You are on page 1of 193

1.

1
Project Management Plan

1.1
Project Management Plan

1.1.1
Organization Charts

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

1.1.1 Organization Charts

Port of Long
Beach

Bridge Engineering
Prof. Niels Gimsing

Bridge Construction
Luis Viuela

Geotechnical
Engineering
Dr. Ross Boulanger

Project Manager
Giorgio Desideri
Deputy Project
Manager
William A. Corn, P.E.

Long-Span-Bridge
Articulation
Equipment Expert
Dr. Fabio Brancaleoni

Earthquake
Engineering
Andrew Whitaker

Design Management
Don Phillips

Cable-Stayed Bridge
Naeem Hussain

Structures
Peter Matusewitch

Geotechnical &
Foundations
Bob Bittner, P.E.

Deisgn-Build Manager
Robert M. Schraeder,
P.E.

Technical Advisory Panel

Quality Manager
Piyush Mehta

Design Quality
Manager
Dan Devlin, P.E.

Figure 1.1-1: Design Organization Chart

Technical Steering Team

Design Manager
John Karn, P.E.

Cable-Stayed Bridge
Lead Designer
Sena Kumarasena, PhD,
P.E.

Approach Bridge Lead


Designer
Kwong Cheng, P.E.

Geotechnical Engineer
of Record & Lead
Geotechnical Engineer
Kul Bhushan, Ph.D.,
R.C.E., G.E.

Lead Civil Engineer


Duanne Gilmore, P.E.

Roadway Lead
Designer
Natalina Bernardi, P.E.

Maintenance Facility
Lead
Designer
Tom Myers

Visual Quality
Manager
Michael Painter

Deputy CSB Lead


Designer
Matt Carter

Superstructure Lead
Robert Meyer

Approach
Superstructure Lead
Martin Bodemar, S.E.,
P.E.

Certified Engineering
Geologist
Joe Roe, CEG

Pavement
Engineering
Dan Peluso, G.E., P.E.

Geometric
Engineering
Jeff Wang, P.E.

Facility Design
Architecture

Project Bridge
Architectural Designer
Keith Brownlie, RIBA,
RIAS, FRSA

Lead Analyst
Ngai Yeung

Substructure Lead
Sammy Yip

Approach Substructure
Lead

MS Foundations
Liang Shen, P.E.

Drainage Engineering
Tony Kirby, P.E.

Traffic Control
Manager
Tony Gschwend, P.E.,
T.E.

Structural

Project Bridge
Architectural Lighting
Designer
Jason Edling, IALD
Florence Lam

Aerodynamics
Andrew Allsop
Ender Ozkan, PhD

Lead ATVA/Blast
Specialist
Andy Thompson

All Other Foundations


Kul Bhushan, Ph.D.,
R.C.E., G.E.

Stormwater
Engineering
Tony Kirby, P.E.
Paris Borovilos, P.E.

Signing and Pavement


Marking Lead
Designer
Jeff Wang, P.E.

Mechanical

Landscape
Architecture
Jeff Hutchins, LATC

Site Investigations
Djan Chandra, G.E., P.E.

Signalization
Engineering
Robert Onchi, P.E.

Electrical

Visual Quality Graphic


Support Team
Jan Dyer, LATC

Retaining Structures
Enrique Farfan, PhD, P.E.

Lighting Engineering
Jason Edling, IALD

Plumbing

Embankments & MSE


Walls
John Haertle, G.E., P.E.

ITS Engineering
Gareth Ashley

Named Personnel

Railroad Engineering
Genaro Mejia, P.E.

Other Personnel

Seismic Analysis
Francois Lancelot
Yuli Huang, PhD, P.E.
Ramin Motamed, PhD

Concrete Durability
and Performance
Bryan Marsh

Mechanical
Engineering
Murat Karakas, P.E., CEM

Corrosion Control
Graham Gedge

Metallurgy and
Fabrication
Chris Murgatroyd
Simon Cardwell

Electrical Engineering
Vahik Davoudi, P.E.

Key Personnel

Bridge Resource Group

Surveying Manager
David Thresh, PLS

Volume 2 Section 1 Organization Charts

Key
Solid line = reporting
Dotted line = communication

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

1.1.1 Organization Charts

Port of Long
Beach
Executive Management
Committee
Paul C.Camaur
Jaime Freyre
Fulvio Castaldi

Figure 1.1-2: Construction Organization Chart

Key Personnel

Project Manager
Giorgio Desideri

Technical Advisory Panel


(TAP)

Deputy Project
Manager
William Corn, P.E.

Other Personnel

Key
Solid line = reporting
Dotted line = communication

Design-Build Manager
Robert M. Schraeder,
P.E.

Quality Manager
Piyush Mehta

Safety Manager
Steve Wilson, CHST

Design Manager
John Karn

Design Quality
Manager
Dan Devlin, P.E.

Assistant Safety Manager

See
Design Organization
Chart

Construction Quality
Manager
Scott Beyma, P.E.

Safety Engineer

See
Quality
Organization Chart
in Section 1.2

Utility Coordinator
Ron Miller

MOT Engineering

DBE/UDBE Liaison
Joe Hernandex

Public Information
Liaison
Sylvia Novoa

Named Personnel

Environmental
Compliance Manager
Dan Herlihy

Construction Manager
Guillermo Castao

Cable-Stayed
Manager
Andrs Alonzo Quintanilla

Permitting Specialist

Water Pollution Control


Manager

Cable Erection
Superintendent

Towers Superintendent

Deck Erection
Superintendent

West Towers Engineer

Steel Erection Engineer

East Towers Engineer

Qualified SWPPP
Developer

Certified Professional
Erosion and Sediment
Control Supervisor

Technical Support
Engineer

Civil & Utilities


Manager
Mike Munden

Electrical Manager
Brent MacDonald

Foundations Manager
Adam Zagorski

Civil Superintendent

Lighting & Traffic Signal


Superintendent

West Approaches Day &


Night Superintendents

West Substructure &


Superstructure
Superintendent

Civil Engineer

Electrical Engineer

Day & Night Field


Engineers

West Structures Engineer

ITS Superintendent

East Approaches Day &


Night Superintendents

East Substructure &


Superstructure
Superintendent

Electrical Engineer

Day & Night Field


Engineers

East Structures Engineer

Utility Superintendent

Utility Engineer

Vibration Monitoring
West Superstructure
Engineer
Vibration Monitoring
Equipment Installation

Storm Water Installer

Traffic Control
Supervisor
Ruben Sauceda

Construction
Engineering Manager
Jorge Aranda

Project Controls
Manager
Michaiah Revero OR
Gerardo Daz

MSS General
Superintendent

Survey Chief

Business Manager

West MSS Structures


Superintendent

General Survey

East MSS Structures


Superintendent

Monitoring Survey

Project Scheduler

Structures Engineer

Cable-Stayed Survey

Cost Controls Manager

MSS Technical Support


Engineer

Technical
Office Engineer

Subcontracts Manager

Structures Manager
Scott Goss

Equipment Manager
Keith Wood

Payroll & AP

Document Control

East Superstructure
Engineer

Purchasing Manager

Volume 2 Section 1 Organization Charts

Resumes

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Giorgio Desideri
Project Manager

Profession

Civil & Mechanical Engineer


Project Director/Manager

Licenses and Registrations

Career Summary
Mr. Desideri has over 36 years of experience, all of them
with the Impregilo Group. He is an excellent manager
who has achieved significant experience in large infrastructure projects with both public and private clients, and
under various contract types (DBB, DB, DBF). His experience includes roads, bridges, railway, marine, and
hydroelectric projects. Mr. Desideri is a versatile manager
with skills in project management, design-build contracts,
engineering, risk management, cost and budget management, QA/QC programs, and safety programs.

Registered Professional Engineer: Italy


Technical Director of Impregilo S.p.A
(SOA Register)

Experience

36+ years

Experience in Proposed Role

26+ years

Education

M.Sc. Civil & Mechanical Engineering,


Universit degli Studi di Roma (Italy)
1974

With 22 years of experience in transportation projects,


over 25 years in a role of Project Manager, and with his
proven ability to manage DB transportation projects
with construction values above $500 million, Mr.
Desideri is the perfect candidate for the position of
Project Manager for the Gerald Desmond Bridge
Replacement Project.

RFP Required Experience

Relevant Project Experience

Design-build experience:

Various projects based at the Impregilo Head Office


Project Manager and Area 2 (Italy) Manager, 01/2011 to
present

22 years of roadway, bridge, transit, and


rail project management experience
26 years experience as a project
manager
Project manager for the A4 Mestre
Motorway, Ring Road of Mestre Venezia,
Italy - $973 million
California Professional Engineer license in
process
Port of Ancona - New linking and access
motorway network
Salerno-Reggio Calabria Motorway
Pedemontana Veneta Highway Project
A4 Mestre Motorway, Ring Road of
Mestre Venezia, Italy

Project Manager and Proposal Team Leader for the following projects:
Skills
Project Management
New Hospital Ospedale di Trento (DB Project)
Management of DB projects
(tender in progress)
Engineering
Villesse Gorizia Motorway (DB Project) (tender in
Construction management
Risk assessment
progress)
Cost and Budget Management
SS 106 Ionica Motorway (DB Project)
QA/QC program implementation
Port of Ancona project which includes a new access
Safety programs implementation
roadway network to the Port.
A4 Venezia-Trieste Motorway (Italy) including upgrading and enlargement for a third lane of the
existing roadway section of 11.5 miles between Quarto D'altino and San Don di Piave. The
scope of work involves two new viaducts on the Piave River (approximately 0.87 miles in total
length), four new bridges, nine overpasses and four underpasses.
Salerno-Reggio Calabria Motorway, Italy Contract DG 24/03c ($1,258,789,500 DB
Contract)
Project Manager, 01/2009 to 01/2011

As the Project Manager of the Scilla Consortium, Mr. Desideri managed the design phase of the
project and the supervision of construction, including safety coordination. This design-build contract involves modernization and upgrading of the motorway. The overall length of the motorway is
18.5 miles, including 12 tunnels, 3 cut-and-cover tunnels, 22 viaducts, and a spur to Palmi. The

Volume 2 Section 1 Key Personnel Resumes - page 1

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

project also includes the design and construction of two separate double tower cable-stayed bridges,
each with a total length of 1,443 feet and a curved alignment with a radius of 6,068 feet. Each travel
way is formed by three lanes: two lanes for normal traffic flow and a third as an emergency lane. The
width of each travel way between the barriers is 36.7 feet (each way), for a total width of the two
adjacent bridges of 82 feet, including a central lane 8.2 feet wide. Each cable-stayed bridge has two
towers with two symmetric spans of 360.8 feet each and a central span of 722 feet. Each steel tower
has a height of more than 164 feet over the roadway. The bridge deck is formed by 7.2 foot deep
longitudinal steel girders and a reinforced concrete slab.
Pedemontana Veneta Highway Project ($2.8 billion DBF Contract)
Project Manager, 1/2008 to 12/2008

Mr. Desideri, on behalf of Impregilo, led the multi-company team in all phases of the acquisition
process through its financial closure, which is in process. The project scope includes the final design
and the construction of the first section of the Ring Roads of Como and Varese together with the
linking road between the A8 and A9 Motorways (from Cassano Magnago to Lomazzo). The project
includes approximately 29 miles of primary and secondary roads, eight miles of tunnels and about
one mile of bridges and viaducts of various types.
A4 Mestre Motorway, Ring Road of Mestre Venezia, Italy ($973 million DBF Contract)
Project Manager, 04/2004 to 12/2007

As the Project Manager and Chief Executive Officer of the Consortium Passante di Mestre Societ
Consortile per Azioni (PDM S.C.p.A.), Mr. Desideri managed all matters relevant to the project,
including final design and supervision of construction. The new section Pianiga Quarto dAltino is
approximately 20 miles in a heavily urbanized area. The overall minimum width of both travel ways,
each including three lanes plus an emergency lane, is 106.6 feet. The main structures of the work are
nine roadway sections in a trench with eight partially covered and four cut-and-cover tunnels for an
overall tunnel length of 6.3 miles, not including trench sections. There are four viaducts; the longest
one is 2,052 feet long. There are four river crossings, each with a one span bridge (lengths varying
from 82 to 115 feet). There are 14 overpasses, 16 underpasses, five hydraulic structures over existing
rivers, four intermediate toll gates, three interconnections, and new barriers on both the A4 and the
A27 motorways.
A4 Mestre Motorway, Ring Road of Mestre Venezia, Italy ($972,640,118 DBF Contract)
Project Manager , 01/2003 to 04/2004

In this position, Mr. Desideri, on behalf of Impregilo, led the multi-company team in all phases of
the acquisition process through its financial closure.
New Railway Line Pontebba Tarvisio, State Border, Italy ($540,000,000 - DB&B Contract)
Project Manager, 10/1994 to 12/1999

As the General Manager and Technical Director of Consortium Carnia (Impregilo lead partner,
33%), Mr. Desideri functioned as the Project Manager on the project. Work included TBM excavation of a pilot tunnel 15.6 miles long, tunnel excavation for 6.5 miles; viaducts for 0.7 miles, and
construction of the new railway station of Tarvisio Boscoverde.
Safeguarding of Venice and the Lagoon Area DB&B Project, Italy

Project Manager of the Consortium Venezia Nuova, 08/1992 to 09/1994

As the Project Manager, Mr. Desideri supervised all onsite activities on behalf of the New Venice
Consortium. The scope of the work included improvement and reinforcing work for the north and
south wharves of the Chioggia Mouth and protection work of the Pellestrina shore.

Volume 2 Section 1 Key Personnel Resumes - page 2

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

William Corn, P.E.


Project Manager

Licenses and Registrations

Registered Professional Engineer: CA #


C56363

Experience

Career Summary
Mr. Corn is a third-generation infrastructure contractor,
working exclusively in Southern California. His broad
experience includes management, engineering, operations,
and contract administration for highway, transportation,
light rail, and water treatment projects. Mr. Corn is
experienced in different delivery methods including
design-build and bid-build. Due to his fixed-price project
experience, Mr. Corn has developed a thorough
understanding of the importance of delivering projects on
budget, on time, and meeting the owners requirements.
His hands-on experience comes from multiple types of
projects, under different delivery methods, while managing
hundreds of employees. During his career, he has served
in positions ranging from Project Engineer to Operations
Manager, giving him hands-on experience in all aspects of
project management. As a registered Professional Civil
Engineer, he is capable of addressing the needs of the
designers, quality control representatives, city and county
representatives, utility agencies representatives, and Port
and Caltrans representatives. As an experienced builder,
Mr. Corn can communicate effectively with the field
superintendents to transform the needs and visions of the
owner into a completed project.
For the last 10 years, Mr. Corn has served in the
position of Area Manager. Mr. Corn is currently
Operations Manager for the Shimmick southern
California operations, with oversight of projects valued
at over $530 Million.

30 years

Experience in Proposed Role


15 years

Education

B.S. Civil Engineering, California State


University, Long Beach

Professional Associations

International Union of Operating


Engineers 1982 to 1991

RFP Criteria
At least 10 years of roadway, bridge, transit,
or rail construction as a project manager,
deputy project manager or lead
superintendent:
19 years
At least one roadway or bridge construction
project having a construction value greater
than $200 million:
Eastern Transportation Corridor DesignBuild Project
I-5, Caltrans District 12, Buena Park, CA
Licensed as a California Professional
Engineer preferred, but not required:
Registered Civil Engineer, California
#C56363

Design-build experience

5 years
Eastern Transportation Corridor DesignBuild Project

Caltrans experience

I-5, District 12, Buena Park, CA

Relevant Project Experience


I-5, Caltrans District 12, Buena Park, CA ($202 million)
Project Manager, April 2006 March 2008

The widening of I-5 included constructing 1.8 miles of depressed roadway including retaining walls,
bridges, concrete sub-base, lean concrete base, and concrete pavement. Twenty-one traffic stages
were necessary to maintain the traffic flow throughout the project without interruption to the flow.
Mr. Corns responsibilities included staffing, planning and scheduling, quality control, safety, project
schedule, construction engineering, and production oversight.
Eastern Transportation Corridor, TCA, Orange County, CA ($803 million)
Project Manager/Segment Manager, May 1995 December 1998

The project included the construction of 30 miles of roadway in eastern Orange County between the
SR-91 in Anaheim Hills to Oso Parkway in Rancho Santa Margarita. As a Project/Segment Manager
for almost half of the projects segments, Mr. Corns responsibilities included the complete
management and operations, from the commencement of the design through the completion of the

Volume 2 Section 1 Key Personnel Resumes - page 3

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

project for two of the five segments. From start to finish, Mr. Corn managed staffing, relationships
with the Owner and all stakeholders, project planning and scheduling, design management,
constructability reviews for all aspects of design, utility agreements and relocation coordination with
the local utility agencies, MOT and staging plans, safety, environmental mitigation planning, city
coordination for connections to the local roads, quality control and assurance plans, and
construction management of the self-performed work including construction of over 73 structures,
mass-rough-fine grading, drainage installation, and finish roadway. This very successful project was
opened to traffic eight months ahead of schedule.
Assorted Highway Projects, California

Project Manager/Area Manager, 1999 present

For the last 10 years, Mr. Corn has served in the position of Area Manager, managing assorted
projects valued at over $2.4 billion. He is responsible for cost and schedule performance and
adherence to safety and quality programs. Transportation project experience includes:
I-15 Reconstruction (two projects), Caltrans District 11, San Diego and Imperial Counties, CA
($140 million)
I-405, Caltrans District 7, Culver City, CA ($113 million)
La Mesa LRT, San Diego MTS, La Mesa, CA ($60 million)
I-10 Retrofit/Pavement Restoration, Caltrans District 7, City, CA ($25 million)
I-405, Caltrans District 7, Inglewood, CA ($27 million)
I-10, Caltrans District 7, Pomona, CA ($80 million)
SR-30/I-210 highway projects (two projects), Caltrans District 7, Los Angeles County, CA ($130
million)
I-5 (two projects), Anaheim, CA ($44 million)
SR-118, Caltrans District 7, San Fernando Valley, CA ($30 million)
SR-118 Widening, Caltrans District 7, San Fernando Valley, CA ($25 million)
I-5 Rail Bridge, Caltrans District 12, Orange County, CA ($50 million)
I-215, Caltrans District 8, Riverside County, CA ($40 million)
I-105, Caltrans District 7, Los Angeles, CA ($150 million)
Robert B. Diemer Oxidation Retrofit, Metropolitan Water District of Southern California,
Yorba Linda, CA ($188 million)
Operations Manager, October 2009 present

The work consists of performing all necessary mechanical, electrical, civil, and structural work to
retrofit the existing Diemer Water Treatment Plant to treat water with an Oxygen/Ozone system.
The work includes over 60,000 cubic yards of concrete, constructing ozone generation building,
ozone contactors, contactor influent and effluent conduits, contactor rejection tunnel, liquid oxygen
storage and feed system, chemical feed facilities, unit substation, switchgear building, emergency
generator building, large-diameter yard conduits and piping, grading, paving, demolition, adding and
modifying plant utilities and controls, connections to existing facilities, landscaping, commissioning,
training, and the installation of meter vaults and other ozone/oxygen system equipment.
Robert A. Skinner Water Treatment Plant, Metropolitan Water District of Southern California,
Winchester, CA ($206 million)
Project Operations Manager, April 2008 May 2010

The Skinner Ozone Retrofit Facility is a parallel project to the Diemer treatment plant. Both
projects are owned and operated by MWD. The Skinner project is a large and very water treatment
plant that includes over 60,000 cubic yards of structural concrete and many mechanical, electrical,
and architectural structural steel elements. Mr. Corns responsibilities include Quality Control/
Assurance implementation, safety policy implementation, and production and schedule oversight.

Volume 2 Section 1 Key Personnel Resumes - page 4

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

John E. Karn, P.E.


Design Manager

Profession

Civil Engineer

Licenses and Registrations

Career Summary

John Karn is an Associate Principal with Arup and leads


Arups Highways Engineering Practice in the Americas.
John has 20+ years of experience and has developed a
strong technical foundation, considerable communication
skills, and an eye for detail while maintaining a sense of
perspective for broader issues. During his 11+ years with
Caltrans, John developed a broad and balanced knowledge
of designing and building infrastructure projects.
John has led some of the Californias largest and most
complex highway projects. He brings unique experience
to successfully deliver major highway projects in
California.

Relevant Project Experience


Fresno SR 180 Braided Ramps Connections, Fresno,
CA ($40 million)
Design Manager, 2011

This design-build project will replace an existing weave


section on SR 180 between SR 41 and SR 168. The scope
of this project includes constructing two new bridges, one
existing bridge widening, approximately three miles of ongrade ramp connectors, and other associated work.
Doyle Drive Replacement Project, San Francisco
County Transportation Authority (SFCTA)/Caltrans,
San Francisco, CA ($650+ million)

Registered Professional Engineer: CA


#C66743

Experience
20+ years

Experience in Proposed Role


15 years

Education

Advanced Management Institute for


Architects and Engineers, 96 hours of
continuing professional education and
training for Project Management
BS, Civil Engineering, Lehigh Univ.

RFP Criteria
At least 20 years experience in the design
and engineering of transportation (e.g.,
road, rail or transit) structures:
20+ years
At least 10 years experience as lead designer:
15 years
Experience as a lead designer responsible for
at least one roadway, bridge, transit, or rail
project having a construction value greater
than $250 million:
Doyle Drive Replacement Project
Seismic Retrofit by Replacement
of the West Approach to the San
Francisco-Oakland Bay Bridge
Licensed as a California Professional
Engineer:
CA PE #C66743

Lead Designer/Project Manager, 2007 2011

Responsible for managing and delivering concept, detailed design and construction procurement
documents as well as design support during construction for a complete replacement of Doyle
Drive. This 1.6-mile-long 6-lane highway connects San Francisco city streets to the Golden Gate
Bridge, carrying 100,000 vehicles per day. The work includes highway design, elevated structures,
cut-and-cover structures, drainage, utility relocations, geotechnics, and extensive landscaping.
Stakeholders and agencies include FHWA, Caltrans, the National Park Service, as well as residents
and Citizen Action Committees.
Doyle Drive Replacement Project, EIS/R, SFCTA/Caltrans, San Francisco, CA ($650 million)
Lead Designer/Project Manager, 2004 2007

Developed the Preliminary Engineering in support of the EIS/R and PR for this Alternative for
replacing Doyle Drive (see project above). Due to the high visibility and sensitivity of the projects
location, this Alternative sought to preserve much of the natural beauty of the area while catering to
traffic demand and safety. In particular, stage construction for this heavily trafficked route was
developed with to minimize environmental impacts and maintain traffic movements in all directions.

Volume 2 Section 1 Key Personnel Resumes - page 5

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

New York State Thruway AuthorityPreliminary


Design, New York State Thruway Authority, Orange
County, NY ($100 million)

Design-Build Experience:

SR 180 Braided Ramps Connections

Lead Designer/Project Manager, 2003

Caltrans Experience

Project Manager and Lead Designer responsible for the


delivery of scoping and design approval documents and
preliminary engineering for an additional lane, pavement
rehabilitation, and bridge rehabilitation/reconstruction
along I-87 from MP 46 to MP 60.

Seismic Retrofit by Replacement of West Approach to


the San Francisco-Oakland Bay Bridge, Caltrans, San
Francisco, CA ($300+ million)
Design Manager, 1998 2002

SR 180 Braided Ramps Connections


Doyle Drive Replacement Project, PS&E
Doyle Drive Replacement Project, EIS/R
Seismic Retrofit by Replacement of the
West Approach to the San FranciscoOakland Bay Bridge
Highway 101 Rehabilitation
Route 135, Tiburon Blvd, Rehabilitation
Route 101 Seismic Retrofit over Corte
Madera Creek
Seismic Retrofit of I-280/101 Interchange
Route 1 Seismic Retrofit and Resurfacing
Route 1 Rehabilitation and Widening
I-880 Cypress Replacement Project

Complete replacement of the approach structures and


interchanges within the South of Market area. John was
responsible for designing traffic management and stage construction plans to achieve the shortest
time of completion while maintaining all traffic movements during commute hours. He also led the
team charged with designing vertical and horizontal alignments, cross-sections, grading, drainage,
pavement reconstruction and rehabilitation, pavement delineation, and facilities for highways and
local streets. Coordinated groups within Caltrans as well as local agencies and utility owners. Delivered
presentations to numerous stakeholders.
Highway 101 Rehabilitation, Caltrans, Marin, CA ($15+ million)
Project Engineer, 1997 1998

Project Engineer responsible for delivering PS&E for Capital Maintenance of Highway 101 from
Petaluma to Rohnert Park. Program consisted of rehabilitation of PCC pavement by leveling and
grouting, resurfacing AC pavement, and reconstruction of the associated roadway appurtenances.
Route 101 Seismic Retrofit over Corte Madera Creek, Caltrans, Corte Madera, CA ($50 million)
Assistant Resident Engineer, 1996 1997

Project included new bridge substructure, roadway rehabilitation, and traffic management. Negotiated
and wrote contract change orders, interpreted contract plans and specifications, and administered
permits and regulations of numerous agencies (Cal OSHA, RWQCB, FHWA, USACE etc.).
Seismic Retrofit of I-280/101 Interchange, Caltrans, San Francisco County, CA ($50 million)
Assistant Resident Engineer, 1994 1996

In addition to typical elements of roadway/bridge construction, this project involved extensive


traffic management, including temporary ramps and detours. John negotiated and wrote contract
change orders, interpreted plans and specifications, and calculated materials quantities.
Route 1 Seismic Retrofit and Resurfacing, Caltrans, San Francisco County, CA ($40 million)
Assistant Resident Engineer, 1993 1994

This project entailed new seismic approach slabs, bridge rail reconstruction, new median barrier,
pavement resurfacing, new drainage facilities, and nightly road closures with detours. John
interpreted contract plans and specifications to ensure QC/QA, and calculated materials quantities
I-880 Cypress Replacement Project, Caltrans, Oakland, CA ($1.2 billion)
Assistant Project Engineer, 1991 1993

Designed contour grading, intersection layout, curb and gutter flow line elevations, easements and
alignments for railroad and utilities, and right-of-way traverse for property lines as part of the PS&E.

Volume 2 Section 1 Key Personnel Resumes - page 6

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Sena Kumarasena, PhD, PE


Cable-Stayed Bridge
Lead Designer

Profession
Civil Engineer

Experience
20+ years

Experience in Proposed Role

Career Summary
Mr. Kumarasena has over 20 years of experience in the
planning, concept formulation, design development,
construction management, and rehabilitation of bridges of
all types. He has demonstrated a remarkable level of skill
in practical problem solving and the development of
efficient, innovative, elegant bridges designed around site
specifics, economic competitiveness, and constructability.
He has been responsible for developing a number of
original ideas on the application of newer high-strength
materials, innovative combinations of materials, and
optimal structural systems for long-span bridges. His
contributions provide not only economic and
constructability advantages but also added value in a
number of other areas, such as improved maintainability,
high aesthetic quality, and enhanced bridge safety and
security through improved system resilience at no
additional cost.
Mr. Kumarasena has authored a large number of
technical papers on a wide range of topics, including
design innovations, innovative use of newer materials,
and issues of significant future developmental potential.
He is skilled at communicating complex technical ideas
and proficient in refining designs through the use of 3D
computer renderings of bridge concepts.

Relevant Project Experience


Leonard P. Zakim Bunker Hill Signature Cable-Stayed
Bridge, Boston, MA ($125 million)
Lead Bridge Designer, Project Engineer, Deputy Project
Manager, and Project Manager, 1995 2002

20+ years

Licenses and Registrations


Registered Professional Engineer: CA
#C65123

Education

Doctor of Philosophy, Structural


Engineering, Johns Hopkins University
Master of Science, Structural
Engineering, Johns Hopkins University
Bachelor of Science, Civil Engineering,
University of Moratuwa

RFP Criteria
The individual proposed for this position
must have no less than fifteen years
experience.
20 years
This individual shall have prior experience
with the design of at least one cable-stayed
bridge supporting vehicular or rail traffic for
which construction is ongoing or was
completed in the last fifteen years and
having a main span length of at least 700
feet between center lines of towers for a
multi-tower cable-stayed bridge. For a
single-tower cable-stayed bridge, the main
span length, which is the distance between
the center line tower and the face of the
abutment, shall be no less than 400 feet.
Leonard P. Zakim Bunker Hill Signature
Cable-Stayed Bridge
U.S. Grant Cable-Stayed Bridge
This individual must be licensed as a
Professional Engineer in California by the time
the Design-Build Contract is executed.
Registered PE, CA #C65123

This project involved a landmark, award-winning, three-span, two-tower, cable-stayed bridge with a
745-foot main span and 295- and 425-foot asymmetric back spans. The 195-foot-wide steelcomposite main span roadway is supported by two cable planes and includes a 45-foot-wide twolane ramp completely cantilevered to the outer side of one of the cable planes. As Lead Bridge
Designer, Mr. Kumarasena personally developed original solutions to a number of technical and
constructability challenges stemming from the complex structural layout and unique heavily
congested site conditions.
U.S. Grant Cable-Stayed Bridge, Portsmouth, OH ($40 million)
Lead Designer/Engineer, Project Manager, 1998 2006

Mr. Kumarasena led the concept design, final design, and construction phase services for this 1,685foot-long, three-span, two-tower, cable-stayed bridge with a main span of 875 feet replacing an old

Volume 2 Section 1 Key Personnel Resumes - page 7

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

suspension bridge over the Ohio river. The steelcomposite roadway is supported with two cable planes
splaying outward from centrally located single-mast
towers. The bridge features many design innovations that
enhance its economy, serviceability, aesthetics, and
constructability. The bridge towers are supported by
compact water-line foundations. The unique
superstructure design is lighter, uses less structural steel,
and achieves zero net tensile stress on the top side of the
concrete deck under service loads. Construction was
completed in 2006.

Design-Build Experience

Lead Engineer for Anjikhad Arch Bridge,


India, a 900-foot main span, steel
composite, true arch bridge carrying two
railway lines.

Caltrans Experience

San Francisco-Oakland Self-Anchored


Suspension Bridge Alternatives
Mary Avenue Cable-Stayed Pedestrian
Bridge (designed to Caltrans standards)

Deer-Isle Suspension Bridge, Sedgwick, ME

Lead Engineering Analyst Research Investigator, 1984 1989

The project involved a detailed engineering analysis and design review to pinpoint the reasons for
the observed wind vibration susceptibility of this 2,012-foot-long, 1,044-foot main span suspension
bridge. The investigation consisted of developing a detailed finite elements model; extensive analysis
of bridge motion and wind data; and the use of analytical, field-measured, and experimental methods
to develop a mathematical aeroelastic model of the bridge.
Proposed Central Cable-Stayed Bridge, Lexington, KY
Design Engineer, 1990 1991

Mr. Kumarasena was Design Engineer during the final design of this proposed cable-stayed bridge.
Baltimore Harbor (Suspension) Bridges, Baltimore, MD
Design Engineer, 1990 1994

Mr. Kumarasena was Design Engineer for various on-call-type analyses, investigations, and varied
design tasks involved with the upkeep of the bridges.
Kap Shui Mun Bridge and Ma Wan Viaducts, Hong Kong ($200 million)
Design Engineer/Task Leader, 1991 1994

Mr. Kumarasena was Design Engineer and Task Leader during the tender phase and final design of
this design-build project consisting of a 1,400-foot main span double deck, hybrid cable-stayed
bridge and the adjoining 1,650-foot-long, six-span, multicell concrete box girder viaducts carrying
eight lanes of highway and two railway tracks at two levels.
San FranciscoOakland Self-Anchored Suspension Bridge, CA ($1.4 billion)

Technical Lead for the independent review of alternatives to the self-anchored suspension option, 2004

The alternatives evaluated consisted of the redesign of the self-anchored suspension (SAS) with a
composite superstructure and concrete towers, a causeway alternate, and three cable-stayed
alternatives. Mr. Kumarasena developed preliminary designs, quantities and cost estimates, and
construction schedules to enable comparison of the different options on an objective basis. All
designs were developed to be compatible with the locations and capacities of the foundations being
constructed at the time and to meet or exceeded the seismic performance criteria of the SAS design.
Mary Avenue Cable-Stayed Pedestrian Bridge, Cupertino, CA ($12 million)
Engineer of Record for Independent Check, 2007 2008

Mr. Kumarasena led independent verification of design and detailing (final design) for this 450-footlong, 286-foot main span bicycle/foot bridge over I-280. Construction was completed in 2009.

Volume 2 Section 1 Key Personnel Resumes - page 8

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Kwong Cheng, P.E.

Approach Bridge Lead Designer


Career Summary

Profession

Licenses and Registrations

Mr. Cheng has extensive experience in structural


engineering design, management, and constructability
analysis of long-span bridges. Mr. Cheng has served as
Project Manager and Lead Engineer for many bridge
projects in Asia and America. Prior to his founding of
OPAC in 1992, Mr. Cheng had fifteen years of experience
with T.Y. Lin International (TYLI), progressing from
Design Engineer to Vice President and Chief Bridge
Engineer. He was actively involved in managing all phases
of bridge design projects, including design and
construction engineering of long-span structures. His
experience in segmental and cable-stayed bridges includes
conceptual through final design, establishment and stageby-stage analysis of erection procedures, development of
camber and technical consulting during construction.
Mr. Cheng was Project Manager for the Sun Yat-Sen
Freeway Widening in Taipei, directing a team of over 150
engineers and technicians to perform the design of a
13.6-mile elevated twin-viaduct.

Relevant Project Experience


New Carquinez Suspension Bridge, CrockettVallejo,
California ($225 million)
Design Manager for Cable-stayed Alternative, 19972002

Performed concept development and prepared preliminary


design of cable-stayed and suspension bridge alternatives.
Performed final design of the suspension bridge.
Maximum span length is 2,388 ft with deck level 158 ft
above the navigation profile.
New San FranciscoOakland Bay Bridge, SelfAnchored Suspension Spans, San Francisco-Oakland,
California ($1.4 billion)

Civil Engineer

Registered Professional Engineer in


California (C50074), Arizona, Colorado,
Florida, Illinois, Louisiana, Maryland,
Massachusetts, Minnesota, Oregon,
Rhode Island, Texas, Virginia,
Washington
Chartered Structural Engineer in the
United Kingdom

Experience
33 years

Experience in Proposed Role


28 years

Education

M.E., Civil Engineering Rensselear


Polytechnic Institute 1978
B.S., Civil Engineering Massachusetts
Institute of Technology 1976

RFP Criteria
Must have no less than 15 years experience
in the design of bridge structures:
33 years
This individual shall have experience in the
last ten years with the design of two or more
bridges that are 150 feet above grade and
with span lengths of at least 250 feet:
New Carquinez Bridge
SFOBB Temporary Structures for OBG
Erection
Hoover Dam Bypass
Must be licensed as a Professional Engineer
in California by the time the Design-Build
Contract is executed:
Registered Professional Engineer in
California (C50074)

Caltrans Experience
New Carquinez Bridge
SFOBB Temporary Structures for OBG
Erection

Design Check Lead, 2006-2010

The self-anchored suspension spans of the new East Bay Crossing are supported during
construction by contractor-designed temporary structures that are required to meet stringent service
and extreme-event criteria. Provided design criteria input, evaluation for seismic, wind, and ship
collision, independent design checks, and plans review. The length of the main span is 1,263 ft with
deck level 165 feet above mean sea level.
Colorado River Bridge/Hoover Dam Bypass, ColoradoArizona ($114 million)
Construction Design Lead, 20062010

Provided engineering services during construction including development of erection method and

Volume 2 Section 1 Key Personnel Resumes - page 9

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

erection sequence, development of erection protocols to meet strength and serviceability requirements, erection procedures manual, erection wind and seismic performance, geometry and serviceability control. The main arch span is 1,090 ft long and located 900 ft above the Colorado River.
Shenzhen Western Corridor Bridge, Shenzhen, China ($400 million)
Design Supervisor, 20022004

The Shenzhen Western Corridor Bridge is a 12,464ft-long dual-carriageway 3-lane bridge. The
channel spans consist of asymmetrical single-tower cable-stayed bridges with span length up to 688
feet. Provided design supervision and review services, responsible for reviewing wind design, seismic
design, overall structural durability, and pavement design for the orthotropic deck.
I-4/Lee Roy Selmon Expressway Interchange, Tampa, Florida ($389 million)
Design and Technical Consultant during Design Phase, 2006present

This Tampa, Florida multilevel freeway-to-freeway interchange includes 23 bridges, with a length of
12 miles and bridge deck area of 1.5 million ft. Participated in concept, layout, and erection method
development, design criteria and special provisions for segmental construction.
Nanning Butterfly Arch Bridge, Nanning, China ($80 million)
Design Manager, 20002006

Performed design development of a curved 984ft-span through-arch bridge with orthotropic deck
steel box girder, suspended from inclined steel box arch ribs. The deck is 100 ft above the low water
line. Performed shape-finding studies, design, and analytical studies for wind, seismic, global elastic
stability, component capacities, design validation, and construction staging.
Elevated Circulation Roads at San Francisco Intl. Airport, San Francisco, CA ($75 million)
Deputy Project Manager, 19951997

Supervised design of elevated circulation roads. The structures consist of post-tensioned concrete
box girders supported by reinforced concrete bents on pile foundations. Spans vary from 70 to 140
feet; seismic design is to Important Structure, near-fault standards.
Sun Yat-Sen Freeway Widening Project, Taipei, Taiwan, R.O.C. ($1.6 billion)
Project Manager, 19891991

This extensive transportation project consists of interchanges and twin elevated structures for a new
13.6-mile-long freeway within the R.O.W. for an existing freeway and local traffic on surface roads.
The project contains a wide variety of bridge types and span arrangements, including 3.2 miles of
segmental cantilever cast-in-place prestressed concrete box girder bridges with spans up to 590 feet.
H-3 North Halawa Viaduct, Oahu, Hawaii ($100 million)

Project Manager and Lead Engineer for Preliminary Design, 1990

Preliminary and final design for two 6,000-foot concrete viaducts over environmentally sensitive
terrain for Interstate H-3. Prepared a Major Structures Report, performed preliminary design and
analyses, and provided guidance for the final design and analyses for a cast-in-place box girder
superstructure built by the segmental cantilever construction method.
Weirton-Steubenville Bridge, Weirton, WVSteubenville, OH ($30 million)
Project Manager, 19861988

This 1,965-foot crossing of the Ohio River consists of two cable-stayed spans of 820 feet and 688
feet, and four approach spans. The superstructure is composed of longitudinal steel edge girders,
transverse steel floor beams, longitudinal steel stringers and a composite concrete deck. Performed
stage-by-stage erection analyses and a detailed check of erection stresses during construction.
Provided construction engineering services that included redesign of primary loading-carrying
members.

Volume 2 Section 1 Key Personnel Resumes - page 10

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Guillermo Castao

Construction Manager

Profession

Construction Manager
Chief of Department

Licenses and Registrations

Career Summary
Guillermo Castao has 29 years of civil engineering
experience, since 1988 in FCC Construccin, and the last
14 as Construction Manager, all of them managing
transport projects including roads and highways along the
Mediterranean East area of Spain. He has extensive and
unique experience managing construction of megaprojects.
Mr. Castao selected as the Construction Manager for
his experience with this type of bridges and for his work
on the Calatravas Serrera Bridge project.

Mr. Castaos experience as Construction Manager


includes managing works of bridges executed by various
methods: pre-cast segments, on-site progressive
cantilevers, metallic arch bridges, great span bridges, mixed
bridges, and cable-stayed bridges, such as the construction
management of the of Serrera Bridge, in Valencia, which
was designed by the prominent architect Santiago
Calatrava.
Relevant Project Experience
Serreria Bridge, Conditioning the Axis: Alameda El
Saler Motorway; Valencia, Spain ($65 million)
Construction Manager, October 2004 December 2008

Civil Engineer

Experience
29 years

Experience in Proposed Role


14 years

Education

Civil Engineering, Polytechnic University


of Madrid, 1981

Professional Associations

Member of the Spanish Civil Engineers


Professional Association
Member of the Spanish Society of Civil
Engineers

RFQ Criteria
Cable-stayed bridge construction experience
as the construction manager, deputy
construction manager, or lead
superintendent for the construction of at
least one cable-stayed bridge supporting
vehicular or rail traffic:
4.5 years
Construction of the qualifying facility(ies)
shall have been completed in the last 15
years:
9 years
Qualifying facility(ies) shall have a main span
of at least 700 feet (multi-tower), or at least
400 feet between the center line tower and
the face of the abutment (single tower):
Serrera Bridge (590.55-foot-long span,
with a single tower)
Licensed as a California Professional
Engineer preferred, but not required:
CA P.E. in process

The works consisted of a cable-stayed bridge with


orthotropic deck totaling 590.55 feet in length and
reaching 508.53 feet at its main span. It has a mast 410.10
feet high.
The decks width varies between 116.47 feet and 127.95
feet, and its depth varies between 9.91 feet and 11.29 feet.
The foundation is on 20 on-site piles, 145 feet deep by
6.56 feet in diameter. These are joined by caps of variable height and width dimensions.
Twenty-seven internal friction shock absorbers provide vibration control (23 on the longest forward
cables and 4 on the underside of the retaining tubes).
Universal Oceanographic Park; Valencia, Spain ($251 million)
Construction Manager, June 1998 December 2004

Mr. Castao was the Construction Manager for the Oceanographic Park (L'Oceanogrfic) in
Valencia, which is a showcase for a wide variety of ecosystems that represent the planet's marine
fauna, fish, and mammals. Marine and terrestrial coastal environments are recreated for various
climate areas of the Earth. The Oceanographic Park is a set of buildings and landscaped spaces
arranged around a lake that acts as an integrating element of the whole complex from the urban
design point of view. The park was designed in two levels. The underground lower level houses

Volume 2 Section 1 Key Personnel Resumes - page 11

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

most of the aquariums and service areas. The upper level is mostly for outdoor leisure use. This
design makes better use of the available space and has a low environmental impact because there is a
substantial reduction in surface building. The floor area is over a million square feet.
The construction processes used in the most important activities and the differentiating features of
the design are these:
Hyperbolic paraboloid roofs on the Submarino Restaurant and the Admission building
GRC roof over the Arctic Seas building
Water treatment facilities and power plant
Laminated wood structure at the Steak House (the Ocanos Restaurant)
Acrylic
Spatial grid system in the roof of the Arctic Seas, Continental and Chimney buildings
Theme work inside aquariums and outdoors
Western Ring Road of Onteniente; Valencia, Spain ($10 million)
Construction Manager, February 1996 May 1998

The works consisted of the duplication of a 5,150-foot-long road, including a bridge over the
Clariano River. The bridge structure is an arch with an intermediate deck and a single center arch
with a clearance of 459.32 feet and a total sag over the level of the foundation of 114.83 feet, which
is 75.46 feet over the gradient and 39.37 feet under it. The arch over the gradient is combined with a
steel box section, open at the top to allow for concreting. Underneath the gradient, the arch is made
of concrete. The deck is a composite structure under the arches. Its core is structural steel, 84.32 feet
wide where the suspenders are anchored and is concrete between the arch and abutments. The deck
hangs from this arch by means of a system of tubular steel suspenders. Its cross section is tricellular
concrete.
Motorway Utiel Valencia, CN-III. Section: Caudete de las Fuentes; Requena, Valencia, Spain
($68 million)
Site Manager, February 1993 February 1996

Mr. Castao was Site Manager for this new construction 12.29-mile-long motorway. The trunk
section is made of 2 pavements of 2 lanes each way. Five links were built to connect the motorway
with dense urban areas. Seventeen structures were also executed: 7 overpasses, 8 underpasses, and 2
viaducts.

Volume 2 Section 1 Key Personnel Resumes - page 12

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Daniel M. Herlihy, PG, CEG,


CHG, REA, CEM

Profession
Geologist

Environmental Compliance
Manager, Water Pollution Control
Manager & Qualified SWPPP
Developer

Licenses and Registrations

Career Summary

Experience

Dan Herlihy has been involved with hydrogeologic testing


and analysis since 1976 and performed aquifer tests and
hydrogeologic studies in a variety of geologic settings in
California, Wyoming, New Mexico, and Texas. Mr.
Herlihy has been selected as a Subject Matter Expert by
the California Board of Registration for Geologists and
Geophysicists to develop qualifications for the practice of
hydrogeology in California. His hydrologic experience
includes soil and groundwater assessments for remediation
investigations and feasibility studies, and groundwater
resource studies in unconsolidated and fractured rocks.
Mr. Herlihy is an executive manager for the environmental sciences with more than 20 years of experience
in groundwater hydrology and aquifer evaluation,
groundwater and soil contamination, and environmental
project management.

Relevant Project Experience


LNG Field Station, Port of Long Beach ($2 million)
Prepared SWPPP, 2008 2008

Mr. Herlihy prepared a Storm Water Pollution Prevention


Plan for construction. Scope includes grading and drainage
plans prepared by General Physics Corporation using the
format adopted by the California State Water Resources
Control Board. Mr. Herlihy identified and defined best
management practices for the site.

Registered Professional Geologist (PG):


CA #GEO4388, #EG1378, #CHG107)
Registered Environmental Assessor
(REA): CA #224
Certified Environmental Manager (CEM):
NV #1808

35 years

Experience in Proposed Role


30 years

Education

B.S. (Cum Laude) in Geology1973


M.S. in Geology1975
Hydrogeologic Studies, National Science
Foundation Fellowship Traineeship,
Spears and Belford Fellowships

RFP Criteria (Environmental


Compliance Manager)
Graduate degree in a related field (biology,
geology, environmental studies, etc.) or a
California license, in good standing, as a
Professional Geologist:
M.S., Geology
Professional Geologist (PG #4388), CA
Ten years of experience:
30 years
(i) managing environmental investigations:
PEA, Central Region Elementary School

RFP Criteria (Water Pollution


Control Manager)
General Permit for stormwater discharges
associated with construction activity,
Caltrans Standard Special Provisions and
current Stormwater Quality Handbooks and
the SWPPP and WPCP Preparation Manual:
Registered Professional Geologist (PG):
CA #GEO4388, #EG1378, #CHG107)

Water Resource Study for Metro Red Line Segment #3, Los Angeles, CA ($2.4 billion)
Project Manager, 2002 2008

Mr. Herlihy conducted a hydrological monitoring program to determine the impact of Metro tunnel
alignments across six geologic reaches of the Santa Monica Mountains. Analysis of the results identified zones of high tunnel seepage, where grouting was applied to reduce seepage to below accepted
design levels.
Preliminary Endangerment Assessment; Alhambra Unified School District, CA ($1.8 million)
Project Manager, 2008 2010

Mr. Herlihy was responsible for preparing PEA according to California Dept. of Toxic Substances
Control (DTSC) guidelines for a new 2.14-acre high school. The site included the former UST Area,

Volume 2 Section 1 Key Personnel Resumes - page 13

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

and the southern portion of the Materials Storage Area


where PCE was detected. A human health screening
evaluation (HHSE) was performed for the proposed New
High School site.
Metro Preliminary Endangerment Assessment, Avalon
Boulevard Wetland Project; Los Angeles, CA ($6.37
million)
Project Manager, May November 2004

Mr. Herlihy served as the Project Manager responsible for


preparing a PEA Work Plan for a targeted site investigation (TSI) at the 9-acre MTA facility on Avalon Boulevard.
The PEA was prepared in accordance with guidelines of
the Department of Toxic Substances Control (DTSC). Soil
gas samples were collected and analyzed, and soil matrix
samples were obtained. Based on the findings, the impact
was identified and a Health Risk Assessment was prepared, submitted, and accepted by the DTSC.
Contaminated Materials Management Plan, New River
Bridge along Routes 78 and 111; Imperial County
near Brawley, CA ($230.5 million)
CMMP Author, 2008-2009

A Contaminated Materials Management Plan was prepared


by Mr. Herlihy, on behalf Skanska USA Civil West, to
establish management procedures for saturated soils
impacted by sewage waste containing potentially infectious
biological pathogens. According to the Code of Safe
Practices prepared by Mr. Herlihy specifically for this
project, saturated soil removed during soil excavation,
drilling of pilings and other construction activities that
potentially contain sewage waste were stockpiled, drained,
tilled, and allowed to bake in the sun.
111 South Soto Street, Los Angeles, CA ($59,000)
Supervised UST Closure, 2008-2008

Mr. Herlihy supervised underground storage tank closure


performed by Cleveland Wrecking Company for Eastside
LRT Constructors on behalf of the Los Angeles Metro,
and reviewed the UST closure report prepared by CWC.
Based on the oversight and review, UST removal was
conducted pursuant to CWCs South Coast Air Quality
Management District Rule 1166 permit for excavation of
soils impacted by volatile organic compounds (VOCs).

RFP Criteria (cont)


(ii) managing risk assessments
PEA, Alhambra Unified School District
PEA, Avalon Wetland Project, Los
Angeles, CA
PEA, Casa Grande Project, Los Angeles
(iii) managing cleanups
Sampling Program, Camp Pendleton, CA
Soil Sampling for Aerially Deposited Lead,
Sand Canyon / I-5 Intersection, Irvine
(iv) managing mitigation measures related to
remedial and civil construction projects
Metro Red Line Segment #3 Expansion
to North Hollywood, Los Angeles
(v) implementing contaminated materials
management and hazardous waste disposal
plans
Contaminated Materials Management
Plan, New River Bridge Along Routes 78
and 111, Imperial County, CA
(vi) coordination with permitting and regulating authorities
SWPPP for LNG Field Station, Port of
Long Beach
(vii) reporting
Audit, San Diego County Water Authority
NOIs and SWPPP, San Diego
(viii) directing field activities relating to
environmental compliance
UST Closure, Los Angeles Metropolitan
Transit Authority, Los Angeles

Design-Build Experience
Air Sampling, Metro Gold Line Eastside
Extension Project (DB), Los Angeles

Caltrans Experience
Contaminated Materials Management
Plan, New River Bridge

Design-Build Experience
Air Sampling, Metro Gold Line Eastside
Extension Project (DB), Los Angeles

Caltrans Experience
Contaminated Materials Management
Plan, New River Bridge

Gold Line Eastside Light Rail Extension Design-Build, LA Metro, Los Angeles, CA ($90 million)
Air Sampling, 2004 2005

Mr. Herlihy conducted air sampling to monitor airborne lead concentrations at the perimeter of the
work area during removal of surface soils containing elevated lead levels at the site. The sampling
was requested to assess the potential inhalation dose of airborne lead to nearby residential dwellings
and the public. Airborne lead was not detected, and the laboratory detection limit was below the
OSHA 8-hour time-weighted average (TWA) health-based criteria. Based on this result, surface soil
removal activities did not pose an inhalation risk to nearby residents or the public.

Volume 2 Section 1 Key Personnel Resumes - page 14

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Piyush Mehta

Quality Manager
Career Summary

Profession
Quality Control Manager

Experience
32 years

Piyush Mehta has over 30 years of construction


engineering experience with an emphasis in quality
management. Mr. Mehta has been responsible for the
development, implementation, and management of
numerous project quality management plans and programs
throughout his career. This experience includes overseeing
the quality assurance processes and procedures and quality
control (inspection and testing) for both design-build and
bid-build projects.
Mr. Mehta has been responsible for quality control of
concrete production and placements, of a ready-mix
concrete batch plant, and of structural and metals on
freeway projects.

Relevant Project Experience


Robert B. Diemer Oxidation Retrofit, Metropolitan
Water District of Southern California, Yorba Linda, CA
($188 million)
QC Manager, June 2008 Present

Responsible for estimating, negotiating and procuring


quality control of concrete production & placements, for
managing a ready-mix concrete batch plant, and for
structural and miscellaneous metals for the Project. On
this project, approximately 80,000 cubic yards of concrete
will be batched and placed, and approximately one million
pounds of structural and miscellaneous Metals will be
fabricated and installed.

Experience in Proposed Role


15 years

Education

Institute of Design Ahmedabad, India,


1977

RFP Criteria
At least 15 years of quality management
experience on complex infrastructure
projects:
15 years
Five years of experience on at least one
urban freeway, transit, or rail design-build
projects:
Over 9 years total
Eastern Transportation Corridor Design
Build Project 3 years
New Mexico Hwy 44 Design/Build Project
3 Years
San Fernando Valley Orange Line Bus
way Project 3 Years

Design-Build Experience

ETC 28 Mile Toll Road for OCTA/Caltrans


New Mexico Hwy 44/550 for New Mexico
DOT
San Fernando Valley Metro Rapid Way
for Metropolitan Transportation Authority

Caltrans Experience

ETC 28 Mile Toll Road for OCTA/Caltrans


San Fernando Valley Metro Rapid Way
for Metropolitan Transportation
Authority.
Widening of Ave. H for City of Lancaster

Big Tujunga Dam Seismic Rehabilitation, Los Angeles


County Department of Public Works, CA ($90 million)
Construction Quality Manager, 2008 Present

Mr. Mehta is responsible for estimating, negotiating and procuring quality control of concrete
production and placements, for managing a ready-mix concrete batch plant, and for structural and
miscellaneous metals for this $88.5 million dam seismic rehabilitation project. The project includes
conversion of an existing thin arch dam to a thick arch mass concrete dam. The work performed
included rock excavation (drill and shoot), a foundation consolidation grouting program and dental
concrete, rock bolts and anchors (15 feet to 85 feet long), mass concrete production and placement,
a new valve house and various other structures, the demolition and replacement of the control
house and its instrumentation, and replacement of valves ranging in size from 24 inches to 72
inches. All work is performed under the inspection of the Division of Safety of Dams and the
County of Los Angeles.

Volume 2 Section 1 Key Personnel Resumes - page 15

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Robert A. Skinner Water Treatment Plant, Metropolitan Water District of Southern California,
Winchester, CA ($206 million)
Construction Quality Manager, 2005 2008

The Robert A. Skinner Water Treatment Facility is a $203 million project consisting of an upgrade
to an existing water treatment facility for the Metropolitan Water District in Winchester, CA. The
project consists of 25 different structures totaling over 60,000 cubic yards of concrete and includes
new ozone contactors, settling basins and a coal removal structure. Mr. Mehtas duties included
managing a ready-mix concrete batch plant; aggregate crushing, screening, and washing; negotiating
and procuring materials, and quality control of production and placements of the concrete.
Eastern Transportation Corridor, TCA, Orange County, CA ($803 million)
Materials Manager/QA Structural Inspector, 1996 1999

In the Eastern Transportation Corridor, this was a Design-Build project for Silverado Constructors.
It included 27 miles of roadways and 73 bridge structures. The estimated cost is approximately $780
million. Mr. Mehta reported to the QA/QC Manager and had responsibility to manage quality
assurance inspections of the permanent materials on-site and off-site. He developed a Microsoft
Access based material tracking system that proved to be effective for materials management
through closeout of the project. This system allowed tracking of orders, deliveries, warehousing,
Caltrans inspections, and installation statuses. As a lead inspector, he was responsible for inspections
of construction of bridges, box culverts, MSC walls, and overhead sign structures.
Highway 44, New Mexico State DOT ($300 million)
Q/A Segment Manager, 1999 2002

New Mexico Highway 44 was a design-build project, 118 miles long. Works included a new roadway
with super paved pavements and 7 concrete bridge structures. Mr. Mehtas duties included managing
the QA/QC of three construction segments, 68 miles of roadway, 4 bridge structures, and several
drainage and utility structures. His responsibility included managing and scheduling QA inspections,
a testing lab, and QA/QC staff training; regular interactions with construction project managers;
coordinating quality inspection schedules, periodic audits, and surveillance of QC activities; and
consulting with principal QA Engineers and designers regarding any changes, field procedures, and
RFIs.
Orange Line Bus Rapid Transit, LA Metro, San Fernando Valley, CA ($175 million)
Project Quality Manager, 2003 2005

The San Fernando Valley Metro Rapid Way was a $180 million design-build project consisting of a
14-mile-long dedicated bus way through the San Fernando Valley in Southern California. Mr.
Mehtas duties included managing and enforcing all aspects of QA/QC on this Project. Significant
features of the QA/QC Program included:
Independent verification and oversight of activities that affected the quality of work, to verify
and document the achievement of the established quality and technical requirements
Verification that activities affecting the quality of work were performed in accordance with the
specified requirements
Verification that facilities, components, systems, and subsystems performed satisfactorily for the
purposes intended
Appropriate application of resources to provide a high level of confidence in the completed
facility
Retention of objective evidence that the construction services provided by the contractor and by
its subcontractors and suppliers conformed to the requirements of the contract documents and
to the appropriate rules and regulations

Volume 2 Section 1 Key Personnel Resumes - page 16

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Natalina Bernardi, P.E.


Roadway Lead Designer
Career Summary

Profession
Civil Engineer

Experience
27 years

Ms. Bernardi has over 27 years of technical and


management experience in the transportation field. As a
Project Manager and Principal-in-Charge, Ms. Bernardi
has been extensively involved in the engineering design
and enhancement of highways, streets, parking lots and
pedestrian facilities. Her work has included highway and
roadway reconstruction, light rail design, bicycle and
pedestrian access, intersection signals and improvement
plans. Ms. Bernardi has effectively managed large design
teams and worked closely with public agencies, community
organizations, utility companies, institutions, universities
and private owners to incorporate specific concerns and
regulations into design.
Ms. Bernardis ability to facilitate project coordination
between project stakeholders has resulted in the
successful completion of many projects throughout
California.

Relevant Project Experience


I-580 WB HOV Lane Widening Project, Caltrans,
Livermore/Pleasanton/Dublin, CA ($160 million)
Project Manager, 2006 2011

Project Manager for this major 13-mile HOV widening


and roadway rehabilitation project that includes
accommodation for future express lanes, connector ramp
modifications, auxiliary lanes/HOV bypass along 12
interchanges, two interchange modifications, and truck
weight scale modifications. Project involved major
construction staging/traffic detour, utility relocations,
grading and drainage design. Ms. Bernardi oversaw all
facets of the design approval and development, including
the planning, environmental clearance and design aspects
of the project.

Experience in Proposed Role


27 years

Licenses and Registrations

Registered Professional Engineer: CA


#C45407

Education

B.S., Civil Engineering; University of


California, Berkeley; 1985

Design-Build Experience
Sand Hill Road Corridor Project
San Mateo Route 101 Ramp Metering
SVRT BART Extension

Caltrans Experience
I-580 WB HOV Lane Widening
SR4 (East) Widening Project
Marin Sonoma Narrows
Route 87 Widening
SR 152/SR 156 Interchange
Route 17 Widening
Highway 101 Widening
Highway 101/Hillsdale Interchange
Highway 237/I-880 Improvement
Highway 101/University Interchange
Highway 101 3rd Ave to Hwy 92
Highway 101/Marsh Road Interchange
Highway 101/Brittan Avenue
Highway 101/Mary Avenue
Highway 880/Marina Drive Interchange
Route 280/Eastmoor Avenue
Route 85/Prospect Rd to Stelling Ave
Route 101/Tully Road
SR 4 Crosstown Extension
Route 85/Cottle Road Interchange
Route 85/Great Oaks Boulevard
SR 4 / Farmington Road
Highway 9 Safety Project in Santa Clara
County
San Mateo Route 101 Ramp Metering
Route 85 / Miyuki Drive

SR4 Widening Project Contra Loma Boulevard to G Street, Caltrans, Antioch, CA ($87
million)
Project Manager, 2005 2011

The project involved two interchange reconstructions, a rail corridor within the freeway median,
auxiliary lanes and HOV bypass lanes. Located within the city of Antioch, this project involved local
street improvements and restoration, extensive retaining wall and sound wall design, major utility
relocations, ROW acquisitions, and substantial coordination with Caltrans, multiple jurisdictions,
and adjacent designers. As the Project Manager, Ms. Bernardi guided all aspects of the design to
ensure compliance with Caltrans standards and the requirements of the City of Antioch, the mass
transit agency and the regulatory agencies as well as conformance to the interface and construction

Volume 2 Section 1 Key Personnel Resumes - page 17

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

requirements created by adjacent and concurrent reconstruction work to the east and west of the
project site.
Marin Sonoma Narrows Project, Caltrans, Marin and Sonoma Counties, CA ($58 million)
Project Manager, 2008 2012

Project Manager for three separate projects along the congested Marina Sonoma Narrows corridor
which is the familiar name given for the Route 101 freeway through Marin and Sonoma Counties.
The design involved the design of a new interchange, the modification of two existing interchanges
and incorporation of an HOV lane. As part of the design work, the project proposed to realign the
vertical and horizontal profiles to permit the reconstruction of a bridge over a railroad facility. The
project required multi-jurisdictional approvals from Caltrans, regulatory agencies, cities, counties and
transit districts. As well as overseeing the overall project, Ms. Bernardi assisted in right-of-way
acquisition and environmental mitigations.
Highway 101/Hillsdale Interchange, Caltrans San Mateo, CA ($72 million)
Project Manager, 2000 2004

This multiple-phased project involved modifying an existing interchange, collector distributor road,
major roadway infrastructure, local street widening, pedestrian and bicycle facilities, bus terminals
within the freeway, and allowances for train station construction. The incorporation of bicycle
facilities and aesthetic street improvements further complicated the staging of construction, which
required multiple detours. Design also included new and modified traffic signals for three
intersections, ramp metering installation, incorporation of bicycle facilities, right-of-way acquisitions
and utility relocations. As an experienced Caltrans Project Manager, Ms. Bernardi coordinated and
negotiated the cooperative agreements and right-of-way transfers with Caltrans, as well as managed
the construction to smooth implementation of the design.
Route 87 Widening Project, Caltrans, San Jose, CA ($90 million)
Principal-in-Charge, 2000 2006

As the principal-in-Charge for this project involving the 5-mile upgrade and widening from 4 to 6
lanes, Ms. Bernardi was responsible for meeting the project objectives within proposed schedule and
budget. The project included the addition of HOV bypass lanes at on ramps, the addition of
collector-distributor ramp and auxiliary lanes, freeway replacement due to settlement damage to
roadway and structures, and significant storm drainage analysis and improvements. The geometric
design integrated collector-distributor ramps within a freeway-to-freeway connector interchange as
well as modified the vertical alignment through the corridor due to the incorporation of Caltrans
maintenance scope to repair the facility due to settlement. Due to the presence of creek crossings
and the commuter rail set in the center of the highway, significant coordination was required with
stakeholders and regulatory agencies.
SR 152/SR 156 Interchange Project, Caltrans, Santa Clara & San Benito Counties, CA ($17
million)
Project Manager, 2000 2003

Ms. Bernardi was the Project Manager for this project to modify an existing at-grade intersection
into a new interchange. The proposed interchange was a grade-separated flyover with ramp
connectors. Project involved complex stage construction, traffic handling, drainage design, utility
identification, access control, and ROW processing and mapping. The introduction of pedestrian
and bicycle facilities through this Caltrans-controlled facility required coordination with Caltrans to
obtain concurrence and approval. The design development required approval and coordination with
two separate counties, Caltrans (District 4 & 5) and the federal government.

Volume 2 Section 1 Key Personnel Resumes - page 18

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Dan Peluso, G.E., P.E.

Geotechnical Engineer of Record


(GEOR) & Lead Geotechnical
Engineer

Profession
Geotechnical Engineer

Experience
25 years

Experience in Proposed Role


12 years

Career Summary
Dan Peluso is a Senior Geotechnical Engineer with over
25 years of experience in planning and managing
geotechnical investigations and construction monitoring.
His experience includes developing client relationships,
managing schedules and budgets, cost estimating,
preparing proposals, contract review and negotiations,
engineering analysis, and technical report preparation.
Dan has extensive experience in project management,
geotechnical investigations and construction monitoring.

