You are on page 1of 9

Newspaper Headquarter Building in North England

University of Leeds- Civil EngCivil Engineering School


l
01/01/2013
08/02/2014

Project Name
Project Manager
Project Start Date
Project Deadline

403 Days

Scheduling Frequency

duration

Activity description
item No.

site preparation and layout


1

diaphragm wall construction


2

excavating for diaphragmwall


3

steel reinforcement erection


4

conrete casting of diaphragm pile wall


5

Expectd
Actual
Expectd
Actual
Expectd
Actual
Expectd
Actual
Expectd
Actual

4 days

15 days
16 days
17 days

Excavation process and installing prpped pipes


6

First stage of excavation


i

First stage of installing propped pipes


ii

Second stage of excavation


iii

Second stage of installing propped pipes


iv

Third and forth stage of excavation


v

Third stage of installing propped pipes


vi

Excavating rock layer and leveling ground of basement floor


vii

installing tower crane


7

Expectd
Actual 28 days
Expectd
Actual 21 days
Expectd
Actual 26 days
Expectd
Actual 21 days
Expectd
Actual 20 days
Expectd
Actual 19 days
Expectd
Actual 12 days
Expectd
Actual 9 ays

excavation of pad foundation


5 days

steel reinforement erection of an concrete casting pad


foundation
concrete casting basment floor surface

5 days
3days
2 days

10

11

12

Second basement floor constrction


Installing steel column for bothconstruction joints second
basement level
installing steel beams for both construction joint second
basement level
removing forth row of propped pipes

13

Conrete casting of core wall for second basement


14

removing third row of propped pipes


15

16

17

18

19

20

21

22

installing precast hollow concrete for first joint /second


basment floor
installing precast hollow concrete for second joint /second
basment floor
transverse reinforcement placing and casting topping of
second basement slab
transverse reinforcement placing and casting topping of
second basement slab/second joint
First basement floor constrction
installing coulmn in the first basement level / first
construction joint
installing coulmn in the first basement level / second
construction joint
installing steel beams for both construction joint first
basement level
removing second and first row of propped pipes

23

24

25

26

installing precast hollow concrete for first joint /first basment


slab
installing precast hollow concrete for second joint /first
basment slab
transverse reinforcement placing and casting topping of first
basement slab
Conrete casting of core wall for second basement

27

First level constrction


installing coulmn in the first level / first construction joint
28

installing coulmn in the first level / second construction joint


29

installing steel beams for t first level /first joint


30

installing steel beams for t first level /second joint


31

installing precast hollow concrete for first joint /firstlevel slab


32
33

installing precast hollow concrete for second joint /first level


slab
Conrete casting of core wall for first level

34
35
36

transverse reinforcement placing and casting topping of first


level slab/ first joint
transverse reinforcement placing and casting topping of
firstlevel slab/second joint
installing scaffold

37

Second level constrction


installing coulmn in the second level / first construction joint
38

installing coulmn in the first level / second construction joint


39

installing steel beams for t second level /first joint


40

installing steel beams for t first basement level /second joint


41
42
43

installing precast hollow concrete for first joint /second level


slab
installing precast hollow concrete for second joint /first level
slab
Conrete casting of core wall for second level

44

45

46

transverse reinforcement placing and casting topping of


second level slab/ first joint
transverse reinforcement placing and casting topping
ofsecond level slab/second joint
installing scaffold

47

Precast concrete cladding


48

Third level constrction


installing coulmn in the 3rd level / first construction joint
49

installing coulmn in the 3rd level / second construction joint


50

Jan-13

week 1

Expectd
Actual 3 days
Expectd
Actual 5 days
Expectd
Actual 2 days
Expectd
Actual 5 days
Expectd
Actual 2 days
Expectd
Actual 7 days
Expectd
Actual 5 days
Expectd
Actual 7 days
Expectd
Actual

5 days

Expectd
Actual 3 days
Expectd
Actual 5 days
Expectd
Actual 8 days
Expectd
Actual 4 days
Expectd
Actual 4 days
Expectd
Actual 5 days
Expectd
Actual 5 days
Expectd
Actual 7 days
Expectd
Actual 2 days
Expectd
Actual 2 days
Expectd
Actual 5 days
Expectd
Actual 5 days
Expectd
Actual 5 days
Expectd
Actual 5 days
Expectd
Actual 6 days
Expectd
Actual 5 days
Expectd
Actual 5 days
Expectd
Actual 10 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
3 days

week2

week3

Feb-13

week 4

week 5

week 6

Mar-13

week 7

week 8

week 9

wekk10

week 11

Apr-13

week 12

week 13

week 14

week 15

week 16

installing coulmn in the 3rd level / second construction joint


50

installing steel beams for t second level /first joint


51

installing steel beams for t 3rd level /second joint


52
53
54

installing precast hollow concrete for first joint /second level


slab
installing precast hollow concrete for second joint /2nd level
slab
Conrete casting of core wall for 3rd level

55
56
57

transverse reinforcement placing and casting topping of 3rd


level slab/ first joint
transverse reinforcement placing and casting topping of 3rd
level slab/second joint
installing scaffold

58

Precast concrete cladding


59

Forth level constrction


installing coulmn in the 4th level / first construction joint
60

installing coulmn in the 4th level / second construction joint


61

installing steel beams for t second level /first joint


62

installing steel beams for 4th level /second joint


63

installing precast hollow concrete for first joint /4th level slab
64
65

installing precast hollow concrete for second joint /4th level


slab
Conrete casting of core wall for 4th level

66
67
68

transverse reinforcement placing and casting topping of 4th


level slab/ first joint
transverse reinforcement placing and casting topping of 4th
level slab/second joint
installing scaffold

