Professional Documents
Culture Documents
BUILDING )
A
Practical Training Report
BACHELOR OF TECHNOLOGY
SUBMITTED TO
(September, 2016-17)
DECLARATION
ACKNOWLEDGEMENT
Firstly I Would Like To Thank PIYUSH JAWERIYA (Director, Pacific Institute Of
Technology) For Meticulously Planning Academic Curriculum In Such A Way That Students
Are Not Only Academically Sound But Also Technologically Ready By Including Such
Industrial Training Patterns.
I Express My Immense Pleasure And Deep Sense Of Gratitude To MR. NARENDRA SINGH
JI (Chief Engineer, archi buildmart) And All Workers Structural For Spending Their Valuable
Time With Me And Also Helped Me In Completion Of Task.
I Would Also Like To Acknowledge And My Heartfelt Gratitude To MRS. KETKI
MOONDRA (Head Of Department, Civil Engineering) & All The Faculty Of Civil
Department Who Continuously Supported Me In Every Possible Way, From Initial Advice To
Encouragement Till This Date.
Last But Not The Least; I Am Extremely Grateful To All The Technical Staff Of archi
buildmart pvt. Ltd Limited For Their Co-Operation And Guidance That Helped Me A Lot
During The Course Of Training. I Have Learnt A Lot Working Under Them And I Will Always
Be Indebted Of Them For This Value Addition In Me.
TABLE OF CONTENTS
Page No.
Acknowledgement
Abstract
ii
List of Tables
iii
List of Figures
iv
CHAPTER - I INTRODUCTION
Introduction of company
Site Clearance
Demarcation of Site
Positioning of Central
Excavation
PCC Plain Cement Concrete
LAYING OF FOUNDATION
CEMENT
LIST OF TABLES
Table
1
2
3
4
Title
Time Period of Formwork.
Vibrating Needle with Thickness.
Design Mix M20 Proportions.
Development Lengths of Steel Bars
and Its Weight.
Page No.
LIST OF FIGURES
Figure
Title
Page No.
1
2
3
3.1
Formwork of Column
RMC Roller
10
11
12
13
14
LIST OF ABBRIVIATIONS
SHORT TERM
FULL FORM
RMC
RCC
PVT
Private
MM
Mille Meters
DIA
Diameters
KG
kilo gram
HYSD
TMT
ABSTRACT
This Report Is A Summer Internship Report Submitted In Partial Fulfilment Of
Requirement For The Degree Of Bachelor Of Technology In Civil Engineering As Per
Norms Of Rajasthan Technical University, Kota. I visited On the Site of Bhumikesh
builders. For Construction Of The College Campus Structure, Aishwarya College At
New RTO Adarsh Nagar, Udaipur In My Training Period And Technical Knowledge
During The Course, After Which I Am Able Compile This Report. This Report Consist
Of Brief Study And Description Of Construction Of Column & Beam Slab Casting,
Brickwork, RMC,RCC, Steel Types, Formwork, Shuttering And Its Procedure Used At
Site For Construction Of An Interchange. I Have Put My Best To Elaborate The Actual
Site Conditions, And Problem Faced At Site And The Tactics Used To Deal With Them.
The Main Objective Of This Project Is To Construct The Accurate Structure By Using
Indian Standard Codes. The Report Also Covers The Fundamental Aspects Of Practical
Requirement Such As Safety, Feasibility And Economy At Site. In This Report The
Objective Was To Introduce, Wherever Necessary, Material Which Embodies The Most
Recent Methodologies.
CHAPTER I
INTRODUCTION OF COMPANY: Bhumikesh builders Is the Private Construction Company Which Is Situated After 2005
In Udaipur (Rajasthan).This Company Construct the Complexes and Residential
Buildings As well As Institutional Buildings.
This Company Construct The Buildings In Good Manner And Construct The Buildings
By I.S. Codes By Using Measured Amount Of Materials.
RUNNING PROJECTS OF COMPANY: The Running Projects Of This Company Is Construction Of College Campus With
Hostels Also, Which Is Going To Called New Aishwarya College Nearby New RTO,
Adarsh Nagar. The Land Area Of This Campus Is 13 Bighas Or 226930.08 Sq. Feet.