In addition to his design experience, Dan has extensive


consulting experience as a geotechnical reviewer for
several California municipalities, including the cities of
Morgan Hill, Fairfield, Los Gatos, Fremont, Monterey
County and as a reviewer of public assistance construction
design for FEMA. He also has experience in cost
estimating and expert witness consultation.
Relevant Project Experience
Fresno I-80 Braided Ramp Connections, Caltrans,
Fresno, CA ($41 million)
Lead Geotechnical Engineer, 2011 Present

This design-build project will replace an existing weave


section on I-80 between SR41 and SR168 in Fresno. The
scope of this project includes constructing two new
bridges, one existing bridge widening, approximately three
miles of on-grade ramp connectors, and other associated
work. Dan is the Geotechnical Engineer for this project at
bid design stage and, after having recently won the project,
will lead the design through completion.
Transbay Transit Center, San Francisco, CA, Transbay
Joint Powers Authority ($4 billion)
Geotechnical Engineering Reviewer, 2011 - 2012

Licenses and Registrations

Registered Civil Engineer: CA #C49562


Registered Geotechnical Engineer: CA
#GE2367

Education

M.S. Civil Engineering (Geotechnical),


San Jose State University
B.A. Geological Sciences, University of
California, Santa Barbara

Design-Build Experience

Fresno I-80 Braided Ramp Connections

Caltrans Experience

Fresno I-80 Braided Ramp Connections


Butterfield Boulevard Extension, Morgan
Hill, CA
Leavesley Road Widening beneath
Highway 101

RFP Criteria
Experience in the exploration, analysis,
design and construction of:
Department LRFD methodology for bridge
foundations, earth retaining systems, and
other high facilities
Butterfield Boulevard Extension, Morgan
Hill, CA
Fresno I-80 Braided Ramp Connections,
Fresno, CA
Transbay Transit Center Bus Ramps, San
Francisco, CA
Bridge structures and foundations of the
magnitude and type that will be used
Bus Ramp Bridge for Transbay Transit
Center, San Francisco, CA
Planning & conducting subsurface
exploration for highway structures and other
facilities
Fresno I-80 Braided Ramp Connections,
Fresno, CA
West Dunne Avenue Widening, Morgan
Hill, CA
Butterfield Boulevard Extension, Morgan
Hill, CA

Performed pre-construction surveys and prepared reports


of adjacent structures that may be impacted by the
construction of the new Transbay Transit Center
Terminal. This project includes an innovative design for 3,000-foot-long bus ramps that includes the
first vehicular cable-stayed bridge in California. Dan performed geotechnical engineering analysis
and review for design of foundation support for the bus ramps.

Volume 2 Section 1 Key Personnel Resumes - page 19

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

West Dunne Avenue Widening, City of Morgan Hill,


Morgan Hill, CA ($10 million)
Lead Geotechnical Engineer, 2008

Project engineer for geotechnical investigation for


widening of a portion of West Dunne Avenue extending
from Monterey Road to Peak Avenue. The length of
roadway to be widened is approximately 2,500 feet and
will accommodate 4 travel lanes plus a middle turn lane.
The proposed improvements include new pavements,
pavement overlays, retaining walls, curb & gutters, as well
as other associated improvements. As part of the roadway
improvements, several residential driveways to private
properties will need to be reconfigured to accommodate
grade changes at the street. Coordination with traffic
control and obtaining an encroachment permit were
required.
Butterfield Boulevard Extension, Morgan Hill, CA, City
of Morgan Hill, CA ($20 million)
Project Geotechnical Engineer, 2010

Project engineer for a geotechnical study for extension of


Butterfield Boulevard. Improvements include new
roadways, a drainage channel, box culverts, an overcrossing, and two detention basins. Work included
subsurface exploration with soil borings and Cone
Penetrometer Testing, laboratory testing, engineering
analysis and report preparation. Engineering analyses
include pile capacities (compression, tension and lateral)
and settlements, liquefaction potential, bank and levee
stability of drainage channel and detention basins, culvert
foundations, lateral soil pressures, mechanically stabilized
embankments, fill settlement and settlement period, and
pavement sections. Also developed Caltrans-based ARS
curve for seismic design of over-crossing.
West Extension of the VTA Tasman Light Rail Train,
Santa Clara Valley Transportation Agency, Santa Clara
County, CA ($325 million)
Project Geotechnical Engineer, 1996 1997

RFP Criteria (cont)


Site-specific geologic, seismic, and
geotechnical hazard evaluation
Bernal Intermediate School Gym, San
Jose, CA
Herman Intermediate School Gym, San
Jose, CA
Skilled Nursing Facility, The Sequoias,
Portola Valley, CA
Site characterization, including the
development of design soil/rock profiles with
relevant properties for the purpose of
foundation type and size selection, analysis,
design & construction
Fresno I-80 Braided Ramp Connections,
Fresno, CA
West Dunne Avenue Widening, Morgan
Hill, CA
Butterfield Boulevard Extension, Morgan
Hill, CA
Analysis and design of structure foundations
for static as well as dynamic (seismic)
loading
Fresno I-80 Braided Ramp Connections,
Fresno, CA
Butterfield Boulevard Extension, Morgan
Hill, CA
Soil-foundation-structure interaction (SFSI)
analysis
Other members of our geotechnical team
meet criteria
8 years of recent experience in relation to
geotechnical subsurface exploration,
geotechnical analysis, design and
construction of bridge foundations and
retaining walls:
25 years
Fresno I-80 Braided Ramp Connections,
Fresno, CA
West Dunne Avenue Widening, Morgan
Hill, CA
Butterfield Boulevard Extension, Morgan
Hill, CA
Currently Licensed as a California Civil
Engineer and Geotechnical Engineer:
Registered Civil Engineer: CA #C49562
Registered Geotechnical Engineer: CA
#GE2367

Project geotechnical engineer for the West Extension of


the VTA Tasman Light Rail Train. Extensive interfacing
and coordination with other project design professionals,
review agencies and VTA. Project included providing
geotechnical design for retaining walls, box culverts,
shoring and dewatering specifications, bridge pile foundations, track bed foundation, bridge
embankment construction and settlement monitoring. Construction complete 1999.

Volume 2 Section 1 Key Personnel Resumes - page 20

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Daniel Devlin, S.E.

Profession

Design Quality Manager

Structural Engineer

Experience

Career Summary

28 years

Experience in Proposed Role

Daniel B. Devlin has been with Biggs Cardosa since its


inception. Over the past 25 years, Mr. Devlin has been
responsible for the design of numerous building and
bridge structures throughout California. He also serves as
Chief Engineer for the firm. In this role, Mr. Devlins
responsibilities include Quality Assurance, development of
Quality Control and Quality Assurance plans, identifying,
defining, and standardizing analysis and design tools, as
well as implementing policies and procedures to improve
uniformity of design approach between design teams and
design offices.
As Quality Control Manager for multi-disciplinary
projects, Mr. Devlins responsibilities include applying all
of the elements of the Quality Assurance program to
the review of the design, including the review of
procedures for use in the completion of design
documents (including calculations, reports, plans, and
specifications), to ensure accurate tracking and
development of design and ultimately final design
acceptance. He oversees the completed independent
technical reviews, and formal quality reviews before
submittal milestones. Quality assurance verifies that the
quality control check performs the needed review of the
project assumptions and design criteria, analysis
modeling assumptions, model, and results, calculations,
coordination with other disciplines, consistency with
design calculations, plans, details and specifications for
overall completeness, clarity and constructability.
Quality assurance verifies the review includes
coordination for all roadway geometrics, channel work,
traffic control, construction staging, utility coordination
and relocation and environmental issues associated with
the projects including close coordination with Caltrans,
railroads, cities, counties, water districts, Army Corps of
Engineers, Department of Fish and Game, utility agencies
agencies.

18 years

Licenses and Registrations

Registered Professional Engineer: CA


#C39500, #S3116

Education
B.S., Civil Engineering;
University of Santa Clara, 1982
M.S., Structural Engineering;
UC Berkeley, 1983

RFP Criteria
At least 20 years experience in the design
and engineering of transportation (e.g.,
road, rail or transit) structures
28 years
At least 10 years experience as lead
designer, and experience as a lead designer
responsible for at least one roadway, bridge,
transit, or rail project similar in scope to the
Project:
18 years
BART Extension, Central Parkway
Overhead,
Licensed as a California Professional
Engineer by the time the Design-Build
Contract is executed:
Registered Professional Engineer: CA
#C39500, #S3116

Design-Build Experience

Santana Row 5-story mixed-use bldg


Kaiser Hospital Bridge

Caltrans Experience

Route 87 bridge widenings


Arch Road Urban Interchange
Cordelia Interchange structures

and various other government

Relevant Project Experience


Silicon Valley Bart Extension (SVBX), BART, Fremont to San Jose, CA ($1.4 billion)
Quality Control Engineer/Design Criteria Manager, 20082011

Quality Control and Design Criteria development for the Silicon Valley Bart Extension (SVBX)
project; sixteen miles of electrified twin railway lines. BCA was the lead for Stations and Line
Segment Structures. The project consists of design for approximately 40 Line Segment structures
(BART bridges, UPRR bridges, roadway bridges over BART), three elevated platform passenger

Volume 2 Section 1 Key Personnel Resumes - page 21

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

stations, four below-ground passenger stations integrated with the line and tunnel segment
structures, and associated ancillary facilities along the 18-mile BART extension through urban areas.
Warren Avenue UPRR Underpass and Grade Separation: Consisting of a two-span rolled steel
beam with steel deck plate bridge carrying two active UPRR tracks.
Kato Road UPRR Underpass and Grade Separation: Two-span steel beam with steel deck plate
bridge carrying two active UPRR tracks over Kato Road with very tight vertical clearance.
Kato Road UPRR Access Bridge: This structure utilizes composite DSM/Concrete abutment
walls and bent, which is a unique construction approach.
Development of the design-build bid contract documents that included two stations and grade
separation crossings at Dixon Landing Road, Montague Expressway, Capital Avenue, Trade
Zone Boulevard, Hostetter Road and Sierra Road/Lundy Avenue, which is comprised of
overhead and trench u-wall structures, as well as an aerial guideway structure at Berryessa Road.
Route 237/880 Interchange, Caltrans, Milpitas, CA ($43 million)
Quality Control Manager, 20042005

Quality Control review of the E237/N880 Connector Separation flyover structure; a 52-foot-wide,
1,925-foot-long, 10-span bridge constructed over Route 880 and various highway ramps in Milpitas.
The structure is a cast-in-place post-tensioned box girder bridge, consisting of four frames, with a
maximum span of 236 feet. The structure accommodated intricate stage construction requirements,
traffic control through falsework openings, nearby large-diameter gas lines and lengthy embankment
settlement periods.
Airport Blvd On-Ramp UC (VECP), Valley Traffic Authority, San Jose, California ($12 million)
Quality Control Manager, 20052006

Quality Control review of the value engineering fast-track redesign of over 1,000 feet of cut-andcover tunnel and depressed roadway at Route 880. The original design prepared by another
consultant included an underpass to be constructed utilizing slurry walls with full-depth epoxycoated reinforcement cages. Based upon our value engineering review for the contractor, we
proceeded with the design of a more economical structure type using cement deep soil mix (CDSM)
walls and cast-in-place reinforced concrete U-walls.
Southbound Route 87 Connector, Valley Traffic Authority, San Jose, CA ($15 million)
Quality Control Manager, 20022003

Quality Control review of the seismic retrofit of the Southbound Route 87 Connector; a 13-span
bridge approximately 2,200 feet long and 40 feet wide. The bridge spans over Route 85, a freeway
on-ramp, a local street and light rail tracks. Biggs Cardosa performed a complete as-built analysis and
retrofit design of this existing structure. Retrofit work included column casings, bent cap retrofits,
diaphragm bolsters and the addition of isolation gaps at the top of the columns. Biggs Cardosa also
prepared plans and quantities and reviewed the specifications.
Arch Rd / Route 99 Urban Interchange, San Joaquin County, Stockton, CA, ($28 million)
Quality Control Manager, 20002002

Project Manager for the Arch Road/State Route 99 Urban Interchange; A three-span replacement
under-crossing over the proposed Arch Road/Route 99 Urban Interchange and a two-span
temporary steel girder detour overcrossing over Route 99. The existing Arch Road Overcrossing at
State Route 99 was replaced with an urban interchange using staged construction to maintain traffic
throughout the 36-month construction schedule. The first stage included the construction of
Northbound Route 99 embankments, separated from the existing southbound lanes by tall
temporary MSE walls. The northbound half of the overcrossing was constructed first using
abutments supported by steel piles driven through the layers of wire mesh reinforcement embedded
in the backfill behind the temporary MSE walls.

Volume 2 Section 1 Key Personnel Resumes - page 22

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Scott Beyma, P.E.

Construction Quality Manager


Career Summary

Profession
Civil Engineer

Experience
17 years

Mr. Beyma has grown up surrounded by a family of Civil


Engineers. Upon graduating college he has pursued heavy
civil construction with passion and professionalism. After
15 years of dedication to the industry he is now one of the
industry leaders and experts in the engineering and
construction methods that support the heavy civil
industry.
Relevant Project Experience
Robert B. Diemer Oxidation Retrofit, Metropolitan
Water District of Southern California, Yorba Linda, CA
($188 million)
Project Engineer, 2009 to present

Responsible for the construction and coordination of the


Ozone Retrofit Facility, including mechanical, electrical,
architectural and structural aspects. Additional
responsibilities consisted of construction of other
structural concrete on the project including Quality
Control/Assurance, formwork and falsework design
engineering, surveying, production, cost control and
subcontractor management.
Shimmick Construction Company, Inc. Internal
Development

Experience in Proposed Role


7 years

Licenses and Registrations

Registered Professional Engineer: CA #


C68512

Education

B.S., Civil Engineering, California State


University, Fresno

RFP Criteria
At least 15 years of management experience
on complex infrastructure projects:
NN years
List project(s)
At least five years of experience on at least
one urban freeway, transit, or rail designbuild projects:
NN years
List project(s)
Licensed as a California Professional
Engineer preferred, but not required:
Registered Professional Engineer: CA
#C12345, #S1234

Design-Build Experience

Falsework and Formwork Instructor

Metro Orange Line BRT


SR-133/I-5 Interchange - Laguna
Segment

Mr. Beyma is has been responsible for the continuing


internal education of Shimmick Construction in regards to
Falsework and Formwork Design. His class curriculum
includes working with 4-scales, camber strip design,
falsework design, formwork design, falsework inspection
and monitoring, traffic openings and details, column
guying, falsework erection and stripping, pile driving and
post tensioning.

Caltrans Experience

Robert A. Skinner Water Treatment Plant,


Metropolitan Water District of Southern California,
Winchester, CA ($206 million)

I-5 Widening from Broadway to Crescent


SR-133/I-5 Interchange - Laguna
Segment

Summary of Qualifications

Design and/or construction experience in


rail transit on aerial structures
15 years of experience in Quality
Management, including Quality
Assurance/Quality Control activities
Design-Build experience

Structures Engineer, 2005 to present

Mr. Beyma was responsible for the construction and coordination of the Ozone Retrofit Facility, a
large and very complex water treatment plant including many mechanical, electrical, architectural and
structural aspects. Additional responsibilities include assisting with the construction of the 24
structures on the project including Quality Control/Assurance, formwork and falsework design
engineering, surveying, production, cost control and subcontractor management.

Volume 2 Section 1 Key Personnel Resumes - page 23

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Orange Line Bus Rapid Transit, LA Metro, San Fernando Valley, CA ($175 million)
Project Engineer, 2002 - 2005

Mr. Beyma was responsible for the coordination and construction two pre-cast girder bridges and 21
Station platforms along the 14-mile project through the San Fernando Valley under a tight schedule
and difficult conditions. His duties included concrete quality control/assurance, project coordination
and scheduling, and subcontract management.
Various Projects, Gouvis Engineering Consulting Group
Project Manager, 2002 2004

Mr. Beyma was responsible for the structural design of single-family, multi-family and custom
residential project. He performed structural designs in the timber, masonry, concrete, insulated
concrete forming systems and light-gauge steel; as they apply in residential construction. Performed
stress analysis on structural members and force resisting systems. Design of commercial
developments and structural design of commercial remodels and Seismic upgrades.
I-5 Widening from Broadway to Crescent, ($48 Million)
Project Engineer, 1997 2001

Mr. Beyma responsible for the construction of all structures including six overcrossings/ramps, nine
retaining walls and one pump plant. He was heavily involved as a quality control representative in all
aspects of Bridge Construction including temporary foundation shoring and design, pile driving,
bridge falsework construction details and design, superstructure/structure formwork, PostTensioning. Specific bridge construction experience included large diameter CIDH piling, driven
prestressed piling, falsework over Union Railway right-of -way, varied superstructure depth
(parabolic soffits), architectural concrete (soundwall pilasters and retaining wall) and maintaining live
utilities inside superstructures during construction. Duties include preparation and implementation
of all structural details/design for construction, Quality Control/Assurance program, subcontract
administration and scheduling, also tracking quantities/costs, procurement of materials and
managing Owner/Contractor relations.
SR-133/I-5 Interchange - Laguna Segment Design-Build, Irvine, CA
Structures Engineer, 1995 1997

Mr. Beyma was responsible for the construction of six freeway overcrossings and the subcontract
execution of six connectors/overcrossings. He was responsible for all aspects of Bridge
Construction including temporary foundation shoring and design, Pile Driving quality control,
Bridge Falsework construction details and design, superstructure formwork, Post-Tensioning quality
control. Specific foundation construction experience included prestressed piling, cast-in-drilled-hole
piling, post-tension footings, footings with tie-downs and standard bridge footing pile caps. Specific
superstructure construction experience included columns, outrigger bents with post-tensioned caps,
hinges, abutments and bearings, post-tension ducting block-outs, joint assemblies and seals,
approaches and barrier rail. His duties included structure field layouts, structures engineering
calculations/design, subcontract scheduling and quality control/assurance.

Volume 2 Section 1 Key Personnel Resumes - page 24

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Stephen Wilson, CHST


Safety Manager

Education

Credentials

Career Summary

Mr. Wilson has demonstrated success in managing safety


programs for heavy civil projects. He has extensive safety
training and 19 years of experience developing and
implementing safety programs. He is familiar with light
rail-type construction and managing safety programs on
high-hazard work. He recently served as the Safety
Manager for the Big Tujunga seismic rehabilitation which
received an AGC award for safety.

Relevant Project Experience


Big Tujunga Dam Seismic Rehabilitation, Los Angeles
County Department of Public Works, CA ($90 million)
Project Safety Manager

Tri-State University, Angola, Indiana

Construction Health and Safety


Technician (CHST)
Member, American Society of Safety
Engineers (ASSE)
Member, AGC Safety Council

References

Carlos Crisonino,
Panattoni Construction
(Metro Orange Line BRT)
(916) 340-2400
ccrisonino@ panconinc.com
Gary McDonald, RPI Coatings
Big Tujunga Dam Seismic Rehab
RPI Coatings(562) 906-9002, ext 203
gmcdonald@rpicoating.com

Summary of Qualifications

Transit Experience
Design-Build Experience
19 years of experience
Experience with LA County transit
projects
California/Los Angeles County experience
Familiarity with LA Metro requirements
Construction Safety Success

Mr. Wilson managed the safety program and procedures.


Rope access procedures and equipment were used for
much of the work performed on this project including:
rock anchor drilling, rock excavation, and surface prep. An

on-site concrete batch plant operated by Shimmick

provided mass concrete for placement. There was also


cooperation with CDF concerning fire and environmental issues. The project was recognized for its
safety success with the 2008 Safety Excellence on an Individual High Hazard Job Award from AGC
of California.

Robert A. Skinner Water Treatment Plant, Metropolitan Water District of Southern California,
Winchester, CA ($202 million)
Project Safety Manager

Mr. Wilson managed the safety program and procedures. The project scope included working at
heights, underground utilities, and trenching/excavation as the safety-related activities performed. It
was not uncommon to have 70 to 80 carpenters on site at any time, as well as electricians, pipe
fitters iron workers, laborers, and operators.
Orange Line Bus Rapid Transit, LA Metro, San Fernando Valley, CA ($173 million)
Project Safety Manager

This was a 14-mile long dedicated busway through the San Fernando Valley which was designed and
built to LRT standards for later conversion options. Mr. Wilson oversaw the project safety, in which
public protection and vehicle traffic were critical issues on this project. The BRT contained all the
elements of a light rail transit projects, and was designed and constructed to Metro rail transit
guidelines.
New Mexico Highway 44/550, New Mexico Department of Transportation (NMDOT), NM
($300 million)
Project Safety Manager

As safety manager, Mr. Wilsons responsibilities included traffic safety management, job safety
management, safety training and planning, flagger training, accident investigation, writing and
planning toolbox talks (daily safety meetings), and planning and pre-construction meetings.

Volume 2 Section 1 Key Personnel Resumes - page 25

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Various Projects, Albuquerque, MN


Foreman

Mr. Wilsons responsibilities included traffic safety management, flagger training, accident
investigation, crew supervision (pipe installation and paving operations), and planning and preconstruction meetings.
Various Projects, Angola, IN
Crew Foreman

Mr. Wilsons responsibilities included crew supervision, assuring on the job safety, post job followup, troubleshooting problem jobs.
Professional Courses
Construction Health and Safety Technician (CCHEST)
Evaluating High Hazards and Controls (Zurich)
Accident Investigation Techniques (Zurich)
First Aid/CPR Trainer (NSC)
40 Hour HAZWOPER (OSTS)
Hazardous Waste Operations and Emergency Response for Supervisors (National
Environmental Trainers)
Excavation, Trenching and Soil Mechanics (OSHA 3010)
Trainer Course in Trenching Excavation (OSHA 3011)
Permit Required Confined Space Entry (OSHA 2264)
Trainer Course in Confined Space (UCSD 2265)
Fundamentals of Rigging/Train the Trainer (Crosby)
Use, Care and Maintenance of Synthetic Lifting Products (Lift-It)
Flagger Instructor (ATSSA)
Traffic Control Supervisor (ATSSA)
Fugitive Dust Control Class (SCAQMD)
OSHA 500 (UCSD)
High Voltage Electrical Safety (UCSD)
Electrical Standards-OSHA 3095 (UCSD)
Trenching and Excavation Competency (Downey)
Confined Space Awareness (Downey)
Drug/Alcohol Awareness (Downey)
Sexual Harassment Awareness Training (American Safety Training)
Rope Access/Rescue Training (CMC Rescue School)
Fall Protection Training (Golden Gate Safety Associates/Ernie Schulze)
Scaffold Competency Training (Downey)
Lock Out / Tag Out Training (Ontiveros)
For Cause Supervisor Training (Alliance)

Volume 2 Section 1 Key Personnel Resumes - page 26

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Robert M. Schraeder, P.E.


Design-Build Manager

Profession
Civil Engineer

Experience
30 years

Career Summary
Mr. Schraeder has 30 years of experience in construction
and 23 years experience in design and construction of
transit and transportation projects. He brings unmatched
recent, relevant experience in successful delivery of large
multi-disciplined design-build transportation and transit
projects in the Southwest. Mr. Schraeder has solely worked
on large design-build projects for the past 15 years. He is
currently Director of Design-Build. Prior to this role he
was the Project Manager for the $500 million Mid-City
Exposition LRT Design-Build Project, Project Manager
for Foothill South Toll Road design-build, and Sponsor of
design-build projects in Utah. He has the ability to work
effectively with the community, owners, and third parties
in executing transportation projects as demonstrated by
the Orange Line, Exposition LRT Line and Foothill South
Toll Road projects. He brings an understanding of the
greater Los Angeles County community and economic
concerns and knows the subcontracting environment, all
crucial to the success of the Gold Line Foothill Extension.

Experience in Proposed Role


23 years

Licenses and Registrations

Registered Professional Engineer: CA


#C47814

Education

B.S., Civil Engineer, California Polytechnic


University, Pomona
B.S., Applied Mathematics, California
Polytechnic University, Pomona

Design-Build Experience

Metro Exposition LRT


Foothill Transportation Corridor South
Metro Orange Line BRT
SCDOT Carolina Bays Parkway
Eastern Transportation Corridor
UTA Salt Lake City LRT Extension

Caltrans Experience
Caltrans District 7 Partnering Trainer
Foothill Transportation Corridor South
Eastern Transportation Corridor

Mr. Schraeder has served in a wide range of design and


construction operational roles, including Project Sponsor, Project Manager, Deputy Project
Manager, Construction Design Manager, Design Manager, Segment Design Manager and VP of
Design-Build. He has extensive experience mobilizing and managing A&E firms on design-build
projects. Mr. Schraeder was responsible for getting the design back on track on the Mid-City
Exposition LRT Project and the Orange Line BRT Project. He has proven experience and
relationships with numerous third party agencies in Los Angeles County, including Caltrans
District 7, the Los Angeles County Metropolitan Transportation Authority (Metro), LADWP, SCE,
and Metropolitan Water District.

Relevant Project Experience


Exposition Line LRT, Metro, Los Angeles, CA ($500 million)
Project Manager

Mr. Schraeder took over as Project Manager of the $500 million design-build project for 9.6 miles of
light rail track in downtown Los Angeles. Mr. Schraeder reorganized the design and construction
team to focus on the critical path elements of the work. He also established technical task forces to
solve design and construction issues that had lingered for over 6 months. He worked very closely
with the Community Outreach Team and established a new Local Jobs Program to meet the 30%
Local Jobs Goal. In addition, Mr. Schraeder started meeting weekly with the Owner in Executive
Partnering Sessions to address the critical issues that were delaying approval of design and start of
construction. Technical issues were solved and the design was approved for construction so that
work in the field could progress.

Volume 2 Section 1 Construction Resumes page 1

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Foothill Transportation Corridor South, TCA, Orange County, CA ($700 million)


Project Manager

Mr. Schraeder provided direction on this $700 million design-build project to the Design team as
well as constructability reviews and partnering with the Owner, Foothill/Eastern Transportation
Corridor Agency, to support their completion of the environmental review and permit procurement
process prior to the construction phase. Prior to being promoted to Project Manager, Mr. Schraeder
was the Construction Design Manager for the project, overseeing preliminary design of Phase 1A of
this 16-mile limited access toll road.
Orange Line Bus Rapid Transit, LA Metro, San Fernando Valley, CA ($175 million)
Deputy Design Manager

Mr. Schraeder worked directly with the Designers and Contractor to help gain critical third-party
approvals for the $173 million design-build 14-mile BRT project and get it back on schedule. Mr.
Schraeder, through his relationships and knowledge of what was required to complete the design,
brought in additional new design resources to help complete the design so that construction could
proceed. The BRT contained all the elements of a light rail transit projects, and was designed and
constructed to Metro rail transit guidelines.
Caltrans District 7 Partnering Trainer, CA
Partnering Trainer

Due to Mr. Schraeders extensive experience in partnering on projects, he is an Industry Partnering


Trainer for Caltrans District 7. He was trained by Caltrans on how to train others in partnering. In
2009, Mr. Schraeder, with the Caltrans Chief of Construction, conducted six day-long sessions
training Caltrans and industry field personnel on partnering.
Carolina Bays Parkway, SCDOT, Myrtle Beach, SC ($240 million)
Construction Design Manager

Mr. Schraeder coordinated the design of this 20-mile limited access highway $240 million designbuild for the South Carolina Department of Transportation. Partially due to Mr. Schraeders
integration of design and construction, this award-winning project was completed eight months
ahead of schedule. The project included right-of-way procurement, utility relocations, design, and
construction.
Eastern Transportation Corridor, TCA, Orange County, CA ($803 million)
Construction Design Manager and Section Design Manager

Initially responsible for a 3-mile segment of this $803 million toll road, Mr. Schraeder consistently
submitted design packages ahead of schedule and gained early release for construction approval
based on an intermediate submittal for a majority of plans, helping the team complete the main
alignment 14 months ahead of schedule, and the entire project to be completed 10 months ahead of
schedule. Mr. Schraeder was subsequently hired by the Contractor JV as Construction Design
Manager to oversee design completion. He also acted as Resident Engineer, presided over as-built
drawings, and received an award from the Owner for Expediting Approvals by gaining early
releases for construction.
Salt Lake City LRT Extension, UTA, Salt Lake City, UT ($70 million)
Construction Design Manager

Mr. Schraeder was responsible for the bidding and execution of design on national design-build
transportation projects, specializing in integrating design and construction. This included the
University Light Rail Extension for the Utah Transportation Authority, a $70 million design-build
2.5-mile light rail extension in downtown Salt Lake City. With a tight deadline due to the 2002
Olympics, the project was completed on schedule.

Volume 2 Section 1 Construction Resumes page 2

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ron Miller

Utility Coordinator

Profession
Civil Engineering Consultant Specializing in
Utility Coordination

Experience

Career Summary
Mr. Miller has ten years of experience in road; highway;
and mass transit utility and third party coordination
including seven years of major design-build projects in the
Los Angeles area. He is responsible for meeting with each
utility company to identify the location and elevation of all
utilities that are impacted by design and construction. He
serves as a liaison between the owner, design builder, city
agencies and utility companies, ensuring good
communication. Mr. Miller achieves early utility approval
to reduce scope creep, thus reducing costs and schedule
constraints.
Ron Miller has a proven track record of advancing the
schedule of the utility work so that the foundation and
roadway work starts on time or ahead of schedule,
while maintaining the project budget, and meeting the
project milestones.

Mr. Miller regularly interacts with the schedulers,


Construction, and Design Team to achieve an optimum
and fully integrated end product. Furthermore, he
implements a teamwork philosophy, and leads with an
attitude of service. Mr. Miller regularly interfaces with the
Project Managers, Construction Managers, Utility
Companies, Third Party Coordinators, and Approving
Agencies.
Relevant Project Experience
Oakland Airport Connector Project, BART, Oakland, CA
Third Party & Utility Coordinator

The project involved the construction of a 3.4-mile-long


BART Transit Line Connection between the existing
Coliseum Station and the Oakland International Airport.
Mr. Miller coordinated review of utility plans; establishing
contacts for the 3rd Party Utilities, Cities, County, &
Caltrans; developed a utility log of potential conflicts. He
was responsible for permitting and developing a Permit
Matrix; coordinating New Services for the system; and
providing project management.

10 Years Overall, 7 Years Design Build

Experience in Proposed Role


7 years

Licenses and Registrations

Metro Rail Safety Certification


LADWP Electrical Craft Helper
Safe Utility Exposure, Inc. has the
following Certifications: DBE/WBE/SBE by
LACMTA; VSBE by POLB; SBE by City of
Long Beach; Micro SBE by CA DGS;
UDBE with Caltrans

Education

Masters of Divinity, Talbot


Bachelor of Science, Psychology &
Education, Biola University

Design-Build Experience

Exposition LRT, Phase 1


BART Oakland Airport Connector
Metro Gold Line Foothill Extension
Presidio Park Way Project
Exposition LRT, Phase 2

Caltrans Experience

Exposition LRT, Phase 1


BART OAC
Metro Gold Line Foothill Extension
Presidio Park Way Project
Foothill Transportation Corridor South

Summary of Qualifications

Knowledge of CALTRANS Permitting,


ROW Certification & Utility Relocation
Process
Experience with POLB, LA County and LA
County Transit Projects
Familiarity with LA Metro, BNSF, UPRR,
Metrolink and reporting requirements
Expert in providing coordination support
with Utilities and 3rd Parties.
Familiar with permitting and
requirements for the local agencies, oil
companies, and utility companies.
Familiar with the various permitting
agencies and requirements locally, state
wide, and federally.

Gold Line Foothill Extension, Metro, Monrovia, CA


Third Party & Utility Coordinator

The project involved the preliminary design of an 11-mile long extension of a light rail transit line
from Pasadena to Glendora. Coordination included reviewing preliminary plans; establishing
contacts for the third party utilities, cities, and county; and developing a utility log of potential

Volume 2 Section 1 Construction Resumes page 3

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

conflicts.
Exposition Line LRT, Metro, Los Angeles, CA ($500 million)
Third Party & Utility Coordinator

The project involved the construction of a new 8-mile long light rail transit line under construction
from downtown Los Angeles to Culver City. Coordination included over 200 utility rearrangements
made up of USC fiber optic lines, So Cal Gas, AT&T, Time Warner, LADWP Power, So Cal
Edison, LADWP Water, Golden State Water, LAITA, and multiple Los Angeles City and LA
County facilities. This role also required continual coordination with LADOT, LABSL, LABOE,
and CALTRANS to keep the job moving forward in response to the priorities of the project.
Mr. Millers responsibilities included leading a team that determines potential conflicts, overseeing
the design of the composite utility plans, coordination with utility companies to develop
rearrangement plans, permitting rearrangement plans through approving agencies, applying for new
services, permitting, coordinating traffic control plans, and supporting the field during construction.
We also provided underground utility locating; we located the horizontal and vertical position using
air-assisted vacuum excavation; developed a utility matrix and high-resolution digital images of all
the UG utility systems potholed.
Presidio Park Way Project, San Francisco, CA

Permit Coordinator for Golden Link Partners, Flatiron/Kiewit A JV

Mr. Miller provided permitting coordination and developed a log of potential permits needed to
complete the project, which included contacts from various agencies. We also participated in project
management meetings and established meetings for the JV with various permitting agencies.
Signal Design for Bike Path Phase 2, MetroLink, CA
Utility Permitting Coordinator

The project involved the conduit design of various grade crossings through LA City and the Valley.
Coordination included developing preliminary plans; establishing contacts for cities and permitting
agencies, and providing assistance in permitting all work outside of Metro Link ROW. This work
was completed in conjunction with the City of Los Angeles Bike Path Project, Phase 2.
EXPO Phase 2, Light Rail System Extension Stage A, Metro, Los Angeles, CA
Utility & 3rd Party Consultant

Mr. Miller acted Utility & Third Party Consultant for Stage A of the EXPO Phase 2, Light Rail
System Extension. The project involved the preliminary design of a 7-mile long extension of a light
rail transit line from Culver City to Santa Monica. Our coordination included reviewing preliminary
plans; establishing contacts for the 3rd party utilities, cities, & county; and developing a utility log of
potential conflicts. We also provided Permitting coordination and developed a log of potential
permits needed to complete the project, which included contacts from various agencies.
Foothill Transportation Corridor South, TCA, Orange County, CA ($700 million)
Utility Consultant/ Project Mobilization Manager

The Foothill/Eastern Transportation Corridor Agency (TCA) contract for the completion of Phase
1 preliminary design work for the 16-mile Foothill-South project, which will connect the Foothill
(241) Toll Road to the I-5 Freeway. Our coordination included reviewing preliminary plans;
establishing contacts for the 3rd party utilities, cities, & county; and developing a utility log of
potential conflicts. We also provided underground utility locating and Utility Potholing services for
the project.

Volume 2 Section 1 Construction Resumes page 4

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Joe Hernandez

DBE/UDBE Liaison
Career Summary

Profession
UDBE Jobs Compliance Manager

Experience
16 years

Joe Hernandez is a proven executive manager with over 16 Experience in Proposed Role
16 years
years experience in the field of community programs
Education
including: small & disadvantaged business enterprise
programs (SBE & DBE programs), public relations,
B.S. in Engineering, University of
California, Los Angeles, CA
community outreach, local hire programs and labor
compliance. Mr. Hernandez has led the design,
implementation and management of SBE/DBE programs on the largest and most complex
transportation projects in Southern California, including all Metro light rail lines, in various phases
including planning, environmental, design, construction, design-build and operations/maintenance.
On these projects, totaling nearly $11 billion in capital costs, Mr. Hernandez has functioned as DBE
Program Compliance Manager for both public agency and private sector clients. He has extensive
experience working with SBE/DBE stakeholder groups including community leaders, business
organizations, advocacy groups, government agencies, neighborhood policy advisory groups, local
elected officials, trade unions and the media.
Mr. Hernandez brings working relationships with numerous SBE/DBE program administrators
such as Small Business Administration, U.S. Department of Transportation, Metro, City of Los
Angeles, Los Angeles Unified School District, California Department of General Services, Caltrans
and the California Unified Certification Program. He has performed extensive small business
outreach including SBE/DBE good faith efforts, technical support services, advertising, and
collaboration with professional business organizations. Mr. Hernandez is a seasoned public
speaker and has facilitated numerous SBE/DBE meetings, workshops, and seminars.

Relevant Project Experience


SR-91 Corridor Improvement Project/Riverside County Transportation Commission (RCTC);
Riverside, CA

Developing Disadvantaged Business Enterprise (DBE) program requirements for this


Transportation Infrastructure Finance and Innovation Act (TIFIA) assisted heavy highway
construction project. Responsibilities include development of overall DBE Project goal and DBE
Program compliance requirements to be included in Design-Builder contract specifications. Will
oversee Design-Builder compliance with DBE Program requirements and will monitor DBE
participation on project. Related activities include assisting RCTC in implementing race-neutral
outreach activities aimed at increasing SBE and DBE participation on the project.
Iconic Freway Structure (IFS)/ Metro Gold Line Foothill Extension Construction Authority;
Los Angeles, CA

IFS Project Community Liaison for the Design-Builder responsible for building the steel reinforced
concrete bridge, known as the IFS, across the I-210 Freeway as part of the Foothill Extension Phase
2A light rail project. Responsible for the implementation of a Communications Program that
includes efforts to increase SBE participation on the project. Activities include development of SBE
subcontracting plan, establishing relationships with key SBE community stakeholders and
performing outreach and technical support activities.

Volume 2 Section 1 Construction Resumes page 5

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Metro Capital Projects/ Los Angeles County Metropolitan Transportation Authority; Los
Angeles, CA

Responsible for the development and implementation of Metros community programs for this light
rail project and other agency projects, including SBE/DBE programs. Developed a comprehensive
small business outreach program that provides business supportive services aimed at increasing the
pool of business-ready Metro small business vendors (including M/W/DBE). Program includes
small business orientation seminars, small business certification workshops and other small business
related technical support activities. Developed Metros Small Business Certification database to
streamline small business certification processing and to allow increased access to small business
vendor information to purchasing department. Facilitated monthly Transportation Business
Advisory Council meetings where representatives of several small business professional
organizations provide input on Metro small business practices.
Corporate Responsibility Programs, LA LIVE Project/ Anschutz Entertainment Group (AEG),
Los Angeles, CA

Director of economic development related corporate responsibility programs for AEG, a provider
of live entertainment and owner of the Downtown Los Angeles entertainment district known as LA
LIVE. Mr. Hernandez responsibilities included oversight of the City of Los Angeles mandated
small/disadvantaged business program on the development of the $2.5 billion LA LIVE. In this
capacity, Mr. Hernandez served as the corporate wide business industry liaison. He maintained
relationships with the Los Angeles Chamber of Commerce, the Central City Association and several
other advocacy groups. Mr. Hernandez also participated on corporate advisory boards with Los
Angeles area small business organizations. He established key partnerships with public agency
entities. Mr. Hernandez prepared corporate responsibility program status reports to executive staff
and public agency oversight entities.
Exposition Line Phase I & II, Exposition Construction Authority; Los Angeles, CA

Provided guidance and technical support to the Exposition Construction Authority regarding the
development of economic development related community programs, including the DBE Program,
for this light rail project. Working with the Authoritys procurement and legal team, the programs
administered by Mr. Hernandez during his tenure at the Los Angeles County Metropolitan
Transportation Authority were tailored to meet the specific needs of the Phase I project. Mr.
Hernandez facilitated relationships with several community organizations, trade unions and business
organizations in support of these programs. The programs and their policy/procedures were
adopted by the Authoritys Executive Board and are still in use as the construction of this project
continues.
Alameda Corridor Project/ Alameda Corridor Construction Authority (ACTA), Irwindale, CA

Contract Compliance Program Manager for the Alameda Corridor Transportation Authoritys
(ACTAs) freight rail project from the ports of San Pedro/Long Beach to the City of Los Angeles.
Responsible for overseeing D/M/WBE Program compliance covering over 140 public works
contracts on this $2.4 billion project. Served as primary contact with the U.S. Department of
Transportation, Caltrans, California Department of Industrial Relations and the Small Business
Administration. Prepared detailed monthly reports to the ACTA legislative staff, governing board,
and executive team, informing of the successful implementation of the projects community
programs.

Volume 2 Section 1 Construction Resumes page 6

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Sylvia Novoa

Public Information Liaison


Career Summary

Profession
Public Liaison Lead

Experience
25 years

Experience in Proposed Role


Ms. Novoa has over twenty years consulting experience in
20 years
public affairs, government relations, and client/vendor
Education
relations, including experience in strategic planning,
project implementation, and staff and budget
B.A. English; Minor, Spanish, Ethnic &
Womens Studies, California State
management. Ms. Novoa also possesses over fifteen years
Polytechnic University, Pomona
of negotiation experience. Ms. Novoa is experienced in
Certificate, Forensic Translation;
developing culturally-sensitive and language-specific
University of California, Los Angeles
community outreach, participation and education
programs for large-scale infrastructure projects, retail, transportation studies, environmental
documentation and the health care industry. She has also been responsible for developing project
supporters and volunteers to ensure participation in long-term outreach efforts.
25 years of experience with increasing responsibility in implementing communications / public
outreach plans for large public works/capital improvement projects. Knowledge of communications
challenges inherent in major capital improvement projects. Knowledge of emerging trends in the
field of communications, including use of new technologies (Twitter, Facebook, YouTube, etc.).
Knowledge of the principles of public administration, public information, and intergovernmental
relations, including over 10 years of work with elected officials and over 15 years of project
development work with local governments and agencies. Experience in serving as a spokesperson
for large-scale public works projects, including experience as a bilingual spokesperson.

Relevant Project Experience


Alameda Corridor-East Project (ACE); San Gabriel Valley, CA
Strategic Advisor

Ms. Novoa is responsible for developing project collaterals for the San Gabriel Trench Grade
Separation Project. She develops and delivers project information to educate community leaders
regarding the Alameda Corridor-East Construction Authority. Ms. Novoa is also responsible for
developing the stakeholder database for project. The ACE Project involves a consortium of 31
cities in the San Gabriel Valley to prepare for the expected 160% increase in rail traffic by 2020.
Stumpf Consulting

Director of Marketing and Government Relations

Ms. Novoa provided consulting services to healthcare clients, was responsible for bi-lingual
marketing of the Win Pacifico Reduced Fee Dental Program, developed project collaterals and
developed the client database.
URS Corporation

Public Outreach Group Manager

Ms. Novoa directed and/or managed all community outreach programs for many high-visibility
projects. She led companys public outreach practice by successfully developing and marketing URS
public outreach services. Ms. Novoa was instrumental in developing a successful outreach strategies
for transportation, energy, environmental and education clients. She was also responsible for
developing, tailoring and overseeing communication protocols. Example project experience includes
but not limited to:
California High Speed Rail Project. Ms. Novoa led a team that helped pass a bond measure that
guaranteed future project funding, developed and implemented a building block approach that

Volume 2 Section 1 Construction Resumes page 7

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

educated the public on high-speed rail and its benefits, impacts, and mitigations, coordinated
with elected officials along the corridor, including the cities of Los Angeles, Glendale, Burbank,
Lancaster, Santa Clarita and Palmdale, and updated interested jurisdictions on the project status.
Granite Mountain Wind Energy Project-Granite Wind, LLC, a subsidiary of Sierra Renewables,
LLC. Ms. Novoa developed a public outreach and education program that addressed the publics
concerns about wind energy, turbine safety, noise and aesthetic impacts. She coordinated with
the Bureau of Land Management (BLM) to ensure that public comment and concerns were
addressed in the NEPA document.
Project Manager-Public Outreach and Education Program, City of Anaheim Public Utilities
Canyon Power Project Working in conjunction with the City of Anaheim and the California
Energy Commission (CEC), Ms. Novoa led a team that secured approvals for proposed power
plant. She coordinated and facilitated community meetings and ensured community support for
power project.

Metro Gold Line Foothill Extension Construction Authority


Community Outreach Coordinator

Ms. Novoa coordinated public outreach and education programs for the Metro Gold Line Foothill
Extension. She ensured that the 11 corridor cities along the proposed Metro Gold Line route were
updated on the status of the project. Ms. Novoa planned and implemented meetings to educate
community leaders regarding the Gold Line and dispelled project misinformation and built support
for the project by providing tours and one-on-one meetings with interested community members.
Consensus Planning Group, Inc.

Director

Ms. Novoa directed and/or managed multiple outreach projects for both public and private clients.
She specialized in developing political strategy for large public transportation and infrastructure
projects with an emphasis on reaching minority and underrepresented communities. Example
project experience includes but is not limited to:
The Riverside County to Orange County Major Investment Study. Ms. Novoa provided both
Orange and Riverside Counties with project and political strategy and interacted with numerous
corridor cities, elected officials and public agency personnel.
Interstate 710 Major Corridor Study. Ms. Novoa supervised and coordinated a multi-lingual,
multi-jurisdictional and highly controversial public outreach effort for I-710 Major Corridor
Study. Her efforts included coordination with numerous elected officials along the I-710
corridor, inter-action with technical committee as well as State and Federal agencies. Ms. Novoa
was responsible for implementation of public outreach efforts with more than fifteen local cities
along the corridor. The I-710 Corridor included a large portion of Los Angeles County and
numerous cities from SR-60 in Los Angeles to the Ports of Long Beach and Los Angeles.
Interstate 5 (I-5) HOV and Major Investment Study. Ms. Novoa managed public outreach
program involving the proposed addition of a carpool lane between the 91 freeway for the
California Department of Transportation. The bilingual program included coordination with
local elected officials, the development of community awareness materials and planning and
conducting public workshops in coordination with the six cities along the I-5 corridor.

Volume 2 Section 1 Construction Resumes page 8

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Andrs Alonso Quintanilla


Cable-Stayed Manager
Career Summary

Profession
Construction Manager

Experience
31 years

Andrs Alonso is an outstanding Construction Manager of


FCC Construccin, S.A. He brings 31 years of experience
in all aspects from Construction Management to construction, including comprehensive expertise in preliminary and final projects for bridges, roadway and highway
plans, and hands-on knowledge in relevant projects.
Andrs was selected as Cable-Stayed Bridge Manager
due his extensive experience in cable-stayed bridges
and roadway works. In his professional career he has
built 3 cable stayed bridges and many others with
different typologies: post-tension, prestressed,
segmental, metallic, cantilever, arches, continuous slab.

Relevant Project Experience


Motorway A8 of Cantabrico, Las Dueas-Muros del
Naln Section, Asturias, Spain ($231.7 million)
Construction Manager, September 2008 Present

Experience in Proposed Role


17 years

Licenses and Registrations

Registered Professional Engineer: CA


#C12345, #S1234

Education

MSc Civil Engineering, Polytechnic


University of Madrid, 1981

Professional Associations

Member of American Society of Civil


Engineers (ASCE)
Member of the Spanish Civil Engineers
Professional Association
Member of the Spanish Society of Civil
Engineers
IABSE International Association for
Bridge And Structural Engineering
Member of FIB Federation International
du Beton
Member of ATPC a section of PIANC

Design-Build Experience

Fredricton Moncton. Canada


The project was carried out by the Ministry of Develop N-632 Motorway
ment, General Secretariat of State for Infrastructures.
Length of the carried out section 5 miles, 1 cable-stayed
bridge and 5 post-tensioned viaducts being the major one of 2723 feet long, three tunnels, one
junction, excavation in rock, concrete HP-40, 71-inch and 79-inch diameter piles. Three double
tunnels are executed, with total length higher than 1,312.34 yards, as well as six viaducts, with a total
length of 7218 feet, three overpasses and two underpasses. We highlight the construction of
Cudillero interchange, three double tunnels, with a total length longer than 3,9371 feet, six viaducts
with a length of 7,218 feet, three overpasses, two underpasses, eight works of transversal drainage,
the replacement of the deport for water supply to El Manto, as well as a control center of the
tunnels designed.

Enlargement of the Port of Gijn, Asturias, Spain ($1.326 billion)


Construction Manager, December 2006 August 2008

New harbor 12,580-foot-long wall to provide a space of 1.4 square miles on land and a harbor area
of 0.54 square mile, thus doubling the current installations in the port. A bulk solids unloading terminal has been built with a berth of 4100 feet, depths of up to 89 feet and a width of 1312 feet. It
will be able to unload and store 20 and 2 million tons of iron ore and coal, respectively. This project
is one of the great challenges for Spanish port engineering. For vibration control, 27 internal friction
shock absorbers where installed.
Cantabrian Dual Carriageway, Navia Bypass, Asturias, Spain ($123.8 million)
Construction Manager, November 2003 December 2006

In this section of Cantabrian Dual Carriageway (3.9 miles long) we can highlight Anleo and Navia
River viaducts: bridge of precast concrete segment with a total length of 2,977 feet, distributed in 11
spans, with lengths varying between 138 feet and 525 feet. It shows two central spans of 525-foot-

Volume 2 Section 1 Construction Resumes page 9

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

long supported by two metallic arches. With relation to the foundations, 72 piles are needed with
diameter between 6.5 feet and 7 feet and the maximum length of 164 feet.
N-632 Motorway, Grases (Villaviciosa) Infanzn (Gijn) Section, Spain ($219.4 million)
Construction Manager, May 2002 November 2003

The Project consisted in the construction of a highway with a trunk total length of 5,62 mi a
minimum radius of 1,968.50 ft which connects the ring road of Gijn with the Cantabrian
Motorway. 2 carriageways with 2 lanes of 11.48 ft width; Interior roadside of 4.92 ft and exterior of
8.20 ft; with a project speed designed for 62.14 mph. The Braaviella tunnel length of 3,983 ft left
carriageway and 4,065 ft on the right one, made by the New Austrian Method; The Nievares tunnel
7,831 ft left carriageway and 7,746 ft on the right one; 4 double viaducts on the motorway trunk
with continuous slabs, and pre-stressed girders and with spans 82 ft to 13,123 ft; 4 viaducts using
pre-stressed girders for a viaduct length of 328 ft and spans of 131,23 ft; 1 One double viaduct built
by successive overhangs of pre-fabricated segments 1,969 ft length, divided into 6 spans.
Concession, construction, operation and maintenance of the Fredericton Moncton
Motorway DB Project, Canada ($629.89 CAD million, $631.75 million)
Construction Manager, January 2001 May 2002

The Fredericton dual carriageway project has 122 miles and 4 lanes. It was built twenty junctions, 28
overpasses and 2 bridges 1 kilometre long over Saint John and Jemseg Rivers.
Profesor Juan Bosch Bridge over the Ozama River, Santo Domingo, Dominican Republic
($59.62 million)
Construction Manager, August 1997 December 2000

New bridge over Ozama river. The structure is a cable stayed bridge. It is 2106 long with a central
span of 590 and 113.5 wide. The central span was built with the Free Cantilever Method, while the
accesses were built with precast beams and the central area in situ with false work fitted and
concrete poured on site.
Rias Bajas Motorway, Orense-Vigo CN-120, Orense-Barbantes-Meln Section, Orense, Spain
($235.11 million)
Construction Manager, January 1995 July 1997

22 miles section, including one double tunnel, 1883 of a double balanced cantilever bridge, 1,067 of
a double caisson bridge, 3,225 of prestressed concrete bridge, 1,168 of launching bridge and nine
other minor structures and two tunnels.
4th Bridge over the River Guadiana by Badajoz, Real Bridge of Badajoz, Spain ($26.60
million)
Construction Manager, January 1994 December 1994

Cable stayed bridge with 3 spans of 446 + 288 + 105, prolonged with an access viaduct of 6 spans
of 105 each. The total length is 1,483 over the Guadiana river. The deck is 75.5 wide with 2
carriageways of 2 lanes each. The deck is a white concrete box of 6,935 high with 2 cantilevers on
each side. It has 28 cables on fan disposition were used, distributed symmetrically on both sides of
central pier. The central pier has triangular shape with 266 high made of white concrete.The
constructive system consisted on building the bridge over provisional supports by Movable Scaffold
System, proceeding once finished to tight the cables.
Oviedo Pola de Siero Motorway, El Cueto Matalablima Section, Asturias, Spain ($111.8
million)
Structures Site Manager, July 1990 December 1993

The Works consisted in the execution of a section of 13,39 Km length, that included a double tunnel
of 572 m, a prestressed concrete bridge with a surface of 22,391 m2, a pushed bridge of 8,163 m2
and a mixed structure bridge with 30 m length spans.

Volume 2 Section 1 Construction Resumes page 10

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Mike Munden

Civil & Utilities Manager


Career Summary

Profession
Project Manager

Experience
18 years

Experience in Proposed Role


Mr. Munden has over 18 years experience in heavy civil
18 years
construction. He started his career with an underground
Education
utilities contractor wherein he was able to expound his
skills in the implementation and installation of wet and dry B.S., Civil Engineering; San Diego State
University, 1998
utilities, structures, grading, paving and flatwork. Upon
receiving his Civil Engineering degree he then moved on
Design-Build Experience
to the multi-discipline endeavor of constructing
Rialto WWTP Plant #5
water/wastewater treatment plants and conveyance
Pala WWTP
Rialto Biosolids/Slurry Carb Facility
facilities using various project delivery methods. Mr.
DBIA Western Pacific Chapter
Mundens design build experience on the technically
complex and detailed nature of plant work enhances his
ability to collaborate with the project partners from inception of the project through the completion
to achieve a fully functional and aesthetically pleasing product.

Mr. Munden is currently the Project Manager at the Robert B. Diemer Water Treatment Plant
Oxidation Retrofit Program. Prior to this role he was Sponsor of the Fresno/Clovis WWTP
Expansion, Project Manager of design-build Rialto Biosolids/Slurry Carb Facility, Sponsor of the
design-build Pala WWTP, Project Manager Robert A. Skinner WTP Expansion #4 Module 7,
Project Manager IEUA Regional WRF Plant #5 and Project Manager of design-build Rialto
WWTP Plant #5.

Relevant Project Experience


Robert B. Diemer Oxidation Retrofit, Metropolitan Water District of Southern California,
Yorba Linda, CA ($188 million)
Project Manager, August 2009 Present

As Project Manager Mr. Munden champions the culture of safely producing a high quality product,
oversees the daily activities on the project, coordinates upcoming work with the client, cost
reporting and controls, scheduling, change management and issue resolution. The project is to
provide a new Ozone injection process train to an existing 550 million gallon per day water
treatment plant to reduce chemical residuals and provide a better tasting drinking water. The Work
consists of various concrete water bearing structures, electrical duct banks and wiring, numerous
above and below grade piping systems ranging in size from 2 to 144 diameter and materials (i.e.
stainless steel, carbon steel, PVC, HDPE, RCP, copper, Alloy 20), mechanical equipment,
instrumentation and electrical equipment, along with site grading and paving. The project is
currently on time and within budget.
Fresno/Clovis WWTP Expansion, City of Fresno, Fresno, CA ($105 million)
Sponsor, April 2006 July 2009

Mr. Mundens role was to provide sponsor level support to the Project Management team, identify
and assess Value Engineering opportunities and collaboratively resolve construction and contractual
issues with the client. The project was to expand the facility by 12 million gallons per day (MGD) to
allow for a peak flow of 80MGD. The work required the construction of an additional process train
consisting of new Aeration, Sedimentation and Digestion facilities, electrical distribution and
rehabilitation of various existing structures and process systems. The project was successfully
completed on time and within budget.

Volume 2 Section 1 Construction Resumes page 11

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Pala Casino WTP, Pala Casino Resort and Spa, Pala, CA ($16 million)
Sponsor, September 2008 April 2009

Mr. Mundens role was to provide sponsor level support to the Project Management team, facilitate
the design build process between the parties and identify Value Engineering opportunities. The
project consisted of constructing a Headworks, Sequencing Batch Reactor and Chlorination Facility
along with an Administration building. Value Engineering yielded a cost savings of over $1 million
to the client and the project won the DBIA Western Regional and National Award of Excellence in
water/wastewater under $25 million. Despite an unforeseen environmental delay and subsequent
mitigation efforts executed by all parties the project was completed on time and under budget.
Rialto SlurryCarb Facility, Enertech LLC, Rialto, CA ($85 million)
Project Manager, May 2007 May 2009

This design build venture was to construct a prototype Biosolids-to-Alternative Fuel facility using
Enertechs patented SlurryCarb biosolids processing technology. The technology would turn 750
wet tons per day of biosolids into 150 tons per day of dried e-fuel for burning in boilers or other
fuel applications. As construction Project Manager Mr. Munden was involved during conceptual
design stages with the client and design engineer. The result was design and constructability reviews
being achieved concurrently which facilitated procurement of long lead equipment items prior to
mobilizing to the site therefore allowing Mr. Munden and his team to streamline the construction
duration and in conjunction, the overall cost of the project with savings being shared between the
parties. The project was completed 3 months ahead of schedule and within budget.
Robert A Skinner Filtration Plant Expansion #4 Module 7, Metropolitan Water District of
Southern California, Winchester, CA ($84 million)
Project Manager, November 2004 April 2007

As Project Manager Mr. Munden, oversaw the daily activities on the project, coordinated upcoming
work with the client, cost reporting and controls, scheduling, change management and issue
resolution. The project expanded the existing facility by 110 MGD with a new process train of
Sedimentation Basins, Filtering Facilities, Pump Stations, and electrical distribution. The project was
completed on time and within budget.
Regional Plant #5, Inland Empire Utilities Agency, Chino, CA ($52 million)
Project Manager, September 2000 April 2004

As Project Manager Mr. Munden, oversaw the daily activities on the project, coordinated upcoming
work with the client, provided Value Engineering opportunities, cost reporting and controls,
scheduling, change management and issue resolution. The project was a greenfield wastewater
treatment facility processing 15 MGD. The project consisted of Influent and Effluent Pump
Stations, Clarifiers, Aeration Basins, Chlorination Facilities, Chemical processing facilities. Value
Engineering yielded over $4 million in savings shared between the parties. The project was
completed on time and within budget.

Volume 2 Section 1 Construction Resumes page 12

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Brent MacDonald
Electrical Manager
Career Summary

Profession
Electrical Project Manager

Experience
29 years

Mr. MacDonald has 27 years of experience in construction Experience in Proposed Role


15 years
and 10 years experience in design and construction of
Education
electrical projects. He brings a wide variety of experience
in successful delivery of large electrical projects. Mr.
IBEW Local 11, Apprentice Program,
1983 - 1987
MacDonald is currently an Electrical Manager. He
currently is overseeing multiple estimators and electrical
Design-Build Experience
superintendents on 2 projects. Prior to this role he was the BP Plaza 1-MegaWatt Co-Generation
Project Manager on multiple projects. He has proven the
Project
ability to work effectively and hand in hand with owners,
third party engineering firms and multi-owner facilities. Mr. MacDonald has well over 20-years of
experience working hand in hand on projects involving high profile public, private and institutional
clients. Having spent time living and working in, on and around the Long Beach area he understands
the critical nature of all Port projects where communication, execution and commitment to getting
the project done on time is key.
One example of the commitment to getting the job done is the OCSD P2-80 project. This
project was a fast track rehabilitation project requiring the demolition of multiple clarifier pairs.
All the while not impacting the County of Orange sanitation process. During the project Mr.
MacDonald identified issues with the project coordinated with the owner to implement solutions
that not only benefited the project, they also brought the project in on time and under budget.

Relevant Project Experience


P2-91 Plant No 2 Primary Sludge Feed System & job No P2-80 Primary Treatment
Rehabilitation and Refurbishment, Orange County Sanitation District, Huntington Beach, CA
($37 million)
Electrical Project Manager, 2007 - 2010

Project Installation Includes12kV Distribution Upgrade, installation of 2 Station Transformers, 19


Motor Control centers, 9 Remote I/O Instrumentation Cabinets, 2 Programmable Logic
Controllers, Fiber Optic System Upgrade. Associated Power, Control, Signal and instrumentation
Conduit, Cable, Testing and Commissioning.
San Vicente Dam Raise Project & Temporary Power Installation, San Diego County Water
Authority, Lakeside, CA ($140 million)
Electrical Manager, 2010 - Present

Project Installation Includes 12kV Distribution Upgrade, Installation of 12kV Primary Metering,
Installation of 7.5 MVA OH Power Line Installation, 5 Station Transformers, 5 large Motor Control
centers for RCC Dam. Fiber Optic Interface, Overland Conveyor Control System. Associated
Power, Control, Signal, Conduit and Cable for dam interface equipment, instrumentation, dam
monitoring, inlet/outlet water control, fish screening control.

Volume 2 Section 1 Construction Resumes page 13

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Big Tujunga Dam, Los Angeles County Department of Public Works, Tujunga, CA ($88
million)
Electrical Manager, 2010 - 2011

Project Installation Includes New 480-Volt Service Upgrade, New Emergency Generator Building,
New Control House, New Automated Valve House, New Fiber Optic Control Interface with
Automated Valve House Controls. Approximately 150 Dam Monitoring Instruments. Associated
Power, Control, Signal, Conduit and Cable.
BP Plaza, TRC Solutions, Los Angeles, CA (Project Costs Confidential)
Electrical Project Manager, 2002 2003

Furnish and install 1-Mega Watt Co-Generation Facility. New DWP Switchgear, paralleling
switchgear, 1000 of parallel 4000-amp bussway and building controls. Project highlights include
multiple level coordination incorporating multiple existing building controls to remove the building
from a central plant located outside the building site to a self contained go-generation facility located
within the building. The facility provided heating, cooling and electrical generation to the 55 story
BP Plaza building.
Multiple Projects, Multiple Owners, CA (25+ Million)
Role, 2004 2006

Manage multiple electrical projects for multiple owners. Projects ranged from small 1-million dollar
school upgrades to multiple million water treatment facility projects. All of the projects included
extensive coordination with the project owners, construction management teams and engineers.
Some of the projects were high visibility high public interest projects that required very detailed
coordination to ensure the projects were done on time and within budget.

Volume 2 Section 1 Construction Resumes page 14

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Adam Zagorski

Foundations Manager
Career Summary

Profession
Civil Engineer

Experience
20 years

As Project Sponsor, Mr. Zagorski has had overall


responsibility for field operations. His duties include
forming effective management teams that focus on sound
safety practices, optimum production, jobsite safety,
communication and problem solving for each project. Mr.
Zagorski helped develop and maintain project planning,
cost control systems, productivity monitoring, equipment
utilization and sub-contract coordination.

Experience in Proposed Role


18 years

Education

B.S., Civil Engineering; San Diego State


University Name, San Diego, CA 1993

Design-Build Experience
SR 73
I-15 Salt Lake City Utah

Caltrans Experience

Mr. Zagorski has over eighteen years experience in


Hwy 1, PCH Bolsa Chica Ecological
Reserve
heavy civil construction management & supervision.
Hwy - 44
During those years he has acquired the following skills
SR-73
that contribute to his knowledge and expertise in the
industry: earthmoving, structural concrete, dewatering,
RCC delivery and placement, sheet pile and tie back wall installation and complex shoring,
marine jetty construction, tunneling, mechanical installations, electrical distribution and control
systems, underground utility installations, water treatment facilities and bridge construction.

Mr. Zagorski started as an engineer on the San Joaquin Hills Design/Build Toll Road after obtaining
a B.S. in Civil Engineering from San Diego State University. From there he moved up to manage
complex projects while working on the Eastside Reservoir Project for MWD, LAX High Speed
taxiway improvements. Mr. Zagorski managed the Hwy-44 widening and realignment work for
Caltrans and the HWY-1, PCH Bolsa Chica Ecological Reserve and restoration project. Mr.
Zagorski has been involved with planning, scheduling, managing work activities, developing work
plans, and handling design-build contracts and community relations. Mr. Zagorski continued his
professional career with Shimmick Construction where he estimated and ran a $190 million Ozone
Oxidation Retrofit Program (water treatment) project for MWD, and the $140 million San Vicente
Dam Raise Project.
Relevant Project Experience
San Vicente Dam Raise Project, San Diego County Water Authority, Lakeside, CA ($140
million)
Project Sponsor

Project sponsor responsible for the $140 million San Vicente Roller Compacted Dam Project for the
San Diego County Water District. Project includes 630,000 CY of roller compacted concrete with a
tunnel, outlet works, valve house, aggregate production and quarry development.
Robert B. Diemer Oxidation Retrofit, Metropolitan Water District of Southern California,
Yorba Linda, CA ($188 million)
Project Manager

Managed the $190 million Ozone Oxidation Retrofit Project for the Metropolitan Water District of
Southern California. Lead the estimate and managed the initial project startup through 50%
completion with over 180 employees, where the utility relocations, foundation work, mechanical,
electrical, and structure work was self performed by Shimmick Construction.

