope of Work.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 223 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The substation Contractor should make all necessary arrangements to connect cable
circuits at new GIS at Salata substation. The Contractor shall be responsible to
maintain rating of the existing circuits after diversion.

Diversion of the existing 66kV, 1x630mm2, XLPE, 60MVA, double circuit, from
the existing 66kV GIS into new 66kV GIS, connected to Khalifat S/S, laid in unfilled
concrete troughs with all accessories and communication cables. Approx. route
length: 500m. Existing cables are diverted under phase 9 project from the GIS at
old Khalifat S/S into new GIS by M/s Siemens. Refer to attached drawing No.
TRANS-113-2014.

All labels related to Power and fiber optic cables (within existing substations and
along cable route) shall be replaced based on new connection scheme after
diversion.

 Requirement for KM distribution S/S:

Contractor shall coordinate with Kahramaa distribution department to get approval


on starting a new project, called a new scheme, required for construction of
Kahramaa distribution S/S.

Contractor shall work in close coordination with Kahramaa distribution department


to get approval for the work and get the material required for completing the work.

For the subject work Contractors scope of work is:

Supply and installation of Two (2) Nos. Transformers 11/0.415kV, of 1000kVA


rating, complete with current transformer on high voltage side with 11 kV air filled
cable box. These transformers shall be for connection to LVAC switchboard for
purpose of power supply to car park building.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and 11/0.415, 1000kVA transformers. Approx.
route length: 30m.

Supply and installation of LVAC switchboard which will be used for power supply to
car park building. The contractor shall provide necessary equipment such as
distribution boards, LV cables, etc. and complete the works as specified and
required.

Supply and installation of 415V cables between 11/0.415kV transformer and LVAC
switchboard.

Supply & Installation of other required equipment and materials such as battery
chargers, batteries and any other materials as required for the completeness of the
work as per the scheme approved by Kahramaa distribution department ).

 REMOTE END WORKS AT KHALIFAT S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 224 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66/11kV Khalifat is an existing substation with 66kV GIS and 11kV Switchgear built by
Siemens under Phase 9 Project. Khalifat will be connected to Salata substation by
diverting the existing 2x66kV, Khalifat Salata cable circuits into new 66kV GIS. All
required modifications, End to End test, testing and commissioning and putting into
service of the two circuits shall be carried out under the scope of this project.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing GIS bays,


including required modifications in the existing GIS bays along with Local Control
Panels including indicating meters in the local control Panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
Two 2x66kV existing bays to be connected to Salata substation are with Protection
Relays/Equipments under GTC/240D/2008 Phase-9 project.

The relay provided at Khalifat for Main-1 protection is Siemens make 7SD5 and for
Main-2 Protection is ABB make RED670. The new Relays/Equipment to be
installed at Salata substation should match the protection at 66kV Khalifat
Substation end (supplied under Phase-9 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 REMOTE END WORKS AT MUSEUM ROAD S/S


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 225 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Museum Road is an existing 66/11kV substation which will be upgraded under Package
(S-6) in this project. The Museum Road Substation will be connected to Salata Substation
with 2x66kV Cable circuit. The cables will be installed by a cable contractor under
separate contract. The substation Contractor shall coordinate with cable contractor and
Museum Road substation Contractor for the successful completion of all necessary works
for putting these feeders into service including end to end test, overall stability, coordination with NCC, SCS modification, etc. All contractors shall mutually agree and coordinate the activities. In case of any disputes in this regard, Kahramaa decision will be
final.

2x66 feeder bays at Salata substation will be connected by 2x66kV cable circuits to
Museum Road substation. All the required works at New Museum Road substation
shall be carried out under S6 package.

All protection coordination work with S6 package contractor including testing and
commissioning, relay testing on final setting, end to end test, overall stability and
putting in service are included in the present Scope.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 226 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S8

3.8

3.8.1

132/11KV MASHAF 1 SUBSTATION


132/11kV Mashaf 1 substation is intended to cater power supply for the new growing
demand of Mashaf area. Mashaf 1 S/S will be connected to network by 132kV double
circuit cable from RAF South and Mashaf 2 substations. Both cable circuits will be installed
under separate Contract (GTC/736/2015, Package C7).
The principal elements of new 132/11kV Mashaf 1 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 227 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to RAF South substation. The new relays to be installed at 132/11kV
Mashaf 1 substation shall match the protection at RAF South substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 228 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- 40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 229 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT RAF SOUTH S/S


132/11kV RAF South is a new Substation, being under constructed under Phase 12
Project. Mashaf 1 shall be connected to RAF South by double circuit 132kV Cable lines.
All modifications, End to End test, testing and commissioning and putting into service of
two circuits shall be carried out under the scope of this project. Modification works at RAF
South shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 230 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 2x132kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

2x132kV existing bays to be connected to Mashaf 1 Substation are with Protection


Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Mashaf 1 substation should
match the protection at 132kV RAF South Substation end (supplied under Phase12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Mashaf-2 Remote End S/S Works:


The remote end substation, Mashaf-2, is also to be built under the same package and will
be connected to the new Mashaf-1 S/S with 2x132kV cable circuits. The cables will be
installed under separate contract (GTC/736/2015, Package C7). The substation contractor
shall coordinate with cable contractor and complete all necessary works for putting these
feeders into service.

3.8.2

132/11KV MASHAF 2 SUBSTATION


132/11kV Mashaf 2 substation is intended to cater power supply for the new growing
demand of Mashaf area. Mashaf 2 S/S will be connected to network by single 132kV cable

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 231 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

circuits from Mashaf 3 and Al Wukair 10 substations and by 132kV double cable circuits
from Mashaf 1 substation. The cable circuits will be installed under separate Contract
(GTC/736/2015, Package C7).
The principal elements of new 132/11kV Mashaf 2 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 232 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 233 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 234 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Mashaf-1, 3 & Al Wukair-10 Remote End S/S Works:


The remote end substations, Mashaf-1, 3 & Al Wukair-10 are also to be built under the
same package and will be connected to the new Mashaf-1 S/S with 132kV cable circuits.
The cables will be installed under separate contract (GTC/736/2015, Package C7). The
substation contractor shall coordinate with cable contractor and complete all necessary
works for putting these feeders into service.

3.8.3

132/11KV MASHAF 3 SUBSTATION


132/11kV Mashaf 3 substation is to cater power supply for the new growing demand of
Mashaf area. Mashaf 3 S/S will be connected to network by single 132kV cable circuit
from Mashaf 2 and from Bul Hemmaid substations. The cable circuits will be installed
under separate Contract (GTC/736/2015, Package C7).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 235 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The principal elements of new 132/11kV Mashaf 3 substation shall be as follows:


 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 236 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.
 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substation. The new relays to be installed at 132/11kV
Mashaf 3 substation shall match the protection at Bul Hemmaid substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 237 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS& Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 238 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

openings such as panel openings including future openings, cable sleeve/duct


openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT BUL HEMMAID S/S


400/132/11kV Bul Hemmaid is a new Substation, being constructed under Phase 12
Project. Mashaf 3 shall be connected to Bul Hemmaid by single circuit 132kV Cable line.
All modifications, End to End test, testing and commissioning and putting into service of
the circuit shall be carried out under the scope of this project. Modification works at Bul
Hemmaid shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of the existing switchgear bay, including


required modifications in the existing switchgear bays along with Local Control
Panels including Indicating Meters in the Local Control Panels, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 239 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeder in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to Mashaf 3 Substation are with Protection


Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Mashaf 3 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Mashaf-2 Remote End S/S Works:


The remote end substation, Mashaf-2, is also to be built under the same package and will
be connected to the new Mashaf-3 S/S with 1x132kV cable circuit. The cables will be
installed under separate contract (GTC/736/2015, Package C7). The substation contractor
shall coordinate with cable contractor and complete all necessary works for putting these
feeders into service.

3.8.4

132/11KV AL WUKAIR 10 SUBSTATION


132/11kV Al Wukair 10 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 10 S/S will be connected to network by single 132kV
cable circuit from Mashaf 2 and from Bul Hemmaid substations. The cable circuits will be
installed under separate Contract (GTC/736/2015, Package C7).
The principal elements of new 132/11kV Al Wukair 10 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 240 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 241 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substations. The new relays to be installed at
132/11kV Al Wukair 10 substation shall match the protection at Bul Hemmaid
substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 242 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 243 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT BUL HEMMAID S/S


400/132/11kV Bul Hemmaid is a new Substation, being constructed under Phase 12
Project. Al Wukair 10 shall be connected to Bul Hemmaid by single circuit 132kV Cable
line.
All modifications, End to End test, testing and commissioning and putting into service of
the circuit shall be carried out under the scope of this project. Modification works at Bul
Hemmaid shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of the existing switchgear bay, including


required modifications in the existing switchgear bays along with Local Control
Panels including Indicating Meters in the Local Control Panels, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 244 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeder in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to Al Wukair 10 Substation are with


Protection Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 10 substation
should match the protection at 132kV Bul Hemmaid Substation end (supplied
under Phase-12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Mashaf-2 Remote End S/S Works:


The remote end substation, Mashaf-2, is also to be built under the same package and will
be connected to the new Al Wukair-10 S/S with 1x132kV cable circuit. The cables will be
installed under separate contract (GTC/736/2015, Package C7). The substation contractor
shall coordinate with cable contractor and complete all necessary works for putting these
feeders into service.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 245 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S9

3.9

3.9.1

132/11KV AL WUKAIR 9 SUBSTATION


132/11kV Al Wukair 9 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 9 S/S will be connected to network by single 132kV
cable circuit from Al Wukair 8 and from Bul Hemmaid substations. The cable circuits will
be installed under separate Contract (GTC/736/2015, Package C8).
The principal elements of new 132/11kV Al Wukair 9 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 246 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substations. The new relays to be installed at
132/11kV Al Wukair 9 substation shall match the protection at Bul Hemmaid
substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 247 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 248 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT BUL HEMAID S/S


400/132/11kV Bul Hemmaid is a new Substation, being constructed under Phase 12
Project. Al Wukair 10 shall be connected to Bul Hemmaid by single circuit 132kV Cable
line.
All modifications, End to End test, testing and commissioning and putting into service of
the circuit shall be carried out under the scope of this project. Modification works at Bul
Hemmaid shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 249 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Re-testing and Re-commissioning of the existing switchgear bay, including


required modifications in the existing switchgear bays along with Local Control
Panels including Indicating Meters in the Local Control Panels, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeder in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to Al Wukair 9 Substation are with


Protection Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 9 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Al Wukair-8 Remote End S/S Works:


The remote end substation, Al Wukair-8, is also to be built under the same package and
will be connected to the new Al Wukair-9 S/S with 1x132kV cable circuit. The cables will
be installed under separate contract (GTC/736/2015, Package C8). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 250 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.9.2

REV. 0

132/11KV AL WUKAIR 8 SUBSTATION


132/11kV Al Wukair 8 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 8 S/S will be connected to network by single 132kV
cable circuits from Al Wukair 6, Al Wukair 9 and Bul Hemmaid substations. The cable
circuits will be installed under separate Contract (GTC/736/2015, Package C8).
The principal elements of new 132/11kV Al Wukair 8 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (three (3) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 251 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substation. The new relays to be installed at 132/11kV
Al Wukair 8 substation shall match the protection at Bul Hemmaid substation ends.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 252 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- 40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 253 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT BUL HEMAID S/S


400/132/11kV Bul Hemmaid is a new Substation, being constructed under Phase 12
Project. Al Wukair 8 shall be connected to Bul Hemmaid by single circuit 132kV Cable
Line.
All modifications, End to End test, testing and commissioning and putting into service of
the circuit shall be carried out under the scope of this project. Modification works at Bul
Hemmaid shall be arranged in a way not to affect the Warranty Period.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 254 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of the existing switchgear bay, including


required modifications in the existing switchgear bays along with Local Control
Panels including Indicating Meters in the Local Control Panels, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeder in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to Al Wukair 8 Substation are with


Protection Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 8 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Al Wukair-6 & 9 Remote End S/S Works:


The remote end substations, Al Wukair-6 & 9, are also to be built under the same package
and will be connected to the new Al Wukair-8 S/S with 1x132kV cable circuits. The cables
will be installed under separate contract (GTC/736/2015, Package C8). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 255 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.9.3

REV. 0

132/11KV AL WUKAIR 7 SUBSTATION


132/11kV Al Wukair 7 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 7 S/S will be connected to network by single 132kV
cable circuit from Al Wukair 6 and from Bul Hemmaid substations. The cable circuits will
be installed under separate Contract (GTC/736/2015, Package C8).
The principal elements of new 132/11kV Al Wukair 7 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 256 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Bul Hemmaid substations. The new relays to be installed at
132/11kV Al Wukair 7 substation shall match the protection at Bul Hemmaid
substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 257 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 258 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT BUL HEMAID S/S


400/132/11kV Bul Hemmaid is a new Substation being constructed under Phase 12
Project. Al Wukair 7 shall be connected to Bul Hemaid by single circuit 132kV Cable Line.
All modifications, End to End test, testing and commissioning and putting into service of
the circuit shall be carried out under the scope of this project. Modification works at Bul
Hemmaid shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 259 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Re-testing and Re-commissioning of the existing switchgear bay, including


required modifications in the existing switchgear bays along with Local Control
Panels including Indicating Meters in the Local Control Panels, inscription of
additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under Phase 12 project to include


changes to 1x132kV Cable feeder in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

1x132kV existing bays to be connected to Al Wukair 7 Substation are with


Protection Relays/Equipments under Phase-12 Project.

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 7 substation should
match the protection at 132kV Bul Hemmaid Substation end (supplied under
Phase-12 project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Al Wukair-6 Remote End S/S Works:


The remote end substation, Al Wukair-6, is also to be built under the same package and
will be connected to the new Al Wukair-7 S/S with 1x132kV cable circuit. The cables will
be installed under separate contract (GTC/736/2015, Package C8). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.

3.9.4

132/11KV AL WUKAIR 6 SUBSTATION


132/11kV Al Wukair 6 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 6 S/S will be connected to network by single 132kV

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 260 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

cable circuits from Al Wukair 7, Al Wukair 8 and Al Wukair 5 substations. The cable
circuits will installed under separate Contract (GTC/736/2015, Package C8 and C9).
The principal elements of new 132/11kV Al Wukair 6 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (three (3) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 261 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 262 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 263 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END works at Al Wukair 5


Al Wukair-5 is a new 132/11kV substation which will be constructed under separate
package (S-10) in this project. The Al Wukair-6 Substation will be connected to Al Wukair5 Substation with 1x132kV Cable circuit. The cables will be installed by a cable contractor
under separate contract. The substation Contractor shall coordinate with cable contractor
and Al Wukair-5 substation Contractor for the successful completion of all necessary
works for putting these feeders into service including end to end test, overall stability, coordination with NCC, SCS modification, etc. All contractors shall mutually agree and coordinate the activities. In case of any disputes in this regard, Kahramaa decision will be
final.
 Al Wukair-7 & 8 Remote End S/S Works:
The remote end substations, Al Wukair - 7 & 8, are also to be built under the same
package and will be connected to the new Al Wukair-6 S/S with 1x132kV cable circuit. The
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 264 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

cables will be installed under separate contract (GTC/736/2015, Package C8). The
substation contractor shall coordinate with cable contractor and complete all necessary
works for putting these feeders into service.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 265 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S10

3.10

3.10.1

132/11KV AL WUKAIR 5 SUBSTATION


132/11kV Al Wukair 5 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 5 S/S will be connected to network by double 132kV
cable circuit from Al Wukair 4 and by single 132kV cable circuits from Al Wukair 2, Al
Wukair 3 and Al Wukair 6 substations. The cable circuits will be installed under separate
Contract (GTC/736/2015, Package C9).
The principal elements of new 132/11kV Al Wukair 5 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (one (1) No. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 266 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 267 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 268 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END works at Al Wukair 6


Al Wukair-6 is a new 132/11kV substation which will be constructed under separate
package (S-9) in this project. The Al Wukair-5 Substation will be connected to Al Wukair-6
Substation with 1x132kV Cable circuit. The cables will be installed by a cable contractor
under separate contract. The substation Contractor shall coordinate with cable contractor
and Al Wukair-6 substation Contractor for the successful completion of all necessary
works for putting these feeders into service including end to end test, overall stability, coordination with NCC, SCS modification, etc. All contractors shall mutually agree and coordinate the activities. In case of any disputes in this regard, Kahramaa decision will be
final.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 269 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Al Wukair-2, 3 & 4 Remote End S/S Works:


The remote end substations, Al Wukair-2, 3 & 4, are also to be built under the same
package and will be connected to the new Al Wukair-5 S/S with 132kV cable circuits. The
cables will be installed under separate contract (GTC/736/2015, Package C9). The
substation contractor shall coordinate with cable contractor and complete all necessary
works for putting these feeders into service.

3.10.2

132/11KV AL WUKAIR 4 SUBSTATION


132/11kV Al Wukair 4 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 4 S/S will be connected to network by double 132kV
cable circuits from Al Wukair 5 and 132kV FACILITY D (QEZ-3) substations under
separate Contract (GTC/736/2015, Package C9).
The principal elements of new 132/11kV Al Wukair 4 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Four (4) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish two 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal
enclosed switchgears with vacuum circuit breakers, consisting of the following:

Switchgear A:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.

Switchgear B:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 270 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- One (1) No. Bus section bay rated 2500A;


- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Four (4) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to 132kV FACILITY D substation. The new relays to be installed at
132/11kV Al Wukair 4 substation shall match the protection at 132kV FACILITY D
substation ends.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 271 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 272 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 132kV GIS & Fire Pump room Cranes


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between
132/11kV Power Transformers and 11kV switchgear, laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 273 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests,. Cables and terminations will be
supplied by Kahramaa. Contractor shall coordinate with concerned Kahramaa
department.

 REMOTE END WORKS AT 132kV FACILITY D (QEZ 3) S/S


Facility D is a new generation project including 400kV, 220kV and 132kV Gas insulated
switchgear being constructed under IWPP project. The Facility D IWPP Substation with
400kV GIS shall be owned, operated and maintained by the IWPP. 220kV and 132kV GIS
shall be owned, operated and maintained by Kahramaa and will be connected to the Al
Wukair 4 S/S by double circuit 132kV Cable line.
All modifications, End to End test, testing and commissioning and putting into service of
two circuits shall be carried out under the scope of this project. Modification works at QEZ
3 shall be arranged in a way not to affect the Warranty Period.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of two numbers of the existing switchgear bays,


including required modifications in the existing switchgear bays along with Local
Control Panels including Indicating Meters in the Local Control Panels, inscription
of additional Alarm facia as required, replacing of Switchgear Name plates and any
required works including, wiring, testing & complete re-commissioning of the above
switchgear bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS to be supplied under IWPP project to include changes


to 2x132kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:

2x132kV existing bays to be connected to Al Wukair 4 Substation are with


Protection Relays/Equipments under IWPP Project.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 274 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these circuits is included in the Present
Scope. The new Relays/Equipment to be installed at Al Wukair 4 substation should
match the protection at 132kV Facility D Substation end (supplied under IWPP
project).

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

 Al Wukair-5 Remote End S/S Works:


The remote end substation, Al Wukair-5, is also to be built under the same package and
will be connected to the new Al Wukair-4 S/S with 2x132kV cable circuits. The cables will
be installed under separate contract (GTC/736/2015, Package C9). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.

3.10.3

132/11KV AL WUKAIR 3 SUBSTATION


132/11kV Al Wukair 3 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 3 S/S will be connected to network by single 132kV
cable circuit from Al Wukair 2 and from Al Wukair 5 substations. The cable circuits will be
installed under separate Contract (GTC/736/2015, Package C9).
The principal elements of new 132/11kV Al Wukair 3 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
- One (1) No. Bus section bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Four (4) Nos. Cable feeder bays (two (2) Nos. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 275 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;


- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 276 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 277 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 278 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
Al Wukair-2 & 5 Remote End S/S Works

The remote end substations, Al Wukair-2 & 5, are also to be built under the same package
and will be connected to the new Al Wukair-3 S/S with 1x132kV cable circuits. The cables
will be installed under separate contract (GTC/736/2015, Package C9). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.

3.10.4

132/11KV AL WUKAIR 2 SUBSTATION


132/11kV Al Wukair 2 substation is intended to cater power supply for the new growing
demand of Al Wukair area. Al Wukair 2 S/S will be connected to network by single 132kV
cable circuits from Al Wukair 1, Al Wukair 3 and Al Wukair 5 substations. The cable
circuits will be installed under separate Contract (GTC/736/2015, Package C9).
The principal elements of new 132/11kV Al Wukair 2 substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays (three (3) No. spare);
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 279 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Eighteen (18) Nos. Outgoing feeder bays rated 630A;


- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Two (2) Nos. Bays for future Capacitor bank;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the present total
load of the substation with additional capacity of 30%. The capacity of the
Transformer is to be justified by calculation note which shall be subject to
approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 280 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 281 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 282 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT AL WUKAIR 1 S/S


132/11kV AL WUKAIR 1 is an existing substation with 132kV and 11kV Switchgear built by
Siemens under Phase 11 Project. AL WUKAIR 1 will be connected to AL WUKAIR 2 by
single 132kV cable circuit. All required modifications, End to End test, testing and
commissioning and putting into service of the one circuit shall be carried out under the
scope of this project. Modification works at AL WUKAIR 1 shall be arranged in a way not
to affect the Warranty Period, if still valid at the time of new works.
The SOW includes but is not limited to the following:

Re-testing and Re-commissioning of one number of the existing GIS bay, including
required modifications in the existing GIS bays along with Local Control Panels
including indicating meters in the local control Panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bay.

Protection and SCS systems as detailed below:

 SCS and Power Control Scope

Required Modifications to SCS supplied by Siemens under Phase 11 project to


include changes to 1x132kV Cable feeders in the SCS including Gateway data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and alarms related to modifications are
to be included in the SCS.

 Protection
One 1x132kV existing bay to be connected to AL WUKAIR 2 are with Protection
Relays/Equipments under GTC/488C Phase-11 project.

The relays provided at AL WUKAIR 1 are provided under phase 11 projects. The
new Relays/Equipment to be installed at AL WUKAIR 2 substation should match
the protection at 132kV AL WUKAIR 1 Substation end (supplied under Phase-11
project).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 283 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for breaker failure, gas pressure low and bus bar protection
operation are to be made available between the stations based on requirement.

