Generation and Reservoirs Statistics

08th June 2015

PUBLIC UTILITIES COMMISSION OF SRI LANKA

08th June 2015

Generation Mix in MWh


1593

1861
14184

CEB Hydro
CEB Thermal Oil

15690

CEB Coal
IPP Thermal

2990

SPP Wind

Total Generation - 36,318MWh

Note: Generation from other SPPs (Mini Hydro, Solar and Biomass) is not included

Cumulative Dispatch
01st June 08th June

From 01st January 08th June

Category

Dispatch (MWh)

Category

Dispatch (GWh)

CEB Hydro

113,236

43.26%

CEB Hydro

2,150

40.16%

CEB Thermal Oil

18,439

7.04%

CEB Thermal Oil

254

4.74%

CEB Coal

114,090

43.59%

CEB Coal

2,401

44.86%

IPP Thermal

5,757

2.20%

IPP Thermal

268

5.02%

SPP Wind

10,237

3.91%

Renewable

280

5.22%

Total

261,760

Total

5,353

Note: Generation from Mini Hydro, Solar and Biomass power plants in April, May and June is not
included in annual cumulative renewable generation figure.

Dispatch on 08th June 2015


MWh
7000

6000

5000

4000

Rated Capacity
Available
Dispatched

3000

2000

1000

Night Peak Contribution on 08th June 2015


MW
300

250

200
Installed
Capacity
150

Available
Capacity
Night Peak Load

100

50

Contribution to the Night Peak in MW


108.7 76.1

658

CEB Hydro

1038.8

CEB Thermal Oil


CEB Coal

217.4

IPP Thermal
SPP Wind

Night Peak - 2099MW

Day Peak Demand 1840.4MW


Minimum Recorded Demand 944.8MW

Reservoir Storage Levels ( As at 06.00 hr on 09th June 2015)


GWh
270
56.3%

240
210
180
150
120

38.2%

90

84.8%
68.2%

54.1%

60
30

21.3%

0
Castlereigh

Maussakelle

Kotmale

Victoria

Randenigala Samanalawewa

Note: Hydro Reservoir Storage Capacity as at 08th June 2015 677.5Wh (53.83%)

GWh

Comparison of Reservoir Storage

1200

1000

800

2012
2013

600

2014
2015
400

200

Demand Variation 2015


2400

MW

2200
2000
1800
1600
1400
1200

Nigh Peak

1000

Day Peak

800

Minimum
Demand

600
400

200

Note: Contribution from Mini Hydro, Solar and Biomass is not included

4-Jun

28-May

21-May

14-May

7-May

30-Apr

23-Apr

16-Apr

9-Apr

2-Apr

26-Mar

19-Mar

12-Mar

5-Mar

26-Feb

19-Feb

12-Feb

5-Feb

29-Jan

22-Jan

15-Jan

8-Jan

1-Jan

6000

GWh

Comparison of Cumulative Dispatch from 01st January - 08th June

5000

4000

SPP Wind
IPP
CEB Coal

3000

CEB Oil
CEB Hydro

2000

1000

2014

2015

Year

GWh

Comparison of Cumulative Dispatch

12000
11000
10000

9000
8000
7000

2014

6000

2015
5000
4000

3000
2000
1000
0

Note: Generation from SPP Mini Hydro, Solar and Biomass is not included
9

List of Power Stations


Power Station

Capacity (MW)

Primary Fuel

CEB Hydro
Victoria
Ukuwela
Kotmale

Randenigala
Rantambe
Bowatenna
Nilambe
Upper Kotmale
Old Laxapana
New Laxapana
Polpitiya
Wimalasurendra
Canyon
Samanalawewa
Kukuleganga
Inginiyagala
Udawalawe

210
40
201
122
49
40
3.2
150
50
115
75
50
60
120
75
10
6

CEB Thermal
Sapugaskanda 1
Sapugaskanda 2
Kelanitissa Small Gas Turbines
GT 7 - Kelanitissa
Kelanitissa CCY
Lakvijaya (Puttalam Coal)
Lakvijaya (Puttalam Coal) Stage II
Lakvijaya (Puttalam Coal) Stage III
New Chunnakam

72
72
85
115
165
285
285
285
24

Private Thermal (IPPs)


Asia Power
AES Kelanitissa
Colombo Power
West Coast
Northern Power

51
163
60
270
27

10

Heavy Fuel
Heavy Fuel
Auto Diesel
Auto Diesel
Naptha & Diesel
Coal
Coal
Coal
Heavy Fuel

Heavy Fuel
Auto Diesel
Furnace oil
Low Sulphur Furnace oil
Auto Diesel