Volume 2 Section 1 Construction Resumes page 15

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Big Tujunga Dam Seismic Rehabilitation, Los Angeles County Department of Public Works,
CA ($90 million)
Deputy Project Manager

Project Manager on initial start up for $90 million seismic retrofit project and the design and
procurement of the mass concrete batching, cooling and delivery system, along with site
development dam foundation excavation and blasting.
Robert B. Diemer Water Treatment Plant Foundation Improvements, Metropolitan Water
District, Yorba Linda, CA ($71 million)
Project Manager

Project Manager on the $71 million site preparation project for the Metropolitan Water District of
Southern California. Responsible for managing over 80 employees, 7 superintendents and 10 major
subcontractors. The project involved relocation of gas, electrical and other mechanical piping
systems from 2 inch up to 144 inch diameter. In addition, there was the design, installation and
excavation of a 80,000 s.f. tie back retaining wall and construction of a 200,000 CY Roller
Compacted Concrete buttress fill foundation.
Bolsa Chica Lowlands Restoration Project, US Department of Fish and Wildlife / Caltrans,
Huntingdon Beach, CA ($65 million)
Project Manager

Project Manager on the $65 million restoration project for the U.S. Fish and Wildlife Service and
Caltrans. Responsible for managing over 70 employees, 5 superintendents and 7 major
subcontractors. The project involved restoration of over 500 acres of oil fields including
construction of two bridges, dredging, 20,000 LF of levees, jetty and breakwater construction and
handling and disposal of over 100,000 CY of contaminated and hazardous materials.
Highway 44, Caltrans, Susanville, CA ($13 million)
Project Manager

Job Superintendent for this $13 million Cal Trans highway widening project in Northern California.
This project involved roadway excavation and highway realignments and widenings, asphalt paving,
and aggregate processing.
San Joaquin Hills Transportation Corridor SR-73, TCA, Orange County, CA ($780 million)
Project Engineer

Segment Project Engineer responsible for scheduling, subcontract coordination, utility relocations,
traffic control, project phasing and permit and job closeout to Caltrans the County of Orange and
other local cities.

Volume 2 Section 1 Construction Resumes page 16

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Francisco Javier Blzquez


Garca
Formwork Manager

Profession

Licenses and Registrations

Career Summary
Mr. Blzquez has been working for FCC for more than 25
years, as a Formwork Manager and Structures Manager; he
has been working basically in roadway and bridge
construction projects, collaborating in some FCC
landmark projects as the Professor Juan Bosch Bridge in
the Dominican Republic or the Orense-Barbantes Meln
Motorway in the north of Spain. As such, he brings
comprehensive expertise and hands-on knowledge to any
project.
Mr. Javier Blzquez is the perfect candidate for the
position of Formwork Manager due his great experience
in bridges and major cable-stayed structures as the
bridge over Ozama river in Santo Domingo. He also has
DB experience in roadway projects.

Relevant Project Experience


Toronto-York Spadina Subway Extension.
(Canada)($447.51 million)

Structures Manager
Formwork Manager

Member of the Spanish Topographical


Engineers Professional Association
Member of the Official Association of
Technical Engineers in Topography in
Spain.

Experience

27 years

Experience in Proposed Role

27 years

Education

Bachelor Degree in Topographical


Engineering

Design-build experience:
I-95 Managed Lanes. Miami. USA

Skills
Implementation of the works
Engineering
Distribution of the resources available for
the proper execution of the works
Risk assessment
Coordination of the weekly work
schedule, time and budget
QA/QC program implementation
Safety programs implementation

Structures Manager, March 2011/ Present

The Toronto-York Spadina Subway Extension will provide a subway service between Toronto and
York. The project includes the construction of the North tunnels and the Highway 407 Station. It
includes a 2.8 mile underground section with three intermediate stations, as well as a train depot.
Highway 407 Station will be a newly-built underground station 540lf long, 72lf wide and 75lf deep; it
will have a central platform and three floors, two below grade and one above grade, forming a Yshaped building with a bus terminus and open-air parking for 600 cars. The project is being built
using two tunnel-boring machines (TBM) in three phases.
I-95 Managed Lanes. Miami. USA (121.50 million)
Structures Manager, May 2008/ February 2010

Design-Build Project carried out for the FDTO District 6. FCC Co IN Joint Venture with MCM
Corp actuates to create Managed Lanes between the North of the city of Miami and Broward
County (Where I-95 connects to I-595). These managed lanes consist in two limited access HOV
lanes per sense of circulation. In order to successfully carry out the project, it was necessary to widen
the existing structures to the new adopted ones. The works were divided into two phases. Phase 1A
consisted of the execution of 6.2 mi Northbound. The second phase, 1B, included the ITS work and
reconfiguration of the Southbound Lanes similar to what was done in the NB plus the
reconfiguration
A-68 Ebro Dual-Carriageway, Doubling Lanes of N-232. Section: 4 Buuel - Cortes. Navarra.
Spain ($27.78 million)
Formwork Manager, September 2006/ April 2008

The works consisted in the doubling of a section of 3.73 mi, including the enlargement of one

Volume 2 Section 1 Construction Resumes page 17

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

underpass and 2 bridges of three spans. These works were carried out for the Gobierno de Navarra.
It consisted on the extension a current motorway section of 4 miles to a dual carriageway with two
lanes per direction. The project also included the construction of 2 beams bridges of 200 lf each, 2
overpass structures and 1 underpass. The high AADT of the motorway of 20,000 vehicles per day
made this job highly complicated from the MOT point of view.
Plan Riberas Del Ebro U-4 And U-5 Actions. Urban Section Expo 2008. Zaragoza. Spain
($22.16 million)
Formwork Manager, July 2004/ July 2006

The works consisted of the adaptation and improvement of the Ebro Riversides, by the installations
of services, improvement of the Almozara Park and the construction of a singular tightened metallic
footbridge. Include works of drainage and earth moving.
Profesor Juan Bosch Bridge over the Ozama river in Santo Domingo. Dominican Republic.

($59.62 m illion)

Formwork Manager, July 1997/ June 2001

This cable stayed bridge allows the communication between the East and West side of Santo
Domingo. Constructions of a suspension bridge of 1,050 lf of suspension section, the entry is on
two section pre-stressed beams leaning only, 700 lf on the left bank and 2050 lf on the right bank.
Rias Bajas Motorway, Orense-Vigo CN-120. Section: Orense-Barbantes- Meln. Orense.
(SPAIN) ($235.11 million)
Formwork Manager, July 1994/July 1997

Project carried out for the Ministry of Development General Directorate of Roads and Motorway.
22 miles section, including one double tunnel, 836.6 ft of a double balanced cantilever bridge,
1,067ft of a double caisson bridge, 3,225 ft of prestressed concrete bridge, 1,168 ft of launching
bridge among nine other minor structures and two tunnels.
Widening And Improvement Or-410. Section: Pontebarxas-Cortegada. Phase I. P.K. 0.000 To
9.910. Orense ($6.82 million)
Formwork Manager, September 1993/June 1994

CC-546 Lugo-Ourentse by Monforte. Section: Nadel-Sarri.P.K 0 to 25.9.Renovation. Corua


($11.23 million)
Formwork Manager, April 1991/August 1993

CN-640, Vegadeo to Villagarcia de Arosa. Section: Chapa-Villagarcia de Arosa. Improvement


Pontevedra($24.44 million)
Formwork Manager, February 1988/March 1991

Widening and improvement of the pavement. C-547 From Lugo to Santiago. P.K. 531.3 Al
560.0. Section: Guntn-Mello. Lugo and La Corua. Lugo ($4.76 million)
Formwork Manager, August 1985/February 1991

Volume 2 Section 1 Construction Resumes page 18

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ruben Sauceda

Traffic Control Supervisor


Career Summary

Experience
17 years

Experience in Proposed Role


16 years

Education
Mr. Sauceda has been providing field supervision of large,
Palomar Community College, Project
complex transit construction projects for 17 years. The
Management coursework.
past 16 years as a Civil Superintendent, General Project
Summary of Qualifications
Foreman or Labor Foreman. Past light rail project
experience includes the Sprinter Rail Transportation Train 2 years as Superintendent on Sprinter
Rail Transportation Train System
System project. In his Civil Superintendent role on that
17 years of experience on heavy civil
project Mr. Saucedo had the responsibility of managing
construction projects
the work crews installing the ITSS (Intelligent
Key contact for city, state, and local
Transportation Systems & Signal) as well as the electrical
inspectors, resolving any issues.
Responsible for managing multiple crews
utilities crews installing the power systems that supported
and performance
the ITSS systems.
Additional responsibilities include maintaining work zone
traffic control in accordance to projects guidelines as well as coordination among state and local
agencies.

Relevant Project Experience


Robert B. Diemer Oxidation Retrofit, Metropolitan Water District of Southern California,
Yorba Linda, CA
Civil Superintendent

Mr. Sauceda is responsible for overseeing all civil responsibilities on a 188 million dollar project. The
work includes 38,000 linear feet of pipe excavation and installation, ranging from 1 to 144 carbon
steel pipe, excavation and backfill of 8000 LF of electrical duct bank, structure excavation, and
backfill.
Skinner Water Treatment Plant Expansion Project, Metropolitan Water District, Winchester,
CA
Civil Superintendent

Mr. Sauceda oversaw and assisted in all civil responsibilities on a 200 million dollar project. He
oversaw and self-performed all site improvements which included structure backfill, all building of
slopes and 700,000 SF of road grading. He also maintained consistent coordination of
subcontractors for curb and gutter, landscaping and paving. During the tie-in he was in charge of
subcontractors, welders, and safety measures.
Sprinter Rail Transportation Train System, San Diego, CA
Civil Superintendent

Mr. Sauceda oversaw and self-performed 28 miles of rail road track communications and rail road
track preemption. Work included 71 instrument houses and 200 foundations for crossing arms and
signals, structure excavation and backfill for 13 tram stations, excavation and backfill of 400,000 LF
of signal communications duct bank. In charge of coordinating subcontractors for curb and gutter,
landscaping, and paving. He provided coordination with four different cities for removal and
replacement of 32 intersections for road widening and implementation of track preemption.
I-405 Highway Widening Project, CA
Civil Superintendent

Started in late 2004, the project involved widening an approximately 6 mi. (9.6 km) span of I-405,

Volume 2 Section 1 Construction Resumes page 19

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

from Interstate 10 to State Route 90, by one HOV lane in each direction, performing bridge
widening and improvements, and constructing reinforced concrete retaining walls. Each segment
included lane widening, retaining wall, and bridge and various city street work. With different
portions of the project occurring simultaneously, as many as 100 craft employees, during either day
or night, were onsite during construction. During the entire construction process the contractor was
required to maintain four to five lanes of traffic throughout different sections. Mr. Sauceda was
responsible for the management of structural excavation for retaining walls, building all settlement
fills for abutments. Responsibilities also included coordination of all wet utility, storm drain,
drainage inlets, and sewer installations.
Various Projects, (DLS Constructors, Inc.)
Drainage Superintendent

Mr. Sauceda was responsible for coordination of all wet utility, storm drain inlets, water, sewer and
storm drain installations. He managed crews that were staffing approximately four to five jobs
running concurrently and was responsible for scheduling and accelerated schedules as well as
tracking contract quantities. Mr. Sauceda facilitated contract change orders from inception to
completion and maintaining existing budgets and schedules. He coordinated with all Caltrans and
City Agency inspectors daily during all installations.
Various Projects, (DLS Constructors, Inc.)
General Project Foreman

Mr. Sauceda was responsible for maintaining and dispersing crew for the installation of all wet
utility, storm drain inlets, water, sewer and storm drain. Reported and coordinated all activities with
Project Superintendent. He coordinated with all Caltrans and City inspectors daily during all
installations, for all of the following projects:
Various Projects, (DLS Constructors, Inc.)
Laborer Foreman

Mr. Sauceda was responsible for maintaining schedule of crew and crew performance for the
installation of all wet utility, storm drain inlets, water, sewer and storm drain. He reported and
coordinated all activities with Project Superintendent.
Various Projects, (DLS Constructors, Inc.)
Laborer

Mr. Sauceda was responsible for performing labor (e.g. laying pipe, building storm drain inlets) while
meeting scheduling deadlines and budgets on the following project: 241 TOLL ROAD, Subcontract
with FCI Constructors, Inc. He was responsible for assisting the Structures Engineers throughout
the project; duties included structures field layout, engineering, calculations/design, quality tracking
and quality control.

Volume 2 Section 1 Construction Resumes page 20

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Scott Goss

Structures Manager
Career Summary

Profession
Structures Manager

Experience
35 years

Mr. Goss has 40 years experience in construction, and 35


years in heavy civil construction, which includes several
transportation projects. He has a background that has
been developed from hands-on experience to management
relevant in execution of projects that are safe, successful
and completed on time. Over the years he has developed
unsurpassed background in all phases of construction
under various roles from foreman, superintendent and
manager. Key to his successes is his extensive experience
and commitment to successful delivery of projects to the
owners.
Relevant Project Experience
Robert B. Diemer Oxidation Retrofit, Metropolitan
Water District of Southern California, Yorba Linda, CA
($188 million)

Experience in Proposed Role


7 years

Education

AA Fresno City College Cal State


University of Fresno

Design-Build Experience

SR-22

Caltrans Experience
680, 280 101 Interchange
LACTA Aerial Structures Project
I5, 55 Project Orange County
Santa Clara Valley Transit Authority
Guadalupe Corridor Project
Fresno Madera Bridge widening over
Highway 99
Fresno County Bridge Replacement

Structures Manager

Mr. Goss has served as structure manager for Shimmick Construction at the Diemer Water
Treatment Plant in Yorba Linda. An Ozone retrofit to an existing plant the job had over 940,000
square feet of from work and 75,000 cubic yards of concrete that was constructed on difficult terrain
overlooking the town of Yorba Linda. His responsibilities consisted of performing all necessary
structural work to retrofit the existing Diemer Water Treatment Plant to treat water with an
Oxygen/Ozone system. Includes; constructing ozone generation building, ozone contactors,
contactor influent and effluent conduits, contactor rejection tunnel, liquid oxygen storage and feed
system, switchgear building and emergency generator building.
Robert B Diemer Ozone Retrofit, Metropolitan Water District, Yorba Linda Orange County, CA
($184 million)
Structures Manager

Mr. Goss served as the structure manager for this Ozone Retrofit Facility which is very similar to
the Diemer Facility described above with several added elements to the existing plant, with over a
million square feet of formwork and 90,000 cubic yards of concrete. In constructing this large and
complex water treatment plant Mr. Goss oversaw the hiring of new craft resources, coordination of
engineering, implementation of cost controls and tracking that would assure the timely completion
of the concrete structures and Ozone Building.
Olivenhain Pump Station, San Diego Water District, San Diego, County, CA ($52 million)
Structures / Civil Superintendent

Mr. Goss assisted in completion of a new pump station building, new pumps, a new motor control
center, new electrical panels, yard piping and grading.
San Gabriel Track Improvements, Metrolink, Los Angeles, Riverside and San Bernardino
County, CA ($32 million)
Structures Superintendent

Mr. Goss was responsible for construction of new, expanding existing stations, bridges as well as
coordination of trades and disciplines from the City of Covina to the City of Rialto.

Volume 2 Section 1 Construction Resumes page 21

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

SR-22, Orange County, CA ($400 million)


Structures Superintendent

Mr. Goss was involved in the coordination and scheduling of the bridges over the SR 22 Freeway.
River Mountain, Southern Nevada Water Authority, Las Vegas, NV ($166 million)
Structures Superintendent

Mr. Goss was responsible for construction of basins and clarifiers.


Fresno City Waste Water Treatment, Fresno, CA ($76 million)
Structure / Civil Superintendent

Project included the rehabilitation of the existing facilities, a new headworks, biosolids dewatering
equipment, and additional process units to increase capacity. The new facilities came online with an
increase in capacity to 68 MGD. Mr. Goss was responsible for the construction of the Digesters,
Splitter Box, Clarifiers as well as site grading.
Bridge Replacement Project, County of Fresno, CA ($3 million)
Project Manager

Mr. Goss was responsible for the construction of 2 fast track bridges in the remote area of the
Coalinga Hills replacing 2 that were destroyed during a storm. Both bridges were completed ahead
of schedule.
Highway 99 Bridge Widening, County of Fresno and Madera, CA ($3 million)
Project Manager

As Project Manager Mr. Goss was responsible for the bridge widening of 3 bridges over highway 99
in Fresno and 3 bridges in Madera ca.
Santa Clara Valley Transit Authority, Santa Clara, CA ($88 million)
Foreman

Mr. Goss was responsible for constructing bridge structures, pump stations, pump stations and
Branham Lane train station.
I-5/SR-55 Project, Orange County, CA ($18 million)
Foreman

Mr. Goss was responsible for constructing bridge structures, abutments and retaining walls.
Mid Corridor LRT Aerial Structures, Orange County, CA ($18 million)
Structures Superintendent

The LA Metro Blue Line LRT completed in 1990 that consisted of bridges at the Long Beach switch
yard, over the 710 freeway, Delamo Avenue and Slauson Avenue. Responsibilities included setting
up saw shop facilities, and overseeing the falsework, form design, and form fabrication of all bridges
as well as coordination of disciplines and trades.
680 280 101 Interchange, Santa Clara County, CA ($39 million)
Foreman

A Caltrans project to complete the flyover and clover leafs and ramps. Responsibilities included
constructing of hinges, transflex joints, stems, soffits, lost decks and falsework.

Volume 2 Section 1 Construction Resumes page 22

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Keith Wood

Equipment Manager
Career Summary

Profession
Equipment Manager

Experience
28 years

Keith Woods 28 years in the heavy construction


equipment repair and maintenance industry have been
very diverse. Experience with cranes of all types,
earthmoving equipment and utility equipment, as well as
modification and fabrication of specialized equipment and
tools, leading mechanics thru minor repairs to complete
machine rebuilds on time and on budget.

Experience in Proposed Role


18 years

Education

Associates Degree; Denver Automotive


and Diesel Collage 1984

Relevant Project Experience


K&S Heavy Equipment Repair Inc, Livermore CA
1996 to 2005

Executive management of corporation, manage day to day operations, managed all compliance and
regulatory needs, managed workmans comp and liability insurance, Negotiated contracts with
Operating Engineers Local 3 and all labor issues, managed all repairs including estimate, parts
procurement and technical research. K&S developed a reputation for being able to tackle complete
machine overhauls and special projects while staying on budget.
Wagner & Son Inc., Livermore CA
1999 to 2005

Executive management of corporation and business development took this company from a low
volume engine machine shop to a full line machine shop specializing in construction equipment.
C.W. Roen Construction Co, Livermore CA
1986 to 1996

Management of equipment fleet, compliance and regulatory needs, build and supervise repair staff,
purchase and sell equipment. Helped C.W. Roen develop an equipment maintenance program and a
well-equipped repair shop.

Volume 2 Section 1 Construction Resumes page 23

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Volume 2 Section 1 Construction Resumes page 24

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Jorge Aranda Martnez


Construction Engineering
Manager
Career Summary

Profession

Licenses and Registrations

Jorge Aranda is an outstanding Construction Engineering


Manager of FCC Construccin, S.A. He brings 14 years of
experience in all aspects of road and motorway
Construction Management. He has spent his entire career
with FCC.
Jorge is the elected as Construction Engineering
Manager due to his great experience in this type of
bridges and his work in two DB roadway projects that
included numerous bridges and structures. He also has
a wide experience in the construction of singular
bridges of different typologies.

Construction Engineering Manager


Member of the Spanish Civil Engineers
Professional Association
Member of the Spanish Society of Civil
Engineers

Experience

14 years

Experience in Proposed Role

14 years

Education

MSc Civil Engineering, 1998

Design-build experience:

New Road. Motorway N-632. Section:


Grases (Villaviciosa) Infanzn (Gijn).
Asturias (SPAIN)
Mieres Gijn Motorway

Skills

Relevant Project Experience

Connection road Naln Corridor. Motorway of


Cantbrico (3rd Phase). Asturias (SPAIN) ($64.42
million)

Construction Engineering Manager, 09/2010 to present

Civil Works scheduling


Establishment of the Execution
procedures
Responsibilities on Quality, Costs and
Schedule
Engineering
Construction management
Risk assessment
Cost and Budget Management
QA/QC program implementation
Safety programs implementation

This project was carried out for the Asturian Government


General Technical Department. The project consists in
the construction of a section of the Cantbrico motorway
with a total length of 2.62 miles. The structures to be
executed are: 2 tunnels 2 structures over the railway line, 2 metallic structures, 1 viaduct and 4 under
passes. The starting date was April 2010.
Enlargement of the Port of Gijn. Asturias (SPAIN)
($1,326 million)

Construction Engineering Manager June 2006 / August 2010

New harbor 12,580-foot-long wall to provide a space of 1.4 square miles on land and a harbor area
of 0.54 square mile, thus doubling the current installations in the port. A bulk solids unloading
terminal has been built with a berth of 4100 feet, depths of up to 89 feet and a width of 1312 feet. It
will be able to unload and store 20 and 2 million tons of iron ore and coal, respectively. This project
is one of the great challenges for Spanish port engineering. For vibration control, 27 internal friction
shock absorbers where installed.
A-8 Cantabrian motorway. Section: Queruas-Otur. Asturias (Spain) ($75.71 million)
Construction Engineering Manager. April 2004 / May 2005

This motorway project was carried out by the Ministry of Development. General Directorate of
Roads. Motorways.. The project has a length of 5.41 miles, includes the execution of different
junctions, 1 new viaduct, enlargement of two viaducts, San Timoteo Viaduct (1,771.6 ft) and Canero
Viaduct (1,542 ft), 4 underpasses. FCC carried out the works according to the conditions document
for the contracted project to the full satisfaction of the client.

Volume 2 Section 1 Construction Resumes page 25

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

New Road. Motorway N-632. Section: Grases (Villaviciosa) Infanzn (Gijn). Asturias
(SPAIN) ($219.4 million)
Construction Engineering Manager. April 2002 / March 2004

This Design Build project was carried out by Ministry of Development General Directorate of
Roads and Motorways. The total length of the main line is 5.62 miles, ant the most important works
were: 1 junction, 2 double tunnels, with lengths 4,065 ft and 7,802 ft, 9 viaducts with a total length
of 4,219 ft, 3 overpasses and 2 underpasses.
million)

Construction Engineering Manager. October 2001 March 2002

This Design Build project was carried out by the Principality of Asturias. Department for
Infrastructures. General Management of Roads. The total length of the main line is 5.80 miles.
Along the motorway 3 viaducts (1 of them double), 2 double tunnels, 3 overpasses, 5 underpasses
and 3 false tunnels were built
Motorway of Cantbrico. Section: Lamadrid Unquera. Santander (SPAIN) ($165.99
million)
Construction Engineering Manager. October 1998 September 2001

Ministry of Development General Management of Roads and Motorway. The project consisted in
the execution of 9.8 miles of motorway between the proximities of Lamadrid and the border of the
province of Asturias, with 4 links. 28 structures, 3 of which are of particular interest: Escudo
Viaduct of 1,251 ft long, and Tina Menor viaduct of 751 ft long.

Volume 2 Section 1 Construction Resumes page 26

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Michaiah Revero

Project Controls Manager


Career Summary

Profession
Project Manager

Experience
12 years

Mr. Reveros construction engineering and management


career is characterized by innovation in construction, solid
understanding and execution of contractual requirements
and procedures, and a clear commitment to owner collaboration via partnering methods. His effective partnering
skills are evidenced by receipt of two Caltrans project
partnering awards. Maintaining a high standard of ethics in
project delivery, recognizing the human element of construction management, and a commitment to understanding contractual details constitutes the backbone of Mr.
Reveros management ability.
Mr. Revero also has a strong background in Caltrans
highway and bridge construction through his engineering and management experience on seven Caltrans
contracts.

Experience in Proposed Role


8 years

Licenses and Registrations

Registered CA EIT: #EIT111929

Education

B.S., Civil Engineering; California State


University, Long Beach; 2002 (Cum
Laude)

Caltrans Experience
I-5 Widening & Soundwalls, San
Fernando
I-10 Rehabilitation & Methacrylate,
Downtown Los Angeles
SR-91 / Green River Rd Interchange,
Corona
SR-133 Hwy Reconstruction, Irvine
I-405 / Jeffery Rd Interchange, Irvine
I-405 / SR-55 Interchange, Santa Ana
I-405 / SR-73 Interchange, Costa Mesa

Relevant Project Experience


Robert B. Diemer Oxidation Retrofit, Metropolitan Water District of Southern California,
Yorba Linda, CA ($188 million)
Assistant Project Manager, 2010 Present

A substantial upgrade to a large, existing water treatment plant to provide ozone disinfection capability. Mr. Revero has been responsible for management and implementation of contractual
requirements and procedures, maintaining, updating, and performing analysis of the project CPM
schedule, change management, and managing operational activities such as owner correspondence
and inquiries, submittals, cost control, and billings.
I-5 Widening & Soundwalls, Caltrans District 7, San Fernando, CA ($16 million)
Project Manager, 2009 2010

Mr. Revero successfully managed construction of this 3-mile-long highway widening, including castin-place and precast bridge construction, bridge seismic retrofit, HMA and PCC paving, retaining
walls, barrier rail, masonry sound walls, Gross Solids Removal Device structures, and Austin Vault
Sand Filter structures. Mr. Revero and his Caltrans counterpart applied for and won a Caltrans partnering award for successful use of partnering methods.
I-10 Rehabilitation & Methacrylate, Caltrans District 7, Los Angeles, CA ($18 million)
Project Manager, 2007 2009

Difficult working conditions characterized this freeway viaduct rehabilitation in a busy, congested,
urban area. This project was 80% night work requiring extensive traffic control and direct
coordination with the local community. In managing startup, execution, completion, and close-out
of this project, Mr. Reveros achievements included establishing mutually acceptable inspection,
quality control, and payment methods for the newly created deck treatment technology, as well as
strategically modifying work plans to best incorporate post-bid owner design changes, related to
unknown existing conditions, at the lowest possible cost to the owner. Despite the difficult and

Volume 2 Section 1 Construction Resumes page 27

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

changed conditions, Mr. Revero lead the project team to complete the work seven months early.
I-405 / Jeffrey Road Interchange, City of Irvine / Caltrans, Irvine, CA ($9 million)
Project Manager, Engineer, 2005 2007

Mr. Revero managed startup construction, and contract closeout of this freeway overcrossing bridge
widening, which included City sponsored cast-in-place post tensioned box girder bridge construction, roadway widening, and ramp reconstruction under Caltrans oversight. This project included
development and execution of a cost reduction proposal for a combination cast-in place, precastonsite bridge design and construction methodology that was never previously used in California,
which was then utilized by other contractors for subsequent Caltrans work. Mr. Reveros coordination efforts on this project were recognized by a Caltrans partnering award.
SR-91 / Green River Rd Interchange, Caltrans District 8, Corona, CA ($13 million)
Project Manager, Engineer, 2006 2007

While managing this bridge replacement project, which included cast-in-place post tensioned box
girder bridge construction, demolition of an existing high-traffic bridge, retaining wall construction,
roadway widening, and ramp reconstruction, Mr. Revero successfully initiated the first phases of
construction, including development of a strategic partnering alliance with the Caltrans construction
team that paved the way for a collaborative construction process. Mr. Revero also helped pioneer
the Districts then-new electronic Lane Closure System by voluntarily participating in direct,
Contractor entry of planned lane closures into the new online system, in conjunction with the
projects traffic control program.
SR-133 Highway Reconstruction, Caltrans District 12, Irvine, CA ($25 million)
Project Manager, Engineer, 2006 2007

Upon being assigned to manage this 4-mile complete highway reconstruction project, which
included 8 bridges, over 1,000,000 CY of earthmoving, complex above ground and subsurface
drainage facilities, as wells as stringent environmental and archaeological requirements, Mr. Reveros
accomplishments included significantly improving owner-contractor relations, successfully resolving
previous longstanding CPM schedule disputes, and working to strategically control owner costs after
a significant archaeological find.
SR-133 / Laguna Cyn Rd Intersection, The Irvine Company, Irvine, CA ($2.5 million)
Project Manager, Engineer, 2006 2007

This project was situated within the above listed SR-133 project, despite contract documents that
depicted the SR-133 project as previously completed. Mr. Reveros collaborative efforts with the two
respective owners, multiple outside agencies, and interested community organizations, enabled both
projects to be constructed simultaneously.
Pier G Reconstruction, Port of Long Beach, Long Beach, CA ($50 million)
Office Engineer (CM), 2001 2002

Pier and wharf reconstruction consisting of revetment import, dredging and fill operations, battered
piling, grading, paving, new pier facilities, and truck scale installation. Mr. Revero fulfilled the office
engineer position for the owners construction manager.
Henry Ford Avenue Grade Separation, Alameda Corridor Transportation Authority, Long
Beach, CA ($88 million)
Project Engineer (CM), 2000 2002

Railroad grade separation at southern end of Alameda Corridor. Project features included cast-in
steel shell piles, subsurface stone and concrete columns, MSE walls, roadway and ramp construction,
waterline installation, 20-span precast box girder viaduct structure, precast I-girder bridge, structural
steel plate girder and truss bridges, and railroad construction. Mr. Revero fulfilled the project
engineer position for the owners construction manager.

Volume 2 Section 1 Construction Resumes page 28

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Kul Bhushan, GE

Geotechnical Engineer of Record


(GEOR) and Lead Geotechnical
Engineer

Profession
Geotechnical Engineer

Experience
40 years

Experience in Proposed Role


40 years

Career Summary
Dr. Bhushan is a registered Civil Engineer and
Geotechnical Engineer with over 39 years diverse
geotechnical experience, and is responsible for all
geotechnical work at GDC. Dr. Bhushan has personally
directed four design-build transportation projects, over
200 bridge and railroad crossing investigations, four
freeway improvement studies, six transportation corridor
section design studies, 30 soundwall and retaining wall
investigations, geotechnical recommendations for seismic
retrofit of 50 bridges, 50 probabilistic seismic hazard and
liquefaction studies, and a wide variety of other
geotechnical projects.
Dr. Bhushan directed the geotechnical investigation for
the seismic retrofit of the existing Gerald Desmond
Bridge. He has extensive experience working with Caltrans
7, 8, 11 and 12, RCTC, SANBAG and OCTA.
Relevant Project Experience
State Route 22 Design Build Improvements
OCTA/Caltrans/ Orange County ($490 million)
Senior Geotechnical Engineer, 2007 2010

Dr. Bhushans responsibilities included review of design


build contractors submittals, and QA/QC testing during
the construction. All work was performed under a formal
QA/QC program in accordance with ISO 9000.
Los Angeles to Pasadena Gold Line MTA/Los
Angeles, CA
Senior Geotechnical Engineer 2000

Licenses and Registrations

Registered Professional Engineer: CA


#C12345, #S1234
Registered Geotechnical Engineer: CA
#144

Education

Ph.D., Geotechnical Engineering, Duke


University, Durham, North Carolina, 1970
M.S., Highway Engineering Panjab
University, India, 1963
B.S., Civil Engineering; Panjab University,
India, 1962

RFP Criteria
More than 40 years experience in the design
of roadway on highway systems:
40 years
Experience in the last 10 years with the
design of roadways in major urban freeway
systems similar in scope and complexity:
SR-22 Design Build
SR-91 Design Build
SR-125 Design Build
SR-60
Licensed as a California Professional
Engineer by the time the Design-Build
Contract is executed:
Registered Geotechnical Engineer: CA
#144

Design-Build Experience

SR-22 Design Build


SR-91 Design Build
LA to Pasadena Gold Line
Gerald Desmond Bridge

Dr. Bhushan was responsible for all geotechnical work for Caltrans Experience
the deign-build team including 10 segments, 13 stations, 2 All above roadway projects were under
Caltrans oversight
seismic retrofit reports, two box structures, and one
pedestrian overcrossing. This work including underpinning
and monitoring of up to six story buildings, retaining walls, MSE walls, etc.
SR-91 Widening Design Build Improvements -RCTC/Riverside County, CA
Senior Geotechnical Engineer - 2000

Dr. Bhushan directed geotechnical work for SR-91 HOV lanes, retaining walls, and sound walls for
24-mile section from SR-57 to Magnolia Avenue in Riverside. The current project, which adds a
general purpose lane in each direction from County Line to Pierce Street, is within the eastern
portion of the original study directed by Dr. Bhushan. He directed foundation reports for four new
bridges and preliminary foundation reports for widening of 10 bridges along SR-91 to accommodate
HOV lanes.

Volume 2 Section 1 Design Resumes page 1

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Volume 2 Section 1 Design Resumes page 2

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Duanne Gilmore

Lead Civil Engineer


Career Summary

Profession
Civil Engineer

Experience
11 years

Duanne Gilmore is a civil engineer with extensive


experience in complex interdisciplinary projects. Duanne
has led multidisciplinary teams on various types of
projects, including highway interchanges, site development
and grading, master plans, stormwater schemes, flooding
analysis, and the design of sanitary sewer, potable water
and various dry utilities.

Experience in Proposed Role

Duanne is experienced with both the design-build


process and Caltrans procedures, having managed a
multidisciplinary design team as part of the $1 billion
Presidio Parkway project.

Caltrans Experience

9 years

Education

B.E., Civil Engineering; University Victoria


University, Australia; 2003

Design-Build Experience

Airport Link, Brisbane, Australia


Braided Ramps, Fresno CA
Presidio Parkway San Francisco, CA

Relevant Project Experience


Presidio Parkway, San Francisco County Transportation Authority, San Francisco, CA ($1.0
billion)
Technical Manager, 2008 Present

Technical Manager for Roadways, Utilities and Stormwater Drainage responsible for managing and
delivering detailed design and construction procurement documents for this $1 billion project. The
project entails a complete replacement of Doyle Drive, a 1.6-mile-long 6-lane highway carrying
100,000 vehicles per day from city streets through the Presidio of San Francisco National Park to
the Golden Gate Bridge. Significant portions of the work include highway design, elevated
structures, cut-and-cover structures and extensive landscaping.
Positioned alongside San Franciscos northern shoreline, the roadway faces several significant
challenges: the design team must preserve the natural beauty of a national park and its numerous
historic landmarks, while catering for high traffic flows. Under an earlier contract with the San
Francisco County Transportation Authority, Arup carried out extensive consultation with Caltrans,
the Presidio Trust, the Golden Gate National Recreation Area and several other agencies and public
representative groups to reach consensus on the scheme to be taken forward. A wide range of
stakeholders and agencies participate in this project including the FHWA, Caltrans, the National
Park Service (Presidio Trust and the Golden Gate National Recreation Area), the Golden Gate
Bridge Highway and Transportation District, as well as nearby residents and Citizen Action
Committees.
Airport Link, Brisbane, Australia ($5 billion)
Lead Civil Design Engineer, 2008 2009

Lead Design Engineer for the East-West Arterial Bypass of the largest road infrastructure project in
Australia ($5 billion). Designer of the flooding analysis and the utility relocations for the site.
Designed the roadway geometry to ensure that the area did not flood and that it complied with local
standards, requiring constant coordination with the utility relocations in the area. Worked
collaboratively in this design-build project with the construction contractor to ensure that all designs
could be implemented.

Volume 2 Section 1 Design Resumes page 3

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Kuwait University City, Canadian Consortium of Architects, Kuwait


Lead Civil Engineer, 2006

Civil Design Manager for the highway design of 8.1-mile roadway network and interchanges. Led
the civil design team to establish various design controls, with focus on earthwork balance and
coordination of mass transit strategy, overall circulation and functionality of the site. The roadway
and interchanges were designed to AASHTO standards. The roadway geometry was tactfully graded
to compliment the intended architectural language of the site.
Delta Redevelopment Project, JFK International Airport, New York
Civil Engineer, 2010 2011

Civil Engineer for the development of Terminals 2, 3 and 4 for Delta Airlines, in conjunction with
the Arup/SOM design joint venture. Landside project scope includes planning and design of
approach roadways, curbs, pedestrian routing and parking. The design will be progressed through
schematics to 30% design development and includes planning and simulation, highways, elevated
structures, drainage, utility and geotechnical disciplines. Construction phasing planning will allow for
continuous operation of the existing facilities while delivering the proposed infrastructure.
Deer Park Bypass, Melbourne, Australia ($34 million)
Role, 2005 2006

Project Engineer for the design of 5.8-mile, $34 million grade-separated full-diamond interchange.

Volume 2 Section 1 Design Resumes page 4

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Thomas Myers, AIA, LEED AP


Maintenance Lead Designer
Career Summary

Profession
Principal, Commercial Architecture

Experience
30 years

A licensed architect in the State of California and a LEED Licenses and Registrations
Licensed Architect, State of California
Accredited Professional, Tom has over 30 years of
Education
experience in architecture, planning and design. As
Principal, Commercial Architecture, Tom oversees the
University of Hawaii at Manoa, School of
Architecture Bachelor of Architecture
Commercial/Public Architecture Department, as well as
our specialized retail team in our Irvine Corporate Office.
His responsibilities include client development, staff management and overseeing project
management. Tom is a member of the American Institute of Architects (AIA), International
Council of Shopping Centers (ICSC), and the Society of Office and Industrial Realtors (SIOR)
Inland Empire/Orange County chapter. Tom's expertise includes retail, restaurant, hospitality,
commercial office, industrial, manufacturing and distribution projects.
Relevant Project Experience

Norm Reeves Honda Superstore - West Covina, CA

New two-story 56,360 SF Honda Dealership Image Program on a 7 acre site. The building
consisted of showroom and support offices, parts storage, service facility for 28 bays, 4 express
service lanes and 6 wash and detail bays.
Allen Cadillac - Laguna Niguel, CA

Architectural services provided for the implementation of GM Branding upgrades to Cadillac and
GMC dealerships.
Coastal Coachworks - Santa Ana, CA

Architectural and interior design services for the building renovation of the new 44,000 SF corporate
headquarters and factory for a stretch limousine manufacturing company. The project consisted of
a 40,000 SF factory floor which included an assembly line to convert standard luxury automobiles
and SUVs into stretched limousines. The plant included disassembly areas, frame cutting and
welding operations, metal body panel fabricating machines and assembly, bodywork, spray paint
booth, wood shop, upholstery installation, interior fit and finish, and final trim and detailing
functions. The remaining 4,000 SF consisted of corporate office space.
9to5 Seating - Hawthorne, CA

Architectural, interior design, civil engineering and graphic design services for a 100,000 SF, twostory build-to-suit corporate headquarters facility including distribution, manufacturing, office, and
showroom space. The state-of-the-art warehouse space includes racking and conveyor systems, and
features modern manufacturing processes and equipment. The project is currently pursuing LEED
NC Gold Certification and has received a certificate of recognition for the 2011 SEED Awards by
the South Bay Business Environmental Coalition for environmental excellence.
LESTA Large Battery Storage - Westminster, CA

Architectural and civil engineering services for the construction of an enclosed large battery storage
facility. Layout and design consisted of a structural concrete slab, structural supports for
prefabricated battery storage containers with interconnecting skid platforms, stormwater quality
devices, and lighting layout.

Volume 2 Section 1 Design Resumes page 5

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

R+L Carrier - Anaheim, CA

Architectural services for a 9,100 SF addition to an existing warehouse and office building. The total
proposed building area will be 17,500 SF.
1600 E. Orangethorpe Renovation - Fullerton, CA

Architectural and design services provided for improving the exteriors and interiors of an existing
warehouse building. Improvements include addition of mezzanine with offices, new exterior facade
at new offices, minor revisions to site.
FreshPoint - City of Industry, CA

Renovation, addition and site planning for an existing industrial facility totaling 162,661 SF on a 12.6
acre site. The project includes cold storage, warehouse, office mezzanine, and a breakroom.
FreshPoint is the largest fresh produce distributor in North America.

Volume 2 Section 1 Design Resumes page 6

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Michael Painter, FASLA


Visual Quality Manager
Career Summary

Landscape Architecture

Experience
46 years

Michael Painter is founder, owner, and President of MPA


Design. He is known for his forward-looking design
sensibility, his keen interest in sustainability, and decades
of experience in California, all of which enhance the work
of the firm. Mike was the visionary for the Presidio
Parkway Design, which he conceived over 25 years ago.
The original vision persevered through successful
guidelines and master plans, and is under construction true
to course. Mike specializes in formulating the big idea, the
initial design, and continues to contribute to projects
through their duration.
Michael will work with the team to ensure a strong
initial vision, and to oversee the project as it develops
for continuing input, direction, and quality control.

Relevant Project Experience


Presidio Parkway, Caltrans, San Francisco, CA ($1
billion)
Role, 1988 Present

Profession

Experience in Proposed Role


42 years

Licenses and Registrations

California Landscape Architect License


No. 971

Education

Master of Landscape Architecture, Urban


Design, Harvard Graduate School of
Design, 1966
Bachelor of Sciences, Landscape
Architecture, University of California,
Berkeley, 1956

RFP Criteria
Shall be a California-licensed architect,
landscape architect or engineer with no less
than 10 years of experience in leading the
visual quality aspects of bridge architecture
and landscape architecture design in major
transportation projects:
California Landscape Architect License
No. 971
44 years
Shall be certified by the Department (or
similar training program sanctioned by
AASHTO, FHWA, or another state DOT) as
having completed a minimum of eight
Professional Development Hours in Context
Sensitive Solutions/Design or proof of
equitable experience in transportation
projects where Context Sensitive Solutions
principles were implemented:
Green Street Bridge, Waterfront Square,
17 Mile Drive, Great Hwy.
Shall have a minimum of 10 years of recent
experience in conducting a visual quality
public planning process, producing a visual
quality manual, and providing technical
assistance in implementing visual quality
requirements during design and
construction:
42 years
Presidio Parkway, I-80 Aesthetic
Treatment, I-80 Berkeley Bridge
Overcrossing

Presidio Parkway is the primary transit link from San


Francisco to the north along Highway 101. The project
area extends from the Golden Gate Bridge Toll Plaza to
the Palace of Fine Arts. It is located within the Presidio
and connects to Highway 1.
Michael Painter re-envisioned the site with the freeway as
part of a connected, accessible, green parkway. MPA
Design formed a partnership with ARUP. Our vision was
soon adopted as the Preferred Alternative.
The Parkway Vision includes separating north and south
bound lanes with a median, redesign of the High Viaduct
Bridge to be structurally sound yet transparent, and
placing the roadway underground in two separate tunnels
that emerge into the second bridge structure.
Michael was involved in the aesthetic visioning of the
structural features including bridges, tunnels, portals, walls,
and abutments. The bridge features a modern orange fin
as structural support that relates to the Golden Gate Bridge. The tunnels are primarily naturally
ventilated, minimally lighted, and short enough for drivers to see the end. The portals are angled so
they emerge from existing slopes and provide a seamless transition from tunnel to roadway.
Similarly, walls are sited so they are not visible from the park and reduce vehicular noise. The
abutments demonstrate a modern interpretation of patterns seen in the historical battery structures.
In an effort to activate all parts of the sight we proposed using the space at the abutments and under

Volume 2 Section 1 Design Resumes page 7

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

the ramps in creative ways, such as dog parks or recreational courts, which allow these often
forgotten spaces to be utilized rain or shine. We also proposed functional uses for under the ramps,
such as parking, water runoff treatment, and marsh expansion. Other functional elements such as
lighting and fencing are integrated into the structural features as part of a comprehensive design.
It took years of thoughtful design to align the roadway in a way that perfectly enhances the adjacent
facilities. Our team worked closely with various interest groups and consultants to consider views,
historic features and buildings, existing trees, auxiliary streets, roads and infrastructure. We
redesigned adjacent auxiliary roads and streetscapes to their original historical alignments, current
design standards, and evolving park needs. As part of the highway vision, we designed a series of
trails that provide frequent connections to park features, the city fabric, and future plans. All new
features are designed to retain important features such as the military batteries and historically
registered buildings. The design carefully transitions from the urban and formal Main Post design
and Veterans Cemetery to the naturalistic recreation area of Crissy Field. The project ends with a
delicate transition where it becomes part of the urban fabric and enters the city.
As the vision for the Presidio Parkway emerged, our team carefully documented it to ensure it
remained true in the built work. Together we created Architectural Criteria, Basis of Design, multiple
guidelines and graphics to guide the end result. These documents define elements including
restoration of historical buildings and features, preserving and reinforcing the values of the Presidio,
and activating space that had previously been used only as vehicular infrastructure. These clear
guidelines, in connection with concise graphics, defined goals and physical models, have resulted in
bringing a unique vision to fruition.
I-80 Aesthetic Treatment, Solano Transportation Authority, Fairfield and Solano County, CA
($2 billion)
Role, 2009 Present

This ongoing project is a reconfiguration of freeway connections between I-80, I-680, and SP-12,
which includes the addition of new ramps and bridge structures. Mikes role is to create aesthetic
wall and structure finishes that reflect the nature and character of the surrounding area. The modules
are to be applied on tall, short, narrow, and wide structures. Aesthetic Treatment Guidelines and
implementation oversight are our deliverables. Team collaboration includes Solano Transportation
Authority (STA), Caltrans, and City of Fairfield.
I-80 Berkeley Bridge Overcrossing, Caltrans, Berkeley, CA ($400 million)
Role, 1998 2004

MPA Design and other dedicated professionals were asked to envision a pedestrian and cycling
bridge to connect the city of Berkeley to the Bay where I-80 created a barrier between the two.
Through a collaborative effort, an attractive structure emerged which spanned over the highway at a
logical point to provide the most practical access. While working on the design Mike realized that
the bridge could be angled slightly so that it was not perpendicular to the road, but instead on axis
with the Golden Gate Bridge. The change was approved and the bridge realigned to capture the
picturesque view over the bay.

Volume 2 Section 1 Design Resumes page 8

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Matt Carter

Deputy Cable Stayed Bridge Lead


Designer

Profession
Civil Engineer

Experience
15 years

Experience in Proposed Role

Career Summary
Matt Carter is an Associate Director in the Hong Kong
Civil Group. He has extensive experience of the
conceptual and detailed design of bridge structures in
Europe, North America, East Asia, Africa and Australia.
Matt has specialized in long span cable stayed bridges with
notable career highlights including the Forth Replacement
Crossing in Scotland, Incheon Bridge in Korea and
Stonecutters Bridge in Hong Kong which are three of the
longest spanning cable stayed bridges in the world.
Through his work on major bridge projects, Matt has
gained important experience in the seismic design of
bridges and ship collision risk.
With a reputation for technical innovation and
excellence, Matt has experience in leading the design of
world class cable stayed bridges.

8 years

Licenses and Registrations

Chartered Engineer (registered with the


Engineering Council UK)
Member, Institution of Civil Engineers,
UK
Member, Hong Kong Institution of
Engineers

Education

B.S., Civil Engineering; University Name,


Location; 1999

Design-Build Experience

A30 Highway, Montreal, Canada


Forth Replacement Crossing, Scotland
Incheon Bridge, South Korea
Macintosh Island Bridge, Australia

Caltrans Experience
Gerald Desmond Bridge Replacement
Tender Design

Relevant Project Experience


Forth Replacement Crossing, Transport Scotland, UK ($2.6 million)
Cable Stay Bridge, Deputy Lead Designer, 2008 2010

Arup are the clients engineer for this unique cable stayed bridge currently under construction in
Scotland with back to back main spans of 2,130 ft. Working with bridge architects Dissing +
Weitling, Matt developed the conceptual design proposals for the project which enabled substantial
cost savings to be made in the substructure by adopting a world first crossing stay cable technology.
He then went on to lead the structural scheme design of one of the Specimen Design options.
Incheon Bridge, Incheon Bridge Co.Ltd., Songdo, South Korea ($1.4 million)
Cable Stay Bridge Independent Check Lead Engineer, 2005 2007

Matt was the lead engineer for the independent check of the cable stayed navigation bridge with a
2,624-foot main span which was designed to AASHTO LRFD and the PTI Recommendations for
Stay Cable Design, Testing and Installation. The scope included an independent seismic hazard
assessment as well as multi-modal response spectrum analysis of the bridge.
Stonecutters Bridge, Highways Department of Hong Kong Special Administrative Region,
Hong Kong ($450 million)
Cable Stay Bridge Senior Engineer, 2002 2009

During the detailed design of this 3,340-foot main span cable stayed bridge, Matt was the lead
engineer responsible for the detailed design of the main girders of the steel superstructure. He also
prepared the conceptual design and performance specification of the access and maintenance
facilities throughout the bridge.
Matt continued to provide head office support to the site supervision team throughout the
construction.

Volume 2 Section 1 Design Resumes page 9

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Izmit Bay Suspension Bridge, NOMAYG, Izmit Bay, Turkey ($1.2 million)
Project Manager, 2010 2011

Matt was the Project Manager and Design Manager for the tender design of this 5,085-foot main
span suspension bridge to be built adjacent to the North Anatolian Fault in one of the most seismic
regions of the world. As well as coordinating the design input of all disciplines Matt devised a unique
anti-seismic design concept for the anchorages which led to significant cost and schedule savings.
Second Penang Bridge, Jambatan Kedua Sdn Bhd, Penang, Malaysia ($1.3 million)
Project Manager, 2009 2010

Matt was the Project Manager for the independent check of this 9.3-mile sea crossing which is
currently under construction with typical 180-foot-span precast segmental viaducts and
incorporating a 790-foot main span concrete deck cable stayed bridge.
Macintosh Island Bridge, Gold Coast City Council, Surfers Paradise, Australia ($5 million)
Cable Stay Bridge Lead Engineer, 2007

This award winning cable stayed footbridge on the Gold Coast of Australia was designed and built
in a little over six months. With the very fast construction schedule being a critical part of the design
process, Matt worked very closely with the D&B contractor to deliver a successful design.
Tappan Zee Bridge, New York State Thruway Authority, New York, NY
Project Engineer, 2010 2011

Arup are currently preparing tender documentation and Reference Information Design proposals
for the Tappan Zee Bridge project. Matt has been responsible for supervising the design
development of the long span approach bridge option with 430-foot typical spans as well as the arch
option for the main navigation span of 1,150 ft.
A30, Nouvelle Autoroute 30, Montreal, Canada (1.5 billion)
Beauharnois Canal Bridge Lead Designer, 2007 Present

The A30 project involves the design and construction of over 24.8 miles of new highway close to
Montreal on a PPP basis. Matt is the Lead Designer for the detailed design of the Beauharnois Canal
Bridge, a 4,500-foot-long continuous steel-concrete composite structure which is currently being
installed by push launching to overcome seasonal and operational construction constraints. The
bridge includes a temporary stay cable system to assist with the launch across the 490 foot main
span.
Center Street Bridge, River Front Development Authority, Des Moines, IA
Independent Check Lead Engineer, 2006 2007

The Principal Riverwalk is the realization of the River Front Development Authoritys mission to
transform the banks of the Des Moines River into a downtown amenity. The Center Street Bridge is
the northern river crossing of a loop trail that passes new and refurbished civic buildings, an
amphitheatre, plazas, and an outdoor skating rink. Visible from Iowas State Capital Building and
much of Des Moines Downtown, the Center Street Bridge provides both an intriguing route and a
unique destination for pedestrians and bicyclists. With the Center Street Dam just below the deck,
the unobstructed views of the City, and the outdoor room created by the structural system, users
and visitors enjoy a multi-faceted experience throughout their journey. Matt was the lead engineer
for the independent design check of a 425-foot-span arch pedestrian bridge designed by Arups San
Francisco office.

Volume 2 Section 1 Design Resumes page 10

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Robert Meyer

Superstructure Lead
Career Summary

Profession
Bridge Engineer

Experience
10 years

Robert Meyer is a bridge engineer with 10 years experience


in the design and analysis of complex bridge structures in
various countries.
He is involved in a variety of projects in steel, concrete
and steel-composite construction.
Robert has gained significant skills in the analysis and
design of long-span cable supported bridges as well as
integral bridges and footbridges from concept to detailed
design stage.

Experience in Proposed Role


3 years

Licenses and Registrations

Chartered Engineer, Member Institution


of Civil Engineers

Education

Dipl.-Ing. (TU), University of Technology


Dresden, Germany, 19952001

Design-Build Experience
Chartist Bridge, UK
Botlek Lifting Bridge, Netherlands

Robert Meyer has broad knowledge and experience in


the analysis and design of complex long-span bridge structures in steel and composite
construction.

Relevant Project Experience


Forth Replacement Crossing, Scotland, UK
Design Engineer, 2008 Present

Option selection, comparative design studies and scheme design for 1.6-mile-long cable-stayed
bridge with two main spans of 2,132-foot length and three pylons across the Firth of Forth. Global
analysis and specimen design for selected option with central towers and orthotropic/composite box
girder decks. Review of submissions by D&B contractor.
Tappan Zee Bridge, New York, USA

Design Engineer Cable Stayed Bridge, 2011 Present

Scheme design for cable-stayed highway bridge across the Hudson River with main span of 1,200ft.
Global analysis and design of composite deck and concrete towers. Design team leader.
Chartist Bridge, Wales, UK

Design Engineer, 2003 2005

Detailed design of 754-foot-long cable-stayed bridge crossing a valley in South Wales with central
A-tower and composite ladder beam deck for D&B contractor. Global analysis including
construction stages and design of composite deck and stay anchor box. Construction support for
contractor and steelwork fabricator.
Botlek Lifting Bridge, Rotterdam, Netherlands
Design Engineer, 2009 2010

Option selection and tender design for 574-foot-wide and 295-foot-long lifting bridge for rail, road
and pedestrian traffic. Analysis and design of steel superstructure (truss and box girder with
orthotropic deck plates).
Stratford City Bridges, London, UK

Design Engineer, Project Manager, 2006 2008

Option selection, scheme and detailed design of two footbridges, assessment of two existing integral

Volume 2 Section 1 Design Resumes page 11

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

bridges. Project manager for detailed design of 295-foot-span tied-arch bridge with single steel arch
and composite box girder deck.
A25 Prairies River Bridge, Montreal, Canada
Design Engineer, 2006

Scheme and tender design of 934-foot-span river bridge (tied arch and cable stayed options) and
2,642-foot push-launched approaches. Analysis and design of bridge structure with composite deck.
3rd Namchang Bridge, Korea
Design Engineer, 2005

Scheme and tender design for 492-foot-span tied-arch bridge with diagonal space truss arch made
from tubular steel elements and composite ladder beam deck. Scheme optimization and global
analysis including construction sequence.
Cowfold Bridge, North England, UK
Design Engineer, 2005

Assessment and design of repair works for a damaged composite bridge over the A1. Analysis,
development of repair methodology and temporary works design.

Volume 2 Section 1 Design Resumes page 12

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ngai Yeung

Profession

Lead Analyst

Bridge Engineer

Experience

Career Summary

16 years

Experience in Proposed Role


Dr. Ngai Yeung is an experienced bridge designer with
10 years
special skills in numerical analysis and aerodynamics. His
experience in this field dated back to his research including Licenses and Registrations
both the wind tunnel testing and numerical analysis of the
Chartered Engineer: Reg. No. 553241,
Engineering Council UK
dynamic response of structures. His practical design and
analysis experience started with the 1,975-foot main span
Education
Yangpu Bridge in China, the longest span cable stayed
PhD, The University of Hong Kong; 1999
bridge in the world when completed in 1993.
MPhil, Shanghai Jiao Tong University;
1993
In Hong Kong he involved in the bridge design work of
BE, Shanghai Jiao Tong University; 1990
Route 8 and Stonecutters cable-stayed bridge and a
Design-Build Experience
number of bridge tender designs and cable-supported
Izmit Bay Bridge
bridge design checks. He has spent periods overseas in
Forth Replacement Crossing
UK and Denmark, working on the computer simulation of
Incheon Bridge
vehicle impact on bridge parapets and optimisation of
complicated steel joints for CCTV Tower in Beijing.
He has also spent time in China, collaborating on cable-stayed bridge design, investment and cost
estimate of large bridge projects, and wind tunnel study of rain/wind-induced vibrations in stay
cables, and acted as a Committee Member in Chinas Wind Engineering Society.

With his strong background in numerical analysis and bridge design, Ngai is leading the
numerical analysis of all types of bridges, especially the dynamic wind and seismic analysis of
cable-stayed and suspension bridges.

Relevant Project Experience


Stonecutters Bridge, Highways Department of Hong Kong Special Administrative Region,
Hong Kong ($450 million)
Design Engineer, 2002 2004
Resident Chief Technical Officer, 2004 2009

Ngai works as design engineer and analyst for the structural analysis and detailed design of the
Stonecutters Bridgea 3,339-foot main span cable-stayed bridge. He is responsible for modeling
the whole bridge using TDV2000 and conducting the static, modal, and dynamic analysis for design
purposes. The stage-by-stage construction has also been modeled and analyzed in detail. He is
familiar with the geometry and behavior of all structural components, steel and concrete decks,
concrete piers and composite tower, and foundations.
During the design process he travelled to Denmark to finalize the dynamic wind buffeting analysis
and witness the wind tunnel test of the section model. He also went to China to inspect the drag
coefficient tests and rain/wind vibration tests of stay cables with different surface configurations.
Ngai works as the Resident Chief Technical Officer for supervision of the construction works of the
3,339-foot main span bridge, handling the key technical issues such as construction stage wind
tunnel testing and geometry control and appraise the Contractors technical submissions.

Volume 2 Section 1 Design Resumes page 13

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Izmit Bay Suspension Bridge, Government of Turkey, Turkey ($1 billion)


Project Coordinator, 2010 2011

Ngai is the project coordinator for joint bidding of the Izmit Bay Bridge with Chinese partners. It is
a 5,084-foot main span suspension bridge in the high-seismic area of Turkey. This is a D&B project
involving two contractors in mainland China and a design institute in China forming a design JV
with Arup. Ngai is responsible for liaising with all parties to sort out the technical issues and
commercial issues for a quality delivery of the bidding submission, as well as developing the scheme
with UK and HK engineers.
Long Span Bridge Research, GS Engineering & Construction Corp., Korea ($0.5 million)
Deputy Project Manager, 2009 2011

Ngai is the deputy project manager and lead engineer for the 4,590- to 5,900-foot main span selfanchored cable-stayed bridge and the 4,590- to 5,900-foot main span partially earth-anchored cablestayed bridge, a joint project with Korean construction company targeting the longest span cablestayed bridge following the construction of Sutong Bridge in Mainland China and the Stonecutters
Bridge in Hong Kong. The design is based on Korean code and an optimized specimen design was
produced to AASHTO LRFD.
Hong Kong Zhuhai Macau Bridge, Highways Department, Hong Kong Government, China ($5
billion)
Project Coordinator, 2009 2011

Ngai provides technical support to the durability design and dynamic analysis of the project during
preliminary design stage. He also acted as an expert reviewer in the professional panel to assess the
parapet design and impact test for the project. He is the project coordinator for joint bidding of the
detailed design of this project with Chinese partner. He is responsible for finalizing the commercial
and technical submissions, involving in the development of the optimization scheme of the cable
stayed bridge and approaching viaducts, and coordinating the drawing and reporting with all related
parties.
Hwayang Jeokgeum Road Project, GS Engineering & Construction Corp., Korea ($0.1 million)
Design Engineer, 2010 2011

Ngai is the design engineer helping the Korean contractor to prepare a conceptual design for the
Hwayang Jeokgeum Road Project. The proposed the 2,460-foot main span bridge is an innovative
type of fully earth anchored cable stayed bridge which is a cost effective solution to suit the site
condition.
Forth Road Bridge Viaduct Bearing Replacement Project, Forth Estuary Transport Authority,
Scotland ($27 million design)
Design Engineer, 2008 2011

The Forth Replacement Crossing is a major infrastructure project for Scotland, designed to
safeguard a vital connection in the countrys transport network. Ngai is the design engineer for the
wind buffeting analysis and issues related to the wind tunnel for the cable-stayed bridge of the
project.
Incheon Bridge, The Incheon Bridge Co. Ltd., Songdo, Korea ($1.4 billion)
Design Checking Engineer, 2005 2007

Arup formed a joint venture to complete the Contractors Checking Engineer services for this 7.5mile sea crossing which is a fast-track design-build project with a value of US$1.4 billion. The design
is to AASHTO LRFD. Ngai is responsible for the dynamic analysis of the 2,624-foot main span
cable-stayed bridge. The global response of the whole bridge under wind buffeting was analyzed
using TDV2000 based on the wind tunnel test results of the bridge deck section model.

Volume 2 Section 1 Design Resumes page 14

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Sammy Yip

Substructure Lead
Career Summary

Profession
Bridge Engineer

Experience
8 years

Sammy is a Chartered Civil Engineer with over 8 years


experience of analysis, design and checking work for
various bridge projects around the world. He is
experienced with various design standards such as British
Standards, Eurocodes and AASHTO LRFD.
Sammy has worked on a wide range of structures,
including concrete viaducts and cable-stayed bridges. In
particular, he is experienced in the design of structures
where seismic loading and aerodynamics are the key design
considerations.
Sammy has been leading the analysis and design of
major bridges around the world.

Experience in Proposed Role


5 years

Licenses and Registrations

Chartered Engineer (CEng)


Corporate Member of Institution of Civil
Engineers (MICE)

Education

MEng., Civil Engineering; Imperial


College London, UK; 2004

Design-Build Experience

Penang Second Bridge, Malaysia


Forth Replacement Crossing, U.K.
Dubai Metro, UAE
Incheon Bridge, Korea

Relevant Project Experience


Second Penang Bridge, Jambatan Kedua Sdn Bhd, Malaysia ($1.3 million)
Checking Team Leader, 2009 2010

The Second Penang Bridge is a US$ 1.3B project to build a 9.3-mile sea crossing between peninsular
Malaysia and Penang Island. The bridge mainly comprises 180-foot-span precast viaducts with a
navigation channel provided by a 787-foot-span concrete cable stayed bridge.
Sammy led a team of engineers in the independent checking of the 9.9-mile-long precast segmental
concrete viaduct substructure and both superstructure and substructure of the 787-foot main span
cable-stayed bridge. Seismic design was a critical issue for the viaduct substructure and seismic
isolation was adopted to achieve an economical structure. Sammys role also included a review of the
design brief, ship impact, aerodynamics and seismic design of the structure.
Forth Replacement Crossing, Transport Scotland, UK ($2.6 million)
Substructure Lead, 2008 2010

The Jacobs-Arup joint venture has been commissioned for the management and delivery of the
project inclusive of all roads and other infrastructure with Arup being the lead partner for the Main
Crossing across the Firth of Forth. The new crossing involves a 1.7-mile cable-stayed bridge with a
pair of back to back 2,132-foot main spans together with associated highway infrastructure and
intelligent transport systems on a design and build basis. This elegant, unique bridge incorporates a
world first crossing stay cable system. It will also become the worlds longest steel-concrete
composite span and the worlds longest torsion span. This triple world record was achieved by a
rigorous assessment by the Arup team responsible for the Main Crossing and has been validated by
the conforming design and builds tenders submitted within our cost estimates.
Sammy was the substructure lead in the Hong Kong office. One of his key responsibilities is the
analysis of substructure. In particular, ship impact risk assessment and wind buffeting analysis were
also carried out for the 2,132-foot back-to-back main spans. Sammy coordinated the necessary
inputs required for the wind buffeting analysis from wind experts, wind tunnel testing and also
carried out the structural analysis in specialist structural analysis package TDV RM2006 Spaceframe.