This Campus Is 4 Storey Building Consist Of the Three Blocks A, B, &C and Our
Hostels H1, H2, H3 &H4 Including Garden and Basket Court, Volley Ball Court.
Another Project Of This Company Is Behind DPS School Where The Residential
Building Is Constructing And The Building Is 6 Storey Including Different Area Land
Flats.
BUDGETS OF COMPANY: The Budget Of Aishwarya College Project Is Around 20-25 Crores Including All
Construction And Finishing Works.
CHAPTER II
PRESENT WORK:-
BRICK MASONRY: Masonry Is The Building Of Structures From Individual Units Laid In And Bound
Together By Mortar; The Term Masonry Can Also Refer To The Units Themselves. The
Common Materials Of Masonry Construction Are Brick, Building Stones Such As
Marble, Granite, And Limestone, Cast Stone, Concrete Block, Glass Block. Masonry
Is Generally Highly Durable Form Of Construction. However, The Materials Used, The
Quality Of The Mortar And Workmanship, And The Pattern In Which The Units Are
Assembled Can Significantly Affect The Durability Of The Overall Masonry
Construction. A Person Who Constructs Masonry Is Called A Mason Or Bricklayer. The
Ratio Of Cement And Sand Is 1:6 at site of The Aishwarya College. The Masonry
Commonly Used For the Wall of Buildings, Retaining Walls.
Timber;
Scaffold Tube with Adjustable Screw Jacks, Top or Bottom, Or Both;
SETTING UP FALSEWORK:
Base Must Be Level And Firm. A Sole Plate Is Preferable;
Props and Frames Must Be Placed As Per Design;
Place Props Centrally Under Members;
Brace False Work in Two Directions;
Floor Centres Must Have Full Bearing for the End Tongues;
Beams Must Be Centred Over Props To Prevent Eccentric (Out Of Line)
Loading.
FORMWORK: -
The Formwork Is The Term Given Either Temporary Or Permanent Moulds Into Which
Concrete Or Similar Materials Are Poured. In The Context of Concrete Construction, the
false work supports the Shuttering Moulds. The formwork shall be designed and
constructed so as to remain sufficiently rigid during placing and compaction of concrete,
and shall be such as to prevent loss of slurry from the concrete. Three General Principles
Govern Formwork Design And Construction:
Quality Accuracy of the Concrete Shape and the Final Finished Surface Quality.
Safety Strength of the Formwork Structure. Personal Safety of People, both
TYPES OF FORMWORK:
STAIR FORMWORK CONSTRUCTION: Sheathing Can Be Dressed Boards Laid Across Or Longitudinally Or Use
Sheet Material Such As Plywood Or Particle Board.
Dressed Boards May Have Sheet Material Fixed On Top To Prevent Loss Of
Grout.
Joists And Bearers Must Be Spaced To Avoid Undue Sagging Of Any Part Of
The Structure. Select Timber Carefully To Avoid Weaknesses Caused By Knots
Or Cross Grain.
Vertical Struts Must Have A Means Of Height Adjustment And Be Very
Securely Fixed To The Bearers To Prevent Sideways Movement.
Place and Fix Riser Boards Accurately. For Safety All Steps Must Be The
Same Size.
Ensure That All Reinforcing Steel Is Placed Exactly As Shown On The
Drawings. Misplacing the Steel, Particularly In depth, Can Alter the Strength of
the Finished Stair. Ensure Adequate Cover On Exterior Stairs.
Place Inserts for Balusters and Nosing Pieces as Required.
Striking: - As column and beam side formwork will be removed before beam
and slab soffit formwork, provision must be made for easy removal and in the
correct order. If beam and slab soffit formwork is to be removed before the
concrete has achieved working strength, permanent propping or shoring is
required. Take care to avoid damage to formwork which is to be re used. Eight
or more uses may be obtained from timber formwork.
