You are on page 1of 63

BIL

Project Title :

Jetty 19
Owner :
Location :

No.

Work Description

Unit

Q'ty

1
2
3

PREPARATION WORK
Mob & Demobilization
Site Clearing & Facility
Survey

ls
ls
ls

1
2
3
4
5
6

EARTH WORK
Excavation ( dredging )
Excavation
Back Fill
Disposal
Rubble Stone
Filter Cloth ( Geotextile )

m3
m3
m3
m3
m3
m2

67,795.00
2,184.00
1,310.00
68,668.60
6,556.00
5,244.80

1
2
3
4
5
6

PILING WORK
Spun Pile driving ( off shore )
Spun Pile driving ( on shore )
Jointing ( off shore )
Jointing ( on shore )
Cut off dispose
PDA Test

m
m
point
point
point
point

11,293.00
1,035.00
491.00
45.00
536.00
3.00

1
2

CONSTRUCTION
PRECAST BEAM
Form Work Expose ( on shore )
Rebar

m2
kg

8,154.69
307,288.85

Concrete K-300 ( Early Setting)

m3

1,853.66

Erection Precast Beam

unit

846.00

1
2

PRECAST SLAB
Form Work Expose ( on shore)
Rebar

m2
kg

6,153.04
332,392.23

II

III

IV
A

1.00
1.00
1.00

Concrete K-300 ( Early Setting )

m3

1,256.98

Erection Precast Slab

unit

391.00

1
2
3
4
5
6

CAST INSITU
Form Work Expose ( off shore)
Form Work Expose ( on shore)
Form Work Unexpose ( on shore )
Rebar
Concrete K-300 ( off shore )
Concrete K-300 ( on shore )

m2
m2
m2
kg
m3
m3

7,580.62
657.97
2,087.00
1,182,627.30
4,306.84
559.87

Lean Concrete K-125 ( on shore )

m3

32.90

8
9
10
11
12
13
14

Epoxy Rexin Grout


Coating Floor
Steel Trowel Finish Floor
Curing Compounds
PVC Pipe Drainage dia 3"-500
Drainage Cover (Grating)
Install ex. Cutting Spun Pile

m2
m2
m2
m2
pc
set
set

119.49
79.20
7,965.69
7,965.69
90.00
31.00
556.00

1
2
3
4
5
6

STEEL FENDER
PILING WORK
Offshore Pile Driving
Jointing ( off shore )
Steel Profile H-Beam
Sand Blasting
Epoxy Paint 1
Epoxy Paint 2

Epoxy Paint 3

m2

1,062.60

1
2
3
4

STEEL WORK
Steel Structure
Sand Blasting
Epoxy Paint 1
Epoxy Paint 2

kg
m2
m2
m2

176,083.43
2,464.08
2,464.08
2,464.08

Epoxy Paint 3

m2

2,464.08

6
7
8
9
10
11
12
13

Cell Fender
KRFC Fender
Galvanized Anchor Bolt 1
Galvanized Anchor Bolt 2
Galvanized Anchor Bolt 3
Ex. Tyre Installation
Clam and Chain or Wire Sling 12 mm
Rail + Completed

unit
unit
pc
pc
pc
m
set
m

46.00
43.00
276.00
525.00
146.00
552.00
552.00
396.00

V
A

m
point
kg
m2
m2
m2

1,104.00
46.00
151,248.00
1,062.60
1,062.60
1,062.60

14

Cable Pipe

198.00

VI
1
2
3
4

CONCRETE ROAD
Survey
Excavation
Disposal
Compaction ( Soil )

m2
m3
m3
m2

2,704.00
540.80
540.80
2,704.00

Fill Base Coarse

m3

780.00

6
7

Plastic Layer
Form Work Unexpose

m2
m2

2,496.00
166.00

BRC M8

kg

14,832.00

Rebar

kg

51,726.40

10

Concrete K-300 (sB) ( Normal )

m3

624.00

11
12
13

Steel Trowel Finish Floor 1


Curing Compounds
Fill Base Coarse

m2
m2
m3

2,496.00
2,496.00
780.00

1
2

OTHER
Indirect Cost
CAR Insurance

VII

ls
ls
TOTAL
ROUNDED

1.00
1.00

BILL OF QUANTITY
Jetty 198 M Project at Rasau Kuning

Unit Price ( IDR) )


Wage

Price ( IDR )
Material

925,500,000.00
5,000,000,000.00
130,500,000.00

67,500.00
37,500.00
27,500.00
32,000.00
212,000.00
12,200.00

445,000.00
445,000.00
414,000.00
473,570.00
217,485.60
28,000,000.00

Wage

6,056,000,000.00
925,500,000.00
5,000,000,000.00
130,500,000.00

665,000.00
48,000.00

8,345,341,260.00
4,576,162,500.00
81,900,000.00
36,025,000.00
2,197,395,200.00
1,389,872,000.00
63,986,560.00

800,000.00
800,000.00
633,000.00
376,430.00
230,280.00
-

5,911,116,931.60
5,025,385,000.00
460,575,000.00
203,274,000.00
21,310,650.00
116,572,281.60
84,000,000.00
17,438,803,777.85

