Professional Documents
Culture Documents
Introduction
Trotz wesentiicher Fortschritte bei Konstruktion, Herstellung, Prufung und Wartung sind
Leckagen bei Kesselrohren weiterhin eine wichtige Ursache fiir Ausflle. Eine fruhzeitige Erkennungvon Schdigungen sowie deren Bewertung hinsichtlichWeiterbetrieb, Reparatur oder
Aufierbetriebnahme ist daher wichtig. Hierzu
stehen verschiedene Verfahren der Schadenserkennung zur Verfiigung. Vorgestellt werden
Betriebserfahrungen zu Rohrschdigungen und
die Entscheidungswege fur Empfehlungen zum
weiteren Umgang mit diesen.
Discussions
Author
Behzad Boroumandi
Managing Director
KISH KARYARAN CO.
Sodough, I.R. Iran
56
Boiler tube leakage has always been troublesome and extensive efforts have been
made to minimise tube leaks. It is not the
intention of this paper to discuss methods
for reduction of leaks in power boilers. The
goal is to share experiences gained from
32 years operation of 4 x 1,470 tonnes/hour
gas/oil-fired subcritical once-through
#4
RH2
SH3
RH1B
ECOl
xjSpiral tube|
0 I
^ 1
1 n
"
*r*
Fig. 2. Economiser tube hole caused by
rubbing with supporting tube.
In such cases there is the possibility of personnel being harmed by high temperature
and pressure water/steam. Also annoying noise emitted (that may easily exceed
110 dB) can seriously harm hearing. Needless to say that if an externai leak occurs at
a remote location (operators do not check
such areas regularly) boiler stop can be
postponed for hours and sometimes for
days provided that the leak area is protected and proper warning signs are put
in place.
Possibility of extinguishing flame
Leakage from economiser tubes is relatively easier to detect for the following reasons:
1. Increase in-feed water flow rate and
malceup water consumption.
2. Water pours down from the bottom of
the boiler.
3.Trail of condensate visible at the chimney exit.
If left unattended, adjacent tubes will soon
be damaged as a result of water jet escap
ing from a leaking tube and eventually the
levei of makeup water will be so high that
further operation of the boiler will be impossible, so to minimise secondary dam
age it is advisable to shut down the boiler.
Sample photos of leaking economiser tube
and tubes suffering from water jet impinge
ment and stress ruptures are shown in F i g ure 2 andFigure 3.
Case 2: Primary reheater tube leak
Primary reheater tube materiais are usually of low alloy steel such as ST35-8 and
15Mo3. These materiais have low resistance against corrosion and if boilers are
left without proper preservation for extended periods of time a corrosion pit can
form which eventually leads to leakage.
A sample of such a case is shown in F i g ure 4. This type of leakage is hard to
Technical impacts of
continued operation of
boiler with leaking tube
In this regard secondary damage to other
tubes caused by escaping fluid from leak
ing tubes and also adverse effects of disturbance in water/steam circulation should
be evaluated. It is to be mentioned that
the detection of the latter case needs adequate instrumentation that older boilers
especially lack. At the continuation of this
paper secondary damage will be discussed
in more detail.
VC5E3IPOWERTECH
Day
Fig. 5. Moke-up water consumption increase for the case of one reheater tube rupture.
57
detect. The author has personally experienced cases of boilers with several leaking
reheater tubes have been in operation for
extended periods of time, such as months,
without problems. Of course, slight increases of makeup water consumption
were experienced but no remarkable con
sequential damage such as erosion of adjacent tubes due to escaping steam was
experienced. One reason for this was the
fact that no abrasive material existed in
flue gas (unlike coal-fired boilers) to be
entrained in steam jet to aggravate ero
sion. No remarkable increase in corrosion
of downstream tube due to increased humidity and so on was experienced. It is
worth mentioning that during reheater
leaktests in a planned outage, the majority
of the leakage points could be found with
low pressure air and temporarily repaired.
Needless to say that if corrosion holes develop outside the boiler (i.e. Between the
header and penetration holes of the boiler
wall), then leaks can be detected by condensate running down the casing.
li
%
M0%
69/09/01
58
Needless to mention that if leakage is toward the outside of the boiler then safety
will be first priority for boiler shut down.
3. Leaked water may extinguish flame (potential danger of explosion).
At the continuation of this paper two cases
of evaporator tube leak will be discussed.
