DRAINAGE DESIGN

THAT MAKES SENSE

August 25, 2016


4 p.m.

DRAINAGE INITIATIVE
UPDATE
Calcasieu Parish Police Jury
Drainage Committee Meeting

OVERVIEW
Proposed Policy Framework
How It Works: Proposed Drainage
Management & Enforcement Structure
Proposed Capital Improvements Program
Proposed Funding Sources
Calcasieu Drainage Coalition
Timeline & Next Steps
DRAINAGE DESIGN THAT MAKES SENSE

PARISHWIDE DRAINAGE MANAGEMENT


Calcasieu Drainage Coalition

Policies and Ordinances

DEVELOPMENT

Drainage standards for


development parish and cities
should be similar

ENFORCEMENT
Appropriate departments at
Police Jury and cities; GDDs

DRAINAGE DESIGN THAT MAKES SENSE

Capital Improvement
Program (CIP)

Police Jury takes lead role,


solicits input from cities and
drainage districts prior to
program development

Functions as a three-year
revolving program updated
annually utilizing sound criteria
for prioritization

PROPOSED POLICY FRAMEWORK

DRAINAGE DESIGN THAT MAKES SENSE

PROPOSED DRAINAGE DESIGN &


CONSTRUCTION CRITERIA
All new development activity must meet or
exceed the following:
Maintain or lower existing water surface elevation
profiles entering and exiting new developments

Protect and enhance flood storage volumes within


the established 100-year floodplain
All new structures to follow minimum freeboard
requirements
DRAINAGE DESIGN THAT MAKES SENSE

MAINTAIN OR LOWER EXISTING WATER SURFACE ELEVATION


PROFILES ENTERING AND EXITING NEW DEVELOPMENTS
Sample Detention Pond Design Comparison v. Full Spectrum Design Approach
Pre-Dev Post-Dev

Post
Detention

Runoff
Increase

Full Spectrum 25 Year Protection

Storm

Q (cfs)

Q (cfs)

Q (cfs)

2yr

76

187

103

35%

0% increase

5yr

123

257

134

8%

0% increase

10yr

161

310

161

0%

0% increase

25yr

214

384

287

34%

0% increase

50yr

258

445

393

52%

< 52%

100yr

303

506

506

67%

< 67%

DRAINAGE DESIGN THAT MAKES SENSE

PROTECT AND ENHANCE FLOOD STORAGE VOLUMES


WITHIN THE ESTABLISHED 100-YEAR FLOODPLAIN
Fill Required For
New Development

Fill Mitigation
Excavated Area

DRAINAGE DESIGN THAT MAKES SENSE

ALL NEW DEVELOPMENT IN FLOODWAYS TO MEET


NO-RISE CERTIFICATION REQUIREMENTS

DRAINAGE DESIGN THAT MAKES SENSE

HOW IT WORKS: PROPOSED DRAINAGE


MANAGEMENT & ENFORCMENT
STRUCTURE
DRAINAGE DESIGN THAT MAKES SENSE

DRAINAGE MANAGEMENT AND ENFORCEMENT


FUNCTIONS & RESPONSIBILITIES
Function

Currently Responsible

Create policies and


ordinances for development

Police Jury
Cities

Police Jury, cities, and GDD


policies and ordinances should be
similar

Enforce policies and


ordinances for development

Police Jury
Cities

Police Jury Permitting Dept.


City Permitting Depts.

Administer parishwide
Capital Improvement
Program

N/A

Police Jury Drainage Section


Cities and GDDs continue
overseeing small watershed
lateral projects

GDDs

GDDs

Drainage lateral maintenance

Proposed Responsibility

Street drainage projects


and maintenance

Police Jury
Cities

Police Jury
Cities

Clean water stormwater


enforcement (water quality)

Police Jury
Cities

Police Jury
Cities

DRAINAGE DESIGN THAT MAKES SENSE

10

PROPOSED CAPITAL
IMPROVEMENTS PROGRAM (CIP)
DRAINAGE DESIGN THAT MAKES SENSE

11

CAPITAL IMPROVEMENTS PROGRAM


Development and maintenance of program
Police Jury takes lead role, solicits comprehensive
input from cities and drainage districts prior to CIP
development