100,320.00
6,060.00

268,320.00
11,140.00

818,078,500.80
1,862,170,431.00

254,400.00

1,303,470.00

471,571,104.00

1,918,820.50

1,623,322,143.00

10,320.00
6,060.00

268,320.00
11,140.00

63,499,372.80
2,014,296,913.80

254,400.00

1,303,470.00

319,775,712.00

1,918,820.50

750,258,815.50

14,540.00
10,320.00
12,321.00
6,060.00
451,400.00
254,400.00

298,643.00
268,320.00
268,320.00
11,140.00
1,303,470.00
1,303,470.00

110,222,214.80
6,790,250.40
25,713,927.00
7,166,721,438.00
1,944,107,576.00
142,430,928.00

190,800.00

511,350.00

6,277,320.00

65,725.00
83,250.00

245,000.00
183,240.00
175,000.00
510,000.00
1,768,000.00

7,853,480.25
6,593,400.00
0.00
91,207,150.50
5,671,800.00
2,241,300.00
0.00

11,450.00
63,020.00
72,300.00

10,330,421,523.48
874,800.00
414,000.00
5,736.00
175,600.00
405,000.00
405,000.00

236,400.00
633,000.00
24,235.20
216,000.00
216,000.00

965,779,200.00
19,044,000.00
867,558,528.00
186,592,560.00
430,353,000.00
430,353,000.00

405,000.00

216,000.00

430,353,000.00

5,736.00
175,600.00
405,000.00
405,000.00

24,235.20
216,000.00
216,000.00

1,010,014,554.48
432,692,448.00
997,952,400.00
997,952,400.00

405,000.00

216,000.00

997,952,400.00

32,450,000.00
23,450,000.00
1,243.00
1,143.00
1,705.00

172,456,000.00
52,345,000.00
16,400.00
15,750.00
21,230.00

124,000.00

645,000.00

1,492,700,000.00
1,008,350,000.00
343,068.00
600,075.00
248,930.00
0.00
0.00
49,104,000.00

63,020.00

350,000.00

12,477,960.00

15,000.00
37,500.00
32,000.00
42,300.00

1,182,264,382.00
40,560,000.00
20,280,000.00
17,305,600.00
114,379,200.00

246,797.00

146,436.00

192,501,660.00

1,200.00
12,321.00

8,000.00
268,320.00

2,995,200.00
2,045,286.00

2,756.00

7,500.00

40,876,992.00

6,060.00

11,140.00

313,461,984.00

254,400.00

1,303,470.00

158,745,600.00

23,250.00
11,450.00
246,797.00

175,000.00
146,436.00

58,032,000.00
28,579,200.00
192,501,660.00

22,778,262,746.39
16,450,967,539.06
6,327,295,207.33
72,042,210,621.32

16,450,967,539.06
6,327,295,207.33

Price ( IDR )
Material

Sub Total
6,056,000,000.00

4,611,490,400.00
4,359,740,000.00
251,750,400.00

12,956,831,660.00

10,313,572,430.00
9,034,400,000.00
828,000,000.00
310,803,000.00
16,939,350.00
123,430,080.00
-

16,224,689,361.60

39,093,546,143.36

56,532,349,921.21

2,188,066,420.80
3,423,197,789.00
2,416,190,200.20
-

1,650,983,692.80
3,702,849,442.20

1,638,435,720.60
-

2,263,899,098.66
176,546,510.40
559,983,840.00
13,174,468,122.00
5,613,836,734.80
729,773,748.90
16,823,415.00
29,275,050.00
14,512,608.00
1,393,995,750.00
45,900,000.00
54,808,000.00
0.00
21,032,760,642.34
260,985,600.00
29,118,000.00
3,665,525,529.60
229,521,600.00
229,521,600.00
229,521,600.00
4,267,417,142.74
532,241,280.00
532,241,280.00
532,241,280.00
7,932,976,000.00
2,250,835,000.00
4,526,400.00
8,268,750.00
3,099,580.00
0.00
0.00
255,420,000.00

31,363,182,165.82

69,300,000.00

2,230,586,656.00

3,412,851,038.00

114,220,080.00
19,968,000.00
44,541,120.00
111,240,000.00
576,232,096.00
813,365,280.00
436,800,000.00
114,220,080.00
0

22,778,262,746.39

77,281,956,271.70

149,324,166,893.02
157,089,600,000.00

Date :
Revision :

Remark

Incl. Heavy Equipmnet


All by Contractor
Incl. Constr, Survey, and Sonding

for off shore by clamp cheel


for on shore
select good soil
max. 7 km ( at landfill )
Good Stone dia 500mm @ 50 kg
Polyelth TS-500,

Spun pile dia 600mm Type C (15 + 8)


Spun pile dia 600mm Type C (15 + 8)
for spun pile
for spun pile
for spun pile
3 x arrival

Used plywood 9mm, incl. frame


deform bar, U32, SNI
Lowerst Structure (Composition with trength) incl. waste
All eqp. By contractor