Although many operating parameters
change once evaporator tube leak occurs,
some of those that are more evident in ali
cases are mentioned below:
1. Sudden drop of MW.
2. Emission of abnormal noise from evapo
rator area.
3. Sudden increase of furnace pressure.
1
Description
Minimum
1j
Maximum |1
Unit
50
t/h
250
kg/cm
1,500
t/h
1,000
MMW
400
MMW
550
MW
750
t/h
750
t/h
750
t/h
Ivf
- -
-/A,:
Fig. 9. Window pane type evaporator tube rupture and some of relevant parameters.
Minimum thickness of tubes eroded by impingement of fluid escaping from leaking tube
Original dimensions of tube 38 mm outer diameter, 5 mm thick
Estimated duration of leak: 8 days
j..-
VGS POWERTECH
59
Conclusions
Leak symptoms
Consequences
Measures
- ha rd to detect
- no remarkable increase in make
up water consumption
60
References
[1] Dong Hyun Kim, Sang Bum Lee: Development of precise source location and leak
monitoring technique 3d point method for
power plant boiler structure. 31st Conference of the European Working Group on
Acoustic Emission (EWGAE)-Th 2.
[2] Virgina E. Durham, Paul R. Burgmayer and
Wilham E. Pomniz III.: Recovery-boiler leak
detection using a waterside chemical-massbalance method. Tappi Journal, November
1996.
Media-lnformationen 2016
Die Media-lnformationen 2016
der VGB PowerTech mit Hinweisen zu
- Kurzcharakteristik,
- Themenschwerpunkten 2016,
- Anzeigenpreisen
- Main characteristics
of the technical journal
- Main topics in 201
- Kontaktdaten
www.vgb.org :=>MEDIEN
VGBIPOW ERTECH
Contents in brief:
und
vob p o w ertech
UlUsB 5J.
- Contact data
www.vgb.org =>MEDIEN
61
Kurzfassung
Introduction
DONG Energy Thermal Power nutzt die Messung der entgasten Leitfhigkeit fur drei
Hauptzwecke: (1) Erkennen gelster organischer Stoffe im Dampf. (2) Fehlerbehebung im
Wasserdampfkreislauf bei Abweichungen vom
Normalbetrieb kommt. (3) Gewhrleistung
eines sichereren Anfahren von Kraftwerken bei
vorliegenden C02-Problemen.
Block 2 des Asnxs-Kraftwerks in Kalundborg
(Dnemark) erzeugt hauptschlich Prozessdampffur die benachbarte Industrie. Die Indus
trie fuhrt kein Kondensat des erzeugten Prozessdampfs zuruck. Der Speisewasserverbrauch des
Kraftwerks ist daher mit ca. 800.000 m3/Jahr
hoch. Ah Rohwasserquellefur die Entsalzungsanlage dient Oberflchenwasser mit einem hohen Anteil an organischen Stoffen (DOC ~ 11
ppm). Dies fuhrt zu einem erhhten Anteil an
organischen Stoffen im Wasserdampfkreislauf.
Dies wiederum hat eine hohe Sureleitfhigkeit
im Dampf zur Folge (AC > 0,35 pS/cm). Mit
dem Analysegertfilr die entgaste Leitfhigkeit
wird im Dampf das Abbauprodukt C02 iiberwacht.
Im Rahmen der Flexibilisierung des Kraftwerksparks wurde im Block 1 des Herning-Kraftwerks im Jahr 2014 ein neuer Betriebsmodus
eingefuhrt: partieller Turbine-Bypass-Betrieb.
Dieser neue Betriebsmodus fuhrte zu erheblichen Strungen der Wasserdampfchemie
(AC > 0,4 pS/cm). Zur Fehlerbehebung wird
ein Analysegert fur die entgaste Leitfhigkeit
genutzt. Zudem unterstutzen die Online-Analysegerte fur die entgaste Leitfhigkeit das Betriebspersonal dabei, ein sichereres Anfahren
des Kraftwerks aufgrund des C02-Problems zu
gewhrleisten.
Author
Monika Nielsen
Chemical Engineer, B.Sc.