 Al Wukair-3, & 5 Remote End S/S Works:


The remote end substations, Al Wukair-3 & 5, are also to be built under the same package
and will be connected to the new Al Wukair-2 S/S with 1x132kV cable circuits. The cables
will be installed under separate contract (GTC/736/2015, Package C9). The substation
contractor shall coordinate with cable contractor and complete all necessary works for
putting these feeders into service.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 284 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S11

3.11

3.11.1

66/11KV ABU HAMOUR WEST S/S


66/11kV Abu Hamour West is a new 66/11kV Transmission Substation to be constructed
to meet the Power supply requirements in Abu Hamour area. The new 66/11kV Abu
Hamour West substation will be fed by 2x66kV cables from the existing Al Wadi West
substation. The cable circuits will be installed under separate Contract (GTC/736/2015,
Package C10).
The principal elements of 66/11kV Abu Hamour West Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Nos. Bus Section bays;

Two (2) Nos. Bus Coupler bays;

Two (2) Nos. Outgoing Transformer bays for 66/11 kV;

Four (4) Nos. Outgoing feeder bays (2 spare);

Space for four future bays, two on each side of the switchgear.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

One (1) No. Bus section bay rated 2500A;

Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;

Eighteen (18) Nos. Outgoing feeder bays rated 630A;

Two (2) Nos. Bays for future capacitor bank;

Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;

Space for four future bays, two on each side of the 11kV switchgear.

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 285 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C rated
for 750A for 30 seconds (including NER monitoring system) for earthing the neutral
of 66/11kV 32/40MVA Power Transformer.

Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Al Wadi West substation. The new relays to be installed at 66/11kV
Abu Hamour West substation shall match the protection at Al Wadi West
substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

Separate panel shall be provided for each one of the 11kV incomer bays and each
one of the Auxiliary Transformer bays. Separate load shedding panel shall be
provided for 11kV outgoing feeders of each bus, i.e., for a two bus substation there
shall be two load shedding panels.

 SCS & Associated Equipment


Substation Control System Including Gateway data mapping to NCC/ENCC/DCC
and s/s works necessary for NCC/ENCC/DCC End to End testing.
 Online Monitoring System

Condition monitoring system comprising of:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 286 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment with all accessories
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 132/11kV substation including building services,
 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 287 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment


 Power Cables:

66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT AL WADI WEST SUBSTATION:


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 288 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66/11kV Al Wadi West Substation is an existing substation constructed by M/s Hyosung


under Phase 10 project. The new Abu Hamour West Substation will be connected to Al
Wadi West Substation with 2 x 66kV Cables. The cables will be installed by a cable
contractor under separate contract.
All the required modifications at Al Wadi West substation shall be carried out under the
present scope of work.

Re-testing and re-commissioning of the GIS bays along with Local Control Panels
including indicating meters in the local control panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS of Siemens make supplied by NCC under Phase 10


project to include changes to 2x66kV Cable feeders in the SCS including Gateway
Data mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to
End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:
2x66kV existing bays to be connected to Abu Hamour West Substation are with Protection
Relays/Equipments under Phase-10 Project.

The relay provided at Al Wadi West for Main-1 protection is Siemens make 7SD52
and for Main-2 Protection is Alstom make P545. The new Relays/Equipment to be
installed at Abu Hamour West substation should match the protection at 66kV Al
Wadi West Substation end (supplied under Phase-10 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 289 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.11.2

REV. 0

66/11KV RAWDAT AL KHAIL 2 S/S


66/11kV Rawdat Al Khail 2 is a new Transformer Feeder Substation to be constructed to
meet the Power supply requirements in surrounding area. The new 66/11kV Rawdat Al
Khail 2 substation. The cable circuits will be fed by 2x66kV cables from the existing
Rawdat Al Khail substation to be installed under the separate Contract (GTC/736/2015,
Package C10).
The principal elements of 66/11kV Rawdat Al Khail 2 Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

One (1) No. Bus section bay rated 2500A;

Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;

Eighteen (18) Nos. Outgoing feeder bays rated 630A;

Two (2) Nos. Bays for future capacitor bank;

Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;

Space for four future bays, two on each side of the 11kV switchgear.

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C rated
for 750A for 30 seconds (including NER monitoring system) for earthing the neutral
of 66/11kV 32/40MVA Power Transformer.

Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 290 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected Rawdat Al Khail substation. The new relays to be installed at 66/11kV
Rawdat Al Khail 2 substation shall match the protection at Rawdat Al Khail
substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

Separate panel shall be provided for each one of the 11kV incomer bays and each
one of the Auxiliary Transformer bays. Separate load shedding panel shall be
provided for 11kV outgoing feeders of each bus, i.e., for a two bus substation there
shall be two load shedding panels.

 SCS & Associated Equipment


Substation Control System Including Gateway data mapping to NCC/ENCC/DCC
and s/s works necessary for NCC/ENCC/DCC End to End testing.
 Online Monitoring System

Condition monitoring system comprising of:


- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

GTC-735 SCOPE OF WORKS R0

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 291 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All Civil works related to new 66/11kV substation including building services,
 Fire Pump Room Cranes
 Air-conditioning and ventilation systems to cover the switchgear and Control &
Relay buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers & Shunt Reactors. All Transformers shall be manufactured with the
necessary provision of connection points for installation of TEP System (if
Kahramaa decides to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for Transformer Yards (Power & Auxiliary), Control
& Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (MV & LV including
cable trays) for the entire length of the cable which includes also the substation
cables and all cables inside the Cable basement of all buildings including 11kV
outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 292 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power Cables:

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT RAWDAT AL KHAIL SUBSTATION:


66/11kV Rawdat Al Khail Substation is a new substation being constructed by M/s L&T
under Phase 11 project. The new Rawdat Al Khail 2 Substation will be connected to
Rawdat Al Khail Substation with 2 x 66kV Cables. The cables will be installed by a cable
contractor under separate contract.
All the required modifications at Rawdat Al Khail substation shall be carried out under the
present scope of work.

Re-testing and re-commissioning of the GIS bays along with Local Control Panels
including indicating meters in the local control panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS supplied by Siemens under Phase 11 project to include


changes to 2x66kV Cable feeders in the SCS including Gateway Data mapping to
NCC/ENCC and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:
2x66kV existing bays to be connected to Rawdat Al Khail 2 Substation are with Protection
Relays/Equipments under Phase-11 Project.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 293 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.11.3

REV. 0

The relay provided at Rawdat Al Khail for Main-1 protection is Alstom make P545
and for Main-2 Protection is Siemens make 7SD52. The new Relays/Equipment to
be installed at Rawdat Al Khail 2 substation should match the protection at 66kV
Rawdat Al Khail Substation end (supplied under Phase-11 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

66/11KV LUAIB S/S


66/11kV Luaib is a new 66/11kV Transmission Substation to be constructed to meet the
Power supply requirements in surrounding area. The new 66/11kV Luaib substation will be
fed by 2x66kV cables from the existing Mehairja Super substation. The cable circuits will
be installed under separate Contract (GTC/736/2015, Package C10).
The principal elements of 66/11kV Luaib Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Nos. Bus Section bays;

Two (2) Nos. Bus Coupler bays;

Two (2) Nos. Outgoing Transformer bays for 66/11 kV;

Six (6) Nos. Outgoing feeder bays (4 spare);

Space for four future bays, two on each side of the switchgear.

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

One (1) No. Bus section bay rated 2500A;

Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;

Eighteen (18) Nos. Outgoing feeder bays rated 630A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 294 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Bays for future capacitor bank;

Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;

Space for four future bays, two on each side of the 11kV switchgear.

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with ONAN/ONAF
cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C rated
for 750A for 30 seconds (including NER monitoring system) for earthing the neutral
of 66/11kV 32/40MVA Power Transformer.

Space for two (2) future capacitor banks along with space for vacuum contactor
panels for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all Bays) as detailed in
Main Scope of Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote end
(in line with remote end protection scope of works) shall be provided for feeders
connected to Mehairja Super substation. The new relays to be installed at 66/11kV
Luaib substation shall match the protection at Mehairja Super substation end.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the capacitor
bank bay.

Separate panel shall be provided for each one of the 11kV incomer bays and each
one of the Auxiliary Transformer bays. Separate load shedding panel shall be
provided for 11kV outgoing feeders of each bus, i.e., for a two bus substation there
shall be two load shedding panels.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 295 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS & Associated Equipment


Substation Control System Including Gateway data mapping to NCC/ENCC/DCC
and s/s works necessary for NCC/ENCC/DCC End to End testing.
 Online Monitoring System

Condition monitoring system comprising of:


- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM)
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All Civil works related to new 66/11kV substation including building services.
Note: The architectural appearance of the Substation buildings and boundary wall shall
aesthetically match with the structures in the surrounding area and is subject to approval
of concerned authorities. All design approvals in this regard shall be coordinated with the
concerned authorities.
 66kV GIS & Fire Pump room Cranes
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 296 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (MV & LV including
cable trays) for the entire length of the cable which includes also the substation
cables and all cables inside the Cable basement of all buildings including 11kV
outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment


 Power Cables:

66kV, 1x500 mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Transformers laid in unfilled concrete troughs with
all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV Power
Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20 m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 297 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) between 11kV switchgear and Auxiliary Transformers. Approx. route length:
50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 REMOTE END WORKS AT MEHAIRAJAH SUPER:


220/132/11kV Mehairja Super is a new Substation being constructed under Phase 11
Project by M/s L&T under Phase 11 project (GTC488F). The new Luaib Substation will be
connected to Mehairja Super Substation with 2 x 66kV Cables. The cables will be installed
by a cable contractor under separate contract.
All the required modifications at Mehairja Super substation shall be carried out under the
present scope of work.

Re-testing and re-commissioning of the GIS bays along with Local Control Panels
including indicating meters in the local control panels, inscription of additional
alarm facia as required, replacing of GIS name plates and any required works
including, wiring, testing & complete re-commissioning of the above GIS bays.

Protection and SCS systems as detailed below:

 SCS and Power Control:

Minor Modifications to SCS of ABB make supplied under Phase 11 project to


include changes to 2x66kV Cable feeders in the SCS including Gateway Data
mapping to NCC/ENCC and S/S works necessary for NCC/ENCC End to End
testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:
2x66kV existing bays to be connected to Luaib Substation are with Protection
Relays/Equipments under Phase-11 Project.

The relay provided at Mehairja Super for Main-1 protection is Siemens make
7SD52 and for Main-2 Protection is ABB make RED670. The new
Relays/Equipment to be installed at Luaib substation should match the protection
at 66kV Mehairja Super Substation end (supplied under Phase-11 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 298 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.11.4

REV. 0

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

33/11KV ABU SAMRA SUBSTATION (UPGRADE)


33/11kV Abu Samra substation is the existing substation built under earlier Kahramaa
projects. Existing 33/11kV transformer feeder S/S shall be upgraded by addition of the
33kV GIS. Abu Samra S/S will stay connected to Ain Hamad S/S by 33kV double OHL,
which will be diverted from the existing 33kV switchgear to 33kV GIS at Ain Hamad.
The principal elements of new 33/11kV Abu Samra substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 33kV, 2500A at 40C, 31.5kA / 1 sec, single bus bar GIS, consisting of
the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. outgoing Transformer bays for 33/11kV Transformers;
- Four (4) Nos. feeder bays rated 1250A (two (2) spare);
- Space for four future bays, two on each side of the 33kV switchgear.

 Existing 11kV switchgear bays - Re-testing and re-commissioning of the existing A 18,
A 28 , A30 & A 40 switchgear bays and any required works/modifications including,
wiring, naming, label changes, testing & complete re-commissioning of the above
switchgear bays.
 Two (2) Nos. Auxiliary Transformers 11/0.415kV, 500kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 4.75%
impedance, neutral CTs, etc. Existing 315kVA auxiliary transformers to be replaced
with 500kVA transformers as specified above at new location and existing power
cables from A 30 & A 40 11kV switchgear bays to be diverted to the new auxiliary
transformers
 Dismantling of 315kVA aux Transformers and to hand over safely to KM store.
 Protection:
Relay Protection Equipment for all Primary Equipment (all bays) as detailed in Main
Scope of the Work shall be provided as per standard specification, Protection SLD and
Technical Schedules. Relay and equipment compatible with remote end (in line with
remote end protection scope of works) shall be provided for feeders connected to Ain
Hamad substation. However, the following specific requirements shall be considered:
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 299 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Protection at Abu Samra substation for 2x33kV OHL feeders to be connected to


Ain Hamad substation shall be provided to be compatible with already installed
relays at Ain Hamad substation. End to End test, Testing and commissioning and
putting into service of these two OHL circuits shall be substation Contractor's
responsibility.

New (HV side) protection for existing 33/11kV Power Transformer shall be
provided based on Phase 13 specifications, installed in new control room. All
modification on the 33kV and 11V sides of the 33/11kV Power Transformer
protection shall be done to make it compatible with 33kV side protection.
Contractor shall ensure all the required modifications including provision of any
trip/auxiliary relays, cabling/wiring to achieve Interlocks and Intertrips between
33kV HV side (new control building) and existing 11kV LV switchgears and
protection.

Presently, existing panels (E11 & E21), provided with transformer (HV) side
protection and OHL line differential protection. OHL line differential protection
shall be dismantled and returned to Kahramaa store as per standard procedure.
Transformer mechanical protections relays are provided in the 33kV HV panels as
per old protection philosophy. However, new provision of transformer mechanical
protections relays based on new 33/11kV transformer protection philosophy shall
be contractors responsibility. Existing HV side panels shall be converted to LV
side protection panels. Alternatively, new LV protection panels can be provided
and exact details shall be decided during detail engineering. Contractor shall
ensure that the relays provided in new 33kV Transformer HV Bays protection
panels and those installed in existing 11kV LV bay protection panels are complete
so as to achieve a complete functional protection for the Transformers. Testing
and commissioning of the 33/11kV Transformers protection.

AVR panels with AVR relays are provided for existing two number 33/11kV
Transformers, located in existing control room. Existing AVR equipment shall be
tested and its proper functioning shall be ensured by the Contractor; however, any
AVR equipment modifications, testing and commissioning for AVR scheme due to
connection to new 33kV GIS shall be Contractor's responsibility.

All other protections shall be provided as per the standard specification.

Contractor is responsible to lay control cables (as necessary) and fibre Optic
Cables from existing OTP installed in telecom room up to new 33kV control room
to complete the necessary connection and end-to-end test of protection for the
said links (New control room in Abu Samra to Ain Hamad).

Any required changes to existing protection relay settings, testing and recommissioning of existing 33/11kV transformer, 11kV Switchgear and earthing
transformer shall be the responsibility of the Contractor.

 SCS & Associated Equipment

New Substation Control System Including Gateway data mapping to NCC/ENCC


and S/S works necessary for NCC/ENCC End to End testing.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 300 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The existing control system of Alstom PSCN 3020 with Gateways being modified
by M/s. Schneider is having IEC101 for communication to both DCC and NCC.
New SCS shall manage communication to NCC/ENCC/DCC of the new 33kV GIS,
the existing 11kV switchgear and existing station common alarms.

Existing 11kVA BCUs and Measurement Units shall be replaced to integrate with
new SCS. Old 11kV-A protection IEDs to be wired through new BCUs.
(alternatively communication module of protection IEDs can be replaced for
communication with new SCS)

Existing substation signals shall be shifted to from IEC-101 to IEC-104 through


new SCS.

Existing SCS shall be dismantled and handed over to Kahramaa.

Unwanted alarms to be deleted and alarms related to modifications are to be


included in the SCS and S/S work necessary for remote signaling to NCC/ENCC.

Redundant Multimode FO cables, including OTBs, shall be laid between new


Control Room and existing Control & Relay Room.

For new common alarms the contractor will use additional BCUs to maintain 20%
spare availability.

One HMI shall be provided in existing 11kV relay room.

 FO and Copper Cables:

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 Online Monitoring System

Condition monitoring system comprising of:


- 33kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);

 LV Power Cables, Control Cables with all accessories for the new equipment as well
as for the connections to the existing equipment/systems. Sizing and Voltage drop
calculation shall be strictly carried out for the cables to be proposed from existing LV
services to the new building.
 Small Power & Lighting
 Earthing & Lightning Protection including connection to the existing system,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 301 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 LVAC Board with all accessories - LV cables from the new 500kVA auxiliary
transformers shall be connected to the new LVAC Board. Besides, two dedicated
feeders shall be provided with adequate capacity to feed existing LVAC board situated
in the existing control room building.
 New LVDC Board, Battery, Battery charger and UPS to cater the load requirements
of new equipment and building.
 Security Management System according to specification enclosed in section 3.3.15.

Security management system shall cover both existing and new substation
building and open areas. If due to bidders design there are more than one control
rooms, the bidder shall be bound to provide additional SMS material, if required,
for both control rooms.

 FOC and Pilot wire

Laying, termination and testing of copper cables to extend Telephones from old to
new building.

Laying, termination and testing of two FO single mode cables (2 * 48F) from old to
new building including OTBs in new building.

 All civil works related to new 33kV GIS including building services,

Dismantling and reconstruction of existing septic tank and manhole to new


location.

New / Reconstruction of internal road as required.

 Air-conditioning and ventilation systems to cover the GIS.


 Fire Fighting System

Fire Detection & Alarm System for the 33KV GIS building & all other areas.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 302 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Required modification works with the existing system (tie-in) for Fire Detection and
Alarm System, testing & commissioning, battery calculations, replacement of
batteries (as per calculations, if required) etc in the existing Fire Detection & Alarm
System (which must be verified during commissioning) are included in the present
scope of works.

EPC Contractor must engage the services of the vendor or specialist Fire
contractor involved in execution of existing Fire Alarm System during the tie-in
works with the existing Fire Detection & Alarm System. Commissioning works
must be carried out only by the authorized vendor or Fire contractor who has
installed the existing system.

Introduction of loop card, interface modules & provision of required number of


relays in the existing Fire Alarm Control Panel for transmitting signals to SCS. In
case of there is no space in the existing FACP to introduce loop card for serving
new 33KV GIS & other areas Fire alarm system, existing FACP shall be upgraded
or replaced with new FACP.

Existing Fire Detection & Alarm System drawings shall be updated.

 Power Cables:

Diversion of the existing 33kV, 2x500mm2, XLPE, 100MVA, double circuits,


from 33/11kV Transformer into 33kV GIS, laid in unfilled concrete troughs with all
accessories. Approx. route length: 100m.

33kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor between 33kV GIS and 33/11kV Power Transformers, laid in
unfilled concrete troughs with all accessories. Approx. route length: 50m.

 Sequence of Construction Works

Milestone A
Complete 33kV GIS, connect one cable from the 33kV existing transformer to the
new GIS and the remote end works at Ain Hamad.

Milestone B
Connect the second cable from the 33kV existing transformer to the new GIS and
the corresponding remote end works at Ain Hamad.

 REMOTE END WORKS AT AIN HAMAD S/S


132/33/11kV Ain Hamad substation is the existing substation built under earlier Kahramaa
projects. Existing 33/11kV S/S has been upgraded by addition of the 132kV GIS, 2 x
132/33kV, 100MVA transformers and an additional 33kV GIS under phase 12 project. Abu
Samra will remain connected to Ain Hamad Substation with 2 x 33kV OHL.
Minor modifications at Ain Hamad substation shall be carried out under the present scope
of work.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 303 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 SCS and Power Control:

Minor Modifications to SCS supplied under Phase 12 project to include changes to


2x33kV OHL feeders in the SCS including Gateway Data mapping to NCC/ENCC
and S/S works necessary for NCC/ENCC End to End testing.

Alarms no more required shall be deleted and Alarms related to modifications are
to be included in the SCS.

 Protection:
2x33kV existing bays connected to Abu Samra Substation are with Protection
Relays/Equipments under Phase-12 Project.

The new Relays/Equipment to be installed at Abu Samra substation should match


the protection at 132/33/11kV Ain Hamad Substation end (supplied under Phase12 project).

Retesting of the Relays/Equipment, all modifications, End to End test, testing and
commissioning and putting into service of these two circuits is included in the
Present Scope.

Contractor has to do proper CT sizing calculation and check the adequacy of


existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).

Minor modification of the existing Bus bar protection, including conducting Bus bar
stability and addition of modules if required, shall be provided under this Contract.
Direct inter-trip for Breaker failure, Gas pressure low and Bus bar protection
operation are to be made available between the Stations based on requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 304 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-12

3.12

3.12.1

220/132/11KV FRAMEWORK SUBSTATION


The principal elements of new 220/132/11kV Framework Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. outgoing Transformer bays for 220/132kV Transformers suitable
for cable connection as per the approved connection arrangement;
- Two (2) Nos. Shunt Reactor bays suitable for cable connection as per the
approved connection arrangement;
- Six (6) Nos. cable feeder bays;
- Space for four future bays, two on each side of the switchgear;

Establish 132kV, 3150A at 40C, 40kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Three (3) Nos. incoming Transformer bays for 220/132kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. outgoing Transformer bays for 132/11kV Transformers;
- Six (6) Nos. Cable feeder bays;
- Three (3) Nos. 132kV, 315MVA bus duct between 220/132kV Power
Transformers and 132kV GIS;
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 132/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 305 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. Bays for future Capacitor bank;


- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on each side of the 11kV switchgear.
Alternatively, 11kV GIS is also acceptable.
 Power Transformers, NERs

Three (3) Nos. Power Transformers (Auto) 220/132kV, 189/236/315MVA,


YNa0(d1) ONAN/ONAF/OFAF cooling, 10% on load taps in steps of 1.25%,
13.6% impedance on ONAN (189 MVA), provided with AVR, terminal CTs, neutral
CTs etc.

Two (2) Nos. 220kV, 60MVAr Shunt Reactors with terminal CTs, neutral CTs etc.

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 2000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to
be justified by calculation note which shall be subject to approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 306 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:


- Partial discharge online monitoring system for 220kV GIS;
- Online condition monitoring system for new 220/132kV, 315MVA Transformers;
- Online condition monitoring system for new 220kV, 60MVAr Shunt Reactors;
- 132kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 307 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Earthing & Lightning Protection


 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 220/132/11kV substation including building services.
 220kV and 132kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Fire Fighting System

Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers

Fire Pumping Station & Fire Water Tanks.

Fire hydrant and ring main piping (all around the substation buildings perimeter).

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers & Shunt Reactors. All Transformers & Shunt Reactors shall be
manufactured with the necessary provision of connection points for installation of
TEP System (if Kahramaa decides to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 308 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power Cables:

3.12.2

220kV, 1x1600mm2, XLPE, 315MVA, triple circuit, single point earthed with
earth continuity conductor cable links between 220kV GIS and 220/132kV
Transformers, laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.

220kV, 1x500mm2, XLPE, 60MVA, double circuit, solid bonded cable links
between 220kV GIS and 220kV Shunt Reactors, laid in unfilled concrete troughs
with all accessories. Approx. route length: 100m.