Used plywood 9mm, incl. frame


deform bar, U32, SNI

Lowerst Structure (Composition with strength) incl. waste


All eqp. By contractor

Used plywood 9mm, incl. frame


Used plywood 9mm, incl. frame
Used plywood 9mm, incl. frame
deform bar, U32, SNI
for cast insitu
for precast, road, retaining wall
lowerst Structure (Composition normally) incl. waste, slump
12mm
for base plate crane rail ( heavy duty )
for cable line ( t= 400 mc )
use floor hardener
by Antisol S
for floor
( 900x2000x130)
for floor

Steel Profile H-Beam


Steel Profile H-Beam
SS41
for new material
Primer 1 Layer 100 Micron
Intermediate 1 Layer 100 Micron
Top Coat Asphaltic Polyurethane, 1 Layer 50 Micron
Fabrication + Installation, SS41
for new material
Primer 1 Layer 100 Micron
Intermediate 1 Layer 100 Micron
Top Coat Asphaltic Polyurethane, 1 Layer 50 Micron
Type KCEF 800
Type 200 x 200 x 1300mm
25mm x 900mm + 2 nuts
24mm x 350mm + 2 nuts
dia 32-1000
dia 1000mm
for tyre
Rail CR.73, incl. anchor bolt

sgp pipe dia 2.5"

skilled surveyor
for total exc. Is more than 25 m3
per layer, by slumper
wage, each t=30 cm (total = 60 cm), must be compacted,
material & transportation by contractor
Polyurithene
Used plywood 4 mm, incl. frame
2,1 x 5,4 M @61,79 kg (Base on bar bending schedule incl.
waste material)
> 6m, incl. wire rope
Lowerst Structure ( all by Contractor incl. vibrator, curing &
delivery)
exclude floor hardener ( use machine trowel)
use standard product like Antisol
wage t= 30 cm and compacted

BIL
Project Title :

Jetty 19
Owner :
Location :

No.

Work Description

Unit

Q'ty

1
2
3

PREPARATION WORK
Mob & Demobilization
Site Clearing & Facility
Survey

ls
ls
ls

1
2
3
4
5
6

EARTH WORK
Excavation ( dredging )
Excavation
Back Fill
Disposal
Rubble Stone
Filter Cloth ( Geotextile )

m3
m3
m3
m3
m3
m2

67,795.00
2,184.00
1,310.00
68,668.60
6,556.00
5,244.80

1
2
3
4
5
6

PILING WORK
Spun Pile driving ( off shore )
Spun Pile driving ( on shore )
Jointing ( off shore )
Jointing ( on shore )
Cut off dispose
PDA Test

m
m
point
point
point
point

11,293.00
1,035.00
491.00
45.00
536.00
3.00

1
2

CONSTRUCTION
PRECAST BEAM
Form Work Expose ( on shore )
Rebar

m2
kg

8,154.69
307,288.85

Concrete K-300 ( Early Setting)

m3

1,853.66

Erection Precast Beam

unit

846.00

1
2

PRECAST SLAB
Form Work Expose ( on shore)
Rebar

m2
kg

6,153.04
332,392.23

II

III

IV
A

1.00
1.00
1.00

Concrete K-300 ( Early Setting )

m3

1,256.98

Erection Precast Slab

unit

391.00

1
2
3
4
5
6

CAST INSITU
Form Work Expose ( off shore)
Form Work Expose ( on shore)
Form Work Unexpose ( on shore )
Rebar
Concrete K-300 ( off shore )
Concrete K-300 ( on shore )

m2
m2
m2
kg
m3
m3

7,580.62
657.97
2,087.00
1,182,627.30
4,306.84
559.87

Lean Concrete K-125 ( on shore )

m3

32.90

8
9
10
11
12
13
14

Epoxy Rexin Grout


Coating Floor
Steel Trowel Finish Floor
Curing Compounds
PVC Pipe Drainage dia 3"-500
Drainage Cover (Grating)
Install ex. Cutting Spun Pile

m2
m2
m2
m2
pc
set
set

119.49
79.20
7,965.69
7,965.69
90.00
31.00
556.00

1
2
3
4
5
6

STEEL FENDER
PILING WORK
Offshore Pile Driving
Jointing ( off shore )
Steel Profile H-Beam
Sand Blasting
Epoxy Paint 1
Epoxy Paint 2

Epoxy Paint 3

m2

1,062.60

1
2
3
4

STEEL WORK
Steel Structure
Sand Blasting
Epoxy Paint 1
Epoxy Paint 2

kg
m2
m2
m2

176,083.43
2,464.08
2,464.08
2,464.08

Epoxy Paint 3

m2

2,464.08

6
7
8
9
10
11
12
13

Cell Fender
KRFC Fender
Galvanized Anchor Bolt 1
Galvanized Anchor Bolt 2
Galvanized Anchor Bolt 3
Ex. Tyre Installation
Clam and Chain or Wire Sling 12 mm
Rail + Completed

unit
unit
pc
pc
pc
m
set
m

46.00
43.00
276.00
525.00
146.00
552.00
552.00
396.00

V
A

m
point
kg
m2
m2
m2

1,104.00
46.00
151,248.00
1,062.60
1,062.60
1,062.60

14

Cable Pipe

198.00

VI
1
2
3
4

CONCRETE ROAD
Survey
Excavation
Disposal
Compaction ( Soil )

m2
m3
m3
m2

2,704.00
540.80
540.80
2,704.00

Fill Base Coarse

m3

780.00

6
7

Plastic Layer
Form Work Unexpose

m2
m2

2,496.00
166.00

BRC M8

kg

14,832.00

Rebar

kg

51,726.40

10

Concrete K-300 (sB) ( Normal )

m3

624.00

11
12
13

Steel Trowel Finish Floor 1


Curing Compounds
Fill Base Coarse

m2
m2
m3

2,496.00
2,496.00
780.00

VII

OTHER
1

Indirect Cost

ls

1.00

CAR Insurance

ls

1.00

TOTAL
ROUNDED

BILL OF QUANTITY
Jetty 198 M Project at Rasau Kuning

Unit Price ( IDR) )