Utilizes sound criteria for prioritization


(ensures allocations to smaller areas)
Program would be a three-year revolving
program, updated annually
DRAINAGE DESIGN THAT MAKES SENSE

12

PUBLIC FEEDBACK: PROJECT NEEDS

DRAINAGE DESIGN THAT MAKES SENSE

13

PROJECTS TO BE CONSIDERED ON A
WATERSHED BASIS
City of Sulphur

W-3
W-36

DRAINAGE DESIGN THAT MAKES SENSE

14

CRITERIA FOR PRIORITIZATION

Water course types


Flow reduction project
Impervious area reduction project
Flood zone reduction project
Existing right-of-way
Number of citizens impacted directly
Structures directly impacted
Flow (Q) cubic feet-per-second
Benefit-cost analysis (based on structure)
Matching funds

DRAINAGE DESIGN THAT MAKES SENSE

15

PROPOSED FUNDING SOURCES FOR


DRAINAGE MANAGEMENT AND
CAPITAL PROJECTS
DRAINAGE DESIGN THAT MAKES SENSE

16

FUNDING SOURCES
Portion of existing Police Jury Road & Drainage Property Tax
Portion of Gravity Drainage District property taxes (as local match
dollars to fund projects in those specific areas)
State and federal grants that may become available
Initiate drainage impact fee on unmitigated new development and
re-development
Utilize a fee rate using dollars/cents per square foot of impervious
surface
Permitting departments would collect fees as part of development
permit process
Impact fee revenues would be used for regional detention and major
capital projects

DRAINAGE DESIGN THAT MAKES SENSE

17

CALCASIEU DRAINAGE COALITION

DRAINAGE DESIGN THAT MAKES SENSE

18

PARISHWIDE DRAINAGE MANAGEMENT


Calcasieu Drainage Coalition

Policies and Ordinances

DEVELOPMENT

Drainage standards for


development parish and cities
should be similar

ENFORCEMENT
Appropriate departments at
Police Jury and cities; GDDs

DRAINAGE DESIGN THAT MAKES SENSE

Capital Improvement
Program (CIP)

Police Jury takes lead role,


solicits input from cities and
drainage districts prior to
program development

Functions as a three-year
revolving program updated
annually utilizing sound criteria
for prioritization

19

CALCASIEU DRAINAGE COALITION


Serves a key role in consistent enforcement of
polices and ordinances for development (the
glue)
Includes staff representatives from parish,
cities, and Gravity Drainage Districts
Examples: public works directors, planners,
superintendents, engineers, DOTD, and others as
needed

DRAINAGE DESIGN THAT MAKES SENSE

20

CALCASIEU DRAINAGE COALITION


Enforcement and accountability
Shorter Term: Meet frequently in short term to
transition from policies to ordinances; as-needed
afterward
Longer Term: Meet quarterly to discuss capital
improvement programming and coordinate
policy/ordinance enforcement
Following disasters and emergencies (including
major rain events), coalition will meet to reassess
project needs and other necessary changes
DRAINAGE DESIGN THAT MAKES SENSE

21

TIMELINE & NEXT STEPS

DRAINAGE DESIGN THAT MAKES SENSE

22

STAKEHOLDER AND PUBLIC INPUT


Date

Key Activity

June 2

Drainage Committee Meeting

June 13-20

Stakeholder Focus Group Meetings

August 16

Meeting with Cities and


Gravity Drainage Districts

August 25

Drainage Committee Meeting

August 25
September 16

Public Comment Period

October 11

Drainage Committee Meeting

October 20

Police Jury Meeting

DRAINAGE DESIGN THAT MAKES SENSE

23

PUBLIC COMMENT PERIOD


Online

http://cppj.citizenreach.com

Contact the Parish Administrators Office:

Phone

Mail

(337) 721-3510
CPPJ Drainage Design Planning Team
1011 Lakeshore Drive, Ste. 614, Lake Charles, LA 70601

DRAINAGE DESIGN THAT MAKES SENSE

24

NEXT STEPS
Receive public and stakeholder comments on
draft policy framework, proposed drainage
management and enforcement structure,
proposed Capital Improvements Program
prioritization criteria and high-level funding
structure

Recommendations to be presented at the next


Drainage Committee meeting
DRAINAGE DESIGN THAT MAKES SENSE

25

QUESTIONS?

DRAINAGE DESIGN THAT MAKES SENSE

26