Volume 2 Section 1 Design Resumes page 15

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Dubai Metro (Red and Green Line) Viaduct detailed design, Dubai Roads and Transport
Authority, Dubai, UAE ($7.6 million)
Substructure Lead, 2007 2008

The Dubai Metro is a driverless, fully automated metro network in Dubai. Sammy was involved in
the design of the viaduct structure for the Red Line and Green Line (total 43 miles) which are
currently in operation. The concrete viaducts have typical span lengths of 65.6144 feet long and are
designed for typical loadings as well as extreme event loading such as seismic load. The
substructures are governed by seismic loading and economical design was achieved by the use of
ductile design of columns.
Sammy was a team leader in the substructure design. He also liaised with the independent checker to
facilitate the approval. The programme of this design and build contract was originally delayed due
to various difficulties. With the newly appointed design consultant (Sammys previous employer), the
project was back to schedule.
Incheon Bridge, The Incheon Bridge Co. Ltd., Songdo, Korea ($1.4 billion)
Substructure Design Checker, 2005 2007

The bridge was constructed on a BOT basis by KODA, the AMEC led Concessionaire Company.
The major part of the bridge is constructed as 50m span low level viaducts over tidal mud flats and
shallow water. Balanced cantilever approach bridges with 145m spans rise up to meet the cable
stayed navigation span. The 2,624-foot-span cable stayed bridge is constructed in 66 feet of water
across the main navigation channel. The cable stayed bridge is designed to withstand buffeting by
typhoon strength winds and is provided with protection against impact from 100,000-ton ships.
Sammy was involved in the independent checking of the substructure of the approach bridges and
the cable-stayed bridge. The substructures are governed by seismic loading. The checking was
carried out on a fast-track programme and the checking was delivered on time successfully to
facilitate the construction programme.
Brunei-Muara to Temburong Fixed Link Feasibility Study, Department of Roads, Government
of Brunei, Brunei (est. ~$1.5 million)
Project Coordinator, 2010 Present

The fixed link is anticipated to involve 24.8 miles of new highway comprising 11.2 miles of sea
crossing (including two cable stay bridges, 10.6 miles of viaduct and at-grade road on embankment
on soft soils requiring ground improvement, and other connections to existing road network.
Sammy is the project coordinator for the feasibility study which requires multi-disciplinary inputs
and consideration of both technical, social, economic and political issues. He is also leading the
conceptual and preliminary design of the concrete viaduct and cable-stayed bridges. The viaducts
will be concrete box girders of 164-foot typical spans. The two cable-stayed bridges will have main
spans of 426 and 853 feet. The pylons have been designed architecturally to form a national
landmark for Brunei. The substructure design requires special consideration due to the very soft top
soil in Brunei Bay and the mangrove area in Temburong.
Forth Road Bridge Viaduct Bearing Replacement Project, Forth Estuary Transport Authority,
Scotland ($27 million design)
Design Team Leader, 2005 2007

The steel roller and rocker bearings of Forth Road Bridge approach viaducts had deteriorated
significantly over the years and had to be replaced. Similar to other older structures, the
superstructure was not designed for bearing replacement loading. As a result, a structural assessment
had to be done and a strengthening scheme was designed for the replacement works.
Sammy led a design team in the assessment and strengthening of the steel-concrete composite box
girder superstructure and concrete pier using Eurocodes.

Volume 2 Section 1 Design Resumes page 16

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ender Ozkan, PhD


Aerodynamics

Profession
Wind Engineer

Experience

Career Summary

13 years

Ender provides wind engineering expertise to clients


across the world on projects ranging from bridges to highrise buildings. He has wide experience in prototype and
wind tunnel testing, as well as response prediction
methods using analytical and computational techniques.
Ender joined Arup in 2003 after completing his PhD
degree at the Johns Hopkins University in Baltimore,
USA. During his studies Ender specialized in aerodynamic
and aeroelastic design of bridges, with emphasis on longspan bridges. Since joining Arup Ender has been project
manager and technical expert on wind studies for over 200
projects including high-rise buildings, long-span bridges,
stadia, telecommunication towers and sculptures.

Experience in Proposed Role


8 years

Licenses and Registrations

Chartered Engineer, Institution of


Mechanical Engineering, UK

Education

Ph.D., Civil Engineering; Johns Hopkins


University, Baltimore; 2003
B.S., Civil Engineering; METU, Turkey;
1998

Design-Build Experience
Beauharnois Bridge, Canada
Kurilpa Bridge, Australia

Ender is one of the leading aerodynamic experts in the


world, and has significant experience in all aspects of wind-resistant design.

Relevant Project Experience


Forth Replacement Crossing, Scottish Government, Edinburgh, UK ($1,200 million)
Aerodynamic Expert, 2008 Present

Ender has been the lead wind engineer during the specimen design stage of this major infrastructure
project. He managed extensive wind studies, including wind shielding tests, sectional aeroelastic tests
and full-bridge aeroelastic studies. These contributed to the understanding of bridge aerodynamics,
and the results have been presented in various conferences and journal papers. Depending on the
flexibility and aerodynamic characteristics of Gerald Desmond Bridge, similar wind tunnel tests are
likely to be required for confirming the design wind loads and optimizing the structural systems.
Fred Hartman Bridge, Texas DoT, Houston,TX
Full-Scale Monitoring, 1998 2003

Ender was part of a team that carried out a long-term full-scale monitoring programme on the Fred
Hartman Bridge in Texas. During this time Ender gained considerable experience in full-scale,
analytical and numerical aspects of wind-induced bridge response. In particular the large-amplitude
cable vibration problems observed at the time on this cable-stayed bridge provided an opportunity
for Ender to experience some of the aerodynamic challenges associated with such bridge types.
Damping systems were retrofitted on the Fred Hartman Bridge subsequent to this study to suppress
cable vibrations. The findings of this study have been published in international journals
Beauharnois Bridge, Transports Quebec, Quebec, Canada, CA
Aerodynamic Expert, 20010 2011

Ender provided wind engineering expertise to this design and build projects in Canada involving a
150m span cable-supported bridge across the Beauharnois Canal near Montreal. One of the
challenges associated with this bridge was the light-weight structural system used during
construction, which posed particular challenges during construction. Ender carried out expensive
wind tunnel tests for this twin-deck structure, using an advanced test setup which accounted for the

Volume 2 Section 1 Design Resumes page 17

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

full aerodynamic coupling between the two parallel decks. Aerodynamic control features designed by
Ender (e.g. winglets) were introduced into the design to ensure the aerodynamic stability of the
bridge during extreme storm events during construction. This project provided a reminder that in
some cases bridges can be more susceptible to wind effects during construction period. Wind effects
may delay the construction programme by creating excessive vibrations and discomfort for workers.
In extreme cases aeroelastic problems such as vortex shedding have been known to create significant
disruptions for bridge construction, and therefore aerodynamic evaluations are likely to be needed
for Gerald Desmond Bridge to avoid such issues form the onset.

Volume 2 Section 1 Design Resumes page 18

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Andy Thompson, PE, LEED AP


Lead ATVA/Blast Specialist
Career Summary

Profession
Risk Management

Experience
14 years

Andy Thompson leads Arups Advanced Technology +


Research practice in San Francisco and the Risk practice in
the Americas. As an expert in risk-based design, property
insurance, and business continuity, he has advised
corporations and governments throughout the world. His
work also includes supporting clients in post-disaster
situations, most recently following the Japan, Chile, and
Haiti earthquakes. He is author of the book Peace of Mind
in Earthquake Country, and a recipient of ConsultingSpecifying Engineers 2010 40-Under-40 Award.

Experience in Proposed Role

As an expert in risk-based design, property insurance,


and business continuity, Andy has advised corporations
and governments throughout the world.

RFP Criteria

Relevant Project Experience


Transbay Transit CenterExtreme Event Consulting
and Design, Transbay Joint Powers Authority, San
Francisco, CA ($1.5 billion)
Project Manager, 2008 Present

Project Manager for blast engineering and progressive


collapse analysis for a major $1.5B transportation hub in
San Francisco, including blast protection systems.
Pocahontas Parkway, Multi-hazard Risk and Valuation
Assessment, Transurban, Richmond, VA
Project Manager and Lead Consultant, 2008

Project Manager and Lead Consultant for a multi-hazard


risk assessment (including wind, flood, earthquake, and
terrorism) for a major toll roadway system for the greater
Richmond VA area. Probable Maximum Loss estimates
were generated.

11 years

Licenses and Registrations

Registered Professional Engineer: CA


#C65777

Education

Master of Engineering, University of


California, Berkeley (Emphasis:
Earthquake Engineering)
Bachelor of Science, Civil Engineering,
University of Colorado at Boulder

Experience completing blast evaluations and


design of blast protection systems on at least
three structures - experience on buildings
can be used
Dubai Towers
Transbay Transit Center
Federal Reserve Bank of New York
Scottish Parliament
Seattle Center
Fisher Brothers
Meet Requirements of Exhibit 2-13-F
Yes
Possession of a valid Transportation Worker
Identification Credential (TWIC) card, or can
pass the Owner's security clearance
requirements
Yes
Agreement to confidentiality protocol
Yes

Design-Build Experience
Transbay Transit Center

Caltrans Experience
Doyle Drive

California High Speed Train, California High-Speed


Rail Authority, Fresno to Palmdale, California (14.9 billion)
Risk Manager, 2009 to Present

Risk Manager for the Fresno to Palmdale section. Risk Register and Project Risk Management Plan
development and implementation. Lead coordinator for the Risk Register workshops.
Dubai TowersBlast Engineering and Analysis, Dubai
Project Manager, 2008

Project Manager for blast engineering and analysis services for several of the tallest buildings in the
world.

Volume 2 Section 1 Design Resumes page 19

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Federal Reserve Bank of New YorkBomb Blast Risk Assessment, New York, NY N/A
Consultant 2006

Bomb blast safety study, risk assessment, and mitigation options analysis.
South Ferry Transit CenterTerrorism Threat and Risk Assessment, New York, NY
Consultant 2006

Performed a semi-quantitative risk assessment for this major transportation hub. Studies included
critical asset identification, threat scenario identification, vulnerability assessment, risk assessment,
and mitigations options analyses.
Scottish Parliament BuildingBlast Consultancy, UK
Consultant 2000

Blast consultancy for the new parliamentary building for Scotland. Faade design assessment.
Structural design of blast mitigation enhancements. Conducted physical test trials.
Seattle CenterBomb Blast Safety Studies, Seattle Center, Seattle, WA
Project Manager and Lead Consultant, 2005

Project Manager and Lead Consultant for bomb blast safety studies and mitigations options analyses
for three major public venues in Seattle.
Fisher BrothersSecurity Risk Assessment; Bomb Blast Safety Study, Fisher Brothers, New
York, NY
Consultant 2002

Bomb blast threat and risk study for a 44 story building in New York, including threat
determination, blast-wave generation and damage prediction to structure and faade.
Multi-purpose Disaster-Room and Layered Security Design, Confidential Client, Japan
Consultant 2003

Multi-layered security design for a confidential disaster-protection unit able to withstand targeted
criminal attack, building collapse, chem/bio attack, and bomb blast.

Volume 2 Section 1 Design Resumes page 20

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Martin Bodemar, SE, PE

Approach Superstructure Lead


Career Summary

Profession
Structural Engineer/Project Manager

Experience
17+ years

Martin Bodemar has been employed with Biggs Cardosa


Associates for over 12 years. He has over 17 years of
design and managerial experience and has led design teams
for numerous complex transportation projects throughout
the United States, with special emphasis on projects in
California. His experience as Project Manager also includes
close coordination with clients, subconsultants,
contractors, and numerous agencies such as Caltrans,
cities, counties, utilities, railroads, permitting agencies, and
water districts during both design and construction phases
of projects.
Mr. Bodemar has been involved in several types of
transportation projects, including new construction,
widening, rehabilitation, replacement and seismic
retrofit for transit, railroad, highway/roadway, and
pedestrian bridges. He has also been involved in the
design of other structures such as tunnels, retaining walls

Experience in Proposed Role


7 years

Licenses and Registrations

Registered Professional Engineer: CA


#C57856, #S4869; CO #35894

Education

B.S., Civil Engineering; Santa Clara


University; Santa Clara, CA 1994

Design-Build Experience
San Francisco Bay Area Rapid Transit
(BART) Warm Springs Extension

Caltrans Experience

Southbound Route 87 Connector


101-85/S 101 HOV Connector
Jack Tone Road/SR-99 Interchange
Caltrans Seismic Retrofit Programs

and soundwall structures.

Relevant Project Experience


Caltrans Seismic Retrofit Contract No 59X850, Caltrans, Various Locations, CA ($32 million)
Structures Designer, 1994 1995

Mr. Bodemar was a Structures Designer for this project that included the seismic retrofit of over
twenty structures that were identified as vulnerable to earthquake damage. The retrofit of these
structures was part of Caltrans Phase I and Phase II Seismic Retrofit Programs.
Jack Tone Road/SR-99 Interchange, Caltrans, Ripon, CA ($30 million)
Structures Designer, 1995 1996

Mr. Bodemar performed preliminary bridge design for this interchange project that included four
bridge structures, including an overhead structure over UPRR and two overcrossings of SR-99.
Sanborn Road Overhead, Caltrans, Salinas, CA ($2.7 million)
Structures Engineer, 1997 2000

Mr. Bodemar was the Structures Engineer for the seismic retrofit and barrier replacement of two
separate 850-foot-long bridges. The 20-span east bridge superstructure consists of a cast-in-place
reinforced concrete T-beam with precast prestressed concrete girders and composite concrete deck
spans over the railroad tracks. The 21-span west bridge superstructure consists of steel girders with a
cast-in-place concrete deck.
Southbound Route 87 Connector, Caltrans, San Jose, CA ($40.5 million)
Structures Engineer, 1999 2001

Mr. Bodemar was a Structures Engineer for the seismic retrofit design of a 2229-foot-long, 13-span,
cast-in-place prestressed box girder bridge. This project included the addition of a 1100-foot-long,
six-span, cast-in-place prestressed box girder bridge to an existing hinge stub.

Volume 2 Section 1 Design Resumes page 21

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

101-85/S101 HOV Connector Separation, Caltrans, San Jose, CA ($40.5 million)


Quality Control Engineer, 2001

Mr. Bodemar was the Quality Control Engineer for a four-span, 636-foot-long prestressed box
girder bridge with an outrigger (straddle) bent.
Four Bears Bridge, North Dakota DOT, New Town, ND ($50 million)
Structures Engineer, 2002 2005

Mr. Bodemar performed the final bridge design for this 4500-foot-long precast segmental box girder
bridge. This balanced cantilever bridge features 316-foot typical spans and spans across Lake
Sakakawea. The substructure design featured two foundation options (drilled shaft and steel pipe
pile) to improve the competition during the bidding phase of the project. A drilled shaft and steel
pipe pile option were produced in the final plans. Additionally, Mr. Bodemar led the development of
a load rating manual to help North Dakota DOT determine allowable permit loads for the bridge.
Trinidad I-25, Colorado DOT, Trinidad, CO ($35 million)
Lead Structures Engineer, 2004 2005

Mr. Bodemar was the Lead Structures Engineer for the final design of two 2200-foot-long viaduct
structures, two ramp bridges and four bridges over the Purgatoire River. The project is designed
with a precast segmental box girder superstructure to be erected in both span-by-span and balanced
cantilever construction. The balanced cantilever construction method was utilized over two BNSF
railroad tracks which had a significant skew to the alignment. Mr. Bodemars responsibilities on this
project included design oversight of all superstructure and substructure components and final review
of the plans prior to bidding.
Mon/Fayette Expressway (Section 53K), Pennsylvania Turnpike, Pittsburgh, PA ($75 million)
Assistant Lead Structures Engineer, 2004 2006

Mr. Bodemar led the preliminary structural design of a two-mile-long section of the Mon/Fayette
Expressway on the northern banks of the Monongahela River. The steep hillside north of the river
requires either large retaining walls or viaducts throughout this two-mile stretch of the expressway.
Preliminary design considerations include superstructure erection methods on the environmentally
sensitive hillside and foundation solutions for the landslide forces anticipated due to slope stability
problems.
Fourth Street Bridge, Colorado DOT, Pueblo, CO ($36 million)
Assistant Lead Structures Engineer, 2005 2006

Mr. Bodemar led the structural design of twin, 5-span, 1100-foot-long bridges over a railroad yard.
The main span of this cast-in-place segmental bridge is 378 feet long and was constructed in the
balanced cantilever method. The main span was designed to span over approximately 20 railroad
tracks and avoids the placement of piers within the railroad yard.
Allegheny River Bridge, Pennsylvania Turnpike, Pittsburgh, PA ($190 million)
Assistant Lead Structures Engineer, 2005 2006

Mr. Bodemar was a lead engineer for the structural design of twin 6-span, 2350-foot-long bridges.
The bridges are cast-in-place segmental box girder bridges to be constructed by the balanced
cantilever method. The bridges feature 532-foot-long main spans, and the piers are twin walls to
maximize longitudinal flexibility, but maintain rotational stiffness for cantilever construction. Mr.
Bodemar led the design of foundation alternates to improve competition among bidders, and he was
the lead engineer for the design of several superstructure components.

Volume 2 Section 1 Design Resumes page 22

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Dana De Vera, P.E., S.E.

Approach Substructure Lead

Profession
Civil/Structural Engineer/
Engineering Manager

Experience

Career Summary
Mr. De Vera has over 14 years experience specializing in
the design of bridge and marine structures. Dana has spent
10 years employed at Biggs Cardosa Associates working in
the main office in San Jose, California and since 2009,
managing the firms Orange County Office.
When first relocating to Southern California in 2002, Dana
worked as a Structural Engineer for the Port of Long
Beach.
Dana De Veras structural design expertise consists of
numerous projects, including new construction,
rehabilitation and/or seismic retrofit of various highway,
marine, pedestrian, vehicular, and rail bridge structures
and other complex infrastructure projects throughout
California.

14 years

Experience in Proposed Role


3 years

Licenses and Registrations

Registered Professional Engineer: CA


#C58894, #S4702

Education

B.S., Civil Engineering; University of


Southern California, Los Angeles; 1995
M.S. Structural Engineering, University of
California at Berkeley, 1996

Caltrans Experience

85/101 South Interchange


Schuyler Heim Bridge Replacement
Sprinter Rail Project
Tustin Rose Grade Separation

Relevant Project Experience


85/101 South Interchange, Caltrans, San Jose, CA ($40.5 million)
Design Engineer, 2002

Mr. De Vera was the Design Engineer for the 101-85/South 101 HOV Connector Separation, a 58foot-wide cast-in-place prestressed box girder bridge with a 90-foot outrigger bent. The total length
of the bridge is 636 feet. Assistant Design Engineer for the seismic retrofit of the Coyote Creek
Bridge (Widen), a three-span, 474-foot-long cast-in-place prestressed box girder bridge. QA/QC,
Engineer for Bernal Road Undercrossing (Widen) at Highway 101 a two-span 214-foot-long cast-inplace prestressed box girder bridge
Tustin/Rose Grade Separation, OCTA, Placentia/Anaheim, CA ($38 million)
Engineering Manager, 2009 2011

Mr. De Vera was the Engineering Manager leading all engineering work. This project raises Tustin
Avenue/Rose Drive over Orangethorpe Avenue and BNSF railroad tracks. The initial 6-month
phase of work consisted of conducting a feasibility and alternatives development phase to support
the environmental document. BCA started Final Design at the end of 2009 on an 18-month
schedule, submitted a bid-ready set in June 2011on schedule.
Tenth Street Bridge Girder Repair Project, Port of Long Beach, Long Beach, CA ($0.5 million)
Lead Structural Engineer, 20062007

Mr. De Vera was the Lead Structural Engineer in charge of the steel bridge girder repair. The
exterior steel girder was damaged by an unpermitted oversize truck traveling on the 710 freeway.
The steel cross bracing and approximately 30 feet of plate girder was damaged and displaced
approximately one foot from vertical. The damaged girder was repaired by heat straightening
techniques. To repair the bridge girder, a shoring structure was installed on the bridge deck to relieve
the bridge girder of any loads from above. Since the damaged bridge crosses over the heavily
traveled 710 freeway, all work was done at night.

Volume 2 Section 1 Design Resumes page 23

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Schuyler Heim Bridge Replacement, Caltrans, Long Beach, CA ($361 million)


Lead Structural Engineer, 2004 2005

Mr. De Vera was the Lead Structural Engineer for the ACTA team and led the structural feasibility
portion of the Caltrans PR/PSR. This portion of the project consisted of nearly two miles of
elevated structure and numerous ramps adjacent the Alameda Corridor.
POLB Pier G South Slip Fill Project, Port of Long Beach, Long Beach, CA ($20 million)
Engineering Manager, 2009 - Present

Mr. De Vera was the Engineering Manager for the design of the wharves at Berths G230 and G234,
which will connect to the existing wharves at Berths G232 and G236. This is part of the Pier G
Terminal Redevelopment Program. The wharf at Berth G230 will be approximately 600 feet long
and the wharf at Berth G234 will approximately be 800 feet long.
POLB Pier G G236 Ship to Shore Power Retrofit Project, Port of Long Beach, Long Beach, CA
($3 million)
Engineering Manager, 2010-2011

Mr. De Vera was the Engineering Manager for the design of the structural infrastructure required to
cold iron container vessels berthed at Pier G, Berth G236. The infrastructure required is a conduit
hanger system below the wharf, a conduit guard at the wharf face. The existing wharf will be
modified by excavating and constructing concrete walls which will house the shore power vault
outlets. Six shore power vaults will be installed at Berth G236.
Central Artery I-93 Viaducts and Ramps, Massachusetts Highway Department, Boston, MA
($187 million)
Design Engineer, 1997 1998

Design Engineer for 8 ramps that connect to the Charles River Bridge. All 8 ramps were curved
concrete segmental bridges.
Bath-Woolwich Bridge, Maine DOT, Bath, ME ($46.6 million)
Design Engineer, 1997-1998

Design Engineer for the 69-foot-wide cast-in-place concrete segmental bridge. The total length of
the bridge is almost 3,000 feet.
Smart Road Bridge, Virginia DOT, Blacksburg, VA ($17.4 million)
Design Engineer, 1997 1998

Design Engineer for the design of a four-lane, five-span cast-in-place concrete segmental bridge
over Ellet Valley. The total length of the bridge is approximately 2,000 feet.
Sprinter Rail Project, North County Transit District, San Marcos, CA ($200 million)
Structures Representative, 2005 2006

Structures Representative for the owner, NCTD. The project consisted of five cast-in-place
prestressed box girder bridges for light rail traffic and multiple structures including concrete
retaining walls, MSE walls and steel sheet pile walls, concrete box culverts and station platforms.
Caltrans was involved in the design and construction process since two bridges crossed over SR-78.

Volume 2 Section 1 Design Resumes page 24

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Yuli Huang, Ph.D, PE


Seismic Analysis

Profession
Structural Engineer

Experience

Career Summary

3 years

Yuli Huang is an analyst in the advanced technology and


research group of Arups San Francisco office. He
specializes in the methodology development in analysisoriented structural and earthquake engineering, interacting
with blast, bridge, fire, geotechnical, mechanical, offshore,
risk, and vehicle engineering disciplines.
Yuli Huang is uniquely experienced in the development,
implementation and application of numerical analysis
methods in structural engineering

Relevant Project Experience


Robert I. Schroder Overcrossing, Contra Costa County
Redevelopment Agency and Public Works, Pleasant
Hill, CA

Experience in Proposed Role


3 years

Licenses and Registrations

Registered Professional Engineer: CA


#C78548

Education

B.S., Civil Engineering; Tsinghua


University, Beijing; 2002
M.S., Structural Engineering, Tsinghua
University, Beijing; 2005
Ph.D., Engineering, University of
California, Berkley; 2009

Design-Build Experience
Robert I. Schroder Overcrossing
Guggenheim Museum
King Abdulaziz International Airport

Analyst, 1999 2010

Bridge engineering and geotechnical, civil, utility relocation, and lighting design for a pedestrian and
bicycle crossing that allows users of the Iron Horse Trail, a 33-mile trail in the San Francisco Bay
Area, to safely cross over a busy eight lane roadway. The bridge is the centrepiece of the sustainable
Contra Costa Centre Transit Village, recognised as a successful demonstration of a transit-oriented
development. As project manager and bridge designer, Arup engaged the community in an outreach
programme to reach consensus on the bridges form and location. This included stakeholder
meetings, a public design charrette and an online survey for residents. As prime consultant, Arup
retained sub-consultants for architectural design of bridge components, landscape design, and
modifications to the traffic signals. Erection of the bridge took place over three nights in June 2010.
Analyst responsible for bridge arch-deck impact resilience assessment in earthquake events.
Transbay Terminal,Transbay Joint Powers Authority, San Francisco, CA ($1.8 billion)
Analyst, 2009 Present

New five-level multi-modal facility and a 1.3-mile underground commuter rail extension in San
Franciscos downtown. Commuter rail, light rail, multiple bus services and joint development are to
be accommodated in the current scheme for this $1.8 billion program. Arup is Geotechnical
Engineer and Blast/Progressive Collapse consultant for the project, and is designing the cable stayed
approach bridge to the bus deck. Michael Willford has played a key technical lead role in a number
of aspects of the project. (1) Non-linear soil-structure interaction analysis of the 65-foot-deep
trainbox and its effect on adjacent existing structures during construction and in earthquakes. (2)
Non-linear seismic soil-structure analysis to quantify the effect of the trainbox on the foundations
and superstructure of the cable stayed approach bridge, designed to Caltrans Standards. (3) Nonlinear blast and progressive collapse analysis to develop the robustness design of the steel and
reinforced concrete superstructure to terrorist threats. Analyst responsible for soil-structure
interaction analysis for the excavation/construction stage and blast resilience assessment for service
stage. Also responsible for development and implementation of strain rate effect model for soil in
seismic analyses.

Volume 2 Section 1 Design Resumes page 25

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Rail Car Blast Vulnerability Assessment, Joint Transportation Security


Administration/Federal Railroad Administration Project, United States
Analyst, 2009 Present

Analyst responsible for assessment of blast resilience and evaluation of methodology for air blasttrain interaction analysis.
Guggenheim Museum Abu Dhabi, Abu Dhabi Tourism Development & Investment Company,
Saadiyat Island, United Arab Emirates (Cost is Confidential)
Analyst, 2010 Present

Structural Engineer for this 968,000ft museum located on reclaimed land at the tip of Saadiyat
Island. This museum, designed by Gehry Partners, will house modern and contemporary art and will
contain 140,000ft of exhibition space.
King Abdulaziz International Airport, Saudi Binladin Group, Saudi Arabia (Cost is
Confidential)
Analyst, 2010 - 2011

Analyst responsible for assessment of structural fire performance


BART Railcar Blast, Bay Area Rapid Transit District, Oakland, CA
Analyst, 2010 2010

Review of existing BART railcars, review of current specifications, assess the impact of various
explosive scenarios on railcar performance, develop preliminary mitigation measures, host a
workshop with BART, develop specifications, and reporting. Analyst responsible for assist in the
identification and investigation of blast resilience.
A 30 Montreal, Ministry of Transport Quebec, Quebec, Canada (CAD$ 1.5 billion)
Analyst, 2007 Present

A consortium of Spanish contractors, with Arup as lead designer, is designing, building, operating,
financing, maintaining and repairing the A30 design/build highway project. Including two major
bridge crossings (St. Lawrence River and the Beauharnois Canal), 31 bridge structures, 26 miles of
new expressways, nine interchanges and a tunnel under the Soulange Canal, the project is to ease
road congestion by providing drivers with a way to bypass the Island of Montreal. To meet the
clients timely and economic construction objectives, Arup mobilized international resources,
rescheduled designs to allow early construction commencement, and used various studies to take
account of local ground and weather conditions. Analyst responsible for seismic capacity analysis of
column-to-cap beam connection.

Volume 2 Section 1 Design Resumes page 26

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ramin Motamed, Ph.D


Seismic Analysis

Profession
Geoseismic Engineer

Experience

Career Summary

5 years

Experience in Proposed Role


Ramin Motamed is an engineer in the geotechnical
3 years
earthquake engineering group in Arups San Francisco
Licenses and Registrations
office, which specialize in earthquake and dynamic related
problems in the field of geotechnical engineering. His
Engineering-In-Training: CA #140722
particular skills include seismic hazard assessment; site
Education
response analysis; generation and spectral matching of
B.S., Civil Engineering; Urmia University,
acceleration time history records; microtremor
Iran; 2000
measurements and local site effect studies; liquefaction
MSc (Hons), Civil Engineering
(Earthquake); University of Science &
assessment and countermeasures; lateral spreading; pile
Technology, Iran; 2002
foundations; quay walls; and instrumentations.
PhD, Civil Engineering (Geotechnics);
University of Tokyo, Japan; 2007
Dr. Motamed has previously been involved in several
Post-Doctoral Fellowship, Tokyo Institute
seismic projects in Iran from 2001 to 2004, including
of Technology, Japan; 2009
microzonation and hazard studies. His main
responsibilities were probabilistic seismic hazard
assessment, site response analysis, local site effect evaluation, and microtremor measurements.

Ramin combines strong academic background with practical experience in delivering value to
clients in understanding and mitigating seismic hazards.

Relevant Project Experience


Confidential Campus Headquarter, Cupertino, CA ($3.5 billion)
Geo-seismic engineer, 2010 Present

Carried out site-specific seismic hazard analysis (PSHA and DSHA). Considered the effect of nearfault directivity by explicit consideration of velocity pulse-like motions in PSHA. Developed
spectrally compatible ground motions using RSPMatch, taking care to preserve the non-stationary
characteristics of each motion, including preservation of the velocity pulse. Analyzed site response
analysis using DEEPSOIL.
Transbay Terminal, Transbay Joint Powers Authority, San Francisco, CA ($1.8 billion)
Geo-seismic engineer, 2010 Present

Developed spectrally matched acceleration time history records using RSPMatch taking into account
the near fault effect. Performed site response using DEEPSOIL.
California High Speed Rail Project, California High-Speed Rail Authority, Fresno-Bakersfield,
CA ($7.2 billion)
Geo-seismic engineer, 2010 Present

Reviewed preliminary geological and seismic hazard report for the alignment between Fresno to
Bakersfield. Performed 15% Engineering seismic design calculations. This work included derivation
of seismic design response spectra and liquefaction assessment. Developed 30% Engineering ground
motions.
Vegas High Roller, Caesars Entertainment Inc., Las Vegas, NV ($150 million)
Geo-seismic, 2010 2011

Reviewed geotechnical borings, p-s suspension logs, and refraction microtremor survey results.

Volume 2 Section 1 Design Resumes page 27

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Calculated seismic design parameters. Derived spectrally matched time history records for dynamic
analysis. Carried out liquefaction assessment. Prepared seismic engineering section of the
geotechnical design report.
Guggenheim Museum, Abu Dhabi Tourism Development & Investment Company, Saadiyat
Island, UAE (Cost is Confidential)
Geo-seismic engineer, 2009 2010

Carried out site response analysis and liquefaction assessment to determine the extent of required
soil improvement for liquefaction mitigation for this 968,000ft museum located on reclaimed land
at the tip of Saadiyat Island. This museum, designed by Gehry Partners, will house modern and
contemporary art and will contain 140,000ft of exhibition space.
Evaluation of Seismic Risk in Port Systems, Internal Research Project ($10k)
PI, 2009 2010

Evaluate the seismic risk in port systems from liquefaction-induced lateral spreading perspective.
Conducted a thorough literature review on the available methods to predict liquefaction-induced soil
displacement in (1) waterfront structures, (2) sloping grounds, and (3) free-face ground conditions.
Several case studies were selected and the above-mentioned approaches were applied. Finally, merits
and demerits of each method were addressed and practical recommendations were made.
Sengkang LNG Terminal, Energy World Corporation, Sengkang, Indonesia ($350 million)
Role, 2009 2010

Performed site-specific probabilistic seismic hazard analysis for determining design parameters
including Peak Ground Acceleration (PGA) and Uniform Hazard Response Spectrum (UHRS) for
bedrock level. Conducted seismic hazard analysis to evaluate the above mentioned parameters at the
ground surface. Moreover, performed DYNA5 and PIGLET modelling for pile group analyses.
Generated spectrally matching acceleration time history records using RSPMatch2005. Analysed pile
foundation under seismic-induced loading (kinematic and inertial) using Oasys ALP.

Volume 2 Section 1 Design Resumes page 28

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Bryan Marsh

Concrete Durability and


Performance

Profession
Concrete Technologist

Experience
32 years

Experience in Proposed Role

Career Summary

14 years

Bryan is a key member of Arup Materials Consulting, a


Licenses and Registrations
specialist group within Ove Arup & Partners, which
Chartered Engineer (CEng) [UK]
provides advice to all parts of the Ove Arup Partnership
Member, Institution of Civil Engineers
and external clients, worldwide, on the use of materials in
(MICE) [UK]
the construction process. He is Arups leading expert in
Fellow, Institute of Concrete Technology
concrete and cement based materials, undertaking
(FICT) [UK]
specialist design studies, specification writing and
Education
reviewing, and investigation of in-service performance. He B.Sc., Civil Engineering; University of
has been involved with UK and European standards for
Surrey, England; 1979
concrete, particularly with respect to durability. Prior to
Ph.D., Concrete Technology; Hatfield
Polytechnic, England; 1984
joining Arup, he was Head of the Concrete Technology
Diploma of Advanced Concrete
Section at the UK Building Research Establishment for
Technology; Institute of Concrete
over ten years. He is a former president of the Institute of
Technology, England; 1988
Concrete Technology and has over 40 published papers
and book chapters on various aspects of concrete technology.
Bryan Marsh is Arups leading specialist on concrete materials and technology, with over 30
years of relevant experience

Relevant Project Experience


New Forth Crossing, Transport Scotland, Queensferry, Scotland ($1.5 billion)
Concrete Technologist, 2008 Present

The Forth Replacement Crossing will be the worlds longest 3-tower cable stayed bridge, and the
largest infrastructure project in Scotland for a generation. The new bridge is to replace the existing
Forth Road Bridge, opened in 1964, which is showing signs of deterioration as a result of increased
traffic and the influence of weather and climate. The project has encompassed development of a
concept design, through parallel parliamentary and procurement processes to award of design and
build contracts for construction in early 2010. Bryan assisted in the production of the Clients
Requirements with respect to concrete durability and review of tenders.
2nd Penang Crossing, Jambatan Kedau Sdn Bhd, Malaysia ($1.3 billion)
Concrete Technologist, 2010 Present

The Second Penang Bridge is a 9.3-mile sea crossing between peninsular Malaysia and Penang
Island. The bridge mainly comprises 180-foot-span precast segmental viaducts with a navigation
channel provided by a 787-foot-span concrete cable stayed bridge. The Arup Group is Independent
checking engineer for the project, a role which involves acting as the clients engineer as well as
verifying the design criteria and carrying out independent analysis and multi-disciplinary checks to
certify the project. Bryan provides specialist input with respect to concrete durability, performance
and technology.
Brisbane Airport Link, BrisConnections, Brisbane, Australia ($4.8 billion)
Concrete Technologist, 2008 Present

The project comprises of two tunnels and a new airport connection: the 4.2-mile mainly

Volume 2 Section 1 Design Resumes page 29

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

underground Airport Link toll road, the 46-foot-wide Northern Busway tunnel, and the 2,460-foot
flyover and fast-diamond intersection replacing the airport roundabout. Arup is the concept
designers and are delivering the detailed design with more than 500 design packages throughout the
construction of the project. Our design has many innovative improvements from the reference
design to achieve better outcomes for roads users, local communities and the environment. Our
design solutions also maximize benefits and minimize disruption to the community and
environment. Bryan assisted in the development of project-wide durability report for civil
infrastructure and underground structures, and provided on-going advice on concrete technology.
New Tyne Crossing, Tyne & Wear Passenger Transport Authority, Newcastle, UK ($0.4
billion)
Concrete Technologist, 2001 2011

The New Tyne Crossing is a 1-mile immersed tube to carry two lanes of southbound traffic and an
emergency escape cell beneath the River Tyne 3.7 miles east of the centre of Newcastle upon Tyne.
The purpose is to double the capacity of the existing tunnel and operate the crossing for 30 years.
Bryan assisted in the development of project-wide durability report for civil infrastructure and
underground structures, and provided on-going advice on concrete technology.
Lake Mead Intake No.3, Southern Nevada Water Authority, Lake Mead, NV, USA ($700
million)
Concrete Technologist, 2008 Present

Lake Mead provides water to Las Vegas, and severe drought has caused declining lake water levels
during recent years. Vegas Tunnel Contractors (Impregilo and SA Healy), with Arup as designer, are
designing and constructing a deep water intake at Lake Mead to protect the existing system against
potential inoperability of the two shallower intake valves already in place. The project consists of a
600-foot-deep shaft on the lake shore, around 3 miles of tunnel out under the lake and an intake
structure on the lake bed. The job also includes some highway improvements and earthworks. Bryan
provided durability design of in situ shaft lining and precast tunnel segments for new water intake,
and ongoing advice on concrete technology.
HSBC Headquarters Canary Wharf, HSBC Holdings Ltd., London ($ confidential)
Concrete Technologist, 1998 2002

Structural and building services engineering for shell core and Category A and B fit out for a 689foot-high, 44-story office building with 900 dealing positions on three of the largest trading floors in
London, covering a net area of 1,183,000ft. Bryan provided durability design of the concrete raft.
Kingdom Trade Centre, Kingdom Establishment, Riyadh, Saudi Arabia ($240 million)
Concrete Technologist, 1996 1998

Structural and facade engineering design of a 984-foot, 30-story building containing offices, hotel
accommodation and retail space. Designed to be a globally-recognizable icon of Saudi Arabia, the
building consists of a slim tube that rises out of an elliptical floor plan and ends in a parabolic curve
and shallow arch. As Riyadh's planning ordinance stipulates that buildings can have no more than 30
occupied floors, the top third of the building is purely sculptural, with the exception of an
observation deck on the uppermost level. Hot-weather and large-pour aspects of 13.1-foot-deep
concrete raft foundation. He has been involved in similar large pours in Africa, the Philippines, and
the UK.

Volume 2 Section 1 Design Resumes page 30

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Graham Gedge, BSc.MSc.


MIMMM, CEng
Corrosion Control

Profession
Metallurgist

Experience
25 years

Experience in Proposed Role

Career Summary

20 years

Graham joined Arup Materials in 1987 to provide


specialist advice on corrosion and corrosion control to
Arup projects and clients worldwide. Graham is now
based in the UK but has previously been based in Hong
Kong and has worked in other parts of the Far East,
Australia and the US.

Licenses and Registrations

Registered Chartered Engineer, UK

Education

B.Sc. Chemistry, University of


Manchester
M.Sc. Offshore Engineering, Cranfield
Institute of Technology

Graham has worked on many Arup bridge projects


Design-Build Experience
around the world. This work includes long-span bridges, Forth Crossing
and he is very familiar with the durability issues and
Tappen Zee Bridge
concerns of owners with respect to corrosion control.
He has been at the forefront of the use of innovative approaches to durability of structures that
provide long, maintenance-free lives. He ensures that durability solutions are not only
technically robust, but also integrated with the design of the project. He tailors these solutions
to reflect the owners requirements for durability and approaches to whole-life maintenance,
while respecting local specification and construction practices.

He is now responsible for the provision of consultancy services to clients worldwide in relation to
corrosion, corrosion control and durability of materials. This work includes corrosion risk
assessments, use of corrosion resistant alloys, coating specifications and the use of cathodic
protection for both steel and reinforced concrete structures.
He has experience in both offshore and onshore engineering, including bridge and other civil
structures, offshore platforms, nuclear engineering and building engineering.
Relevant Project Experience
Tappen Zee Replacement Bridge, New York State Thruway Authority (NYSTA), NY
Corrosion Consultant 2011 to 2012

Technical specification of corrosion protection for all steel parts of the bridge for use in this designbuild tender. Assessment of corrosion risks to internal spaces of the decks and arches that use closed
sections recommendations to the owner of options to control these risks including dehumidification,
corrosion allowance and protective coatings; the assessment took account of the preferred US
practice in bridge engineering. The study will also provide input to a life cycle cost assessment to
assess the most cost-effective option for owner over the 150-year design life. Many of the
corrosion/durability concerns are likely similar to those on the Gerald Desmond Bridge. The work
is also relevant as the outputs are to US specifications for a design-build contract.
Forth Crossing, Transport Scotland, Edinburgh, Scotland, UK
Corrosion Consultant, 2007 Present

Assessment of corrosion risks for the steel deck and cable structures and corrosion risks for
reinforcement in concrete passing through the splash zone. Specification of corrosion protection for
external steelwork using standard UK Highways Agency specifications for painting modified to
reflect the requirements of European standards and current best practice. Currently checking the
Design and Build contractors proposals for compliance with the specification requirements.

Volume 2 Section 1 Design Resumes page 31

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Specification of stainless steel reinforcement for the towers within a carefully defined area of the
splash zone to ensure long-term durability against chloride induced corrosion of the reinforcement.
Stonecutters Bridge, Hong Kong Highways Department, Hong Kong
Corrosion Consultant Role, 2002 2009

Provided input to and a review of the overall durability study for the cable stayed and approach
bridges undertaken by Arup Hong Kong. The report included durability of both the steel deck and
cable structures and the reinforced concrete for the towers and resulted in the specification of
corrosion protection to meet the particular durability requirements of the projects.
A unique feature of the work on Stonecutters was the need for the upper 394 feet of the towers to
be a composite steel/concrete section. This presented specific durability and maintenance issues for
the owner. The chosen solution was to replace the carbon steel outer section with a duplex stainless
steel section that could provide a maintenance free structure for the design life of the bridge.
Graham was responsible for the commissioning and monitoring of the fabrication of full-scale trial
sections of the skin followed by the specification of the materials. Subsequently he provided both
remote and onsite support during the fabrication and erection of the sections in China and at the
bridge site.
The work is relevant to GDB because the cable stayed bridge spans the entrance to a busy container
port in Hong Kong and durability of the structure was an important aspect of the design for the
owner.
Oresund Crossing, Oresundbro Konsortiet, Malmo/Copenhagen, Sweden/Denmark
Corrosion Consultant, 1993 to 1999

Review and assessment of best practice with respect to corrosion control using paints for marine
structures. This work included research on best practice in European bridge fabrication, offshore
structures and ports and harbors and made recommendations to the owner of the most appropriate
options. Development of project specific corrosion protection specifications for the approach and
main cable stayed spans of the bridges on the crossing. Review of contractors fabrication
procedures and methodology to ensure maximum durability from the specification.
Monitoring of the steel construction of the approach spans in Cadiz, Spain and main span in
Karlskrona, Sweden and on site to ensure corrosion protection was applied to the highest standard.
Working with the Contractor to develop appropriate methods for the onsite repair of corrosion
protection, particularly at site-welded connections on the approach spans.

Volume 2 Section 1 Design Resumes page 32

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Chris Murgatroyd

Metallurgy and Fabrication


Career Summary

Profession
Metallurgist/Welding Engineer

Experience
40 years

Chris Murgatroyd is a member of the Arup Materials


Consulting which provides advice to all parts of the firm,
both in the UK and overseas, on the use of materials in
building, civil engineering and offshore structures and on
methods of construction.
Chris Murgatroyd has many years experience as a technical
adviser in welding, fabrication, NDT and materials.
Forensic investigations and expert witness form another
part of duties offered to the firm and externally.
Prior to joining Arup he worked in structural and
mechanical engineering for 20 years both onshore and
offshore.

Experience in Proposed Role

Chris specialises in the use of metals in construction


with an emphasis on welding technology and NDT
based on experience in construction of international
projects both onshore and offshore. His expertise spans
many varied industries and is readily transferable to any
aspect involving metal fabrication.

22 years

Licenses and Registrations

Chartered Engineer: C.Eng. #400860


European Engineer: Eur lng,
UK/NDT/0016
European Welding Engineer, European
Welding Federation: EWE/GB/00851994
Registered Welding Engineer, Group 1,
TWI/SCSWIP 1994
Registered Welding Materials Engineer,
Group 1, TWI/CWIP, 703, 1994
Registered Welding Construction
Engineer, Group 1, TWI/CSWIP, 703,
1994

Education

BSc (Hons) Metallurgy, City of London


Polytechnic, 1987
MSc Underwater Technology/Subsea
Engineering, Cranfield Institute of
Technology, Bedfordshire, U.K.: 1989

Relevant Project Experience


Fort Replacement Crossing, Transport Scotland, Scotland, UK
Metallurgical Engineer, 2011 Present

The Forth Replacement Crossing is a major infrastructure project for Scotland. Designed to
maintain the vital cross-Forth connection in Scotlands transport network and reduce traffic loads on
the existing Forth Road Bridge. Arup form part of the Employers Delivery Team which are
operational on site across all three major contracts to monitor progress, quality and compliance with
contract. . This will require specialist input relating to the quality of welded steel fabrications and
inspection at various contractors in Europe and China.
Millennium Footbridge Bridge, Corporation of London, London, UK ($28 million)
Metallurgical Engineer, 1997 2001

New 1,066-foot-long, 13.1-foot-wide flat suspension bridge spanning the river Thames, London.
Arup provided full structural, geotechnical and maritime engineering design and supervision.
Preparation of structural steelwork specifications including locked coil cable specifications and
specialist input/supervision during the fabrication and installation of the bridge. Specialist input
relating to the quality of welded steel fabrications and inspection at various contractors in Europe.
Dutch Bridges, Rijkswaterstaat (RWS), Ministry of Infrastructure and the Environment,
Holland
Managing Contractor, 2008 Present

Assessment and remediation of a number of significant road traffic bridges for RWS, Holland. In
many cases the steel orthotropic decks have developed longitudinal fatigue cracks as well as fatigue

Volume 2 Section 1 Design Resumes page 33

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

cracking in other heavily loaded locations. Assessments have been done to assess the efficacy of the
RWS proposed remediation procedures. In conjunction with Royal Haskoning the remedial
measures are in the process of being implemented. Assistance provided in control of welding to
avoid distortion and inspection of various elements.
Tees Barrage Bridge, TARMAC Construction Ltd., Gatehead, UK ($3.7 million)
Materials Welding Engineer, 1990 1995

8-arch steel road bridge and low-level footbridge crossing the Tees Barrage. Each arch is 57.4-foot
span, with four crossing the barrage and two on each end crossing the navigation channel, fish pass
and canoe slalom. Materials/Welding Engineer: Tees Barrage Bridge is an unusual structure that has
large cast steel sections incorporated into the bridge structure. Advice and assistance was provide
during initial design and progressed into fabrication with inspection visits to the fabricators. Audits
were conducted on all quality related activities and materials.
New Doha International Airport, New Doha International Airport Authority, Doha, Qatar
Materials Welding Engineer, 2008 Present

Assessment of solutions proposed to address non conformity reports raised during the construction
of the foundations for the New Doha International Airport. Materials/Welding Engineer
performing investigations into the acceptability of structural weld quality and providing advice on
materials following failures of such material during construction.
Abu Dhabi International Airport, Abu Dhabi International Airport, UAE (Cost is Confidential)
Materials Engineer, 2006 2009

Expansion of Abu Dhabi International Airport featuring a 6,300,000ft terminal building, a


commercial complex, a central plant, parking garages, miscellaneous airside facilities, an air traffic
control tower and hotels. Works required an assessment and recommended enhancements to
upgrade the airports information communications technology (ICT) systems, infrastructure, and
procedures, and creation of airport-wide ICT guidelines designed to standardize economies of scale
across the airport. Materials Engineer: Proving assistance on specification and connection design
prior to tender assessments.
Hulme Arch Bridge, City of Manchester, Greater Manchester, UK ($2.7 million)
Metallurgical Engineering, 1995- 1997

Single-span, 164-foot road and footbridge with 82-foot-high diagonal steel arch to carry deck.
Preparation of structural steelwork specifications and specialist input/supervision during the
fabrication and installation of the bridge.
Southern Star Observation Wheel, ING VA STGOED ONT WIKKELING BV, Docksland,
Australia (Cost is Confidential)
Metallurgical Engineer, 2009 2011

Critical review of the design of observation wheel that to identify the premature failure at welded
connections. Assessment of potential remedial options of the existing wheel, which ultimately
resulted in the decision to dismantle and re-design and re-build the structure. Specialist input to
design fatigue details to allow manufacture. On-going assistance necessitating frequent site visits to
provide support during the fabrication phase to ensure that the fabrication quality satisfied design
intent and specification requirements.

Volume 2 Section 1 Design Resumes page 34

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Simon Cardwell

BSc (Hons), CEng, MIMMM


Career Summary

Profession
Metallurgical Engineer

Experience
22 years

Experience in Proposed Role


Simon is a member of Arup Materials Consulting which
22 years
provides specialist materials advice both within the
Partnership and to external clients. He is based in the UK, Licenses and Registrations
but has extensive experience of working on projects
Registered Charted Engineer, UK
throughout the world.
Education
BSc(Hons) University of Salford
Simon covers all aspects of the use of metals in the built
environment, including material selection and
Design-Build Experience
specification, fabrication, welding and manufacturing
London Docklands 3-Car Upgrade, UK
technology, and corrosion and corrosion protection.
Besides his extensive metallurgical knowledge and
experience Simon is a recognized expert in the field of Fracture and Fatigue. He currently sits on the
UK panel of experts with respect to fracture and fatigue for Eurocode 3 for the design of steel
structures.
He has a broad experience of a variety of different metals and product forms, including
conventional fabricated structural steel, structural steel castings, structural cables and tendons,
fixings and fasteners, and reinforcing steels. He has used this experience across a broad spectrum of
industry sectors including offshore, energy, civil and structural engineering, and transportation.

Simon has worked on many Arup Bridge and related infrastructure projects around the world.
He will bring his specialist knowledge and skills to the development of appropriate designs,
selection and specification of materials. His specialist fracture and fatigue knowledge will ensure
that optimum performance of materials can be assured through appropriate specification and
detailing. During the construction phase his skills will be used to ensure that the fabrication
works are delivered in accordance with the design intent and specification requirements.

Relevant Project Experience


Millennium Footbridge Bridge, Corporation of London, London, UK
Metallurgical Engineer, 1997 2001

New 1,066-foot-long, 13.1-foot-wide flat suspension bridge spanning the river Thames, London.
Arup provided full structural, geotechnical and maritime engineering design and supervision.
Preparation of structural steelwork specifications including locked coil cable specifications and
specialist input/supervision during the fabrication and installation of the bridge. Specialist input
relating to the fatigue performance of the welded steel fabrications and the locked coil cables.
Dutch Bridges, Rijkswaterstaat (RWS), Ministry of Infrastructure and the Environment,
Holland
Managing Contractor, 2008 Present

Assessment and remediation of a number of significant road traffic bridges for RWS, Holland. In
many cases the steel orthotropic decks have developed longitudinal fatigue cracks as well as fatigue
cracking in other heavily loaded locations. Assessments have been done to assess the efficacy of the
RWS proposed remediation procedures. In conjunction with Royal Haskoning the remedial
measures are in the process of being implemented. Fatigue design assessment based on conventional
S-N theory and standard codes of practice. Specialist Fracture mechanics based fatigues assessments
on fitness-for-purpose basis using the procedures outlines in BS 7910 for specific details.

Volume 2 Section 1 Design Resumes page 35

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Docklands Light Rail, 3-Car Upgrade, London, UK (200 million)


Metallurgical Engineer, 2006 2011

Transport of London identified the need to increase the capacity of the DLR from a 2-car to a 3-car
system to accommodate increased demand during the 2012 Olympics. This involved assessing the
existing infrastructure against the increased capacity demands. Review of the use of Ultrasonic
Impact Treatment (UIT) weld toe improvement technique to improve the projected fatigue life of
web stiffener details, which was determined empirically. This included pre-fatigue of test specimens
to simulate existing accumulated damage, UIT treatment, fatiguing to failure and determining an
appropriate detail category with consistent probability of survival with the design code of practice.
Stonecutters Bridge, Hong Kong Highways Department, Hong Kong
Metallurgical Engineer, 2002 2009

New cable stayed bridge with two single-pole towers 951 feet high and twin aerodynamic deck. The
bridge is 5,235 feet long and has a main span of 3,339 feet.Brittle fracture assessment of fabricated
structural steelwork leading to specification requirements for structural steelwork in terms of
required fracture toughness requirements in order to meet local code of practice requirements. Ongoing assistance and support during the fabrication phase to ensure that the fabrication quality
satisfied design intent and specification requirements.
Hulme Arch Bridge, City of Manchester, UK
Metallurgical Engineering, 1995- 1997

Single-span, 164-foot road and footbridge with 82-foot-high diagonal steel arch to carry deck.
Preparation of structural steelwork specifications including locked coil cable specifications and
specialist input/supervision during the fabrication and installation of the bridge. Specialist input
relating to the fatigue performance of the welded steel fabrications and the locked coil cables.
Railtrack Plc, Rail Head Checking Investigation, UK
Metallurgical Engineer, 2000 2002

Technical and managerial investigation into the causes of the fatigue cracking phenomenon in rails
that led to the Hatfield derailment in 2000. Specialist metallurgical investigation of the incidence and
extent of rolling contact fatigue (RCF) on the UK rail network, leading to an understanding of the
relationship of surface crack length and depth into the rail head. This work was used to assist the
development of an appropriate control strategy.
Southern Star Observation Wheel, Melbourne
Metallurgical Engineer, 2009 Present

Critical review of the fatigue design of structural steel observation wheel that suffered premature
fatigue damage. Assessment of potential remedial options of the existing wheel, which ultimately
resulted in the decision to dismantle and re-design and re-build the structure. Specialist input to
optimise fatigue details of the re-design options. Ongoing assistance and support during the
fabrication phase to ensure that the fabrication quality satisfied design intent and specification
requirements.
Metro Rolling Stock, Design and Maintenance Appraisal, UK
Expert Witness, 2006 2008

Specialist metallurgical input to investigate the overall design adequacy of a metro rolling stock;
including code based fatigue assessment of the rolling stock bogie frame and review of the vehicle
operators maintenance practices. Review of and commentary on fatigue test data with particular
relevance to the design of the bogie frame.

Volume 2 Section 1 Design Resumes page 36

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Joe Roe, C.E.G.

Certified Engineering Geologist


Career Summary

Profession
Project Geologist

Experience
11 years

Mr. Roe has extensive experience managing and


conducting field geotechnical investigations for various
projects including slope stabilization, fault investigations,
mass grading, piles, caissons, asphalt paving, footings,
utility backfills, drill logging, rock coring, test trenching,
monitoring and pump well installations. His experience
includes planning and directing subsurface investigations,
earth and rock material characterization, sampling and
laboratory soil testing; interpreting and analyzing data and
test results, performing geotechnical analyses pertaining to
foundation, slope stability, seepage, groundwater,
instrumentation and construction monitoring, preparing
cost estimates and technical reports.

Experience in Proposed Role

Mr. Roe has participated in many aspects of project


development, from project planning, investigation,
construction services, and project management.

Caltrans Experience

5 years

Licenses and Registrations

California Certified Engineering Geologist:


#2456
California Professional Geologist: #7921
Certified Nuclear Density Gauge Operator
Radiation Safety Officer (RSO)

Education

B.S. Geology, Cal State University


Fullerton, 2000

Design-Build Experience
Foothill Transportation Corridor - South
SR 241 Loma Ridge Stabilization
California High Speed Rail
SR 241 Loma Ridge Stabilization

Relevant Project Experience


California High Speed Rail, Los AngelesOrange County Segment, California High-Speed Rail
Authority ($2 billion)
Project Geologist, 2008

Project Geologist for the proposed 30-mile rail alignment from Los Angeles Union Station to the
Anaheim Station. Geologic data collected and analyzed for the study area included topography,
geology, soils, landslide hazards, surface fault ruptures, ground shaking, liquefaction, seismically
induced landslides, dam failure inundation, subsurface gas hazards, mineral resources, oil and natural
gas resources, and paleontological resources. The data was evaluated in relation to the proposed atgrade sections, tunnel and cut-and-cover sections, cut and fill sections, and aerial sections.
Brea Canyon Road Grade Separation, Alameda Corridor-East, City of Industry, CA ($67.4
million)
Project Geologist, 2006

Project geologist for hydrogeologic investigation and water characterization for the lowering of Brea
Canyon Road under the existing railroad. The scope included field exploration, engineering analysis
and monitoring well installation to define the hydrologic properties of the underlying groundwater
basin, evaluate the engineering properties of the subsurface soil, characterize the groundwater with
respect to its chemical constituents, and obtain static groundwater levels over the course of one
month. Data collected was analyzed for construction of a roadway subdrain system to permanently
dewater the subgrade material below Brea Canyon Road.
Edgeridge Drive Embankment Stabilization, County of Los Angeles Department of Public
Works, Hacienda Heights, CA ($.5 million)
Project Manager/Geologist, 2007-2008

Project Manager/Geologist responsible for developing a field investigation to support

Volume 2 Section 1 Design Resumes page 37

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

recommendations for the stabilization of the existing


Edgeridge Road embankment where a concrete retaining
wall failed along the southerly and downslope edge of the
active roadway. The observed distress was associated with
erosion of colluvial materials, exposing roadway subgrade
and the retaining wall foundation. It was determined that
primarily grading and drainage improvements were
required to reduce if not eliminate erosion.
Recommendations to stabilize the embankment consisted
of soldier piles anchored by corrosion-resistant steel
anchor cables, with a spanning concrete wall face to
support the road embankment.
Oakmont Industrial, J.H. Baxter Facility, Long Beach,
CA ($unknown)
Project Geologist, 2007

Project Geologist responsible for planning and


implementing a subsurface investigation for the 13-acre
area intended for development of 142 cross-dock
positions, 50 semi-tractor stalls, 402 trailer stalls, 412 auto
stalls, an office building, maintenance shed and a guard
booth totaling 10,400 square feet.
Nohl Canyon Reservoir, City of Anaheim, Anaheim, CA
($18 million)
Project Geologist, 2008 2011

Project Geologist in planning and instituting investigations


to evaluate subsurface conditions for the 10-million-gallon
tank. The scope involved installation and monitoring of an
array of inclinometers and monitoring wells as well as
design to establish baseline conditions prior to
construction. Responsibilities during construction included
extensive field mapping of bedrock exposures during
grading to collect geotechnical data used in slope stability
analysis, daily communication with engineers, client, and
multiple superintendents on the job, evaluation and
approval of stability excavations, and overseeing
installation of extensive sub and backdrain systems during
grading operations.

RFP Criteria
Experience in the exploration, analysis,
design and construction of:
Department LRFD methodology for bridge
foundations, earth retaining systems, and
other high facilities
Not a CEGs purview
Bridge structures and foundations of the
magnitude and type that will be used
Foothill Transportation Corridor - South
Planning & conducting subsurface
exploration for highway structures and other
facilities
J.H. Baxter Facility
Santa Ana River Interceptor
Site-specific geologic, seismic, and
geotechnical hazard evaluation
Ball Road Grade Separation
Nohl Canyon Reservoir
Site characterization, including the
development of design soil/rock profiles with
relevant properties for the purpose of
foundation type and size selection, analysis,
design & construction
Nohl Canyon Reservoir
Rawling Reservoir
Analysis and design of structure foundations
for static as well as dynamic (seismic)
loading
Not a CEGs purview
Soil-foundation-structure interaction (SFSI)
analysis
Not a CEGs purview
Licensed as a California Certified Engineering
Geologist by the time the Design-Build
Contract is executed:
California Certified Engineering Geologist:
#2456

Athletic Facility, West Los Angeles Community College, Culver City, CA ($80 million)
Project Geologist, 2008 2009

Project Geologist for geotechnical exploration. The sites split level, proposed design and
undocumented fill presented challenges for the geotechnical recommendations. While the Athletic
building, with a two-level basement, would require up to 20 feet of excavation, which would
essentially remove the undocumented fill, the Fitness Center is an at-grade structure that would
require removal and compaction. Leighton recommendations for the foundations and site grading
were based on the laboratory test results and field exploration that included hollow-stem auger
borings and Cone Penetration Test (CPT) soundings.

Volume 2 Section 1 Design Resumes page 38

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Liang Shen P.E.

Profession

Foundations Lead

Professional Consulting Civil Engineer


Experience

Career Summary

32 years

Mr. Shen is a structural engineer with 32 years experience


in design of bridge, inland waterway, marine, offshore and
transportation structures. Mr. Shen has focused on the
cost effective design of the structures through innovative
construction concepts and state-of-the-art analysis and
design methods. His work has been employed on the
designs of bridges, locks, dams, immersed tube tunnel,
mass rapid transit structures, and water front structures.
Extensive experience designing bridges in California.

Relevant Project Experience


Tri-Met Willamette River Bridge, Tri-Met, Portland,
Multnomah County, Oregon ($129 million)
Role, 2008 Present

Lead Structural Designer for the main span-in-water


foundations including 10-ft diameter drilled shafts and pile
caps. Project is currently under construction.

Experience in Proposed Role


28 years

Licenses and Registrations

Registered Civil Engineer, 1994 CA #


C51843
Registered Civil Engineer, 2008 OR #
81989

Education

B.S. (Civil Engineering) Tamkang


University, 1978

Design-Build Experience
Tri-Met Bridge
Cooper River Bridge

Caltrans Experience
Skyway Contract San Francisco
Oakland Bay Bridge
Carquinez Bridge
Benicia Martinez Bridge
Richmond San Rafael Bridge Seismic
Retrofit

Cooper River Bridge, South Carolina DOT, Charleston, South Carolina ($650 million)
Role, 2000- 2005

Mr. Shen was the Lead Project Structural Engineer, responsible for the main span and high level
approach piers foundation design of Replacement of Cooper River Bridge. The 1,546-foot long
main span over Cooper River is a cable-stayed bridge supported by two diamond-shaped towers
sitting on eleven 10-ft diameter drilled shafts. The high level approach is approximately 6890-ft long
supported by two-column bents on large diameter drilled shafts. Due to the high seismicity in the
region and potential vessel impact, very high lateral loadings dominated the drilled shaft foundation
design. Non-linear soil-structure interaction analyses are conducted for each pier under different
load cases and site conditions to enable detailed design for individual foundations.
Strait of Messina Suspension Bridge, Italy
Role, 2006 - 2008

Lead Project Structural Engineer and BCG Design manager responsible for the tender design of the
tower foundations and anchor blocks of the Messina Bridge to link mainland Italy with the island of
Sicily. The bridge will have a 3,300 m (2 miles) main span and 183 m side spans, overall length of
3,700 m (2.5 miles) which would be the worlds longest central span suspension bridge. Mr. Shens
major responsibilities includes: soil-foundation-structure seismic interaction analysis, determination
of equivalent foundation stiffness for the global seismic structural model, seismic response analysis
of the tower foundations and anchor blocks, and tower foundations design. Our client has
successfully won the project but the project is currently on hold due to the political issues.

Volume 2 Section 1 Design Resumes page 39

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Seismic Retrofit of the Richmond-San Rafael Bridge, Richmond, California


Role, 2008 Present

Project Structural Engineer responsible for the seismic retrofit design of Richmond-San Rafael
Bridge at the north end of San Francisco Bay. Major responsibilities included the structural design of
main tower uplift friction damper, the transfer mechanism between the superstructure chords and
the eccentrically braced frames of the anchor towers, split bents column restrainers, 2 and 4-bell
shafts strengthening, and independent check of foundation retrofit design.
New San Francisco Oakland Bay Bridge (SFOBB) Self Anchored Suspension (SAS) Bridge,
California
Role, 2008 Present

Lead Project Structural Engineer and Design Manager for the tender design of the temporary towers
and foundations for the construction of the SFOBB SAS Bridge. 26 temporary steel towers are
designed to support the bridge girders for the bridge erection operations. Due to the high seismicity
in the Bay Area and potential vessel impact, the design of towers and foundations are dominate by
large expected lateral loads. Non-linear soil-structure interaction analyses are conducted for 6 typical
towers under different load cases and site conditions.
San Francisco Oakland Bay Bridge East Span Replacement, South South Detore,
California
Role, 2008 Present

Lead Project Structural Engineer responsible for the tender design of the South-South Detour
design-build project. The detour structure consists of three structurally different segments: West TieIn - a multi-cell, post-tensioned reinforced concrete box structure; Viaduct - a double deck, multile
span, steel plate girder supported on steel towers and piers; and East Tie-In reuse and reinforce
existing YB4 span decks while replacing the existing trusses with a new support structure.
I-880 Cypress Structure Replacement, Oakland, California
Role, 2008 Present

Lead Project Structural Engineer responsible for special seismic analysis, superstructure analysis and
design review, and foundation design of 2,680 ft. long CIP/PS box-girder bridge and the detailed
design of 1,400 ft. long temporary steel viaduct near the Bay Bridge Toll Plaza.
Central Viaduct, San Francisco, California
Role, 2008 Present

Lead Project Structural Engineer responsible for developing the seismic retrofit concept, and the
subsequent detailed design of 3,810 ft. long multi-column bent steel bridge seismic retrofit and the
independent check of the seismic retrofit design of a 480 ft, long double-deck concrete bridge.

Volume 2 Section 1 Design Resumes page 40

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Djan Chandra, G.E., P.E.