Wage

Price ( IDR )
Material

925,500,000.00
5,000,000,000.00
130,500,000.00

67,500.00
37,500.00
27,500.00
32,000.00
181,500.00
12,200.00

325,450.00
325,450.00
124,125.00
124,125.00
423,404.00
26,500,000.00

Wage

6,056,000,000.00
925,500,000.00
5,000,000,000.00
130,500,000.00

423,500.00
48,000.00

8,145,383,260.00
4,576,162,500.00
81,900,000.00
36,025,000.00
2,197,395,200.00
1,189,914,000.00
63,986,560.00

775,623.00
775,623.00
289,625.00
289,625.00
-

4,385,123,144.00
3,675,306,850.00
336,840,750.00
60,945,375.00
5,585,625.00
226,944,544.00
79,500,000.00
18,026,085,206.41

65,423.00
6,060.00

97,220.00
11,140.00

533,504,283.87
1,862,170,431.00

254,400.00

1,303,470.00

471,571,104.00

1,918,820.50

1,623,322,143.00

65,423.00
6,060.00

97,220.00
11,140.00

402,550,335.92
2,014,296,913.80

254,400.00

1,303,470.00

319,775,712.00

1,918,820.50

750,258,815.50

65,423.00
65,423.00
65,423.00
6,060.00
451,400.00
254,400.00

97,220.00
97,220.00
97,220.00
11,140.00
1,303,470.00
1,303,470.00

495,946,902.26
43,046,371.31
136,537,801.00
7,166,721,438.00
1,944,107,576.00
142,430,928.00

190,800.00

511,350.00

6,277,320.00

65,725.00
83,250.00

245,000.00
183,240.00
175,000.00
510,000.00
1,768,000.00
-

7,853,480.25
6,593,400.00
0.00
91,207,150.50
5,671,800.00
2,241,300.00
0.00

11,450.00
63,020.00
72,300.00

5,864,248,045.24
325,540.00
124,125.00
5,736.00
115,430.00
405,000.00
405,000.00

289,625.00
14,235.20
216,000.00
216,000.00

359,396,160.00
5,709,750.00
867,558,528.00
122,655,918.00
430,353,000.00
430,353,000.00

405,000.00

216,000.00

430,353,000.00

5,736.00
115,430.00
73,164.00
73,164.00

14,235.20
48,776.00
48,776.00

1,010,014,554.48
284,428,754.40
180,281,949.12
180,281,949.12

73,164.00

48,776.00

180,281,949.12

16,750,000.00
11,243,500.00
1,243.00
1,143.00
1,705.00

164,750,000.00
52,345,000.00
16,400.00
15,750.00
21,230.00

290,250.00

354,750.00

770,500,000.00
483,470,500.00
343,068.00
600,075.00
248,930.00
0.00
0.00
114,939,000.00

63,020.00

245,000.00

12,477,960.00

15,000.00
37,500.00
32,000.00
42,300.00

1,191,079,314.00
40,560,000.00
20,280,000.00
17,305,600.00
114,379,200.00

246,797.00

146,436.00

192,501,660.00

1,200.00
65,423.00

8,000.00
97,220.00

2,995,200.00
10,860,218.00

2,756.00

7,500.00

40,876,992.00

6,060.00

11,140.00

313,461,984.00

254,400.00

1,303,470.00

158,745,600.00

23,250.00
11,450.00
246,797.00

175,000.00
146,436.00

58,032,000.00
28,579,200.00
192,501,660.00
15,262,892,017.99

11,992,272,299.85

11,992,272,299.85

3,270,619,718.14

3,270,619,718.14
58,930,810,987.64

Price ( IDR )
Material

Sub Total
6,056,000,000.00
-

3,028,216,400.00
2,776,466,000.00
251,750,400.00

11,173,599,660.00

9,717,119,344.00
8,759,110,539.00
802,769,805.00
142,205,875.00
13,033,125.00
-

14,102,242,488.00

34,648,917,951.10

52,675,003,157.51

792,798,961.80
3,423,197,789.00

4,300,000.00

2,416,190,200.20

5,857,870.00

598,198,548.80
3,702,849,442.20

1,638,435,720.60
-

736,987,876.40
63,967,843.40
202,898,140.00
13,174,468,122.00
5,613,836,734.80
729,773,748.90
16,823,415.00
29,275,050.00
14,512,608.00
1,393,995,750.00
45,900,000.00
54,808,000.00
15,756,300,550.58
13,322,750.00
2,153,045,529.60
229,521,600.00
229,521,600.00
229,521,600.00
2,506,582,842.74
120,187,966.08
120,187,966.08
120,187,966.08
7,578,500,000.00
2,250,835,000.00
4,526,400.00
8,268,750.00
3,099,580.00
0.00
0.00
140,481,000.00