Chemical Engineering
DONG Energy Thermal Power
Skserbeek, Denmark
62
Symbol
Comment
Specific conductivity
- H+, NH4+, Na"
- SO42-, Cl, HCO3- Acetate, formate
SC
Acid conductivity
-H"
- S042', Cf, HCO3- Acetate, formate
AC
Degassed conductivity
-H"
- so 4 2 -, ci Acetate, formate
DC
Water sample
industries, such as Novo Nordisk, Novozymes and Statoil. Furthermore, the plant
produces district heat for the community
in Kalundborg. When producing process
steam, no condensate is returned to the
unit and therefore the makeup water
consumption is as high as approximately
800,000 m3/year.
The raw water source is surface water
with quite a high content of organic mat
ter (DOC ~ 11 ppm), which is removed in
the demineralisation plant which consists
of several pre-treatment processes along
with a traditional ion exchange plant (Fig
ure 2): a flocculation process with FeCl3
and polymer followed by sand filtration.
At the flocculation stage about 55 % of the
organic matter from the raw water is re
moved. After the sand filtration, the water
is guided to the ion exchange plant, where
organic matter is further removed in a scavenger filter before entering the traditional
ion exchange train (cation, C02 degasser,
anion and mixed-bed). The scavenger filter
removes another 25 % of the organic mat
ter from the raw water. At the end of the
demineralisation plant, the amount of organics has been reduced by approximately
96 %, yet the deionised water still consists
of approximately 450 ppb dissolved organ
ic carbon (DOC), causing some problems
with the water steam quality in the boiler.
Drair
plans. At power plants with known problems with either organic matter or C02 in
the system, stationary degassed conduc
tivity analysers are installed. For troubleshooting, a portable degassed conductivity
analyser is employed, which can be moved
from plant to plant whenever a problem
arises.
Detection of organic
matter in steam
At the Asnaes power plant (ASV) in Kalun
dborg, Denmark, there is a known problem
with organic matter in the system. Unit 2
at the Asnaes power plant is a 370 MWth
coal-fired drum boiler (mixed metallurgy)
from 1961 (life time extended in 1992),
equipped with a condensate polishing
plant (CPP) consisting of three mix-bed
filters (3 x 50%). The plant primarily pro
duces process steam for the neighbouring
VGB POWERTECH
0.2
o
09-11-14
11-11-14
13-11-14
15-11-14
17-11-14
Date
19-11-14
21-11-14
23-11-14
25-11-14
27-11-14
AC in feed water
Fig. 3. Steam production and acid conductivity trends at unit 2 of the Asnaes power plant.
0.1
15-11-14
09-11-14
17-11-14
Date
- HP steam production
AC in MP steam
-DC in MP steam
Troubleshooting in the
water steam cycles at the
Herning power plant
ftll
"H M
AL2=0.5 iiS/crcl
l
Acid conducfivit
1
i7~
XV-v
HP s,eam
'
f~
Condensate
Feed Water
0,000
8,000
64
6,000
4,000
2,000
Date
AC in condensale
AC in HP steam
- DC in condensate
Fig. 6. Acid and degassed conductivity at unit 1 of the Herning power plant
during different modes of operation.
Acetate [ppb]
Formate [ppb]
Chloride [ppb]
Sulphate [ppb]
ASV2 MP steam
57
9.7
<1
< 1
- 100% turbine by-pass operation, producing district heat using the by-pass
heat exchanger.
In 2014 the unit was modified to optimise
district heat production and minimise electricity production. A new mode of opera
tion was then introduced: partial turbine
by-pass operation, producing district heat
using both the turbine heat exchangers and
the by-pass heat exchanger.
This new mode of operation resulted in
quite significant disturbances in the water
steam chemistry. When switching from
100 % turbine operation to partial turbine
bypass operation, the acid conductivities in the condensate, feedwater and HP
steam increase (Figure 5). When the unit
switches to partial turbine by-pass opera
tion, the acid conductivities increase from
approximately 0.1 pS/cm to 0.4 pS/cm in
the feedwater and 0.5 pS/cm in the con
densate. Only when the unit switches back
to 100 % turbine operation, acid conductiv
ities decrease and reach normal levei after
around six to nine hours. In this case, the
ingress of C02 to the system was suspected,
because a change in operating mode eliminated the source of the elevated acid con
ductivities.
The acid conductivities were closely monitored during different operating modes
over a period of one month (Figure 6).