Site Investigations Lead
Career Summary

Profession
Geotechnical Engineer

Experience
23 years

Mr. Chandra brings 23 years of experience in geotechnical


services from the early planning, site investigation,
laboratory testing, data analysis, report preparation
through grading and construction of various types of civil
facilities, including transportation, governmental and utility
projects. During this time, he has managed a wide range of
projects with varying geologic conditions and constraints,
including large-scale design-build projects and
transportation projects with Caltrans oversight, and has
proven skills in scheduling, budgeting, and managing
complex projects.
Mr. Chandras areas of expertise include foundation
design, soil reinforcement, slope stability analysis, finite
element analysis, and computer applications in
geotechnical engineering. His extensive experience in
design and application of geosynthetics reinforcements in
geotechnical engineering, including oversteepened slopes,
pavement subgrade stabilization, and segmental retaining
walls has proven an asset on a variety of projects.
For over 10 years, Mr. Chandra has been actively
involved with the California Board for Professional
Engineers, Land Surveyors, and Geologists in
overseeing the State Geotechnical Engineer examination.

Experience in Proposed Role


20 years

Licenses and Registrations

Registered Geotechnical Engineer: CA


#2376
Registered Professional Engineer: CA
#C50068

Education

M.S., Civil Engineering, Texas A&M


University, College Station, Texas, 1988
B.S., Civil Engineering, Chung Yuan
Christian University, Taiwan, 1985

Design-Build Experience

Foothill Transportation Corridor South


Eastern Transportation Corridor
Mid-City/Exposition Light Rail Transit
Gold Line Eastside Extension

Caltrans Experience

Mid-City/Exposition Light Rail Transit


Foothill Transportation Corridor South
Eastern Transportation Corridor
Northbound SR 57 Widening
Westbound SR 91 Widening
Gold Line Eastside Extension

Relevant Project Experience


Port of Long Beach Pier A Terminal, POLB ($2 billion)
Project Engineer/Manager, 1990 1998

Project Engineer/Manager for design and construction of 170-acre terminal that included 3,600
linear feet of pier. The pier is supported on 2,388 24-inch octagonal piles of 70 to 110 feet long.
Over 600,000 cy of underwater fill was hydraulically placed and surcharge fill was constructed to
accelerate the settlement. On the land side, 2.7 million cy of fill was placed to achieve the designed
grades. Impact of the fill on Terminal Island Freeway was evaluated.
Foothill Transportation Corridor South, Orange County, CA ($900 million)
Project Engineer, Geotechnical Engineer of Record for Design, 1994 2011

Project Engineer for the preliminary geotechnical investigation during the EIR to study the potential
alignments, and subsequently Geotechnical Engineer of Record for Design Section 2 during the
design-build phase. Field exploration program included field reconnaissance and geologic mapping,
134 borings (including rock coring), and a geophysical study. The alignments pass through areas with
geotechnical issues such as landsliding, liquefaction, and compressible soils. Recommendations
provided for seismic design criteria and both deep and shallow foundations for the proposed bridges
and wildlife crossings, and remediation for liquefaction potential, settlement, and landslides.

Volume 2 Section 1 Design Resumes page 41

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Mid-City/Exposition Light Rail Transit, MTA, Los


Angeles to Culver City, CA ($862 million)
Geotechnical Engineer of Record, 2006 2011

This 8.6-mile LRT alignment includes major rehabilitation


and reconstruction of Flower Street bridge over I-110,
modifications of existing retaining walls supporting I-110
and a new tieback retaining wall. A -mile segment of the
LRT is located in a trench structure and four major
overcrossings were constructed to elevate the LRT over
major streets. The geotechnical scope included preparation
of geotechnical design and foundation reports
documenting subsurface and groundwater conditions,
seismic study, pavement design, foundation design, and
construction recommendations for each structure.
Gold Line Eastside Light Rail Extension Design-Build,
LA Metro, Los Angeles, CA ($898M)
Geotechnical Engineer of Record, 2006 2009

This design-build project includes two underground


stations, six at-grade stations, two miles of tunnel, four
miles of at-grade track and roadway improvements, several
traction power stations, and bridge improvements at I-710
and SR-60. A geotechnical planning report outlining the
scope and technical approach of the geotechnical
investigation was prepared and approved by MTA. The
geotechnical study is intended to use sound engineering
and design approach to develop cost-effective and
environmentally acceptable design for the project.
Northbound SR 57 Widening, Orange County ($50M)
Project Manager/Engineer, 2008 2011

This freeway widening project includes widening of two


bridges, tieback walls under four undercrossings, over
mile of retaining walls, and new concrete and asphalt
pavement. The field exploration included 23 borings and
five Cone Penetration Tests (CPTs) to a maximum depth
of 110 feet for the geotechnical study and 35 borings for
the ADL survey. The deliverables included six Foundation
Reports, one Geotechnical Design Reports, one Materials
Report, and one ADL report.

RFP Criteria
Experience in the exploration, analysis,
design and construction of:
Department LRFD methodology for bridge
foundations, earth retaining systems, and
other high facilities
Mid-City/Exposition Light Rail Transit
Northbound SR 57 Widening
Bridge structures and foundations of the
magnitude and type that will be used
Mid-City/Exposition Light Rail Transit
Planning & conducting subsurface
exploration for highway structures and other
facilities
Mid-City/Exposition Light Rail Transit
Northbound SR 57 Widening
Gold Line Eastside Extension
Foothill Transportation Corridor South
Site-specific geologic, seismic, and
geotechnical hazard evaluation
Mid-City/Exposition Light Rail Transit
Northbound SR 57 Widening
Gold Line Eastside Extension
Foothill Transportation Corridor South
Site characterization, including the
development of design soil/rock profiles with
relevant properties for the purpose of
foundation type and size selection, analysis,
design & construction
Mid-City/Exposition Light Rail Transit
Northbound SR 57 Widening
Gold Line Eastside Extension
Foothill Transportation Corridor South
Analysis and design of structure foundations
for static as well as dynamic (seismic)
loading
Mid-City/Exposition Light Rail Transit
Northbound SR 57 Widening
Gold Line Eastside Extension
Foothill Transportation Corridor South
Soil-foundation-structure interaction (SFSI)
analysis
Mid-City/Exposition Light Rail Transit
Northbound SR 57 Widening

SR 91 Widening, Orange County, CA ($75 million)


Project Manager/Engineer, 2008 2010

For this 5-mile widening project, prepared preliminary foundation reports for six bridges along the
alignment that included evaluation of the subsurface conditions at the project site, review of the asbuilt foundation plans, and preliminary geotechnical recommendations for the proposed bridge
widening. Prepared a preliminary pavement structural section design report, conducted aerially
deposited lead (ADL) survey, and performed asbestos and lead-based paint assessment.

Volume 2 Section 1 Design Resumes page 42

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Enrique Farfn, PhD, PE, LEED


GA

Retaining Structures Lead


Profession
Geotechnical Engineer

Experience

Career Summary
Enrique Farfan is a Senior Engineer in the Los Angeles
infrastructure group. Since joining Arup, he has gained
experience in design of deep foundations and retaining
walls. His diverse industry experience includes bridge
design, building design, foundations analysis, structural
design, highway design, mining, hydraulic structures, and
geo-environmental projects. In addition to his consulting
skills, he is experienced in a diverse number of computer
programs including his extensive numerical analysis
capabilities.
Enrique has proved to combine his geotechnical
experience, structural capabilities and diverse computer
skills to develop cost-effective solutions.

13 years

Experience in Proposed Role


6 years

Licenses and Registrations

Registered Professional Engineer: NM


LEED Green Associate

Education

Ph.D Engineering, University of New


Mexico
MSc Engineering, University of New
Mexico
BS Civil Engineering, Military School of
Engineering, La Paz, Bolivia

Design-Build Experience
LAX Central Utility Plant
Jeffrey Energy Center

Relevant Project Experience


California High-Speed Rail, California High Speed Rail Authority, Palmdale to Los Angeles, CA
($13.1 billion)
Senior Geotechnical Engineer, 2009 Present

Senior Geotechnical Engineer for the Los Angeles to Palmdale Section. This section is
approximately 60 miles long through the Soledad Canyon Area and will require bridges, tunnels and
grade separation for roadways. Stations are planned for Burbank, Sylmar and the vicinity of
Palmdale Airport. The completed project will provide intercity travel in California between the
major metropolitan centers of Sacramento, the San Francisco Bay Area, the Central Valley, Los
Angeles, the Inland Empire, Orange County, and San Diego.
Guggenheim Abu Dhabi, Abu Dhabi, UAE (Cost is confidential)
Senior Geotechnical Engineer, 2009 Present

Senior Geotechnical Engineer for this 968,000ft museum located on reclaimed land at the tip of
Saadiyat Island. This museum, designed by Gehry Partners, will house modern and contemporary art
and will contain 140,000ft of exhibition space.
The Red Sea Astrarium, Aqaba, Jordan ($1.5 billion)
Senior Geotechnical Engineer, 2009 Present

Senior Geotechnical Engineer for a 184-acre entertainment resort and theme park in Aqaba. The
Astrariums sustainable features include up to 19% of its electrical demand being generated by
renewable energy systems, all wastewater being treated and recycled onsite, onsite composting and
reuse of food and landscape waste and a water demand reduction of 35% when measured against
other similar developments.
Central Utility Plant, Los Angeles International Airport, Los Angeles, CA ($438 million)
Senior Geotechnical Engineer, 2011 Present

Senior Geotechnical Engineer for a new 20,000-ton, 8-megawatt cogeneration central utility plant at
Los Angeles International Airport (LAX). Arup is the lead design consultant on the Clark/McCarthy

Volume 2 Section 1 Design Resumes page 43

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Joint Venture design-build team. Providing geotechnical design and review input for shallow and
deep foundation systems, performing observation and analysis tasks to promote soil-structure
performance.
Jeffrey Energy Center, Westar Energy, St. Marys, KS
Structural/Geotechnical Engineer, 2007 2008

Structural/Geotechnical Engineer for the renovation project for the Jeffrey Energy Center, located
in St Marys, Kansas, which consists of three generating units capable of delivering 2,250 net MW of
power and is the largest coal-fired plant in Kansas. The main plant site occupies 600 of the 10,500
total acres owned by JEC. Responsible for design and evaluation of retaining walls, pump housing
structures, pump and machine foundations, evaluation of 54-inch-diameter pipe supports, concrete
design and construction supervision.
Stormwater Management Project, Chemical Waste Management, Carlyss, LA
Structural/Geotechnical Engineer, 2008

The CWM Facility, located in Carlyss, Louisiana, treats and disposes of hazardous and nonhazardous waste from industrial clients in secure double-lined landfills. Responsible for the
geotechnical analysis, and design of a retaining wall to extend an existing retaining wall to improve
the site stormwater system.
Snowcat Road Soil Nail and MSE Walls, Vail Resorts Development Company, Vail, CO
Geotechnical Engineer, 2008

Project Geotechnical Engineer assisting in the design of the soil nail wall and MSE wall to support
the construction of a snowcat bypass road at the base of Vail Mountain in Vail, Colorado. The
snowcat bypass road was needed to provide seasonal access for ski slope maintenance.
US 62 over the Black River, NMDOT, Carlsbad, NM
Structural Engineer, 2006

Project Engineer assisting with detail drawings and peer review for the girders design and
abutments. The bridge consists of six 84-foot spans with an overall bridge length of nearly 510 feet,
AASHTO Bulb-T girders, semi-integral abutments, and drilled shaft foundation.
Gallup Bridge Rehabilitation Over 2nd St, NMDOT, Gallup, NM
Structural Engineer, 2006

Project Engineer assisting with detail drawings and peer review for the girder design and abutments.
The bridge consists of approximately 65-foot single span and precast girders.

Volume 2 Section 1 Design Resumes page 44

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

John E. Haertle, P.E., G.E.

MSE Walls and Embankments


Career Summary

Profession
Geotechnical Engineer

Experience
20 years

Mr. Haertles primary responsibilities include the


preparation and review of geotechnical engineering
reports, client communications, and oversight of the
projects scope, schedule, and budget on a wide variety of
projects throughout California. Mr. Haertle also performs
classification and interpretation of the subsurface materials
found at each site, determines the appropriate laboratory
testing program tailored to the specific nature of the
project, and conducts the relevant engineering analysis to
formulate recommendations for design and construction.

Experience in Proposed Role

John has experience with Caltrans bridge projects and


design-build projects involving analysis and evaluation
of CIDH foundations and stability of reinforced
embankments and slopes as both primary project
engineer and QC reviewer.

Mid-City/Exposition LRT
Metro Gold Line Eastside Extension

Relevant Project Experience

14 years

Licenses and Registrations

Registered Professional Engineer: CA


#C48309, #GE2352

Education

B.S., Mining Engineering; University of


Wisconsin, Madison; 1984
M.S., Civil Engineering, University of
Wisconsin, Madison; 1986

Design-Build Experience

Caltrans Experience
SR241 Slope Repair
Metro Gold Line Eastside Extension 3rd
Street Overcrossing
Magic Mountain Parkway/I-5
Improvements to Access Ramps

Mid-City/Exposition Light Rail Transit (LRT) Project, Metropolitan Transit Authority (MTA),
Los Angeles to Culver City, CA ($862 million)
Technical Review, 20062011

The proposed Mid-City/Exposition LRT line extends approximately 8.6 miles from downtown Los
Angeles to Culver City. The proposed rail development is a design-build project sponsored by the
Exposition Metro Line Construction Authority. Leighton Consulting was retained as the
geotechnical consultant for the project by Parsons Transportation Group.
Mid-City/Exposition LRT, MSE Wall Stability, La Cienega and Ballona Creek Overcrossings
Technical/QC Review, 2009

MSE walls were required at each abutment of the proposed overcrossings. Each wall consisted of
pre-cast panels vertically stacked with the retained soil internally reinforced by steel mesh at 2-foot
design intervals. The wall heights ranged from 14 to 29 feet. Global stability analyses were
conducted using the plans prepared by the wall designer to develop the numerical models. Stability
analyses were performed by limit equilibrium techniques using computer software that included the
capability to model the internal reinforcement. Provided technical review of the analysis and report.
Mid-City/Exposition LRT, La Brea Avenue Overcrossing and Aerial Station
Technical/QC Review, 2007

The proposed overcrossing required design of new foundation elements to support the proposed
bridge and evaluation of stability of the associated approach embankments. Geotechnical aspects of
significance for this project included the presence of compressible clays and the stresses associated
with the quantity of fill required for embankment construction; the presence of potentially
liquefiable soils; and the subsurface conditions which resulted in the use of a deep foundation
system. Provided technical review of the analysis and report.

Volume 2 Section 1 Design Resumes page 45

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Mid-City/Exposition LRT, National Boulevard Bridge Replacement at Ballona Creek

Technical/QC Review, 2007

The existing bridge required removal and replacement with a new bridge that was approximately 167
feet long and 78 feet wide. The new bridge consisted of a single span, supported at its eastern and
western ends by an abutment. The foundations for the abutments consisted of 24-inch-diameter
Cast-In-Drilled-Hole (CIDH) piles with a center-to-center spacing of approximately 8 to 11 feet. A
Caltrans Type 1 retaining wall with a maximum wall height of approximately 16 feet was planned
north of the eastern abutment. Typical pile analyses were conducted to provide axial compressive,
tensile and lateral load capacities along with analysis of the global stability of the proposed retaining
wall. Performed technical review of the analyses and geotechnical report.
Mid-City/Exposition LRT, Flower Street/Exposition Boulevard Grade Separation
Technical Review and Analysis, 2006

The grade separation for the proposed rail line was accomplished by a 2,540-foot-long trench
structure that consisted of cast-in-place concrete retaining walls and structural slab in the entry/exit
regions and secant pile retaining structures where excavation was deepest (approx. 28 feet). The
location of this proposed constructionand the proximity to existing structures including Caltrans
retaining walls along Interstate 110, a multi-story office building and parking structure, and smaller
commercial structures along the alignmentrequired the development of a field instrumentation
and monitoring program during construction. The instrumentation was recommended to consist of
settlement control points/monuments and slope inclinometers. Provided engineering analysis,
preparation of report and assisted in preparation of instrumentation plan.
Improvements to Magic Mountain Parkway and Interstate 5 Interchange, Caltrans, Santa
Clarita, Los Angeles County, CA ($60 million)
Project Engineer, 2007

The proposed Retaining Wall Nos. 64 and 90, located continuously along the northbound off-ramp
and Magic Mountain Parkway, were initially planned to be supported by a driven pile foundation
system. Conditions encountered during initial pile driving activities resulted in significant driving
difficulties and termination at depths far short of planned tip elevation. Specific field exploration in
the areas of wall construction was conducted. The results of the exploration indicated a shallow
foundation system was feasible. Recommendations were provided for preparation of the foundation
areas that would allow the use of standard Caltrans wall designs.
Gold Line Eastside Light Rail Extension Design-Build, 3rd Street Overcrossing, LA Metro, Los
Angeles, CA ($898 million)
Project Engineer, 20062009

The Metro Gold Line Eastside Extension (MGLEE) begins at Union Station, passes through
downtown Los Angeles and Boyle Heights, and terminates in East Los Angeles at Pomona and
Atlantic Boulevards. The alignment consists of approximately 4 miles of double-track at-grade
trackwork and nearly 2 miles of underground guideway.
The 3rd Street overcrossing of I-710 consisted of removing the central portion of the existing bridge
along its centerline and the installation of a new concrete box structure for support of new
trackwork. The installation of new track also included the installation of new Cast-In-Drilled-Hole
(CIDH) pile foundations at the abutments and bents to support the additional structural loads. Field
exploration was undertaken and engineering analysis performed to provide recommendations for the
design and construction of the new foundations. The proximity of an existing storm drain also
require special considerations in the design and construction to avoid imposing lateral load
surcharge upon this Los Angeles County facility.

Volume 2 Section 1 Design Resumes page 46

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Anthony Kirby P.E., LEED


Green Associate

Stormwater/Drainage Engineer

Profession
Civil Engineer

Experience
12 years

Experience in Proposed Role

Career Summary

8 years

Anthony Kirby is an Associate in Arups Los Angeles


infrastructure group, responsible for the development and
leadership of the civil engineering team. Since joining
Arup, he has gained experience in design of drainage
systems, general civil works, flood studies and storm water
management systems. He has extensive knowledge in the
design of Best Management Practices (BMPs) associated
with storm water drainage systems and published a paper
on this subject matter for the Institution of Civil
Engineers in 2004.
Prior to joining Arup, Anthony worked for a contractor,
Costain Ltd. Employed as a Graduate Engineer in 1999;
Anthony worked on a variety of projects in water, roads,
structures and building in different roles. He had
responsibility for managing sections of work, coordination
of subcontractors and junior engineers and planning. This
has allowed him to develop good interpersonal, planning
and management skills.
Anthony understands the interrelationships between
design and construction and has a proven track record
in delivering complex multidisciplinary civil engineering
projects.

Relevant Project Experience


LAX Central Utility Plant Replacement, Los Angeles
World Airports, Los Angeles, CA ($438 million)
Lead Civil Engineer, 2011 Present

Licenses and Registrations

Registered Professional Engineer: CA


#C79357.
Chartered Civil Engineer (Institution of
Civil Engineers).
Member of the Chartered Institute of
Water and Environmental Management
(CIWEM)
Member American Society of Civil
Engineers (ASCE)
LEED Green Associate

Education

B.Eng (Hons), University of Salford, UK


(1995 to 1999)

RFP Criteria
Qualifications and certifications related to
development of plans, specifications, reports
and construction related stormwater
requirements in local, state, and federal
provisions.
Yes
California Registered Civil Engineer.
Registered Professional Engineer: CA
#C79357.

Design-Build Experience
LAX Central Utility Plant(2011-present)
Tregaron Flood Alleviation Scheme, UK
(2006-2010)

Caltrans Experience
California High-Speed Rail
LAX Central Utility Plant

Anthony is the lead civil Engineer for Arup on this


Design-Build project, which will replace the existing Central Utility Plant with a more modern and
more efficient facility, including site wide piping network, new maintenance facilities, and a new
thermal energy storage tank. Anthony is responsible for the site storm water quality management,
hydrology, grading, drainage, and utilities for the overall project.
California High-Speed Rail, California High Speed Rail Authority (CHSRA), Palmdale to Los
Angeles Segment, CA ($13.1 billion)
Lead Civil Engineer, 2011 Present

California's electrically-powered high-speed trains will help the state meet ever-growing demands on
its transportation infrastructure. The Palmdale to Los Angeles Segment covers a wide variety of
design coordination between various jurisdictions, including Caltrans. Anthony is a Civil Engineer
on the Joint Venture project, providing a wide variety of design services, including hydrology,
drainage, and storm water quality.

Volume 2 Section 1 Design Resumes page 47

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Guggenheim Abu Dhabi, Saadiyat Island, UAE (Cost is confidential)


Lead Civil Engineer, 2010 Present

Lead Civil Engineer for this 968,000ft museum located on reclaimed land at the tip of Saadiyat
Island. This museum, designed by Gehry Partners in Los Angeles, will house modern and
contemporary art and will contain 140,000 ft of exhibition space. Anthonys responsibilities include
the design of a sustainable storm drainage strategy and coordination of the site-wide utilities
infrastructure.
Qatargas II LNG Terminal, Qatargas, Milford Haven, Wales, UK, ($1.5 billion)
Civil Engineer, 2004 2005

Anthony was responsible for the design of the surface water drainage strategy for the Qatargas II
Liquefied Natural Gas (LNG) Terminal at Milford Haven, UK. The design involved catchment
modelling works and involved utilization of some of the existing drainage systems at the site.
Detention basin modelling was carried out to control flows and bypass the existing skim pond on
the site. Mitigation measures for the control of firewater and the need for complete shutdown of the
system were parameters that had to be built into the design. In March 2004, Anthony co-ordinated
camera survey works of the existing drainage infrastructure and designed the new systems around
the existing ones where possible. The new LNG terminal was opened in 2008 and is now critical to
the UKs energy mix.
The Red Sea Astrarium, Rubicon Group Holdings, Aqaba, Jordan ($1.5 billion)
Lead Civil Engineer, 2011 Present

Lead Civil Engineer for a 184-acre entertainment resort and theme park in Aqaba. The Astrariums
sustainable features include up to 19% of its electrical demand being generated by renewable energy
systems, all wastewater being treated and recycled onsite, onsite composting and reuse of food and
landscape waste and a water demand reduction of 35% when measured against other similar
developments. Anthony is responsible for the design of the site-wide storm water drainage systems,
which utilize a number of BMPs to collect and treat storm water run-off in a sustainable manner.
Tregaron Flood Alleviation Scheme, Environment Agency Wales, Tregaron, Wales, UK, ($5
million)
Design Project Manager, 2006 2010

Anthony was the Arup design Project Manager for this scheme, which gained Environment Agency
approval in April 2007 and was constructed in three separate seasons between 2008 and 2010 . The
scheme comprises river dredging, new flood walls and flood bund construction in an ecologically
sensitive area of West Wales, UK.
Caerphilly Local General Hospital, Designed for Life, Caerphilly, Wales, UK, ($200 million)
Lead Civil Engineer, 2008 2010

Anthony served as Lead Civil Engineer for this new hospital delivered as part of the Designed for
Life Framework in Wales, UK. The project was completed and opened in Autumn 2011. Some of
the key design challenges included the development of a flood alleviation strategy to provide
diversion swales around the site to cater for the 100-year flood event in the adjacent river and
significant discharge limitations leading to the need to provide a significant volume of storm water
retention on the site.

Volume 2 Section 1 Design Resumes page 48

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Paris Borovilos, P.E.


Stormwater Engineer
Career Summary

Civil Engineer

Experience
8 years

Paris Borovilos is a Civil Engineer and part of the Los


Angeles offices infrastructure group. His background is in
land development, and he has worked on a wide variety of
site development projects. Paris has undertaken a number
of responsibilities during the project site development
stage including grading, hydrology, stormwater quality and
management, utilities, and public improvements.
Paris has QSD certification and knowledge in developing
SWPPPs and obtaining permits for stormwater and nonstormwater discharges during the construction phases of a
project, along with post-developed water quality
requirements which generally get regulated under local
jurisdiction. Paris is also a LEED Green Associate and has
general knowledge of sustainable sites.
Paris has experience with the various phases of a
development project. His expertise includes stormwater
quality and management, grading, drainage, hydrology,
and utilities.

Relevant Project Experience


LAX Central Utility Plant, Los Angeles World Airports
(LAWA), Los Angeles, CA ($438 million)
Civil Engineer, 2010 Present

Profession

Experience in Proposed Role


8 years

Licenses and Registrations

Registered Professional Engineer: CA


#C77286

Education

B.S., Civil Engineering; University of


California, Irvine; 2004

RFP Criteria
Qualifications and certifications related to
development of plans, specifications, reports
and construction related stormwater
requirements in local, state, and federal
provisions.
PE, QSD & QSP
California Registered Civil Engineer.
Registered Professional Engineer: CA
License #C77286
Qualified SWPPP Developer in accordance
with Section VII of the CGP 2009-0009DWQ.
Certification #20511
A qualified SWPPP Practitioner in accordance
with Section VII of the CGP 2009-0009DWQ.
Certification #20511

Design-Build Experience

LAX Central Utility Plant


The project will replace the existing Central Utility Plant
with a more modern and more efficient facility, including
Caltrans Experience
site wide piping network, new maintenance facilities, and a California High-Speed Rail
new thermal energy storage tank. Paris Borovilos is the
Civil Engineer of Record and responsible for the site stormwater quality management, hydrology,
grading, drainage, and utilities for the overall project.

California High-Speed Rail, California High Speed Rail Authority (CHSRA), Palmdale to Los
Angeles Segment, CA ($13.1 billion)
Civil Engineer, 2009 Present

California's electrically-powered high-speed trains will help the state meet ever-growing demands on
its transportation infrastructure. The Palmdale to Los Angeles Segment covers a wide variety of
design coordination between various jurisdictions, including Caltrans. Paris Borovilos is a Civil
Engineer on the Joint Venture project, providing a wide variety of design services, including
hydrology, drainage, and storm water quality. Paris has expertise with local and federal requirements
(including Caltrans) for stormwater design and management.

Volume 2 Section 1 Design Resumes page 49

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Volume 2 Section 1 Design Resumes page 50

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Rodolfo Onchi, P.E.

Signalization Engineering Lead


Career Summary

Profession
Civil Engineer

Experience
10 years

As a Traffic Engineer, Mr. Onchi has over 10 years


experience in traffic signal design and development of
major roadway and highway projects. Mr. Onchi has
extensive experience in developing and interpreting
dynamic and complex traffic analysis, operational and
forecasting reports in order to provide a basis of design
for traffic signal requirements. He is also well versed in
stage construction and traffic handling, signing and
pavement delineation, ramp metering and multi-modal
design that infuses bicycle, pedestrian, mass transit, and
vehicular traffic.
Mr. Onchis strengths include geometric design, traffic
signal design, ramp metering, signing plans,
construction detour design, pavement delineation, and
staged construction plan preparation.

Relevant Project Experience


I-580 WB HOV Lane Widening Project, Caltrans,
Livermore/Pleasanton/Dublin, CA ($160 million)
Traffic Engineer, 2006 2011

The project consists of widening of westbound I-580 to


provide an HOV lane and auxiliary lanes within the TriValley area in Alameda County for a distance of 13 miles.
As the traffic engineer on the project, Mr. Onchi worked
in the preparation of the signing, pavement delineation,
and traffic signal plans. In addition, Mr. Onchi worked in
the preparation of the Transportation Management Plan
(TMP) and Lane Closure Report for the project.

Experience in Proposed Role


10 years

Licenses and Registrations

Registered Professional Engineer: CA


#39507

Education

B.S. Civil Engineering, San Jose State


University

Design-Build Experience
San Mateo Route 101 Ramp Metering
SVRT BART Extension

Caltrans Experience

I- 580 WB HOV Lane Widening


SR4 (East) Widening Project
SR 152/SR 156 Interchange
Route 87 Widening
Marin Sonoma Narrows
Route 17 Widening
Highway 101/Mary Avenue
Highway 880/Marina Drive Interchange
SR 4 Crosstown Extension
Route 85/Cottle Road Interchange
Route 85/Great Oaks Boulevard
San Mateo Route 101 Ramp Metering
I-580/Dougherty Road
Highway 880/Davis Street
Route 84/Vallecitos Road
Highway 9 Pedestrian Improvements
Highway 9/Santa Cruz Avenue
Highway 680/Bernal Avenue
I-80/Abernathy Road
Route 237/Main Street
Route 82/Victoria Avenue

SR4 Widening Project Contra Loma Boulevard to G Street, Caltrans, Antioch, CA ($87
million)
Traffic Engineer, 2005 2011

The project consists of widening SR4 from four lanes to an eight-lane facility from west of Contra
Loma Boulevard to east of G Street. Two interchanges at Contra Loma Blvd and G St. were
modified. As the traffic engineer, Mr. Onchi worked in the preparation of traffic operation systems,
signing, pavement delineation, and traffic signal plans. The project required the installation of three
new traffic signal systems and the modification of one traffic signal. Given that the project was
administered by Caltrans and two of the traffic signals were maintained and operated by the City of
Antioch, considerable coordination efforts were required to obtain approval on the signal design
specifications and details. Mr. Onchi also assisted in the preparation of the Transportation
Management Plan (TMP) and Lane Closure Reports for the project, which were extensive given the
numerous detour and freeway and roadway closures required. Additionally, he designed the ramp
metering at the interchanges and the traffic operations system, including the closed-circuit television
monitoring system through the highway corridor.

Volume 2 Section 1 Design Resumes page 51

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Westgate Parkway Extension, City of San Leandro, San Leandro, CA ($4 million)
Traffic Engineer, 2002 2010

The project was a phased project for the new construction of Westgate Parkway, which tied into
Caltrans interchange at I-880/Davis Street (Route 61), and widening of Davis Street. The purpose of
the project was to construct a new roadway connecting Davis Street to Williams Street and
reconfigure the intersection of Westgate Parkway and Timothy Drive. This project also proposed to
reconfigure Westgate Shopping Center parking lot, north of the Wal-Mart parking lot. The existing
arterial suffered from high-volume, impacted, signalized intersections, and only one access point to
the adjoining freeway (I-880). The project also integrated multi-modal interface concepts for
pedestrians and bicycles, while considering parking access points, utility master planning, drainage
requirements, and grading. Mr. Onchi provided the design of three new traffic signals, two modified
traffic systems and a recessed in-pavement pedestrian crossing warning system. The signal
modification and design at Davis Street required Caltrans approval.
Highway 85/Cottle Road/Great Oaks Boulevard, Caltrans, San Jose, CA ($6 million)
Project Engineer, 2008 2011

As part of site redevelopment and rezoning, the interchanges at Highway 85/Cottle Road and
Highway 85/Great Oaks Boulevard were modified. At Highway 85/Great Oaks Boulevard the offramps were modified to add capacity and provide free-flow right turn movement. For the Highway
85/Cottle Road project, the interchange was modified from a diamond interchange to a partial
cloverleaf interchange. The ramps were modified to add capacity and HOV preferential lanes.
Queuing analyses were conducted to substantiate the storage lengths provided by the additional
lanes at the off-ramp. Traffic operations with this improvement resulted in a Level of Service C in
the AM peak hour at the ramp intersections of Highway 85 and Cottle Road and Great Oaks
Boulevard. Mr. Onchi performed the traffic analysis and provided the design for the ramp metering,
Route 85 traffic operations system modifications and two signal modifications.
Dublin Boulevard/Dougherty Road Intersection Project, City of Dublin and Caltrans, Dublin,
CA ($6 million)
Traffic Engineer, 2004 2008

The Dougherty Road Improvements project from I-580 to Houston Place and from Houston Place
to Camps Park Entrance also involved the modification of the Dublin Boulevard/Dougherty Road
intersection and major street widening along Dublin Boulevard and Dougherty Road which tied into
Caltrans I-580 interchange. Dougherty Road was widened from four lanes to eight lanes, with three
left-turn lanes, three through lanes, and two right-turn lanes. The design considered the
incorporation and interface of pedestrians and bicycles. In addition, the project also required three
signal modifications, drainage improvements, utility coordination and relocations, retaining wall
design, and signing and striping. Mr. Onchi was responsible for the design of the traffic signal
systems, ramp metering modifications and temporary signals during construction.
North Connector, Solano County and Caltrans, Dublin, CA ($22 million)
Traffic Engineer, 2007 2010

To address the growing traffic operations and congestions, Solano County and Caltrans proposed
improvements to the existing I-80/I-680/SR12 Interchange. The project consisted of constructing a
4-lane arterial that parallels I-80 from Suisun Valley Creek and connects to the I-80/Abernathy Road
Interchange. Project features included geometric alternatives, pedestrian/bicycle path integration,
roadway profiling, drainage and utility improvements, intersection signalizations, signing and
striping, and stage construction and traffic handling design. Coordination efforts with STA, County
of Solano, City of Fairfield and Caltrans were considerable to ensure continuity with interrelated
construction and staging issues. As the traffic engineer, Mr. Onchi prepared the design of three new
traffic signals and one signal modification. Additionally, he designed the interconnect system and the
signing and striping for the project.

Volume 2 Section 1 Design Resumes page 52

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Jason Edling, IALD

Project Architectural Lighting


Design Lead

Profession
Lighting Consultant

Experience
12 years

Experience in Proposed Role

Career Summary
Jason leads Arups lighting group in San Francisco with a
diverse portfolio of projects across the region and abroad.
His lighting approach and design principals were fostered
in the theater at Schuler Shook (1998) and Auerbach &
Glasow (19992001), both theater lighting and
architectural lighting design firms. He joined Arup in 2001
to better engage clients on a breadth of projects that
allowed for total designthe idea that the built
environment is best designed collaboratively with multidisciplinary teams.
Jason is well versed in Caltrans standards and the lighting
requirements for bridges in North America.
Jasons aim is to inspire design that is both
architecturally and technically integrated. He believes
that bridge lighting solutions should complement and
reveal the structural form of the span with light and
shadow.

Relevant Project Experience


Doyle Drive Replacement, Caltrans and the San
Francisco County Transportation Authority, San
Francisco, CA ($1.1 billion)
Lead Lighting Designer, 2008Present

Doyle Drive connects the Golden Gate Bridge with San


Francisco. The redesigned Presideo Parkway includes
bridges, multiple tunnels, a park and improved views to
San Francisco and the Bay. Arup designed a modern
bespoke luminaire to illuminate the roadways. The fixture
called on the existing historic steel poles used to illuminate
the Golden Gate bridge for inspiration. In addition, Jason
consulted on daylighting vehicular tunnels, light trespass
and light pollution.

9 years

Licenses and Registrations

IALD Professional #00752

Education

BAE, Architectural Engineering, University


of Colorado Boulder, 1999
Instructor at University of California
Berkeley, 2005 and 2006

RFP Criteria
Professional member of the International
Association of Lighting Designers
IALD Professional #00752
Completion of architectural lighting on at
least two major built bridges and at least
two other projects in design or under
construction
Center Street Bridge
Robert I Schroder Bridge
Doyle Drive Replacement
Sacramento International Airport
Experience working with large and diverse
stakeholder groups, including state
departments of transportation, elected
officials, and community organizations
Doyle Drive Replacement
UC Merced Campus & Bridge
Bay Area Rapid Transit Modernization
Sacramento International Airport
California Academy of Sciences

Design-Build Experience
Alaska Airlines Terminal Expansion

Caltrans Experience
Doyle Drive Replacement
Robert I Schroder Bridge (built to
Caltrans standards)
Transbay Cable Stayed Bridge (designed
to Caltrans standards)
UC Merced Bridge

Transbay Cable Stayed Bridge, Transbay Joint Powers


Authority, San Francisco, CA ($40 million)
Lead Lighting Design, 2010Present

The Cable Stayed Bridge will add another signature bridge span to the San Francisco skyline. It will
connect the I-80 freeway to the Transbay Transit Center. Dynamic lighting will respond to the
movements of buses traveling across the bridge by accentuating the form of the structure through
varied light intensities.

Volume 2 Section 1 Design Resumes page 53

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Robert I Schroder Bridge, Contra Costa County, Pleasant Hill, CA ($6.8 million)
Lead Lighting Designer, 20012010

Aesthetic lighting design of an 800ft iconic pedestrian bridge, the center piece of the sustainable
Contra Costa Transit Village. The bridge spans 240ft over Treat Boulevard, an 8-lane roadway. The
pedestrian deck is illuminated by continuous LED lighting that runs the length of the span integral
to the structure. The iconic lighting accentuates the vertical elements that support the bridge and the
underside of the span over the roadway.
Center Street Bridge, Principal Financial, Des Moines, IA (not disclosed)
Lead Lighting Designer, 20072010

In honor of the 125th anniversary, Principal Financial donated the Center Street Bridge to the City of
Des Moines. The bridge spans the Des Moines River were the river is 400ft wide. Continuous LED
lighting integral to the handrail is used to illuminate the deck that serves pedestrians and bicycles.
Color-changing LEDs are located below the glazed walking surface that spans the mid-section of the
bridge.
Coronado Bridge Competition Finalist, Port Authority of San Diego Art Commission, San
Diego, CA (n/a)
Lead Lighting Design, 20092010

Competition finalist with Ned Kahn and Patrick McInerney for illuminating the Coronado Bridge
on behalf of the Public Arts Commission in San Diego (90+ submissions with 3 finalist). The design
solution entailed dynamic lighting that illuminated a bespoke turbine within each bridge support.
The wind activated, and powered, the aesthetic lighting on the bridge via the turbine so that the
intensity of light correlated to available wind, acting like a register.
UC Merced Bridge, Masterplan & Site, University of California, Merced, CA ($160 million)
Lead Lighting Designer, 20012005

Full design services for the campus masterplan, the site and select art installations. The UC Merced
Campus was the first LEED-certified campus. This included a bespoke design for the custom light
fixture developed for the campus vehicular bridge and plazas throughout the campus.
Sacramento International Airport, Sacramento County, Sacramento, CA ($1.0 billion)
Lead Lighting Designer, 20072011

Lighting and daylighting design for a 675,000ft complex, which include a new central terminal and a
19-gate airside concourse. The new Terminal B features 3-story, canted glass curtain walls that offer
a sweeping view of Sacramento and surrounding mountain ranges. Arup was selected to perform
electric lighting and daylighting design for Terminal B and the Concourse.
Alaska Airline Terminal Expansion, Alaska Airlines, Los Angeles, CA ($271 million)
Lead Designer, 2008

Design of Alaska Airlines new LAX facilities, which includes a passenger lounge, central service
counter, and Alaska Airlines Airport of the Future kiosk check-in facilities.
California Academy of Sciences, San Francisco, CA ($480 million)
Lead Lighting Designer, 20042008

Electric lighting design for living exhibits within the new, and refurbished, Steinhardt Aquarium.
The project includes: life support lighting for animals & fish, the Water Planet with undulating
lighting that is indicative of the movement of water, a living penguin exhibit with life support
lighting that dynamically changes to accommodate the diurnal habits of penguins and the living
rainforest exhibitory.

Volume 2 Section 1 Design Resumes page 54

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Gareth Ashley, LEED AP


ITS

Profession
Information and Communications
Technology Consultant
Experience

Career Summary
Gareth has worked in the information technology industry
for over twenty years. He has provided consultancy in the
international transportation sector for most of his
professional career. He meets the challenge of bringing
effective teams together across functional and
organizational boundaries to achieve mutually desired
goals; he thrives on interfacing diverse skills, attitudes and
systems.
Gareth believes that effective communication is a key
element in the success of systems and infrastructure design
and deployment. His ability to communicate at all levels
from board member to contractor/technician has greatly
helped him to achieve the goals of his client
organizations..
Gareth Ashley has dedicated his professional life to
providing solutions at the intersection of technology and
the built environment in the transportation sector.

Relevant Project Experience

20 years

Experience in Proposed Role


10 years

Licenses and Registrations

LEED Accredited Professional


Chartered Manager (CMgr)

Education

University of Kingston, UK, Postgraduate


Diploma in Business Administration, 2003
University of Essex, UK Bachelor of Laws
LLB, 1991
Universt de Paris X, France Droit
Syndicale, 1990

Design-Build Experience
Doyle Drive Replacement Project Utility
Relocation
Channel Tunnel Rail Link
San Francisco International Airport
Terminal 2

Caltrans Experience
Doyle Drive Replacement Project Utility
Relocation

Doyle Drive Replacement Project, Utility Relocation,


San Francisco County Transportation Authority, San Francisco, CA ($1 billion)
ITC Project Manager, 2007 Present

Information Technology and Communications (ITC) Project Manager responsible for managing and
delivering detailed design and construction procurement documents for utility relocations along the
alignment of the proposed complete replacement of South Access to the Golden Gate Bridge. The
utility relocation was an enabling work prior to construction of the replacement infrastructure.
The site was a former military base and included abandoned cable plant in duct banks containing
hazardous materials, the owner had leased access to third party telecommunications providers, and
therefore migration to replacement plant was a key consideration in the design.
Channel Tunnel Rail Link, Rail Link Engineering, London, UK ($7.7 billion)
IT Consultant, 1993-2001

IT Consultant managing the technical and operational information technology requirements of this
5bn project, Overseeing a 2000 user multi-site expanding WAN serving over 30 joint venture
partners, client organizations and contractors; other responsibilities included: system analysis,
planning & implementation; disaster recovery & business continuity planning and network security.
In 2001 the Head Office was relocated. Project management duties included relocation of the main
data center, client PCs, Network equipment and 20+ WAN links between site offices and parent
organizations. Relocation coincided with migration and replacement of many systems and involved
parallel operation of critical systems during transition.

Volume 2 Section 1 Design Resumes page 55

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

San Francisco International Airport T2, T2Partners, San Francisco, CA ($383 million)
Communications Consultant, 2009 2011

Owners Representative acting in a project auditor role. The scope was to represent the interests of
the ITT department to the design-build construction team. Scope of representation included design
review of the passive infrastructure, active wired/wireless network; advising the owner on ITC
procurement and constructability, monitoring progress and reviewing test procedures.
Silicon Valley Berryessa Extension (SVBX), Valley Transit Authority, San Jose, CA, ($2.5
billion)
Security Stations Design Manager, 2005 Present

Security Stations Design Manager responsible for the design and specification of station security
systems for a project to extend BART transit lines to the Silicon Valley area. Systems included
Access Control System; CCTV System, interface design and coordination. Security systems were
designed to be connected back to a local BART Police sub-station and a central control room.
Terminal 3, McCarran International Airport, PGAL, Las Vegas, NV ($2.4 billion)
ITC Project Manager, 2005 Present

Project Management of the team designing ITC systems and infrastructure for the new terminal at
Las Vegas McCarran International Airport. Scope covers Infrastructure design for Premise
Distribution and Distributed Antenna; Systems design of Airport systems including Voice & Data
network, Dynamic Signage/Flight Information Displays and Ramp Services. Other services include
Interface/Integration design and passenger processing consultancy.
Fulton Street Transit Center, New York City Transit Authority, New York, NY ($1 billion)
Communications Project Manager, 2003 2005

Communications Project Manager responsible for the Design, Procurement and Integration of a
number of Network, Wireless, Security and Passenger information systems on this project to create
a subway and intermodal transit hub in lower Manhattan. Passenger information systems include
Help Point Information kiosks, intermodal departure information displays, and information kiosks.
All these systems were linked with New York City Transit control centers and integrated with city,
state and inter-state transport and law enforcement agencies.
Toronto Pearson International Airport Terminal 1, GTAA, Toronto, ON ($5 billion)
Systems Integration Project Manager, 2001-2004

Systems Integration Design at Toronto airport, including proposed systems within New Terminal
One, parking garage and existing systems at older terminals & throughout the Campus. Analysis
included hardware, software, communications and logical & physical interfaces, together with a
process based information flow study, highlighting information required at each stage and how it
could be leveraged to enhance and automate the operations of the airport and generate revenue
streams for the client. Systems involved included: Airport Operations Database, Flight Information
Display Systems, Common Use Passenger Processing Systems, Baggage Handling Systems, Baggage
Tracking and Reconciliation System and Building Management Systems.
JFK Terminal 5, Jetblue, New York, NY ($740 million)
ITC Project Manager, 2002-2004

Managing the ITC design component of construction project to provide a new 23 gate terminal
existing behind landmark terminal. Scope included design of fixed and wireless communication
infrastructure, systems design and systems integration. This project required close project
management, working with architects, other engineering disciplines and client telecommunications
and data teams to complete design of new terminal on an aggressive timescale and with challenging
budgetary constraints

Volume 2 Section 1 Design Resumes page 56

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Genaro Mejia, P.E.

Railroads Engineering
Career Summary

Profession
Civil Engineer

Experience
9 years

Experience in Proposed Role


Genaro Mejia is a Civil Engineer and part of the Los
9 years
Angeles office Infrastructure Group. He specializes in
Licenses and Registrations
engineering design for rail transportation projects
including grade separation, shoofly and rail spur design,
Registered Professional Engineer: CA
high speed rail construction, rail widening, infrastructure
Education
rehabilitation, tunnel construction, station platform design, MS, Civil Engineering Transportation,
roadway and intersection widening and utilities
University of Southern California
coordination.
BS, Civil Engineering Transportation,
University of California Irvine
Genaro is very active within the Southern California
Design-Build Experience
community. He has mentored interns from the Los
California High-Speed Rail
Angeles Department of Public Works summer internship
program. He was a Selection Committee Member of The
Caltrans Experience
East Los Angeles Community Union Scholarship Program SR-74 Ortega Highway Widening, San
in 2007. Genaro has also donated his time as a tutor at the
Juan Capistrano Project
Pio Pico Elementary School in Santa Ana and presented
interactive science based exhibits to grade school children at the Discovery Science Center.

Genaro brings a multidisciplinary approach focusing on engineering solutions but also


understanding the sensitivities of environmental and social impacts

Relevant Project Experience


California High-Speed Rail, California High Speed Rail Authority, Palmdale to Los Angeles
Segment, CA ($13.1 billion)
Alignment Engineer, 2009 Present

Alignment Engineer for the Palmdale to Los Angeles segment of the California high speed rail
project. This section is approximately 60 miles long through the Soledad Canyon area. In this
segment, the high-speed train will reach speeds of over 220 mph, greatly reducing travel times
compared to existing Metrolink commuter service. Genaro is a part of the alignment team working
on the Sylmar to Union Station portion where the alignment passes through dense urban/suburban
areas with residential, commercial and industrial land uses. Constraints include waterways, seismic
faults, historical and cultural resources, existing highway network and existing rail transportation
facilities. He has developed alternatives for proposed station locations planned to be located at
Burbank, Sylmar and in the vicinity of the Palmdale Airport.
Pier A West/Area 2 Interim, Source Removal Action, Long Beach, CA
Alignment Engineer

Civil Design Engineer for a complex remediation project located at Pier A West, an 80-acre site in
the Port of Long Beach. Genaro was responsible for the development of conceptual grading and
drainage systems.
Pier A West/Area 2 Interim, Source Removal Action, Long Beach, CA
Alignment Engineer

Alignment Engineer for 2,800 linear feet of new spur track and earthen bumpers at the terminus at
Pier S. Additional activities, included stockpiling of materials and a truck scale for the measurement

Volume 2 Section 1 Design Resumes page 57

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

of import fill and export material.


San Marcos Inland Rail Trail Phase II, San Marcos, CA
Lead Civil Engineer

Lead Civil Engineer for trail improvements on 2.2 miles of Class 1 multi-use which included
grading, drainage, pavement, lighting, planting, and irrigation, an 85-foot long prefabricated steel
truss bridge, and 2,000 feet of retaining walls at various locations per the NCTD Sprinter Plans.
SR-74 Ortega Highway Widening, San Juan Capistrano, CA
Alignment Engineer

Alignment Engineer for widening of the existing two-lane road to four-lanes, bordered on the north
by steep terrain and on the south by existing residential developments. The design was completed
with Caltrans oversight and adhering to the Caltrans Design Manual.
Miliken Avenue Grade Separation, Ontario, CA
Alignment Engineer

Alignment Engineer for the elevation of railroad tracks above the existing road at Miliken Avenue.
This grade separation is expected to improve circulation on Milliken, improve vehicular safety, and
stream line regional freight movements.
Union Landing Transit Center, Union City, CA
Civil Engineer

Civil Engineer for this nine bus bay depot. The center features transit shelters, drivers rest area,
pedestrian crossings with visual and audible beacons.
Santa Clara Caltrain Transit Center and Parking Expansion, Santa Clara, CA
Lead Civil Engineer

Lead Civil Engineer for the expansion of this transit center located directly across from Santa Clara
University. The center features an additional 50 parking spaces and a redesigned bus platform to
accommodate new larger buses.
Fairfield/ Vacaville Intermodal Station Phase 1, Fairfield, CA
Civil Engineer

Civil Engineer for site improvements of this bus transfer facility, parking for 200 vehicles, and rail
improvements for both passenger and freight rail lines.
Coliseum BART to Bay Trail Connector, Alameda County, CA
Alignment Engineer

Alignment Engineer for this study to implement the Bay Trail and provide regional transportation
connections. This particular segment connects the existing Bay Trail to the Coliseum BART station.
Mary Street Grade Separation, Feasibility Study, Riverside, CA
Alignment Engineer

Alignment Engineer for this study to evaluate grade separation options including a sub-grade
crossing, an above grade crossing or a combination of lowering the road and raising the railroad
tracks. This grade separation is one of several where goods movement is intended to be improved.

Volume 2 Section 1 Design Resumes page 58

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Davis Thresh, PLS


Surveying Manager
Career Summary

Surveyor

Experience
28 years

Mr. Thresh will serve as the Surveying Manager. His


survey experience spans over 28 years. Throughout his
tenure with BKF, he has played a key role in many
projects, for both the public and private sectors. His
responsibility involves project management of all survey
projects including scheduling, budget tracking,
dispatching, supervision of crews, and coordination of the
office and field surveyors. Mr. Thresh has directly
overseen the topographic surveys, construction staking
survey and right-of-way acquisition and mapping for many
of the firm's highway and roadway projects.
Mr. Thresh has overseen topographic and control
surveys, construction staking, and right-of-way mapping
for multiple agencies ranging from cities, counties,
Caltrans, BART, and CalTrain.

Relevant Project Experience


SR 152/SR 156 Interchange Project, Caltrans, Santa
Clara & San Benito Counties, CA ($17 million)
Survey Project Manager, 2000 2003

As the Survey Project Manager for this project, which


converted an at-grade intersection to grade-separated
Trumpet-Style interchange, Mr. Thresh prepared a GPS
Report, obtained Caltrans ABC Mapping approval,
oversaw topographic surveys, and conducted QA/QC
surveying for the construction.
Route 87 Widening Project, Caltrans, San Jose, CA
($90 million)
Survey Manager, 2000 2006

Profession

Experience in Proposed Role


17 years

Licenses and Registrations

Registered Land Surveyor: CA #6868

Education

Surveying, Diablo Valley College, CA

RFP Criteria
At least 15 years experience in the design of
roadway on highway systems:
17 years
Experience in the last 10 years with the
design of roadways in major urban freeway
systems similar in scope and complexity:
I- 580 WB HOV Lane Widening
SR4 (East) Widening Project
Marin Sonoma Narrows
Route 87 Widening
SR 152/SR 156 Interchange
Highway 101 Widening
Highway 101/Hillsdale Interchange
SVRT BART Extension
BART Extension To San Francisco Airport
Licensed as a California Land Surveyor by
the time the Design-Build Contract is
executed:
Licensed Land Surveyor: CA #6868, In
June of 1992.

Design-Build Experience

Sand Hill Road Corridor Project


San Mateo Route 101 Ramp Metering
SVRT BART Extension
BART Extension To San Francisco Airport

Caltrans Experience

I- 580 WB HOV Lane Widening


SR4 (East) Widening Project
Marin Sonoma Narrows
Route 87 Widening
SR 152/SR 156 Interchange
Highway 101 Widening
Highway 101/Hillsdale Interchange
Highway 237/I-880 Improvement

The project primarily consisted of the rehabilitation and


widening of the highway from 4 to 6 lanes. As the
Surveyor Manager, Mr. Davis was responsible for
obtaining a Caltrans encroachment permit to conduct
surveys, preparing a GPS survey report, preparing right-ofway hardcopy mapping, performing a GPS survey,
conducting ongoing settlement monitoring, and confirming monumentation and construction
control.
Highway 101/Hillsdale Interchange, Caltrans San Mateo, CA ($72 million)
Survey Manager, 2000 2004

This project involved a new interchange, collector distributor road, major roadway infrastructure,
local street widening, pedestrian and bicycle facilities, bus terminals within the freeway, and

Volume 2 Section 1 Design Resumes page 59

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

allowances for train station construction interchange modification and local street widening. As the
survey project manager, duties included right-of -way mapping, preparation of appraisal maps and
hard copy maps, record of survey and project control, GPS surveying, monumentation perpetuation,
topographic surveying, and construction staking.
SR4 Widening Project Contra Loma Boulevard to G Street, Caltrans, Antioch, CA ($87
million)
Survey Project Manager, 2005 2011

Survey Project Manager for this major freeway widening from 4 to 8 lanes. The project involved two
interchange reconstructions and construction of a rail corridor within the freeway median, auxiliary
lanes and HOV bypass lanes. Located within the city of Antioch, this project involved local street
improvements and restoration, extensive retaining wall and sound wall design, major utility
relocations. Mr. Thresh oversaw the preparation of the right-of-way hard copies, topographic
surveys, legal description for ROW acquisitions, coordination with Caltrans survey department, and
preconstruction record of survey.
Highway 101 Widening, Caltrans, San Jose and Morgan Hill, CA ($40 million)
Survey Project Manager, 2000 2004

Led the surveying of this 7.5-mile upgrade of Highway 101 from a 4-lane to 8-lane freeway. The
upgrade included three interchange modifications and a HOV connector ramp. Mr. Thresh prepared
and processed the record ROW mapping and oversaw the GPS control and topographic surveying.
An accelerated design and surveying schedule was successfully implemented for the project.
I-580 WB HOV Lane Widening Project, Caltrans, Livermore/Pleasanton/Dublin, CA ($160
million)
Survey Manager, 2006 2011

Survey manger for this major 13-mile HOV widening and roadway rehabilitation project that
included accommodations for future express lanes, connector ramp modifications, auxiliary lanes,
and HOV bypass along 12 interchanges, two interchange modifications, and truck weight scale
modifications. Project involved major construction staging/traffic detour, utility relocations, grading
and drainage design. Surveying included high-definition scanning of payement, GPS control,
deferential level loops, traffic control and topographic surveying.
Silicon Valley Rapid Transit BART Extension, BART, Fremont/Milpitas/San Jose/Santa
Clara, CA ($4.2 billion)
Survey Manager, 2006 2011

As part of the SVRT project, BKF Engineers was retained as a consultant to VTA to provide
preliminary roadway design, utility relocation, topographical survey, agency coordination and project
oversight services for VTAs Silicon Valley Rapid Transit (SVRT) extension from Warm Springs to
San Jose. Design involves 10.5 miles of track along the Line Segment, 4.5 miles of subterranean
track within the Tunnel Segment, 1.3 miles of track along Yards and Shops Segment, six Stations,
and nine grade separations. Mr. Threshs Survey Project Manager role included project oversight and
management, and specifically, coordination with VTA and its design team to provide topographical
survey for design development. Mr. Thresh managed the surveying services along approximately 10
miles of existing railroad lines. He oversaw the setting of secondary survey control to perform
topographic surveys that included: track horizontal alignment and top-of-rail elevations, key points
on rail, surface and overhead utilities within the right-of-way, adjacent canals, creeks and drainage
structures, bridge crossings, and cross sections for railroad design. Working within an active railroad
right-of-way required additional safety training and procedures, with daily coordination with a
railroad flagman.

Volume 2 Section 1 Design Resumes page 60

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Jeff Wang, P.E.

Geometric Engineering,
Signing & Pavement Marking
Engineering

Profession
Civil Engineer

Experience
29 years

Experience in Proposed Role


26 years

Career Summary
Mr. Wang has over 29 years of experience as a
Transportation Engineer and is responsible for the
geometric engineering of highway and roadway design
projects. In addition to developing the geometric designs,
he also is proficient in developing traffic signal, ramp
metering, signing, pavement marking, stage construction,
and construction detour plans. Mr. Wangs experience has
the reputation of optimizing geometric designs, including
highway interchange designs, by meeting the project
operational requirements and minimizing costs.
Mr. Wang has over 25 years of experience in developing
the horizontal and vertical geometric alignments and
signing striping for major highway interchanges in
California.

Relevant Project Experience


I-580 WB HOV Lane Widening Project, Caltrans,
Livermore/Pleasanton/Dublin, CA ($160 million)
Transportation Engineer, 2006 2011

Licenses and Registrations

Registered Professional Engineer: CA


#C57006

Education

B.S., Highway & Traffic Engineering;


Tonji University, Shanghei; 1982
M.S., Civil Engineering; San Jose State
University, San Jose; 1991

Design-Build Experience
Sand Hill Road Corridor Project
San Mateo Route 101 Ramp Metering
SVRT BART Extension

Caltrans Experience

I- 580 WB HOV Lane Widening


SR4 (East) Widening Project
Marin Sonoma Narrows
Route 87 Widening
SR 152/SR 156 Interchange
Route 17 Widening
Highway 101 3rd Ave to Hwy 92
Highway 101/Hillsdale Interchange
Highway 101/University Interchange
Highway 101/Marsh Road Interchange
Highway 101/Mary Avenue
Highway 880/Marina Drive Interchange
Route 280/Eastmoor Avenue
Route 85/Prospect Rd to Stelling Ave
Route 101/Tully Road
SR 4 Crosstown Extension
Route 85/Cottle Road Interchange
Route 85/Great Oaks Boulevard
San Mateo Route 101 Ramp Metering

Geometric designer of major 13-mile HOV widening and


roadway rehabilitation project that includes
accommodation for future express lanes, connector ramp
modifications, auxiliary lanes/HOV bypass along 12
interchanges, two interchange modifications, and truck
weight scale modifications. Developed the signing and
pavement marking plans for the project and supported the
maintenance of traffic by preparing the construction staging and traffic handling plans.

SR 152/SR 156 Interchange, Caltrans, Santa Clara & San Benito Counties, CA ($17 million)
Transportation Engineer, 2000 2003

Mr. Wangs primary role was the geometric designer of this project to modify an existing at-grade
intersection into a new interchange. After designing and evaluating several geometric alternatives,
the interchange was designed with a grade-separated flyover and ramp connectors. The project also
required the development of signing and striping plans and very complex multiple staging plans and
traffic handling considerations. Dual counties, Caltrans (District 4 & 5) and federal coordination was
required.
SR4 Widening Project Contra Loma Boulevard to G Street, Caltrans, Antioch, CA ($87
million)
Transportation Engineer, 2005 2011

Geometrician for the project who also oversaw the signing, pavement delineation and construction

Volume 2 Section 1 Design Resumes page 61

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

staging design. Project scope for this major corridor improvement involved freeway widening from
4 to 8 lanes, two interchange reconstructions, a rail corridor within the freeway median, auxiliary
lanes and HOV bypass lanes. The construction staging and traffic handling required the design of
detours for street, ramp and freeway closures. Located within the city of Antioch, this project
involved local street improvements and restoration, extensive retaining wall and sound wall design,
major utility relocations, ROW acquisitions, and substantial coordination with Caltrans, multiple
jurisdictions, and adjacent designers.
Marin Sonoma Narrows Projects, Caltrans, Marin and Sonoma Counties, CA ($58 million)
Transportation Engineer, 2008 2012

Geometrician for three separate projects along the congested Marina Sonoma Narrows corridor
which is the familiar name given for the Route 101 freeway through Marina and Sonoma Counties.
The geometric design involved the design of a new interchange, the modification of two existing
interchanges and the realignment of the highway for the incorporation of an HOV lane. The staging
and traffic handling was complicated by the reconstruction and raising of an existing bridge over
railroad tracks. Mr. Wang oversaw the staging design as well as the signing and pavement delineation
development. The project required multi-jurisdictional approvals from Caltrans, regulatory agencies,
cities, counties and transit districts.
Route 87 Widening Project, Caltrans, San Jose, CA ($90 million)
Transportation Engineer, 2000 2006

Transportation engineer for this project involving the 5-mile upgrade and widening from 4 to 6
lanes. The project included the addition of HOV bypass lanes at on ramps, the addition of collectordistributor ramp and auxiliary lanes, freeway replacement due to settlement damage to roadway and
structures, and significant storm drainage analysis and improvements. Mr. Wang developed the
geometric design including the complicated integration of the collector-distributor ramps within a
freeway to freeway connector interchange. With project objectives and costs considered, the
geometric designs targeted minimizing the magnitude of the utility relocations and right-of-way
acquisitions. Leading a group of traffic engineers, local traffic, residential, and business impacts were
mitigated through effective stage construction and traffic management plan.
Highway 101/Hillsdale Interchange, Caltrans San Mateo, CA ($72 million)
Transportation Engineer, 2000 2004

This multiple phased project involved modifying an existing interchange, collector distributor road,
major roadway infrastructure, local street widening, pedestrian and bicycle facilities, bus terminals
within the freeway, and allowances for train station construction. Mr. Wang participated in the
phasing of the project and developed the staging, construction signage and traffic handling plans
including detours for the interchange project. He was the primary geometric designer, which
required adjustments throughout the development process to mitigate construction staging
complexities. Design also included new and modified traffic signals for 3 intersections, ramp
metering installation, incorporation of bicycle facilities, right of way acquisitions and utility
relocations.
Highway 101 Widening, Caltrans, San Jose and Morgan Hill, CA ($40 million)
Transportation Engineer, 2000 2004

Developed the geometric design of the 7.5-mile upgrade of Highway 101 from 4-lane to 8-lane
freeway, modification of three interchanges and inclusion of an HOV connector ramp. As near-term
future phases of work would modify the corridor, the geometry was developed for the ultimate
future alignments in addition to the interim condition to facilitate the future design work. An
accelerated design schedule was successfully implemented.

Volume 2 Section 1 Design Resumes page 62

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Anthony Gschwend, P.E., T.E.

Traffic Control Manager


Career Summary

Profession
Traffic Control Engineer

Experience
41 years

Mr. Gschwend is a professional civil engineer and traffic


engineer. His experience includes traffic impact studies,
computerized traffic analyses, preparation of grade
separation and interchange design, final roadway
improvements, traffic signal design, the development of
traffic management concepts and design for construction
including preparation of stage construction and traffic
handling plans, parking studies and designs, master plans,
land use plans, entitlements, improvement plans for
complex transportation and highway projects. He has
successfully negotiated agreements with agencies including
Corps of Engineers, EPA, Regional Water Quality Control
Board, California Department of Fish and Game, USFWS,
and CIWMB.
Mr. Gschwend has extensive experience in traffic
engineering, civil engineering, and construction support
on many public and private infrastructure projects
including major freeway widenings and interchanges in
urban locations.