132kV, 1x2000mm2, XLPE, 315MVA, triple circuit, single point earthed with
earth continuity conductor cable links between 132kV GIS and 220/132kV Power
Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m. (alternative to 132kV GI bus duct in case of layout difficulty)

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 2000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

220/66/11KV FRAMEWORK SUBSTATION


The principal elements of new 220/66/11kV Framework Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 220kV, 4000A at 40C, 50kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 309 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. outgoing Transformer bays for 220/66kV Transformers suitable for
cable connection as per the approved connection arrangement;
- Two (2) Nos. Shunt Reactor bays suitable for cable connection as per the
approved connection arrangement;
- Six (6) Nos. cable feeder bays;
- Space for four future bays, two on each side of the switchgear;

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
- Two (2) Nos. Bus section bays;
- Two (2) Nos. Bus coupler bays;
- Two (2) Nos. incoming Transformer bays for 220/66kV Transformers suitable
for GIB connection as per the approved connection arrangement;
- Two (2) Nos. outgoing Transformer bays for 66/11kV Transformers;
- Six (6) Nos. Cable feeder bays;
- Two (2) Nos. 66kV, 200MVA bus duct between 220/66kV Power Transformers
and 66kV GIS;
- Space for four future bays, two on each side of the switchgear;

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- One (1) No. Bus section bay rated 2500A;
- Two (2) Nos. Incomers for 66/11kV Transformers rated 2500A;
- Eighteen (18) Nos. Outgoing feeder bays rated 630A;
- Two (2) Nos. Bays for future Capacitor bank;
- Two (2) Nos. Bays for 11/0.415kV Auxiliary Transformers;
- Space for four future bays, two on each side of the 11kV switchgear.

Alternatively, 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers (Auto) 220/66kV, 120/150/200MVA,


YNyn0(d1) ONAN/ONAF/OFAF cooling, 10% on load taps in steps of 1.25%,
13% impedance on ONAN (200 MVA), provided with AVR, terminal CTs, neutral
CTs etc.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 310 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. 220kV, 60MVAr Shunt Reactors with terminal CTs, neutral CTs etc.

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1, with


ONAN/ONAF cooling, OLTC with +5% to -15% in steps of 1.25%, 13.6%
impedance on ONAN provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.5 ohm at 50C
rated for 750A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 32/40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 2000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%, 6%
impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformer supplied shall be of adequate capacity to cater to the total load of the
substation with additional capacity of 30%. The capacity of the Transformer is to
be justified by calculation note which shall be subject to approval.

 Protection:

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules.

For 11kV outgoing feeders pilot wire differential relay (for copper pilot) or
Numerical relay with fibre optic interphase (for Fibre optic cable) shall be provided
which shall be decided during detail design. Other protection and schemes as
applicable in specification shall be provided.

For capacitor bank bays, all protection similar to outgoing feeders shall be
provided. Separate protection panel shall be provided for each one of the
capacitor bank bay.

Separate panel shall be provided for each of the 11kV Incomer bays and each
Auxiliary Transformer bays. Separate Load Shedding Panel shall be provided for
11kV outgoing feeders of each Switchgear i.e., for a two Switchgear Substation (A
& B) there shall be two Load Shedding Panels.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing

 Online Monitoring System

Condition monitoring system comprising of:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 311 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Partial discharge online monitoring system for 220kV GIS;


- Online condition monitoring system for new 220/66kV, 200MVA Transformers;
- Online condition monitoring system for new 220kV, 60MVAr Shunt Reactors;
- 66kV GIS shall be equipped with the internal UHF couplers so the retrofitting
can be easily done in the future (sensor location shall be done as per
Specification for PDM);
- 40MVA Transformers shall have all provisions as mentioned in the TMS
specification so the retrofitting can be easily done in the future. Some are listed
as below:

Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.

Provision to install moisture sensor.

Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.

Sensor for Transformer Load Current and voltage.

Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

- Integrated HMI workstation for monitoring system including software for each
online condition monitoring system installed in S/S as well as for their remote
access;
- Necessary LAN & WAN equipment including router/firewall for connection to
remote end.
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 LV Service Equipment
 Security Management System according to specification enclosed in section 3.3.15.
 All civil works related to new 220/66/11kV substation including building services.
 220kV and 66kV GIS & Fire Pump room Cranes
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 312 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Fire Fighting System

Deluge Water Spray System for Power Transformers, Shunt Reactors & Auxiliary
Transformers

Fire Pumping Station & Fire Water Tanks.

Fire hydrant and ring main piping (all around the substation buildings perimeter).

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers & Shunt Reactors. All Transformers & Shunt Reactors shall be
manufactured with the necessary provision of connection points for installation of
TEP System (if Kahramaa decides to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Shunt Reactors, Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material (fire penetration) for all the
MEP openings including HVAC & Fire/Smoke damper openings, floor/slab
openings such as panel openings including future openings, cable sleeve/duct
openings (spare/future) & all other cable openings including 11kV outgoing
feeders and all cables inside the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation

 Underground Remote Oil Containment Tank


 Power Cables:

220kV, 1x1200mm2, XLPE, 200MVA, double circuit, single point earthed with
earth continuity conductor cable links between 220kV GIS and 220/66kV
Transformers, laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m.

220kV, 1x500mm2, XLPE, 60MVA, double circuit, solid bonded cable links
between 220kV GIS and 220kV Shunt Reactors, laid in unfilled concrete troughs
with all accessories. Approx. route length: 100m.

66kV, 1x2000mm2, XLPE, 200MVA, double circuit, single point earthed with
earth continuity conductor cable links between 66kV GIS and 220/66kV Power

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 313 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Transformers laid in unfilled concrete troughs with all accessories. Approx. route
length: 100m. (alternative to 66kV GI bus duct in case of layout difficulty)

3.12.3

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 2000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

REMOTE END WORKS TYPICAL


The following remote end works shall be done in all types of remote end substations:

Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.

Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.

 Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later

The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 314 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 220kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation for Kahramaa review and
Adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control Scope:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-2: Substations Built During Phase 7

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 315 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 220kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be replaced to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications. Replacement of the existing Trip relay and
TCS Relay.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable)..
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 316 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
 Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53

All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:

Re-testing and re-commissioning of the existing GIS/ Switchgear bays in service


along with Local Control Panels including indicating meters in the local control
panels, inscription of additional alarm facia as required, replacing of GIS/
Switchgear name plates and any required works including, wiring, testing &
complete re-commissioning of the above GIS bays.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:
- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 220kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable). Installation of additional CT core or changing of the existing
CTs shall be the responsibility of the Contractor. Optional unit price for the
(132kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 317 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- All modifications, testing and commissioning, relay setting calculations, relay


testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Existing BCUs shall be replaced to accommodate additional alarms.

 Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier

All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.

The contractors scope of work includes thorough checking and refurbishment of


the existing equipment to deliver fully working system. For Control and Protection
the contractor shall deliver new equipment as mentioned in the scope of work of
the protection works. The scope of work shall include but not limited to the
following:

Refurbishment of existing 220kV switchgear bays

Replacement of 220kV isolators, if required (to be quoted in price schedule as an


optional item)

The existing 220V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.

Existing Panel Transducers shall be replaced as applicable according to the


enhancement of CT/VT etc.

New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Replacing existing labels by new labels

Replacement of existing 220kV CTs and VTs as detailed under protection scope of
work hereunder.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 318 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

New Alarm facia equipment shall be installed on CP/RP to incorporate additional


alarms locally as well as remote NCC/DGCC.

Re-commissioning and Re-calibration of Tariff meters at generating stations shall


be envisaged as applicable if CT/VT capacities/ratios are changed.

SCS and Power Control:


- Required modifications to existing conventional control panel to include
changes on the 220kV feeders.
- Required modifications in the existing SCS control panel to include changes on
the 220kV feeders.
- Required modification to TMMC/TDB/RTU to incorporate the changes on the
220kV feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained. Old and faulty transducers shall be
replaced and all related testing shall be done.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS, conventional control panel and TMMC/TDB/RTU.
- Existing BCUs shall be replaced to accommodate additional alarms.

Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 220kV New Typical Substation bays. Existing
trip relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 319 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- All modifications, testing and commissioning, relay setting calculations, relay


testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 320 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-13

3.13

3.13.1

132/11KV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11KV SWG)


2 NOS
The principal elements of new 132/11kV Framework TYPE A Substations shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bus bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Four (4) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV switchgear A:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear

11kV switchgear B:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
Alternatively 11kV GIS is also acceptable.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 321 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power Transformers, NERs

Four (4) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 322 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 132kV GIS & Fire Pump Room Crane
 Power cables

132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 323 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.13.2

132/11KV FRAMEWORK TYPE B SUBSTATION (SINGLE 11KV SWG)


2 NOS
The principal elements of new 132/11kV Framework TYPE B Substations shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bus bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Two (2) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 324 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. incomers rated 2500A


- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
- Alternatively 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 325 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 132kV GIS & Fire Pump Room Crane
 Power cables

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 326 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.13.3

132/11KV FRAMEWORK TYPE C SUBSTATION (SINGLE 11KV SWG)


The principal elements of new 132/11kV Framework TYPE C Substation shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz single bus bar
GIS consisting of following bays:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 327 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- One (1) Bus section bay,


- Six (6) cable feeder bays,
- Two (2) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
- Alternatively 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 328 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 132kV GIS & Fire Pump Room Cranes
 Power cables

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 329 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 330 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.13.4

REV. 0

REMOTE END WORKS TYPICAL


The following remote end works shall be done in all types of remote end substations:

Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.

Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.

 Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later

The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 331 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Contractor has to do proper CT sizing calculation for Kahramaa review and


Adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control Scope:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-2: Substations Built During Phase 7

The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be replaced to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications. Replacement of the existing Trip relay and
TCS Relay.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 332 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- New relays/equipment shall be installed at the new substation to match the


protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable)..
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53

All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:

Re-testing and re-commissioning of the existing GIS/ Switchgear bays in service


along with Local Control Panels including indicating meters in the local control
panels, inscription of additional alarm facia as required, replacing of GIS/
Switchgear name plates and any required works including, wiring, testing &
complete re-commissioning of the above GIS bays.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 333 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- The required modification works for protection systems is detailed under


protection scope of work hereunder
- For those 132kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable). Installation of additional CT core or changing of the existing
CTs shall be the responsibility of the Contractor. Optional unit price for the
(132kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Existing BCUs shall be replaced to accommodate additional alarms.

 Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier

All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.

The contractors scope of work includes thorough checking and refurbishment of


the existing equipment to deliver fully working system. For Control and Protection
the contractor shall deliver new equipment as mentioned in the scope of work of
the protection works. The scope of work shall include but not limited to the
following:

Refurbishment of existing 132kV switchgear bays

Replacement of 132kV isolators, if required (to be quoted in price schedule as an


optional item)

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 334 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The existing 132V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.

Existing Panel Transducers shall be replaced as applicable according to the


enhancement of CT/VT etc.

New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Replacing existing labels by new labels

Replacement of existing 132kV CTs and VTs as detailed under protection scope of
work hereunder.

New Alarm facia equipment shall be installed on CP/RP to incorporate additional


alarms locally as well as remote NCC/DGCC.

Re-commissioning and Re-calibration of Tariff meters at generating stations shall


be envisaged as applicable if CT/VT capacities/ratios are changed.

SCS and Power Control:


- Required modifications to existing conventional control panel to include
changes on the 132kV feeders.
- Required modifications in the existing SCS control panel to include changes on
the 132kV feeders.
- Required modification to TMMC/TDB/RTU to incorporate the changes on the
132kV feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained. Old and faulty transducers shall be
replaced and all related testing shall be done.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS, conventional control panel and TMMC/TDB/RTU.
- Existing BCUs shall be replaced to accommodate additional alarms.

Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 335 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

the new protection provided at 132kV New Typical Substation bays. Existing
trip relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 336 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

PACKAGE S-14

3.14

3.14.1

132/11KV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11KV SWG)


2 NOS
The principal elements of new 132/11kV Framework TYPE A Substations shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bus bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Four (4) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV switchgear A:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear

11kV switchgear B:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
Alternatively 11kV GIS is also acceptable.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 337 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power Transformers, NERs

Four (4) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 338 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 132kV GIS & Fire Pump Room Cranes
 Power cables

132kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shallbe considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 339 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.

 Security Management System according to specification enclosed in section 3.3.15.


3.14.2

132/11KV FRAMEWORK TYPE B SUBSTATION (SINGLE 11KV SWG)


2 NOS
The principal elements of new 132/11kV Framework TYPE B Substations shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz double bas bar
GIS consisting of following bays:
- Two (2) Bus section bays,
- Two (2) Bus coupler bays,
- Six (6) cable feeder bays,
- Two (2) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 340 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Two (2) Nos. incomers rated 2500A


- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
- Alternatively 11kV GIS is also acceptable.
 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 341 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 132kV GIS & Fire Pump Room Cranes
 Power cables

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 342 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises..

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.14.3

132/11KV FRAMEWORK TYPE C SUBSTATION (SINGLE 11KV SWG)


The principal elements of new 132/11kV Framework TYPE C Substation shall be as
follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 132kV, 3150A @ 40C, 40kA / 1 sec, 3-phase, 50Hz single bus bar
GIS consisting of following bays:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 343 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- One (1) Bus section bay,


- Six (6) cable feeder bays,
- Two (2) 40MVA outgoing Transformer feeder bays
- Space for four future bays, two on either side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
- Two (2) Nos. incomers rated 2500A
- One (1) No. bus section bay rated 2500A
- Eighteen (18) Nos. Bays for outgoing feeders rated 630A
- Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers
- Two (2) Nos. Bays for future capacitor banks feeders
- Space for four future bays, two on either side of the switchgear
- Alternatively 11kV GIS is also acceptable.

 Power Transformers, NERs

Two (2) Nos. Power Transformers 132/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 132/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 344 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

132kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 132kV GIS & Fire Pump Room Cranes
 Power cables

132kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 132kV GIS and 132/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 132/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 132/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 345 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary Transformers.
Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary provision
of connection points for installation of TEP System (if Kahramaa decides to adopt
this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 346 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.14.4

REV. 0

REMOTE END WORKS TYPICAL


The following remote end works shall be done in all types of remote end substations:

Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.

Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.

 Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later

The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 347 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Contractor has to do proper CT sizing calculation for Kahramaa review and


Adequacy of existing CTs must be checked.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control Scope:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-2: Substations Built During Phase 7

The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 132kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be replaced to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications. Replacement of the existing Trip relay and
TCS Relay.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 348 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- New relays/equipment shall be installed at the new substation to match the


protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable)..
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53

All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:

Re-testing and re-commissioning of the existing GIS/ Switchgear bays in service


along with Local Control Panels including indicating meters in the local control
panels, inscription of additional alarm facia as required, replacing of GIS/
Switchgear name plates and any required works including, wiring, testing &
complete re-commissioning of the above GIS bays.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 349 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- The required modification works for protection systems is detailed under


protection scope of work hereunder
- For those 132kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable). Installation of additional CT core or changing of the existing
CTs shall be the responsibility of the Contractor. Optional unit price for the
(132kV GIS) CT replacement and all associated works shall be provided.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Existing BCUs shall be replaced to accommodate additional alarms.

 Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier

All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.

The contractors scope of work includes thorough checking and refurbishment of


the existing equipment to deliver fully working system. For Control and Protection
the contractor shall deliver new equipment as mentioned in the scope of work of
the protection works. The scope of work shall include but not limited to the
following:

Refurbishment of existing 132kV switchgear bays

Replacement of 132kV isolators, if required (to be quoted in price schedule as an


optional item)

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 350 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The existing 132V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.

Existing Panel Transducers shall be replaced as applicable according to the


enhancement of CT/VT etc.

New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Replacing existing labels by new labels

Replacement of existing 132kV CTs and VTs as detailed under protection scope of
work hereunder.

New Alarm facia equipment shall be installed on CP/RP to incorporate additional


alarms locally as well as remote NCC/DGCC.

Re-commissioning and Re-calibration of Tariff meters at generating stations shall


be envisaged as applicable if CT/VT capacities/ratios are changed.

SCS and Power Control:


- Required modifications to existing conventional control panel to include
changes on the 132kV feeders.
- Required modifications in the existing SCS control panel to include changes on
the 132kV feeders.
- Required modification to TMMC/TDB/RTU to incorporate the changes on the
132kV feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained. Old and faulty transducers shall be
replaced and all related testing shall be done.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS, conventional control panel and TMMC/TDB/RTU.
- Existing BCUs shall be replaced to accommodate additional alarms.

Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 351 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

the new protection provided at 132kV New Typical Substation bays. Existing
trip relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

PACKAGE S15

3.15

3.15.1

66/11KV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11KV SWG)


2 NOS
The principal elements of 66/11kV TYPE A Substations shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 352 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV Switchgear A:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the switchgear

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:
-

Two (2) Nos. Incomers rated 2500A

One (1) No. Bus section bays rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.

The rated Power of the Auxiliary Transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 353 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire pump Room Cranes
 66kV GIS Room Crane
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 354 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 355 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 All civil works related to new substation including building services.


 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.15.2

66/11KV FRAMEWORK TYPE B SUBSTATION (SINGLE 11KV SWG) 2


NOS
The principal elements of 66/11kV TYPE B Substations shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 356 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps of
2.5%, 5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 357 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 LV Power Cables, Control Cables with all accessories


 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 358 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.15.3

66/11KV FRAMEWORK TYPE C SUBSTATION (SINGLE 11KV SWG)


The principal elements of 66/11kV TYPE C Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
-

One (1) Bus section bay,

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 359 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps of
2.5%, 5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 360 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.
 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS Room & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 361 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Transformers. All Transformers shall be manufactured with the necessary


provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.15.4

REMOTE END WORKS TYPICAL


The following remote end works shall be done in all types of remote end substations:

Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.

All necessary co-ordination with the cable contractor for the termination of the EHV
cables at both ends.

Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 362 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later

The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 363 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
 Remote End Modification - TYPE-2: Substations Built During Phase 7

The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control Scope for remote end modification:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 364 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Required modifications to existing SCS to include changes on feeders in the


SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.
 Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53

All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:

Re-testing and re-commissioning of the existing GIS/ Switchgear bays in service


along with Local Control Panels including indicating meters in the local control
panels, inscription of additional alarm facia as required, replacing of GIS/
Switchgear name plates and any required works including, wiring, testing &
complete re-commissioning of the above GIS bays.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection scope for remote end modification:


- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 66kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 365 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- All modifications, testing and commissioning, relay setting calculations, relay


testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control Scope for remote end modification:


- Required modifications to existing SCS to include changes on the 66kV feeders
in the SCS and S/S works necessary for NCC/ENCC End to End testing.
- Existing BCUs shall be replaced to accommodate additional alarms.
- Alarms no more required shall be deleted and those related to modifications are
to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC

 Remote End Modification - TYPE-4: Substations Built During Phase 4 and Earlier

All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.

The contractors scope of work includes thorough checking and refurbishment of


the existing equipment to deliver fully working system. For Control and Protection
the contractor shall deliver new equipment as mentioned in the scope of work of
the protection works. The scope of work shall include but not limited to the
following:

Refurbishment of existing 66kV switchgear bays

Replacement of 66kV isolators, if required (to be quoted in price schedule as an


optional item)

The existing 66V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.

Existing Panel Transducers shall be replaced as applicable according to the


enhancement of CT/VT etc.

New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Replacing existing labels by new labels

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 366 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Replacement of existing 66kV CTs and VTs as detailed under protection scope of
work hereunder.

New Alarm facia equipment shall be installed on CP/RP to incorporate additional


alarms locally as well as remote NCC/DGCC.

Re-commissioning and Re-calibration of Tariff meters at generating stations shall


be envisaged as applicable if CT/VT capacities/ratios are changed.

SCS and Power Control:


- Required modifications in the existing SCS to include changes related to 66kV
feeders.
- Required modifications in the existing conventional control panel to include
changes on the 66kV feeders.
- Required modification to TMMC/TDB/RTU to incorporate the changes on the
66kV feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained. Old transducers shall be replaced and
necessary testing shall be carried out.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS, conventional control panel and TMMC/TDB/RTU.
- Existing BCUs shall be replaced to accommodate additional alarms.

Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 66kV New Typical Substation bays. Existing trip
relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 367 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

protection operation are to be made available between the stations based on


requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

PACKAGE S16

3.16

3.16.1

66/11KV FRAMEWORK TYPE A SUBSTATION (DOUBLE 11KV SWG)


2 NOS
The principal elements of 66/11kV TYPE A Substations shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:
-

GTC-735 SCOPE OF WORKS R0

Two (2) Nos. Incomers rated 2500A


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 368 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

One (1) No. Bus section bays rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 369 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 370 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15

3.16.2

66/11KV FRAMEWORK TYPE B SUBSTATION (SINGLE 11KV SWG) 2


NOS
The principal elements of 66/11kV TYPE B Substations shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

GTC-735 SCOPE OF WORKS R0

Two (2) Bus section bays,


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 371 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps of
2.5%, 5.45% impedance, neutral CTs, etc.

The rated Power of the Auxiliary Transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 372 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 373 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 374 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.16.3

66/11KV FRAMEWORK TYPE C SUBSTATION (SINGLE 11KV SWG)


The principal elements of 66/11kV TYPE C Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, single bus bar
GIS consisting of following bays:
-

One (1) Bus section bay,

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 375 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN


cooling, Vector group of Dyn11, off load tap change with +5% to -5% in steps of
2.5%, 5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
7. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
8. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
9. Provision to install moisture sensor.
10. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
11. Sensor for Transformer Load Current and voltage.
12. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 376 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power cables

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 377 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.16.4

REMOTE END WORKS TYPICAL


The following remote end works shall be done in all types of remote end substations:

Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.

Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.

 Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later

The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 378 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-2: Substations Built During Phase 7

The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 379 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Protection systems as detailed under protection scope of work hereunder.

Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53

All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:

Re-testing and re-commissioning of the existing GIS/ Switchgear bays in service


along with Local Control Panels including indicating meters in the local control
panels, inscription of additional alarm facia as required, replacing of GIS/
Switchgear name plates and any required works including, wiring, testing &
complete re-commissioning of the above GIS bays.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 380 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:
- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 66kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on the 66kV feeders
in the SCS and S/S works necessary for NCC/ENCC End to End testing.
- Existing BCUs shall be replaced to accommodate additional alarms.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-4: Substations Built During Phase 4 and


Earlier

All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 381 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The contractors scope of work includes thorough checking and refurbishment of


the existing equipment to deliver fully working system. For Control and Protection
the contractor shall deliver new equipment as mentioned in the scope of work of
the protection works. The scope of work shall include but not limited to the
following:

Refurbishment of existing 66kV switchgear bays

Replacement of 66kV isolators, if required (to be quoted in price schedule as an


optional item)

The existing 66V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.

Existing Panel Transducers shall be replaced as applicable according to the


enhancement of CT/VT etc.

New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Replacing existing labels by new labels

Replacement of existing 66kV CTs and VTs as detailed under protection scope of
work hereunder. Contractor has to do proper CT sizing calculation. CTs shall be
replaced (unit rates in Price Schedule 4.5 will be applicable).