21,620,548,595.82

48,510,000.00

2,202,184,056.00

3,393,263,370.00

114,220,080.00
19,968,000.00
16,138,520.00
111,240,000.00
576,232,096.00
813,365,280.00
436,800,000.00
114,220,080.00
0

15,262,892,017.99

65,352,738,301.68

124,283,549,289.31

Date :
Revision :

Remark

Incl. Heavy Equipmnet


All by Contractor
Incl. Constr, Survey, and Sonding

for off shore by clamp cheel


for on shore
select good soil
max. 7 km ( at landfill )
Good Stone dia 500mm @ 50 kg
Polyelth TS-500,

Spun pile dia 600mm Type C (15 + 8)


Spun pile dia 600mm Type C (15 + 8)
for spun pile
for spun pile
for spun pile
3 x arrival

Used plywood 9mm, incl. frame


deform bar, U32, SNI
Lowerst Structure (Composition with trength) incl. waste
All eqp. By contractor

Used plywood 9mm, incl. frame


deform bar, U32, SNI

Lowerst Structure (Composition with strength) incl. waste


All eqp. By contractor

Used plywood 9mm, incl. frame


Used plywood 9mm, incl. frame
Used plywood 9mm, incl. frame
deform bar, U32, SNI
for cast insitu
for precast, road, retaining wall
lowerst Structure (Composition normally) incl. waste, slump
12mm
for base plate crane rail ( heavy duty )
for cable line ( t= 400 mc )
use floor hardener
by Antisol S
for floor
( 900x2000x130)
for floor

Steel Profile H-Beam


Steel Profile H-Beam
SS41
for new material
Primer 1 Layer 100 Micron
Intermediate 1 Layer 100 Micron
Top Coat Asphaltic Polyurethane, 1 Layer 50 Micron
Fabrication + Installation, SS41
for new material
Primer 1 Layer 100 Micron
Intermediate 1 Layer 100 Micron
Top Coat Asphaltic Polyurethane, 1 Layer 50 Micron
Type KCEF 800
Type 200 x 200 x 1300mm
25mm x 900mm + 2 nuts
24mm x 350mm + 2 nuts
dia 32-1000
dia 1000mm
for tyre
Rail CR.73, incl. anchor bolt

sgp pipe dia 2.5"

skilled surveyor
for total exc. Is more than 25 m3
per layer, by slumper
wage, each t=30 cm (total = 60 cm), must be compacted,
material & transportation by contractor
Polyurithene
Used plywood 4 mm, incl. frame
2,1 x 5,4 M @61,79 kg (Base on bar bending schedule incl.
waste material)
> 6m, incl. wire rope
Lowerst Structure ( all by Contractor incl. vibrator, curing &
delivery)
exclude floor hardener ( use machine trowel)
use standard product like Antisol
wage t= 30 cm and compacted

Overhead (5%), Profit (3%), HSE (1%), Contigency (2%)


3% from total project cost

BIL
Project Title :

Jetty 19
Owner :
Location :

No.

Work Description

Unit

Q'ty

1
2
3

PREPARATION WORK
Mob & Demobilization
Site Clearing & Facility
Survey

ls
ls
ls

1
2
3
4
5
6

EARTH WORK
Excavation ( dredging )
Excavation
Back Fill
Disposal
Rubble Stone
Filter Cloth ( Geotextile )

m3
m3
m3
m3
m3
m2

51,120.05
1,082.76
1,280.00
69,020.00
5,032.71
4,063.36

1
2
3
4
5
6

PILING WORK
Spun Pile driving ( off shore )
Spun Pile driving ( on shore )
Jointing ( off shore )
Jointing ( on shore )
Cut off dispose
PDA Test

m
m
point
point
point
point

11,293.00
1,035.00
492.00
45.00
536.00
3.00

1
2

CONSTRUCTION
PRECAST BEAM
Form Work Expose ( on shore )
Rebar

m2
kg

12,823.14
306,627.00

Concrete K-300 ( Early Setting)

m3

1,741.21

Erection Precast Beam

unit

846.00

1
2

PRECAST SLAB
Form Work Expose ( on shore)
Rebar

m2
kg

6,417.45
327,451.00

II

III

IV
A

1.00
1.00
1.00

Concrete K-300 ( Early Setting )

m3

1,254.83

Erection Precast Slab

unit

391.00

1
2
3
4
5
6

CAST INSITU
Form Work Expose ( off shore)
Form Work Expose ( on shore)
Form Work Unexpose ( on shore )
Rebar
Concrete K-300 ( off shore )
Concrete K-300 ( on shore )

m2
m2
m2
kg
m3
m3

7,312.54
687.23
2,223.00
1,359,018.00
4,230.00
553.00

Lean Concrete K-125 ( on shore )

m3

31.75

8
9
10
11
12
13
14

Epoxy Rexin Grout


Coating Floor
Steel Trowel Finish Floor
Curing Compounds
PVC Pipe Drainage dia 3"-500
Drainage Cover (Grating)
Install ex. Cutting Spun Pile

m2
m2
m2
m2
pc
set
set

118.75
79.20
7,965.69
7,965.69
90.00
31.00
556.00

1
2
3
4
5
6

STEEL FENDER
PILING WORK
Offshore Pile Driving
Jointing ( off shore )
Steel Profile H-Beam
Sand Blasting
Epoxy Paint 1
Epoxy Paint 2

