Professional Documents
Culture Documents
For
AkronPK12School
December13,2011
ExecutiveSummary
JirsaHedrickStructuralEngineers,Inc.providedanindependentpeerreviewofthestructuraldesignfor
AkronPK12School.MarkSorensenisthestructuralEngineerofRecord.
Theresultsofthereviewcanbesummarizedinthreecategories:
Nosignificantstructuralissuesthatwouldresultinunsafeconditionsorfailureofthestructural
system
Twomoderatestructuralissues:
o Foundationmodificationsattworestroomcorestopreventsettlement
o Additionofcolumnbracingatthe2ndfloorandrooftoenhanceperformanceofthe
structure
Minormodificationstooriginaldetailsforclarityandconsistencywiththestructuralsteelshop
drawings
Whenconstructioniscomplete,priortooccupancybytheSchoolDistrict,theEngineerofRecordwill
confirmtheresultsofthepeerreviewreportwereincorporatedintotheconstructionoftheproject.
TableofContents
Section1
Section2
Section3
Section4
Section5
PeerReviewReportCoverLetter
IndependentPeerReviewProcessSummary
MemorandumofAction
LetterofAgreementfromJirsaHedrickStructuralEngineers
ResponsefromEngineerofRecordtoPreliminaryPeerReviewComments
Section6
Section7
PreliminaryPeerReviewCommentsfromJirsaHedrick
SupplementalInformation
Section2
IndependentPeerReviewProcessSummary
1. The3rdpartyreviewfirmisselectedonqualificationsandcapacity.
2. Existingrecorddrawings,shopsdrawings,soilsreport,calculations,peerreviewprocessflow
map,andscopeofworkaregiventothe3rdpartyreviewfirm.Additionalinformationsuchas
caissiondrillinglogs,etc.,arealsoprovidedasneededandrequested.
3. 3rdpartyreviewfirmmakesafeeproposal(typicallyhourlyrateswithanestimateoftotalcost
tocompletethereviewprocess).
4. Contractisputinplacewiththe3rdpartyreviewfirm.
5. 3rdpartyreviewfirmconductsreviewandcreatespreliminarylistofquestionsandpossible
concerns.ThereviewfirmalsosubmitsinquiriestoEngineerofRecord/ResponsibleEngineerin
Chargeasneededduringthistime.
6. 3rdpartyreviewfirmandEngineerofRecord/ResponsibleEngineerinChargemeettoreview
preliminarylistofquestionsandpossibleconcerns.Thetwopartiesagreeuponnextsteps.
7. EngineerofRecord/ResponsibleEngineerinChargecompleteswork(i.e.calculations,details,
researchordrawings)neededtorespondinwritingtothepreliminarylistofquestions.
8. 3rdpartyreviewfirm,EngineerofRecord/ResponsibleEngineerinCharge,andNeenanstaff
worktogethertoalignonanyneededactions.
9. EngineerofRecord/ResponsibleEngineerinChargecreateswrittenresponsewithproposed
modifications(asneeded)to3rdpartyreviewfirmscommentsandquestions.
10. 3rdpartyreviewfirmsubmitsletterofagreementregardingtheEngineerofRecord/Responsible
EngineerinChargesresponsesandproposedmodifications.
11. EngineerofRecord/ResponsibleEngineerinChargewritesandstampsaMemorandumofAction
(MOA)thatprovidesdirectiononstructuralmodificationsofthebuilding(ifneeded),or
confirmationoftheadequacyofthestructuraldesign.
12. TheMOA,letterofagreement,andotherdocumentationarepresentedtotheclientinafinal
report.
Ifmodificationstothebuildingarerequired,Neenanschedulesnecessaryworkwiththeclient.
SECTION3
MemorandumofAction
AsEngineerofRecord,Mr.SorensonissuedaMemorandumofAction(MOA)toformalizetherequired
modificationsforAkronPK12SchoolaftertheindependentstructuralpeerreviewbyJirsaHedrick
StructuralEngineers.
TheMOAoutlineschangesthathavebeenincorporatedinthesubmittalreviewprocessanditemsthat
needtobeimplementedinthefield.
Thefinalcommentsthatrequiredactioncanbesummarizedinthreecategories:
Nosignificantstructuralissuesthatwouldresultinunsafeconditionsorfailureofthe
structuralsystem
Twomoderatestructuralissues:
o Foundationmodificationsattworestroomcorestopreventsettlement
o Additionofcolumnbracingatthe2ndfloorandrooftoenhanceperformanceofthe
structure
Minormodificationstooriginaldetailsforclarityandconsistencywiththestructuralsteel
shopdrawings
Comments17and20havebeenaddressedwithVulcraft.Formoredetails,pleaserefertoattachments
inSection7.