Maintenance: - Clean forms with stiff brush and clean cold water. Use scrapers
only as a last resort. Keep forms well oiled to prevent delaminating of plywood
or rusting of steel and always oil the edges.
STRIKING TIME PERIOD OF FORMWORK: There Are Different Time Periods of Placing the Formwork Or Temporary
Supports to the Structure And This Time Periods Is Shown By the Upcoming
Table Which Is Followed as;
MINIMUM
S.NO.
TYPE OF FORMWORK
TIME PERIOD
BEFORE
STRIKING
FORMWORK
1
2
16-24 Hours
3 Days
Removal Of Formwork).
Soffit Formwork To Beams (Props Refixed Just
7 Days
7 Days
14 Days
a) Spanning up to 6 m.
b) Spanning over 6 m.
14 Days
21 Days
SHUTTERING:-
Deduct The Thickness Of Beam Soffit Depth Of Joist And The Depth Of Bearer
From The Overall Height. This Provides The Height to Set Steel Props and Other
False Work Support Systems.
Adjust The False Work Systems To Lengths Determined From The Story Rod.
Assemble and Position Props, Adjustable Head Jacks, False Works, Bearers and
Spreaders
This Task Normally Involves Working In Pairs. It Is Important To Bear In Mind
the Safety Required To Assemble Props And Temporary Support Systems. Often
Continuous Or Mobile Scaffolding Are Used To Help Erect The False Work System.
Lay Out Lengths Of Bearers On Each Side Of The Columns. Joints Should Be
Staggered.
Position The Scaffold At Each End Of The Bearer.
Carefully Position Bearers into the Centre of Prop or False Work U Head. Use
Centralising Packers Nailed To U Head.
Repeat This Procedure On The Other Side.
Plumb Supports Both Ways And Nail Spreaders At Each End Hard Against the
Column Face. This Is To Prevent Movement.
Secure Props And False Work At U Head And Sole Plate.
Place Spreaders in Position at Required Spacing.
Position, Plumb And Fix Intermediate Props.
Sole Plates Are Bedded Firmly And Positioned Central To The Bearer.
All Bearer Supports Are Plumb.
Bearer Joins Are Supported.
Bearers Are Seated Centrally In U Heads.
Supports Spaced As Specified and Are Firmly Fixed At the Head and Bearing
Plate.
All Supports Are Horizontally and Diagonally Braced.
FIXING THE SHEETING: If Using Form ply For Sheeting, Its Important to Avoid Damaging the Edges of
sheets.
R.C.C.:
concrete;
Concrete Structure;
Explain The Points To Be Remembered In Removing Of Form Work Used In
STEPS OF PLACING REINFORCED CEMENT CONCRETE: The RCC Is Just Placed After The Procedure Of Shuttering, Formwork, False
Work,
Centring.
After The Work Of Reinforcement Works Like Placing The Steel Grids.
It Is Also Placing After the Placing the Cover Blocks To the Slabs.
It Can Be Placed By Manually As Well As By Machinery Also.
WHY USE RMC: - Concrete, In Its Freshly Mixed State, Is A Plastic Workable
Mixture That Can Be Cast Into Virtually Any Desired Shape. The Properties Of
Concrete Can Be Customized For Almost Any Application To Serve In Wide Variety Of
Extreme Environments. Concrete Is A Very Economical Building Material That Can
Serve Its Function For Several Years With Minimum Maintenance, Provided With
Proper Mixture Relative To The Application And Established Construction Practice Are
Used. A Wide Variety Of Options With Colour, Texture And Architectural Detail Are
Available To Enhance The Aesthetic Quality Of The Concrete Application.
HOW TO ORDER RMC: - For Ordering The RMC, The Area Is Required Where
It Is To Be Placed. In The Procedure To Order RMC The Aggregate Size And Its Type,
Amount And Type Of The Admixture, Amount Of Sand: Cement: Water And The Main
Important Thing Is Proportion Of The Grade Of Cement. The One RMC Roller Is Cover
The 12 Cubic Yards Or It Covers The Area Of 6 Cubic Meters.