69

Precast concrete cladding


70

Fifth level constrction


installing coulmn in the 5th level / first construction joint
71

installing coulmn in the 5th level / second construction joint


72

installing steel beams for5th level /first joint


73

installing steel beams for 5th level /second joint


74

installing precast hollow concrete for first joint /5th level slab
75
76

installing precast hollow concrete for second joint /5th level


slab
Conrete casting of core wall for 5th level

77
78
79

transverse reinforcement placing and casting topping of 5th


level slab/ first joint
transverse reinforcement placing and casting topping of 5th
level slab/second joint
installing scaffold

80

Precast concrete cladding


81

Sixth level constrction


installing coulmn in the 6th level / first construction joint
82

installing coulmn in the 6th level / second construction joint


83

installing steel beams for 6th level /first joint


84

installing steel beams for 6th level /second joint


85

installing precast hollow concrete for first joint /6th level slab
86
87

installing precast hollow concrete for second joint /6th level


slab
Conrete casting of core wall for 6th level

88
89
90

transverse reinforcement placing and casting topping of 6th


level slab/ first joint
transverse reinforcement placing and casting topping of 6th
level slab/second joint
installing scaffold

91

Precast concrete cladding


92

Seventh level constrction


installing coulmn in the 7th level / first construction joint
93

installing coulmn in the 7th level / second construction joint


94

installing steel beams for 7th level /first joint


95

installing steel beams for 7th level /second joint


96

installing precast hollow concrete for first joint /7th level slab
97
98

installing precast hollow concrete for second joint /7th level


slab
Conrete casting of core wall for 7th level

99
100
101

transverse reinforcement placing and casting topping of 7th


level slab/ first joint
transverse reinforcement placing and casting topping of 7th
level slab/second joint
installing scaffold

102

Precast concrete cladding


103

Eighth level constrction


installing coulmn in the 8th level / first construction joint
104

installing coulmn in the 8th level / second construction joint


105

installing steel beams for 8th level /first joint


106

installing steel beams for 8th level /second joint


107

installing precast hollow concrete for first joint /8th level slab
108
109

installing precast hollow concrete for second joint /8th level


slab
Conrete casting of core wall for 8th level

110
111
112

transverse reinforcement placing and casting topping of 8th


level slab/ first joint
transverse reinforcement placing and casting topping of 8th
level slab/second joint
installing scaffold

113

Precast concrete cladding


114

Ninth level constrction


installing coulmn in the 9th level / first construction joint
115

installing coulmn in the 9th level / second construction joint


116

installing steel beams for 9th level /first joint


117

Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days

installing steel beams for 9th level /second joint


118

installing precast hollow concrete for first joint /9th level slab
119
120

installing precast hollow concrete for second joint /9th level


slab
Conrete casting of core wall for 9th level

121
122
123

transverse reinforcement placing and casting topping of 9th


level slab/ first joint
transverse reinforcement placing and casting topping of 9th
level slab/second joint
installing scaffold

124

Precast concrete cladding


125

Tenth level constrction


installing coulmn in the 10th level / first construction joint
126

installing coulmn in the 10th level / second construction joint


127

installing steel beams for 10th level /first joint


128

installing steel beams for 10th level /second joint


129

installing precast hollow concrete for first joint /10th level slab
130
131

installing precast hollow concrete for second joint /10th level


slab
Conrete casting of core wall for 10th level

132
133
134

transverse reinforcement placing and casting topping of 10th


level slab/ first joint
transverse reinforcement placing and casting topping of 10th
level slab/second joint
installing scaffold

135

Precast concrete cladding


136

Eleventh level constrction


installing coulmn in the 11th level / first construction joint
137

installing coulmn in the 10th level / second construction joint


138

installing steel beams for 11th level /first joint


139

installing steel beams for 11th level /second joint


140

installing precast hollow concrete for first joint /11th level slab
141
142

installing precast hollow concrete for second joint /11th level


slab
Conrete casting of core wall for 11th level

143
144
145

transverse reinforcement placing and casting topping of 11th


level slab/ first joint
transverse reinforcement placing and casting topping of 11th
level slab/second joint
installing scaffold

146

Precast concrete cladding


147

Roofing
148

landscaping and Gardenning


149

water supplement and sewarage


150

electrical work
151

mechanical work
152

finishing
153

Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days

Expectd
Actual 3 days
Expectd
Actual 3 days
Expectd
Actual 4 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 6 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 7 days
Expectd
Actual 12 days
Expectd
Actual 17 days
Expectd
Actual 12 days
Expectd
Actual 14 days
Expectd
Actual 200 days
Expectd
Actual 200 days
Expectd
Actual 40 days
Expectd
Actual 150 days

May-13

week 16

week 17

week 18

Jun-13

week19

week 20

week 21

week 22

Jul-13

week 23

week 24

week 25

week 26

Aug-14

week 27

week 28

week 29

week 30

Sep-13

week 31

week 32

week 33

wek34

week 35

week 37

week 38

Oct-13

week 38

week 39

Nov-13

week 40

week 41

week 42

week 43

Dec-13

week 44

week 45

week 46

week 47

Jan-13

week 48

week 49

week 50

week 51

Feb-13

week 52

week 53

week 56

You might also like