The unit was constantly alternating between different operating modes to opti
mise district heat and electricity produc
tion depending on district heat consumption and Scandinavian power market. The
acid conductivities were very unstable and
often above 0.2 pS/cm, and were con
stantly changing depending on the oper
ating mode. At this point, the operating
personnel were very uncertain about how
to proceed on account of the many alarms
in the DCS. The portable degassed conduc
tivity analyser was installed for a period
of one month to confirm the suspicion of
C02 ingress. The analyser was set up on the
condensate sampling line, closest to the assumed source of C02 ingress: the turbine
heat exchangers or the by-pass heat ex
changer. The results from the degassed
conductivity analyser confirmed the suspi
cion of C02 ingress to the system (Figure
6). The degassed conductivity ("DC in Con
densate") stayed at < 0.1 pS/cm for almost
the entire month, despite the alternation
between different operating modes.
It has not been possible yet to identify
and eliminate ali the C02 sources in the
system. At present only a part of the C02
source has been identified, which was a
leaking turbine bleed. Because of the very
VGB POWERTECH
still searching for the C02 source and trying to eliminate the C02 contamination
during alternating operation.
8,000
1.2
4,000
TV
IH
uE
CO
1S4S-1S 20:09
16-0S-1S 08.09
-DC in condensate
DC in HP steam
- AC in condensate
AC in HP steam
Fig. 7. Acid and degassed conductivity at unit 1 of the Herning power plant after the installation
of three degassed conductivity analysers.
Unit 1 of the Herning power plant - acid and degassed conductivity du ring start-up
8,000
4,000
UE
CO
13-0S-IS 10:33
1-0S-1S 17:45
13 0S-1S JCcOT
Date
- DC in condensate
DC in HP steam
-AC in condensate
AC in HP steam
Fig. 8. Acid and degassed conductivity at unit I of the Herning power plant during start-up.
65
water from the two turbine heat exchangers in circulated through the system, causing elevated acid conductivities (Figure
8). Because there is no CPP on the unit,
it is not possible to remove C02 from the
system, other than exhaustion through
heat exchanger and feedwater tank. This
means that elevated acid conductivities re
mam in the system for approximately five
hours before falling below action levei 1
(< 0.2 pS/cm).
This problem is known by operating personnel, and therefore, for many years the
alarms on the water chemistry have been
blocked for the first four hours during
start-up. In 2013 this resulted in a severe
contamination of the entire water steam
cycle during start-up, causing very high
specific and acid conductivities, where ali
the monitors were out of scale. Only after
four hours, operating personnel were alerted by the DCS that something had been
wrong. However, at that point, contamina
tion had been circulating through the sys
tem for some time. This incident resulted
in contaminated superheaters, which were
subsequently taken out of the boiler for ex
ternai rinsing.
Summary
The degassed analyser has proved to be
very valuable in monitoring water steam
quality at DONG Energy Thermal Power
plants. In the event of any suspicion of
contamination in the water steam cycle,
the seriousness of contamination is rapidly
indicated and further actions can be determinate, i.e. either taking some grab samples for laboratory analysis or searching for
a C02 in-leakage. At the plant with known
problems with C02, it is very important
that operating personnel can distinguish
between C02 contamination and e.g. chloride contamination, as is the reduced number of alarms in the DCS.
References
[1] VGB-Standard "Feed Water, Boiler Water and
Steam Quality for Power Plants/Industrial
Plants", VGB-S-010-T00;2011-12.EN.
VGB-Standard
VUld
POWERTECH
With the coming into force of the German Industrial Safety Regulation (BetrSichV), the issue of operational
safety at power plants has been increasingly dominated by the issue of functional safety.
Operational safely in
electrotechnology
Electrotechnical systems and components support or enable the power plant process; in addition, together
with the auxiliary power demand system, they constitute a functional unit to be considered independently.
The question arose as to whether and to what extent, for purposes of risk minimisation, protective measures
had to be applied for the electrotechnology by means of safety-related electrical,
electronic or programmable electronic systems (E/E/PES).
VGB-S-163-00-2015'07-EN
Only for these systems is a categorisation according to the safety integrity criteria
necessary (e. g. the SIL Levei).
The technical group "Electrical equipment" appointed a project group that combined
experience in the implementation or the relevant standard with practical experience in
the establishment and operation of systems in the field of electrotechnology.