SECTION4
LetterofAgreementfromJirsaHedrickStructuralEngineers
TheLetterofAgreementissuedbytheindependentstructuralpeerreviewfirm,JirsaHedrickStructural
Engineers,acknowledgestheiragreementwiththeresponsesandproposedactionsfromMark
Sorensen,EngineerofRecord.Theletterlistsfiveexceptions,whichwereresolvedpriortotheissuance
oftheMemorandumofAction(seesection3).
JtRSAI
7000 E BelleviewAve, Suite250
GreenrvoodVillage.CO tlOtI I
3 0 3 . 8 3 9| .9 6 3
November
16,2011
MarkE.Sorenson,
P.E.
THENEENAN
COMPANY
2620E.Prospect
Road,Suite100
FortCollins,
CO80545
RE:
AkronSchoolPeerReview
JHProjectNo.: 20110903
DearMark:
We havereviewedyourresponse
to our PeerReviewComments
dated13 October2011whichincludes
updateddrawings,
updatedcalculations
andyourletterof November
7,zOL', Wetakeno exceptlons
to
yourresponses
andnotedcorrected
actionswithinthesedocuments
exceptasoutlinedbelow:
comment1
Comment3
The specialtyengineerdesignof the helicalpiersshallbe reviewedand acceptedthe
Engineer
of Recordprior to installation.Notethe difficultyof transferring
50 kip loadsbetweenthe
screwpilesandthe existingshallowfootingandCMUwall.
C,omment
8
Clarifythe type and amountof weldingbetweenthe anglesand the metal deckto
transferthe braceforcesto the diaphragm.
Comment20 Vulcraftshouldalsoreviewthe imposeduplifton the back-span
of thesejoistsdue to
thisnewbracingandverifono repairsarerequired.
Comments
35 and45 Thesedetailsshouldalsobecloudedto highlightthe notedchanges.
Sincerely,
JIRSA
HEDRICK
J.TimothyHickisch,
P.E.
SECTION5
ResponsefromEngineerofRecordtoPreliminaryPeerReviewComments
MarkSorensen,EngineerofRecord,issuedaresponsetothepreliminarypeerreviewcommentsfrom
JirsaHedrickStructuralEngineers.OnOctober17,2011,priortoissuingthisresponse,Mr.Sorensenmet
withEdButeynofJirsaHedricktoreviewanddiscussJirsaHedrickscommentsandconcerns,andreview
structuraldrawingandcalculations.Asaresultofthatmeeting,bothpartiesagreedthatasignificant
amountofthepreliminarycommentsrequirednofurtheraction,asnotedintheresponseletter.
November 7, 2011
To:
JIRSA|HEDRICK
& ASSOCIATES
Structural Engineers
Mark E. Sorenson, PE
From:
Structural Engineer
THE NEENAN COMPANY
2620 E. Prospect Road, Suite 100
Fort Collins, CO 80525
Re:
Response to: Akron School Peer Review Comments dated 13 October 2011
Ed:
As I am sure that you are aware, the Design Build delivery method is one in which numerous
items are coordinated and checked during the submittal review process. This is due to the fact
that the designer does not have all of the required information at the time of the initial design. I
appreciate your review of this project. Below are my responses to all of your comments.
Comment
Number
1
Number
S0.02
S0.02
S1.22
S1.22
CDN#2409A-089
S1.24
S1.24
S1.24
S1.24
S1.24
10
S1.24
11
S1.24
12
S1.24
CDN#2409A-089
13
S1.24
14
S1.31
15
S1.31
16
S1.31
17
S1.31
18
S1.31
19
S1.31
20
S1.31
21
S1.31
22
S1.32
CDN#2409A-089
23
S2.11
24
S2.11 &
S2.12
25
26
S2.14
(Should
be S4.11)
S5.11
27
S5.11
28
S5.11
29
S5.12
30
S5.12
31
S5.12
32
S5.12
33
S5.13
CDN#2409A-089
34
S5.13
35
S5.13
36
S5.13
37
S5.13
38
S5.14
39
S5.14
40
S5.14
CDN#2409A-089
41
S5.14
42
S5.14
43
S5.15
44
S5.15
45
S5.15
46
S5.15
47
S5.15
48
Calcs
CDN#2409A-089
49
Calcs
CDN#2409A-089
The exterior columns are all adequate for the bending induced
by the offset connections. RISA calculates the actual Cb. Your
comment indicates that Cb values of 2.7 and 1.75 were used
for the two column segments. The RISA output indicates that
Cb values of 2.3 (not 2.7 as indicated) and 1.75 were used. The
code puts an upper bound of 2.3 on Cb. While it is
conservative to use a value of Cb = 1.0, the code does allow for
the actual value of Cb to be computed. The RISA output is
correct and the columns are adequate for the design loads. As
indicated previously, all columns will be braced at the roof and
the floor level so the wind load will transfer directly into the
diaphragm, and not have to be resisted by the column. No
action is required for this item.