Relevant Project Experience


Bay Meadows Development, Paine Webber Realty
Group, San Mateo, CA ($200 million)
Project Manager, 1998 2004

Experience in Proposed Role


38 years

Licenses and Registrations

Registered Professional Engineer: CA


#21552
Professional Traffic Engineer: CA #52

Education

B.S., Civil Engineering, University of


California, Berkeley
M.S., Civil Engineering, Institute of
Transportation and Traffic Engineering,
University of California, Berkeley

RFP Criteria
The Traffic Control Manager shall be a
licensed California Professional Engineer and
a licensed California Traffic Engineer with no
less than 10 years experience.
Registered Professional Engineer: CA
#21552
Professional Traffic Engineer: CA #52
38 years experience
The Traffic Control Manager shall have prior
experience managing similarly complex
projects.
Bay Meadows Development (including Rt
101/Hillsdale Interchange
Rt 101/Marsh Rd
Howard and Brittan Ave Grade
Separations
Redwood Shores Development
Jefferson Avenue Underpass

Led the daily design operations and implementation of this


design-build 90-acre site development project that
Design-Build Experience
included the design and construction of a roadway
Sandhill Road Corridor Project
network and infrastructure for 153 single-family residential
Bay Meadows Development
units, 575 luxury apartment/condominium and live/work
Caltrans Experience
units, 350-room hotel site, supermarket and retail shops,
residential and commercial site grading and improvements Rt 101/Hillsdale Interchange
Rt 101/Brittan Avenue
and modifications to existing transportation improvements
Rt 280/ Eastmoor Ave
including local streets, a state expressway, a Caltrain
Rt 85 Prospect Rd to Stelling Ave
station and a highway interchange. Mr. Gschwend was
Rt 101/Marsh Road
responsible for and embedded in the existing and
proposed traffic operations and maintenance. He oversaw the design of stage construction and
traffic handling of the multi-phased project which was broken out to 16 phases of construction.
Successfully established cooperative agreement/EIR compliance, wetlands mitigation, and JPB and
Caltrans coordination and permitting.
Highway 101 / Hillsdale Widening and Interchange Modifications, Caltrans, San Mateo, CA
($15million)
Traffic Control Manager, 2000 2004

As part of the Bay Meadows Development mitigation requirements, the Highway 10/Hillsdale

Volume 2 Section 1 Design Resumes page 63

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

interchange was modified to improve operations and capacity and provide the inclusion of a
collector distributor road and bus terminals within the freeway. Additionally, the project included
major roadway infrastructure improvements, local street widening and the incorporation of
pedestrian and bicycle facilities. Mr. Gschwend was responsible for the phasing of the project and
developed the staging, construction signage and traffic handling plans, including detours for the
interchange project.
Jefferson Avenue Underpass, City of Redwood City, Redwood City, CA ($7.5 million)
Traffic Control Manager, 1994 2000

Led the traffic maintenance design and implementation for this project involving the reconstruction
of an at-grade railroad crossing in the historic downtown district of Redwood City to an underpass.
This highly visible project, due to its proximity to the downtown, the new Redwood City Hall and
the Sequoia Train Station, required the lowering of Jefferson Avenue to accommodate the vertical
clearances required for the railroad crossing. One of the most significant aspects of the design was
to minimize impacts to the users with effective stage construction and traffic handling plans and the
incorporation of a railroad shoofly. The multi-jurisdictional approval of the stage construction and
detours consisted of the City of Redwood City, Caltrain and Caltrans whose expressway was affected
by the construction.
Redwood Shores Planned Development, Redwood Shores Property, Redwood City, CA ($260
million)
Traffic Manager, 1977 2003

This large development project consisted of constructing a 1,400-acre master planned community in
a challenging geotechnical area in the City of Redwood City. BKF was involved with all facets of the
project including the planning, entitlement, environmental clearance, design and construction
phases. As the traffic manager of the project, Mr. Gschwend oversaw the development of the
provisions for the roadway requirements and subsequently was responsible for the roadway, traffic
signal, signing, striping and stage construction design including the development of traffic handling
plans and detours.
Howard and Brittan Avenue Grade Separations, City of San Carlos, San Carlos, CA ($11
million)
Traffic Manager, 1988 1995

The project required the engineering design, surveying, construction administration and inspection
for this dual heavy-rail grade separation project at Howard Avenue and Brittan Avenue. The design
included two bridge deck structures for the railroad shoofly, two twin box culverts, and one single
box culvert beneath the new railroad tracks. BKFs innovative design involved constructing this
culvert between the Caltrain track, the new shoofly, and vehicular crossing. Leading the effort on the
traffic maintenance design, Mr. Gschwend developed the stage construction and traffic handling
design with detours and temporary sign modifications, which balanced the impacts of reconstructing
two arterials within the same project.
Highway 101/Marsh Road Interchange, Caltrans, Menlo Park, CA ($10 million)
Traffic Manager, 1993 1994

Highway 101/ Marsh Road interchange was reconstructed to improve operation, efficiency and
capacity. As part of the reconstruction, the existing overcrossing was reconstructed and raised to
provide standard Caltrans vertical clearance over the freeway. Marsh Road, a very congested arterial
thats a freeway-to-freeway connector between Route 84 and Highway 101 and is the entrance to
Menlo Park, was widened and realigned. Mr. Gschwend was responsible for the development of the
signing and striping design, traffic signalization design and the complicated stage construction,
which required the realignment of ramps and frontage roads, detours and accommodations for bus
stops, pedestrians and bicyclists.

Volume 2 Section 1 Design Resumes page 64

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Keith Brownlie, RIBA RIAS


FRSA
Project Bridge Architectural
Designer

Profession
Architect

Experience
23 years

Experience in Proposed Role


17 years

Career Summary

Licenses and Registrations

Keith Brownlie is a Registered Chartered Architect with


comprehensive knowledge and experience of major
infrastructure and engineering projects including design
for transportation, bridges and public realm.
Major project experience includes High Speed 1, The
Channel Tunnel Rail Link in the UK, the Metsovitikos
Crossing in Greece, the Sutong Crossing in China, Tappan
Zee corridor and bridge in the US, and the Westgate
Bridge retrofit in Australia. He was Project Director for
the Gateshead Millennium Bridge and Architectural
Director for the design of the 1,443-foot-high Guangzhou
International Finance Centre in China. His bridge design
experience spans 17 years from 1994 starting with the
South Quay Footbridge in London Docklands. Projects
with which he has been involved have received the highest
international architecture and engineering awards,
including the RIBA Stirling Prize in the UK, The Arthur
G Hayden Medal in the US and the Balthasar Nuemann
Prize in Germany.
Keith operates as an independent consultant to
engineers and clients on significant bridge projects. His
experience covers some of the worlds largest bridge
and infrastructure projects.

Registered Professional Architect UK ARB


RIBA

Education

BA Architecture, University of Brighton ,


1986. DiplArch, University of Glasgow,
1989

RFP Criteria
A minimum of 15 years of experience as a
bridge architectural designer
17 years
Experience as lead architectural designer,
having collaborated with bridge engineers on
at least 3 major bridge projects of
comparable scale, prominence, and
complexity
Tappan Zee Bridge, NY
Metsovitikos Crossing, Greece
Channel Tunnel Rail Link, UK
3 project examples that convey proficiency in
bridge architectural design. Client reference
required from each project example
including: name, title, project role, address,
phone number, and email address
Tappan Zee Bridge, NY
Gateshead Millennium Bridge, UK
Fehmarn Fixed Link, Denmark

Design-Build Experience

Peace Bridge, Londonderry, UK


Keith graduated from Brighton School of Architecture
Caltrans Experience
and The Mackintosh School of Architecture at the
Glasgow School of Art/Glasgow University. He is a
SFOBB East Span
member of the International Association of Bridge
Engineers (IABSE), and serves on the Design Review Panel of Architecture + Design Scotland
(A+DS) for the peer review of nationally significant projects.

Relevant Project Experience


Tappan Zee Bridge, NYSDOT/NYSTA, New York, NY ($5billion)
Architectural Lead, 2005 Present

Mark Roche
Arup
Highways Business
77 Water Street
Leader, Americas Region New York
t +212 896 3000
e. Mark.Roche@arup.com NY 10005 USA

Volume 2 Section 1 Design Resumes page 65

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

The existing Tappan Zee Bridge spans the Hudson River at its widest stretch between Westchester
and Rockland counties. Maintenance issues and capacity limitations on the 16,000ft bridge gave rise
to the Tappan Zee Bridge/I-287 Corridor Project, and the subsequent current Tappan Zee Hudson
River Crossing Project. Keith was Architectural Lead to the Structures component of the initial
corridor modal study, and acts as a consultant for the subsequent river crossing project.
Gateshead Millennium Bridge, Gateshead Council, Gateshead, UK ($34 million)
Lead Architect Lead/PM, 1997 2001

Steve Richards, Engineering Manager, Transport Strategy


Gateshead Council Civic Centre
t: +44 (0)191 4333091
Gateshead, NE8 1HH
e: steverichards@gateshead.gov.uk
United Kingdom
393-ft-long pedestrian and cyclist bridge crossing the River Tyne between Gateshead and Newcastle.
The bridge features a signature opening mechanism which hydraulically tilts the supporting arch and
curved deck through 40 degrees to provide an 82-ft-high double arched portal for the passage of
shipping. Commissioned through design competition and procured through a partnering contract
with Client, Contractor Engineer and Architect acting jointly as Project Manager. Keith acted as
Architect Lead/PM for the duration of the project. Winner of the 2002 RIBA Stirling Prize for
Architecture, IstructE Supreme Award and many others.
Fehmarnbelt Fixed Link, Femern A/S, Fehmarn Sund, Denmark ($6.35 billion)
Lead Architect, 2008 2011

Kim Smedegaard Andersen, Design Manager, Tunnel


Femern A/S
t: +45 (33) 41 63 00
Vester Sgade 10
e: ksa@femern.dk
DK-1601 Copenhagen V
The Fehmarnbelt Fixed Link will connect the German island of Fehmarn and the Danish island of
Lolland across the Fehmarn Strait at the mouth of the Baltic Sea. The Danish government
commissioned both detailed bridge and tunnel designs. In late 2010, the tunnel option replaced the
bridge as preferred solution and was subsequently adopted for construction. The tunnel will be an
11-mile immersed tube construction, the worlds longest, with twin 2+1 highway compartments and
a double-track railway. Keith Brownlie was Architectural Lead in support of the engineering
consortium.
High Speed 1 (Channel Tunnel Rail Link), HS1Ltd, UK ($9 billion)
Lead Architect, Structures, 2000 2007

HS1 follows a route between London and the Channel Tunnel in Kent as the first operational high
speed line in the UK. The project was designed and constructed in 2 parts: the 43-mile Section 1
from the tunnel which opened in 2003, and the 24-mile western Section 2 to London which opened
in 2007. The route contains multiple structures including 117 bridges which were designed by RLE
with visual design consultancy from Wilkinson Eyre. The project employs common detailing to
brand the railway through its structures asset and includes a number of significant bespoke bridges.
Keith Brownlie was Architectural Lead for both Sections.
Metsovitikos Crossing, Egnatia Odos AE, Greece ($50 million)
Lead Architect, 1998 2000

The Metsovitikos Crossing carries Egnatia Odos, the Greek section of Euroroute E90 through an
area of outstanding natural beauty in the Pindos Mountains. The structure takes a 426-foot-high
vertical alignment over the Metsovitikos river valley between two bored tunnel sections. The design
for a tower-less suspension structure was won in international competition and developed to full
tender tender design. The design features a twin deck 2+1 arrangement spanning 1,837 feet between
portals, supported from a pair of catenary cables anchored on the valley sides. Keith Brownlie acted
as Lead Architect.

Volume 2 Section 1 Design Resumes page 66

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Florence Lam, CEng MIET


MCIBSE, MSLL

Project Architectural Lighting


Designer

Profession
Lighting Consultant

Experience
22 years

Experience in Proposed Role


22 years

Career Summary

Licenses and Registrations

Florence Lam is a Director of Ove Arup & Partners Ltd


and leads our global lighting design practice. She has been
responsible on a wide range of creative and well-executed
interior and exterior projects in the UK, Europe, the US
and the Far East.
Florence has a strong interest in visual light art as a
lighting designer and has worked with a number of artists/
architects in creating public art installation integrated with
light.
She has co-authored in a publication of the RIBA
Technical Review series on Lighting and a book called
Space Craft on Developments in the Architectural
Computing.
Florence believes in Total Architecture solution, in
combining lighting creativity with the highlyskilled
expertise of Arups engineers and environmental
specialists. Architectural lighting has made leaps and
bounds in recent decades and bridge lighting is no
exception. Capitalising on the advancements in
technology, she uses light on bridges to explore
lightness and mass, sculpture and scale. Through a
number of recent projects, as a global design firm, she
has demonstrated how lighting can add a sense of
magic to bridges and inviting people to return to
encounter a different, yet fascinating, experience after
dark.

Relevant Project Experience


Cross Bay Link, Hong Kong Civil Engineering and
Development Department, Hong Kong, China

CEng, Reg no:411583


MIET, Reg no:24735873
MCIBSE, Reg no: 9723
MSLL, Reg no: 9723
Lighting Diploma (Jan 2002)

Education

Bachelor of Art (Cantab)


Master of Art (Cantab)
Master of Science in Architecture: Light
and Lighting

RFP Criteria
Professional member of the International
Association of Lighting Designers
No, but hold equivalent professional
qualification
See Jason Edling resume (Lead
Architectural Lighting Designer)
Completion of architectural lighting on at
least two major built bridges and at least
two other projects in design or under
construction
Stonecutters Bridge, Hong Kong
London Millennium Bridge, UK
Forth Replacemnt Crossing, UK
Cross Bay Link, Hong Kong
Experience working with large and diverse
stakeholder groups, including state
departments of transportation, elected
officials, and community organizations
London Olympic projects
Rail projects: Kings Cross, Crossrail
All of the above bridge projects

Design-Build Experience

All London Olympic projects


Baku International Airport

Lead architectural lighting designer, 2011 Present

The Cross Bay Link is a road bridge connection comprises 1.1 miles of dual two-lane carriageways
on a viaduct, mainly in the sea. This will be the first long-span bridge in Hong Kong to include both
cycle track and footpath. It is proposed that the feature lighting scheme would be aesthetically
pleasing for both viewing perspectives: for the remote onlookers around the bay looking at the
bridge from the outside, as well as drivers and pedestrians crossing the bridge that experience the
bridge from the deck. To cater for both, the scheme incorporates lighting principles that will allow
for the outer faces of the arches to be lit up, as well as for the faces visible from within to be
illuminated.

Volume 2 Section 1 Design Resumes page 67

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Forth Replacement Crossing, Transport Scotland, Scotland, UK

Lead architectural lighting designer, 2008 Present


The Forth replacement crossing, the worlds longest 3-tower cable stayed bridge, is being built across
the Firth of Forth in Scotland. The project aims to provide a fitting twenty-first century icon standing
alongside existing nineteenth and twentieth century grade A listed bridges. Construction commenced
in 2011 and the bridge is expected to be completed in 2016. The main lighting theme is the Line: the
bridge will appear at night as a continuous line of light floating on the water. The vertical elements will
be lit carefully to accentuate this effect and avoid visual clutter. There will be a gentle accent effect on
the towers, above and below the bridge deck.

Stonecutters Bridge, Hong Kong Highway Department, Hong Kong, China


Lead architectural lighting designer, 2001 2009

Cable stayed bridge with two single pole towers 951 feet high and a twin aerodynamic deck. The
bridge is 5,235 feet long and has a 3,339-foot-long main span. The simple yet elegant lines of this
bridge are picked out with crisp cool white light to reinforce their beauty and the simplicity of the
bridge structure against the backdrop of the local golden night sky. The lighting scheme is based
around three key architectural elements: the tower beacons and light strips; the tower pylons and the
cross-girders.
Millennium Bridge, London Borough of Southwark, London, United Kingdom
Lead architectural lighting designer, 1997 2000

New 1,066-foot-long, 13.1-foot-wide steel footbridge over the River Thames between St Pauls steps
and the Tate Modern at Bankside. The Blade of Light design has been developed in close
collaboration with Foster & Partners and Claude Engle. Light pipe technology has been used to
create a perception of a blade of Arctic white light across the river, with the edge of the 4 metrewide bridge deck lit at low level along its length. This edge lighting, achieved using light pipe
technology, allows easy maintenance, illuminates the deck, uplights the handrail and allows
pedestrians on the bridge to be well-lit.

Volume 2 Section 1 Design Resumes page 68

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Jeff Hutchins, LATC


Landscape Architect,
Principal

Profession
Landscape Architecture

Experience
24 years

Experience in Proposed Role

Career Summary
Jeff Hutchins has led the design and implementation of a
variety of large-scale public projects ranging from
comprehensive master planning to design for individual
urban park sites, responsible for project management,
production of contract documents, irrigation design and
construction administration services. In his role as
Principal, Mr. Hutchins manages quality control and
technical review of construction documents produced inhouse.
Mr. Hutchins has served as a city landscape architect for
the cities of San Dimas, San Gabriel, La Verne, West
Covina, and Azusa, providing design review, plan check
services, ordinance writing, and advisory services for tree
protection programs, street tree programs and
maintenance guidelines. Mr. Hutchins is committed to
sustainable planning and applying sustainable principles to
project design.

19 years

Licenses and Registrations

Licensed Landscape Architect:


CA #3815
Certified Landscape Irrigation Auditor:
#7920

Education

B.S., Landscape Architecture; California


State Polytechnic University, Pomona;
1990

Caltrans Experience

101 Hollywood Freeway Ramps


Environmental Enhancement, Los
Angeles, CA
Foothill Boulevard, Upland, CA
Caltrans Slopes, San Dimas, CA
Caltrans Foothill Boulevard, Median
Design, La Verne, CA

Jeff Hutchins is recognized amongst his peers for his collaboration with clients and contractors
to implement award-winning, sustainable and inspiring projects to last for generations.

Relevant Project Experience


Water +Life Museums, City of Hemet, / Riverside County, CA (Phase 1 $4 million, $34 million
total)
Project Manager, 2005-2007

The first LEED Platnium museums in the world, two museums are located at the base of the
Diamond Valley Reservoir Dam in Southern California: The Western Center for Archaeology and
Paleontology exhibits the artifacts uncovered by the recent reservoir construction and houses a
regionally significant research facility, and The Water Education Center illustrates the history of
water infrastructure in California. This primarily arid campus was designed as an immersive
environmental learning experience. Interpretive exhibits showcase historic water uses, current stateof-the-art conservation techniques and sustainable landscape practices. The arrival procession
introduces the principal qualities of water and illustrates the importance of irrigation and agriculture
in the history of water infrastructure and use in California. Additional components of the outdoor
learning exhibits include: archaeological digs, Paleolithic habitats, industrial water uses, cultural water
uses, water conservation and local Native American settlement. The stories of water and life are
woven into the interpretive exhibits that express the importance of water from ancient times to the
present day and the responsibility we have for the future conservation of water. Mr. Hutchins
administrated construction focusing on hardscape, planting and irrigation system installation. Mr.
Hutchins collaborated with the contractor on budget and schedule management, providing input on
cost-saving design decisions during construction. Mr. Hutchins involvement led to the delivery of
the hardscape and landscape scope on time and on budget.

Volume 2 Section 1 Design Resumes page 69

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Vista Hermosa Natural Park, Mountains Recreation and Conservation Authority, Santa
Monica Mountains Conservancy, Los Angeles Unified School District, Los Angeles/Los
Angeles County, CA ($12 million)
Construction Administrator, 2007-2008

Mia Lehrer + Associates worked closely with multiple stakeholders including the Santa Monica
Mountains Conservancy, Mountains Recreation and Conservation Authority, the Los Angeles
Unified School District, City of Los Angeles officials and community members to create an oasis of
nature in a heavily populated area in Downtown Los Angeles. The 9-acre park incorporates active
recreation including a modern, stadium-sized synthetic turf soccer field, trails, grotto, a childrens
adventure area and picnic areas in native habitat landscapes. The park is an urban watershed
demonstration project that accommodates community and school recreational programs integrated
with an extensive network of introduced natural features, ecosystems and sustainable technologies.
Mr. Hutchins led the approval and permitting of construction documents through multiple public
agencies including DSA, LAUSD and MRCA. Mr. Hutchins managed bidding and administrated
construction. Mr. Hustchins efforts led to the successful implementation of the first new public
park in the City of Los Angeles in 100 years.
Los Angeles Zoo Parking Lot, Los Angeles Zoo, Los Angeles/Los Angeles County, CA (approx.
$2 million)
Project Manager, 2010

ML+A redesigned the existing parking lot at the Los Angeles Zoo as a Proposition O Sustainable
Project, a demonstration project to educate the general public about sustainable stormwater
treatment and management. The scope of work includes: preserving an existing perimeter bioswale,
adding new bioswales to the parking lot, retrofitting the parking lot with permeable paving systems,
planting over one hundred new trees and drought-tolerant plant material, and use of reclaimed water
for irrigation. Included in the project are ML+A-designed interpretive graphics that communicate
the benefits of these stormwater management improvements to visitors. Mr. Hutchins served as the
lead designer and administrated construction for the planting and irrigation scope, delivering the
project on time and on budget. The project is the result of a close collaboration with the civil
engineer in design of stormwater management best management practices.
Lemon Creek Restoration, City of Walnut/Los Angeles County, CA ($0.5 million)
Project Manager, 2008 Present

Lemon Creek is a prime example of a channelized urban stream. To the north and to the south of
the project site, the stream has been confined to a concrete channel. Within the site, the stream has
been restricted to a man-made path with a soft bottom and sides. ML+A created a plan that
beautifies, educates, and employs sustainability strategies on the site. Minor grading was utilized to
enable access to the water and relax steep slopes. Local native plant material was introduced to both
stabilize the slopes and beautify the site. Trails that lead to wayside educational display stations
containing descriptions of the history of the site were planned. Mr. Hutchins served as the lead
designer of the project, focusing on trails, planting, irrigation, and grading. He also led consultant
coordination, especially with the civil engineer. Mr. Hutchins led the permitting effort, coordination
with the U.S. Department of Fish and Game and U.S. Army Corps of Engineers and served as the
client interface. Today, Lemon Creek is a treasured natural amenity in the City of Walnut.

Volume 2 Section 1 Design Resumes page 70

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Jan Dyer, LATC

Visual Quality Graphic Support


Team Lead,
Principal

Profession
Landscape Architecture

Experience
20 years

Experience in Proposed Role


8 years

Career Summary
Jan Dyer has led project teams on the design and
implementation of mobility planning, infrastructure, park
master planning and higher education projects, responsible
for managing project design through construction
administration. Ms. Dyer applies creative leadership in
sustainable design to all phases of projects and has
facilitated numerous community outreach meetings for the
firm. Ms. Dyer often leads the design and production of
full-color, three-dimensional, computer-generated
visualizations for presentation and approval to clients,
public agency officials and the general public. Ms. Dyer
presently serves as the Project Manager for many LACCD
projects including three currently under construction at
Mission College in Sylmar.
Jan Dyer has led the planning, community outreach and
implementation of award-winning projects throughout
Southern California.

Relevant Project Experience


East Los Angeles Transit Oriented District Specific
Plan, County of Los Angeles Department of Regional
Planning, Los Angeles / Los Angeles County, CA ($121
million)
Project Manager, 2008 2011

Licenses and Registrations

Registered Landscape Architect:


CA #5623

Education

Certificate of Landscape Architecture;


University of California at Los Angeles,
Extension, Los Angeles; 2006

RFP Criteria
Shall have at least five years of experience
providing drawings (e.g., plans, elevations
and sections), manually drawn renderings,
and 3D and 4D full-color computer
generated visualizations to depict conceptual
and detailed design solutions to visual
quality elements
Jan has eight years of experience
directing graphics support teams in
providing drawings (e.g. plans,
elevations, sections), manually drawn
renderings, and 3-D full-color computergenerated visualizations to depict
conceptual and detailed design solutions
to visual quality elements.

Design-Build Experience

Los Angeles Mission College Student


Services, Sylmar, CA
Los Angeles Mission College East
Campus, Sylmar, CA
Santa Monica Civic Auditorium, Santa
Monica, CA

Transforming a 2.5 mile stretch of Third Street in East


Los Angeles through the use of form-based code, the East LA Transit Oriented District Specific
Plan creates an integrated set of standards for re-development and streetscape improvements. This
transformative plan guides development along the MTA Gold Line alignment with an innovative
urban design that integrates all forms of transportation into the neighborhood. Ms. Dyer was
responsible for managing project design, consultant coordination and the production of full-color
computer-generated visualizations, including plans, elevations, sections, and perspectives. Successful
design solutions for a complex transit project were presented to the client for review and approval.
PiggyBack Yard Intermodal Facility Conceptual Master Plan, Friends of the Los Angeles
River, Los Angeles/Los Angeles, CA (projected: $400 million)
Project Manager, 2010 Present

The Union Pacific-owned PiggyBack Yard intermodal facility is the largest contiguous property in
Downtown Los Angeles. The PiggyBack Yard Conceptual Master Plan is the result of collaboration
between a multi-disciplinary consultant team working pro bono to propose a visionary solution to
the challenges and opportunities posed by this important site. This ambitious plan for urban
revitalization maintains the existing use as a container transfer facility while transforming a sea of

Volume 2 Section 1 Design Resumes page 71

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

asphalt into an efficient transportation center including mixed use development, connections to
public transit, an engineered naturalized 45-acre rehabilitated wetland, and stormwater detention
basins, creating 125 acres of open space. Ms. Dyer was responsible for open space design, consultant
coordination, and graphics production. The full-color, computer-generated project visualizations,
including 3-D aerial perspectives, vignette perspectives, plans, elevations, and sections were used to
promote the potential for alternate land uses of this site to elected officials and to the general public.
Compton Creek Earthen Bottom Feasibility Study, Los Angeles and San Gabriel Rivers
Watershed Council, Compton/Los Angeles County, CA ($15 million)
Project Manager, 2008 2010

Set within a 42.1 square mile sub-watershed, Compton Creek is a tributary to the Los Angeles River.
The Compton Creek Earthen Bottom Feasibility Study is the result of a one-year effort by ML+A,
the city of Compton, and the Rivers and Mountains Conservancy for the redevelopment of the citys
existing flood control channel and adjacent land into a safe, ecologically beneficial, multi-use, public
greenway. Ms. Dyer was responsible for the production of the Feasibility Study including design and
production of visualizations, including full-color, computer-generated diagrams, plans, sections,
elevations and 3-D perspectives. Graphic visualization materials were utilized to present design
opportunities and constraints (as determined by a scientific team analyzing concrete removal) for
presentation to the client.
Pacoima Greenway Vision Plan, Los Angeles County, Los Angeles / Los Angeles County, CA
($20 million)
Project Manager, 2009 2011

The Pacoima Greenway Vision Plan was prepared to engender ideas and community-based action
for the creation of new recreational amenities and a multi-use path along the length of the Pacoima
Wash through the communities of Sylmar and Pacoima. The plan recognizes that a multi-benefit
approach can achieve a variety of goals, including improvements in public health, recreation, wildlife
habitat, water quality, transportation, and community building. This approach creates a cohesive
vision that identifies, preserves, and enhances the areas unique historic and ecological character. Ms.
Dyer managed the production of the design and full-color, computer-generated visualizations for the
Vision Plan document, including plans, sections, and 3-D perspectives. Visualizations of
improvements along and within the Pacoima Wash that aided in consensus building amongst
community members and political support amongst local elected officials.

Volume 2 Section 1 Design Resumes page 72

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Donald Phillips

Technical Steering TeamDesign


Management

Profession

Licenses and Registrations

Career Summary
Mr. Phillips currently holds the senior management and
engineering positions on a number of major projects:
Tappan Zee Bridge, Lake Mead Intake # 3, A30 P3
Highway project, and the California High Speed. Mr.
Phillips also acts as a reviewer and provides support and
expert advice on major infrastructure projects. He has
been an expert for several legal cases.
Mr. Phillips has over 35 years of heavy civil engineering
experience and has a strong focus on major transport
projects, particularly design-build.

Mr. Phillips was Construction Manager and Design


Manager/Chief Engineer for the Lantau Link, which
included Tsing Ma Crossing, the worlds longest road and
rail bridge, and the Kap Shui Mun Bridge, the worlds
longest road and rail cable-stayed bridge.
Relevant Project Experience
A30 Highway, Montreal, Quebec ($1.9 billion)
Lead Designer/Project Director, 2007 2010

Civil & Structural Engineer


Project Director/Manager

Registered Professional Engineer: NV


#CE 018902
Registered Professional Engineer: NY
#16-084020
Chartered Engineer, United Kingdom,
1978, No. 308 728
Chartered Professional Engineer,
Australia, 2001, No. 233 7846

Experience
36 years

Experience in Proposed Role


23+ years

Education

BSc (Hons) in Civil Engineering1974


Awarded College and Institution of Civil
Engineer's Prizes for outstanding
undergraduate work1974

Design-Build Experience:

A30
A25
Airport Link, Brisbane
California High-Speed Rail
Eagle P3, Denver
Lake Mead
North East Line
MRTA North
Medway Tunnel
Merset Barrage
Tees Barrage

Mr. Phillips was responsible for the bid and final design
for the 25.2-mile-long, 4-lane highway located south of
Montreal. The project includes 3.6 miles of bridges, a
tunnel beneath the Soulanges Canal; bridges over the St Laurent River (0.75 mile long), over the
Beauharnois Canal (1.2 miles long), over the St. Louis River, and over Chateauguay River; and many
other interchanges and bridges. The project is a P3 project.
A25 River Prairies Bridge, Montreal, Quebec ($460 million)
Lead Designer, Project/Bid Director, 2005 2006

Mr. Phillips was responsible for the bid design for the 0.8-mile, 6-lane highway bridge over the River
Prairies in Montreal, Quebec. The project was a P3 project.
California High-Speed RailLos Angeles-Palmdale & Fresno-Palmdale Sections ($28 billion)
Lead Designer, Engineering Manager, Bid and Project Director, 2007 2010

Mr. Phillips has been one of Arups Lead Designers, Engineering Manager and Bid and Project
Director for the groundbreaking HSR project, which will link the cities of Los Angeles to Palmdale
with a route length of 61 miles (15 miles of tunnels, 35 miles of viaduct, and 11 miles at grade). Mr.
Phillips is also Project Director for the 200-mile Fresno to Palmdale section, which includes 20 miles
of tunnel and 30 miles of viaduct. Project is currently in the EIS and Preliminary Engineering stage.

Volume 2 Section 1 Design Resumes page 73

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Airport Link, Brisbane, Queensland, Australia ($4.8 billion)


Project Reviewer, 2009 2010

Mr. Phillips was the Project Reviewer for Australias largest road project. Set in the urban area of
Brisbane, the busway project has an overall length of 6.7 miles. Works include twin 2-lane
unidirectional TBM tunnels, large-span mined 3-lane roadway tunnels with on and off ramps, plus
numerous bridges and viaducts, a high-capacity interchange, and high-quality urban design solutions.
Eagle P3 LRT System, Denver, Colorado ($2.5 billion)
Technical Reviewer, 2009 2010

Mr. Phillips is a Technical Reviewer in the Lenders Technical Advisors team, on this LRT P3
project. The project comprises the design, build, financing, and operation of three LRT lines, the
East Corridor, the North West Line, and the Gold Line. These three LRT lines are 23, 5.5 and 7.5
miles long, with 6, 3, and 5 stations, respectively, and include yards, shops, rolling stock, and all
systems.
Tappan Zee /I287 Corridor Alternate Analyses, Rockland & Westchester Counties, New York
($16 billion)
Project Director, 2002 Present

Mr. Phillips is the Project Director responsible for all design and engineering services. He was
previously Technical and Project Management Advisor to the Arup team on the alternatives analyses
for the corridor study and new river crossing of the Hudson River. The primary objective of the
study is to improve mobility of the 30-mile corridor to the north of New York City from Suffern in
the west to Port Chester in the east. CRT, LRT, and BRT options were considered together with
highway alternates. Hudson River crossings that were considered include retention of the existing
bridge and replacement bridges and tunnels (bored and immersed).
Second Avenue Subway, New York, New York ($17 billion)

Lead Designer/Deputy Project Manager and Chief Engineer, 2001 2006

Mr. Phillips was one of the Lead Designers, Deputy Project Manager and Chief Engineer
responsible for all design and engineering services for this $17 billion subway line in New York City.
The new, twin-track line will include sixteen mined and cut-and-cover stations, and various softbored, rock-bored, and cut-and-cover tunnels. He was responsible for the multi-disciplinary
feasibility study, the concept design, and the preliminary engineering, with the exception of the
rolling stock and signaling designs, although the integration of these elements was included in the
remainder of the project. Additionally, he was responsible for the preparation of the tunnel
design/build contract documentation. He was responsible for preliminary engineering for Phases 1
to 4, then the final design phase of Phase 1 of the project.
Lantau and Airport Railway (LAR), Hong Kong ($4.5 billion)

Lead Designer/Chief Civil Engineer and Construction Manager, 1991 1998

The project included the Lantau Link, a road and rail water crossing, which includes the Tsing Ma
Suspension Bridge (the worlds longest road and rail suspension bridge), the Kap Shui Mun CableStayed Bridge (the worlds longest road and rail suspension bridge), and the Ma Wan Viaduct, which
has an overall length of 2 miles. He was involved in the design and engineering of all elements of the
bridges, trackwork, and rail movement joints including the movement, noise, and vibration aspects.
He was extensively involved with the team and the contractor in the development, testing,
installation, and acceptance of the Tsing Ma Bridge rail movement joints, which are the largest rail
movement joint in the world, and which successfully accommodate the longitudinal movement of 7
feet plus other modes of movement. Mr. Phillips also led the negotiations for MTRC with the
Department of Highways and their team on the contract document preparation and the award of the
outsourcing for the Bridge/Crossing operator and maintainer.

Volume 2 Section 1 Design Resumes page 74

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Naeem Hussain

Technical Steering Team (CableStayed Bridges)

Profession
Civil Engineer

Experience
48 years

Experience in Proposed Role

Career Summary

25 years

Mr. Hussains education in both engineering and


Committees & Associations
architecture has enabled him to combine the best of both
Fellow, Institution of Civil Engineers, UK,
disciplines in winning international bridge design
1996
competitions and designing award-winning bridges.
Fellow, Institution of Structural
Engineers, UK, 1996
Mr. Hussains success in bridge engineering can be
Fellow, Hong Kong Institution of
illustrated by several award-winning projects. Most
Engineers, 1998
recently, he was the Project Manager for the detailed
Hong Kong Delegate to the Permanent
design and construction supervision for the Hong Kong
Committee, International Association of
Bridge and Structural Engineers (IABSE),
Stonecutters Bridge, a cable-stayed bridge with a main
2003
span of 3,340 feet, the second-longest cable-stayed span in
Fellow, Hong Kong Academy of
the world, which was awarded the Joint HKIE/ IStructE
Engineering Sciences, 2010
Grand Award and the UK IStructE 2010 Supreme Award.
Education
Another notable project is the 6.2-mile-long combined rail BSc (Eng), University of Engineering and
and road resund bridge crossing between Denmark and
Technology, Lahore, Pakistan, 1962
Design Studies, Architectural Association
Sweden, for which Mr. Hussain was a key member of the
School of Architecture, London, 1967
original design team that won the international design
DIC, MSc (Concrete Structures), Imperial
competition for the bridge. The bridge has a double-deck
College, University of London, 1971
main cable-stayed span of 1,600 feet and approach spans
Design-Build Experience
of 460 feet. The resund bridge received the IABSE
Forth Replacement Crossing, Scotland,
outstanding Structure Award.
UK
Mr. Hussain was the Engineering Manager for the detailed resund Crossing, Denmark/Sweden
design of KCRC West Rail Yuen Long Section, which
comprises 5.6 miles of precast segmental post-tensioned viaducts with spans up to 295 feet and
three elevated stations, each over 1,300 feet long. The KCRC viaducts include innovative noise
attenuation systems that include floating slab tracks.
Currently, he is the Main Bridge Design Leader for the Forth Replacement Crossing in Scotland
which will comprise of a 3-tower cable-stayed bridge with spans of 2,133 feet. He is also the lead
Arup designer for the viaducts and cable-stayed bridges on the 25-mile Hong Kong-Zhuhai-Macau
Sea Crossing Link.
Mr. Hussain is Arups global bridge leader and has over 40 years experience of award-winning
civil and bridge engineering works around the world.

Relevant Project Experience


Hong Kong Zhuhai Macao Link ($10 billion)
Dy. Project ManagerBridges, 2008 Present

The work included Concept, Preliminary Design, and Detail Design of a dual 3-lane carriageway, 18miles-long sea-crossing bridge that includes three navigation cable-stay bridges ranging in span from
867 feet to 1,500 feet and includes approach spans ranging from 283 feet to 600 feet.

Volume 2 Section 1 Design Resumes page 75

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Forth Replacement Crossing, Scotland, UK ($2.55 billion)


Main Crossing Manager, 2008 Present

Mr. Hussain is the Main Crossing Manager for this back-to-back 3-tower cable-stayed bridge with
dual 2,133-foot spans. The Forth Replacement Crossing will carry three lanes of traffic in each
direction and will provide 180 feet of vertical clearance for shipping. Construction is expected to
start in April of 2011 for completion in 2016.
Stonecutters Bridge, Hong Kong ($960 million)
Project Manager, 2001 2010

Mr. Hussain was the Project Manager for the detailed design of the Stonecutters cable-stayed bridge,
which has a main span of 3,570 feet, the second longest cable-stayed span in the world. The bridge
comprises two 980-foot-tall single towers, a split deck of widely separated twin longitudinal boxes,
and two cable planes in a semi-fan arrangement. Three lanes of traffic plus hard shoulders are
supported in each direction, and the bridge provides 246 feet of vertical clearance for shipping.
Construction of the bridge commenced in April 2004 and was completed in November 2010. The
Stonecutters Bridge has won multiple world-class awards, including the prestigious IStructE 2010
Award for Transportation Structure and the Supreme Award for Structural Engineering Excellence.
Machang Bridge, Korea ($242 million)
Project Manager, 2005 2008

Mr Hussain was the Project Manager for the construction supervision of the 1,476-foot main span
cable-stayed bridge in Machang.
Incheon Bridge, Songdo, Korea ($1.0 billion)
Project Manager, 2005 2009

Mr Hussain was the Project Manager for detail design check for this 7.5-mile, dual 3-lane seacrossing bridge between Incheon and Songdo. The bridge comprises 164-foot-span low-level
viaducts, 460-foot-span balanced-cantilever approach spans, and a 2,625-foot cable-stayed span, the
fifth longest cable-stayed span in the world.
Deep Bay Link and Shenzhen Western Corridor, Hong Kong ($720 million)
Concept Designer & Structural Manager, 2002 2006

Mr. Hussain was the Concept Designer for the viaducts and the cable-stayed bridge on the 7.1-milelong dual 3-lane fourth boundary connection between Hong Kong and Shenzhen, China. The 3.4mile land portion was built with the span-by-span construction technique using 130-foot spans and
precast segments. The sea crossing was built with the balanced cantilever construction technique
using 246-foot spans and precast segments. The cable-stayed bridge is a single inclined tower bridge
with a main span of 689 feet and utilizes a wide steel orthotropic box deck. The bridge provides 100
feet of vertical clearance for shipping traffic.
resund Crossing, DenmarkSweden ($1.125 billion)
Project Manager (London), 1994 1996

Mr. Hussain was a member of the competition-winning design team and was subsequently the
Project Manager in London for the design and preparation of illustrative and definition drawings for
the 6.2-mile-long bridge section of the 10.5-mile-long resund Crossing between Denmark and
Sweden, which carries road and rail traffic. The crossing has 460-foot approach spans and a main
cable-stayed navigation span of 1,600 feet. The main span comprises a double-deck composite truss
with dual 2-lane motorway on top and twin railway tracks below. The main span is also a composite
truss with an orthotropic lower deck.

Volume 2 Section 1 Design Resumes page 76

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Peter Matusewitch

Technical Steering Team-Structures

Profession
Structural Engineer

Experience
25 years

Experience in Proposed Role

Career Summary
Peter Matusewitch is a Senior Structural Engineer with
Arup. His expertise lies in structural design, rehabilitation,
planning studies, cost estimates and inspection of fixed
and movable bridges.

25 years

Licenses and Registrations

Education

Peters strength is in the technical leadership of diverse


aspects of planning and design of bridges

Registered Professional Engineer: NY


BS, Civil Engineering, Polytechnic
University, New York, 1987

Design-Build Experience

A30 Bridges, Montreal


Tappan Zee Bridge Replacement, NY

Relevant Project Experience


Autoroute 30 Major Bridges, Ministry of Transport Quebec, Quebec, Canada (CAD$1.5 billion)
Technical Coordinator, 2007 2012

Technical Coordinator for the major river crossings on this 26-mile-long Public-Private Partnership
project to extend Autoroute 30 around Montreal. The project encompasses 31 new bridges and a
tunnel. Coordination included seismic design, foundations, prestresed concrete beam fabrication
issues and environmental issues for the 1.8km-long St. Laurent River Bridge, for which he also
served as Lead Designer, and the 1km-long western approach to the Beauharnois Canal Bridge.
I-287 Corridor/Tappan Zee Bridge Rehabilitation/Replacement Study, New York State
Department of Transporation, New York State Thruway and MTA Metro North Railroad,
Rockland/Westchester Counties, NY ($5 billion)
Senior Analyst and Reviewer, 2001 2012

Senior Reviewer for the concept design, planning studies alternatives analyses and engineering
support, and Lead Analyst for cost, schedule, security and risk analyses for the Environmental
Impact Statement, indicative design and design-build documents for the replacement of the 3-milelong Tappan Zee Bridge and reconstruction of the New York State Thruway in the Rockland and
Westchester Counties corridor.
Cancun Airport Taxiway Bridge, ASUR ($15 million)
Technical Coordinator, 2007 2009

Technical Coordinator. Supervision and review of the design, specifications and construction
support for a 3-span, post-tensioned concrete box airside taxiway bridge over the main access
roadway to the airport.
Throgs Neck Bridge Vessel Collision Protection Project, MTA Bridges and Tunnels, New York,
NY, ($13 million)
Project Engineer, 2005 Present

Project Engineer for in-depth study of vessel collision vulnerability of the main spans, including a
performance-based analysis of the response of the anchorages to vessel collisions using digital
dynamic impact modeling, and final design of main tower fender rehabilitation.

Volume 2 Section 1 Design Resumes page 77

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Williamsburg Bridge Reconstruction, NYC Department of Transportation, New York, NY


($850 million)
Project Engineer, 1998 - 2004

Project Engineer for the in-depth inspection and final structural design of Contract 8 for the
reconstruction of this 100-year-old combined highway and rail transit suspension bridge. The
contract scope encompassed: the repair of the main cable wrapping; rehabilitation of the cable
saddles; replacement of the suspender cables; restoration of the original bridge profile; rehabilitation
and strengthening of the main and intermediate towers and the main span stiffening trusses;
replacement of truss bearings at the anchorages and main towers, including temporary support
towers within the main towers; replacement of the lateral wind load transfer systems at the main
towers; and miscellaneous repairs and retrofits to bring the bridge up to current AASHTO and
AREMA design standards. Also conducted constructability review and failure analysis of preliminary
seismic retrofit design by others, and final design to AASHTO and AREMA standards. Initially an
estimated US$34m retrofit cost, the failure analysis, constructability review and subsequent final
design realized a savings of over US$15m in construction cost for New York City DOT.
Throgs Neck Bridge Approach Spans, MTA Bridges and Tunnels, New York, NY, ($18 million)
Project Engineer, 2001 2004

Project Engineer for forensic engineering and analysis of the superstructure to determine the cause
of floorbeam and subfloorbeam web cracking and connection bolt failures following the 1980s
installation of an orthotropic deck. Supervised development and final design of prototype retrofits
to address these participation problems.
Northbound Whitestone Expressway over the Flushing River, New York State Department of
Transportation, Queens, NY ($80 million)
Project Engineer, 1990 - 1996

Project Engineer for the Design Report and Environmental Assessment for rehabilitation or
replacement of this 60-year-old bascule bridge and 22 approach spans. Included in-depth inspection,
structural analyses, preliminary design alternatives, cost estimates and schedules to balance traffic
disruption during construction, operational improvements, property impacts, river impacts, and cost.
Willis Avenue Bridge over the Harlem River, New York City Department of Transporation,
New York, NY ($300 million)
Project Engineer, 1992 1996

Project Engineer for in-depth inspection, load rating, fatigue and seismic evaluations and
preparation of a Design Report for rehabilitation or replacement of this 95-year-old swing bridge
and 48 approach spans.
Shore Road Bridge, New York City Department of Transporation, New York, NY ($9 million)
Project Engineer, 1996 2000

Project Engineer for in-depth inspection, design report, and preliminary and final design plans and
specifications for replacement of the deck and mechanical system and re-balancing of this double
leaf rolling lift span located in an environmentally sensitive park. Included rehabilitation of the
concrete arch approach spans, which are eligible for listing on the National and State registers of
Historic Places. Also supervised completion of an Alternatives Study for replacement and provided
engineering support for the Environmental Impact Statement for replacement.

Volume 2 Section 1 Design Resumes page 78

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Robert B. Bittner, P.E.

Technical Steering Team


(Geotechnics & Foundations)

Profession
Civil Engineer

Experience
41 years

Experience in Proposed Role

Career Summary
Mr. Bittner is a professional engineer with 41 years of
experience in construction engineering and project
management on major marine construction projects
worldwide. The focus of Mr. Bittners work has been on
minimizing construction costs through the design and
development of innovative methods and equipment for
marine construction projects. These innovative methods
and equipment have been employed on the construction
of bridges, immersed tube tunnels, ocean outfalls and
intakes, marine terminals, offshore structures, locks and
dams.
Mr. Bittner has a combination of structural design
experience of bridge foundations and extensive heavy
construction engineering experience. This combination
is essential for developing innovative cost efficient
bridge foundation solutions.

Relevant Project Experience


Tri-Met Willamette River Bridge, Tri-Met, Portland,
Multnomah County, OR ($129 million)
Foundation Design Manager, 2008 Present

Foundation Design Manager for the main span in-water


foundations including 10-ft-diameter drilled shafts and pile
caps. Project is currently under construction.
Cooper River Bridge, South Carolina DOT, Charleston,
SC ($650 million)

12 years

Licenses and Registrations

Registered Civil Engineer, 1974,


#C23742
Registered Civil Engineer, 1975,
#O8664
Registered Civil Engineer, 1979,
#18494
Registered Civil Engineer, 1998,
#8803
Registered Civil Engineer, 2001,
#21513
Registered Civil Engineer, 2005,
#31715
Registered Civil Engineer, 2011,
#037638
Registered Civil Engineer, 2009,
Columbia, Canada, #157746

CA
OR
WA
ME
SC
LA
NC
British

Education

B.S. (Civil Engineering) Stanford


University, 1969
M.S. (Construction Management)
Stanford University, 1970

Design-Build Experience

resund Immersed Tube Tunnel


Tri-Met Bridge
Cooper River Bridge

Caltrans Experience

Skyway Contract San FranciscoOakland Bay Bridge


Carquinez Bridge
Benicia-Martinez Bridge

Foundation Design Manager, 2000 2005

Foundation Design Manager for the main span and high-level approach spans of the Cooper River
Bridge in Charleston, South Carolina, the longest span cable-stayed bridge in the North America.
Ben C. Gerwick, Inc. (Senior Project Manager), Multiple Projects
Senior Project Manager, 1996 2008

As Senior Project Manager with Ben C. Gerwick, Inc., Mr. Bittner developed the initial concepts and
supervised the detail design of an innovative float-in cofferdam system for the Bath-Woolwich
Bridge across the Kennebec River at Bath, Maine. Mr. Bittner later supervised the adaptation of this
concept for the bridge foundations on the new Carquinez Bridge, the new San Francisco-Oakland
Bay Bridge and the new Benicia-Martinez Bridge in California. These same concepts were later used
to construct the foundations for three major bridges in East Asia.
Foundation consultant on the following major bridges:
Su-Tong Bridge across the lower Yangtze River, China, the longest cable-stayed bridge in the world.

Volume 2 Section 1 Design Resumes page 79

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Second Tacoma Narrows Bridge, Washington State


Chacao Bridge, Chile
Dong Hai Bridge (20-mile open-sea crossing), China
Hangzhou Bay Bridge (13.7-mile open-sea crossing), China
2nd Inchon Bridge, Korea
Oresund Tunnel Connecting Denmark and Sweden ($650 million)
Design Manager, 19941996

Design Manager for Oresund Tunnel Contractors JV responsible for design of all temporary works
for the cast and launch of twenty 55,000-ton immersed tube tunnel elements. Supervised design subconsultant for the permanent immersed tube tunnel, the largest immersed tunnel in the world.
Riedel International (Chief Engineer), Multiple Projects
Chief Engineer, 19761993

As Chief Engineer for Riedel International, Mr. Bittner developed construction methods and
designed falsework, cofferdams, caissons, heavy lift equipment, and pile driving equipment for the
following major bridges:
I-205 Columbia River Bridge - North Channel Crossing at Portland, OR
I-205 Columbia River Bridge - South channel Crossing at Portland, OR
Union Pacific Railroad Bridge No. 7.44, across Columbia River at Pasco, WA
I-90 East Channel Bridge, Mercer Island, WA
Swinomish Channel Bridge, Skagit County, WA
Annacis Channel Bridge, Vancouver, BC, Canada

Volume 2 Section 1 Design Resumes page 80

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Professor Niels J. Gimsing


Technical Advisory Panel

Professor Emeritus, Consulting Bridge


Engineer

Experience

Career Summary
As a member of our Technical Advisory Panel, Prof.
Gimsing brings with him a lifetime of bridge design
experience. His unparalleled experience includes both
academic research and practical applications in the field of
bridge design and construction. He has consulted on
numerous structures, including the long-span cable-stayed
resund Link, the Forth Replacement Crossing, and the
Stonecutters Bridge.
Professor Emeritus Gimsing has over 45 years of bridge
design experience. He has received numerous awards
for his research, including the Anton Tedesko Gold
Medal of the IABSE and the Professor A. Ostenfeld Gold
Medal by the Danish Society for Structural Engineering
and Science.

Relevant Project Experience


Forth Replacement Crossing, Transport Scotland ($2.5
billion)
Specialist Adviser, 2008

Specialist Adviser on Structural Design and


Constructability to Transport Scotland on the design of
the Forth Replacement Crossing, comprising a cable-stay
bridge with two 2,132-foot main spans (dual 3-lane decks),
with 180 feet of clearance for shipping. Originator of the
innovative cable-stayed system with overlapping fans to
stabilize the central pylon between the two main spans.
Stonecutters Bridge, Hong Kong Highways
Department, Hong Kong ($960 million)
Specialist Adviser, 2001

Profession

53 years

Experience in Proposed Role


45 years

Licenses and Registrations

Danish Academy of Technical Sciences


Danish Society of Structural Engineering
and Science, Honorary Member
IABSE (International Association for
Bridge and Structural Engineering),
Honorary Member

RFP Criteria
At least 20 years experience in bridge design
52 years
At least three cable-supported
vehicular/rail/pedestrian bridges
Forth Replacement Crossing,
Stonecutters Bridge
resund Link
At least one bridge needs to be a cablestayed structure with a main span length of
at least 700 feet between center lines (or a
main span length of at least 400 feet)
Forth Replacement Crossing,
Stonecutters Bridge
resund Link
At least 20 years technical experience in the
analysis of large structures in the fields of
structural dynamics, wind engineering,
inelastic modeling of structural systems,
inelastic material and member models, and
behavior of steel member connections
45 years
Published research results on at least 10
occasions in technical journals with a
national or international subscription base,
and have had research results or
recommendations based on research results
be adopted by at least one bridge design
code or standard that is adopted and in use
by the Department
Yes

Member of the Highway Departments Technical


Evaluation Committee and the Executive Committee for
the Stonecutters Bridge Competition to select the final
design for construction. Specialist Adviser to Arup Hong
Kong on the subsequent detailed design of the
Stonecutters Bridge. Participated in the design development during the detailed design phase where
aerodynamic issues played a dominant role and required a number of design changes. This is the
worlds second-longest cable-stayed span, with a main span of 3,570 feet. Project was delivered on
time and on budget.
resund Link, resundskonsortiet, Denmark to Sweden ($1.1 billion)
1993

Member of the design team in the ASO Group for the design of a 4.8-mile-long, double-deck road

Volume 2 Section 1 TAP Resumes - page 1

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

and railway bridge forming the eastern portion of the


resund Link. This bridge included at completion the
tallest free-standing bridge pylons in the world (667ft) and
a 1,600-foot span, the longest for a cable-stayed bridge
carrying both road and rail traffic. Responsible for the
double deck competition design that was chosen as basis
for the Clients tender design. The design-build project
was delivered on time and on budget.
Myodo Suspension Bridge, Samsung, Korea
Expert Adviser, 2006

Expert adviser in the development of the design based on


a suspension bridge with A-shaped towers and a vented
deck. Special emphasis on constructability issues related to
the cable erection and lift of deck elements.
Sutong Bridge, China
Expert Adviser, 2002

Participated in the conceptual design of cable stayed


bridges with one or two record-long main spans.

RFP Criteria (contd)


At least 20 years experience in seismic
design and large-scale physical seismic
experimental research of large bridge
structures, research achievements include
the development of large-scale structural
testing techniques, seismic assessment and
retrofit of bridges in California
Yes
Currently or previously a tenure-tracked
professor in a public research university that
has a graduate PhD program in civil or
structural engineering
Professor of Steel Structures at the
Department of Structural Engineering,
Technical University of Denmark
At least 20 years experience in bridge
construction engineering on large complex
bridge projects
Yes

Education & Awards

Jeokgeum-Yeongam, LG Construction, Korea

Expert adviser on the tender design of a 2,690-foot-span


suspension bridge as part of a Turnkey Submission by LG
Construction. Participated in the development of the
design based on a suspension bridge with towers as freestanding posts and a unique triangular stiffening truss.

Expert Adviser, 2003

Tsing Lung Suspension Bridge, Hong Kong


Member of the Expert Panel, 2000

Member of the Expert Panel for the Tsing Lung


Suspension Bridge in Hong Kong. Proposed to design the
bridge with towers formed as free-standing posts and with
transversally inclined cable planes. Participated in the
evolution of the innovative design.
Millennium Bridge Competition, UK

Finalist, 1996

Finalist in the Millennium Bridge Competition for a


pedestrian bridge across the Thames River at St. Pauls
Cathedral in London.

Second Severn Crossing, Worcester, England


Design Adviser, 1989

Degree in Civil Engineering (M.Sc.) from


the Technical University of Denmark
1959
Professor of Steel Structures at the
Department of Structural Engineering,
Technical University of Denmark 1976
2005
2009 : Awarded the Professor A.
Ostenfeld Gold Medal by the Danish
Society for Structural Engineering and
Science
2004 : Awarded the Gold Medal of the
Technical University of Denmark for
outstanding achievements within
research and teaching in the field of
structural engineering.
2003 : Honorary Member of the Danish
Society for Structural Engineering and
Science
2000: Awarded the Anton Tedesko Gold
Medal of the IABSE Foundation
1996: Honorary Member of the
International Association for Bridge and
Structural Engineering (IABSE)
1993: Member of the prize winning
design team in the ASO Group for the
design of a 4.8-mile-long, double-deck
road and railway bridge forming the
eastern portion of the resund Link
1991 : Awarded the Saxild Price for
outstanding achievements within the
field of bridge design and research.

Adviser to Ove Arup & Partners on the tender design of


the second Severn Bridge, comprising a 1,476-foot cablestayed main span. Develop in a team effort the design
based on a main span with a composite deck supported by inclined cable planes and an A-shaped
pylon.

Volume 2 Section 1 TAP Resumes - page 2

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Luis Viuela Rueda, Ph.D.


Technical Advisory Panel
Career Summary

Civil Engineer. PhD

Experience
37 years

From 1975 to 1988 worked as designer in Ibrica de


Estudios e Ingeniera (IBERINSA).
1989 to 1990 Entrecanales y Tvora S.A: as Director of
Singular Works.
1991 to 2011 FCC Constuccin S.A. as a Director of the
Singular Works Department.
Currently, Mr. Viuelas is an Independent Structural
Consultant.
Alone or together with others Mr. Vuuelas been working
as a Director of Construction of Singular and several
typologies of bridges (cable-stayed, composite, arch, truss
and bascule bridges).
Mr. Viuela directed the unique structure and erection
procedures for the Serrera Bridge. This asymmetric
cable-stayed bridge features a 410-foot-tall, backleaning inclined pylon.

Relevant Project Experience


Serrera Bridge, Ciudad de las Artes y las Ciencias,
S.A., Valencia, Spain ($64 million). CALATRAVAS
PROJECT
Direction of construction, 2008

Profession

Experience in Proposed Role


22 years

Awards

Professional Award of Colegio de


Ingenieros de Caminos (Spanish Civil
Engineers Society) , 2003.

Education

Civil Engineer Degree by Escuela de


Ingenieros de Caminos (Polytechnic
University of Madrid) (1974)
PhD courses, 19751979

RFP Criteria
At least 20 years experience in bridge
construction engineering on large complex
bridge projects
37 years of experience
Prior cable-stayed bridge construction
experience as the construction manager,
deputy construction manager, or lead
superintendent for the construction of at
least two cable-supported
vehicular/rail/pedestrian bridges
Suspension Bridge in Elche (Spain)
Serrera Bridge
El Alamillo Bridge
...At least one of the qualifying facilities shall
be a cable-stayed bridge with a main span
length not less than 700 feet between center
lines of towers for a multi-tower structure or
a main span length of no less than 400 feet
(measured between the center line tower
and the face of the abutment) for a single
tower structure
Serrera Bridge (City of Arts and Sciences
S.A. Valencia -Spain-)

Directed structure and erection procedures for this


asymmetric cable-stayed bridge. This signature bridge
comprises an inclined steel pylon with a height of 410 feet
and a deck with a 508-foot-long main span. The
backward-inclined steel pylon tower above the bridge
supports 29 front cable stays comprising between 31 and
Design-Build Experience
61 strands and the 4 back stays with 85 strands each,
Les Fosses bridge. Barcelona (Spain)
supporting more than 1,800 tons of steel used for the
Draw Bridge at Port of Barcelona (Spain)
bridge deck. During pylon construction, three provisional
front stays were installed to bear the weight of the inclined pylon.
The orthotropic deck is 116.5 to 128 feet wide, 9.9 to 11.3 feet thick, and is composed of a central
triple box structural backbone running the length of the bridge, supporting ribs cantilevered out
crosswise atop the backbone every 16.4ft. The foundation is established by means of 20 piles 145
feet deep and 6.6 feet in diameter. The piles are joined together with caps of variable heights and
widths. A metal frame is secured to the capping by means of 172 post-tensioned bars 1.85 inches in
diameter and 19.7 feet long. The mast is 410 feet tall, with a cross-section ranging from 20x133 feet
at the base to 10.8x9.7 feet at the top. The mast was fabricated in 15 sections, which were
transported to the site and joined into 7 assemblies for placement using a 750-ton crane and a 200ton crane..Construction started in October of 2004 and completed in December of 2008.

Volume 2 Section 1 TAP Resumes - page 3

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Alamillo Bridge, EXPO'92, Seville (Spain) ($50 million). CALATRAVAS PROJECT


Project and Direction of construction, 1998

The cable-stayed El Alamillo Bridge in Seville is a landmark job in its conception. The principle on
which it works is a balance in which equilibrium is attained by inclining the 432-foot-tall mast at an
angle of 58 to the horizontal. The design is by Santiago Calatrava. The bridge has a span of 650 ft,
which enters the technical domain of cable-stayed bridges. The mast to which the cables are
anchored is a compound structure made of concrete and steel. Its cross section varies, from 13 feet
in diameter from the ground to a height of 250 feet. The masts inclination enables the cables pull to
be balanced without using guy cables. The deck is made up of a metal casing of varying width and 43
foot-wide lateral overhangs. The metal casing measures 14 feet along its edge, and its cross-section
forms a hexagon whose upper and lower wings vary in width from 12 feet to 20 feet in the upper
frame and from 10-7 to 19-4 in the lower frame. The overhangs are built with metal ribs set 13.2
feet apart holding a reinforced concrete slab on top, built with prefabricated 4-inch-thick plates with
5 inches of concrete laid on site on top of the plates. The deck is anchored to the mast by 13 pairs
of parallel cables that spring from the edges of the central metal casing.
Draw Bridge at Port of Barcelona (Spain), Port of Barcelona Authority, Barcelona (Spain)
($37.5 million)
Direction of construction, 20012002

This drawbridge stands between the Poniente wharf and the Adosado wharf at Barcelona Harbour.
It is a two-leaf steel bascule bridge. The free span of the navigation channel measures 328 feet
between piers, while the span between ball-and-socket joints is 358 metres. The 179-foot freestanding projecting end makes this bridge a world record holder in its class. The piers, on a pilot
foundation, are made of reinforced concrete, with some local pre-tensioning so that they can
withstand the forces exerted by the main jacks. The bridge is reached by two concrete viaducts that
lead to the level of the deck, situated 66 feet above sea level. Not only the deck of this bridge but
also its primary piers can be considered unique; they all harmonize and work together to form a
sculptural assemblage. Each of the two leaves of the bridge deck is 225 feet long: 46 feet long from
the rear, where the counterweight is hung, to the joints; and 179 feet of projecting end, from the
joints to the centre of the span. The total width on the ground plan is as much as 59 feet, due to the
outward inclination of the deck's edge beams. The deck width is 50 feet.
The bridge was assembled using one of the biggest floating cranes in the world, able to lift the 2,100
tons that each span weighed.
Elche Suspension Bridge, Department of Public Works- of Valencia , Elche (Spain) ($25
million)
Direction of construction, 19992000

This 463-foot-span asymmetric single-pylon suspension composite bridge has two inclined planes of
cables that connect with the 120-foot-high pylon. The cross section is 65 ft wide and a variable
depth of between 2 and 2-10". It allows four traffic lines and two sidewalks 10 feet wide. The steel
box is formed by a continuous plate placed at the bottom. Over this plate there are longitudinal and
transverse floor beams every 19-8" that connect with the hangers. Over these floor beams the upper
plates are placed. Finally a 8" cast-in-place slab complete the cross section.
Construction started in 1998 and completed in 1999.

Volume 2 Section 1 TAP Resumes - page 4

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Fabio Brancaleoni

Technical Advisory Panel

Profession
Full Professor of Structural Engineering

Experience

Career Summary

38 years

Since 1981, Professor Brancaleoni has consulted on 19


major long-span bridges, in addition to dozens of
smaller bridges and other structures.

23 years

Experience in Proposed Role


Licenses and Registrations

Chartered Engineer, Italy

As a member of our Technical Advisory Panel, Prof. Brancaleoni brings with him enormous bridge
design experience. He has served as a specialist consultant on some of the worlds largest cablestayed bridges, including Stonecutters Bridge. Mr. Brancaleoni is currently a Full Professor in the
Dipartimento di Strutture, University of Rome TRE, where he chairs Strengths of Materials and
lectures upon Structure and Material Mechanics, Bridge Theory and Design, Structural Dynamics,
Theory of Structures, and Structural Design. He has authored over 100 scientific papers50
published internationallyon themes of structural dynamics, long-span suspension and cable-stayed
bridges, identification and structural diagnostics, computational mechanics, seismic engineering.
Relevant Project Experience
Stonecutters Bridge, Hong Kong Highways Department, Hong Kong ($960 million)
Specialist Adviser, 2001

Specialist Adviser to Arup Hong Kong on the detailed design of the Stonecutters Bridge in Hong
Kong. Member of international Review panel for the Design JV. Activities comprised examination
of the bridge design solutions and alternatives, providing consultancy on suitability and selection of
optimal concepts. This is the worlds second-longest cable-stayed span, with a main span of 3,570 ft.
Messina Strait Bridge, Italy, ($5.1 billion)
Designer, 19922011

Participation in preliminary (19901992), tender (20022003), and final design (20102011) for this
suspension bridge with a main span of 10,800 feet. The bridge will be the largest in the world.
Previous participation in feasibility analyses (19741986), concept design and analyses for
alternatives (19871990). Activities have comprised, among others, design coordination, design of
the suspension system, design of the terminal structures and access viaducts, updating of tender
deck and tower design, FEM structural analyses, including seismic and railway runability.
Storebealt East Bridge, Denmark

Member of International Review Board (19871988), Designer, 19891990

Member of Review Board 2. Activities comprised a peer review of the deign basis and of the
structural design, with expressions of independent opinion on the solutions adopted and suggestions
for improved concepts. In the tendering stage (19891990) designer for the contractor (CMF
SUD/COINFRA)of global and minor alternatives for access viaducts (winner with global alternative
design) and suspension bridge (winner with minor alternative design variations), that with a main
span of 5,320 feet is the largest in Europe. The access viaduct winning design was based on the span
increase from 520 to 630 feet for the typical span, adopting high-strength steel for the orthotropic
steel structure. The alternatives for the suspension bridge concerned mainly the deck , with
improved diaphragm solutions and stiffener/detailing optimization.