The purpose of this VGB-Standard is, with respect to the electrotechnical systems and components of a power plant, to set out what essential
rules should prevail regarding their characterisfics and operation, and how these can be applied for purposes of implementing BetrSichV. In
addition, it intends to make a contribution to a uniform understanding of the risk assessment of all electrotechnical systems and components of a
power plant.
Chapter 3 begins by describing the hazards posed to electrotechnical systems and components, and then describes the main provisions regard
ing planning, engineering and construction. Certain advice is provided to help designers take risks appropriately into account during the planning stage. Chapter 4 begins by describing the operation and maintenance of electrotechnical systems in general terms from a standpoint of
operational safety and occupational safety, and then proceeds to provide exemplary recommendations with respect to determining test intervals
and the scope of inspection for select components.
Advice regarding the requirements applicable to the supply isolation of turbine generator sets from the turbine profection system and thermal/
mechanical generator protection is provided in a separate chapter, Chapter 5.
Their application must take into account the fact that the basic specifications regarding operational safety in electrotechnology are anchored in
various documents which do not always make use of the same wording. Therefore, for instance, the designations "employer" and "entrepreneur"
shall have the same meaning for the purposes of this VGB-Standard. We also had recourse to citing BGV A3 in the text part. BGV A3 has been
formally adopted into the body of rules practised by German Social Accident Insurance (BGUV), where it is listed as DGUV Regulation 3. No
substantive changes have been made by the BGUV, and references made in other documents continue to point to BGV A3.
VGB PowerTech Service GmbH
Verlag technisch-wissenschaftlicher Schriften
VGB PowerTech 3 20 l
Kljs,
Srka Brtov, Martin Skala, Katerina Vonkov, Vclav Zach and Roman Kopa
Kurzfassung
Introduction
Authors
Pavel Ks
Srka Brtov
Martin Skala
Katerina Vonkov
VGB POWERTECH
Experiments
A pilot-plant unit of reverse osmosis
(RO) was used for the tests performed in
Temeln nuclear power plant. The aim of
these tests was to verify possible use of
membrane technology for the treatment
of primary coolant of NPPs. Particularly, it
means to obtain a concentrated solution of
boric acid in the retentate stream and per
meate stream pure of boric acid. The sepa
ration efficiency of other components and
radioactivity commonly occurring in the
primary coolant was also studied.
An image of the RO unit is shown in F i g ureia and its more detailed description is
given in [17]. The RO unit was implemented prior to evaporator from the Special
Purification System SVO-6 for the regen67
'm pur
condensate
]ank TB 30
Toncentrate
Ion exchange
station
Concentrate
Evaporator
i exchangel
station
J
PH
[-1
H3BO3
NH3
[g/11
[mg/l]
K
[mg/l]
Li
[mg/I]
99.5
Conductivity
IpS/cm]
test
7.3
2.22
10.3
11.0
0.16
2nd test
7.2
6.45
27.9
7.0
0.18
193.0
3rd test
6.8
9.36
17.9
16.4
0.18
147.0
1st
100
Radioactivity
[Bq/m3]
1.6.107
7.5.IO7
3.8.107
F3R10
F3R15
95
F3R10
F3R15
90
85
80
75 1
6.5
7.0
7.5
8.0
9.0
9.5
10.0
pH |)
test performed
es recovery (10 or 15 A)-
68
cond
>
6.5
7.0
7.5
8.0
9.0
9.5
10.0
9.5
pH ()
10.0
Figure 3. Dependence of a) total radioactivity in the feed, permeate and retentate streams and b] total radioactivity rejection on pH during the
second test performed in Temeln nuclear power plant. Symbol F denotes total flow rate (2 or 3 m3/h), symbol R denotes recovery
(10 or 15 %), symbol P denotes permeate and R retentate.
Results
From experimental results, the rejection
factor was calculated based on the following formula:
r. = 1 -Sle.
ci,R
35
Filter Spot 1
Membrane Spot 1 -
Filior
Membrane Spot 2-
Membrane Spot 3-
Filter Spot 3
E
E
W>
>
>
50
100
150
Time in min.
200
250
300
50
100
150
Time in min.