SECTION6
PreliminaryPeerReviewCommentsfromJirsaHedrick
JirsaHedrickissuedtheirpreliminarycommentsafterreviewingthedrawingsandcalculationsprovided
byTheNeenanCompany.Thiswastheinitialstepintheindependentpeerreviewprocess,whichalso
includedtheresponsefromtheEngineerofRecord,letterofagreementfromJirsaHedrick,and
MemorandumofAction.
CDN#2409A-089
13 October 2011
Comment
Number
Sheet
Number
Comment
S0.02
S0.02
The seismic overstrength factor is 3.0, not 2.5, for systems not
specifically detailed for seismic resistance as defined in the code.
S1.22
Confirm the 2-0 wide footing (WF20) for the interior CMU walls is
adequate for gravity loads and overturning forces due to lateral
loads. The footing capacity at 1500 psf is 3000 plf. The gravity
loads for some walls exceed 5000 plf. It appears that this footing is
significantly undersized.
S1.22
Confirm that the west wall of the eastern CMU core is adequate to
resist lateral forces. Page 41 of the calculations indicates this wall is
to resist 33 kips of wind load laterally. This wall has two door
openings in it, leaving only 10-0 of CMU. Is additional reinforcing
required?
S1.24
S1.24
There are two beams framing into the southeast corner of the CMU
elevator shaft. The saddle detail (4/S5.13) does not work at this
location.
S1.24
There should be additional snow load due to sliding from the high
roof to the low roof between grids 5 and 7 north of grid E.4.
CDN#2409A-089
Comment
Number
Sheet
Number
Comment
S1.24
S1.24
Confirm that the snow drift on the low roof is 25 psf over the entire
low roof north of grid F.3 between grids 8.7 and 9.8 due to sliding
snow off the adjacent high roof.
10
S1.24
W18x35 beams are being used for beams less than 22-0 in many
locations. Typical beams of 22-0 or less only require a W14x22 or
smaller.
11
S1.24
There are many locations where the beams are the same depth or
deeper than the girders. This requires double coping of the beam,
which is not very desirable. It would be better if the girders were
deeper than the beams.
12
S1.24
Confirm the following columns are connected to the C15 edge beam:
B.1 @ 8 & 10 and A.2 @ 8.8 & 9.2. Graphically, it appears they are
not.
13
S1.24
The two C4 columns along grid 7 at grid C and C.1 are overstressed
with a unity check of about 3.0 because the girders frame into the
side of the column with no balancing load on the opposite side. A
solution may be to extend the girders over top of the columns. As
mentioned elsewhere in these comments, all columns must be
designed for combined axial and flexural loads.
14
S1.31
15
S1.31
CDN#2409A-089
Comment
Number
Sheet
Number
Comment
16
S1.31
The brace along grid 9.8 (6/S2.12) transfers load from the high roof
only. Confirm that loads parallel to this brace from the low roof north
of grid H can be transferred by the HSS columns or provide another
level of bracing similar to 7/S2.12.
17
S1.31
18
S1.31
19
S1.31
The graphics for the framing between grids 10.8 and 12 and
between A.7 and C are so dense that it is difficult to determine the
actual framing. Our recommendation is to provide an enlarged plan
for this area.
20
S1.31
Confirm the snow drift on the cantilevered ends of the joist between
grids C.4 and D. The step between these two roofs varies. When
the roof step is greater than 7.5, the maximum drift is 133 psf.
Where the step is less than 7.5, the maximum drift is 62 psf.
Confirm the nearly 7-0 cantilevered ends of the joist are adequate
for strength and deflection.
21
S1.31
Clarify how the loads from the roof top units are to be supported by
the open web roof joists. For instance, the 28K10 joists over the
cafetorium are just adequate for standard roof loads. The HRV
weight is only 3480 lb., not 6000 lbs while the EC4 is 1360 lbs. The
point loads to the joists need to be defined. It is common practice to
increase the point loads somewhat since the load is not uniformly
distributed.
22
S1.32
The tops of the columns must be braced. Many of the columns are
positively braced by perpendicular framing in one direction only.
23
S2.11
CDN#2409A-089
Comment
Number
Sheet
Number
Comment
24
S2.11 &
S2.12
The centerline of the braces does not align with mid-height of the
beams but instead aligns with either the top or bottom flange. This
connection geometry creates bending in the beams due to lateral
forces. Confirm that all members are still adequate based on the
actual eccentricities of these connections.
25
S2.14
The east wall of the east CMU core jogs at 2nd floor from about grid
9.7 to about grid 9.5. Confirm lateral forces in this wall can transfer
with this jog.
