Professional Documents
Culture Documents
1.0 INTRODUCTION
The study conducted for flexible pavement on the Summerlin Subdivision has been
accomplished. The developed area is located in the intersection of Railroad Drive and
Angora Loop Street in northeast El Paso, Texas.
2.0 PROJECT DESCRIPTION
The area to be covered with flexible pavement at the Summerlin Subdivision is
approximately 13,200 lineal feet. The scope of this study is to give the parameters needed
for the flexible pavement design that will be used in the area above mentioned.
3.0 ENGINEERING INVESTIGATION
3.1 Field Exploration
Fourteen soil borings were drilled in the planned section for paving. The ASTM D 6151
and D 1586 were followed for drilling using a truck-mounted CME-55 rig. The rig drilled
to a depth of approximately 6.5 feet at regular intervals along what is going to be the
street. See the attached appendix for further reference of the logs that belong to each
boring hole. The soils samples obtained were properly labeled and placed in containers
and tested in the laboratory.
3.2 Geotechnical Laboratory Testing
Once in the laboratory, the samples were tested in order to obtain their mositure content,
the size of the soils particles by doing sieve analysis and the Atterberg Limits. Along
with the tests mentioned above, four California Bearing Ratio (CBR) tests were
performed using ASTM D 1883. The CBR value is needed for the AASHTO pavement
design calculations.
4.0 GENERAL SITE CONDITIONS
4.1 Area Geology
The area where the Summerlin Subdivision is going to be constructed lies on the
Northeast of El Paso, Texas. The soil in this section is made up of fine sand and caliche.
4.2 Site Topography
The section has been developed for construction similar to the surroundings where there
are commercial and residential lots. The area is mostly arid.
Page 2 of 5
Unit
2.0
inches
5.5
inches
8.0
inches
Layer
Page 3 of 5
Based on the clayey sands soils potential for shrinking and swelling, we recommend that
these soils not be used as support of the base course component for the pavement
sections. Removal of the underlying soils should be achieved and replaced with a
minimum of 8.0 inches of an adequate structural fill material. Soils recommended as
structural fill should be classified according to the Unified Soil Classification System and
are as follows:
GM, GC, GW-GC, GW-GM, GP, GP-GM, GP-GC, SM, SC, SW-SM, SW-SC, SP-SM,
SW-SC, and SC-SM.
Soils not recommended as structural fill material are those with a liquid limit exceeding
35 and a plasticity index that exceeds 15. Compaction of the material should be done
with approved types of pneumatics or tamping equipment that agree with Item 210 from
TxDOT.
5.4 Site Preparation
All organic matter such as vegetation should be removed before construction of pavement
sections is begun. Subgrade soils should be compacted to a minimum of 95% of dry unit
weight in accordance with ASTM D1557 test procedure.
5.5 Site Drainage
Surface drainage should be provided during and after construction by providing a ground
surface slope of 2 percent grade (minimum) away from the pavement structure.
Page 4 of 5
Calculations
Procedure:
The steps in the 1993 AASHTO flexible pavement design procedure combined with the
City of El Paso Subdivision Improvement Design Standards are summarized below in the
context of the baseline scenario presented by LEC:
1.
2.
3.
4.
Determine the allowable serviceability loss due to traffic: PSI = 2.2 given by
equation:
PSI = pt po=4.22.0=2.2
5.1
5.
6.
7.
Page 5 of 5
Also,
Solving Equation:
5.3
for the required overall structural number (SN): SN = 2.71.
Therefore, use SN=2.5
8.
Determine the design layer thicknesses for the pavement section to apply to
equation:
5.4
rounding to the nearest half-inch, per the recommendations in the 1993 AASHTO Design Guide.
Unbound layer thicknesses are rounded to the nearest inch.