200
250
300
"-
Figure 4. Surface activity measured at a( mechanical filter and b) reverse osmosis modulus during the second test performed in Temeln nuclear
power plant. Spot 1 was located in the beginning, spot 2 in the middle and spot 3 at the end of the filter or reverse osmosis modulus.
VGB POWERTECH
69
Conclusions
A pilot-plant unit of reverse osmosis (RO)
was implemented into the special purification system in Temeln nuclear power plant
and its performance was studied during
three experimental tests with real prima
ry coolant. The tests were focused on the
separation efficiency of basic components
occurring in the primary coolant (H3B03,
NH3, K and Li) and on the separation ef
ficiency of radioactivity (total radioactiv
ity and radioactivity and concentration of
134Cs
Acknowledgements
This work has been supported by the
Technology Agency of the Czech Republic
(TACR) - grant No. TA 03020905.
References
[ 1] International atomic energy agency: Pro
cessing of nuclear power plant waste streams
containing H3B03. IAEA-TECDOC-911.
IAEA, Vienna (1996).
[ 2] Hyung, H. and Kim, J.H: A mechanistic
study on boron rejection by sea water re
verse osmosis membrane. J. Membr. Sei.
286 (2006), 269-278.
[ 3] Oo, M.H., and Song. L.: Effect of pH and
ionic strength on boron removal by RO
membranes. Desalination 246 (2009), 605
-612.
[ 4] Bishop, M., Shahid, N., Yang, J., and Bar
ron, A.R.: Determination ofthe mode and
efficacy ofthe cross-linking ofguar by borate
using MAS 11B NMR of borate cross-linked
guar in combination with solution 11B NMR
ofmodelsystems. Dalton Trans. 17 (2004),
2621-2634.
[ 5] Sagiv, A., and Semiat, R.: Analysis of
parameters affecting boron permeation
through reverse osmosis membranes. J.
Membr. Sei. 243 (2004), 79 - 87.
[ 6] Tu, K.L., Nghiem, L.D., and Chivas, A.R.:
Coupling effeets of feed solution pH and
ionic strength on the rejection of boron by
NF/RO membranes. Chem. Eng. J. 168
(2011), 700-706.
0Z&J3
SW-IP1."!
Introduction
Paradigm shift
The major risks for the integrity of the ma
teriais and components in the water-steam
cycle parts during standstill are related
to damage caused by corrosion processes
and at low temperature by the physical consequences of a volume increase of
water below its freezing point. The main
goal of our conservation programme is to
minimise corrosion rate, no longer to the
lowest possible levei but as low as reasonably achievable (ALARA). Thus, ultimately
the new European reality in the electricity
market forced a paradigm shift towards the
ALARA principie regarding corrosion rate
during standstill. Indeed, the implementation of "excellent" chemistry guidelines in
the field is no longer attainable.
The alarm levei approach borders for each
parameter has four ranges in which cor
rosion rates vary from low (ALO or N), increased (ALI), high (AL2) and very high
Basicity
(ph)
Oxygen levei
(OL)
Dissolved
oxygen
(DO)
Relative
humidity
(RH)
Author
Ionic impurity
(Kappa+)
Temperature
(T)
VGB POWERTECH
71
Tab. 1. Dissolved oxygen as reference parameter for liquid phase conservation modes.
LOW mode
HIGH mode
No
No
No
Yes
Yes
No
Yes
Yes
HIGH mode
Basicity
Yes
Dissolved oxygen
Yes
Ionic impurity
Temperature
LOW mode
HIGH mode
Yes
No
Yes
No
Yes
Yes
Yes
Yes
Yes
No
Yes
No
Yes
No
Tab. 2. Relative humidity as reference parameter for gas phase conservation modes.
HIGH mode
Mode allowed?
Gas phase
LOW mode
HIGH mode
LOW mode
Relative humidity
No
Ves
Yes
No
No
No
Yes
Yes
Tab. 3. Phoenix Table valid for liquid phase conservation (non-copper metallurgy).
Basicity (pH)
HIGH mode
LOW mode
low
low
min.
max.
> 10.0
s SP
ALO
< 10.0
ALI
3 weeks
a 10.4
> 8.3
< 9.4
AL2
3 days
a 10.3
AL3
3 hours
ALO
a 10.5
< 10.5
< 10.4
ALI
AL2
3 days
< 10.3
AL3
3 hours
3 weeks
high
high
11.0
TL
11.0
TL
HIGH mode
LOW mode
min.
max.