26
S5.11
27
S5.11
Detail 13 the two tall sections of wall on the south side of the
building, shown in elevation 3/S2.14, seem to have a combination of
systems that are not very compatible. The 8 cmu is identified as a
veneer, which implies ties back to the metal stud and steel girt and
column backup. In this assembly it would be expected that the
backup system would take the wind loads, but the masonry is likely
much stiffer than the backup. This will concentrate load transfer at
the stiffest point between the two systems and potentially fail the
veneer ties.
28
S5.11
29
S5.12
30
S5.12
CDN#2409A-089
Comment
Number
Sheet
Number
Comment
31
S5.12
Detail 12 there is a bent plate from the channel to the roof deck. If
this is a diaphragm connection it should be specified that the deck is
welded to this plate. Continuous weld is shown from the bent plate
to the channel. An intermittent weld should be sufficient.
32
S5.12
33
S5.13
34
S5.13
35
S5.13
Detail 7 the weld of the brick support angle to the stud is shown as
a 3/16 fillet weld top and bottom of the angle. This size weld cannot
be achieved with a 16 gage stud, and the capacity of this connection
is pretty limited. It appears that about 10 to 12 feet of brick is
supported on this angle. Perhaps HSS or channel sections should
be used in the stud space for brick support. The capacity of this
connection should be carefully reviewed.
36
S5.13
37
S5.13
Detail 19 does the deck have the capacity to support the brick? If
not spacer bars should be added in the flutes with a plate or angle
over top of the spacers to support the brick directly to the beam
below.
38
S5.14
CDN#2409A-089
Comment
Number
Sheet
Number
Comment
39
S5.14
Detail 12 the tube cantilevered off the top of the beam will
potentially twist the top flange and bend the web of the beam.
Stiffeners should be added in the beam.
40
S5.14
41
S5.14
42
S5.14
43
S5.15
Detail 6 design forces for the joists due to the roof screen are not
listed. A horizontal member across the top chords of the joists is
probably required to resolve the forces.
44
S5.15
Details 6 and 7 the vertical load from the roof screen should be
provided as a joist design load
45
S5.15
Detail 10 this detail refers to loose lintels but both the structural
and architectural sections show the roof interrupting the veneer.
The brick above the roof, which is quite tall, must have structural
support.
46
S5.15
47
S5.15
CDN#2409A-089
Comment
Number
Sheet
Number
Comment
48
Calcs
Page 41 shows a map of the roof that includes brace loads. Confirm
the lateral load distribution is consistent with diaphragm stiffness.
Our copy is only in black and white so the notes on the top of the
page indicating that red loads are from the roof while green loads
are from 2nd floor are difficult to discern. It appears that wind loads
were distributed based on a flexible diaphragm which is appropriate
for the roof only. The second floor should be considered a rigid
diaphragm and the lateral loads should be distributed based on
stiffness. The CMU cores will be significantly stiffer than the steel
bracing. This will result in these CMU walls resisting a greater
amount of lateral load and could result in some of the braced frames
dumping load into the 2nd floor diaphragm.
49
Calcs
SECTION7
SupplementalInformation
TheMemorandumofUnderstanding(MOA),asprovidedinSection3,includesreferencestocomment
#17andcomment#20thatweretobeaddressedwithVulcraft.Thissectionincludesdocumentationto
confirmthattheseitemswereresolvedwithVulcraft.
James Ohlson
Job Captain
Enc.
James Ohlson
From:
Sent:
To:
Cc:
Subject:
James,
The top chord extensions are acceptable with the support provided by the revised detail. That should close item #20.
The additional joist that is required due to the new drift load (item #17) is in process. We will notify you when it is to be
delivered. That will close item #17.
If you have any additional items, please let us know.
Thanks,
Maryann
With the TCX being considered supported, those joists can support the added drift loads.
Doug Dominisse
From: Maryann Davis
Sent: Tuesday, November 29, 2011 5:24 PM
To: Doug Dominisse; Dave Henley
Subject: FW: Akron#Structural Review item #20. 055#11#0337
As promised.
Maryann
Maryann,
Attached you will find the structural calculations for the snow drift at grid line D. If you need any additional information
please feel free to give me a call.
1
Best regards,
JAMES ohlson, Assoc. AIA
Design
THE NEENAN COMPANY
2620 E. Prospect Road, Suite 100 | Fort Collins, CO 80525
P: 970.416.7277 | C: 303.990.4631 | james.ohlson@neenan.com
Visit us on the web:
www.neenan.com | Blog | Twitter | Facebook | Flickr | YouTube
CONFIDENTIALITY NOTICE
This e-mail contains privileged and confidential information which is the
property of Nucor, intended only for the use of the intended recipient(s).
Unauthorized use or disclosure of this information is prohibited. If you
are not an intended recipient, please immediately notify Nucor and destroy
any copies of this email. Receipt of this e-mail shall not be deemed a
waiver by Nucor of any privilege or the confidential nature of the information.