Volume 2 Section 1 TAP Resumes - page 5

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Fehmarnbelt Crossing, Germany to Denmark, Femern


A/S
Member of the International Review Panel, 2009

Fehmarnbelt Crossing from Germany to Denmark


through the Baltic Sea comprises two 2,950-foot road and
rail cable-stayed bridges. Member of the International
Review Board for the preliminary design. Activities
comprised a peer review on behalf of the client, with
expressions of independent opinion on the solutions
adopted and suggestions for improved concepts.
Milan-Bologna High-Speed Railway Bridge on Po
River, Piacenza, Italy, Prof. M. P. Petrangeli
Consultant, 1995

Consultant for the railway cable-stayed bridge on the Po


River. Activities comprised railway runability dynamic
analyses for evaluation of safety & comfort condition.
Cable-Stayed Bridge on the Uadi Dib, Algeria
Consultant, 1994

Consultant for the railway cable-stayed bridge on the Uadi


Dib. Activities comprised seismic analyses of the bridge
for the detailed design, including soil structure and fluid
structure interaction modelling.
Kirumi Cable-Stayed bridge, Tanzania, GSLE Inc.
Designer, 1985

Construction design for the Kirumi cable-stayed bridge.


Activities comprised analyses of erection stages for the
contractor, with preparation of steelwork segments
geometry sequence for the fabricator.
resund Link Alternative Design Development,
Denmark to Sweden, CMF Sud S.p.A. and Burmeister
& Wein A/S),
Designer, 1995

Alternative design development for access viaducts and


1,600-foot-span cable-stayed bridge. Preliminary design of
a multi-box deck steel alternative to the basic design.
3rd Tagus Crossing, Lisbon, Portugal, Tavetejo Inc.
Consultant, 20082009

1,800-foot-span road and rail cable-stayed bridge and


access viaducts for the 3rd Tagus crossing. Consultancy
for the tender design for concession, mainly concerned
with seismic design and steelwork design.

RFP Criteria
At least 20 years experience in bridge design
38 years
At least three cable-supported
vehicular/rail/pedestrian bridges
Messina Strait Crossing
Stonecutters Bridge
Storebaelt East Bridge
...At least one bridge needs to be a cablestayed structure with a main span length of
at least 700 feet between center lines (or a
main span length of at least 400 feet)
Stonecutters Bridge
Fehmarn Bridge
resund (alternative design)
At least 20 years technical experience in the
analysis of large structures in the fields of
structural dynamics, performance-based
seismic engineering, wind engineering,
inelastic modeling of structural systems,
inelastic material and member models, and
behavior of steel member connections
38 years
Research of structural dynamics, windengineering, performance-based seismic
engineering, inelastic modeling of structural
systems, inelastic material and member
models for nonlinear structural analysis, and
computational tools for nonlinear analysis of
structures
Yes
Currently or previously a tenure-tracked
professor in a public research university that
has a graduate PhD program in civil or
structural engineering
Yes
At least 20 years experience in the following:
- Seismic soil-structure interaction and
design of deep foundations
38 years
Geotechnical/foundation design experience
on no less than five long-span (more than
300 feet per span) bridge structures in the
past twenty years
Motorway Rome Ring Bridge on the Tiber
River
Della Scienza on Tiber River
Bridge Della Scafa on the Tiber
Third Tagus Crossing
Messina Strait suspension bridge
Sparvo and Molino di Setta viaducts

RN 77 Motorway, Algeria, Condotte Inc.


Consultant, 2008

Cable-stayed bridge and steel truss bridges. Design of major bridges for concession international
tender.

Volume 2 Section 1 TAP Resumes - page 6

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ragusa-Catania motorway, Italy, Condotte Inc.


Designer, 2007

Two cable-stayed bridges and 30 composite or prestressed concrete viaducts on the Ragusa-Catania
motorway. Design of mayor bridges for concession tender.

Volume 2 Section 1 TAP Resumes - page 7

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Prof. Stephen A. Mahin


Technical Advisory Panel
Career Summary

Profession
Professor of Structural Engineering

Experience
45 years

Dr Mahin is Director of the Pacific Earthquake Engineering


Research Center and the Byron and Elvira Nishkian Professor
of Structural Engineering at UC Berkeley, having held Assistant
and Associate Professor posts at Berkeley since 1977.

Dr. Mahins research focuses on improving understanding


of the seismic behavior of systems and improving
earthquake performance. He has carried out field
investigations following more than 17 major earthquakes.
He is an advocate of high-fidelity numerical simulation,
optimization and performance-based design. He pioneered
the development of hybrid simulation methods so that
structures too large to be tested by conventional means
can be studied experimentally, and has carried out a wide
variety of destructive shaking table, quasi-static and field
tests. These tests have included field tests of retrofit
strategies for the Cypress Viaduct following the 1989
Loma Prieta Earthquake, numerous shaking table tests of
innovative bridge systems including ones incorporating
foundation rocking and uplift, seismic isolators, viscous
dampers, and self-centering reinforced concrete columns.
Currently, he is working on a number of advanced precast
concrete systems for Accelerated Bridge Construction.

Experience in Proposed Role


30 years

Education

University of California at Berkeley, Civil


Engineering, B.S. (Honors)
University of California at Berkeley,
Structural Engineering, M.S.; Ph.D.
University of California at Berkeley,
Earthquake Engineering, Post-doctoral
scholar

Design-Build Experience

Peer review of numerous design-build


projects involving buildings,
infrastructure and bridge systems.

Caltrans Experience

Caltrans Research Committee (1990


2000)
Organizing Committees, Seismic
Research Symposium and Workshop
Multiple Research Contracts related to
retrofit and design of double deck
viaducts, shaking table tests of bridge
circular and interlocking spiral columns,
rocking foundations and seismically
isolated bridges.

Prof Mahin is an internationally recognized leader in


seismic engineering research and its application to improved design practice. His diverse
activities include significant contributions to seismic bridge design. He has extensive experience
in Technical Review panels for major infrastructure projects.

Dr. Mahin has carried out post-earthquake studies of bridges following more than a dozen
earthquakes, including studies of cable-stayed bridges in the 1995 Kobe, Japan and Chi Chi, Taiwan
Earthquakes.
He has published more than 300 technical papers and reports.He was awarded the Huber Civil
Engineering Research Prize in 1978 and earned the Norman Medal by ASCE in 1987. Dr. Mahin
was a finalist for the Charles Pankow Civil Engineering Innovation Prize in 1998 for the
development of practical methods of seismic isolation. In 2001, he was awarded a special
achievement award by AISC for his leadership in managing the SAC Steel Project. FHWA honored
him in 2007 with the James Cooper Best Paper Award for his innovative research on self-centering
bridges. He was inducted into the ASCE Offshore Technology Hall of Fame in 2011.
Relevant Publications

Espinoza, A. and Mahin, S., Seismic Performance of Reinforced Concrete Bridges Allowed to
Uplift During Multi-Directional Excitations, PEER Report, Pacific Earthquake Engineering
Research Center, UC Berkeley, in press.
Orgazalik, K. and Mahin, S., Experimental and analytical investigation of segmental
displacement control of seismically isolated bridges, PEER Report, Pacific Earthquake

Volume 2 Section 1 TAP Resumes - page 8

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Engineering Research Center, UC Berkeley, in press.


Becker, T. and Mahin, S., Experimental and analytical RFP Criteria
At least 20 years technical experience in the
study of the bi-directional behavior of triple friction
analysis of large structures in the fields of
pendulum isolators, Earthquake Engineering &
structural dynamics, performance-based
Struct. Dynamics, May 2011.
seismic engineering, wind engineering,
Mahin, S., Achieving Resiliency in Buildings and
inelastic modeling of structural systems,
Bridges with Seismic Isolation (keynote paper),
inelastic material and member models, and
behavior of steel member connections
Proceedings, 8th Int. Conf. on Urban Earthquake
Engineering, Tokyo Institute of Technology, p 8,
20+ years
March 2011.
Published research results on at least 10
occasions in technical journals with a
Jeong, H., Sakai, J. and Mahin, Shaking Table Tests
national or international subscription base,
and Numerical Investigation of Self-Centering
and have had research results or
recommendations based on research results
Reinforced Concrete Bridge Columns, PEER Report
be adopted by at least one bridge design
2008/06, Pacific Earthquake Engineering research
code or standard that is adopted and in use
Center, UC Berkeley, Sept. 2008
by the Department
Matsumoto, T., Okstad, E., Kawashima, K., Mahin, S.,
Yes
Sesimic performance of rectangular columns and
At least 20 years experience in seismic
interlocking spiral columns, Proceedings, 14th World
design and large-scale physical seismic
Conference on Earthquake Engineering, Beijing, China,
experimental research of large bridge
October 12-17, 2008, Beijing, China, 2008.
structures, research achievements include
the development of large-scale structural
Rogers, J. and Mahin, S. Transient Response in Steel
testing techniques, seismic assessment and
Moment Frames Caused by Brittle Connection
retrofit of bridges in California
Fracture, Earthquake Engineering & Structural
20+ years
Dynamics. Vol. 36, no. 15, Dec. 2007
Lee, W., Jeong, H., Billington, S., Mahin, S., and Sakai, J., Research of structural dynamics, windengineering, performance-based seismic
Post-Tensioned Structural Concrete Bridge Piers with
engineering, inelastic modeling of structural
Self-Centering Characteristics, Proceedings, 2007
systems, inelastic material and member
Structures Congress, ASCE, 2007
models for nonlinear structural analysis, and
computational tools for nonlinear analysis of
Sakai, J., Mahin, S and Jeong, H., Reducing residual
structures
displacements in bridge columns using unbonded
Yes
post-tensioning, Proceedings, Fifth National Seismic
Currently or previously a tenure-tracked
Conference on Bridges and Highways, FHWA, Sep.
professor in a public research university that
2006. (James D. Cooper Best Paper Award).
has a graduate PhD program in civil or
J. Sakai, J. and Mahin, S., Analytical Investigations of
structural engineering
New Methods for Reducing Residual Displacements
Yes
of Reinforced Concrete Bridge Columns, PEER
PhD in Civil Engineering
2004/02, Pacific Earthquake Engineering Research
Yes
Center, UC Berkeley, 2004.
At least 20 years experience in the following:
Hachem, M., Mahin, S. and Moehle, J., Performance
- Seismic soil-structure interaction and
of Circular Reinforced Concrete Bridge Columns
design of deep foundations
Under Bidirectional Earthquake Loading, PEER Report Yes
2003/06, PEER, UC Berkeley.
Extensive experience in the practical
Chadwell, C., Mahin, S. and Fenves, G., Cable Stayed
application of seismology and ground
Bridge Behavior under Earthquake Excitation: A Case
motions
Study, Proceedings, 7NCEE, Boston, July 2002.
Yes
Cook, C. and Mahin, S., Parametric study of the effects
of bi-directional, near-field ground motions on reinforced concrete columns containing interlocking
spirals. Masters Thesis, UC Berkeley, 2001.
Zayati, F., Mahin, S., and Moehle, J., Experimental and analytical evaluation of a retrofit doubledeck viaduct structure, Report No. UCB/EERC-96/03, Earthquake Engineering Research
Center, University of California, Berkeley, 1996-06, 334 pages.
Mazzoni, S., Moehle, J. and Mahin, S., Design and response of lower-level beam-column joints
in ductile reinforced concrete double-deck bridge structures, EERC Report 95/05, UC

Volume 2 Section 1 TAP Resumes - page 9

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Berkeley, 1995.

Bollo, M., Mahin, S. Moehle, J., Stephen, R., and Qi, X., Observations and implications of tests on the
Cypress Street Viaduct test structure, UCB/EERC-90/21, EERC, UC Berkeley, December 1990.

Volume 2 Section 1 TAP Resumes - page 10

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Ross William Boulanger


Technical Advisory Panel

Profession
Civil Engineering Professor

Experience

Career Summary

24 years

Professor Boulanger is a world-renowned authority on


geo-seismic engineering and has published extensively
on pile foundations, seismic response, and liquefaction
subjects. In particular he led the recent research
sponsored by Caltrans on bridge pile foundations in
liquefied and laterally spreading ground.

7 years

Experience in Proposed Role

Relevant Project Experience


Select Consulting Assignments

Licenses and Registrations

Registered Professional Engineer: CA #


48837

Education

Ph.D. Geotechnical Engineering,


University of California, Berkeley
M.S. Geotechnical Engineering, University
of California, Berkeley
B.A.Sc. Civil Engineering, University of
British Columbia, Vancouver

U.S. Department of the Interior, Bureau of


RFP Criteria
Reclamation. Member, Consulting Review Board,
Licensed as a Professional Engineer in the
Scoggins Dam, Tualatin Project, Oregon (2011
State of California
present)
Registered Professional Engineer: CA #
California Department of Water Resources.
48837
Independent Review Committee, Delta Habitat
Currently or previously a tenure-tracked
professor in a public research university that
Conservation and Conveyance Program, CA (2010)
has a graduate PhD program in civil or
Los Angeles Department of Water and Power.
structural engineering
Member, Technical Review and Advisory Panel,
Headworks Reservoir Project, Los Angeles, CA (2009 Yes
At least 20 years experience in the following:
present)
-Liquefaction assessment and mitigation
California Department of Water Resources, Division
methods
of Engineering. Technical support for seismic
21 years
evaluation of B. F. Sisk Dam, CA (2007present)
At least 20 years experience in the following:
B.C. Hydro. Technical Specialist for review of seismic
- Seismic soil-structure interaction and
evaluations for the John Hart Powerhouse
design of deep foundations
Replacement and Dam Deficiency Investigation
21 years
Projects, Campbell River, BC, Canada (20092011)
Extensive experience in the practical
EBA Engineering Consultants, Ltd. Port Mann
application of seismology and ground
Highway Project, Seismic Engineering Review,
motions
Category 3 Checking for the Port Mann Bridge,
Yes
Vancouver, Canada (20092010)
PhD or DEng in Civil Engineering and/or a
ENGEO Incorporated. Technical Panelist for review
Civil or Geotechnical Engineer license
of Treasure Island geotechnical conceptual design
Yes
work, CA (20072008)
Design-Build Experience
U.S. Army Corps of Engineers. Technical Panelist for
See Select Consulting Assignments
review of seismic evaluations for Isabella Dam, CA
(2005present) and for Success Dam, CA (1999
present)
URS Corporation. Member, Seismic Review Panel for the Delta Risk Management Strategy
Project's seismic levee vulnerability studies, CA (20072008)
Terra / Ninyo & Moore Joint Venture. Member, Independent Review Board, San Pablo Dam
Seismic Upgrading Project, CA (20062007)

Volume 2 Section 1 TAP Resumes - page 11

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Recent Service and Special Assignments

Co-lead, Geotechnical Extreme Events Reconnaissance (GEER) team for the March 11, 2011,
Tohoku earthquake, Japan (2011)
Member, USSD Board of Directors, United States Society on Dams (2009present)
International Core Member, Center for Urban Earthquake Engineering, Tokyo Institute of
Technology, Tokyo, Japan (2007present)
Vice-Chair (2009 - present) and Core Member (20062009), Technical Committee No. 203
Earthquake Geotechnical Engineering, International Society of Soil Mechanics and Geotechnical
Engineering
Member, Research Committee, Pacific Earthquake Engineering Research (PEER) Center (2003
2010)
Chair (20042009), Co-chair (20002004) and Member (1996present), Earthquake Engineering
and Soil Dynamics Committee of the ASCE Geo-Institute
Team Member, International Familiarization of ISO Code for Geotechnical Earthquake
Resistant Design, New Energy and Industrial Technology Development Organization, Japan
(20052009)

Volume 2 Section 1 TAP Resumes - page 12

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Prof. Andrew Stuart


Whittaker, S.E., P.E.

Technical Advisory Panel

Profession
Professor of Civil and Structural Engineering

Experience
34 years

Experience in Proposed Role

Career Summary

20 years

Dr. Whittaker is currently Professor and Chair in the


Department of Civil, Structural, and Environmental
Engineering at the University at Buffalo (UB), former
Director of the NSF-funded NEES facility that is housed
in the Department, and Director of MCEER at Buffalo,
formerly the Multidisciplinary Center for Earthquake
Engineering Research. He was President (20052011) of
the Consortium of Universities for Research in
Earthquake Engineering (CUREE), which includes 26
research universities and 280+ affiliated faculty. Dr.
Whittaker has led the development of numerous multicampus, multidisciplinary proposals including the NIST
funded, $30M NEHRP Consultants Joint Venture (a joint
venture of CUREE and the Applied Technology Council).

Licenses and Registrations

Registered Professional Engineer: CA #


C045013, # S03618

Education

Ph.D., Structural Engineering, University


of California at Berkeley
M.S., Civil Engineering, University of
California at Berkeley
B.E., Civil Engineering, University of
Melbourne, Australia

Design-Build Experience
A30 Project, Canada

Caltrans Experience
Member, Caltrans UCSD SRMD Peer
Review Panel, 19972000
Member, Caltrans Statewide Seismic
Program Advisory Board, 19982001

Prof Whittaker is a world authority on performancebased seismic design, including structural design,
seismic protection technologies, ground motions and
soil-structure interaction, and has previously served on many technical review panels for major
infrastructure projects.

Dr Whittakers research interests have included large-scale physical testing of steel and reinforced
concrete structures, seismic isolators and energy dissipation systems, and development of design
procedures for bridges and buildings. In addition he has worked on seismic safety of critical
facilities, ground motions, soil-structure interaction and blast engineering.
Dr. Whittaker has provided extensive consulting, peer-review and expert-witness services. A focus
of his consulting work is the application of performance-based seismic design and advanced blast
engineering to tall buildings, bridges, and infrastructure.
Relevant Publications

Makris, N., Y. Roussos, A. S. Whittaker, and J. M. Kelly, Viscous heating of fluid dampers II:
large-amplitude motions, Journal of Engineering Mechanics, Vol. 124, No. 11, ASCE, Washington,
D.C., November 1998.
Bruneau, M., C. M. Uang, and A. S. Whittaker, Ductile Design of Steel Structures, McGraw-Hill, New York,
N.Y., September 1997

Whittaker, A. S., C. Rojahn, and G. C. Hart, Seismic response modification factors, Journal of
Structural Engineering, Vol. 125, No. 4, ASCE, Washington, D.C., April 1999.
Chang, S.-P., N. Makris, A. S. Whittaker, A. C. T. Thompson, Experimental and analytical
studies on the performance of hybrid isolation systems. Volume 31, No. 2, Earthquake
Engineering and Structural Dynamics, Wiley, London, pp 421-443, February 2002
Mosqueda, G., A. S. Whittaker and G. L. Fenves, Characterization and modeling of Friction
Pendulum bearings subjected to multiple components of excitation, Journal of Structural
Engineering, Volume 130, No. 3, pp. 433-442, March 2004.
Warn, G. and A. S. Whittaker, Energy-related demands on seismic isolators in bridges,

Volume 2 Section 1 TAP Resumes - page 13

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Proceedings, 13th World Conference on Earthquake


Engineering, Paper 3250, Vancouver, B.C., Canada,
August 2004.
Grant, D., G. L. Fenves and A. S. Whittaker,
Bidirectional modeling of high-damping rubber
bearings, Journal of Earthquake Engineering, Vol. 8,
Special Issue 1, pp 161-185, September 2004.
Warn, G. and A. S. Whittaker, Performance estimates
in seismically isolated bridges, Engineering Structures,
Vol. 26, No. 9, pp. 1261-1278, July 2004
Warn, G., A. S. Whittaker and M. C. Constantinou,
Vertical stiffness of elastomeric and lead-rubber
seismic isolation bearings, Journal of Structural
Engineering, Vol. 133, No. 9, ASCE, pp. 1227-1236,
September 2007.

Constantinou, M. C., A. S. Whittaker, D. M. Fenz and G.


Aposotolakis, Seismic isolation of bridges, Report to the
California Department of Transportation, Sacramento, CA,
June 2007.
Gulec, K., A. S. Whittaker and B. Stojadinovic, Shear
strength of squat rectangular reinforced concrete walls,
ACI Structural Journal, Vol. 105, No. 4, pp. 488-497, JulyAugust 2008.
Warn G. and A. S. Whittaker, Vertical earthquake loads on
seismic isolation systems in bridges, Journal of Structural
Engineering, Vol. 134, No. 11, ASCE, pp. 1696-1704,
November 2008.
Marin, C. C, A. S. Whittaker and M. C. Constantinou,
Experimental study of the XY-Friction Pendulum bearing
for bridge applications, Journal of Bridge Engineering, Vol. 14,
No. 3, pp. 193-202, May 2009

Kalpakidis, I. V., M. C. Constantinou, and A. S.


Whittaker, Modeling strength degradation in leadrunner bearings under earthquake shaking, Earthquake
Engineering and Structural Dynamics, Vol. 39, No. 13, pp.
1533-1549, November 2010.
Huang, Y.-N., A. S. Whittaker, N. Luco, and R. O.
Hamburger, Selection and scaling of earthquake
ground motions in support of performance-based
design, Journal of Structural Engineering, Vol. 137, No. 3,
pp. 311-321, March 2011.
Bolisetti, C. and A. S. Whittaker. Seismic structuresoil-structure interaction in nuclear power plant
structures, Transactions, 21st International Conference
on Structural Mechanics in Reactor Technology
(SMiRT 21), Paper 228, New Delhi, India, November
2011.

RFP Criteria
Licensed as a Professional Engineer in the
State of California
Registered Professional Engineer: CA #
C045013, # S03618
At least 20 years technical experience in the
analysis of large structures in the fields of
structural dynamics, performance-based
seismic engineering, wind engineering,
inelastic modeling of structural systems,
inelastic material and member models, and
behavior of steel member connections
20+ years
Published research results on at least 10
occasions in technical journals with a
national or international subscription base,
and have had research results or
recommendations based on research results
be adopted by at least one bridge design
code or standard that is adopted and in use
by the Department
Yes
At least 20 years experience in seismic
design and large-scale physical seismic
experimental research of large bridge
structures, research achievements include
the development of large-scale structural
testing techniques, seismic assessment and
retrofit of bridges in California
20+ years
Research of structural dynamics, windengineering, performance-based seismic
engineering, inelastic modeling of structural
systems, inelastic material and member
models for nonlinear structural analysis, and
computational tools for nonlinear analysis of
structures
Yes
Currently or previously a tenure-tracked
professor in a public research university that
has a graduate PhD program in civil or
structural engineering
Professor and Chair in the Department of
Civil, Structural, and Environmental
Engineering at the University at Buffalo
PhD in Civil Engineering
Yes
Extensive experience in the practical
application of seismology and ground
motions
Yes

Volume 2 Section 1 TAP Resumes - page 14

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Hugo Corres Peiretti

Technical Advisory Panel


Career Summary

Profession
Professor of Structural Concrete

Experience
36 years

Professor Corres currently serves as Chair of Structural


Concrete Department at the Civil Engineering School of
the Polytechnic University of Madrid, and as President of
FHECOR Consulting Engineers, Spains largest specialist
company in Structural Engineering. He was a member of
the team responsible for drafting the Spanish Structural
Concrete Code EHE, Spanish Codes on Actions in
Bridges IAP-96 and IAP-2011, Spanish Code for
Structural Steel (EAE), and the FIB Model Code.
Prof. Corres is the author or co-author of 20 books, and
author of more than 200 courses and conferences. He
has directed seven Ph.D. theses and participated in 33
research projects. He speaks Spanish, English, and
Italian.

Experience in Proposed Role


20 years

Education

Licenses and Registrations

Relevant Project Experience


Arbizelai Viaduct, Client: Laurena CJV (Dragados
OSSA Moyua), Gipuzkoa, Spain ($19 million)
Construction Project and Technical Assistance to the
Contractor, 2009

Cable-stayed bridge of 461-foot span with steel pylon and


composite deck. The viaduct is 1,341 feet long, composed
of six spans. The single dual-carriageway deck varies from
8290 feet with a depth of 8.7 feet. The deck is a bicellular
box girder with a trapezal shape. The cantilevers of the
upper concrete slab are supported by steel struts
connecting the bottom flange of the box girder to the end
of the cantilever.
Noia Viaduct, Client: Regional Government of Galicia
(XUNTA de Galicia), A Corua, Spain ($38 million)
Construction Project, 2010

Chair of Structural Concrete Department


at the Civil Engineering School of the
Polytechnic University of Madrid
Ph.D. in Civil Engineering. Polytechnic
University of Madrid
Degree in Civil Engineering (M.Sc.)
Polytechnic University of Madrid.
Licensed Professional Engineer in Spain
Presidium Member of FIB (Fderation
Internationale du Bton)
Former president of ACHE (Spanish
Scientific and Technical Association for
Structural Concrete)
Doctor Honoris Causa by the
Technological University of Bratislava

RFP Criteria
At least 20 years experience in bridge design
23 years
Engineer-of-record on large complex bridge
(segmental, cable supported, structural
steel, etc) projects
Suspension Bridge over the River
Vinalop
Arch Bridge over El Burguillo Reservoir
Bridge over the Sil River
Segmental Bridge at Manzanal del Barco
Hybrid suspension and cable-stayed
Bridge over the Oria River
Cable-stayed bridge over Noia estuarine
in Noia
Pavilion-Bridge over the Ebro River for
the 2008 World Exhibition
Cable-stayed bridge Arbizelai
Segmewntal Bridge over the Tajua
Centura Cable-Stayed Bridge Structure
Arch Bridge over the Dambovita
Cable-stayed Bridge over River Tagus

Cable-stayed bridge of 335-foot span. The total length of


the Noia viaduct is 4,822 feet, divided into 46 spans. The
deck is 44 feet wide, including two-lane roadway and
pedestrian lane. The longest span, over the entire navigable canal, constitutes a cable-stayed solution
with a single pier placed on the axis of the deck.
Centura Cable-Stayed Bridge, Client: FCC, Bucharest, Romania ($10 million)
Construction Project and Technical Assistance to Contractor, 2011

The cable-stayed Centura Bridge has a 115+279+279+115 span distribution, with a 154-foot-high
central pylon (397 feet over the deck) and two intermediate piers. The deck, 66.6 feet wide, is made
up by two steel caissons 8.2 feet wide at the bottom, with top flanges of 1.6 feet, so the total width

Volume 2 Section 1 TAP Resumes - page 15

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

of the longitudinal beam is 9.8 feet. Both caissons are


joined together by cross girders conserved pin-connected
to the longitudinal girders.
Footbridge in San Juan de la Cruz over the Carrin
River, Client: COPASA, Palencia, Spain ($0.5 million)
Construction Project and Technical Assistance, 2004

This cable-stayed curved footbridge of 232-foot span has a


radius in plan of 148 feet and is 9.8 feet wide. The deck of
the bridge consists of a triangular steel section with a
depth of 2 feet. The tubular suspension mast is placed on
the concave side of the footbridge. It is 59 feet high and
made up of a circular steel section.
Bridge over the Oria River, Client: Regional
Government of Gipuzkoa, Orio, Spain ($45 million)
Construction Project, 2011

This hybrid suspension and cable-stayed bridge has a main


span of 591 feet and two compensation spans of 207 feet,
with a deck 72 feet wide. The piers are made of highstrength concrete with a cross section of 6.6-foot
diameter.
Bridge over the Tagus River (Tender Project), Client:
FCC, Conduril, Impregilo, Cimolai CJV, Lisboa,
Portugal ($1.0 billion)
Tender project, 2009

This 1,770-foot-span cable-stayed bridge will carry highspeed railway to Lisbon. It consists of a cable-stayed
bridge with spans five spans of 192+192+1770+192+192
feet, a record for a high-speed rail bridge. This bridge
represents a technological challenge for its main span, the
magnitude of earthquake expected in the area, and the
presence of land with little foundation bearing capacity
(piling 245 feet deep). The bridge has a two-level deck; the
upper level is 305 feet wide for 6 lanes, while the lower
level has a width of 225 feet for 4 rail tracks. The pylons
are A-shaped of very lightweight concrete, with a total
height of 650 feet. Each leg of the tower is anchored by
piles of 8.2 feet in diameter.
A30 motorway, Client: NA30CJV (Dragados-AccionaAecon-Verreault), Montreal, Canada ($330 million)

Project and technical assistance to the contractor, 20112012

The bridge over the Beauharnois Canal has a total length


of 8,366 feet, 4,774 feet of which has a composite box
girder deck and the rest precast concrete beams. The metal
section has 12 spans of 268.7 feet and a main span of 492
feet. Hugos role in this project is the definition of the
launch of the steel deck and the design of temporary
works. The launch is complicated by the fact that the
section has a longitudinal slope and a parabolic elevation.

At least three cable-supported


vehicular/rail/pedestrian bridges
Centura Cable-Stayed Bridge
Noia Viaduct
Arbizelai Viaduct
...At least one bridge needs to be a cablestayed structure with a main span length of
at least 700 feet between center lines (or a
main span length of at least 400 feet)
Railway Bridge over River Tagus, main
span of 1,771 feet
Arbizelai Viaduct, main span of 461 ft
At least 20 years technical experience in the
analysis of large structures in the fields of
structural dynamics, performance-based
seismic engineering, wind engineering, inelastic
modeling of structural systems, inelastic
material and member models, and behavior of
steel member connections
23 years
Published research results on at least 10
occasions in technical journals with a
national or international subscription base,
and have had research results or
recommendations based on research results
be adopted by at least one bridge design
code or standard that is adopted and in use
by the Department
Yes
Research of structural dynamics, windengineering, performance-based seismic
engineering, inelastic modeling of structural
systems, inelastic material and member
models for nonlinear structural analysis, and
computational tools for nonlinear analysis of
structures
Yes
Currently or previously a tenure-tracked
professor in a public research university that
has a graduate PhD program in civil or
structural engineering
Yes
PhD in Civil Engineering
Yes
Geotechnical/foundation design experience
on no less than five long-span (more than
300 feet per span) bridge structures in the
past twenty years
Segmental Bridge at Manzanal del Barco
Hybrid suspension and cable-stayed
Bridge over the Oria River
Bridge over the Sil River
Arch Bridge over El Burguillo Reservoir
Suspension Bridge over the Vinalop
Pavilion-Bridge over the Ebro River
Cable stayed bridge Arbizelai

Volume 2 Section 1 TAP Resumes - page 16

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Luis Ortuo Abad

Technical Advisory Panel

Profession
Civil Engineer. Geotechnical Consultant.
Lecturer on Geotechnical Engineering

Experience

Career Summary
Mr Ortuo started his professional career in 1985, in the
Geotechnical Engineering Department of Agromn (a
large construction company, now a part of Ferrovial)
under the supervision of Prof. A. O. Uriel. During that
time, he took part in many geotechnical projects within the
broad spectrum of jobs undertaken by a major
construction company. In 1987 he was awarded the C.H.
Roberts Bequest by the Institution of Civil Engineers
(UK), and the Caada Blanch Grant by the British
Council, and entered the Imperial College of Science and
Technology (London). He obtained his MSc degree in Soil
Mechanics with Distinction and was awarded the Soil
Mechanics Ltd. Prize.
Back in Spain, he was entrusted with the direction of the
Geotechnical Engineering Department of Agromn, until
he enrolled in Uriel & Asociados, S.A. in 1990, first as
Technical Director and now as General Director.
Mr. Ortuos experience covers a wide range of
activities. He has provided answers to the technical
needs of a varied customer portfolio, comprising
national and international administrations and
companies, architecture and engineering firms,
construction firms, industrial and real estate developers,
official bodies, etc.

29 years

Experience in Proposed Role


27 years

Licenses and Registrations

Civil Engineer (#8047)

Education

Diploma of Imperial College (DIC) in Soil


Mechanics. University of London.
MSc in Soil Mechanics (Distinction),
Imperial College of Science and
Technology. University of London.
Civil Engineering. Universidad Politcnica
de Madrid.

RFP Criteria
At least 20 years experience in the following:
-Liquefaction assessment and mitigation
methods
Yes
At least 20 years experience in the
following: - Seismic soil-structure interaction
and design of deep foundations
Yes
Extensive experience in the practical
application of seismology and ground
motions
Yes
Geotechnical/foundation design experience
on no less than five long-span (more than
300 feet per span) bridge structures in the
past twenty years
Third Bridge over the River Tajo, Lisbon
New Bridge over the River Guadalhorce.
A-7 Motorway.
Arbizelai viaduct. AP-1 Motorway.
Basagoiti viaduct. Ap1 Motorway.
Vinalop River Bridge.
PhD or DEng in Civil Engineering and/or a
Civil or Geotechnical Engineer license
Yes

His particular focus during the last 15 to 20 years is in the


geotechnical supervision of a large number of motorway
and high-speed railway projects, covering more than 500
miles of constructed roads and railways. This includes the
supervision and revision of every geotechnical aspect
related to this type of construction, from the initial
geological interpretation to the detailed analysis of the
design of embankments and cuts, foundation of bridges,
seismic hazards, tunnels, etc. He is also presently involved
in the geotechnical supervision of the construction works
of a number of high-speed railway lines.
Mr Ortuo has published several papers in specialized journals and conferences related to
geotechnics, both nationally and internationally. Mr. Ortuo is currently Senior Lecturer on Soil
Mechanics and Geotechnical Engineering at the Universidad Politcnica de Madrid. He conducts
lectures on Geotechnics (Year 4) and Constitutive Equations for Soils (doctorate course). He is also
in charge of a specialized course titled Special Foundation Procedures (Year 6). He is a lecturer in
several official MSc courses (CEDEX, AETOS, MC2), and is frequently invited to present
conferences for other specialized courses.

Volume 2 Section 1 TAP Resumes - page 17

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Relevant Project Experience


Third River Tajo Bridge, Lisbon
Geotechnical Designer. 2010

Five-mile-long, double-decker, high-speed railway/motorway bridge over the Tajo River in Lisbon.
The client was FCC. The maximum span of the central part of the bridge (cable-stayed) is 1,377 feet.
The foundation of the central pillars consists of in situ piles 197 feet in depth. Due to the
characteristics of the existing soil profile, formed by alluvial soft deposits reaching 213 feet in
thickness, and the high seismicity of the construction zone, a main topic of analysis in this case was
the design of the foundations of the bridge in combination with seismic properties of the foundation
soils, including their liquefaction potential. Determination of the applicable dynamic parameters and
the performance of dynamic calculations constituted a key factor in the geotechnical design. Special
analyses were also carried out on the construction constraints of the complex tidal regime of the
estuary and its implications.
Mr. Ortuo and his team at Uriel & Asociados, were in charge of the geotechnical analysis and the
foundation design. Selected as a preferred bidder, the project is stopped at the present moment due
to the present economic downturn.
Motorway A-7New Bridge over the River Guadalhorce. Mlaga West Ring Road (Spain).
Owner: Ministry of Public Works
Geotechnical Designer, 2006

Included in the new motorway project are two large new bridges 2,755 and 1,902 feet long. One of
them, the Guadalhorce Viaduct, has a central span reaching 446 feet in length. The existing soil
profile is constituted by quaternary soft and loose soils some 100 to 130 feet in thickness, overlying a
plio-quaternary and miocene deposits. The foundations of the bridge were solved by means of 6- to
6.5-foot-diameter piles, 115 to 165 feet in length. The approaching embankments required
preloading and the installation of wick drains. The high seismicity risk of the site, (ab=0,11 g;
ac=0,16 g), required the performance of nonlinear dynamic calculations, based on an appropriate
determination of the corresponding soil dynamic parameters.
Mr. Ortuo and his team at Uriel & Asociados, were in charge of the geotechnical interpretation and
the foundation design.
Motorway AP-1. Eskotiatza Arrasate. Guipzcoa (Spain). Owner: Bidegi (Local
Administration)
Geotechnical Designer, 2004

Located within the mountain region of the Spanish northern province of Guipzcoa, this 6.3 km
motorway extension includes 3 tunnels and 2 singular viaducts.
Arbizelai viaduct is a 408 m long cable-stayed bridge, with two abutments and 5 pillars. Its central
span is 140 m long. The ground profile consists of interlayered calcareous sandstones and
limestones. Foundations by means of footings were designed and constructed, with allowable
bearing pressures from 43 to 102 psi.
Basagoiti Viaduct is formed by two separate bridges (two lines) of 1,280 and 1,400 feet in length
respectively. Their maximum central spans reach some 410 feet, and are solved by V-shaped pillars.
The foundation ground is formed by sandstones and laminated claystones. The foundations system
consisted of footings working at average vertical pressures of 58 to 87 psi. However, one of the
pillars laid upon an ancient colluvial landslide, and had to be founded by means of large-diameter
piles embedded into the rock substratum.
Mr. Ortuo and his team at Uriel & Asociados, were in charge of the geotechnical analysis and the
foundation design.

Volume 2 Section 1 TAP Resumes - page 18

1.1.2
Design Management Concept

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

1.1.2 Design Management


Concept
RFP ITP Appendix B 1.1.2; D 1.1.1(a)

Shimmick/FCC/Impregilo (SFI) has assembled an experienced and diverse design team to


meet the specific design challenges of the
Project. We have combined international
expertise in bridge design, aesthetics and technical specialtieswith local design experience
and familiarity with the requirements of the
Port and Caltrans. The design team includes
engineers with technical expertise in the design
of geometrics, utilities, drainage, roadway, cablestayed bridges, the construction of concrete box
bridges, installation of foundations in challenging soils.

1.1.2.1 Design Challenges


The development of a Design Management
Plan begins with a clear understanding of the
challenges the design team will face to produce
an outstanding bridge that exceeds the key
design goal: to provide a world-class iconic
structure that will serve as a landmark for decades to come. SFI team has identified 11 key
design challenges for the Project:
1. Improve the geometric arrangement to eliminate design exceptions, improve safety, and
return to the Port land that can be used for
revenue generating operations.
2. Identify the aesthetic features that define an
iconic structure in the raw industrial setting
of the Port and integrate all architectural
elements to achieve that aesthetic.
3. Design the cable-stayed bridge as the most
elegant and efficient structure possible.
4. Provide the long-term durability and low
maintenance expected for modern bridges.
5. Integrate the approach bridges seamlessly
with the cable-stayed bridge.
6. Optimize the substructures and foundations
for the varying demands on the high
approach, low approach and ramp bridges.
7. Develop the least intrusive foundations,
minimizing excavation, the potential migration of the benzene plume, and dewatering.
8. Rigorously address the impacts of seismicinduced soil liquefaction on the deep
foundations in a site with a highly stratified,
depth varying subsurface profile.
9. Provide a safe and convenient Class I bike

SFI Advantages
Local design resources with proven experience
in achieving design approvals with Caltrans.
World-class experience in cable-stayed design of
similar structures to the GDB.
Internationally-acclaimed Technical Advisory
Panel to independently review complex structure
and seismic design issues.
Integrated Design Packages schedule to give the
Port & Caltrans proper review periods.

path fully integrated into the bridge design.


10. Minimize and manage impacts to Port
tenants trucking operations and the public
through reduced number of construction
stages during construction.
11. Sequence the design to allow construction to
start early with full design reviews and
approvals by the Port.

1.1.2.2 Design Organization


Structure
RFP ITP Appendix B 1.1.2 (i,iv)

The design team lead is Arup. Arup is an ISO


9001 certified, international firm of 10,000
designers, planners, engineers, consultants and
technical specialists providing a broad range of
professional services. The Design Team will be
assisted by several talented subconsultants that
bring added resources to allow the design team
to advance multiple design packages in parallel
paths (Table 1.1-1 on page 1-3).
Organization
Design Manager, John Karn

Reporting directly to the Project Manager (PM)


and Design-Build Manager (DBM), the Design
Manager will provide management for the overall design and coordinate the design issues with
the Port and the SFI. The design team will be
organized into seven disciplines, with the Discipline Leads reporting to the Design Manager.
Mr. Karn will be responsible for managing the
resources so that all of the design work packages are accomplished on schedule. Together
with the DBM, he will integrate the design team
into the construction organization.
Cable-Stayed Bridge Lead, Senna
Kumarasena

The Cable-Stayed Bridge Lead Designer, an


experienced designer of long-span bridges, will

Volume 2 Section 1 page 1

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

oversee the design, plans and specifications for


the cable-stayed bridge as well as the global
seismic modeling of the entire bridge. His team
will focus on streamlining the cable-stayed
bridge to the most elegantly simple and efficient
structure possible and integrating the approach
bridges seamlessly with the cable-stayed bridge.
Direct reports: Deputy CSB Lead Designer,
Superstructure Lead, Substructure Lead, and
Lead ATVA/Blast Specialist.
Approach Bridges Lead, Kwong Cheng

The Approach Bridges Lead Designer will oversee the design, plans and specifications for all of
the approach bridges, with major support from
the experienced designers of BCA. He will
focus on the early completion of the design of
the approaches while the design of the cablestayed structure proceeds on its own path.
Direct reports: Approach Superstructure and
Approach Substructure Leads. The foundations
and substructure packages will be advanced
ahead of the superstructure to allow early construction.
Geotechnical Engineer
of Record, Kul Bhushan

bike path fully integrated into the design of the


bridge, and minimize impacts to Port tenants
trucking operations by reducing right-of-way
impacts. Direct reports: Geometric & Signing
and Pavement Marking Engineering and the
Traffic Control Manager.
Lead Civil Engineer, Duanne Gilmore

The Lead Civil Engineer, knowledgeable in


geometry, roadway and drainage disciplines, will
oversee all other aspects of civil design, including pavement design, drainage and stormwater,
signalization, lighting, ITS, railroad and surveying, with all plans and specifications. He will
advance these design elements for inclusion into
the early structure release for construction
packages. His team will seamlessly integrate ITS,
lighting, drainage and ancillaries into the design.
Direct reports: Pavement Engineering Lead,
Drainage Engineering Lead, Storm water Engineering Lead, Signalization Engineering Lead,
Lighting Engineering Lead, ITS Engineering
Lead, Railroad Engineering Lead, and Surveying
Manager.

During the procurement period, the geometrics team proposed several alternative
technical concepts that reduced the right-ofway necessary to construct the Project.

The Geotechnical
Engineer of Record will
oversee the site
investigation, pile load testing, determination of
geotechnical design parameters and assessment
of liquefaction potential, lateral ground movements and pile down drag. He will be supported
by Leighton Group in the geotechnical
investigations and Bittner-Shen in the design of
the foundations for the towers and end-bents.
Mr. Bhushans team will develop the least intrusive foundation schemes, minimizing excavation
and dewatering, and rigorously addressing the
impacts of seismic- induced soil liquefaction on
the deep foundations. Direct reports: Certified
Engineering Geologist, Foundations Lead, the
Site Investigation Lead, Retaining Structures
Lead, and Embankments & MSE Walls Lead.
Roadway Lead, Natalina Bernardi

The Roadway Lead Designer, highly experienced in urban roadway design, will oversee
the design of geometrics, maintenance of traffic
(MOT), and signing and pavement marking. She
will continue to improve the geometric arrangement, provide a safe and convenient Class I

Maintenance Facility
Lead, Tom Myers

The Maintenance Facility


Lead Designer, experienced in multi-disciplinary building design, will oversee the design of
the new maintenance facility, including architectural, structural, mechanical, electrical and
plumbing design, with all plans and specifications. Mr. Myers will be supported by an array
of building disciplines from the supporting
subconsultants. He will focus on the challenge
of providing a new, modern and highly functional maintenance building that will support
and enhance Port operations. Direct reports:
Facilities Design Architecture, Structural
Engineering, Mechanical Engineering, Electrical
Engineering, and Plumbing Engineering Leads.
Visual Quality Manager, Michael Painter

The Visual Quality Manager (VQM) will oversee all aspects of the aesthetics of the Project
and will be responsible for coordinating the
work of the Bridge Architectural Designer, the
Architectural Lighting Designer, the Landscape
Architect, and the Visual Quality Graphics Support Team. Working closely with the architectural team and the Lead Designers, he will focus

Volume 2 Section 1 page 2

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

on the challenge of identifying the aesthetic


features that defines an iconic structure in this
setting and integrating all architectural elements
to achieve the aesthetic goals. The VQM will be
a key person in public outreach and the primary
point of contact with the Visual Quality Advisory Team assembled by the Port. Direct
reports: Project Bridge Architectural Design,
Project Architectural Lighting Design, Landscape Architecture, and Visual Quality &
Graphic Support Leads.
Distribution of Tasks
To ensure adequate resources are available to
accomplish the design work, responsibility for
design production will be distributed among the
Design Team as shown in Table 1.1-1. Each
firm is committed to providing the designers
and support staff required to accomplish their
assigned tasks on schedule, in close cooperation
with the entire SFI Team, and to fully support
the SFI Team in public outreach and third party
consultations and approvals.
Co-Location of Design Personnel
To ensure smooth coordination and communication, an Integrated Project Office (IPO) will
be established at the start of the Project. While
design production will largely remain in the
respective offices of the design team firms, it
will be coordinated from the IPO, and certain
design production tasks that are crucial to
smooth design-build coordination will be
undertaken directly in the IPO.
Task
Cable Stayed Bridge
Cable Stayed Bridge Foundations
Approach Bridges
Approach Bridges Foundations
Geotechnical
Roadway Design
Maintenance of Traffic
Traffic Modeling
Civil Engineering
Maintenance Facility Design
Visual Quality Management
Bridge Architecture
Architectural/Roadway Lighting
Landscape Architecture

Firm
Arup/A&W
Bittner-Shen
OPAC
Group Delta
Group Delta/
Leighton
BKF Engineers
BKF Engineers
Arup
Arup
Ware Malcomb
MPA Design
Keith Brownlie
Arup SF
Mia Lehrer

Table 1.1-1: Distribution of the work among the


design team plays to the strengths of each member,
drawing on their specialized skills and experience.

The Design Manager will be co-located in the


IPO full time for the duration of the Project,
assisted by co-located Deputy Coordinators as
needed. Key design tasks that will be co-located
full time in the IPO include geometrics, roadway, MOT, utility and drainage/stormwater
engineering. A number of design support engineers, including geotechnical, structural and
civil, and CAD support will also be co-located
full time in the IPO. The geotechnical site
investigation, pile load testing and project surveying will be run entirely out of the IPO as
well. Other discipline leads will be present in the
IPO part time as needed for face-to-face meetings and coordination, including geotechnical,
structures and visual quality. A full construction
support team will be based in the IPO for the
duration of construction.
Those team members not co-located will be
fully integrated into the Design Team via faceto-face meetings, teleconferences, video conferences, intranet sites and project integration
web-based software. The project integration
software will house all the common information
that team members require for Scopes, Budgets,
Schedules, Quality Management, Safety, and
Security, as well as design. These tools will allow
for the most efficient sharing of information
and will allow the Design Team to virtually
work around the clock. The co-location of
design team in the IPO will facilitate close
cooperation with the Port and Caltrans,
particularly over the shoulder design reviews
to obtain their regular and timely input.
UDBE Involvement
The design team will strive to make the contractual goal of 11% UDBE participation with
the involvement of OPAC and Mia Lehrer +
Assoc. Additional UDBE companies will be
subcontracted on an as-needed basis as the
Project continues.

1.1.2.3 Technical Advisory


Panel
RFP ITP Appendix B 1.1.2 (ii)

The SFI team will convene an external Technical Advisory Panel (TAP) comprising nationally and internationally recognized specialists
and experts to provide independent advice and
recommendations on complex technical design
and construction issues, particularly questions

Volume 2 Section 1 page 3

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

of seismic analysis and design. The members of


the panel are:
Structural/Bridge Analyses and Design
Expertise, Prof. Niels Gimsing
Earthquake Engineering, Andrew Whitaker
Structural Engineering Research Expertise,
Dr. Fabio Brancaleoni
Geotechnical Engineering, Dr. Ross Boulanger
Bridge Construction, Luis Viuela
The TAP will collectively provide expertise in:
Structural and Bridge Analysis and Design,
including long span cable-stayed bridges.
Structural Engineering Research in seismic
design, structural dynamics, wind design, and
nonlinear analysis of structures.
Bridge Construction, including long span
cable-stayed bridges.
Geotechnical Design, including liquefaction
assessment and seismic soil-structure interaction.
The TAP will meet at least four times a year, as
requested by the SFI Team, the Port, or Caltrans and meetings will be open to any of the
above or other issues that the Port or Caltrans
may want to discuss. The meetings will be scheduled prior to design submittals, with relevant
materials provided to the panel members in
advance of the meetings. The TAP will prepare
written reports to both the SFI Team and the
Port containing their comments and recommendations within five days of each review
meeting. The SFI Team will prepare written
responses to the comments and recommendations and reach resolution with the TAP on
each. The resolved recommendations will be
incorporated into our analyses and designs.
As can be seen in the organizational charts, the
TAP is independent of the design team and will
be coordinated by the DBM to conduct an
independent review of bridge design and procedures and advise the Design Teams responsible
engineer on the design and construction of the
Main Span Bridge and the Approach Bridges.

1.1.2.4 Design Sequencing


RFP ITP Appendix B 1.1.2 (iii)

The design work will reflect the fast-track


approach of design-build and will be sequenced
to support the construction schedule while still
meeting the submittal and review requirements

in the RFP. To control this sequencing, we will


prepare a detailed, logic-driven Design Schedule
to ensure that all design and submittal tasks are
understood and accounted for, and the construction schedule can be supported.
Construction Priorities
Since access to critical properties on the east
side of the channel will not be available at the
start of the Project, and overhead construction
using a Movable Scaffolding System (MSS) is
most efficient if uninterrupted, construction of
the approach bridges will proceed continuously
from west to east. The design of the approach
bridges will be sequenced to support this construction approach.
Initial Submittals
A number of initial design tasks must begin
immediately after NTP1 in order to maintain
the project schedule. These include preparing
and submitting the Visual Quality Management
Plan, Geotechnical Task Execution Plan, and a
Column Testing Plan. Approval of these plans will
permit the design team to advance the geotechnical site investigation and column testing,
which are critical path items. The Accident and
Terrorism Vulnerability Assessment will also be
initiated during this start-up phase.
Concept Design Submittals
The next design tasks on the critical path are the
Conceptual Geometric Plan, followed by the Concept Design Submittals and Type Selection. The
design team will advance these submittals as
high priorities to obtain approval expeditiously.
Key to expeditious approval will be early
involvement of the TAP and timely resolution
and incorporation of their comments and recommendations.
Design Packages
Table 1.1-2 shows the various design packages
required to support the construction schedule.
We have divided the design into packages by
discipline on the west and east side of the channel. Since we will start work on the west side of
the channel, these will be the first packages
released for construction. We will first complete
the maintenance of traffic (MOT) Plans and the
Utility Relocation Plans to allow the detours to
be placed and utilities relocated before building

Volume 2 Section 1 page 4

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

RFC Mos.
from
NTP1

acclaimed Technical Advisory Panel to conduct


the foundations for the low level approaches
an independent review of bridge design and
(LLAs). For the structures, we will divide the
procedures and advise the design teams responplans after the Intermediate Submittal into
sible engineer on the design and construction of
foundations/ substructure and superstructure.
the Main Span Bridge and the Approach
We will then advance the foundations and subBridges.
structure to release for construction status so
that we can start construction on the foundaThe design team will be fully integrated with the
tions.
construction team in the IPO and the value
added Design-Build Manager will facilitate interThe cable-stayed bridge has its own design
face between design and construction and oversequence, with the tower substructures as part
the-shoulder reviews with both the superintenof the superstructure. Package 20 is the
dents and the Port.
remainder of the Caltrans plan elements for the
entire Project.
Independent modeling will be performed under
the direction of the Cable-Stayed Bridge Lead
Designer and the Approach Bridges Lead
Designer to advance the designs. Additionally, a
global non-linear time history model of the
entire bridge will be developed under the
direction of the Cable-stayed Bridge Lead
Designer from the independent designs for
final checking of seismic performance. Timely
review and comment on the time history mod- No. Design Package
1
West MOT & Staging Plans
6
eling will be a key early topic for the TAP.
Final Design Submittals
The design packages for the walls, the port
access undercrossing, and the west approach
bridges will be submitted first (sequenced to
respect the submittal limitations in the RFP) as
these segments will be constructed first. The
corresponding packages for the cable-stayed
bridge will follow a longer submittal sequence,
as those packages will have longer development schedules. The east approach bridges will
lag behind, as they will be constructed later
than the west approach bridges.

2
3
4
5
6
7
8

9
10
11
12
13

1.1.2.5 Conclusion

14

SFIs Design Management Plan provides a


detailed efficient management concept and
design sequencing that supports a fast-track
construction approach. We will provide both
local and international resources to design a
world class cable-stayed bridge with long-term
durability and low maintenance that is seamlessly integrated with the approach bridges.
The technical subconsultants help us ensure
that we have sufficient resources to complete
the design on schedule.
We have assembled an internationally

15
16
17
18
19
20
21
22

West Utility Relocations


East Utility Relocations
Port Access Undercrossing
West Retaining Walls
Rail Realignment Plans
West LLA (A/E Lines) Foundations &
Substructure
West HLA (A/E Lines) Foundations &
Substructure
West LLA (A/E Lines) Superstructure
West HLA (A/E Lines) Superstructure
East MOT & Staging Plans
East Retaining Walls
East HLA (B/C Lines) Foundations &
Substructure
East LLA (B,S Lines) & Ramps (C,N,R)
Foundations & Substructure
East HLA (B/C Lines) Superstructure
East LLA (B,S Lines) & Ramps (C,N,R)
Superstructure
CSB Foundations
CSB Substructure & Articulation
CSB Superstructure & Ancillary
Roadway, Drainage, Signing, PD, Lighting, Signals, ITS
Highway Planting and Irrigation
Maintenance Facility Plans

4
9
9
9
10
8
10
11
13
10
13
12
13
15
16
11
14
18
14
14
14

Table 1.1-2: Design packages support the construction


schedule. Key: MOT = maintenance of traffic; LLA = low
level approach; HLA = high level approach; CSB = cablestayed bridge.

Volume 2 Section 1 page 5

1.1.3
Construction Management Concept

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

SFI Advantages

1.1.3 Construction
Management Concept
RFP ITP Appendix B 1.1.3; D 1.1.1(b)

SFI has assembled a highly-skilled team to


successfully deliver this Project through from
Proposal to completion. The same team
leading the development of the Technical and
Price Proposals, as well as the preliminary
design and estimate, will lead the design and
construction work, ensuring this knowledge is
incorporated into the Project.
The construction organization shown in Section 1.1.1 is designed to effectively manage all
aspects of the Project and leave no work without proper leadership and resources. Through
our detailed construction approach, we have
divided up the work among specific technical
disciplines: cable-stayed, foundations, structures,
civil and utilities, traffic control, and electrical.
Each discipline has an experienced manager and
the correct resources to oversee the work.

1.1.3.1 Construction
Organization Structure,
Resources & Personnel

RFP ITP Appendix B 1.1.3(i-ii); Appendix D 1.1.1(i-iii)

Efficient allocation of the proper personnel and


resources necessary to successfully manage the
Project from NOA to completion.
Technical resources with experience on cablestayed bridges around the world.
Key managers with success on local complex
design-build & Caltrans transportation projects.
Key superintendents who have worked locally
for the last 20 years.
Established working relationships with all the
local crafts unions.
Independent safety and quality management
which assures a quality project and a safe, efficient workplace.
Project Manager (PM), Giorgio Desideri

The Project Manager (PM), Giorgio Desideri,


will be responsible for the overall execution of
the Project from design through commissioning, and he will be the direct point-of-contact
with the Port. The PM will ensure that all of the
major programs are in harmony (for example,
design, construction, quality, public information, environmental compliance) to ensure the
technical requirements are met for each discipline. The PM will chair a weekly meeting with
the various discipline managers to ensure
proper communication is maintained and all
project issues are being addressed. The PM will
prioritize all activities to ensure operations
needs are met through the appropriate
management of the available resources.

SFIs organizational structure was developed to


provide a highly experienced integrated management team that will apply not only worldclass expertise in cable-stayed structures but a
seamless design-build management approach.
The organizational structure will ensure that
Deputy Project Manager (DPM), William A.
each discipline of the
Corn, P.E.
Project is overseen by
Initial Startup Involvement
The Deputy Project
highly experienced staff.
The same team that developed the SFI proManager (DPM), William
posal will be ready to continue the work at
Executive Management
A. Corn, will assist the
project start up, building on the preliminary
Committee
Project Manager in overdesign and work plans that they created,
seeing all aspects of the
The Executive
and bringing with them an intimate knowProject. Mr. Corn has
Management Committee, ledge of the Project and our solutions.
extensive experience in
consisting of top-level
constructing Caltrans
members of each joint venture partner, will
highways
and
structures
over the last 20 years.
guarantee that the correct resources will be
The
DPM
will
work
closely
with the PM to
committed at every phase. To ensure the same
ensure
that
the
project
is
administered
and contype of independence as the Quality Manager,
structed
according
to
Caltrans
and
other
local
SFI will have the Safety Manager also report to
standards.
the Executive Management Committee, while
he will directly report to the Project Manager
To maintain an on-going focus on safety, Mr.
for day-to-day and week-to week coordination.
Corn will support the Safety Manager by working directly with each superintendent to identify

Volume 2 Section 1 page 6

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

safety risks and address those risks during the


design phase. This includes access requirements,
identifying and addressing hazards, and ensuring
all construction staff are properly trained.
Mr. Corn will coordinate with the Quality Manager to ensure the proper plans and specifications are used in construction.
Design-Build Manager (DBM), Robert M.
Schraeder, P.E.

The Design-Build Manager (DBM), Robert M.


Schraeder, P.E., will maintain continual integration between the design and construction teams,
including overseeing the proper sequence of
design document preparation to keep the construction schedule on track. The DBM will
coordinate constructability reviews, value engineering, and technical work groups. The DBM
will also oversee utility coordination and design,
to ensure that design and construction are not
impacted by utility delays.
Design Manager, John Karn, P.E.

The Design Manager, John Karn, reporting


directly to the Project Manager and the DBM,
will manage all designers and disciplines for the
Design Team. He will be responsible for
coordination and cooperation between design
firms and between disciplines, and for seeing
that all of the design work is accomplished on
schedule. Together with SFIs DBM, he will
integrate the design team into the SFI Team to
ensure that the needs, preferences, capabilities,
expertise and experience of our partners are
incorporated in the designs.
Quality Manager, Piyush Mehta

Although the Quality Manager will report


directly to the Executive Committee, he will
functionally report to the PM regarding the dayto-day logistics, Piyush Mehta will have stopwork authority and will have no production
responsibilities.
Mr. Mehta will begin work at the start of design
and continue through the construction phase.
He will coordinate closely with the Port on all
quality activities to ensure that all testing and
inspections are completed before the next phase
of work.
The Construction Quality Manager and the
Design Quality Manager will report to Mr.
Mehta, along with a full quality team of inspec-

tors and an independents lab.


Steve Wilson, Safety Manager, CHST

Like the Quality Manager, the Safety Manager


will functionally report to the PM regarding the
day-to-day logistics and have stop-work authority. Mr. Wilson will have no production responsibilities. Mr. Wilson will begin at the start of
design and continue through the construction
phase. Mr. Wilson, or a safety representative,
will always be onsite during construction.
Construction Manager, Guillermo Castao

Construction Manager, Guillermo Castao, with


worldwide extensive cable-stayed experience,
will oversee construction of the Project. The
Construction Manager has divided the construction based on technical expertise and the
progression of the work. Managing the various
elements of the work are the Cable-Stayed Manager, the Civil and Utilities Manager, the Electrical Manager, the Foundations Manager, the
Traffic Control Supervisor and the Structures
Manager.
Mr. Castao will work directly with each of the
construction disciplines to develop summary
level production goals (for example, durations
for foundation construction, utility relocation,
superstructure construction) and daily tracking
methods to ensure the proper resources are
assigned. Mr. Castao will coordinate all of
these discipline resources to ensure that the
project stays on schedule and quality is not
compromised. Mr. Castao will also coordinate
with the DBM to conduct constructability
reviews so that the design packages meet the
Ports specifications.
Mr. Castao will also maintain close coordination with design, construction engineering, environmental compliance and public information.
In planning the various elements of construction, the Construction Manager will work
closely with the Critical Activity Point Managers
to ensure that all required tests and inspections
have been performed leading up to critical
activity points, and that the test and inspection
results meet Contract requirements.
Cable-Stayed Manager, Andres Alonso
Quintanilla

Mr. Alonzo, who has built many cable-stayed


structures around the world, has divided the

Volume 2 Section 1 page 7

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

work into three elements based on technical


build these structures.
expertise: the towers, cable erection, and deck
Foundations Manager, Adam Zagorski
erection. Reporting to Mr. Alonzo are a Tower
Superintendent, Cable Erection Superintendent
Because the migration of contaminated water
and a Deck Erection Superintendent.
from the benzene plume and other contaminates is such a critical issue, SFI has assigned a
SFI will self-perform the construction of the
full-time Foundations Manager to manage the
deck and the towers, while a specialty subconconstruction of the Foundations. Mr. Zagorski
tractor will install the cable stays. Due to the
has been the project manager on many complex
access requirements and the technically chalprojects in excess of
lenging nature of the work, we have developed a infrastructure
$200,000,000.
Reporting to Mr. Zagorski will be
lift program to ensure every critical pick mainseveral
superintendents
and engineers to contains the geometry and quality of the work and
struct
the
foundations.
We
anticipate having
meets Cal/OSHA requirements to protect both
four
foundation
crews
with
their own support
worker and public safety.
equipment working at the same time.
We have gained and accumulated technical
Civil & Utilities Manager, Mike Munden
knowledge from all of the technical structures
our joint venture members have constructed
Civil & Utilities Manager, Mike Munden, has
around the world. We have a Technical Serextensive experience with utility relocations,
vices Group with over 300 engineers that will
new utility installation, and civil construction in
be a resource to the Cable-Stayed Manager in
constructing projects over $200 million. He will
planning and performing the construction.
be supported by superintendents with over 20
years of experience in constructing utilities and
The Technical Services Group will provide suproadways in southern
port for the selection,
California. The Utility
planning, operation and
Building it right the first time!
Superintendent will work
maintenance of all the
with the DBM and the
Building quality into the Project results in
specialized construction
maximized production because it cuts out
Utility Coordinator
equipment. They will
rework and lost time.
during the utility relocaalso be in charge of
tion phase to determine
defining, with the design
which
utilities
will
be
protected
in place and
team, the means and methods, the construction
which
utilities
will
be
relocated.
The Civil
sequence and constructibility, making sure that
Superintendent
will
support
Mr.
Munden in the
there are no breakdowns between the design
construction
of
the
paving,
walls,
grading, and
and the actual construction of the different
signing
and
striping.
Early
work
includes
elements.
building detours and frontage roads.
Structures Manager, Scott Goss
Maintaining a successful schedule means aggresStructures Manager, Scott Goss, will oversee the
sively managing the identification, approval, and
substructure and superstructure of all other
relocation of all impacted utilities, since they are
structures. He will supervise and track the conalmost always a critical path item. As such, the
struction submittals, including structure excavaUtility Coordinator will work closely with Mr.
tion plans, shoring plans, ground water control
Munden to verify the locations of the utilities,
plans, column forms, the Movable Scaffold
working directly with the utility agencies in finaSystem (MSS) and lost deck forming systems.
lizing relocation plans. Nighttime work on the
Project will be kept to a minimum. We
Mr. Goss will audit the job hazard analyses
anticipate conducting nighttime traffic switches
(JHAs) included in each work package. The
as we change stages and nighttime closures for
JHAs will identify specific hazards for each
paving operations. To manage this work, Mr.
operation.
Munden will assign a superintendent to be
Mr. Goss has trained field staff and superintenpresent during night work.
dents over the last 25 years and has built the
Traffic Control Supervisor, Ruben Sauceda
same kinds of structures throughout southern
California. He knows the resources necessary to
The Traffic Control Manager, Ruben Sauceda,

Volume 2 Section 1 page 8

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

will manage the overall flow of traffic through


the Project site, seamlessly coordinating all
detours, lane closures, and redirections as
detailed in the approved Maintenance of Traffic
Plan. He will review the constructions plans
against the Maintenance of Traffic Plan to ensure
that traffic remains open to the general public,
local businesses, and Port customers.
Project Controls Manager, Micaiah Revero

The Project Controls Manager, Micaiah Revero,


has been Project Controls Manager on large
complex infrastructure projects. Mr. Revero will
support the PM by overseeing all project
administration. He will ensure that the schedule,
costs, accounts payable and receivable, subcontracts, and document control activities fully
support the project design and construction.
Environmental Compliance Manager, Dan
Herlihy

Environmental Compliance Manager, Dan


Herlihy, will work closely with the discipline
managers to ensure the Project meets all the
applicable environmental standards, including
all regulatory requirements for contaminated
soils, contaminated ground water, air quality,
storm water protection, biological monitoring
and compliance, noise and vibration monitoring, and the goals established by the Ports
Green Port Policy.
Supporting Managers
Equipment Manager, Keith Wood

Because of the technical requirements of the


GDB, it will require a substantial amount of
heavy construction equipmentan oscillator
drill rigs, multiple large crawler cranes, two 550foot 580 Leibherr Tower Cranes with 137-foot
booms, two Construction access elevators, selfclimbing jump forms, Putzmeister line pump,
multiple backhoes and bulldozers, wheel
loaders, scissor liftsas well as a substantial
amount of standard construction equipment.
Therefore, SFI has assigned an Equipment
Manager to make sure that all equipment is
procured on time and properly maintained.
The Equipment Manager, Keith Wood, will
implement the BMPs for fueling of all equipment, both onsite and offsite, in full compliance
with the South Coast Air Quality Management
District (AQMD). To comply with the Ports air

emission standards, the Equipment Manager


will ensure that the equipment is in compliance
at all times.
Electrical Manager, Brent MacDonald

The Electrical Manager, Brent MacDonald, will


oversee all construction of highway lighting,
bridge lighting, traffic signals, intelligent transportation systems, dry utility relocations,
provisions for new dry utility corridors and
temporary electrical needs. Mr. MacDonald has
been a member of IBEW for the past 25 years,
and has managed many electrical installations in
southern California. Electrical superintendents
and electrical subcontractors who construct the
electrical portions of the project will report to
Mr. MacDonald. SFI team members currently
has 50 IBEW electricians working on other
heavy civil projects in California and will be
capable of marshalling the appropriate
resources.
Construction Engineering Manager, Jorge
Aranda

Jorge Aranda, the Construction Engineering


Manager will oversee all of the temporary works
design such as shoring, false work, crane picks,
and special equipment. A California Registered
Engineer, who has extensive Caltrans
experience designing shoring and falsework, will
assist Mr. Aranda in the design of temporary
works. Reporting to Mr. Aranda will be the
survey chief and the technical office engineer.
The survey chief will manage all construction
survey based on the control points established
in design and the record of survey. The office
engineer will manage all construction engineering submittals to the Port and Caltrans. The
Construction Engineering Manager will work
closely with the DBM during constructability
reviews to ensure that what is designed can be
constructed within the right-of-way constraints
and protection of existing facilities.

