Professional Documents
Culture Documents
< 5 MW
<10 MW
< 15 MW
< 20 MW
< 20 MW
< 25 MW
< 25 MW
<30 MW
< 30 MW
< 50 MW
< 50 MW
In India, Small Hydro schemes are further classified by the Central Electricity authority
(CEA) as follows:
Classification of Micro, Mini, & Small Hydro Schemes in India.
Type
Micro
Mini
Small
Station Capacity
Upto 100 KW
101 KW to 2000 KW
2001 KW to 25000 KW
35
Unit rating
Upto 100 KW
101 KW to 1000 KW
1001 KW to 5000 KW
Number of
stations
Installed capacity
(MW)
Annual output
(GWh)
Guangdong
6,525
3,576
11,928
13.6
Sichuan
4,395
3,529
13,933
13.4
Fujian
5,096
3,057
11,540
11.6
Yunnan
1,904
2,250
9,614
8.6
Hunan
4,615
2,033
7,198
7.7
Zhejiang
2,738
1,873
4,693
7.1
Hubei
2,292
1,466
3,670
5.6
Guangxi
2,547
1,407
5,061
5.4
Jiangxi
3,965
1,180
3,301
4.5
Guizhou
1,154
958
3,657
3.6
Chongqing
1,061
839
2,851
3.2
Xinjiang
525
662
2,114
2.5
Shaanxi
2,158
453
1,037
1.7
Gansu
467
363
1,299
1.4
Henan
735
318
552
1.2
Hebei
195
317
304
1.2
36
Stateowned
Community- Individual
based
4,483
13,175
1,113
19.7
58.0
4.9
Share- Other
holding
Total
7.5
100.0
government gives grants of RMB 300 million (US$36 million) to the 400 Rural
Electrification Counties annually, and the soft loans account for 38% of the total investment
for this. This offers local developers different sources for funds, as Table 6 shows.
TABLE 6. Investment sources for SHP station construction
Sourcesa
National input (RMB
million)
Percentage (%)
State
inputb
Bank's
loan
Foreign
investment
Local Others
input
3,017
11,093
236
4,975
14.1
52.0
1.1
23.3
Total
2,035 21,356
9.5
100.0
The investment sources are the composition of the construction fund for the project owner
State input comprises state investment, Special Hydro Power Infrastructure Fund, and
Agriculture & Water Allowance
the national grid at a certain point to make full use of the seasonal power and to get more
benefits.
39
India has an estimated small hydro potential of about 15,000 MW. Out of this total potential
of small hydro identified so far, is 10,265 MW through 4278 sites. As on 31.03.2005, 523
small hydro projects (up to 25 MW) with an aggregate capacity of 1705 MW have been
installed. Besides these, 205 projects with total capacity of nearly 480 MW are under
construction. State wise identified small hydro projects are given in table-1.
Target capacity addition
Tenth plan (2002-07)
: 600 MW
: 2000 MW
Table-1
State wise identified Small Hydro Projects in India (Up to 25 MW Capacity)
Sl no.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
State
Andhra Pradesh
Arunachal Pradesh
Assam
Bihar
Chhattisgarh
Goa
Gujarat
Haryana
Himachal Pradesh
Jammu & Kashmir
Jharkhand
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Manipur
Total
No.
377
452
40
74
47
4
287
23
288
208
89
221
207
85
221
99
40
Capacity (MW)
250.50
243.47
119.54
149.35
57.90
4.60
186.37
36.55
418.68
294.43
170.05
534.76
455.53
336.33
484.50
91.75
17
18
19
20
21
22
23
24
25
26
27
28
29
Meghalaya
Mizoram
Nagaland
Orissa
Punjab
Rajasthan
Sikkim
Tamil Nadu
Tripura
UT( A&N Islands)
Uttar Pradesh
Uttaranchal
West Bengal
Total
90
53
84
206
122
55
70
155
10
5
211
354
141
4278
197.32
135.93
149.31
217.99
124.22
27.82
214.33
373.46
30.85
1.15
267.06
1478.24
213.52
10,265.45
11. Small hydro does not require much expertise to build and operate. Components of
small hydro projects are so simple and fairly visible at site distinctively that they can
become centre of education.
12. Capital investment is less in compared to others scheme such as thermal as well as big
hydro.
13. On the basis of project life cycle cost in real terms, inflation- free small hydro
becomes several times cheaper than thermal option due to cheaper operational cost
and zero cost input.
14. Under Kyoto Protocol, the Small Hydro Project can earn extra revenue through Clean
Development Mechanism (CDM).
IMPEDIMENTS OF SMALL HYDRO
Despite the fact that various incentives are available from IREDA, UN and MNES for
development of the small hydro power schemes, the momentum for their development is less
due to following reasons:
Low load factor and revenues:
Majority of small hydro projects are located in remote places and not connected with the grid
and in general stand alone power stations. Therefore, transmission of the surplus power to
other places is not possible. Accordingly, they can fulfill the need of local area only. Incase,
the demand is less, then the power station will continue to run at the reduced load i.e at low
load factor and thereby loss in power generation which in turn result in poor revenue
collection.
Operation and Maintenance Cost:
Inaccessibility of the small hydro plants due to poor transport and communication, the
adequate support of operation and maintenance for this power station is not available. Another
factor due to which operation & maintenance is very high is that design of such power
stations is based on inadequate hydrological and geological data which lead to frequent
damages to the structures.
Insufficient management for the operation:
Due to remoteness, the technical and management skill of local is not sufficient for operation
of the power plants. Therefore, lot of training is to be provided to the managerial and
operational staff.
Inadequate Quality and performance:
The quality of small power stations is not as good as of bigger power stations as these power
plants are generally designed on the basis of short term raw data. Thus the ground conditions
of operation are much different from the conditions taken for design. Due to such differences
the quality and performance of equipment becomes a constraint.
42
The tariff:
The methodology adopted for tariff in case of small hydro is the same as in Mega Hydro,
which is not reasonable.
Low interest of Private Developers:
Private developers avoid to have a stake in small hydro because they are firstly afraid whether
they will be able to generate electricity commensurate with the predicted Hydrology. And
secondly, once commissioned there is no surety of a buyer at a rate that is comparable to the
outcome of the investment he has put.
Statutory clearances:
Various clearances like forest clearances, defense clearances, environmental clearances; land
acquisition etc. given by different ministries takes one to two years time. A single window
statutory clearance should be provided or State Govt. should get these clearances beforehand
and then only entrusted these projects for execution.
Transmission lines:
The major impediment to majority of SHP stations is non-availability of high voltage
transmission lines resulting in heavy line losses wherever the load centers were spaced far
apart.
Financing Small Hydro:
IREDA (Indian renewable Energy Development Agency), World Bank, Asian Development
Bank and Japan Bank for international cooperation etc. finance small hydro projects. Govt.
encourages private sectors for their participation in development of small hydro power.
CONCLUSION
For a power starved country like India, it is important that all the sources of power be tapped
optimally and viably. Small hydro, being a very good source of renewable energy and India is
having vast potential of Small hydro i.e. 15,000 MW, its development must be given due
importance. This in turn help in capacity addition to the hydro power generation and shortage
of electricity can be avoided to some extent. MNES is launching a programme for
electrification of remote and inaccessible village through Small Hydro Power projects. This
will improve the living condition as well as economic condition of the people in the areas and
overall development of the country.
43