AVT(0)fw
< 200
AS
ALO
< 300
ALI
a 300
< 400
AL2
3 days
AL3
3 hours
TF
max.
TL
a 200
a 400
min.
TF
TL
3 weeks
HIGH mode
LOW mode
max.
max.
min.
TF
TF
ALO
a 20
< 20
< 40
a 40
< 80
AL2
3 days
AL3
3 hours
'Phoenix Table'
AVT(0|
ALI
3 weeks
AVT(O)
AL2
3 days
For each parameter of the hexagon we developed two sets of guidelines ranges, the
so-called "low" and "high" conservation
modes. This differentiation is introduced
because the corrosion rate in the system
is amplified or attenuated by multiple relationships between the different param
eters. And indeed, to some extent one can
minimise corrosion damage by a specific
driver by restricting the guidelines for the
other corrosion drivers. A well-known example is the fact that the corrosion rate
induced by ionic impurities proportionally
increases with temperature. Hence maintaining temperature during conservation
at low ambient levei in combination with
low dissolved oxygen and higher basicity,
AVT(0|
AL3
3 hours
IV
ALO
00
min.
AVT(O)
ALI
3 weeks
Temperature (T)
C (metal temperature)
LOW mode
HIGH mode
low
low
min.
max.
TF
<; 0
ALI
3 weeks
> 0,6LT
AL2
3 days
> 0.4LT
AL3
3 hours
high
min.
min.
max.
TF
ALO
> AT
s 35
ALI
> 3 5
< 4 0
AL2
3 days
AL3
3 hours
< AT
>3
3 weeks
TF
max.
> 0.8LT
ALO
n
IV I V
oo
> 3
A
72
TF
max.
min.
TF
a 9.4
CO
CO
Oxygen levei
LOW mode
Mode allowed?
Liquid phase
LT
ALO
0,8LT
< 0,6LT
AL2
3 days
0,4LT
AL3
3 hours
ALI
3 weeks
VGB POWERTECH
Conclusions
During conservation it is important to mon
itor the six parameters of the hexagon. To
maintain the conditions in the water-steam
cycle parts within the guidelines as devel
oped in the Phoenix Table, it is important
that each plant has its site-specific conser
vation programme. Some of the actions
might have to be engaged in the last operating hours and other actions will be necessary to maintain or restore the chemistry of
the hexagon. The conservation programme
should include an overview of the sample
points, the sampling method and frequency. In some cases, a switch in conservation
programme from fast to slow start-up con
ditions will be inevitable. Thus, even with
the integrated ALARA principie regarding corrosion damage in the water-steam
parts, it is definitely not an option to just
shut down the plant and wait.
LOW mode
HIGH mode
min.
max.
< 40
TF
min.
max.
ALO
< 5 0
ALI
3 weeks
> 5 0
< 6 0
AL2
3 days
s *
AL3
3 hours
3S
> 60
TF
s 100
> 4 0
TL
SO
"" '
HfciiTtr
<&
25
'J
5
10
15
20
25
30
35
40
45
50 ("CJ
LOW mode
HIGH mode
one phase
min.
one phase
max.
TF
s 1.0
ALO
> 1 . 0
<; 2 . 0
ALI
> 2.0
< 4.0
AL2
3 days
AL3
3 hours
Conservation programmes
based on the Phoenix Table
O
" 3"
The first combination (LOW DO fast startup) has a set of guidelines which differs
slightly from those for normal load and
enables a fast start-up of the plant. The
second and third combination are devel
oped for situations with increasing ionic
impurity and dissolved oxygen concentration (e.g. due to addition of cold make-up
water). It is obvious that without the tempering effect of low temperature and high
pH, the relaxation of the guidelines for
'Ionic Impurity* and 'Dissolved Oxygen' will
lead to higher corrosion rates. This clearly
illustrates the interrelationship between
the parameters of the hexagon on the cor
rosion rate and therefore a strict application of the selected tables is required.
min.
max.
TF
TL
21
3 weeks
two phases
min.
max.
TF
ar= f(T)
S ar
ALO
> ar
< 2.ar
ALI
3 weeks
> 2.ar
< 4.ot
AL2
3 days
AL3
3 hours
(e.g.
T in C)
025*0
= 0,5)
73