New Alarm facia equipment shall be installed on CP/RP to incorporate additional


alarms locally as well as remote NCC/DGCC.

Re-commissioning and Re-calibration of Tariff meters at generating stations shall


be envisaged as applicable if CT/VT capacities/ratios are changed.

SCS and Power Control:


- Required modifications in the existing SCS to include changes related to 66kV
feeders.
- Required modifications in the existing conventional control panel to include
changes on the 66kV feeders.
- Required modification to TMMC/TDB/RTU to incorporate the changes on the
66kV feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained. Old and faulty transducers shall be
replaced and all related testing shall be done.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 382 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Existing BCUs shall be replaced to accommodate additional alarms.


- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS, conventional control panel and TMMC/TDB/RTU.

Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 66kV New Typical Substation bays. Existing trip
relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

PACKAGE S17

3.17

3.17.1

66/11KV FRAMEWORK TYPE A SUBSTATION (CONVENTIONAL,


DOUBLE 11KV SWG CIVIL WORKS DONE BY DEVELOPER)
66/11kV Framework is conventional substation that shall be constructed to meet the
Power supply requirements of the future development project.
Civil works for the substation buildings will be undertaken by Developer. Roles and
responsibility matrix for the scope of works of EPC contractor and the Developer shall be
developed before project execution. All necessary coordination with the Developer and
their contractors shall be the responsibility of the substation contractors.
Interface between EPC Contractor and civil design team of developer will be required in
the early stage of the project, to ensure that any specific requirements are defined and

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 383 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

integrated in construction works in due time. High level of coordination between developer
and substation Contractor will be required during the complete construction period.
The principal elements of 66/11kV TYPE A Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:
-

Two (2) Nos. Incomers rated 2500A

One (1) No. Bus section bays rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 384 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.

Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 385 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 386 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 Civil works and building services for the substation buildings will be undertaken by
Developer. All necessary coordination with the Developer and their contractors shall be
the responsibility of the substation contractors.
 Security Management System according to specification enclosed in section 3.3.15
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
3.17.2

66/11KV FRAMEWORK TYPE B SUBSTATION (CONVENTIONAL,


SINGLE 11KV SWG - CIVIL WORKS DONE BY DEVELOPER)
66/11kV Framework is conventional substation that shall be constructed to meet the
Power supply requirements of the future development project.
Civil works for the substation buildings will be undertaken by Developer. Roles and
responsibility matrix for the scope of works of EPC contractor and the Developer shall be
developed before project execution. All necessary coordination with the Developer and
their contractors shall be the responsibility of the substation contractors.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 387 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Interface between EPC Contractor and civil design team of developer will be required in
the early stage of the project, to ensure that any specific requirements are defined and
integrated in construction works in due time. High level of coordination between developer
and substation Contractor will be required during the complete construction period.
The principal elements of 66/11kV TYPE B Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Dyn1 ONAN/ONAF


cooling, +5% -15% on load taps in steps of 1.25%, 13.6% impedance on ONAN
provided with AVR, terminal CTs, neutral CTs etc.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 388 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc.

The rated Power of the Auxiliary Transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

66kV GIS shall be equipped with the internal UHF couplers so the retrofitting can
be easily done in the future (sensor location shall be done as per Specification for
PDM)

32/40MVA Transformers shall have all provisions as mentioned in the TMS


specification so the retrofitting can be easily done in the future. Some are listed as
below:
1. Dedicated Inlet and Outlet connections to connect multigas DGA sensor.
2. Provision to install additional Probes (Pt100) for Main Tank Top Oil Temp,
OLTC oil temperature, Cooler inlet and outlet temperature, Oil pressure.
3. Provision to install moisture sensor.
4. Sensors (Transducers) for Main Tank Conservator Oil level, OLTC Oil level
and OLTC tap position.
5. Sensor for Transformer Load Current and voltage.
6. Spare aux contacts in the cooling unit (fans/pumps) to obtain its operating
status. Access to bushing taps for PD measurement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 389 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Provision for future expansion / interfacing with Transformer Explosion Prevention


System shall be considered by providing necessary connection points at the
Transformers. All Transformers shall be manufactured with the necessary
provision of connection points for installation of TEP System (if Kahramaa decides
to adopt this system in future).

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 390 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 Civil works and building services for the substation buildings will be undertaken by
Developer. All necessary coordination with the Developer and their contractors shall be
the responsibility of the substation contractors.
 Security Management System according to specification enclosed in section 3.3.15
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
3.17.3

66/11KV FRAMEWORK UNDERGROUND TYPE A SUBSTATION


(DOUBLE 11KV SWG CIVIL WORKS DONE BY DEVELOPER)
66/11kV underground Framework substation shall be constructed to meet the Power
supply requirements of the future development project.
Civil works for the substation buildings will be undertaken by Developer. Roles and
responsibility matrix for the scope of works of EPC contractor and the Developer shall be
developed before project execution. All necessary coordination with the Developer and
their contractors shall be the responsibility of the substation contractors.
Interface between EPC Contractor and civil design team of developer will be required in
the early stage of the project, to ensure that any specific requirements are defined and
integrated in construction works in due time. High level of coordination between developer
and substation Contractor will be required during the complete construction period.
The principal elements of 66/11kV TYPE A Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

GTC-735 SCOPE OF WORKS R0

Two (2) Bus section bays,


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 391 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:
-

Two (2) Nos. Incomers rated 2500A

One (1) No. Bus section bays rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 392 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

detailed specification of the proposed cooling system and special construction


requirements for the same, if any.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.

Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

Partial discharge monitoring system for 66kV GIS

Condition monitoring system for 40MVA Transformers

Integrated HMI workstation for monitoring system

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 393 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Necessary LAN & WAN equipment including router/firewall for connection to


remote end

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Transformer Explosion Prevention System for Power Transformers.

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 394 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 Civil works and building services for the substation buildings will be undertaken by
Developer. All necessary coordination with the Developer and their contractors shall be
the responsibility of the substation contractors.
 Security Management System according to specification enclosed in section 3.3.15
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
3.17.4

66/11KV FRAMEWORK UNDERGROUND TYPE B SUBSTATION


(SINGLE 11KV SWG - CIVIL WORKS DONE BY DEVELOPER)
66/11kV underground Framework substation shall be constructed to meet the Power
supply requirements of the future development project.
Civil works for the substation buildings will be undertaken by Developer. Roles and
responsibility matrix for the scope of works of EPC contractor and the Developer shall be
developed before project execution. All necessary coordination with the Developer and
their contractors shall be the responsibility of the substation contractors.
Interface between EPC Contractor and civil design team of developer will be required in
the early stage of the project, to ensure that any specific requirements are defined and
integrated in construction works in due time. High level of coordination between developer
and substation Contractor will be required during the complete construction period.
The principal elements of 66/11kV TYPE B Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 395 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
detailed specification of the proposed cooling system and special construction
requirements for the same, if any.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.

The rated Power of the Auxiliary Transformer mentioned here is provisional.


Transformers to be supplied shall be of adequate capacity to cater to the total station

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 396 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

Partial discharge monitoring system for 66kV GIS

Condition monitoring system for 40MVA Transformers

Integrated HMI workstation for monitoring system

Necessary LAN & WAN equipment including router/firewall for connection to


remote end

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 66kV GIS & Fire Pump Room Cranes
 Earthing & Lightning Protection
 Power cables

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 397 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Transformer Explosion Prevention System for the Power Transformers.

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 398 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Civil works and building services for the substation buildings will be undertaken by
Developer. All necessary coordination with the Developer and their contractors shall be
the responsibility of the substation contractors.
 Security Management System according to specification enclosed in section 3.3.15
3.17.5

66/11KV FRAMEWORK
(DOUBLE 11KV SWG)

UNDERGROUND

TYPE

A SUBSTATION

66/11kV underground Framework substation shall be constructed to meet the Power


supply requirements of the future project.
The principal elements of 66/11kV TYPE A Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Four (4) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:

11kV Switchgear A:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.

11kV Switchgear B:
-

GTC-735 SCOPE OF WORKS R0

Two (2) Nos. Incomers rated 2500A


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 399 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

One (1) No. Bus section bays rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Bays for future capacitor banks feeders

Space for four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Four (4) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
detailed specification of the proposed cooling system and special construction
requirements for the same, if any.

Four (4) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for four (4) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,
5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total
station load with additional 30% margin. The capacity of the Transformer is to be
justified by calculation note which shall be subject to approval.

 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
shall be provided for feeders connected to remote end substation.

Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 400 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,


issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.
 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

Partial discharge monitoring system for 66kV GIS

Condition monitoring system for 40MVA Transformers

Integrated HMI workstation for monitoring system

Necessary LAN & WAN equipment including router/firewall for connection to


remote end

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection
 66kV GIS & Fire Pump Room Cranes
 Power cables

66kV, 1x500mm2, XLPE, 40MVA, quadruple circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, quadruple circuit, single point earthed with
earth continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, four single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 401 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department.
 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Transformer Explosion Prevention System for Power Transformers.

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.17.6

66/11KV FRAMEWORK
(SINGLE 11KV SWG)

UNDERGROUND

TYPE

SUBSTATION

66/11kV underground Framework substation shall be constructed to meet the Power


supply requirements of the future project.
The principal elements of 66/11kV TYPE B Substation shall be as follows:
 Gas Insulated/ Air Insulated Switchgear
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 402 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Establish 66kV, 2500A at 40C, 31.5kA / 1 sec, 3-phase, 50Hz, double bus bar
GIS consisting of following bays:
-

Two (2) Bus section bays,

Two (2) Bus coupler bays,

Six (6) Nos. Outgoing cable feeder bays

Two (2) Nos. 66/11 kV, 40MVA outgoing Transformer bays

Space for four future bays, two on each side of the switchgear

Establish 11kV, 2500A at 40C, 31.5kA / 3 sec, single bus bar metal enclosed
switchgear with vacuum circuit breakers, consisting of the following:
-

Two (2) Nos. incomers rated 2500A

One (1) No. bus section bay rated 2500A

Eighteen (18) Nos. Bays for outgoing feeders rated 630A

Two (2) Nos. Feeders for 11/0.415kV Auxiliary Transformers

Two (2) Nos. Bays for future capacitor banks feeders

Space four future bays, two on each side of the 11kV switchgear

Alternatively 11kV GIS is also acceptable.


 Power Transformers, NERs

Two (2) Nos. Power Transformers 66/11kV, 32/40MVA, Vector group of Dyn1,
OLTC with +5% to -15% in steps of 1.25%, 13.6% impedance at ONAN, AVR,
neutral CTs, etc. Due to absence of natural ventilation, substation Contractor is
obliged to perform detailed study of ventilation requirements and coordinate
design for the same with civil Contractor. Preferred are Transformers with
standard, ONAN / ONAF, cooling system and with FO winding temperature
monitoring which should be offered as optional item. Optionally, gas insulated
Transformer may be proposed. Bidders should include in their technical offer
detailed specification of the proposed cooling system and special construction
requirements for the same, if any.

Two (2) Nos. of 11kV Metallic Neutral Earthing Resistors 8.50 ohm at 50C
rated for 750 A for 30 seconds (including NER monitoring system) for earthing the
neutral of 66/11kV, 40MVA Power Transformer.

Space for two (2) future capacitor banks and space for vacuum contactor panels
for the future capacitor banks shall be provided for in the substation layout.

Two (2) Nos. Auxiliary Transformers 11/0.415kV, 1000kVA, with ONAN cooling,
Vector group of Dyn11, off load tap change with +5% to -5% in steps of 2.5%,

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 403 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

5.45% impedance, neutral CTs, etc. Consider rated Power and indoor installation
environment, Bidder may propose dry type Transformers. This needs to be clearly
indicated in the Technical Data Sheets.
The rated Power of the Auxiliary Transformer mentioned here is provisional.
Transformers to be supplied shall be of adequate capacity to cater to the total station
load with additional 30% margin. The capacity of the Transformer is to be justified by
calculation note which shall be subject to approval.
 Protection Systems

Relay Protection Equipment for all Primary Equipment (all bays) as detailed in
Main Scope of the Work shall be provided as per standard specification, Protection
SLD and Technical Schedules. Relay and equipment compatible with remote ends
(in line with remote end protection scope) shall be provided for feeders connected
to remote end substation.

Metering system: Tariff meters shall be provided on the 11kV sides of 40MVA
Power Transformers. Standard specification for the bulk consumers shall apply.
Guidelines for Protection Energy Meter and System Control Requirements for
Power Supply to Bulk Consumers are included in the technical specification in
Volume 2 (along with the Scope of Works) as Annexures IV & V (ET-P26-G1,
issue 4 14/5/2014 & ES-EST-P1-G1, issue 0 10/3/2014). Tariff meters shall be
interfaced with SCS using communication protocol, preferable IEC61850, to
enable signal transfer from tariff metering system to NCC.

 SCS & Associated Equipment

Substation Control System Including Gateway data mapping to NCC/ENCC/DCC


and S/S works necessary for NCC/ENCC/DCC End to End testing.

 Online Monitoring System

Partial discharge monitoring system for 66kV GIS

Condition monitoring system for 40MVA Transformers

Integrated HMI workstation for monitoring system

Necessary LAN & WAN equipment including router/firewall for connection to


remote end

 LV Service Equipment
 LV Power Cables, Control Cables with all accessories
 Small Power & Lighting
 Earthing & Lightning Protection

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 404 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 66kV GIS & Fire Pump Room Cranes


 Power cables

66kV, 1x500mm2, XLPE, 40MVA, double circuit, solid bonded cable links
between 66kV GIS and 66/11kV Power Transformers laid in unfilled concrete
troughs with all accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, 40MVA, double circuit, single point earthed with earth
continuity conductor, four (4) cables per phase cable links between 66/11kV
Power Transformers and 11kV switchgear, laid in unfilled concrete troughs with all
accessories. Approx. route length: 50m.

11kV, 1x630mm2, XLPE, two single cable links between 66/11kV Power
Transformers and 11kV NER. Approx. route length: 20m.

11kV, 1x500mm2, XLPE, 1000kVA, double circuit, solid bonded (one cable per
phase) cable links between 11kV switchgear and 11/0.415, Auxiliary
Transformers. Approx. route length: 50m.

11kV outgoing feeder Cables: Installation for 11kV outgoing cable feeders
between 11kV SWG and service corridor outside the Substation boundary wall,
included but not limited to cable laying, cable supports, cable cleats, heat
shrinkable caps and commissioning tests. Cables and terminations will be supplied
by Kahramaa. Contractor shall coordinate with concerned Kahramaa department

 Fire Fighting System

Deluge Water Spray System for Power Transformers & Auxiliary Transformers

Fire Pumping Station & Fire Water Tanks.

Transformer Explosion Prevention System for the Power Transformers.

Sprinkler System inside the Fire Pump Room.

Fire Detection & Alarm System for the GIS buildings, Transformer Yards (Power &
Auxiliary), Control & Relay building and all other buildings.

FM200 System for the control & relay room, LVAC/DC Room.

Passive fire protection system Cable Coating for all cables (EHV, HV, MV & LV
including cable trays) for the entire length of the cable which includes also the
substation cables and all cables inside the Cable basement of all buildings
including 11kV outgoing feeders & incoming feeders.

Passive fire protection system Fire Sealant material for all the MEP openings
including HVAC & Fire/Smoke damper openings, floor openings such as panel
openings including future openings, cable openings (spare/future) & all other cable
openings such as substation cables, 11kV outgoing feeders and all cables inside
the Cable basement of all buildings.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 405 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Fire Extinguishers (Portable & Trolley Mounted) at designated areas inside the
substation premises.

 Underground Remote Oil Containment Tank.


 All civil works related to new substation including building services.
 Air-conditioning and ventilation systems to cover the GIS and Control & Relay
buildings and all other buildings.
 Security Management System according to specification enclosed in section 3.3.15
3.17.7

REMOTE END WORKS TYPICAL


The following remote end works shall be done in all types of remote end substations:

Re-testing and re-commissioning of the existing GIS spare bays along with Local
Control Panels including indicating meters in the local control panels, inscription of
additional alarm facia as required, replacing of GIS name plates and any required
works including, wiring, testing & complete re-commissioning of the above GIS
bays.

Direct intertrip for breaker failure, gas pressure low and busbar protection
operation to be made available between the stations based on requirement.

Alarms no more required shall be deleted and those related to modifications are to
be included in the SCS scope All necessary co-ordination with the cable contractor
for the termination of the EHV cables at both ends.

Other necessary works, depending of the substation built date, are divided into four
categories (types) which are described below.

 Remote End Modification - TYPE-1: Substations Built During Phase 8 and Later

The spare bays at remote end Substations built under Phase 8 and later shall be
used for establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 406 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- For Feeders to be connected to substation, the Bays will be equipped with


Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-2: Substations Built During Phase 7

The spare bays at remote end Substations built under Phase 7 shall be used for
establishing the above underground cable connections between the two
substations. All the required modifications to the existing spare bays at remote end
Super substations shall be carried out under the present scope of work. The scope
of work shall include but not limited to the following:

Contractor shall check suitability of the existing termination female part in GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 407 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Protection:
- For Feeders to be connected to substation, the Bays will be equipped with
Protection relays.
- For those 66kV Cable feeders connected to new typical substation, complete
functional protection system as per Standard specification shall be provided.
The bays are fully equipped with protection relays/equipment. The 87C relays
are to be upgraded to get Dual FO port communication wherever applicable as
per latest Kahramaa specifications.
- New relays/equipment shall be installed at the new substation to match the
protection provided at respective Remote end substation bays.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct intertrip for breaker failure, gas pressure low and busbar
protection operation to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on feeders in the
SCS including Gateway data mapping to
NCC/ENCC and S/S works
necessary for NCC/ENCC End to End testing.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-3: Substations Built During Phase 5 & 6 and
GTC/53

All the required modifications in the remote end substations built under Phase 5 &
6 and GTC 53 projects shall be carried out under the present scope of work. The
scope of work shall include but not limited to the following:

Re-testing and re-commissioning of the existing GIS/ Switchgear bays in service


along with Local Control Panels including indicating meters in the local control
panels, inscription of additional alarm facia as required, replacing of GIS/
Switchgear name plates and any required works including, wiring, testing &
complete re-commissioning of the above GIS bays.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 408 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Protection systems as detailed under protection scope of work hereunder.

Protection:
- The required modification works for protection systems is detailed under
protection scope of work hereunder
- For those 66kV Cable feeders connected to new typical substation S/S,
complete functional protection system as per standard specification shall be
provided. Existing trip relays / TCS relays need to be replaced.
- New relays/equipment shall be installed at remote end substation to match the
(new) protection at new typical substation end.
- Contractor has to do proper CT sizing calculation and check the adequacy of
existing CTs. If required, CTs shall be replaced (unit rates in Price Schedule 4.5
will be applicable).
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

SCS and Power Control:


- Required modifications to existing SCS to include changes on the 66kV feeders
in the SCS and S/S works necessary for NCC/ENCC End to End testing.
- Existing BCUs shall be replaced to accommodate additional alarms.
- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS and S/S work necessary for remote signaling to
NCC/ENCC.

 Remote End Modification - TYPE-4: Substations Built During Phase 4 and


Earlier

All the required modifications in the remote end substations with indoor/ outdoor
switchgear supplied under Phase 4 and earlier projects built in early 1980s shall be
carried out under the present scope of work.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 409 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The contractors scope of work includes thorough checking and refurbishment of


the existing equipment to deliver fully working system. For Control and Protection
the contractor shall deliver new equipment as mentioned in the scope of work of
the protection works. The scope of work shall include but not limited to the
following:

Refurbishment of existing 66kV switchgear bays

Replacement of 66kV isolators, if required (to be quoted in price schedule as an


optional item)

The existing 66V control panels shall be modified as required to match with the
new cable feeder MVA rating. The new control panels shall be fully equipped with
ammeter, voltmeter, MW and MVAr meters etc. as per the technical specifications.

Existing Panel Transducers shall be replaced as applicable according to the


enhancement of CT/VT etc.

New Annunciations shall be provided in the local control cabinet in bays at remote
end substation.

Contractor shall check suitability of the existing termination female part in the GIS
considering the size of incoming cables from new typical substation. If necessary,
existing termination female parts shall be replaced by suitable one, including all
necessary material and works required for such modification and optional price for
the existing termination female part replacement and all associated works shall be
provided.

Replacing existing labels by new labels

Replacement of existing 66kV CTs and VTs as detailed under protection scope of
work hereunder. Contractor has to do proper CT sizing calculation. CTs shall be
replaced (unit rates in Price Schedule 4.5 will be applicable).

New Alarm facia equipment shall be installed on CP/RP to incorporate additional


alarms locally as well as remote NCC/DGCC.

Re-commissioning and Re-calibration of Tariff meters at generating stations shall


be envisaged as applicable if CT/VT capacities/ratios are changed.

SCS and Power Control:


- Required modifications in the existing SCS to include changes related to 66kV
feeders.
- Required modifications in the existing conventional control panel to include
changes on the 66kV feeders.
- Required modification to TMMC/TDB/RTU to incorporate the changes on the
66kV feeders in including NCC/ENCC end to end testing. The existing spare
capacity in the RTU shall be maintained. Old and faulty transducers shall be
replaced and all related testing shall be done.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 410 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- Existing BCUs shall be replaced to accommodate additional alarms.


- Alarms no more required shall be deleted and alarms related to modifications
are to be included in the SCS, conventional control panel and TMMC/TDB/RTU.