CASTING OF SLAB, BEAM AND COLUMN: For Casting of Slab, Beam Or Column, There Is A Requirement Of Form Work, Which
Should Be Covered From Four Sides To Retain The Concrete. For Casting Of Slab,
Shuttering Is Also Required. Form Work and Shuttering Are Done By Plywood or Steel
Plates (Panels) Where An Arch Is Provided In Wall. Form Work Is Done According To
the Curve of the Arch, Which Is Known As Centering The Wooden Planks or Steel
Panels Used As Mould, In Which Concrete Is Poured And The Stand Of Ballies
(Bamboos) Or Steel Posts Is Known As Shuttering. It Is Provided Till Concrete Get
Hardened To Bear Loads. The Diameter of Ballies Should Not Be Less than 100 Mm
and At Extreme 80 Mm. Ballies Should Be Provided At The Distance of the Column
and Should Be Placed Straight. Wooden Planks of Size 40 40 Cm. are Provided at The
Bottom of Ballies. The Following Figure Gives The Description About The Horizontal
Shuttering And The Steel Plates Are Used For Making The Surface Of The Roof And
The Steel Plates Are Used To Fill The Concrete In It That The Steel Plates Can Resist
The Concrete And The Shuttering Can Resist The Moisture And Hold The Ratio Of
Water. The Plates Are Provided To The Beams & Columns And These Plates Are
Differently Provided To The Different Spaces For Placing The Concrete And Steel
Plates Hold The Column As Well.
2. JOINT THE CONCRETE PIPES: - First Steps Is That Before The Rmc
Roller Will Arrived On The Site, The Concrete Pipe Can Joint Or Attached To Each
Other And Will Connect To The Concrete Pump So That The Material Can Push By
The Pump And Can Send The Material To The Upper Part Of The Roof Where The
Concrete Is To Be Placed. And Check The Pipe After Attaching By Pushing The
Material That The Joint Is Responding Correctly.
WALL THICKNESS
(mm)
(mm)
25
1.5
35
1.5
40
1.5
50
2.0
60
2.5
75
3.0
90
3.0
The
Cement Is Very Important Material For Any type Of Construction Because It Has The
Good Property Of Binding The Material And Aggregate Is One Of The Most Important
Material Which Provides Strength To The Concrete And Any Structure Also.
QUANTITY OF MATERIAL
335 Kg
Aggregate - 10 Mm
740 Kg
Aggregate - 20 Mm
River Sand
480 Kg
830 Kg
Water
180 Litters
2 Litters
WEIGHT OF STEEL
DEVELOPEMENT
IN
BAR IN KG (FOR 1
LENGTH IN MM
MM
METER)
50 D
d2
length
162
8 MM
10 MM
12 MM
16 MM
20 MM
25 MM
32 MM
.395 KG
.617 KG
.890 KG
1.58 KG
2.46 KG
3.85 KG
6.32 KG
400 MM
500 MM
600 MM
800 MM
1000 MM
1250 MM
1600 MM
CHAPTER III
RESULTS AND DISCUSSIONS: Results - The Results Is That Block B1, B2 With 2 Storey Has Prepared Two
Blocks With Brickwork, Beam, Column And Plastering By Correct
Measurement Amount Of Materials. The Correct Ratio Is Used In Brickwork,
Column Filling, In Plastering Wall Also. The 3 Slab Is Casting With Material
during Our Training Period.
Discussion - The Only Discussion Is Made That The Site Engineer Was
Discussed That The Construction Work Is Little Slower. I Think That The
Engineer Is Right That Way Because The Labour Is Less Present And
Insufficient. That Is Why The Work Is Going Delay Day By Day During Our
Training Period.
CHAPTER IV
CONCLUSION & FUTURE WORK: -
Future work The Future Work Is That The Remaining 1 Block Which Is
Block A And Three 4 Hostels Will Construct With 4 Storey Floors And Other
Two Blocks B&C Will Complete One Floor More And C Will Have Complete 2
Floors With All Type Of Works Like Plastering, Furnishing, Flooring, Walls,
Furniture.
REFERENCES:
google.co.in
Is 456:2000
NRMCA