Professional Documents
Culture Documents
+
Design/Bid/Build
Two
Three
Design-Build
(General Contracting)
Construction
Management
Agency
Design/Bid/Build
Four
Construction
ManagementAt Risk
Construction
Design-Build Management-Agency
Construction
Management-At Risk
Design/Bid/Build
In Design/Bid/Build, also known as the
general contracting project delivery method,
the process is linear, where one phase is
completed before another phase is begun.
Under the design/bid/build example, the
architect is selected under a separate
contract that is based on a negotiated
professional fee. The construction firm is
most often selected based on the lowest bid,
and there may be many subcontractors
under his contract/direction.
Design-Build
Owner
Architect/
Engineer
General
Contractor
Contractor is competitively
bid per the Public Bid Laws.
Subcontractors
Month
26 Months
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Phase
Programming
Programming
Schematic Design
Schematic Design
Design Development
Design Development
Construction Documents
Constructability Review
Construction Documents
Construction
Construction
Occupancy
Disadvantages
Architect/Engineer
Subcontractors
20 Months
Time Savings
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Occupancy
Disadvantages
Advantages
Advantages
Design-Builder
Traditional method
Owner
CM-At Risk
Owner
The Primer
Construction
Manager
Subcontractors
Time
Savings
24 Months
CM-Agency
In the CM-Agency (CMa) project delivery method, also known as Pure CM, the construction manager acts as an
extension of the owners staff and the general contractor role is eliminated. In this scenario the owner, rather than the
general contractor or construction manager-at risk, holds all subcontracts. Essentially, each subcontractor becomes a
prime contractor and is responsible for cost, schedule, quality, and safety on the project. The construction manager
oversees these tasks in the role as a consultant. The construction manager competitively bids the different elements of
construction to trade contractors (or subcontractors), such as electrical, mechanical, plumbing, framing, etc.
Pre-Construction Services
Estimating
Value Analysis
Quality Control Review
Spec Review
Design Development
Construction Documents
Construction
Balance of Phased Bid Packages
Occupancy
Architect/Engineer
Construction
Manager
Project Completion
Disadvantages
Disadvantages
Advantages
Subcontractors
Advantages
Programming*
Schematic Designs
Owner
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Month
Architect/Engineer
The CM - At Risk (CMc) method of project delivery is increasingly being utilized by private and public sector clients,
since it blends assessment of pricing, scheduling and qualifications while limiting the owners risk. This method features a
cohesive three-party team of owner, separate architect-designer, and the construction firm serving as construction manager.
Under separate contracts, both the architect-designer and construction manager are chosen via the qualifications-based
selection process.
The CMc firm enters into a GMP contract with the owner, which assures the project will be constructed for no more
than the amount designated in the signed contract, and no longer than the agreed completion date. Utilizing a GMP
provides peace of mind to the owner, since any budget overruns on the contracted scope of work in excess of the GMP is
assumed by the CMc. If the project is delivered below the GMP, cost savings are typically shared between the owner and
the CMc.
Getting past budget concerns allows the project to proceed with regular open communication and the knowledge that
the CM always has the owners best interests in mind. A previously established scope of work designates pre-construction
services, such as estimating, scheduling, constructability reviews, value analysis, specification review, and quality control
review, that save the owner both time and money.
Vendors and subcontractors can be pre-qualified based on bonding, experience and performance requirements. In the
case of public sector projects, this exercise can greatly enhance the participation by local suppliers and subcontractors who
will be included in the competitive bidding. Contracts with the subcontractors and vendors are then held with the CM firm,
who assumes responsibility for their performance.
CM-At Risk
Owner
The Primer
Construction
Manager
Subcontractors
Time
Savings
24 Months
CM-Agency
In the CM-Agency (CMa) project delivery method, also known as Pure CM, the construction manager acts as an
extension of the owners staff and the general contractor role is eliminated. In this scenario the owner, rather than the
general contractor or construction manager-at risk, holds all subcontracts. Essentially, each subcontractor becomes a
prime contractor and is responsible for cost, schedule, quality, and safety on the project. The construction manager
oversees these tasks in the role as a consultant. The construction manager competitively bids the different elements of
construction to trade contractors (or subcontractors), such as electrical, mechanical, plumbing, framing, etc.
Pre-Construction Services
Estimating
Value Analysis
Quality Control Review
Spec Review
Design Development
Construction Documents
Construction
Balance of Phased Bid Packages
Occupancy
Architect/Engineer
Construction
Manager
Project Completion
Disadvantages
Disadvantages
Advantages
Subcontractors
Advantages
Programming*
Schematic Designs
Owner
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Month
Architect/Engineer
The CM - At Risk (CMc) method of project delivery is increasingly being utilized by private and public sector clients,
since it blends assessment of pricing, scheduling and qualifications while limiting the owners risk. This method features a
cohesive three-party team of owner, separate architect-designer, and the construction firm serving as construction manager.
Under separate contracts, both the architect-designer and construction manager are chosen via the qualifications-based
selection process.
The CMc firm enters into a GMP contract with the owner, which assures the project will be constructed for no more
than the amount designated in the signed contract, and no longer than the agreed completion date. Utilizing a GMP
provides peace of mind to the owner, since any budget overruns on the contracted scope of work in excess of the GMP is
assumed by the CMc. If the project is delivered below the GMP, cost savings are typically shared between the owner and
the CMc.
Getting past budget concerns allows the project to proceed with regular open communication and the knowledge that
the CM always has the owners best interests in mind. A previously established scope of work designates pre-construction
services, such as estimating, scheduling, constructability reviews, value analysis, specification review, and quality control
review, that save the owner both time and money.
Vendors and subcontractors can be pre-qualified based on bonding, experience and performance requirements. In the
case of public sector projects, this exercise can greatly enhance the participation by local suppliers and subcontractors who
will be included in the competitive bidding. Contracts with the subcontractors and vendors are then held with the CM firm,
who assumes responsibility for their performance.