Protection:
- For the Cable feeders connected to New Typical Substation, complete
functional protection system as per standard specification shall be provided.
The new relays/equipment shall be installed at remote end substation to match
the new protection provided at 66kV New Typical Substation bays. Existing trip
relays / TCS relays need to be replaced.
- Remote end SLD to be incorporated in one of the 87C relay.
- Existing VTs installed under Phase 3 or earlier projects shall be replaced with
new three Phase, two core VTs.
- Replacement of the existing CTs to meet with new cable feeder rating. The new
CTs required parameters are given in Protection standard Specification and
standard CT ratio. The new CTs construction and other dimensions shall be
identical to the existing CTs so that it can be mounted in the limited space
available in the indoor switchgear bay (Or Outdoor switchgear bays). The
contractor shall be fully responsible for all associated works and required
interfaces. Contractor has to perform proper CT sizing calculation for Kahramaa
review.
- Modification of the existing bus bar protection, including conducting bus bar
stability and addition of modules if required shall be the responsibility of the
Contractor. Direct inter-trip for breaker failure, gas pressure low and bus bar
protection operation are to be made available between the stations based on
requirement.
- All modifications, testing and commissioning, relay setting calculations, relay
testing on final setting, end to end test, overall stability etc. and putting into
service is included in the Present Scope

PACKAGE S-18 TELECOMMUNICATION SYSTEM

3.18

3.18.1

INTRODUCTION
The works under the subject project includes substation works for establishment of new
transmission substation as well as modification of existing remote end transmission
substation.
This particular scope of works for telecommunication system must be read in conjunction
with other items of the subject document to obtain all details of specified scope of works.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 411 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

3.18.2

REV. 0

SCOPE OF WORKS FOR SUBSTATIONS PACKAGE

 DESCRIPTION OF WORKS
The works and services to be performed by the Contractor shall comprise the design,
manufacture, shop testing, packing, transport, insurance, unloading, storage at site,
construction works, erection, corrosion protection, site testing, submission of
documentation, commissioning, training of the Employers personnel and warranty of
works.
The Contractor is bound to provide complete works in order to provide a fully operational
telecommunication system even if the equipment or services required for this are not
specifically mentioned in the following description of the scope of works.
The obligation of the Contractor is to fully inform himself about the existing
telecommunication system and to provide all necessary new equipment, to make network
modification by upgrade of existing Kahramaas telecommunication equipment, and/or by
telecommunication system/network reconfiguration required for the connection of the new
and refurbished substations, as per Drawing Ref. No. TED-PH13-TEL-001 Rev. 0
Telecommunication Links Diagram, to existing Kahramaa Telecommunication
Network/System.
The Contractor shall make, based on Power Transmission Network and Fiber Optic
Cables network availability, the best design for the telecommunication connection of new
and refurbished/replaced S/Ss to Kahramaa Telecommunication Network/System.
The proposed design shall be based on the Power Transmission Network and shall
therefore consider necessary sizing of the Substations in terms of Optical Termination,
Optical Transmission System and cross connection facilities for potential future expansion
of the network.
The Contractor shall meet listed substations commissioning dates and therefore shall
establish telecom link to NCC/DCC/ENCC as required in order to allow energization of
S/Ss. In case that approved design cannot be applied at S/S commissioning date because
of FO links unavailability or any other reason, then the Contractor shall provide all
necessary temporary set up in order to establish the link on Kahramaa request and after
availability of the planned FO link the Contractor has to migrate to permanent link, as per
approved design, from such established temporary links. Cost of such temporary or
transitory works is assumed to be included in the contract price, and commissioning
spares shall be considered as required. Also, all necessary activity and materials required
and all coordination with concerned Kahramaa departments to shift telecom services
during outage from outage circuit to operational circuit shall be provided by the Contractor.
In case of refurbished/replaced S/S the Contractor is obliged, as mandatory, to maintain,
in addition to services for the new S/S, all telecommunication services at existing
substation until full power load is transferred to the new S/S.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 412 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The final design for telecommunication equipment is subject to Kahramaa approval before
manufacturing.
Kahramaa shall receive a detailed design engineering of new and refurbished/replaced
S/Ss interface to telecom network for review and approval. A Telecom Design Workshop is
required after award of Contract to discuss the topology before submitting proposal to
Kahramaa.
The obligation of the Contractor is to conduct all necessary co-ordination and all
necessary site survey in order to provide complete works for:

Indoor fiber optic cables.

Termination equipment for fiber optic cables.

Required telecom services.

Substation layout for telecom panels.

Power supply and telephone connection to the MUX equipment.

Coordination shall be done with all Phase 13 Contractors (Substations and Cables) as well
with other Kahramaa's Contractors which are currently active as follows:

Phase 12 Substation Contractors (GTC/643/2014),


(GTC/642/2014) and OHL Contractors (GTC/641/2014).

Phase 12 Telecom Contractors (GTC/643/2014).

Phase 11 Substation Contractors (GTC/488/2012 B, C, D, F, G & GTC/679/2014)


and Cable Contractors (GTC/450/2011 A, B, C, D, E, F, G, H, I, J).

Phase 11 Telecom Contractors (GTC/488/2012E &GTC/488/2012H).

NCC/DCC modification Contractor.

Phase 10: Substation


(GTC/372/2010 A; C).

Phase 10, Telecom Contractor (GTC/371/2010 E).

GTC/716/2014 - ESTABLISHMENT OF NEW DISTRIBUTION CONTROL


CENTRE AND EXTENSION PROJECT

Contractor

GTC/371/2010,

Cable

Cable

Contractors

Contractors

The new fiber cables under this project are to be provided by the Substation
Contractor/Cable Contractor and are 1 x 48 cores FO cable/OPGW associated with each
new power cable/OHL.
The brief Scope of Telecommunication Works includes the following:

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 413 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Connection of New Substations to the Kahramaa Telecommunication Network.

Connection of upgraded/replaced or modified substation by means of new


telecommunication equipment and services to the Kahramaa Telecommunication
Network.

Telecom Networks (ALSTOM & ABB networks) modification/re-configuration


resulting of cable diversions, etc. and re-routing of all affected services. This also
includes NMS modification, PAX modification (Alcatel), removal/addition of the
alarms to SCADA, etc.

In case of modification of existing Kahramaa Telecom Network/telecom equipment,


only original system supplier is acceptable to conduct these works and such works
shall be subcontracted to the Original Telecom Equipment Supplier.
To
enable
the
connection
of
these
Substations
to
the
KahramaaTelecommunication Network, the following works shall be provided:

existing

Fiber optic indoor cables.

Fiber Optic Termination equipment FOPPs / OTPs.

SDH and PDH Equipment.

Telephone equipment (in ALSTOM and ABB Telecom networks).

All Kahramaa Telecommunication Management Systems modifications or


upgrading resulting in modification of the Kahramaa Telecommunication Network.

Telecommunication power supply equipment.

Recovery of all services affected by the insertion of a new S/S in the network.

NOTE: For recovery of telecom services (in ALSTOM and ABB Telecom networks) due to
cable diversions only original system supplier is acceptable to conduct these works and
such works shall be subcontracted to the original Telecom Equipment Supplier directly, i.e.
either to ALSTOM or to ABB, as the case may be.

Works for telecommunication equipment dismantling.

Updating of all Existing Drawings and to update general documents such like
routing tables, overall network, IP addresses list, etc.

The detailed technical requirement for telecommunication system is given under the
General Technical Requirements and Technical Specifications in Volume 2 and Volume
3, Section 3.3.11 of GTC/735/2015, Tender Documents.
In case if new telecommunication equipment is proposed by the Contractor at existing
substation all modification works, necessary modifications in SCS/NCC for alarm signals
from telecom equipment shall be arranged in coordination with S/S contractor, but in case
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 414 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

of works on telecom equipment at existing substation without substation modification


works it is sole responsibility of Telecom Contractor for modification works in SCS/NCC
for alarm signals from telecom equipment.

The Contractor shall provide only new equipment and he is not allowed to re-use
any of dismantled equipment. Re-use of dismantled equipment is allowed only in a
case if official approval from Kahramaa is received.

 SUMMARY SCOPE OF WORKS


The Scope of Works as per Telecom Sections of Works i.e. milestones for this Contract is
summarized as follows:
 Works for Fiber Optical Indoor cables:
Works for fiber optic indoor cables to connect optical transmission equipment (Protection,
SDH or PDH equipment) to optical termination equipment (FOPP/OTP) at all stations.
 Works for optical termination equipment
Fiber Optic Patch Panels (FOPP) and Optical Termination Panel Cubicle (OTP) shall be
supplied by telecom contractor. Works for laying, splicing, termination and End to End
testing will be carried as follows.

GTC/735/2015, Substation Contractor, is responsible:


o

In case of Pilot Fiber Optic Cable laid along power cable inside substation
(Supply/installation, termination, splicing at joint closures and OTP/OTB,
including E2E test OTP/OTB - OTP/OTB) or in case of approach cable
within substation area to cable compound (Supply/installation, termination,
splicing at Hood Closure on Gantry and OTP/OTB, including E2E test
OTP/OTB - OTP/OTB) as it has been listed under price schedule for
substations package.

In case of OPGW (Supply/installation, installation splicing at OPGW Joint


Closures, OPGW termination at Hood Closure with splicing, including E2E
test Hood Closure - Hood Closure) as it has been listed under price
schedule for substations package.

In case of FO cables between new substation building and existing


substation building (Supply/installation, termination, splicing and End-toEnd test) as it has been listed under price schedule for substations
package.

GTC/736/2015, Cable Contractor, is responsible in case of Pilot Fiber Optic Cable


(Supply/installation, termination/splicing at OTP/OTB including E2E test OTP/OTB
- OTP/OTB) as it has been listed under price schedule for cables package.

 Works for SDH and PDH equipment

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 415 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The works required shall include all necessary works to include the new and
refurbished/replaced/upgraded substations into the existing Kahramaa Telecommunication
Network as per drawing ref. TED-PH13-TEL-001 Rev. 0 Telecommunication Links
Diagram, Technical Specification Section 3.3.11, and Appendix B Price Schedule.
The drawing TED-PH13-TEL-001 Rev. 0 Telecommunication Links Diagram indicates the
connections between substations. For more details, the Contractor shall refer to
Substations and Cables scope of works.
All S/Ss with fiber optic cable terminated shall have multiplexer equipment with optical
interface.
The scope of work is summarized as follows:

Establishment of dual SDH links STM-4 (400 kV and 220 kV substations shall have
STM-4 equipment as minimum). Kahramaa shall receive a detailed design
engineering of the telecom network for review and approval. A Telecom design
workshop is required after the award of contract to discuss the topology before
submission to Kahramaa.

Each new and refurbished/replaced/upgraded Substations require the following


services to be transferred to NCC, ENCC and DCC:
- Two PAX extensions one for NCC PAX and one for DCC PAX with respectively
3 telephones connected in parallel at the substation
- Two IEC-104 64 kbps TCP/IP connections from SCS gateways to DCC
(SCADA).
- Two IEC-104 64 kbps TCP/IP connections from SCS gateways to NCC and
switching to ENCC (SCADA).

NOTE: NCC/ENCC and DCC SCADA connections shall be fully segregated.

4 Non SCADA channels as follows:


- One Ethernet connection (2Mb/s minimum) to NCC for CMS.
- Necessary connectivity to be provided for the channel to reach Kahramaa2
building using the existing link between NCC and Kahramaa2.
- One Ethernet connection (2Mb/s minimum) to NCC for remote access to SCS
LAN at substation (For Fault recorder, Parameter settings).
- One Ethernet connection connected to PMR file server at NCC and ENCC.
- One Ethernet connection (2Mb/s minimum, bandwidth requirement to be
coordinated with Substation Contractor) to NCC for CCTV.
- Non SCADA channel bandwidth shall be coordinated with S/S Contractors.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 416 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

- All channels shall be segregated, and a mechanism shall be proposed to


establish a 2 way communication between S/S and control centers and avoid
communications between S/Ss.
- Digital input alarm card with a minimum of 16 inputs.
- Engineering order wire; maintenance service telephone at MUX level. Exact
channel requirements depend on the Substation and SCS design.
NOTE: Contractor shall closely coordinate with Substation Contractor and SCS supplier to
meet any of his requirements with respect to communication channel to NCC, DCC and
ENCC.

Full works for Emergency switching to ENCC (Emergency National Control


Centre).

Recovery of all services after the dismantling of any component or equipment or


when diversions are made including removal of applicable alarms from
NMS/SCADA.

Any equipment not running any services to be dismantled and delivered to


Kahramaa.

Recovery of services and network re-configuration for all the S/S connected above
a modified S/S in all affected Kahramaa Network.

All other necessary Extensions/modifications work in existing MUX equipment to


connect the new substations to NCC, DCC, ENCC or any other substations.

All necessary works for migration of existing communication links and services to
the new location at all refurbished/replaced substations.

Maintain 20% equipped spares or existing percentage of spares in case that less
than 20% spares are available in the Kahramaa Telecommunication System at
NCC/ENCC/DCC.

Since new Ethernet switch shall be provided in NCC to enable the PMR service. All
necessary Works to shift the PMR server and existing link to new switches in
coordination with SCS contractor.

 Works for telephone equipment

Works for telephone equipment at DCC telephone Exchanges and at NCC


telephone Exchanges to interconnect two (2) extensions at each new substation.
Extension shall be in 2 different cards, one each for NCC and DCC, in the MUX at
substation side.

Providing minimum six executive tables/wall mounted Telephone sets at each


station paralleled together (three to NCC and three to DCC) and all necessary
works to connect to telecommunication equipment. Telephone sets are required to
be installed in Control Room (2), LVAC/DC Room (1), Fire Pump House (1), each

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 417 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Switchgear Room (1) and Telecom room (1).Each switchgear room (11kV
onwards) will have Telephone set, additional sets, other than six, shall be
considered by the contractor.

In underground stations, Telephone sets shall be provided in all rooms/basements,


transformer areas, near each entrance on the ground floor. Two bells shall be
provided in underground substations.

One unit 240 V AC outdoor bell for each new and refurbished/replaced substation
and all necessary related works.

Work for PAX configuration (Alcatel) to fully interconnect the telecom network.

Maintain 20% spares or existing percentage of spares in case that less than 20%
spares are available in the Kahramaa Telephone System at NCC/DCC (Alcatel).
Additional hardware shall be provided, so as to maintain the spare capacity.

 Works for Telecommunication Management System (TMS)

All communication system shall be compatible with the existing NMS systems.

Works on existing Telecommunication Management Systems to include all new


telecommunication Equipment (allowing equipment monitoring, reporting,
controlling, configuring etc.).

All necessary outstation equipment to connect telecom 48VDC power supply (UPS
at new and UPS or 48VDC at existing), Telecommunication Equipment alarms;
TMS alarm list is to be approved by Kahramaa (16 digital inputs minimum).

Works shall include the Software and Hardware Modifications of one or more
existing TMS System to connect the new Substations.

The NMS license should be upgraded for the required additional nodes keeping
20% spare.

Respective NMS modification resulting of Network modification or node


cancellation.

 Works for telecommunication power supply equipment

The following to be included under telecom Contractors part:

Works for connection of new telecom equipment to 240 V AC UPS as per LV


Service Equipment Volume 3, Section 3.3.5 of GTC/735/2015, Tender Documents,
provision of power cables from UPS MCBs to Telecom equipment and provision of
data cables between alarm terminal blocks at UPS and alarm terminals blocks at
Telecom equipment. No 48VDC power supply is required at new substation.

All works for Telecom chargers and 48VDC Batteries at relative existing
substations to accept new equipment or modifications/upgrading of existing

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 418 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

equipment including, survey, calculations, connecting, documentation and DC


distribution extensions etc.

All works for 240VAC UPS and 110VDC Batteries at relative existing substations to
accept new telecommunication equipment or modifications/upgrading of existing
equipment including, survey, calculations, connecting, documentation and AC
distribution extensions, etc.

The dismantled UPS, Batteries or Battery charger equipment shall be delivered to


Kahramaa stores packed and labeled as per Kahramaa regulations.

240 VAC / 48 VDC converter shall be sized with enough spare power capacity for a
fully equipped cabinet.

 Works for Teleprotection Equipment


Telecom contractor shall be responsible for:

Dismantling of Teleprotection Equipment, as stated in detailed Scope of Work for


individual substation.

All unused wiring related to Teleprotection Equipment shall be removed.

All alarms related to dismantled Teleprotection Equipment shall be removed from


local SCS/NMS/SCADA.

 Works for PLC Equipment


Telecom contractor shall be responsible for:

Dismantling of PLC equipment (and associated teleprotection equipment), as


stated in detailed Scope of Work for individual substation.

All unused wiring related to PLC Equipment shall be removed.

All alarms related to dismantled PLC Equipment shall be removed from local
SCS/NMS/SCADA.

 Works for migration of existing telecom services at/or routed via refurbished /
replaced substations.

Recovery of telecom services affected by OHLs/power cables dismantling and/or


connection's re-arrangement including Network optimization.

Updating of Existing Drawings.

Updating of all network drawings with the same existing format.

 Master Drawing shall be delivered updating the entire network delivered by the
Contractor during past projects (including bulk consumers) in editable format.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 419 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

This shall include but not limited to:

Overall updated Network.

Digital Block Diagram.

Routing Table.

IP addresses.

NMS network (IP and scheme).

FO network and utilization.

Telephone network and numbering plan.

Updating of relevant existing sites (modified substations) drawings using same


existing format (accessible format; PDF or locked formats are not acceptable).

Updating of All general documents such like routing tables, overall network, IP
addresses list etc.

 LIST OF NEW SUBSTATIONS


The new Substations to be connected to the Kahramaa telecommunication network are as
follows:
Package

Name of substation
Al Shahhaniyah Super - New 220/132/11kV

S-1

Al Shahhaniyah South - New 132/11kV


Lebsayyer - New 132/11kV
Doha Super (Upgrade) 220/66/11 kV
Al Waab Super (Upgrade) 220/132/11 kV
Umm Ebairiya - New 132/66/11kV

S-2

Umm Garn - New 132/11kV


Umm Al Amad 1- New 66/11kV
Umm Al Ghahab - Existing 66/11kV (Replacement)
Abu Thailah (Upgrade) 66/11 kV

S-3

Al Jahaniyah-2 - New 132/11kV


Izghawa North - New 132/11kV

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 420 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

REV. 0

Name of substation
Wakrah 3 - New 132/11kV
Mesaieed Ind A (Upgrade) 132/11 kV

S-4

Bin Mahmoud North - New 66/11kV


New Assiri - Existing 66/11kV (Replacement)
Salwa Road - Existing 66/11kV (Replacement)
Musherib - Existing 66/11kV (Replacement)
Murrah South - New 66/11kV

S-5

Umm Al Seneem 2 - New 66/11kV


Al Waab 2 - New 66/11kV
Al Waab (Upgrade) 66/11 kV

S-6

Ain Sinan - 132/11kV


Jeryan Jenihat 1 - 132/11kV
Museum Road - 66/11kV (Upgrade)
Maither Central (Upgrade) 132/66/11 kV

S-7

New Doha E - 66/11kV (Replacement)


Salata - 66/11kV (Replacement)
Mashaf 1 - New 132/11kV

S-8

Mashaf 2 - New 132/11kV


Mashaf 3 - New 132/11kV
Al Wukair 10 - New 132/11kV
Al Wukair 6 - New 132/11kV

S-9

Al Wukair 7 - New 132/11kV


Al Wukair 8 - New 132/11kV
Al Wukair 9 - New 132/11kV
Al Wukair 2 - New 132/11kV

S-10

Al Wukair 3 - New 132/11kV


Al Wukair 4 - New 132/11kV
Al Wukair 5 - New 132/11kV

S-11
GTC-735 SCOPE OF WORKS R0

Rawdath Al Khail-2 - New 66/11kV


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 421 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

REV. 0

Name of substation
Abu Hamour West - 66/11kV
Luaib - 66/11kV
Abu Samra (Upgrade) 33/11 kV

Parallel running of both new and old telecom equipment will be required at above
substations where (Upgrade) is notified. If by substation contractors SCADA channels are
shifted to new telecom, old telecom shall be dismantled and network reconfigured.
Scope of work includes necessary upgrade of remote end S/S to incorporate all the new
S/S to the Kahramaa Telecommunication Network.
Scope of work also includes recovery of all services at any existing S/S affected by the
addition of a new S/S or the insertion between 2 or more S/Ss. The Contractor shall inform
himself of Fiber Optic utilization and telecom network and to plan links accordingly. This
includes patching, network reconfiguration or any other action.
 WORKS AT EXISTING SUBSTATIONS
Here below is an informative list of existing substations where modifications such as:
Provision / Upgrade of OTP/FOPPs, works for interfacing of new substations with
Kahramaa Telecom Network, necessary telecom routing of effected substations due to
new cable line LILO, etc., respectively, shall be done.

Package

Name of substation
400/220/66/11kVUmm Al Amad Super

S-1

220/66/11kV Doha Super


220/132/66/11kV Naeeja Super
220/66/11kV Abu Hamour Super
220/66/11kV Doha South Super
400/220/66/11kV Al Sadd Super
220/132/11kV Al Thumamah
132/66/11kV Old Airport

S-2

GTC-735 SCOPE OF WORKS R0

400/132/11kV Al Sakhamah

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 422 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

REV. 0

Name of substation
400/220/66/11kVUmm Al Amad Super
132/11kVSemaismah

S-3

220/132/66/11kVBani Hajer Super


132/11kVAl Jahhaniya 1
132/11kV Barzan Camp 1
220/132/66/11kVDoha North Super
132/11kV Ras Abu Fontas South
132/11kV QEZ
132/11kV Wakrah North

S-4

400/220/66kV Al Sadd Super

S-5

66/11kVDoha Industrial B
220/132/66/11kVDoha Industrial Super
66/11kVAin Khalid North
66/11kVVegetable Market
220/132/11kVMehairja Super
220/132/66/11kV Al Waab Super

S-6

132/11kV Madinat Al Kabaan


220/132/11kV Jeryan Jenaihat Super
132/11kV Al Khissa West
66/11kV Montazah North
66/11kV Old Ghanem

S-7

220/66/11kV West Bay Super 2


220/66/11kVNew Doha A Super

S-8

400/132/11kVBul Hemmaid
132/11kV Ras Abu Fontas South

S-9

400/132/11kVBul Hemmaid

S-10

132/11kV Al Wukair 1
132/11kV QEZ

S-11
GTC-735 SCOPE OF WORKS R0

66/11kV Rawadat Al Khail


TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 423 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

REV. 0

Name of substation
66/11kV Al Wadi West
220/132/11kVMehairja Super

At some of the existing substations it is necessary to do dismantling of existing equipment


and to shift the same to Kahramaa store as per list below.
Package

S-1

S-1

S-2

GTC-735 SCOPE OF WORKS R0

Name of substation

Scope of Works


Works for upgrade/replacement


existing telecommunication
equipment at Doha Super.
Parallel running of both new and
old telecom shall be required.
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.

Works for upgrade/replacement


existing telecommunication
equipment at Al Waab Super.
Parallel running of both new and
old telecom shall be required.
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.

Dismantling of PLC and


associated Teleprotection
equipment working over OHL
Umm Salal - Umm Al Ghalab and
shifting of the same to KM store,
after packaging/labeling.

Works for removal of all


applicable alarms from local
SCS/NMS/SCADA and all other
applicable places.

Doha Super (Upgrade)


220/66/11 kV

Al Waab Super (Upgrade)


220/132/11 kV

66/11kV Umm Al Ghahab


(Replacement)

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 424 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

Name of substation

REV. 0

Scope of Works


Works for upgrade/replacement


existing telecommunication
equipment at Abu Thailah.
Parallel running of both new and
old telecom shall be required.
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall be
dismantled and shifted to KM
store.

FOPP to be renamed.
Necessary telecom routing of
effected substations due to
diversion of OHL Umm Salal Abu Thailah from Umm Salal S/S
to Um Ebariya S/S.
Dismantling of PLC and
associated Teleprotection
equipment working over OHL
Umm Salal - Abu Thailah and
shifting of the same to KM store,
after packaging/labeling.
Dismantling of TSTU working over
OPGW and shifting of the same to
KM store, after
packaging/labeling.
Works for removal of all
applicable alarms from local
SCS/NMS/SCADA and all other
applicable places.