Epoxy Paint 3

m2

1,065.00

1
2
3
4

STEEL WORK
Steel Structure
Sand Blasting
Epoxy Paint 1
Epoxy Paint 2

kg
m2
m2
m2

174,876.34
2,578.45
2,578.45
2,578.45

Epoxy Paint 3

m2

2,578.45

6
7
8
9
10
11
12
13

Cell Fender
KRFC Fender
Galvanized Anchor Bolt 1
Galvanized Anchor Bolt 2
Galvanized Anchor Bolt 3
Ex. Tyre Installation
Clam and Chain or Wire Sling 12 mm
Rail + Completed

unit
unit
pc
pc
pc
m
set
m

46.00
43.00
276.00
525.00
146.00
552.00
552.00
396.00

V
A

m
point
kg
m2
m2
m2

138.00
46.00
153,457.00
1,065.00
1,065.00
1,065.00

14

Cable Pipe

198.00

VI
1
2
3
4

CONCRETE ROAD
Survey
Excavation
Disposal
Compaction ( Soil )

m2
m3
m3
m2

2,704.00
552.54
552.54
2,653.21

Fill Base Coarse

m3

774.00

6
7

Plastic Layer
Form Work Unexpose

m2
m2

2,502.00
174.00

BRC M8

kg

14,832.00

Rebar

kg

10

Concrete K-300 (sB) ( Normal )

m3

614.00

11
12
13

Steel Trowel Finish Floor 1


Curing Compounds
Fill Base Coarse

m2
m2
m3

2,587.00
2,587.00
774.00

VII

OTHER
1

Indirect Cost

ls

1.00

CAR Insurance

ls

1.00

TOTAL
ROUNDED

BILL OF QUANTITY
Jetty 198 M Project at Rasau Kuning

Unit Price ( IDR) )


Wage

Price ( IDR )
Material

925,500,000.00
5,000,000,000.00
130,500,000.00

67,500.00
37,500.00
27,500.00
32,000.00
212,000.00
12,200.00

874,800.00
678,600.00
414,000.00
473,570.00
217,485.60
28,000,000.00

Wage

6,056,000,000.00
925,500,000.00
5,000,000,000.00
130,500,000.00

665,000.00
48,000.00

6,851,555,568.70
3,450,603,645.00
40,603,612.50
35,200,000.00
2,208,640,000.00
1,066,935,368.00
49,572,943.20

236,400.00
221,400.00
633,000.00
376,430.00
230,280.00
-

11,007,038,331.60
9,879,116,400.00
702,351,000.00
203,688,000.00
21,310,650.00
116,572,281.60
84,000,000.00
19,242,970,035.05

100,320.00
6,060.00

268,320.00
15,549.60

1,286,417,404.80
1,858,159,620.00

254,400.00

1,303,470.00

442,964,332.80

1,918,820.50

1,623,322,143.00

10,320.00
6,060.00

268,320.00
15,549.60

66,228,084.00
1,984,353,060.00

254,400.00

1,303,470.00

319,227,480.00

1,918,820.50

750,258,815.50

14,540.00
10,320.00
12,321.00
6,060.00
451,400.00
254,400.00

298,643.00
268,320.00
268,320.00
15,549.60
1,303,470.00
1,303,470.00

106,324,331.60
7,092,213.60
27,389,583.00
8,235,649,080.00
1,909,422,000.00
140,683,200.00

190,800.00

511,350.00

6,057,900.00

65,725.00
83,250.00
23,250.00
11,450.00
63,020.00
72,300.00
325,000.00

245,000.00
183,240.00
175,000.00
510,000.00
1,768,000.00

7,804,843.75
6,593,400.00
185,202,292.50
91,207,150.50
5,671,800.00
2,241,300.00
180,700,000.00
9,653,492,041.24

874,800.00
414,000.00
5,736.00
175,600.00
405,000.00
405,000.00

236,400.00
633,000.00
24,235.20
216,000.00
216,000.00

120,722,400.00
19,044,000.00
880,229,352.00
187,014,000.00
431,325,000.00
431,325,000.00

405,000.00

216,000.00

431,325,000.00

5,736.00
175,600.00
405,000.00
405,000.00

24,235.20
216,000.00
216,000.00

1,003,090,686.24
452,775,820.00
1,044,272,250.00
1,044,272,250.00

405,000.00

216,000.00

1,044,272,250.00

32,450,000.00
23,450,000.00
1,243.00
1,143.00
1,705.00

172,456,000.00
52,345,000.00
16,400.00
15,750.00
21,230.00

124,000.00

645,000.00

1,492,700,000.00
1,008,350,000.00
343,068.00
600,075.00
248,930.00
0.00
0.00
49,104,000.00

