Professional Documents
Culture Documents
INSTALLATION MANUAL
for
UNDER GROUND
for
Page
1/7
QCP I 03
Revise No
Date
Document No.
Description
1.3 Terminology
Because pipeline installation terminology varies throughout the country, figure 1 has prepared
illustrate the meaning and limits of the terms foundation, bedding, pipe-zone backfill,
primary, and secondary, pipe-zone backfill, and backfill, as used in this document.
BSS-0202-A
A4(210X297)
Page
2/7
QCP I 03
Revise No
Date
Water control. It is always good practice to remove water from a trench before laying and
backfilling on pipe. Prevent runoff and surface water from entering the trench at all times.
1.4.2 Excavation
Where rock, cobbles, or hardpan excavation is encountered, excavated the trench bottom to
provide a minimum 6 inch(0.15m) of bedding under the pipe.
1.4.3 trench width
Minimum width at the bottom of the trench should be 1.25 times the outside diameter of the
pipe plus 12 inch(305mm). The width of the trench at the top of the pipe (see figure 1.1)
should not be grater than necessary to provide adequate room for jointing the pipe in the trench
and compacting the pipe-zone backfill at the sides of the pipe. However, if the trench-wall
material is a soil that will not provide the side support for the pipe required by the design
procedure, increase the trench width and specify a high degree of compaction (70% relative
density) for the pipe-zone backfill material.
Side clearance (see Figure 1.1) must always be wide enough to allow for adequate space to
ensure proper placement of backfill in the haunch region and to operate compaction equipment.
Typically Side clearance for is a minimum of 0.75*ND/2 and for small pipe is minimum 20
inch(500mm). For larger diameter pipes and smaller value for side clearance may be adequate
depending on the native soil, backfill material and compaction technique.
1.4.4 trench depth
Determine the trench by the intended service, properties, size of the pipe, and local conditions
such as the properties of soil and combination of static and dynamic loading. Take care to
ensure that the burial depth is sufficient to prevent the conveyed fluids from being affected by
frost penetration. Follow local, state, and federal safety regulations. If required, shore, sheet,
brace, or otherwise support the trench walls with sufficient strength to protect the employees
working in the trench.
BSS-0202-A
A4(210X297)
Page
3/7
QCP I 03
Revise No
Date
40
50
72
90
100
Rail
Road
Min. Burial
Depth, (m)
0.5
1.0
1.0
1.0
1.5
1.5
3.0
NOTE: But, determine the Minimum Burial Depth by the size of the pipe, and local
conditions such as the properties of soil and combination of static and dynamic
loading.
2. Installation
Store and handle the pipe carefully to prevent pipe damage. Inspect each pipe unit for damage
prior to installation. When installed in a trench, the pipe may be deflected in the joint to a
minimum radius recommended by the manufacture for the kind, type, grade, wall thickness, type
of joint, and diameter of a particular pipe. Where a change in horizontal or vertical alignment, or
both, will produce sufficient thrust to cause movement of the pipe, provide suitable anchors.
3. Backfill
For pipe larger than 10inch (250 mm) in diameter, where the primary pipe-zone backfill is
compacted by tamping or surface vibrators. Place the primary pipe-zone backfill material in layers
on each side of the pipe and compact it in accordance with below procedure. Take extra care to
compact the material under the haunches of the pipe. Place the compact primary pipe-zone
backfill to a minimum depth of 70% of the outside diameter of the pipe.
BSS-0202-A
A4(210X297)
Page
4/7
QCP I 03
Revise No
Date
Document No.
Description
Maximum particle size for the pipe-zone backfill is limited to material passing a 40mm. To
enhance placement around small diameter pipe, typically 375mm and smaller, or to prevent
damage to the pipe wall , a smaller maximum size should be use. At the discretion of the engineer,
the secondary pipe-zone backfill material may be compacted to 6 to 16 inch(150 to 300mm)
above the top of the pipe. Bring the entire pipe-zone backfill up uniformly on both sides of the
pipe, with not including rocks or clods grater than 1 inch(25mm) in diameter being placed within
6 inch(150mm) of the outside pipe. The following installation procedures are intended to assist
the installer in achieving an acceptable pipe installation. However, regardless of soil conditions
and installation method, the initial and long-term deflections must not exceed the values given in
Table 3.1
Table 3.1 Allowable Vertical Deflection
Pipe size
Deflection % of Diameter
5.0
5.0
Install foundation and bedding as required by the engineer according to conditions in trench
bottom. Provide a firm, stable, and uniform bedding for the pipe barrel and any protruding
features of its joint.(see Figure 3.1, 3.2). The depth of the layer being compacted must be
controlled as well as the energy placed into the compaction method.
BSS-0202-A
A4(210X297)
Page
5/7
QCP I 03
Revise No
Date
Document No.
Description
SC1
GW, GP, SW, SP, dual symbol soils containing one of these
designations such as GW-GC containing 12% fines or less
SC2
GM, GC, SM, SC with more than 12% fines; and ML, CL, or
borderline soils beginning with one of these designations, such as
ML/CL, with 30% or more retained on the No.200 sieve.
SC3
SC4
CH, MH, OL, OH, PT, CH/MH, and any frozen materials
SC5
Place embedment materials by methods that will not disturb or damage the pipe.
A blunt tool may be used very effectively to push and compact the backfill under the pipe, without
raising the pipe up. (See Figures 3.1.1). Work in and compact the haunshing material in the area
between the bedding and the underside of the pipe before placing and compacting the remainder
of the pipe zone embedment.(see Figure 3.1.1)
BSS-0202-A
A4(210X297)
Page
6/7
QCP I 03
Revise No
Date
Document No.
Description
Do not permit compaction equipment to contact and damage the pipe. Use compaction equipment
and techniques that are compatible with materials used and located in the trench.
A4(210X297)
Page
7/7
QCP I 03
Revise No
Date
Document No.
Description
conditions; however, their relatively low stiffness precludes their use in deeper installations, and
their moisture sensitivity limits their use where standing water interferes with their compaction.
13
500 to 600
19
700 to 900
25
1000 to 1200
32
1300 to Greater
40
In addition stones larger than 8 inch(200 mm) in diameter should not be dropped on the 300mm
layer covering the pipe top form a height greater than 7 feet(2 m).
8.7.1
Moisture control may be required when compacting the soil to achieve the desired density with
reasonable compaction energy and easily used compaction equipment. To achieve desired relative
compaction, moisture control will most likely be required during compaction. Compaction tests
should be conducted periodically to assure proper relative compaction is achieved. Moisture
content must be controlled during placement and compaction.
BSS-0202-A
A4(210X297)