S-2

66/11kVAbu Thailah
(Upgrade)

S-2

132/66/11kV Umm Salal

GTC-735 SCOPE OF WORKS R0

Dismantling of PLC and


associated Teleprotection
equipment working over OHL
Umm Salal - Abu Thailah and
shifting of the same to KM store,
after packaging/labeling.
Dismantling of TSTU equipment
working over OPGW Umm SalalAbu Thailah and shifting of the
same to KM store, after
packaging/labeling.
Dismantling of PLC and
associated Teleprotection
equipment working over OHL
Umm Salal - Umm Al Ghalab and
TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 425 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

Name of substation

REV. 0

Scope of Works

S-3

S-4

S-4

S-4

S-5

GTC-735 SCOPE OF WORKS R0

Dismantling of existing TSTU


equipment at Mesaieed Ind A and
associated substations (MIB and
Qasco 1) as per agreed
protection scheme, including
removal of all accompanied patch
cords, removal of applicable
alarms from local SCS and
control Centers.

Works for dismantling existing


telecommunication equipment at
New Assiri.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.

Works for dismantling existing


telecommunication equipment at
Salwa Road.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.

Works for dismantling existing


telecommunication equipment at
Musherib.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.

Works for upgrade/replacement


existing telecommunication
equipment at Al Waab.
Parallel running of both new and
old telecom may be required
during commissioning of

Mesaieed Ind A (Upgrade)


132/11 kV

New Assiri - Existing


66/11kV (Replacement)

Salwa Road - Existing


66/11kV (Replacement)

Musherib - Existing 66/11kV


(Replacement)

Al Waab (Upgrade) 66/11


kV

shifting of the same to KM store,


after packaging/labeling.
Works for removal of all
applicable alarms from local
SCS/NMS/SCADA and all other
applicable places.

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 426 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

Name of substation

REV. 0

Scope of Works
substation.
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.


S-6

Museum Road - 66/11kV


(Upgrade)

If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.


S-6

S-7

Maither Central (Upgrade)


132/66/11 kV

Salata - 66/11kV
(Replacement)

S-11

Abu Samra (Upgrade)

GTC-735 SCOPE OF WORKS R0

Works for upgrade/replacement


existing telecommunication
equipment at Maither Central.
Parallel running of both new and
old telecom shall be required.
If by substation contractors
SCADA channels are shifted to
new telecom, old telecom shall
be dismantled and shifted to KM
store.

Works for dismantling existing


telecommunication equipment at
New Doha E.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.

Works for dismantling existing


telecommunication equipment at
Salata.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.

Works for replacement existing


telecommunication equipment at

New Doha E - 66/11kV


(Replacement)

S-7

Works for upgrade/replacement


existing telecommunication
equipment at Museum Road.
Parallel running of both new and
old telecom shall be required.

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 427 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

Name of substation

REV. 0

Scope of Works

33/11 kV

Abu Samra.
Parallel running of both new and
old telecom may be required
during commissioning of
substation.


3.18.3

Dismantling of existing TSTU


equipment at Abu Samra and
associated substations as per
agreed protection scheme,
including removal of all
accompanied patch cords,
removal of applicable alarms
from local SCS and control
Centers.

SCOPE OF WORKS FOR FRAMEWORK CABLES / SUBSTATIONS

 DESCRIPTION OF WORKS
The Contractor is bound to provide complete works to provide fully operational
telecommunication equipment at Framework S/S even if the equipment or services
required for this are not specifically mentioned in the following description of the scope of
works.
The obligation of the Contractor is to fully inform himself about the existing Kahramaa
Telecommunication Network/System and to provide all necessary new equipment, to
make network modification by upgrade of the existing Kahramaas telecommunication
equipment, and/or by telecommunication system/network reconfiguration required for
connection of the new Framework S/S to existing Kahramaa Telecommunication
Network/System.

There will be two FO cables, each 48 cores, laid between Framework S/S and
downstream/upstream S/S, to be provided under Cable Contractors
(GTC/736/2015) and to be utilized for FO connectivity of Framework S/S to
Kahramaa Telecommunication Network/System.

The Contractor shall make, based on Power Transmission Network and Fiber Optic
Cables network availability, the best design for the telecommunication connection of
Framework S/S to Kahramaa Telecommunication Network/System.
In order to meet Framework S/S commissioning date the Contractor shall establish
telecom link to NCC/ENCC/DCC as required in order to allow energization of Framework

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 428 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

S/S. In case that approved design for telecommunication equipment cannot be applied at
Framework S/S commissioning date because of Fiber Optic Cables unavailability or any
other reason, then the Contractor shall provide all necessary temporary set up in order to
establish the telecom link for Framework S/S on Kahramaa request without any additional
cost impact and after Fiber Optic Cables availability of the planned FO link the Contractor
has to migrate to permanent FO link, as per approved design, for such temporary
established links.
The final design for telecommunication equipment is subject to Kahramaa approval before
manufacturing.
Kahramaa shall receive a detailed design engineering of the Framework S/S interface to
telecom network for review and approval. A Telecom design workshop is required after
the award of contract to discuss the topology before submitting proposal to Kahramaa.
The obligation of the Contractor is to conduct all necessary co-ordination and all
necessary site survey in order to provide complete works for:

Fiber optic connectivity of Framework S/S to Kahramaa Telecommunication


Network/System via downstream/upstream S/S.

Required telecom services.

Substation layout for Telecom room for allocation of telecom panels.

Power supply and telephone connection to the MUX equipment.

The brief scope of works include the following:


 Provision of OTP/FOPP for termination of fibre optic cables from Cables Contract
Packages C-11; C-12; C-13 and C-14 Framework for Cable Contractors
(GTC/735/2015).

Provision and installation of new telecommunication equipment at Framework S/S


and wherever it is required as per approved design.

Connection of Framework S/S to existing Kahramaa telecom network. This


includes all necessary modification/re-configuration on Existing Kahramaa Telecom
Network(s) (ALSTOM & ABB Networks) required to enable this connection.

NMS modification, PAX modification (Alcatel), removal/addition of alarms to


SCADA, etc. and re-routing of all affected services.

Only personnel, certified by ALSTOM / ABB and, approved by Kahramaa and in presence
of Kahramaas staff, is allowed to work on existing telecom equipment belonging to
respective telecom vendors (ALSTOM; ABB).or such works shall be subcontracted to the
Telecom Equipment Supplier.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 429 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The detailed technical requirement for new telecommunication equipment is given under
the General Technical Requirements and Technical Specifications in Volume 2 and
Volume 3, Section 3.3.11 of Tender Documents.
The Scope of Works is summarized as follows:
Works for Fiber Optical Indoor cables:

Works for fiber optic indoor cables to connect optical transmission equipment (SDH
or PDH equipment) to optical termination equipment (FOPP/OTP/OTB).
Works for Optical Termination Equipment

Fiber Optic Patch Panels (FOPP) and Optical Termination Panel Cubicle (OTP)
required for Framework Cables as well as to be installed at Framework S/S.
FO cables termination and E2E Tests of fiber optic cables shall be responsibility of
the cable contractor.
Works for SDH and PDH equipment

These works include connection of Framework substation into the existing Kahramaa
Telecommunication Network as per Technical Specification Section 3.3.11, and
Appendix B Price Schedule.
The following services are required to be transferred to NCC, ENCC and DCC for
Framework substation:

Establishment of dual SDH (or PDH) link for Framework S/S.

DCC network, if required, has to be fully independent from NCC/ENCC network


(hardware and software wise).

Two PAX extensions one for NCC PAX and one for DCC PAX with respectively 3
and 3 telephones connected in parallel at the Framework S/S (Minimum six
telephone sets and one outdoor bell). Telephone sets are required to be installed in
Control Room (2), LVAC/DC Room (1), Fire Pump House (1), each Switchgear
Room (1) and Telecom room (1).

Two IEC-104 64 kbps TCP/IP connections from SCS gateways to DCC (SCADA).

Two IEC-104 64 kbps TCP/IP connections from SCS gateways to NCC and
switching to ENCC (SCADA).

One Ethernet connection (2Mb/s minimum) to NCC for TMS / RMS Monitoring
System.

One Ethernet connection (2Mb/s minimum) to NCC for remote access to SCS LAN
at substation (For Fault recorder, Parameter settings ).

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 430 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

One Ethernet connection connected to PMR file server at NCC and ENCC.

One Ethernet connection (2Mb/s minimum) to NCC for CCTV.

Digital input alarm card with a minimum of 16 inputs.

Engineering order wire; maintenance service telephone at MUX level.

Connection to substation GPS for telecom equipment synchronization purpose.

Full works for Emergency switching to ENCC (Emergency National Control


Centre).

Recovery of all services after the dismantling of any component or equipment or


when diversions are made including removal of applicable alarms from
NMS/SCADA.

Any equipment not running any services to be dismantled and delivered to


Kahramaa.

All other necessary extensions/modifications work in existing MUX equipment to


connect the new substation to NCC, DCC, ENCC or any other substations.
The exact channel requirements for Framework substation depend on the Substation
and SCS design. The Contractor shall closely internally coordinate with Telecom and
Substation Sub Contractor and SCS supplier to meet any of his requirements with
respect to communication channel to NCC, DCC and ENCC.
Works for Telephone Equipment

REV. 0

Works for telephone equipment at DCC telephone Exchanges and at NCC


telephone Exchanges to interconnect two (2) extensions at Framework S/S.
Extension shall be in 2 different cards, one for NCC and another for DCC in the
MUX at substation side.

Provision of six executive tables/wall mounted Telephone Sets at Framework S/S


connected in parallel (three to NCC and three to DCC) and all necessary works to
connect to telecommunication equipment.

Provision of one unit 240V AC outdoor bell at Framework S/S and all necessary
related works.

Work for PAX configuration (Alcatel) to fully integrate PAX extensions/telephones


located at Framework S/S.

Maintain 20% spares or existing % of spares in case that less than 20% spares are
available in the Kahramaa Telephone System at NCC/DCC (Alcatel PAX).

Works for Telecommunication Management System (TMS)

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 431 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Works shall include the Software and Hardware Modifications of one or more
existing Telecommunication Management (TMS) Systems to include all new
telecommunication equipment at Framework S/S (allowing equipment monitoring,
reporting, controlling, configuring etc.).

The NMS license should be upgraded for the required additional node(s) keeping
20% spare.

All communication system shall be compatible with the existing NMS systems.

Works on respective NMS modification resulting of network modification or node


cancellation

All necessary outstation equipment to connect telecom 48VDC power supply (UPS
at new and UPS or 48VDC at existing), telecommunication equipment alarms.

TMS alarm list is to be approved by Kahramaa (16 digital inputs minimum).

Works for Telecommunication Power Supply Equipment

Works for connection of new telecom equipment to 240V AC UPS as per LV


Service Equipment Volume 3, Section 3.3.5 of Tender Documents, provision of
power cables from UPS MCBs to Telecom equipment and provision of data cables
between alarm terminal blocks at UPS and alarm terminals blocks at Telecom
equipment. 240 VAC / 48 VDC converters shall be sized with enough spare power
capacity for a fully equipped cabinet.

All works for Telecom chargers and 48VDC Batteries at relative existing
substations to accept new telecommunication equipment, if any, or
modifications/upgrading of existing equipment including, survey, calculations,
connecting, documentation and DC distribution extensions etc.

All works for 240VAC UPS and 110VDC Batteries at relative existing substations to
accept new telecommunication equipment, if any, or modifications/upgrading of
existing equipment including, survey, calculations, connecting, documentation and
AC distribution extensions etc.
The dismantled UPS, Batteries or Battery charger equipment shall be delivered to
Kahramaa stores packed and labeled as per Kahramaa regulations.
Engineering works, updating of the existing drawings

Updating of all existing network drawings in the same existing format shall be
done.
This shall include but not limited to:

Overall updated Network.

Digital Block Diagram.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 432 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Routing Table.

IP addresses.

NMS network (IP and scheme).

FO network and utilization.

Telephone network and numbering plan.

Updating of relevant existing sites (modified substations) drawings using same


existing format (accessible format; PDF or locked formats are not acceptable).

 LIST OF NEW FRAMEWORK CABLES / SUBSTATIONS


The new Framework Cables / Substations to be connected to the Kahramaa
Telecommunication Network are as follows:
Cables:
Package

Name of substation
132 kV New Cables

C-11

132 kV New Cables


132 kV New Cables
132 kV New Cables (LILO)
132 kV New Cables
132 kV New Cables

C-12
132 kV New Cables
132 kV New Cables (LILO)
66 kV New Cables
66 kV New Cables
C-13
66 kV New Cables
66 kV New Cables (LILO)
C-14

GTC-735 SCOPE OF WORKS R0

66 kV New Cables

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 433 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

REV. 0

Name of substation
66 kV New Cables
66 kV New Cables
66 kV New Cables (LILO)

Substations:
Package

S-12

Name of substation
Framework Substation - New 220/66/11kV
Framework Substation - New 220/132/11kV
Framework Substation Type A-1 - New 132/11kV
Framework Substation Type A-2 - New 132/11kV

S-13

Framework Substation Type B-1 - New 132/11kV


Framework Substation Type B-2 - New 132/11kV
Framework Substation Type C-1 - New 132/11kV
Framework Substation Type A-1 - New 132/11kV
Framework Substation Type A-2 - New 132/11kV

S-14

Framework Substation Type B-1 - New 132/11kV


Framework Substation Type B-2 - New 132/11kV
Framework Substation Type C-1 - New 132/11kV
Framework Substation Type A-1 - New 66/11kV
Framework Substation Type A-2 - New 66/11kV

S-15

Framework Substation Type B-1 - New 66/11kV


Framework Substation Type B-2 - New 66/11kV
Framework Substation Type C-1 - New 66/11kV
Framework Substation Type A-1 - New 66/11kV

S-16

Framework Substation Type A-2 - New 66/11kV


Framework Substation Type B-1 - New 66/11kV
Framework Substation Type B-1 - New 66/11kV

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 434 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

Package

REV. 0

Name of substation
Framework Substation Type C-1 - New 66/11kV
Framework Substation Type A/C - New 66/11kV
Framework Substation Type A/U-1 - New 66/11kV

S-17

Framework Substation Type A/U-2 - New 66/11kV


Framework Substation Type B/C - New 66/11kV
Framework Substation Type B/U-1 - New 66/11kV
Framework Substation Type B/U-2 - New 66/11kV

Scope of work includes necessary upgrade of remote end S/S to incorporate all the new
S/S to the Kahramaa Telecommunication Network.
Scope of work also includes recovery of all services at any existing S/S affected by the
addition of a new S/S or the insertion between 2 or more S/Ss. The Contractor shall inform
himself of Fiber Optic utilization and telecom network and to plan links accordingly. This
includes patching, network reconfiguration or any other action.
3.18.4

OPTIONAL SCOPE OF WORK


Optional scope of work includes provision of IP/MPLS and IP phones equipment to
operate in Kahramaa communication network instead of PDH/SDH equipment and analog
phones so the Contractor shall quote this equipment as indicated in Price Schedule.
The Contractor shall coordinate with Contractor for Kahramaa Contract GTC/716/2014 ESTABLISHMENT OF NEW DISTRIBUTION CONTROL CENTRE AND EXTENSION
PROJECT.

PACKAGE S19

3.19

3.19.1

INSTALLATION OF CAPACITOR BANKS


Kahramaa has made a study, which have shown necessity for installation of the new
Capacitor banks at the existing 11kV switchgear of several primary substations.
Some substations, built under recent Kahramaa projects like Phase 10 onward, are
already equipped with the two (2) bays for capacitor bank per 11kV switchgear and the
Space for capacitor banks along with space for vacuum contactor panels for the capacitor
banks in the substation layout. Other substations are not equipped with the bays for
capacitor banks on 11kV switchgear or with the space in the substation layout.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 435 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Some of the substations are currently under construction and the proposed commissioning
date for the capacitor banks shall match the substation commissioning should there be
any unforeseen delays in the substation commissioning.
Installation of the new Capacitor banks shall be as follows:
 Gharafa 132/66/11kV S/S
Gharafa is existing substation built under phase 4 and further upgraded by M/s L&T under
Phase 10 project. Modification of the existing 132/66/11kV Gharafa substation shall be as
follows:

Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;

Install vacuum contactor panels for the capacitor banks;

Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout. Isolation fence shall be
modified to enable construction of the facilities.

All required civil works related to new building including building services.

11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Required Modifications to SCS supplied by Siemens under Phase 10 project to


include installation of capacitor banks in the SCS including Gateway Data mapping
to DCC/ENCC and S/S works necessary for DCC/ENCC End to End testing.

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope.

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Naeeja West 132/66/11kV S/S


Naeeja West is existing substation built under phase 9 project by M/s Siemens.
Modification of the existing 132/66/11kV Naeeja West substation shall be as follows:

Install 3x11kV 8MVAr automatic shunt Capacitors;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 436 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 3;

Convert the existing 11kV cable feeder bay in Busbar 2 into Capacitor bank bay,
including replacement of CTs;

Install one (1) 11kV cable feeder bay on spare space in Busbar 1 or 3;

Modification in Schematic Diagrams on 66/11kV Transformer Feeder 11kV Side of


A18, A28 and A38 to provide CT inputs for capacitor bank control panel.

Modification in Schematic Diagrams on 11kV Bus VT-1, VT-2 and VT-3 to provide
VT inputs for capacitor bank control panel.

Existing CTs (400/1A) shall be replaced with the new ones, as per the CT sizing
calculation.

11kV, 1x500mm2, XLPE, 8MVA, triple circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Installation of one (1) 11kV outgoing cable feeder between new cable feeder bay
and service corridor outside the Substation boundary wall, included but not limited
to cable laying, cable supports, cable cleats, heat shrinkable caps and
commissioning tests. Cables and terminations will be supplied by KAHRAMAA.
Contractor shall coordinate with concerned KAHRAMAA department.

Space for the capacitor banks is available in the place of the old substation;

All required civil works related to new building including building services.

Installation of vacuum contactor panels for the capacitor banks;

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes on the 11kV switchgear and installation of capacitor banks in the
SCS including Gateway Data mapping to DCC/ENCC and S/S works necessary for
DCC/ENCC End to End testing;

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope;

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 SED 132/66/11kV S/S

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 437 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

SED is existing substation built under phase 3 and further refurbished by M/s L&T under
Phase 11 project. Modification of the existing 132/66/11kV SED substation shall be as
follows:

Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;

Install vacuum contactor panels for the capacitor banks;

Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout.

All required civil works related to new building including building services.

11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Required Modifications to SCS of ABB make supplied by L&T under Phase 11


project to include installation of capacitor banks to the SCS including Gateway
Data mapping to DCC/ENCC and S/S works necessary for DCC/ENCC End to
End testing.

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope.

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Asmakh 66/11kV S/S


Asmakh is a new substation currently under construction on Phase 12 project. Modification
of the existing 66/11kV Asmakh substation shall be as follows:

Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;

Install vacuum contactor panels for the capacitor banks;

Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout.

All required civil works related to new building including building services.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 438 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Required Modifications to SCS supplied under Phase 12 project to include


installation of capacitor banks to the SCS including Gateway Data mapping to
DCC/ENCC and S/S works necessary for DCC/ENCC End to End testing.

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope.

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Feriq Al Ameer 66/11kV S/S


Feriq Al Ameer is existing substation built under phase 11 project by M/s NCC.
Modification of the existing 66/11kV Feriq Al Ameer substation shall be as follows:

Install 4x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays;

Install vacuum contactor panels for the capacitor banks;

Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout

All required civil works related to new building including building services.

11kV, 1x500mm2, XLPE, 6MVA, quadruple circuit, solid bonded (one cable per
phase) between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Required Modifications to SCS of Siemens make supplied by NCC under Phase 11


project to include installation of capacitor banks to the SCS including Gateway
Data mapping to DCC/ENCC and S/S works necessary for DCC/ENCC End to
End testing.

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope.

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 439 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Khalifat 66/11kV S/S


Khalifat is existing substation built under phase 9 project by M/s Siemens. Modification of
the existing 66/11kV Khalifat substation shall be as follows:

Install 3x11kV 8MVAr automatic shunt Capacitors;

Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 3;

Convert the existing 11kV cable feeder bay in Busbar 2 into Capacitor bank bay,
including replacement of CTs;

Install one (1) 11kV cable feeder bay on spare space in Busbar 1 or 3;

Modification in Schematic Diagrams on 66/11kV Transformer Feeder 11kV Side of


A18, A28 and A38 to provide CT inputs for capacitor bank control panel.

Modification in Schematic Diagrams on 11kV Bus VT-1, VT-2 and VT-3 to provide
VT inputs for capacitor bank control panel.

Existing CTs (400/1A) shall be replaced with the new ones, as per the CT sizing
calculation.

11kV, 1x500mm2, XLPE, 8MVA, triple circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Installation of one (1) 11kV outgoing cable feeder between new cable feeder bay
and service corridor outside the Substation boundary wall, included but not limited
to cable laying, cable supports, cable cleats, heat shrinkable caps and
commissioning tests. Cables and terminations will be supplied by KAHRAMAA.
Contractor shall coordinate with concerned KAHRAMAA department.

Space for the capacitor banks is available;

All required civil works related to new building including building services.

Installation of vacuum contactor panels for the capacitor banks;

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes on the 11kV switchgear and installation of capacitor banks in the
SCS including Gateway Data mapping to DCC/ENCC and S/S works necessary for
DCC/ENCC End to End testing;

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope;

Required modifications in LVAC/DC system;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 440 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Montazah-2 66/11kV S/S


Montazah-2 is existing substation built under phase 11 project by M/s NCC. Modification of
the existing 66/11kV Montazah-2 substation shall be as follows:

Install 2x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays.

Automatic shunt Capacitors shall be installed in the available space in the building.

Minor Civil Works shall be done to accommodate the Capacitor Banks in the
available space

Install vacuum contactor panels for the capacitor banks;

Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available inside the building.

11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Required Modifications to SCS of Siemens make supplied by NCC under Phase 11


project to include installation of capacitor banks to the SCS including Gateway
Data mapping to DCC/ENCC and S/S works necessary for DCC/ENCC End to
End testing.

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope.

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Naeeja Local 66/11kV S/S


Naeeja Local is existing substation built under phase 9 project by M/s Siemens.
Modification of the existing 66/11kV Naeeja Local substation shall be as follows:

Install 2x11kV 6MVAr automatic shunt Capacitors;

Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 2;

All required civil works related to new building including building services.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 441 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Modification in Schematic Diagrams on 66/11kV Transformer Feeder 11kV Side of


A18 and A28 to provide CT inputs for capacitor bank control panel.

Modification in Schematic Diagrams on 11kV Bus VT-1 and VT-2 to provide VT


inputs for capacitor bank control panel.