63,020.00

350,000.00

12,477,960.00

15,000.00
37,500.00
32,000.00
42,300.00

865,227,815.00
40,560,000.00
20,720,250.00
17,681,280.00
112,230,783.00

246,797.00

146,436.00

191,020,878.00

1,200.00
12,321.00

8,000.00
268,320.00

3,002,400.00
2,143,854.00

2,756.00

7,500.00

40,876,992.00

6,060.00

15,549.60

254,400.00

1,303,470.00

156,201,600.00

23,250.00
11,450.00
246,797.00

175,000.00
146,436.00

60,147,750.00
29,621,150.00
191,020,878.00

24,109,957,349.15
17,412,746,974.38

17,412,746,974.38

6,697,210,374.76

6,697,210,374.76
77,786,241,140.74

Price ( IDR )
Material

Sub Total
6,056,000,000.00

3,541,795,898.00
3,346,754,810.00
195,041,088.00

10,393,351,466.70

3,350,619,630.00
2,669,665,200.00
229,149,000.00
311,436,000.00
16,939,350.00
123,430,080.00
-

14,357,657,961.60

50,813,479,296.11

70,056,449,331.16

3,440,704,924.80
4,767,927,199.20
2,269,617,605.64
-

1,721,930,184.00
5,091,732,069.60

1,635,626,742.75
-

2,183,838,883.22
184,397,553.60
596,475,360.00
21,132,186,292.80
5,513,678,100.00
720,818,910.00
16,235,362.50
29,093,750.00
14,512,608.00
1,393,995,750.00
45,900,000.00
54,808,000.00
0.00
20,904,346,691.57
32,623,200.00
29,118,000.00
3,719,061,086.40
230,040,000.00
230,040,000.00
230,040,000.00
4,238,163,075.17
556,945,200.00
556,945,200.00
556,945,200.00
7,932,976,000.00
2,250,835,000.00
4,526,400.00
8,268,750.00
3,099,580.00
0.00
0.00
255,420,000.00

30,557,838,732.81

69,300,000.00

1,657,682,188.00

2,522,910,003.00

113,341,464.00
20,016,000.00
46,687,680.00
111,240,000.00
0.00
800,330,580.00
452,725,000.00
113,341,464.00
0

24,109,957,349.15

80,267,923,703.68

158,054,164,844.42
158,054,164,844.42

Date :
Revision :

Remark

Incl. Heavy Equipmnet


All by Contractor
Incl. Constr, Survey, and Sonding

for off shore by clamp cheel


for on shore
select good soil
max. 7 km ( at landfill )
Good Stone dia 500mm @ 50 kg
Polyelth TS-500,

Spun pile dia 600mm Type C (15 + 8)


Spun pile dia 600mm Type C (15 + 8)
for spun pile
for spun pile
for spun pile
3 x arrival

Used plywood 9mm, incl. frame


deform bar, U32, SNI
Lowerst Structure (Composition with trength) incl. waste
All eqp. By contractor

Used plywood 9mm, incl. frame


deform bar, U32, SNI

Lowerst Structure (Composition with strength) incl. waste


All eqp. By contractor

Used plywood 9mm, incl. frame


Used plywood 9mm, incl. frame
Used plywood 9mm, incl. frame
deform bar, U32, SNI
for cast insitu
for precast, road, retaining wall
lowerst Structure (Composition normally) incl. waste, slump
12mm
for base plate crane rail ( heavy duty )
for cable line ( t= 400 mc )
use floor hardener
by Antisol S
for floor
( 900x2000x130)
for floor

Steel Profile H-Beam


Steel Profile H-Beam
SS41
for new material
Primer 1 Layer 100 Micron
Intermediate 1 Layer 100 Micron
Top Coat Asphaltic Polyurethane, 1 Layer 50 Micron
Fabrication + Installation, SS41
for new material
Primer 1 Layer 100 Micron
Intermediate 1 Layer 100 Micron
Top Coat Asphaltic Polyurethane, 1 Layer 50 Micron
Type KCEF 800
Type 200 x 200 x 1300mm
25mm x 900mm + 2 nuts
24mm x 350mm + 2 nuts
dia 32-1000
dia 1000mm
for tyre
Rail CR.73, incl. anchor bolt

sgp pipe dia 2.5"

skilled surveyor
for total exc. Is more than 25 m3
per layer, by slumper
wage, each t=30 cm (total = 60 cm), must be compacted,
material & transportation by contractor
Polyurithene
Used plywood 4 mm, incl. frame
2,1 x 5,4 M @61,79 kg (Base on bar bending schedule incl.
waste material)
> 6m, incl. wire rope
Lowerst Structure ( all by Contractor incl. vibrator, curing &
delivery)
exclude floor hardener ( use machine trowel)
use standard product like Antisol
wage t= 30 cm and compacted

Overhead (5%), Profit (3%), HSE (1%), Contigency (4%)


5% from total project cost

ANALISA HARGA SATUAN PEKERJAAN

JENIS PEKERJAAN
HARGA SATUAN/LUMSUM

No

: MOBILISASI DAN DEMOBILISASI ALAT


:

URAIAN

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Crane 45 ton
Hammer Diesel + Leader
Ponton
Dump Truck
Excavator
Buldozer
Service Crane 25 ton
Genset
Compressor
Vibrator
Water Pump
Mesin Las
Theodolite
Waterpass
Concrete Mixer

bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh

JENIS PEKERJAAN
HARGA SATUAN/LUMSUM

No

: MOBILISASI DAN DEMOBILISASI


:

URAIAN
1
2
3
4
5
6
7

Mob. dan Demobilisasi


Personil
Mob. dan Demobilisasi Pemborong
Akomodasi Perjalanan
Akomodasi Selama di Site 180 hari
Sewa Mobil Ford Ranger
Messing Karyawan

JENIS PEKERJAAN
HARGA SATUAN/LUMSUM

SATUAN

SATUAN
Ret
ORG
Lot
ORG
ORG
Lot
Lot

: PEMBERSIHAN LAPANGAN
:

No

URAIAN
1
2
3
4
5

SATUAN

Mandor
Kepala Tukang
Tukang
Pembantu Tukang
Alat Bantu

OH
OH
OH
OH
Lot

JENIS PEKERJAAN
HARGA SATUAN/ LUMPSUM

: PENGUKURAN DAN POSITIONI


:

No

URAIAN

SATUAN

1.

PERALATAN
- Waterpass
- Theodolite
UPAH
- Pekerja
- Juru ukur

2.

hari
hari
hari
hari

SATUAN PEKERJAAN

MOBILISASI DAN DEMOBILISASI ALAT BERAT

KWANTITAS
1.00
1.00
2.00
5.00
1.00
1.00
2.00
1.00
1.00
3.00
1.00
1.00
2.00
1.00
2.00

Rp

344,500,000.00

HARGA SATUAN
(Rp.)
30,000,000.00
26,400,000.00
79,200,000.00
4,800,000.00
4,800,000.00
4,800,000.00
26,400,000.00
3,000,000.00
3,000,000.00
3,000,000.00
1,200,000.00
3,600,000.00
6,500,000.00
4,000,000.00
3,250,000.00

JUMLAH
(Rp.)
30,000,000.00
26,400,000.00
158,400,000.00
24,000,000.00
4,800,000.00
4,800,000.00
52,800,000.00
3,000,000.00
3,000,000.00
9,000,000.00
1,200,000.00
3,600,000.00
13,000,000.00
4,000,000.00
6,500,000.00

TOTAL

344,500,000.00

MOBILISASI DAN DEMOBILISASI

KWANTITAS
2.00
8.00
1.00
1.00
8.00
6.00
7.00

Rp

581,000,000.00

HARGA SATUAN
(Rp.)
7,500,000.00
12,000,000.00
25,000,000.00
24,000,000.00
35,000,000.00
20,000,000.00
3,000,000.00

JUMLAH
(Rp.)
15,000,000.00
96,000,000.00
25,000,000.00
24,000,000.00
280,000,000.00
120,000,000.00
21,000,000.00

TOTAL

581,000,000.00

PEMBERSIHAN LAPANGAN
Rp

47,300.00

KWANTITAS
0.005
0.050
0.050
0.050
1.000

HARGA SATUAN
(Rp.)
110,000.00
90,000.00
80,000.00
65,000.00
35,000.00

JUMLAH
(Rp.)
550.00
4,500.00
4,000.00
3,250.00
35,000.00

TOTAL

47,300.00

PENGUKURAN DAN POSITIONING


Rp
KWANTITAS

HARGA SATUAN
(Rp.)

130,500,000.00
JUMLAH
(Rp.)

150.00
150.00

300,000.00
400,000.00

45,000,000.00
60,000,000.00

150.00
150.00

80,000.00
90,000.00
TOTAL

12,000,000.00
13,500,000.00
130,500,000.00

Pekerjaan Pemancangan
1
2
3
4
5

Pemancangan Spun Pile dia 600mm (on shore)


Proc. Spun Pile
m'
Pilling
m'
Handling & Positioning
m'
Jointing
point
Cut off
point

11,293.00
11,293.00
11,293.00
491.00
491.00

1
2
3
4
5

Pemancangan Spun Pile dia 600mm (off shore)


Proc. Spun Pile
m'
Pilling
m'
Handling & Positioning
m'
Jointing
point
Cut off
point

1,035.00
1,035.00
1,035.00
45.00
45.00

1
2
3
4
5

Pemancangan Steel Pipe


Proc. Steel Pile
Pilling
Handling & Positioning
Jointing
Cut off

1,104.00
1,104.00
46.00
46.00
46.00

m'
m'
point
point
point

775,623.00
325,450.00
147,041.95
413,750.00
423,404.00
SUB TOTAL

775,623.00
325,450.00
147,041.95
413,750.00
423,404.00
SUB TOTAL

96,768.00
325,450.00
147,041.95
413,750.00
423,404.00
SUB TOTAL

8,759,110,539.00
3,675,306,850.00
1,660,544,727.40
203,151,250.00
207,891,364.00
14,506,004,730.40

802,769,805.00
336,840,750.00
152,188,416.97
18,618,750.00
19,053,180.00
1,329,470,901.97

106,831,872.00
359,296,800.00
6,763,929.64
19,032,500.00
19,476,584.00
511,401,685.64

You might also like