1.1.3.2 Management &


Integration of Subcontractors
& Suppliers
RFP ITP Appendix B 1.1.3(iii)

Subcontractor Selection
The Project Controls Manager, Micaiah Revero,
will establish a competitive bidding process as
required for subcontracted work, whereby the

Volume 2 Section 1 page 9

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

needs of the Project are met, local contractors


are actively encouraged to participate and all
subcontractors will be treated fairly. As part of
this process, outreach will focus on UDBE and
DBE subcontractors to maximize all
DBE/UDBE opportunities.
Subcontract packages will be developed using
the intermediate and final design plans and the
project schedule. Using a fair, competitive
process, the focus will be on local subcontractors having every opportunity to contribute.
After the subcontractors are selected, they will
either be directly involved or be asked to buy
in to the schedule as part of their obligations.
The subcontractors will also be required to meet
the safety, quality and environmental requirements, which will include orientation of all subcontractors employees.
Subcontractor Management
Weekly meetings to coordinate schedule and
work area assignments will be conducted by the
construction team. Attendance by a representative for all subcontractors with ongoing work
will be mandatory. Subcontractors will be held
to the same level of performance, commitment
to quality, and commitment to safety as the
design-builder.
Disputes will be handled at the lowest level
possible. On-site construction personnel will
meet with the subcontractors personnel to
resolve disputes when possible. Upon exhausting negotiations at the field level, any outstanding issues will be elevated to the on-site project
executives. If an issue is still not able to be
resolved, it will be further elevated to the corporate executives. If an issue is still not able to be
resolved, it will follow the dispute resolution
procedures set forth in the subcontract agreement between the parties.
Vendors & Manufacturers
To ensure that the proper materials and supplies
are purchased and arrive on time, we will procure these items locally as practical. SFI will
closely mange the procurement of specialty
items such as main span bridge components,
forms, concrete and concrete aggregates, structural steel, cables, bearing pads, and hinges to
ensure that all specifications are followed and
source inspections are completed prior to deli-

very. Purchase orders for these items will be


negotiated during NTP1 and finalized at NTP 2.
Other material needs will be developed as the
plans are finalized. For these materials, the Purchasing Manager will first develop a clear scope,
including the specifications and delivery timeframe. The Quality Manager will verify that all
the required testing and certifications have been
met or source inspections on site will be completed. Finally, the Quality Manager will ensure
that the correct materials are received and carry
the proper certifications, prior to use.

1.1.3.3 Conclusion
SFI has formed a construction organization that
allocates the proper level of resources and personnel needed to effectively design and build
the Project. The SFI team is fully integrated
between construction, design, safety, environmental and quality disciplines. Our value-added
position of DBM will push the integration
between design and construction to help
efficiently design and build the Project.
We are providing experienced engineers,
managers and superintendents each with over
20 years of local experience to oversee the
construction in compliance with Caltrans
specifications. These superintendents, who also
have established relationships with several local
subcontractors as well as local unions and
suppliers, will manage the integration of
subcontractors, labor and vendors.
We have developed our organization to provide
a highly experienced, integrated management
team that will apply both world-class expertise
in cable-stayed structures and a seamless designconstruction management approach. This organizational structure will ensure that each discipline is overseen by highly experienced staff.
The same team that developed the SFI proposal
will continue the work at project startup, building on the preliminary design and work plans
that they created, and bringing with them an
intimate knowledge of the Project and our solutions.

Volume 2 Section 1 page 10

1.1.4
Internal Coordination

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

1.1.4 Internal Coordination


RFP ITP Appendix B 1.1.4; D 1.1.1(c)

SFIs experienced and talented team was


formed to accomplish the Ports and Caltrans
Goals. We have placed key personnel on the
Project who have international experience on
large, complex signature bridges, as well as
those who have previously built large, complex
design-build projects in Southern California.
The Organization Charts and key personnel in
Section 1.1.1 demonstrate how SFI has
integrated the international expertise with
experienced, proven, local construction staff.

1.1.4.1 Design, Construction &


Quality Integration

SFI Advantages
An integrated management approach which
seamlessly connects design and construction
phases.
Added Value of Key Personnel Design-Build
Manager specifically tasked with team
integration.
International expertise on cable stayed design
and construction which will elevate design and
constructability issues early.
Local experience on how to execute design-build
projects.

design and the design schedule, and work on


issue resolution, and accuracy and completeness
of the design.
In addition, the DBM will work with the
Environmental Compliance Manager during
design to integrate the environmental issues into
design and construction.

To effectively coordinate the interrelationships


and interfaces between the design, construction
and quality teams, SFI will use a number of
Integrated Project
proven methods:
Office (IPO) Co Dedicate a DesignOur
managers
and
superintendents
have
Location
Build Manager to
learned from past large projects that we
RFP Book 2 Section 2 2.5.2.3
shepherd the
must spend a substantial amount of time
relationship between
planning, building the team with proper per- Co-locating the design,
design and
construction and quality
sonnel, and preparing the proper Project
construction.
Management Plan to successfully deliver the teams with the Port in an
Co-locate design and
Integrated Project Office
project.
construction staff (as
(IPO) during both design
well as Port and
and construction phases is
Caltrans staff) during the design phase.
the most direct way to achieve effective
Create task forces that join design and
integration. Our experience on major designconstruction personnel for each discipline.
build projects over the last 15 years has taught
Integrate design and construction QA/QC.
us that co-locating offices increases
Integrate Technical Services as a resource.
performance and reduces risks by facilitating
communication, coordination, problem solving,
Design-Build Manager
and quick review times between all the players,
improving project efficiency and results. More
SFI offers Robert Schraeder, P.E. as the
specifically, co-locating personnel results in:
Design-Build Manager (DBM), an added value
position to help integrate design and
Maximizing staff integration and
construction and manage the task forces. Mr.
communication opportunities.
Schraeder has exclusively worked on
Allowing team members to focus on the
transportation design-build projects since 1995
Project without interference.
in the role of lead designer and project manager
Shortening the ramp-up time to allow for
on large complex design-build projects. He can
early environmental support efforts.
therefore speak both design and construction
Streamlining the design submittal and review
languages and will be responsible for the
process with continual over-the-shoulder
integration between design and construction.
reviews and collaboration.
He will work closely with the Project Manager,
Facilitating seamless peer-to-peer
the Design Manager and the Construction
communication.
Manager to get early construction input into the
Promoting efficiencies due to close

Volume 2 Section 1 page 11

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

proximity of all staff, including managers,


decision makers, designers, constructors, and
reviewers.
Providing easy access to the appropriate
decision-makers.
All these maximize the opportunities to
communicate, interact, and review the Project
status and design.
Task Forces

Responsible parties, levels of authority.


Overall Project goals.
Scope applicable to any third parties.
Project schedule and specific detailed
schedule related to the third party.
Applicable specifications, technical
requirements, code compliance.
Project safety requirements.
Community involvement/work restrictions.
Project QA/QC compliance requirements.
Issues, potential challenges and solutions.
Action items, due dates and accountability.
Schedule and frequency for continuing
meetings.
In addition, Internal Coordination Meetings, led
by the DBM, will be targeted for only the core
task force members for any discipline, and
others who have a need to know. This way
communication is kept lean and team members
are freed to focus on their core responsibilities.

Task force groups provide interface between


broader elements of the design-build team. Task
forces consisting of design discipline experts
and their construction counterparts will be
formed to tackle specific issues. The task force
groupsand occasional ad-hoc groups to
address a particular issueprovide the
framework for the team members to confidently
finalize a design that is constructible.
Although the formal
CONSTRUCTABILITY
communication links
Established Relationships
REVIEWS
will be used to maintain
The
individual
relationships
and
task
forces
official communications
SFI will conduct
already formed within the team during the
between the designers
unofficial constructability
Proposal phase create a working
and constructors during
reviews during over-theenvironment where individuals can quickly
design, constant
shoulder reviews and
connect with appropriate resources to seek
informal
official constructability
information, enhance ideas, and develop
communication on all
reviews prior to each of
solutions. This type of informal interaction
levels is essential and
the following design
will maximize the value each individual
brings to the team.
encouraged.
submittals:
As indicated in Section
Concept Design
1.1.2, Design Management Concept, we have
Intermediate Design
identified discrete and manageable design
Final Design
packages, which will drive the work of each task
Release for Construction
force.
The constructability reviews will be led by the
DBM to solicit reviews from specific discipline
INTERNAL TASK FORCE MEETINGS
superintendents.
The Joint Venture Team will meet via its Task
Construction superintendents will have the
Force meetings to identify how each third party
opportunity to review drawings for all the major
fits into the overall sequence of the design and
submittals for constructability. These issues
construction. We will then schedule individual
relate to adequacy of information, tolerances,
coordination Kick-off Meetings with each and
site access and restrictions, safety, economics,
every third party. The meetings may involve
and efficiencies of construction methods and
anywhere from 1 to 20 individuals from the
materials, availability of materials, equipment
organization, depending on the size and
and required labor, consistency with design
complexity of the interface. The purpose of this
objectives and environmental mitigation,
meeting is to identify all stakeholder issues and
interference and conflicts with utilities, and
educate both our design and construction leads
completeness.
on the necessary requirements. Key items to be
discussed are:

Volume 2 Section 1 page 12

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

DESIGN INVOLVEMENT DURING


CONSTRUCTION

Similar to the involvement of key construction


personnel in the design process, the design
engineers and support members will remain
involved throughout construction. Even before
the start of actual construction, the responsible
design discipline manager will attend the weekly
construction meetings, becoming familiar with
current and planned construction activities.
As construction proceeds in a particular area,
the responsible design discipline manager will
be responsible for:
Reviewing working drawings and contractor
submittals.
Responding to requests for information
from construction staff.
Performing routine field visits to observe
construction and verify the design intent is
reflected in construction.
Developing design changes as necessary in
response to requests from the construction
staff.
Quality Integration
Our quality management system is integrated
into every element of workfrom planning of
engineering and final design to procurement,
construction, project management, quality
control, and acceptance testing and
commissioning. The integration of QA/QC
requirements flows down to our subcontractors,
suppliers, and fabricators for implementation
and communication, as appropriate. The
Quality Manager will promote conformance to
these management system requirements through
on-the-spot surveillance, formal audits,
management assessments, and lessons-learned
strategies.
The Executive Management Committee will
confirm that quality management orientation
training is provided for project employees,
including subcontractor management personnel,
to provide a clear understanding that the quality
management system, quality policy, goals, and
objectives are communicated.
DESIGN QA/QC

The Design Quality Manager will conduct

regular design meetings with the design


discipline managers to track progress and
content of the design. These meetings will
address design interfaces, progress, schedule,
design quality, system safety, mandatory
formats, and quality and code compliance. All
drawings and supporting calculations will be
required to follow the document control
process and be submitted in the format
specified by the Port.
During the design phase, the Design Quality
Manager will oversee the following:
Design team internal check.
Internal independent check (all structures).
Interdisciplinary reviews.
High-level design reviews.
Environmental compliance.
CONSTRUCTION QA/QC

The Construction Manager and Construction


Quality Manager will initiate construction
QA/QC integration efforts.
SFI will develop Construction Work Plans
(CWP) for individual work elements. The CWP
is an effective tool for maintaining consistency
and integration planning across all selfperformed and subcontracted work and
typically contains the following information:
RFC plans, any necessary permits and
construction easements.
Description of the planned work: overview
of the work and step-by-step detail on the
sequence of the work activity including
construction methods, key equipment, and
any backup equipment required.
List of required prerequisite activities and
current status.
Potential public exposure: Identification of
work activities that may expose the general
public to danger, inconvenience, or risk.
Job Hazard Analysis (JHA) for the scope of
work and any associated safety issues.
Applicable contract specifications and
drawings.
List of applicable submittals required and
their current status. Typical submittals
include traffic control, administrative
support (permits, insurance, etc.), material

Volume 2 Section 1 page 13

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

and equipment data and personnel


certifications, shop and working drawings,
process and test procedures, and schedules.
Applicable RFIs, Design Changes and their
current status.
Individuals/ positions responsible for
supervising the work, which includes any
subcontractor representatives who will be
supervising.
Planned start date of the work, progress rate
expected, and extended work hours required.
Handling, shipping, storage, and preservation
of material and equipment. This includes
schedule and method of delivery and where
these items will be stored and protected.
Special processes to be used (such as
welding, non-destructive testing, cathodic
protection, and coatings), procedures, and
personnel certifications and training, as
appropriate.
Acceptance criteria and tolerances for critical
work elements. Critical work elements are
items where there is increased exposure and
risk. If not already noted in design
documents, tolerances are listed so that they
may be communicated and met.
In-process and final inspections and
frequencies for testing, including inspection
checklists.
Any imposed inspection hold points, which
are usually identified during the initial
readiness review meeting.
Methods to protect the completed work
from follow-on activities, if required.
Public notifications, detours and locally
approved maintenance of traffic plans, if
required.
Utility impacts and mitigation.
Environmental impacts and construction
impacts.
3D modeling, if necessary, to show critical
interfaces.
SFI will provide the Construction Work Plans
to the Port two weeks prior to starting work
and will then hold a construction kick-off
meeting for major categories of work to verify

that we have integrated all necessary elements


into construction. We have found on past
projects that the Construction Work Plans
greatly contribute to internal coordination and
get everybody on same page prior to starting
construction.
Technical Services
SFI has extensive internal technical services
resources to draw upon, should we need them,
with worldwide design expertise to bring
innovative solutions and specialized technical
support. This Technical Services Group has
performed design and construction for several
cable-stayed structures throughout the world. It
represents five disciplines that consolidate 30
years of global experience into lessons learned:
Equipment
Special projects
Civil engineering and architecture design
Research and development
Quality
The 300+ individuals that make up the
Technical Services Group are top specialists in
engineering and construction techniques,
bringing that added value to the Project:
The Equipment Department can be
commissioned to oversee the operation and
maintenance of the specialized construction
equipment to be used in the Project,
especially the MSS for the Approaches and
travelers for the Cable Stayed Bridge,
bringing all the experience gathered in
previous work.
The Special Projects Department can be
used, in conjunction with the operations
group, to assist in defining the means and
methods and the construction sequence to
be followed on site, making sure that there
are no breakdowns between the design and
the actual construction of the different
elements.
The Civil Engineering Design Department
will work hand-in-hand with the Design
Build Manager to ensure that all the technical
challenges that arise during construction are
solved with clarity and in the most efficient
way possible.

Volume 2 Section 1 page 14

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

1.1.4.2 Environmental
Monitoring

that the construction crews are complying with


the mitigation measures identified in the design
and Book 2 requirements.

Environmental monitoring doesnt just start in


the field after the plans have been released for
construction. Environmental monitoring starts
at the conceptual design phase and leads
through every stage of design and construction.
Our Environmental Management Plan will define
the process to integrate environmental
compliance into design and
construction.

1.1.4.3 Risk Management Plan

Design Matrix of
Critical Interfaces

To bring additional value to the Port, and


facilitate both internal and external
coordination, SFI will implement a Risk
Management Plan. SFI will internally identify risks
early in the design and work internally and
externally to resolve risks
before they impact safety,
Lake Mead Project quality, schedule, or costs.
This approach to risk management has been SFI is committed to
instrumental on the Lake Mead Project (NV) prepare and implement a
Risk Management Plan in
allowing the Owner (Southern Nevada
Water Authority) to save over 20% of their
accordance with the
budgeted premium cost on their Builders
guidelines of the Project

SFI will create a matrix of


all environmental
mitigation measures that
Risk policy.
need to be incorporated
into design. We will track
compliance in design and construction to ensure
that we have met mitigation measures. For
example, we must meet the requirements of the
Regional Water Quality Control Board
(RWQCB Section 402 National Pollutant
Discharge Elimination System (NPDES) in
both design and in construction.

Risk Management
Handbook edited by

Caltrans on May 2, 2007.


In addition, SFI will follow the benchmarks
established by the Code of Practice for Risk
Management of Tunneling Works, edited by the
International Tunneling Insurance Group
(ITIG) in 2006. The ITIG Code is one of the
most advanced codes available in the
construction industry. While the Code was
developed for underground work, it is not
Sign-Off During Design
limited to that type of work and is applicable to
During design, each environmental compliance
any type of infrastructure project.
item will be verified by the design discipline
The Risk Management Plan may help the Port:
manager. A compliance sheet will be created for
each mitigation measure identified in Book 2,
Save on their Builders Risk Policy premium.
Section 4. SFI will track each measure through
Reduce risks on
design and have back-up
schedule,
sign-off sheets to verify
Benzene Plume
environment, quality
that the mitigation
During procurement design, we mitigated
and safety.
measures were correctly
the impacts to the benzene plume through
incorporated into the
innovative foundation design.
Save on contingency
design.
funds due to early
identification and mitigation of risk.
Sign-Off During
Construction
Please see the additional description of the Risk
Management Plan in the Section 1.2, Quality
During construction, the Environmental
Management Plan.
Compliance Manager will independently verify

Volume 2 Section 1 page 15

1.1.5
External Coordination

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

1.1.5 External Coordination


RFP ITP Appendix B 1.1.5; D 1.1.1(d)

From our vast wealth of transportation experience delivering Caltrans-related projects in


southern California, as well as international
cable stayed and design-build bridge experience, SFI has an intimate knowledge of the
standards, requirements, and guidelines on
which the Gerald Desmond Bridge (GDB)
design will be based. Combined with best
world-class practices, design task leaders will be
implementing Project-specific design checklists
for periodic reference to ensure that all required
design and plan preparation elements are considered and implemented. The overall design
quality control process will be monitored by the
Design Manager and implemented by his managers and staff.
Our past design-build experience has taught us
that a main challenge to delivering the design
and consequently, releasing plans for constructionis gaining consensus on design elements
from the Project stakeholders. The stakeholders
for the GDB include such entities as the Port,
Caltrans, the City of Long Beach, program
managers, other governmental agencies, utility
owners, businesses, the public and other contractors working in the vicinity, and other
stakeholders.

SFI Advantages
We have reduced the amount of utility coordination required by eliminating utility relocations in
our innovative geometry and foundation design.
We have eliminated many foundations that are
in the benzene plume and thereby reduced
environmental impacts.
Our design returns seven acres to the Port as
leasable space by reducing the amount of rightof-way required.

solutions for design challenges.


Interdisciplinary constructability reviews.
Safety/quality checks.
Over-the-shoulder design reviews for timely
input on the final product.
Weekly meetings with a look-ahead schedule.
Safety training for workers in active
transportation corridors.
SFI will use each of these throughout the duration of design and construction.
Task Force Meetings

As indicated in Sections 1.2 and 1.3, we will


identify discrete and manageable design and
construction packages so that issues in one
jurisdiction will not impact or delay the
approval of packages in another jurisdiction.
Task forces consisting of design discipline
experts and their construction counterparts will
be formed to tackle specific issues. The SFI
1.1.5.1 Interrelationships and
Team will meet via its Task Forces to identify
how the Port, Caltrans and each third party fits
Interfaces
into the overall sequence of the design and conSuccessful implementation will require assostruction.
ciated agencies, stakeholders, and utilities to
Task force meetings are critical to understandwork with SFI and the Port toward the same
ing the needs of all parties. The information
goal. Our teams extensive design-build expeobtained will form the basis of our approach to
rience provides proven methods for healthy
the design and construction schedules. It will
communication early, often, and throughout the
also allow the Team to
course of the Project. We
evaluate the willingness
will implement the folATC-004A and ATC-006
and ability of third parlowing strategies:
Through our revised geometrics in ATCties to achieve and sus004A and ATC-006, we have greatly reduced
Pre-construction
tain momentum in drivthe environmental footprint and reduced the
meetings to review
ing toward final completime needed to build the Project. Thus, all
the Project timeline.
tion.
external coordination will be improved
Outreach meetings
because we have reduced impacts to the
with stakeholders and
Third Party
community through better maintenance of
utilities.
Coordination
traffic and reduced impacts to utility com Co-location of the
panies through fewer well and utility reloSFI believes that
Project team.
cations. All of this innovation has led to a
embracing third parties
Task forces to identify price that is under the Ports budget.

Volume 2 Section 1 page 16

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Task Lead
+
Port, Caltrans or
Third Party
Owner/Reviewer

Yes

No

Stop

Weekly Task
Force Meeting
Decisions

Yes

No

Third Party
Coordination +
Port, Caltrans or
Third Party
Owner/Reviewer

Yes

Stop

No

Project Manager
+
Port/Caltrans
Representative
+
Owner/Reviewer

Yes

Decision

Figure 1.1-3: Decision making process.

Working with Other Contractors


During design and construction, SFI will meet
with the designers and contractors for projects
adjacent to the GDB. We will hold a kick off
meeting with each contractor/designer leading
the projects (see Book 2, Section 1.3.4, Table 11). For those projects that have critical interfaces in design and schedule, we will meet
monthly and transmit progress prints and schedule updates.

Definitive Design

Interim Design

Final Design

Quality Control
(QC)
Constructability
Review

Quality Control
(QC)
Constructability
Review

Quality Control
(QC)

Revise Plans

RFP ITP Appendix B 1.1.5 (i)

We will advance the


design in specific design
packages per design
development below:
Design package submittals (see Book 2

Stop

as team members and integrating them early,


advances the schedule for design and construction. Third party challenges are treated as team
challenges. It is our responsibility to deliver
accurate and timely information to the third
parties in order to establish trust among the
team members. We will carefully review the
utility relocation agreements to understand the
obligations of each party. The decision making
process is based on two principles (see Figure
1.1-3):
1. Decisions made at the lowest responsible
level.
2. Clear lines of authority are available for escalation and rapid decision making.

1.1.5.2 Plans &


Permits Review

2.4.2.5)
Concept design
Technical Advisory Panel Review
Intermediate design
Final design
RFC
Concurrent submittals
SFI will obtain the permits identified in
Section 4 of Book 2. Since SFI is a local contractor, we have experience obtaining these
permits on other projects. We will have a
local Permitting Specialist to assist us in
acquiring these permits.

1.1.5.3 Coordination Meetings


RFP ITP Appendix B 1.1.5 (ii)

SFI will hold various coordination meetings


with the Port, Caltrans and third parties
throughout the design and construction period
to keep all parties apprised of the Project.
Workshops

Design discipline kick-off meeting (Design


Manager, Discipline leads; lead Superintendent/ Construction Manager and DesignBuild Manager)
Community workshops (PIL, Design-Build

Revise Plans

Quality Assurance
(QA)

Port/Caltrans
Review

Revise Plans

Quality Assurance
(QA)

Port/Caltrans
Review

Quality Assurance
(QA)

Port/Caltrans
Review

Figure 1.1-4: Plan review flowchart.

Volume 2 Section 1 page 17

Permits

Released for
Construction

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Manager, Design Discipline Leads; Design


Manager)
Technical Advisory Panel

Quarterly independent reviews of design


packages.
Expert advice on seismic and geotechnical
issues.
Progress Meetings

process with continual over-the-shoulder


reviews and collaboration.
Facilitating seamless communication.
Promoting efficiencies due to close proximity of all staff and decision-makers.
Simplifying the design QA process.
Partnering
SFI is fully committed to retaining a third party
facilitator for partnering with the Port and Caltrans. Partnering conducts business so that our
three organizations make long term commitments to achieve mutual goals. Partnering
requires changing traditional adversarial relationships into team-based relationships. SFI is
committed to open communication, trust,
understanding and teamwork.

We will hold regular progress meetings with the


Port regarding:
Over-the-shoulder reviews
Full design package schedule
Construction submittals
Look-ahead schedule
Permits
Partnering Training
We will hold the following standard weekly
meetings with the Port:
Training staff from executives down to inspectors
Design-Build Meeting
SFI team members have successfully part Construction Meeting
nered with owners on past large heavy civil and superintendents in
partnering best practices is
Critical Issues Meeting projects, including the Metro Orange Line
critical for partnering to
BRT, Metro Gold Line Eastside Extension
Utility Coordination
work. SFI notes that
LRT,
San
Franciscos
Illinois
Street
InterMeeting
Caltrans rolled out the
modal
Bridge,
Alameda
Corridor
Transporta MOT / Construction
tion
Authority,
BART,
and
Golden
Gate
Field Guide to Partnering on
Easement Development
Bridge Highway and Transportation District. Caltrans Construction Projects
Meeting
in September of 2008.
Public Liaison Meeting
Quality Status/ Inspection Schedule Meeting
Robert Schraeder, the
Design-Build
Manager,
is an industry trainer
Integrated Project Office (IPO) Co-Location
for partnering for Caltrans District 7 and has
RFP Book 2 Section 2 2.5.2.3
conducted seven training sessions with owners
Co-locating the design, construction and quality
and contractors.
teams with the Port in an Integrated Project
Office (IPO) during both design and construcSFI will work with Caltrans and the Port to
tion phases is the most direct way to achieve
implement a partnering training program for all
effective integration. Our experience on major
staff that will be involved in the Project. We
design-build projects over the last 15 years has
have found on past projects that training helps
taught us that co-locating offices increases perissues get resolved at the lowest level.
formance and reduces risks by facilitating comPartnering Kick-Off Meeting
munication, coordination, problem solving, and
quick review times between all the players,
We will hold a two-day partnering kick-off
improving project efficiency and results. With
meeting with the Ports and Caltrans key staff.
the benefits noted in Section 1.1.4, Internal
The first day we will develop a Partnering
Coordination, co-locating personnel results in:
Charter that contains the following elements:
Integrating Port personnel with least disrup Core Project Goals
tion in office space near existing Port offices.
Project Specific Goals
Maximizing staff integration and
Mutually supported individual goals
communication opportunities.
Key Issues/Risks
Shortening the ramp-up time to allow for
Partnering Maintenance and close-out plan
early environmental support efforts.
Partnering dispute resolution plan
Streamlining the design submittal and review
Commitment Statement and signatures

Volume 2 Section 1 page 18

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

During the second day, we will conduct training


on a special topic that the executives choose
ahead of time, such as active listening; facilitation skills; running effective meetings; effective
escalation ladders; emotional intelligence; and
change management.
Dispute Resolution Ladder & Board

Together, SFI and the Port will construct a


Dispute Resolution Ladder (DRL) to help issues
get resolved at the lowest level (see Figure
1.1-5). If the Dispute Resolution Ladder fails to
resolve the issue, then the parties will utilize a
Dispute Review Board to resolve issues.
Construction/Utility Schedule

Third-party utility relocations have the potential


to delay the schedule and increase Project costs.
SFI has experience managing and performing
utility relocations. Utility relocation coordination can potentially be very frustrating because
the utility companies do not have a direct contractual relationship with either the Port or SFI.
Our lessons learned from managing and relocating literally thousands of utilities in the last
15 years have helped us develop our plan for
utility relocations.
We will hire consultants who have previously
worked for the utility companies to walk the
design through with the utility companies. The
best risk position for SFI is to be in control of
both the design and construction of the utility
relocation. We are able to relocate all wet utilities, and we are prequalified with SCE to do
electrical work.

Construction
Manager

Construction Manager

5 Days

Construction Engineer

Discipline Manager

2 Days

Resident Engineer

Foreman/
Superintendent

1 Day

Inspector

Level 1

7 Days

Level 3

Project Manager

District
Director/Chief
Engineer

Level 5

14 Days

Level 4

Executive
Management
Committee

Level 2

ISSUES MAGNITUDE

1.1.5.4 Construction,

Figure 1.1-5: The dispute resolution process ensures that


issues get resolved at the lowest possible level to keep the
Project moving.

Engineering and Inspection

RFP ITP Appendix B 1.1.5 (iii)

Shop Drawings

SFI will internally review and approve all shop


drawings prior to submitting them to the Port
for approval and concurrence.
Temporary Design Works

SFI will design and process designs for the


temporary work of falsework, shoring, traffic
control and signal plans, and erosion and SWPP
plans prior to construction. We will have a list
of all temporary work that needs design
approval in our Construction Work Plans
(CWP). The Port will review and approve the
list prior to the CWP being approved, which
then allows SFI to start work.
QA/QC Coordination

Through our Quality Management Plan (QMP),


we will clearly define requirements, check lists,
lines of authority, hold points, measures of performance, configuration management, and final
documentation of contract and quality documents. Our Quality Manager and quality control
design and construction teams will remain independent by reporting to SFIs Executive
Management Committee and the Port. The
resulting QMP will be a robust set of guidelines
tailored to this Project that outline processes,
data collection, testing and reporting, all of
which will be completely independent from the
design and construction teams.
Testing/Inspection

SFIs Quality Management Plan emphasizes


three specific targets: early planning, documentation prior to design and construction, and
independent inspection and testing. Our experience has demonstrated that quality is not only
about the final product, but also having the well
defined processes and procedures. Samples of
testing that will be completed by SFI are:
Concrete Strength
Welding
Compaction
Gradation and corrosion
Port QA/QC

During construction, SFIs Construction Quality team will work closely with the Port to verify
that elements have been constructed properly

Volume 2 Section 1 page 19

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

before moving on to the next construction


sage signs (CMS), SFI will install four CMS on
activity. All critical activity points will be identithe east and west side of the Project to allow the
fied in the Construction Quality Assurance
CCRD to communicate messages to the public.
Inspection and Testing Plan. The Critical Point
The public will be safe, informed, responded to,
Activity Manager will verify through inspections
and accommodated when possible during the
and test results that the critical activities have
months of construction. Their acceptance of the
been constructed properly with the Ports conProject and its potential inconveniences is
currence.
needed for the most successful outcome possiThe Project will require specialty fabrication of
ble. Understanding these needs, we have taken
structural steel, high strength concrete mix
great care in selecting design and construction
designs and detailed rebar fabrication. SFI will
methods that will minimally impact the public,
prepare a Materials Control Schedule, with
and our public relations firm, Lee Andrews
oversight by the Construction Quality Manager,
Group, will provide a superior Public
to identify all materials and fabrications that
Information Plan and process.
need to be tested and inspected at the source
Public Information Plan and Process
site before being delivered to the Project. We
will include the Port in the
The PIL will support the
off site inspections.
CCRD in communicating
SFIs Public Information Liaison, Lee
There will be many techni- Andrews Group, has developed specialized to all key stakeholders. We
will provide information
cians taking lab samples
expertise in public involvement and commu- materials, attend public
during construction to
nications programs for public infrastructure
meetings and open houses,
verify the concrete mix
projects. They have also coordinated designprovide timely construcdesigns and other elebuild highway projects with Caltrans in
tion
and staging informaSouthern
California.
These
outreach
services
ments. We will coordinate
tion,
establish a 24-hour
include
support
at
every
phase
of
work
from
closely with the Ports staff
telephone
hotline, and
alternatives
analysis
through
construction.
so that Port technicians
refer
all
media
inquiries to
can take their samples at
the
CCRD.
the same time to perform
independent quality assurance.
Before construction begins, our PIL will participate in meetings with the CCRD, Caltrans,
1.1.5.5 Community Relations
and SFI staff to review the proposed road cloRFP ITP Appendix B 1.1.5 (iv)
sures, detours and impacts to commuters and
The Public Information Liaison (PIL) will work
stakeholders. As part of the liaison role between
in association with the Ports Communications
the community and Project implementation, the
and Community Relations Division (CCRD)
PIL will work with CCRD and SFI to identify
and SFI to inform and engage affected thirdand minimize any traffic and access issues raised
party stakeholders in the Project design and
by the community. Once the traffic control
construction. This outreach program will supplans are approved by Caltrans, our PIL will
port the Ports ongoing communications prodevelop traffic and construction alerts to be disgram.
seminated between 72 and 48 hours prior to
construction. Communications will be distriSFI is well aware of Caltrans and the Ports
buted to targeted stakeholders using appropriate
current Intelligent Transportation System (ITS)
tools, including direct mail, door-to-door, webdesign, and will design both the interim and
site, e-mail, public meetings, radio, and print
final ITS for the Project. Prior to setting up
media.
traffic control stages, we will install closed-circuit television (CCTV) cameras and wire them
The PIL will do a special outreach to the Ports
to the Caltrans and the Ports servers so that
tenants to inform them of construction stages
traffic can be monitored during construction
and traffic movements. We will keep all staging
and lane closure windows can be adjusted
information up to date on the Ports website.
accordingly.
The PIL will send out and post a monthly newsletter of the progress on the Project.
In addition to traffic control changeable mes-

Volume 2 Section 1 page 20

1.1.6
Safety and Security

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

1.1.6 Safety and Security


RFP ITP Appendix B 1.1.6; D 1.1.1(e); Book 1 5.2, 10.1

1.1.6.1 Overview
The SFI Joint Venture has set the standard for
safety performance on recent design-build
bridge projects.
We bring this same safety culture, safety program, and management philosophy to the
Gerald Desmond Bridge (GDB) Replacement
Project, assuring the Port that people and
property will be fully protected.
All members of the SFI Joint Venture have
safety metrics that are better than industry
averages. For example, Shimmicks Experience
Mod Rate (EMR) average for the last 5 years is
0.72.
The SFI Joint Venture will bring its individual
safety cultures, experienced Southern California
craft labor, and success in past safety performance to the Project. The Safety Management Plan
will be based on SFI Joint Ventures policies
and procedures, similar to the Metro-approved
safety plan team members implemented so successfully on the Gold Line Eastside Extension
project.

SFI Advantages
SFI team member Shimmick Construction has
garnered many AGC high-hazard safety awards.
All field supervisors (not just safety) and senior
field personnel will seek a CHST credential.
MSS reduces the risk associated with building
and removing traditional falsework.
ATC-004A reduces contaminated material being
removed from the site that could affect workers
and the public.
ATC-006 moves the Ocean Boulevard exit to the
right, making the final configuration safer for the
vehicle traffic.
ATC-015 creates a continuous bikeway that
keeps bicycles and pedestrians protected from
vehicle traffic.

Hazard project for Big Tujunga Dam, 1st Place


Safety Award of Excellence for 200,001-500,000
worker hours (Shimmick/ Obayashi), and 1st
Place Safety Award of Excellence for 500,0001,000,000 worker hours (Shimmick) for the
Heavy Civil/Highway categories. At the 2010
awards, Shimmick received another 1st place
Safety Award for Heavy/Civil/ Highway Division 500,000-1 million worker hours (Shimmick
Obayashi) and a 3rd Place Safety Award for
Heavy/Civil/ Highway Division 200,001500,000 worker hours.
Team Safety Success
As Shimmick has grown, the company has
maintained an Accident Free Culture that
SHIMMICK SAFETY SUCCESS
encourages everyones
Shimmick Constructions
input to promote a safety
safety excellence has been The Gold Line Eastside LRT Extension
program that is among the
recognized with prestigious project achieved an impressive 4.3 million
best in the industry. Crew
California industry awards. hours, including subcontractors, without a
foremen will complete a
single Days Away Injury. From an October
Pre-Task Plan (PTP) using a
At the 2011 Associated
26, 2009 press release by Jose Ubaldo,
prepared PTP Book. This
General Contractors
Media Relations:
helps to plan the work for
(AGC) of California Safety
the day and identify
The [Eastside] project has posted an
Awards, Shimmick
hazards that may be
exemplary safety record more than 4
received several awards
million construction hours without a lost- encountered. This is
including Safety Excellence
time work injury making it perhaps the reviewed with the crew and
for 2010 and the Unique
safest major public works project in U.S. implemented on the job.
Safety Application of the
history.
year award for the
Everyone in the company
Dumbarton Bridge Seismic
is expected to contribute to
Retrofit.
the safety program. Each employees contribution in the area of safety is carefully evaluated in
At the 2009 AGC of California Safety Awards,
his or her annual review. Training is the founShimmick Construction received an award in
dation of the safety program and the firm is
every category they were nominated. Shimmick
proud of its training record achievements. All
was awarded more than any other contractor
salaried
employees are required to complete a
in California. Safety Excellence on a High

Volume 2 Section 1 page 21

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

basic core of eleven safety-related courses.


Topics include Alcohol and Substance Abuse,
Trench Safety, Confined Spaces, Crane Safety,
Fall Protection, First Aid / CPR, OSHA 10/30
Hour, Rigging, Fleet Safety, Scaffolding, and
Anti-Harassment Training. Shimmick considers
itself to be a leader in safety throughout the
construction industry and takes seriously the
responsibility to provide a safe work environment for their employees.

CHST as a stepping stone to greater roles in


safety and health and, in some cases, to the
Certified Safety Professional (CSP) certification.

1.1.6.2 Safety Management


Plan

SFI is dedicated to safety and has a program


that not only complies with CalOSHA requirements, but often exceeds them. Together, SFI
employs multiple full-time safety managers on
IMPREGILO SAFETY SUCCESS
its projects, all of whom have been certified as
Construction
Health and Safety Technicians
Impregilo shares the same core value of safety
(CHST).
We
share
the responsibility to create a
with its Joint Venture partners. Safe, timely
safe
working
environment
that does not rely
delivery of projects, with minimal impacts to
solely
on
the
safety
department,
but is an
communities, is their trademark.
integral part of every employees job description
In 2010, Impregilo/S.A. Healy JV received a
and is ingrained in our corporate cultures.
Gold Award for Safety Excellence from Liberty
Before starting construction work, SFI will
Mutual for completing 18 months and 322,308
submit a comprehensive Safety Management Plan
hours without a Lost Time Injury on the Lake
to the Port that includes our Injury and Illness
Mead Project, as well as a second Gold Award
Prevention Program, Hazard Communication
for Safety Excellence for completing one year
Program, Code of Safe Work Practices and a
and 355,445 hours without a Lost Time Injury.
Site-Specific Safety Plan.
That Project has now
gone over 1,400 days
CHST Certification
Steve Wilson, CHST,
without a lost time acciSafety Manager, will be
All members of our Safety Team have CHST
dent.
responsible for implecertification or are actively working toward
menting the Safety Manthat
credential.
For the Portland West
agement Plan including
Side CSO Project,
education,
formal
training
and enforcement of
Impregilo-Healy received Oregon-OSHA
the
Project
safety
policies.
He will have the
Voluntary Protection Program (VPP) Star staauthority
to
stop
or
suspend
work due to safety
tus. The VPP is a challenging safety program
concerns
at
any
time
and
will
work proactively
that recognizes companies that go beyond
to
resolve
all
safety
issues.
Mr.
Wilson will
OSHA standards. Upon an OSHA audit and
report
directly
to
the
SFI
Executive
Manageacceptance of the VPP application, the site is
ment
Committee.
Additionally,
any
member
of
removed from programmed inspection lists as
the
construction
team
can
stop
work
due
to
the site is determined to be able to auto-regucritical safety concerns.
late itself. The same project received the Recognition of Safety Excellence Award from the
In addition to formal training, weekly training
Oregon Chapter of AGC Heavy Division
topics will be prepared and reviewed with
300,001 700,000 Work Hours.
Project Managers, Superintendents and Supervisors in a weekly meeting, who in turn will take
CONSTRUCTION HEALTH AND SAFETY
this information to the crews during daily Tool
TECHNICIAN (CHST) CERTIFICATION
Box Talks. Information regarding relevant,
timely topics will be received at all levels, from
The Construction Health and Safety Technician
management to workers in the field.
(CHST) certification is designed for individuals
who demonstrate competency and work partWeekly inspections are conducted by teams of
time or full-time in health and safety activities
employees from different trades. There is a difdevoted to the prevention of construction illferent team each week, allowing a different
nesses and injuries.
perspective during each inspection. These
inspections are reviewed at the weekly superviMany construction safety professionals use the

Volume 2 Section 1 page 22

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

sors meeting. Abatement and preventive measures are determined and implemented, whenever necessary.
Injury and Illness Prevention
Program (IIPP)
SFI is dedicated to providing a safe and healthy
workplace for our employees. We consider the
prevention of accidents to be an integral part of
our operation, and to these ends, we have
established a comprehensive Injury and Illness
Prevention Program (IIPP), which, as stated
above, will be part of our Safety Management
Plan submitted to the Port prior to the start of
work. The IIPP is designed to:
Develop a system of communication.
Identify and evaluate workplace hazards.
Establish methods for correcting unsafe or
unhealthful conditions.
Establish training and retraining programs
for the employees.
Assure that records on training, inspections
and corrective measures are maintained.
The responsibility to the Port for the implementation of this Injury and Illness Prevention
Program is assigned to Mr. Wilson, the Safety
Manager.
The responsibility for managing and enforcing
the daily activities of this program are assigned
to the Project Manager, Deputy Project Manager, discipline managers, Safety Manager,
Project Superintendent(s), and Foremen.
This program will be utilized in conjunction
with the Site-Specific Safety Plan as required by
the Contract with the Port and the Employee
Safety & Health Handbook/Code of Safe Work
Practices provided to each SFI employee and
subcontractor on the Project.
Site-Specific Safety Plan
The Site-Specific Safety Plan (SSSP) will be
developed to address the specific safety issues
on the GDB Project. Topics to be covered in
the SSSP include but are not limited to:
Hazardous waste operations
Contaminated soils
Emergency action plan
Confined space program
Personal Protective Equipment (PPE)
Drug and alcohol testing

Aerial Lifts
Traffic control and flagging
Earthquake safety
Boat safety
Electrical safety
Crane safety
Lifting/rigging
Fall protection
Excavation
Incident and accident reporting
General construction safety
The SSSP will also include a Code of Safe Practices.
Responsible Person (8 CCR 3202 (A)
(1))
SFI has designated Mr. Wilson, the Safety Manager, as the Responsible Person for the IIPP. It
is the responsibility of the Safety Manager and
Project Manager to implement the IIPP. In
addition, the Project Manager, Superintendent(s) and Foremen have the job site responsibility for enforcement of the program.
The duties of the Responsible Person are to:
Establish a procedure for clearly communicating SFIs safety and health rules and procedures to employees.
Identify and evaluate workplace hazards and
implement procedures for investigating
occupational injuries and illnesses.
Establish and/or review methods and procedures for correcting unsafe and unhealthy
conditions and work practices.
Provide employee training on general and
specific safety and health practices.
Maintain records on training, inspections,
and corrective measures, as required by the
IIPP and other Cal/OSHA required programs in accordance with Title 8 CCR.

1.1.6.3 Highway and Bridge


Safety
All SFI employees who will encroach upon or
conduct work within the Caltrans ROW will be
trained in highway safety. We will obtain
Caltrans approval for access rights and provide
flaggers and traffic control devices when workers are working next to live traffic. Our policy
is to protect all workers on freeways by placing
K-rail between the traffic and workers.

Volume 2 Section 1 page 23

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

SFI team members have broad experience


working on highway and bridge projects in California. All workers will receive extensive safety
training and specialized training for unique construction circumstances such as fall protection
and working in confined space. Locally, we
have logged many safe hours of operation on
highway and bridge projects over live traffic.
Our Safety Manager or other assigned safety
staff will perform an inspection at the end of
each working day to identify and correct any
unsafe conditions before crews leave the site.

Safety of Workers

In order to maintain the safety of all of our


workers, SFI will:
Perform regular safety reviews for design
and construction activities.
Conduct regular safety training at daily tool
box meetings.
Carry out safety inspections at all levels of
management.
Reward employee behavior and safety
through our proven safety incentive program.

Audit all subcontracted work as part of our


1.1.6.4 Commitment Stateregular safety inspections.
ments
SFI will comply with all applicable health and
Safety is the key to the success of the Project
safety laws. To do this, SFI will constantly be
and is an overriding value of our Joint Venture.
aware of conditions in all work areas that could
Without question, it is
possibly present hazards.
every employees responSFIs Project-Specific Safety ImproveNo employee is required
sibility. Every employee
ments
to perform a work task
is empowered with the
that he or she knows or

MSS

mitigates
risks
to
workers
by
proknowledge that Safety is
believes is not safe or is
viding built in scaffolding and eliminating
our highest priority, and
unhealthful. A daily routhe risks associated with placing and
that each individual plays
removing falsework.
tine inspection detecting
a critical role in the safety CIDH foundations reduces noise
hazards and, in turn,
of every operation.
hazards (decibel levels and vibrations) by
controlling them is a
drilling piles rather than driving steel
condition of employOur goal is to create and
piles.
ment. It is SFIs policy to
sustain a work culture
Traveler building the steel deck using a
immediately take correcwhere all incidents and
traveler eliminates the need to work from
tive action on any unsafe
injuries are avoided. We
the water. This greatly reduces safety
acts, conditions, or situahave combined our
risks associated working with barges and
tions.
award-winning safety
cranes over water, and to Port traffic.
programs with regular
The personal safety and
training, inspections, and
health of each employee is of primary imporaudits that we will execute on this Project.
tance. Prevention of occupationally-induced
injury or illness takes the highest priority on the
SFIs plan has in mind both the safety of the
Project. Our objective is to implement a safety
public and its workers.
and health program that will achieve our goal of
Public Safety
zero accidents and injuries.
Our Safety Management Plan will include proviIn order for the SFI team to succeed in this
sions to:
goal, it is necessary for every employee to be
responsible for following the procedures put
Provide safe routes for pedestrian and bike
forth by management to protect themselves and
traffic.
their fellow workers. We ask each of our
Minimize obstructions to vehicular traffic.
employees to make the commitment to work
Control points of access to the jobsite
safely to prevent injuries to persons or property.
through fencing, barriers, barricades, warning
signs, signals, and lights.
Team members who violate the safety and
Pay special attention to directing the tourist
health rules, orders or standards or expose
and visitor traffic (drivers not familiar with
themselves or others to safety or health hazards
the area).
will be subject to disciplinary measures up to

Volume 2 Section 1 page 24

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

and including termination.


The Project Manager, Deputy Project Manager,
discipline managers, Safety Manager, and
Superintendents are responsible for implementing the IIPP. A copy of SFIs Code of Safe
Practices is provided to every employee and
new hire, who is required to read, acknowledge,
and sign it. Employees are also informed of the
location of the IIPP and Hazard Communication and Material Safety Data Sheets (MSDS)
Right-to-Know Station location.
Public & Traffic Safety
Before each new work activity, the construction
management staff will prepare a Job Hazards
Analysis (JHA) identifying the specific hazards
for both the construction worker and the public. We understand that the construction work is
a risk to the traveling public, pedestrians and
local tenants.
For example, to safely maintain ingress/egress
for materials (ready-mix concrete, steel rebar
cages, structural steel, etc.) delivered to the site,
SFI will prepare plans to provide proper transition lanes to deliver the materials. As part of our
partnering activities, we will review these plans
with the Port, Caltrans, and third parties.
Port & Other Stakeholders

will solicit input into our temporary traffic


detours and maintenance of traffic to ensure
safe operations before lane closures and traffic
switches.
When working within the easements provided
by the Port, we will coordinate with the tenants
the times we will use these easements to further
minimize the impacts to their businesses and
keep at least one access route to each tenant
open at all times.
During critical construction activities, we will
notify the affected tenants and work with them
to mitigate any possible events that may affect
their property or employees.
We will coordinate with the Port and local businesses and tenants before starting any new construction that may impact them.
Other Contractors
SFI is aware that there are many nearby construction projects that may impact the GDB
Project. We will coordinate with all of the contractors who will be working on Port and
Caltrans projects (per Book 2, Section 1.3.4) to
ensure that our work activity does not adversely
affect access to their projects. We will also make
sure to coordinate our staging plans so that they
do not create any issues to the traveling public.
Security

SFI will coordinate with


all affected stakeholders
in preparing our specific
JHA for each construction activity.
For example, we will
coordinate construction
within the Ports maintenance facility ROW to
ensure that we keep the
building and the
employees safe.
We will coordinate with
the Port, Caltrans and
stakeholders before
starting new construction activities.

During construction, we
will provide security to
protect the site from
vandalism and theft of
materials.
We will work closely
with the Ports security
and their CCTV system
to monitor the site when
construction crews are
not present. Please see
the Accident and Terrorist Vulnerability
Assessment and Mitigation of the Volume 4,
Section 1 that identifies
our post-construction
security plan.

Local Businesses &


Tenants
Through our Public
Information Liaison, we

Figure 1.1-6: The SFI Safety Plan will ensure the safety
of local business and Port tenants.

Volume 2 Section 1 page 25

1.1.7
Draft DBE/UDBE Performance Plan

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

1.1.7 Summary DBE/UDBE


Performance Plan
RFP ITP Appendix B 1.1.7; D 1.1.1(f)

1.1.7.1 Policy

SFI Advantages
SFI has established relationships with local
UDBE and DBE firms from past projects.
Our superintendents and foremen know the subcontractors and suppliers, their ability to perform quality work, and their track record of
safety.
SFI has already started our UDBE/DBE Outreach
Program.

The Disadvantaged Business Enterprise/ Underutilized Disadvantaged Business Enterprise


(DBE/UDBE) Performance Plan of the SFI Joint
Venture ensures that DBE/UDBEs receive a
of contracts and providing technical oversight
fair and equitable opportunity to compete for
and appropriate assistance to DBE/UDBEs.
subcontracts awarded by SFI on the Gerald
This
will ensure a successful contractual relaDesmond Bridge Replacement Project (GDB).
tionship with our DBE/UDBE subcontractors
As part of our comprehensive outreach efforts
and suppliers.
and established relationships with local
We will use market research tools and the
DBE/UDBE firms, SFI will actively engage
DBE/UDBE Liaison Officers expertise to
DBE/UDBE firms in all available subcontractassist in administering the DBE/UDBE Outing opportunities throughout the life of the
reach Program as part of our larger subconproject. SFI is committed to utilizing good faith
tracting program. Purchasing managers will
efforts as set forth in 49 CFR 26.53 required for
consider each DBE/UDBEs availability to fulthe GDB Project to meet or exceed the
fill
specific requirements in the area of research
DBE/UDBE participation goal. We have
or
supporting
requirements.
incorporated a focused,
comprehensive outreach
Consistent with the
Ports DBE/UDBE goal
and supportive services
design-build concept,
plan that will assure
SFI will finalize subconSFI will meet or exceed the 11 percent
potential bidders access
tractor/supplier selecDBE/UDBE good faith effort.
that meets the spirit and
tions after final design is
intent of the Project
completed and accepted by the Port. SFI will
Goals.
provide ongoing technical support training,
access to a team of professionals who will assist
SFI will direct all subcontractorsboth large
when appropriate with bonding, funding, lines
and smallto ensure their commitment to
of credit, insurance, necessary equipment, suprecruiting DBE/UDBE subcontractors and
plies, materials and IT support.
suppliers and present a good faith effort (GFE)
throughout the duration of the Contract. SFI
Table 1.1-3 details and identifies major work
will assure that all of its subcontractors and
elements, materials, and equipment that will
vendors abide by the terms of our Plan.
potentially be subcontracted.

1.1.7.2 Subcontractor/Supplier
Project Opportunities
SFI will use a competitive process to select subcontractors and suppliers, and all areas of work
will be considered in order to maximize the use
of DBEs/UDBEs. SFI will compile a comprehensive list of design services, professional services and construction services of all aspects of
the Work that DBE/UDBEs could perform.
SFI will integrate all goals into project planning
and execution, which management and procurement staff will further develop. Together
they are responsible for the successful execution

DBE/UDBE Liaison Officer


Mr. Joe Hernandez has been designated as the
SFI DBE/UDBE Liaison Officer responsible
for the DBE/UDBE Performance Plan for the
GDB Project. His information is:
Name: Joe Hernandez
Address: 818 W 7th Street, Suite 750, Los
Angeles, CA 90017
Telephone: 213-891-2965
Email: jhernandez@leeandrewsgroup.com
CORE DUTIES

Mr. Hernandez is experienced and knowledgea-

Volume 2 Section 1 page 26

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

Subcontract
Mechanical and
electrical design
Traffic and signal design
Scheduling and project
controls
Asbestos/lead
abatement
Asphalt paving
Barge/tug
Bridge demolition
Building removals
CIDH deep foundations
Concrete barrier
Dewatering and
treatment

Fencing and guard rail


Flat work and minor
concrete
Landscaping design and
installation
Maintenance building
Overhead signage
Paintings and coatings
PCC paving
Polymer overlay
Post tensioning
Rebar
Strong motion sensor
instrumentation

Material and Supply


Aggregates
Bearings
Cable stay cables
Concrete
CSB inspection traveler
CSB maintenance
equipment
Dampers (seismic)
Falsework material
(steel pipe post steel
beams)
Joint seals
MSE wall
Permanent elevators
Post-tensioning (furnish
only)
Pre-cast deck panels
Structural steel (CSB)

Equipment
Movable scaffold
system (MSS)
Specialty formwork
(e.g., columns towers)
Tip crane
Tower crane

Table 1.1-3: Major work elements, materials, and equipment that will potentially be subcontracted.

ble concerning federal DBE/UDBE programs


and federal procurement practices. Working
closely with the Port, Mr. Hernandez will be
responsible for the development, preparation
and execution of the DBE/UDBE Performance
Plan and individual subcontracting plans, and
for monitoring performance relative to subcontracting requirements contained in this plan.
Mr. Hernandez other responsibilities include:
Working closely with the Subcontracts Manager to administer the SFI DBE/UDBE Performance Plan for the Project.
Providing technical assistance regarding
implementing the plan and disseminating
information.
Participating in quarterly reviews of the
progress of the DBE/UDBE Performance Plan
with the Port.
Developing and maintaining bidders lists of
DBE/UDBE firms.
Verifying certification of DBE/UDBE
firms.
Prequalifying and maintain logs of prequalified DBE/UDBE firms.
Ensuring the procurement packages allow
DBE/UDBEs to participate to the maximum extent possible.
Ensuring inclusion in solicitations for products or services which DBE/UDBEs are
capable of providing.

Reviewing solicitations to remove statements


which may impede or restrict DBE/UDBE
participation.
Ensuring periodic rotation of potential subcontractors on bidders lists.
Establishing and maintaining records of solicitations and subcontract award activity.
Maintaining records and requiring that subcontractors and suppliers are utilizing
UDBE/DBE firms in their subcontracts,
and are maintaining records for verification.
Monitoring attainment of DBE/UDBE
goals throughout the duration of the project.
Preparing and submitting periodic subcontracting reports.
Coordinating SFI activities during compliance reviews by Federal agencies.
Coordinating the conduct of SFI activities
involving its DBE/UDBE subcontracting.
Participating with local agencies to ensure
the integrity of the DBE/UDBE Performance
Plan throughout the projects duration.
Participating in Business Opportunity Workshops, Minority Business Enterprise Seminars, Trade Fairs, etc.
Developing the Calendar of Outreach
Events with assistance from the SFIs Subcontracts Manager and Business Manager.

Volume 2 Section 1 page 27

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

Figure 1.1-7: Sample of an outreach poster used by SFI during DBE/UDBE outreach.

Submitting the Business Outreach Event


Reports to the SFI Business Manager for all
attended events in order to identify followup and measure the success of the event for
future planning.
Securing the submission of the Business
Questionnaire from potential DBE/UDBE
subcontractors and suppliers. Along with the
request for the submission of the Business
Questionnaire, the Liaison Officer will
request company profiles and statements of
qualifications in order to build upon the
existing database.
Following-up with potential subcontractors
and suppliers to secure the submission of the
Business Questionnaire and disseminate
information to SFI estimators and project
personnel, establishing contact for qualification, proposal, and price quotations from
qualified DBE/UDBE firms.
Inputting information from the Business
Questionnaire, which identifies
DBE/UDBE areas of work and other criteria, into SFIs document control database.
Mr. Hernandez will conduct a monthly Outreach Meeting at a pre-determined location
close to the Port. The meeting will acquaint new
subcontractors and suppliers (including
DBEs/UDBEs) with the compliance criteria
and the SFI team. Working with the approved
Source
FTP Site
Hotline
Email
Port
website

Access
https://shimmick.egnyte.com
(949) 333-1505
SFI.GDB.outreach@shimmick.com
http://www.polb.com/about/projects/g
db/documents.asp

Table 1.1-4: SFI will provide convenient means for


subcontractors to keep up-to-date.

certifying agencies, SFI will also provide assistance to firms in acquiring certifications as
necessary.

1.1.7.3 Outreach Efforts


Outreach efforts conducted by SFI are geared
for the success of the Project. SFI has created
an external FTP site for all potential subcontractors and suppliers (including DBE/UDBE
firms) that will identify work packages. SFI has
also established an Opportunity Hotline, as well
as an email address, to respond to questions
concerning bidding opportunities. Contract
documents will be obtained at the Ports website. Other Outreach Efforts include:
Contacting minority and small business trade
associations, veterans service organizations
and Small Disadvantaged Business Utilization Offices.
Contacting Small/Minority/Disadvantaged
Business Enterprise Professional/ Community-based Organizations.
Contacting with Federal, State, Local and
private development organizations.
Attending small and disadvantaged business
procurement conferences and trade fairs, including outreach events identified not only
by the Port but other local and state agencies. SFI has already been effective in soliciting and identifying interest with participation at outreach events since our team was
prequalified, and continues to identify
potential DBE/UDBE sources to be solicited. SFIs Calendar of Outreach Events
extends to currently identified events
through May 2012.
Outreach Events
As part of our ongoing outreach activities, SFI
will also develop and maintain a comprehensive

Volume 2 Section 1 page 28

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


The Gerald Desmond Bridge Replacement Project Proposal

list of DBE/UDBE firms through multiple


Advertisement
resources:
SFI has identified a number of Trade, Focus
California Department of Transportation
and Local Publications, Local Recruitment/
Placement Organizations, and Small Business
Office of Business and Economic OpporDevelopment Centers in which to place our
tunity Certification Unit
advertisements. SFIs advertisements have been
DBE/UDBE Certification Directory
written to provide our potential DBE/UDBE
http://www.dot.ca.gov/hq/bep/
Subcontractors and
Suppliers with the fol City of Los Angeles
SFI hosted a DBE/UDBE outreach event on
lowing information:
Bureau of Contract
January 17 at the Small Business DevelopAdministration
Project name and
ment Center at Long Beach City College with
DBE/MBE/WBE
description
great success. The calendar of outreach
Listing
events details outreach efforts attended by
Bid date and time
http://bca.lacity.org/i the SFI team during the procurement period
ndex.cfm?nxt=ots&n
and into May 2012.
Subcontracting and
xt_body=otsindex.cf
supplier opportunities
m
Project contact information
Los Angeles Metropolitan Transportation
Specific assistance offered by SFI
Authority DBE Listing.
Availability of plans and specifications
Metropolitan Water District of Southern
California Outreach Listing.
Bonding and subcontracting requirements
UDBEs that Shimmick Construction has
Although 49 CFR Part 26 does not address a
used on past projects.
specific amount of days that advertisements
must be placed before a project bids, SFI will
Port of Long Beach DBE Program.
provide a sufficient amount of time for our
U.S. Federal Central Contractor Registration
potential DBE/UDBE subcontractors and supDatabase.
pliers to submit a well-informed bid price.
SFI Document Control Database.
Dates
8/11/2011
9/12/2011
9(21/2011
10/04/2011
10/28/2011
11/03/2011
12/07/11
1/10/2012
1/19/2012
1/24/2012
1/25/2012
2/01/2012
2/02/2012
2/14/2012
2/27/2012
3/21/2012
4/19/2012
5/15/2012

Event
California Construction Expo 2011
Crenshaw LAX Transit Project Meet and Greet
Caltrans District 12 Construction Contractors Outreach
Port of Long Beach Pre-Proposal Conference
OCTA 2011 Small Business Conference
Matchmaking Event: Creating Access to Opportunity
Regional Connector Transit Corridor Project Meet and Greet
How To Do Business with Metro - Monthly Workshop
5th Annual San Joaquin Valley Regional Conference Public Contracting
Expo
SOF Open House Los Angeles Council District 8
Training & Networking Form Contracting for Success
WTS Caltrans District 7: WTS Annual Small Business Speakers Series
2012 Helping Small Businesses Grow
Metro: Meet the Primes
How To Do Business with Metro Monthly Workshop
Reservation Economic Summit & American Indian Business Trade Fair
Caltrans District 11 8th Annual Small Business Exchange
22nd Annual OSDBU Procurement Conference 2012
Keeping the Promise California Disabled Veterans Alliance Business
Matchmaking

Table 1.1-5: Calendar of outreach events.

Volume 2 Section 1 page 29

Location
Pasadena, California
Los Angeles, California
Irvine, California
Long Beach, California
Orange, California
San Pedro, California
Los Angeles, California
Los Angeles, California
Fresno, California
Los Angeles, California
Long Beach, California
Los Angeles, California
Los Angeles, California
Los Angeles, California
Las Vegas, Nevada
San Diego, California
Washington D.C.
Los Angeles, California

Shimmick Construction Company, Inc./FCC Construccin S.A./Impregilo S.p.A., a Joint Venture


Gerald Desmond Bridge Replacement Project Proposal

SOURCES FOR ADVERTISEMENT

Minority Bidder Bulletin


Construction Update
Compliance News (Focus and Trade Journals)
W/M/S/DVBE Contract and Construction
News
Thomas Bid Register
Small Business Exchange
Reed Construction Data: Daily Construction
Service and Construction Bulletin
McGraw-Hill (Green Sheet)
Press Telegram

1.1.7.4 Assistance Programs


SFI will seek to compress the learning curve for
any DBE/UDBE firm by offering them the
opportunity for personal assistance. Each

DBE/ UDBE firm will be assigned to an SFI


representative who will work directly with the
SFI DBE/UDBE Liaison Officer to provide
technical support. SFI will provide highly participatory programs where subcontractors can
take the next big step by providing independent
evaluations of technical job tasks. Each subcontracting opportunity will be followed by a
meeting to reinforce effective use of technique
and recommend ways to enhance skill development. Whether a DBE/ UDBE firm is in the
initial stages of formalizing training efforts or
looking to augment an existing training plan,
SFI can provide significant help in achieving
goals with the extension of participation in our
training regimens. Financial assistance may be
offered on a case-by-case basis. In addition, SFI
will encourage eligible DBE/ UDBEs to apply
for certification with Caltrans.

Volume 2 Section 1 page 30

You might also like