11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Space for the capacitor banks is available;

Installation of vacuum contactor panels for the capacitor banks;

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes on the 11kV switchgear and installation of capacitor banks in the
SCS including Gateway Data mapping to DCC/ENCC and S/S works necessary for
DCC/ENCC End to End testing;

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope;

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Old Ghanim 66/11kV S/S


Old Ghanim is existing substation built under phase 9 project by M/s Siemens.
Modification of the existing 66/11kV Old Ghanim substation shall be as follows:

Install 2x11kV 6MVAr automatic shunt Capacitors;

Two (2) Nos. 11kV Bays for capacitor bank to be installed on spare space on 11kV
Busbar 1 and Busbar 2;

All required civil works related to new building including building services.

Modification in Schematic Diagrams on 66/11kV Transformer Feeder 11kV Side of


A18 and A28 to provide CT inputs for capacitor bank control panel.

Modification in Schematic Diagrams on 11kV Bus VT-1 and VT-2 to provide VT


inputs for capacitor bank control panel.

11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 442 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Space for the capacitor banks is available;

Installation of vacuum contactor panels for the capacitor banks;

Required Modifications to SCS supplied by Siemens under Phase 9 project to


include changes on the 11kV switchgear and installation of capacitor banks in the
SCS including Gateway Data mapping to DCC/ENCC and S/S works necessary for
DCC/ENCC End to End testing;

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope;

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

 Alternative Items

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

 Rawdat Al Khail 66/11kV S/S


Rawdat Al Khail is existing substation built under phase 11 project by M/s L&T.
Modification of the existing 66/11kV Rawdat Al Khail substation shall be as follows:

Install 2x11kV 6MVAr automatic shunt Capacitors utilizing the existing 11kV
Capacitor banks bays.

Install vacuum contactor panels for the capacitor banks;

Space for the capacitor banks along with space for vacuum contactor panels for
the capacitor banks is available in the substation layout.

All required civil works related to new building including building services.

11kV, 1x500mm2, XLPE, 6MVA, double circuit, solid bonded (one cable per phase)
between 11kV switchgear and Capacitor Banks. Approx. route length: 80m.

Required Modifications to SCS of Siemens make supplied by L&T under Phase 11


project to include installation of capacitor banks to the SCS including Gateway
Data mapping to DCC/ENCC and S/S works necessary for DCC/ENCC End to
End testing.

Retesting of the Relays/Equipment, all modifications, testing and commissioning


and putting into service of these four circuits is included in the Present Scope.

Required modifications in LVAC/DC system;

LV Power Cables, Control Cables with all accessories;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 443 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

 Alternative Items

4.

In case capacitor banks are of the outdoor type, all Civil Works including
foundations and substructure to accommodate the same shall be done.

NOTES TO BIDDERS
Sequence of documents: In the case of any discrepancy between Tender Documents, namely,
Price Schedules and Scope of Works, the Scope of Works will prevail.
Equipment/accessories: Not withstanding absence, if any, of specific mention in the Tender, all
equipment/accessories with all support structures etc., as required to meet the design requirement
of this project are deemed to be part of the scope of works. The end terminations shall be in line
with the end equipment and chosen appropriately after verifying the same.
Technical Requirement: The design, cable sizing etc., provided in the Tender documents are
only guiding principles. These shall be verified and it is the responsibility of the prospective
Contractor to ensure that the specified MVA rating for each cable circuit is achieved by adopting
appropriate method and/ or adequate cable sizing, considering thermally independent cable
circuits.
Technical parameters for all the equipment/ accessories required and offered shall be filled in by
Bidder even if certain specific formats are not provided in the Tender.
The total no of cable spans: The indicated cable spans are for pricing purposes. However,
necessary details, schematic drawings etc., with accurate lengths shall be submitted for approval
during detailed engineering stage.
Good engineering practice in all works shall be adapted to Kahramaas satisfaction.
Power cables for all voltage levels connecting different equipment within substation shall be
supplied and installed by the Substation Contractor which will present nominated subcontractor for
the Cable Works.
HV cables between the Transformers and switchgears and between cable gantry located within
substation boundary to Transformer / switchgear shall be laid in the unfilled concrete cable trough
which will be constructed by the substation civil works subcontractor.
HV Connections between outdoor sealing end and SF6 wall bushing: The Necessary Jumper
for connection between outdoor termination and SF6 wall bushing shall be part of scope of supply
of substation Contractor.
EHV Connections, disconnecting and dismantling of existing termination and their related
accessories, to connect new cable shall be part of scope of work for substation Contractor

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 444 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Equipment/accessories: Notwithstanding absence, if any, of specific mention in the tender, all


equipment/accessories with all support structures etc., as required to meet the design requirement
of this project (to be approved by Kahramaa), are deemed to be part of the scope of works. The
end terminations shall be in line with the end equipment and chosen appropriately after verifying
the same.
Technical parameters for all the equipment/ accessories required and offered shall be filled in by
tenderers even if certain specific formats are not provided in the tender.
Good engineering practice in all works shall be adapted to Kahramaa's satisfaction.
Civil works: In addition to all related civil works along the cable route, construction of all cable
troughs/ concrete trenches, steel support, foundations, structures etc., for cable sealing ends/
connections inside the substations for the cable feeder lines (except foundations/ structures for
equipments inside cable compound and OHL gantry and cable ducts to buildings, Road Crossing
ducts etc., inside substations) as well as necessary coordination with the respective cable/ OHL
Contractor(s) to ensure technical and programme compatibility and compliance, shall be part of the
substation Contractors scope and responsibility.
Architectural view/design of all substations to be built under this contract shall match with the
surrounding structures / buildings etc., as applicable. The same shall be investigated by the
Contractor and a report shall be presented on the proposed options of architectural views to
Kahramaa for review and approval. All design approvals in this regard shall be obtained from
Kahramaa and concerned authorities by the contractor prior to submission of DC1 and structural
design works. It shall then be the EPC contractors responsibility to design and implement
approved design/ final architectural view that is selected by Kahramaa.
Kahramaa has introduced three types of Architectural design which will be applicable for all Facility
D Substations: Residential, Prestigious and Industrial. This architectural design shall be done as
per Appendix F Drawings and table below. Substation classification regarding type of
architectural design is given in the following table:

No.

Name of S/S

Type of Design

Package S-1

1.

220/132/11kV Al Shahhaniyah Super

Prestigious

2.

132/11kV Al Shahhaniyah South

Residential

3.

132/11kV Lebsayyer

Prestigious

Package S-2

4.

132/66/11kV Umm Ebairiya

GTC-735 SCOPE OF WORKS R0

Residential

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 445 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

No.

Name of S/S

Type of Design

5.

66/11kV Umm Al Amad - 1

Residential

6.

132/11kV Umm Garn

Prestigious

Package S-3

7.

132/11kV Al Jahhaniya 2

Residential

8.

132/11kV Izghawa North

Residential

9.

132/11kV Mesaieed Industrial-A

Industrial

10.

132/11kV Wakrah 3

Residential

Package S-4

11.

66/11kV New Assiri

Prestigious

12.

66/11kV Salwa Road

Prestigious

13.

66/11kV Bin Mahmoud North

Residential

14.

66/11kV Musherib

Residential

Package S-5

15.

66/11kV Murrah South

Prestigious

16.

66/11kV Umm Al Seneem 2

Residential

Package S-6

17.

132/11kV Ain Sinan

Residential

18.

132/11kV Jeryan Jenaihat

Residential

Package S-7

19.

66/11kV Doha E New

Residential

20.

66/11kV Salata New

Prestigious

Package S-8

21.

132/11kV Mashaf 1

Residential

22.

132/11kV Mashaf 2

Residential

23.

132/11kV Mashaf 3

Residential

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 446 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

No.

Name of S/S

Type of Design

24.

132/11kV Al Wukair 10

Residential

Package S-9

25.

132/11kV Al Wukair 9

Residential

26.

132/11kV Al Wukair 8

Residential

27.

132/11kV Al Wukair 7

Residential

28.

132/11kV Al Wukair 6

Residential

Package S-10

29.

132/11kV Al Wukair 5

Residential

30.

132/11kV Al Wukair 4

Residential

31.

132/11kV Al Wukair 3

Residential

32.

132/11kV Al Wukair 2

Residential

Package S-11

33.

66/11kV Abu Hamour West

Residential

34.

66/11kV Rawdat al Khail 2

Residential

35.

66/11kV Luaib

Prestigious

Package S-12

36.

220/132/11kV Framework S/S 1

Prestigious

37.

220/66/11kV Framework S/S 2

Residential

Package S-13

38.

132/11kV Framework S/S Type A-1

Prestigious

39.

132/11kV Framework S/S Type A-2

Residential

40.

132/11kV Framework S/S Type B-1

Prestigious

41.

132/11kV Framework S/S Type B-2

Residential

42.

132/11kV Framework S/S Type C

Residential

Package S-14

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 447 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

No.

Name of S/S

Type of Design

43.

132/11kV Framework S/S Type A-1

Prestigious

44.

132/11kV Framework S/S Type A-2

Residential

45.

132/11kV Framework S/S Type B-1

Prestigious

46.

132/11kV Framework S/S Type B-2

Residential

47.

132/11kV Framework S/S Type C

Residential

Package S-15

48.

66/11kV Framework S/S Type A-1

Prestigious

49.

66/11kV Framework S/S Type A-2

Residential

50.

66/11kV Framework S/S Type B-1

Prestigious

51.

66/11kV Framework S/S Type B-2

Residential

52.

66/11kV Framework S/S Type C

Residential

Package S-16

53.

66/11kV Framework S/S Type A-1

Prestigious

54.

66/11kV Framework S/S Type A-2

Residential

55.

66/11kV Framework S/S Type B-1

Prestigious

56.

66/11kV Framework S/S Type B-2

Residential

57.

66/11kV Framework S/S Type C

Residential

Outdoor Cable Sealing End: Substation Contractor responsible for cable line connection with
outdoor type termination shall include following in their bid price for outdoor sealing end connection
at cable compound/gantry:
respective foundation, steel structure and all necessary material and accessories, surge arresters
including their foundation and steel structure, all material required for earthing of equipment and
structure connection to the earth grid, terminals for connection to OHL down leads, removing of
existing cables and sealing end, if any, and all related civil works. In case that existing foundation
is suitable to be used, Contractor may propose such solution and appropriate structural calculation
shall be provided for Kahramaa approval. Kahramaa decision will be followed in this regard.
Substation Contractor shall supply, install, erect and commission cable links within substation as
per execution plan of substation without any delay; all required interface arrangement shall be
cable Contractor responsibility.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 448 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Cable Compounds: Where a Cable Compound is required, a Terminal Tower & Gantries with
their foundations and earthing system to provide no more than 5 resistance to earth for each
structure, Cable Compound Palisade Fence complete with gate, foundations, earthing, kerb stone
etc. shall be provided in order to lead the line in.
Earthing System of mesh type according to IEEE 80 shall be also provided for the whole cable
compound area. The earth conductor shall be of lead sheathed copper as elsewhere specified.
The earthing systems of all structures (tower, gantries, fence etc.) shall be connected to the
earthing mesh. All connections, including mesh earthing conductor intersections shall be made by
thermo weld process.
Testing Equipment: In addition to all related equipment required for cable installation and
commissioning test for cable feeders connected to GIS switchgear and cable feeders to
Transformers as well as necessary coordination with substation manufacturer/Contractor, the test
bushing and degassing, gassing and oil filling/derange shall be part of the substation Contractors
scope and responsibility.
Specifications, Technical schedules and Drawings: New route and relevant new drawings are
provided where necessary. For referring to the main contract information, please note that Single
line diagrams are in Appendix F Drawings, Technical Specifications are in Sections 3.2 & 3.3
and Technical Schedules in Section 3.4 of this Appendix.
Route Length: The quantities given for cable length in TED are approximated for Tendering
purposes and shall be adjusted according to actual results of survey.
Shutdown: The shutdown for diversion of cable circuits or connection of cable circuits to existing
substation shall be arranged by Kahramaa, circuit by circuit only, according to requirement of
Kahramaa network (operation & maintenance).
Earthing Continuity Conductor: Cross-section of earthing continuity conductor should be
provided in order to carry the full value of short circuit current, as specified.
Pilot Fiber optic cable and Pilot Copper cable:
A budget calculation note and cut over plan for diversion of the Pilot FO cables and Pilot Copper
cables shall be provided for Kahramaa approval.
For any of Power outages due to conversion/connection of OHL and/or cable line to cable and/or
OHL line, as specified under GTC 735/2015 and GTC 736/2015 Contracts, the following shall be
provided:
The Substation Contractor shall maintain/restore all protection services running on fibers of OPGW
and Pilot Fiber Optic cables and on copper wires of pilot copper cables associated with above
Power lines.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 449 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The Telecom Contractor shall maintain/restore all telecom and/or IT services running on fibers of
OPGW and Pilot Fiber Optic cables and on copper wires of pilot copper cables associated with
above Power lines.
Coordination between Substation Contractor and Telecom Contractor during above
maintain/restore of services is required. The required Fibre Patch cords for above maintain/restore
of services shall be provided by Substation Contractor and/or Telecom Contractor and shall be
installed in flexible metallic pipes with one patch cord in single pipe, alternatively flexible sheath
patch cables can also be used, subject of Kahramaa approval in both cases.
Old OTBs and Pilot Wire termination equipment not in service, shall be dismantled (subject of
Kahramaa approval) and handed over to Kahramaa stores packed and labeled as per Kahramaa
regulations.
Pilot cable: Installation of gland for termination of pilot cable at relay panel of 11kV SWG is
included in the Scope of substation Contractor.
Cable diversion: Substation Contractor will be responsible to check the existing teleprotection
cable to match with new diversion.
Dismantling of Oil Filled Cable to install new XLPE cable: the following shall be under scope
of work for substation Contractor:
Excavation and related civil work
Removing oil tank
Disconnect Gauge/manometer panels and control/alarm cables
Cut and cap existing oil filled cables
Remove the existing termination
Delivery of dismantled material to Kahramaa store
Work inside Generation/industrial plant (Messaied,
Dukhan and Ras Laffan): All
activities/works inside Messaied, Dukhan and Ras Laffan subject require permission from
Messaied, Dukhan and Ras Laffan authority. Work shall be according to safety rules and
regulations of Messaied, Dukhan and Ras Laffan. Authorised persons for holding required permit
shall be interviewed at Messaied, Dukhan and Ras Laffan.
Alternative Offer (for HV Cable works): Optionally the Bidder is encouraged to submit an
alternative cost effective offer, if he wishes to do so, with complete design justifications,
calculations, parameters, drawings etc., as necessary. However, this optional offer, if submitted
shall be in addition to the main offer and not in lieu of it. Bidders must use the same price schedule
template with only change in the cable conductor for this alternative offer. This shall be submitted
in addition to the main offer.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 450 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Warranty: In the event that a new cable requiring connection to an existing cable which is under
warranty by the original contractor, the new cable Contractor will make arrangements with the
original contractor of the existing cable to carry out the connection and to follow prudent
procedures in order to avoid the cancellation of the remaining warranty period on the existing
cable. The original contractor of the existing cable is expected to be cooperative and Kahramaa
will view any reluctance from the original contractor as unacceptable behavior which will have
impact on future approval of bids by such contractor. The new cable Contractor shall guarantee
that their work will be conducted as per normal procedures and will be responsible for the repair of
any damage they may cause to the existing circuit.
Third Party Damage During Warranty Period: No reduction to the Warranty Period "as specified
in Article 9.51 of the GCC" for the Works or any part of the Works, shall take place for whatsoever
reason during the Warranty Period. The Contractor is responsible to make good all defects that
may arise, in accordance with Article 9.53 of the GCC. If third party damage to the Works or any
part of the Works occurs; Kahramaa and the third party shall be responsible for the repair of the
damaged works in accordance with Kahramaa standard regulations and the specification of the
Contract.
Kahramaa may instruct the original Contractor to perform the repair of any third party damage to
the Works or any part of the Works, if the Contractor accepts Kahramaa instruction to perform the
repair or remedy of any third party damage. The cost of such repair shall be paid by Kahramaa to
the Contractor and shall be calculated based on the unit rates of the Contract or within a
reasonable range of.
If Kahramaa performs the repair works through any of its reputable Contractors, the repair work
shall be performed under the supervision of the original Contractor if available at seven (7) days
notice. Costs of supervisor shall be based on unit rates of the original Contract or reasonable
range of. If the original Contractor does not make available to Kahramaa the required resources for
the repair work or the supervisor within above notice period, Kahramaa may conduct the repairs
without further notice to the original Contractor or the presence of their supervisor or
representative but always in accordance with procedures agreed by Kahramaa and the original
Contractor and clearly specified in the original contract document, in absence of which Kahramaa
will operate within its standard practices.
The above repair works shall in no way be used by the Contractor as an excuse to limit or
terminate the Warranty of the Works or the repaired parts.
For outage required on Power cable and/or OH line in order to establish:
1)
2)

Energisation of: new SS or new Power cable/OH line, or


Power/OH line diversion.

the obligation of the Contractor is to provide programme for outage, all necessary material and
works for shifting of existing communication traffic (protection, telecom, Kahramaa IT traffic)
running over FO cable, OPGW, and/or pilot copper cable associated to Power feeder coming
under the subject outage. Prior the restoration i.e. energisation of feeder being under outage the
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 451 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Contractor is obliged to restore/establish communication traffic as per his final design. The
Contractor is obliged to coordinate closely with Kahramaa System Control on the above
communication traffic shifting
The shutdown for diversion of OHL circuits or connection of OHL circuits to existing substation
shall be arranged by Kahramaa, circuit by circuit only, according to requirement of Kahramaa
network (operation & maintenance).
Foundation Classes (OHL): Foundation classes for OHL specified in the Schedule of Prices are
according to Foundation Design Particulars of Section 3.3.1, Volume 3.

5.

NOTES APPLICABLE FOR FRAMEWORK PACKAGES


Due to the very rapid economic developments in the country, Kahramaa has been frequently
requested by the Developers/Government Authorities to implement the new substations in a very
short period of time. Considering the standard tendering or variation procedure such urgent
request could not be always properly replied within the expected period. In order to facilitate such
urgent requests, which are also expected to arise during the execution of GTC/735/2015 (Phase
13) Contract, it has been decided to establish Framework Packages within this Tender with the
main purpose to enable:

fast award of the new works,


faster implementation due to the availability of the approved equipment, documentation and
subcontractors.

GTC 735/2015 Tender consists of:


Main Packages (Packages S-1 to S-11)
Framework Packages S-12 to S-17), and
Telecom as Package S-18
Each Main Package can be awarded to the separate Bidder, however, more than one Main
Package can be also awarded to the same Bidder, similarly to the practice already applied in
previous Kahramaa Tenders.
In particular, the Framework Packages shall cover the installation of the following typical (most
frequently) used types of the substations:
Package S-12
Containing of 220/132/11kV substation and 220/66/11kV substation with the specification and
description as provided in the clause no. 3.12 of this SOW. Also, it should be noted that types of
remote ends are included (one for SS built after Phase 8, one for those built under Phase 7, one
for those built under Phase 5/6 and GTC 53 projects and one for very old substations with 220kV
indoor/ outdoor switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s).
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 452 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Depending on the connection scheme of the new substation the suitable type of remote end works
shall be applied.
Package S-13 and S-14
Containing of five nos. of 132/11kV substation with the specification and description as provided in
the clauses no. 3.13 and 3.14 of this SOW. Also, it should be noted that types of remote ends are
included (one for SS built after Phase 8, one for those built under Phase 7, one for those built
under Phase 5/6 and GTC 53 projects and one for very old substations with 132kV indoor/ outdoor
switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s). Depending on the
connection scheme of the new substation the suitable type of remote end works shall be applied.
Package S-15 and S-16
Containing of five nos. 66/11kV substations with the specification and description as provided in
the clause no. 3.15 and 3.16 of this SOW. Also, it should be noted that types of remote ends are
included (one for SS built after Phase 8, one for those built under Phase 7, one for those built
under Phase 5/6 and GTC 53 projects and one for very old substations with 66kV indoor/ outdoor
switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s).
Package S-17
Containing of four nos. 66/11kV substations, including underground with the specification and
description as provided in the clause no. 3.17 of this SOW. Also, it should be noted that types of
remote ends are included (one for SS built after Phase 8, one for those built under Phase 7, one
for those built under Phase 5/6 and GTC 53 projects and one for very old substations with 66kV
indoor/ outdoor switchgear supplied under Phase 3 / 4, RAF A/ B projects built in early 1980s).
The Bidders shall quote for the above typical substations as specified in the Scope of Works and
Price Schedules. It should be understood by the Bidders that these substations could be or not
implemented within the Contract Period of the Main Package. Also, the number of various
equipment like switchgear bays, Shunt Reactors, Transformers for various voltage levels and
similar could be modified at the time of implementation, depending on the actual requirements of
the Developer and network configuration where new substation is to be connected.
The following rules shall be applicable for award of the Framework Packages:

Price Schedules for Framework Packages shall be part of the Contract between Kahramaa
and successful Bidder(s) for Main Package(s), and shall be valid for period of 1 (one) year
from the Contract Effective Date.

At any time within the first year from the Contract Effective Date (CED), Kahramaa shall have
the option to award part (but minimum one complete substation) or the complete scope of the
Framework Package based on the prices stated in the Framework Package Price Schedules.

There shall be no liabilities on Kahramaa if the option is not utilized.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 453 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The Contract Period for additional works from the Framework Package shall be calculated
from the date of the Instruction to Proceed. Duration shall be agreed between Kahramaa and
Contractor within the range given in Appendix H Contract Execution Plan for the particular
type of substation. Final Contract Period shall be based on the actual status of the equipment
and design approval, availability of the site plot, and other elements that can influence the
completion time.

Framework Package works award shall be covered by the Instruction to Proceed (similar to
Letter of Award), issued by Kahramaa in the form of letter to the Contractor. The Contractor
should confirm the acceptance of the Instruction to Proceed (including specified Price and
Completion Period, and any other conditions stated therein) by issuance of the letter of
Confirmation.

The awarded works shall be considered as separate Milestone within the existing Contract or
shall be covered by the separate Contract under the same conditions and specifications as
Main Packages Contract.

Any award from the Framework Package shall not affect the 20% limit for Variations as
specified in article 14.2 of General Conditions of Contract.

The criteria for the award to the Framework Packages shall be in the following order:
the Price,
Performance of the Contractor on the Main Packages,
However, the final decision shall be on Kahramaa.

The substation specification and quantities given in the Price Schedules are indicative. The
Kahramaa might decide the change some of the quantities based on the actual requirement,
i.e. alteration in number of xxkV switchgear bays, Shunt Reactors, Power Transformers, etc.
Final Price Schedule shall be established based on the rates derived from the Framework
Package Price Schedules.

Available rates for Remote End works shall be used as applicable to the actual substation
connection point.

LME and Currency adjustment shall be applied based on the date of Final Instruction to
Proceed issued by Kahramaa.

In case of the Framework Package award, the Contractor shall provide Performance Bond
with the value and duration corresponding to the agreed Final Price and Contract Duration
according to the General Conditions of the Contract.

After final price adjustment and approval of Final Price Schedules, Contract shall be amended
by signing and issuing Contract Amendment Agreement.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 454 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

6.

REV. 0

Advance Payment, if agreed for the Main Packages, shall be also applicable for Framework
Package.
IMPORTANT NOTES APPLICABLE FOR ALL PACKAGES

Following documents are included in Volume 2 (along with this document, section 3.1 Scope of
Works) of Tender which may be referred to understand Kahramaa requirements regarding
equipment numbering, interlock scheme, Protection energy meter & system control requirements
for Bulk customer:
Annexure I Interlocking Scheme Rev 3
Annexure II Equipment numbering scheme Rev 2
Annexure IV ET-P26-G1 Guidelines for Protection Energy Meter Requirements for Power Supply
to Bulk Consumers
Annexure V - ES-EST-P1-G1 Guideline for System Control Requirements for Power Supply to
Bulk Consumers.pdf
For applicable CT ratio for all voltage levels and bays refer to the document Annexure III - CT
ratios REV 2.xls in Section 3.3.8 of Vol. 3
All modification works at Kahramaa control centers NCC/ENCC/DCC to include new and modified /
upgraded / refurbished existing substations will be covered under a separate contract. The scope
of substation Contractors under this project includes all necessary works inside the substations to
complete the work successfully. This includes co-ordination works with the above Contractor and
Telecommunication Contractor during all stages until commissioning and end to end test.
If future Transformers / Reactors are envisaged elsewhere in the scope, space reserved for these
equipment and trenches of approach cables to these equipment shall be prepared in such a way to
avoid drilling, cutting etc. in future using heavy equipment so as to avoid damages to the existing
installations. To eliminate these difficulties in future, necessary excavations shall be done for
Transformer / Reactor foundations and trenches of approach cables. Finally, these cavities shall
be filled with loose sands making it convenient to construct the foundations and trenches in future.
Note for refurbishment/ modification/ replacement of substation works:
It is planned to modify / replace / upgrade some of the Kahramaa substations in this project. In
case of some of the substations UPDA has allocated new sites adjacent to the existing
substations. Other substations are to be built within the boundary of existing live substations. The
Contractor shall adopt safety procedures related to work in live environ. Wherever and whenever it
is required to obtain outage of any circuit or part of the substation the Contractor shall co-ordinate
with transmission network department to obtain necessary outage and safety documents. In this
respect please note that during the summer time, between months of April to month of October
none of the circuits on load can be released due to heavy load.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 455 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The Contractor shall plan his works to minimize Power supply interruption. The dismantling and
reconstruction shall be done in phased manner which has been described in detail elsewhere.
Where the shifting of respective 400kV, 220kV, 132kV and 66kV OHL / Oil filled and /or XLPE
cables work is allocated to another Contractor under separate contract(s), all required coordination for work schedule, material management etc. shall be done with the other Contractor to
complete the works in full respect. The Contractor shall consider all such requirements and shall
take all necessary measures required for these works.
It may be noted that the diversion/ shifting of 11kV OHL / cable circuits, wherever applicable, to the
new substation is not within the scope of this contract unless specified otherwise in detailed scope
of works.
Wherever specified the Contractor shall supply set(s) of main protection relay e.g. cable differential
protection relay for each of the feeder for remote end stations.
If specified elsewhere some of the primary equipment (such as Reactor) may be reused as per
main scope of works. However completely new functional protection system for ALL equipment is
to be provided as per the specifications, standard drawings and technical schedules. All 400kV,
220kV, 132kV, 66kV, and 11kV Cable / OHL feeders are to be shifted from existing substation to
new switchgear. Hence all protections at remote end substations must be changed to be
compatible with new protections as described under protection scope of works. An extensive site
survey may be carried out by substation Contractor to study detailed scope of work to be
undertaken at remote substations presently connected to the substation. In case of underground
cable feeders care shall be taken to choose proper protection(s) to connect with existing oil filled
cable / XLPE Power cable and pilot cable /fiber optic cable. Remote end substation(s) where
panels are equipped with protections, the required modification to make it functional and
compatible with the new substation is under the Contractors scope as described under protection
scope of works.
Note for Remote End Modification works:
If the case that substation and its remote end works are not awarded to the same Contractor, all
necessary coordination works are deemed to have been included in the offered price of the both
awarded Contractors.

7.

EXTENT OF SUBSTATION CONTRACT


The project shall be executed as substation Contract. The works and services to be performed by
the Contractor shall comprise the design, manufacture, shop tests, packing, transport, insurance,
and charges incurred up to delivery to the port of entry in Qatar, landing charges, customs,
transport to Site, insurance, site clearing and leveling, excavation, building road crossing ducts as
required after detailed route survey, cable laying and jointing, terminating, etc., in-fill, boundary
wall, access roads, drainage, sewage, construction works, erection of equipment, site testing,
submission of documentation, commissioning, training of Kahramaa s staff, delivery of spare parts
and tools, temporary site buildings and accommodation, warranty and everything necessary to

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 456 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

leave the plant complete and in full working order at the expiration of the warranty period in
accordance with the provisions of the substation Contract.
The establishment of new Overhead lines and LILO of the existing Overhead lines shall be
executed as a part of this substation EPC Contract.
The substation Contractor is bound to provide for all parts of the work to be completed in every
respect for commercial operation and to Kahramaas requirements notwithstanding that any
details, accessories, etc. required for the complete installation and satisfactory operation of the
plant are not specifically mentioned in the Specification. These are to be considered as included in
the Scope of Works and Contract Price.
5.1

7.1

SCOPE OF SUPPLY
The Scope of Supply is as specified in Technical Specifications, Technical Schedules, and
Appendix B: Price Schedules and Appendix F: Drawings.
The quantities indicated in the Schedule of Prices (Appendix B refers) and Drawings
(Appendix F refers) both attached to the Specification are provided for information only. The
substation Contractor is responsible to establish the exact details, quantities of the equipment
and accessories required to complete the whole of the works as described throughout the
Tender Documents, after the necessary approvals.
General Technical Requirements are given in Section 3.2 of Appendix A, while the specific
requirements for the various equipment and works are set forth in Section 3.3 Technical
Specification and Section 3.4 Technical Schedules of Appendix A.

5.2

7.2

SCOPE OF SERVICES
The Scope of Services shall include but be not limited to the following:
Preparation of the detailed specification for each piece of the equipment up to the satisfaction
of Kahramaa before commencement of manufacturing;
Establishment of the project administration and all site and installation procedures as detailed
in the Specification;
Project site organization, at Doha and site offices, stores, local transport etc.;
Detailed soil investigation report and excavation of trial pits and testing of the original soil
properties, including thermal properties;
Detailed site survey at the approved locations, detailed route survey (for underground cables),
preparation of appropriate topographical drawings and establishment of the project set-up;

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 457 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Circulate the location map and civil/architectural design drawing and approval requests to all
concerned government authorities. Follow up and obtain such approvals. Regular renewal of
the approvals and work permits as necessary;
Establish the subcontract agreement with the approved local civil Contractor. Follow up and
supervise the civil works and ensure timely and quality execution of the works;
Procurement of mutually compatible elements / accessories for all equipment and installation
of the same by competent personnel through active direct supervision to ensure highest levels
of quality and good engineering practice.
Local transport storage and delivery to the site / storage yard of the equipment;
Manufacturing, factory acceptance tests, packing and transport to site;
Interfaces with other Contractors of Phase 11 (GTC/488 and GTC/450), Phase 12 (GTC/643,
GTC642 and GTC641) and NCC control and equipment manufacturers at the existing
substations and make all necessary arrangement to facilitate the termination of cables/OHL to
the switchgear.
Civil Works including
Site survey, soil investigation work and testing of soils, water and materials used;
Collection of information required for detailed design and construction, including coordination
with the various government ministries and departments, obtaining of building permits, etc.;
Design, preparation of detailed construction drawings and bending schedules, completion and
maintenance of works;
Earthworks, grading and landscaping;
Site surfacing;
Switchgear, control / relay buildings including all building services, compound wall, gates,
structure and plant foundations, cable ways, toughing and ducts;
Temporary and permanent access roads to substation from public road and road works within
substation;
Site lighting system, including security lighting, small Power and lighting installations. Fire
detection & alarm system, FM200 system, passive fire protection (fire sealant works & cable
coating (for HV/ML/LV cables) inside the buildings and fire protection system & Transformer
explosion prevention system, wherever specified for the Transformers & reactors shall be in
accordance with Kahramaa HSE requirements
All cables in basement shall be coated with fire resistance material

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 458 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Personal access steps or similar where required above HV / EHV cable in basement.
To avoid damage of the Power cable terminations in substation basement before plugging in
all male part termination sealing ends shall be covered with permanent protective cap till
plugging.
In order to properly supervise the installation works permanent presence of your Power cables
and accessories manufacturer is required. Checking of Power cable system prior to
conducting LV and HV tests shall be performed by both main contractor and the manufacturer.
Air-conditioning and ventilation and smoke extract systems;
Transformer compounds; construction of foundations for all Transformers. Excavation and
backfilling for future Transformers and Reactors.
'E' type fire wall for Transformers, Reactors etc.;
Construction of common / combined oil containment tank other than Transformer oil dyke.
All necessary associated works;
Guard Rooms.
Installation of the equipment under the supervision of equipment manufacturers specialist
technicians;
Clearance of site (Removal of site offices, stores, disused materials, grading and landscaping
on completion, and necessary clearances from govt. / concerned authorities);
Testing & Commissioning;
Training of Kahramaas staff.
Defects Clearance;
Submission of final As-Built drawing
Provision of completion reports with the relevant documents;
Documentation in accordance with the requirements;
Warranty Period Services. The period of Warranty for all the works executed under this shall
be 2 years from the date of Taking Over.
The Warranty obligation and the warranty period shall NOT be changed or reduced by any
third party damages to the Works or any part of the Works, in case the Contractor perform the
repair of that damage or the damage has been repaired under the supervision of the
Contractor.
GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 459 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

The Warranty obligation and the warranty period shall NOT be changed or reduced by any
third party damages to the Works or any part of the Works, in case the Contractor perform the
repair of that damage or the damage has been repaired under the supervision of the
Contractor.
5.3

7.3

REQUIRED DISTANCES IN GIS / CONTROL ROOMS


It should be noted that clearances in the GIS room and its final dimensions have to be
specified and confirmed by GIS manufacturer, considering GIS arrangement, type, required
space for testing, replacement of main components (such as circuit breakers) if necessary,
dimensions of specific GIS bays / components, arrangement of pressure relief openings, etc.
Drawings which clearly represent access to the inspection points, testing arrangements,
maintenance and replacement of main components will be provided by Contractor as the base
for building architectural design.
Minimum clearance in the GIS / Control room as specified herein below are based mainly on
the regular maintenance and inspection requirements, conformity of working space and safety
requirement for minimum gangway distances.
Equipment arrangement shall be such to provide: min. personnel working area of 1m and
minimum widths of passageway 0.8m.
All round clearance around the GIS: This space should ensure sufficient space for the free
moving of gas cart and mobile platforms. It should be min. 1.5m.
At the entrance to GIS room, on the side of offloading area of equipment, additional space has
to be provided to enable transport of equipment inside the GIS and handling by the crane. It
should be min. 2.5m after the space for the last future bay.
Space around LCC: LCCs without requirement for the rear access are preferable, since they
require less space. In this case they can be aligned to the wall with minimum clearance for the
easier cooling (i.e. 5cm). Minimum distance between GIS and LCC should be 2m.
Depth of working space in the front of panels (control, protection, etc.): Min. 1.2m.
If the panels are accessible from the rear side, minimum clearance to the wall shall be 1m. In
this case it is required that rear doors (if any) are all closing on the same side and in direction
of emergency exit which will enable fast evacuation of persons from this area.
If panels are arranged in two or more lines, with doors opening to the same aisle, minimum
distance between panels is 2m.
Minimum free height of working space is 2m.
In addition to above, working space around GIS shall ensure the following for repair /
replacement:
Sufficient horizontal free space shall be provided to facilitate removal of components that are
deemed to be withdrawn horizontally

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 460 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

Similarly, sufficient vertical free space shall be provided to facilitate removal of components
deemed to be withdrawn vertically.
For 33kV and 11kV metal enclosed SWG with withdrawable components: From the component
in draw-out position minimum clear space shall be 1.5m.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 461 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

5.4

7.4

REV. 0

INTERFACES BETWEEN CONTRACTORS

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

A.1

GENERAL
AND
CABLES - DESIGN

Substation
plot
layout
x
drawing with coordinates

Cable Line Route drawing in


SS vicinity with coordinates

Matching of cable line route


x
with plot layout

Substation
plot
drawing
showing
routing inside SS

Substation basement layout


drawing
showing
cable x
routing

x
For existing SS

Provide
road
drawing
and
arrangement
at
required)

crossing
duct
s/s
(if

Provide
drawing

crossing

Provide size / arrangement


requirements for the cable
basement sleeves

Provide
duct
size
and
arrangement at s/s basement x
and telecom room

10

Specify the cable bending


radius

GTC-735 SCOPE OF WORKS R0

fence

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

HV

layout
cable x

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 462 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

11

Earthing grid layout drawing


including
details
about
x
material and size of used
conductors

12

Specify link box / link box


support
steelwork
requirements
(include
drawings and fixing details)
and location.

13

Provide details of the cable


support steelwork

14

Provide GIS / Switchgear Bay


details
(including section x
drawings)

15

Provide details of GIS /


Switchgear
Bay
cable x
termination kit compatibility

16

Cable Type (Three Core /


Single core) and Cable
Construction - including cross
section drawings, details
about
material,
crosssections,
diameters,
tolerances.

17

Specify no. of cables per


phase and cable formation
details (Trefoil / Flat spacing)

18

Provide details of 66 & 132kV


GIS male size and type for
cable feeder and s/s cable
links

19

Provide details of 66 & 132kV x


GIS female size and type for

GTC-735 SCOPE OF WORKS R0

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 463 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

cable feeder and s/s cable


links

20

Matching of male - female


cable termination connector x
parts

21

Provide Transformer
box details

22

Provide details of the GA of


the cable termination and its
fixing details (drawing to be
supplied).

23

Switchgear Bay Allocation

x
and Kahramaa

24

Phase Identification

25

Matching of phases on line


terminal ends

26

Identification of
bays /
x
(circuits
and
Power
and Kahramaa
Transformer) numbers

27

Matching of circuit numbers

28

Specify GIS
requirements.

29

30

test

Specify
cable
requirements

cable

bushing

HV

x
x

test

Specify
safety
clearance
required during the HV test as x
per Kahramaa Specifications.

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 464 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

31

Specify milestones for cable


installation/testing/commissio
ning
required
for x
commissioning of substation
(on individual circuit basis).

32

Access for cable installation,


preparation
of
cable
x
terminations, cable electrical
and HVAC testing.

33

Questionnaire
for
data
required
for
protection
x
settings and milestone to
provide required data

34

Reply to questionnaire for


protection setting

A.2

GENERAL
AND
HV
CABLES - EQUIPMENT /
MATERIALS

Cable termination - female


x
part

Cable termination - male part

Cable supports and cable


cleats with fixing material

Cable sleeves for basement

Sealant
sleeves

Ducts for road crossing inside


x
SS

Ducts for crossing under SS


x
perimeter fence

for

GTC-735 SCOPE OF WORKS R0

utilized

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

cable

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 465 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

HV Test bushing

Testing leads

10

All installation material up to


and including OTB / OTP

A.3

GENERAL
AND
HV
CABLES
WORKS
(Including all tools and
materials
required
for
completion)

Construction
of
cable
trenches / ducts inside SS
from the perimeter fence to
the
GIS
basement
/
Transformer
for
incomer
feeders.

Construction of cable ducts


x
for roads and fence crossing

Provision of free access for


cable installation and related
civil works, preparation of x
cable terminations, electrical
and HV AC testing

Installation and fixing of cable


steel supports

Cables installation

Sealing
sleeves

Gassing / de-gassing of GIS x


cable
compartment
and For new SS
removing / establishing of

of

GTC-735 SCOPE OF WORKS R0

utilized

x
For new SS

cable

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

x
For existing SS

x
x
For existing SS

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 466 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

GIS testing link


8

Installation of Cable sealing


ends

Cable termination to GIS / Supervise


Transformer
For new SS

10

Link Installation

11

Cable connection enclosure

12

Enclosure
flange
intermediate plate

13

Seal

14

Insulator collar or adaptor

15

Intermediate gasket

x (if needed)

16

Flange

x (if needed)

17

Electrical
stress
component

18

Cable gland

19

Non linear resistors

x (if needed)

20

Insulating fluid

21

Seal

22

Installation and connections Supervise


of Testing equipment
For new SS

23

Earthing bonds required for


all GTC736/2015 equipment
(steel support, link boxes,

GTC-735 SCOPE OF WORKS R0

or

x
x

control

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 467 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

etc.)
x

24

HV Test performance

FO CABLES

GTC736/2015
FO
cable
design and all technical
details

GTC735/2015 S/S FO cable


design and all technical
x
details (in case of cable
diversion)

GTC735/2015 - Telecom FO
cable design and all technical
details (in case of new and
old
buildings
telecom
connections)

Provision
drawing

Provision of telecom room


equipment layout

Specify OTB/OTP details


(drawings and fixing details)
and location

Specify OTB color to match


with telecom equipment

Specify FO cable routing


inside S/S plot from fence up
to and including telecom
room (to OTP/OTB)

Installation of OTBs included


in the Scope of GTC736/2015

GTC-735 SCOPE OF WORKS R0

of

S/S

layout

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 468 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

10

FO
Patch
cords
from
x
protection relays to OTP/OTB

11

Splicing of all GTC735/2015


S/S FO cables at OTP / OTB x
including E-E test

12

Final E-E test of FO cable line


in case splicing of FO cables x
with OPGW.

13

Splicing of all GTC736/2015


FO cables at OTP / OTB
including E-E test

14

Splicing of all GTC736/2015


Telecom FO cables at OTP /
OTB including E-E test

15

Milestones for FO laying,


termination & end-to-end x
testing

DTS
SYSTEM

Not
Applicable for New Lines

DTS FO cable design and all


technical details

Provision
drawing

Provision of control
equipment layout

Specify DTS FO cable routing


inside S/S plot from fence up
to and including control room
(to DTS panel)

Specify DTS Unit details


(drawings,
fixing
details,

GTC-735 SCOPE OF WORKS R0

of

S/S

layout

room

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 469 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

Power supplies) and location


x

DTS unit connection to SCS

DTS unit connection


TCP/IP Router

Provision of Power cables for


DTS Equipment supply

Milestones for FO
termination & testing

10

Integration of DTS into


integrated W/S for CMS
access (Provision of DTS
remote access software)

11

Integration of DTS into


integrated W/S for CMS
access (Implementation of x
DTS remote access software
in W/S)

TELECOM EQUIPMENT

Provision
drawing

Provision of Telecom room


equipment layout

Provision of Telecom room


for installation of Telecom x
equipment

Provision of cables between


protection
relays
and x
teleprotection equipment

Provision of data cables x


between gateways of SCS to

GTC-735 SCOPE OF WORKS R0

of

S/S

to x
For new SS

laying,

layout

x
For existing SS

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 470 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

connectors at interface cards


on telecom equipment

Provision
of
TCP/IP
connections for OMS remote
x
access
and
non-SCADA
applications

Provision of telecom alarm


connection cables between
SCS common bay controller x
and terminals block at
telecom cabinet.

Provision of earthing system


inside telecom room as part x
of common earthing system

Provision of 240V, AC Power


supply cables from station
x
services supply up to telecom
cabinets for aux. services

10

Provision of cable installation


for non-critical services such
as PMR, CCTV, etc. for future x
connection
to
telecom
equipment

11

Provision of 240V, AC UPS


and MCB for Telecom x
equipment supply

12

Provision of Power cables


from MCBs to Telecom
equipment

13

Provision of data cables


between
alarm
terminal
blocks at UPS and alarm
terminals blocks at Telecom

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 471 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

equipment

14

Modification in 48V DC Power


supply for telecom equipment
in existing SS

PILOT COPPER CABLES

GTC736/2015 pilot copper


cable design and all technical
details

GTC735/2015 pilot copper


cable design and all technical x
details

Specify Pilot Copper Cable


Terminal
Box
details
x
(drawings and fixing details)
and location

Specify
Telecom
Barrier
Transformers Terminal Box
color to match with telecom
equipment

Specify Pilot copper cable


routing from basement to x
telecom room

Installation of Pilot Copper


Cable Terminal Box included
in the Scope of GTC736/2015

Connection and Termination


from protection relays to Pilot
Copper Cable Terminal Box x
(including Protection Barrier
Transformer)

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 472 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

Connection and Termination


from Telecom Equipment to
Pilot Copper Cable Terminal
Box
(including
Telecom
Barrier Transformer)

Termination
of
all
GTC735/2015 SS copper
cables at Pilot Copper Cable
Terminal Box including E-E
test (Copper cable E2E test
x
shall include at least the
following tests: Continuity
test,
Isolation
test,
Attenuation test, Near End
Crosstalk, Far End Crosstalk)

10

Termination
of
all
GTC736/2015 copper cables
at
Pilot
Copper
Cable
Terminal Box including E-E
test (Copper cable E2E test
shall include at least the
following tests: Continuity
test,
Isolation
test,
Attenuation test, Near End
Crosstalk, Far End Crosstalk)

11

Milestones for Copper Cable


laying, termination & end-to- x
end testing

NCC / ENCC
CONNECTIONS

Configuration and testing of


SCS for transfer of signals to
x
control
centers
from
substation*

GTC-735 SCOPE OF WORKS R0

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

DCC

TECHNICAL AFFAIRS
Electricity Projects Dept.

VOLUME 2

SECTION 3.1

PAGE 473 OF 473

GTC/735/2015
QATAR POWER TRANSMISSION SYSTEM EXPANSION - PHASE 13 - SUBSTATIONS
TITLE: SCOPE OF WORKS

REV. 0

TO BE PROVIDED BY

Sl.No

INTERFACE
POINT
SUBSTATION
DESCRIPTION / REQUIRED
CONTRACTOR
ACTIVITY

CABLE
CONTRACTOR

TELECOM
CONTRACTOR

* NOTE: Configuration and


testing of PCS (SCADA) from
Control centers is part of
separate
contract
by
ALSTOM
G

ONLINE
MONITORING
SYSTEM (OMS)

Configuration and E-E testing


of
telecommunication
channels for OMS

Configuration and E-E testing


x
of Remote access for OMS

GTC-735 SCOPE OF WORKS R0

TECHNICAL AFFAIRS
Electricity Projects Dept.