FUTURE RUNWAY 9C/27C AND

OTHER AIRFIELD PROJECTS


UPDATES ON KEY AIRFIELD PROJECTS FROM
JANUARY 2016 AGREEMENT

19

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

AirlineSupport
Facilities

GroundRunUp
Enclosure

NewEastAirfield
LightingVault

ARFF #2Relocation
TankFarmRoad

ATSLotEStation
Demolition

Runway9C/27C

VOR
CentralizedDeicing
Facility

TaxiwaysAandB
CrossfieldTaxiway
System

20

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RUNWAY 9C/27C PACKAGES


Package1
Areas

TWZJ&Tank
FarmRoad

Package2Area

Package3Area

9C/27CEast
Package

Siteconstraintsandrelocationofexistingfacilitiesrequirethe
constructionofRunway9C/27Cinfourmainpackages
Furtherdefinitiontothesepackageswillbedevelopedinthenextfew
months
Note,projectsaresubjecttochange

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

21

CENTRALIZED DEICING FACILITY AND


CROSSFIELD TAXIWAY SYSTEM - DESIGN
General Description
Design of a new centralized deicing facility
on the west side of the airport including a
new crossfield taxiway system. Services
may include, predesign, preliminary,
detailed and final design, as well as
construction phase services. This facility
is expected to include pavement areas,
storm drainage and spent deicing fluid
collection, airfield lighting and signage,
facilities for the operations, storage and
dispensing facilities for deicing fluids and
control systems for the management of
the deicing operations.

ActualAdvertisingDate

July12,2016

EstimatedValue

N/A
22

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RELOCATION OF TAXIWAYS A&B - DESIGN


General Description
Design of the partial relocation of
taxiways A&B in the terminal core..
Services may include, predesign,
preliminary, detailed and final design, as
well as construction phase services.
The design of the relocation of these
two taxiways will require close
coordination with airline and airport
operations to ensure minimum impacts
to aircraft movements as well as
existing infrastructure in the project
area.

AdvertisingDate

July12,2016

EstimatedValue

N/A
23

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RUNWAY 9C/27C &


OTHER AIRFIELD PROJECTS

OMP Phase2 ARFF#1Expansion


Runway9C/27CPackages
AirlineSupportFacilityDemolition
AirlineSupportSitePreparation
ATSLotEStationDemolition
EastAirfieldLightingControlVault
ARFF#2Reloation
TankFarmRoadPhase2
GroundRunupEnclosureRelocation
VOR RelocationSitePrep(FAA)
24

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

ARFF #1 MODIFICATIONS - CONSTRUCTION


General Description
This is a Runway 10R/28 enabling
project being rebid. It consists of
10,800 SF addition to the existing ARFF
#1 Facility. The facility will contain 3
bays for apparatuses and equipment
and other functions on the ground floor
totaling 7,700 SF and 3,100 SF on the
second story for dormitory space for
firefighters in the facility. Construction
is within the Airfield Operating Area.
Project will be delivered as DesignBid
Build

AnticipatedAdvertisingDate

3rdQuarter2016

EstimatedValue

$4 $9million
25

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

ARFF#2 RELOCATION - CONSTRUCTION


General Description
Construction of a replacement on
airport aircraft rescue and fire fighting
station (ARFF) on the north east side of
the airfield.
Construction will be
located airside. Structure will be single
story with a mechanical mezzanine,
with 6high bay apparatus bays.
Project will be delivered through
conventional DesignBidBuild

AnticipatedAdvertisingDate

4thQuarter2016

EstimatedValue

$1525 million
26

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

GROUND RUN-UP ENCLOSURE - CONSTRUCTION


General Description
Construction of a replacement pre
fabricated runup enclosure.
Work
includes
disassembling
existing
structure,
demolishing
existing
foundation and restoring site with PCC
pavement, construction or new
foundation, site preparation, electrical
and lighting improvements.
Project may be delivered through
designbuild services

AnticipatedAdvertisingDate

4thQuarter2016

EstimatedValue

$25 million
27

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

EAST AIRFIELD LIGHTING VAULT - CONSTRUCTION


General Description
Construction of a new airfield lighting
vault (similar to the south vault)
housing the switchgear, ALSC and
regulators needed to power the airfield
lighting and signage for Runway 9C/27C,
Runway 9R/27L and associated
taxiways.
Site for this facility will be adjacent to
the ARFF #2 on the north east of the
airfield.
Project will be delivered as designbid
build.
AnticipatedAdvertisingDate

4thQuarter2016

EstimatedValue

$15 $25 million


28

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

TANK FARM ROAD AND TWY S&J - CONSTRUCTION

ProjectArea

AnticipatedAdvertisingDate

4thQuarter2016

General Description
Construction of an extension of Tank Farm
Road and new Taxiways S and J on the west
side of the Airport. The total roadway
length is anticipated to be approximately
3,600 feet long. Construction involves
earthmoving, excavation, embankment,
placement of base materials, sediment and
erosion control, electrical and lighting,
storm drain pipe and structures, building
structure demolition, seeding, and other
miscellaneous improvements.

EstimatedValue

$45 $55 million


29

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RWY 9C/27C PACKAGE 1 - CONSTRUCTION


General Description
Construction of approximately 201K SY of
PCC pavement, and placement of
approximately 85K SY of asphalt concrete
pavements.
Earth moving, excavation,
embankment, placement of base materials,
sediment and erosion control, electrical and
lighting, storm drain pipe and structures,
building structure demolition, seeding, and
other miscellaneous improvements.

Package1Area

AnticipatedAdvertisingDate

2Q2017

EstimatedValue

$100 $150 million


30

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

CENTRALIZED DEICING FACILITY - CONSTRUCTION


General Description
Development of a (a) Centralized Deicing
Facility west of the terminal core. The
overall development include aircraft ramp
area, taxiway connectors, guidance
system, storm drain collection system,
marshaling areas, operation buildings,
airfield lighting and signage. Pavement
area is expected to be approximately 240K
SY. This project also includes (b)
Construction of ADG VI (Large Aircraft)
Crossfield taxiway system connecting the
north and south airfields.

(b)
(a)

AnticipatedAdvertisingDate

2ndQuarter2017

EstimatedValue

$80 $120million
31

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RWY 9C/27C PACKAGE 2 - CONSTRUCTION


Package2Area

General Description
Construction of approximately 510K SY of
PCC pavement, and placement of
approximately 270K SY of asphalt concrete
pavements.
Earth moving, excavation,
embankment, placement of base materials,
sediment and erosion control, electrical and
lighting, storm drain pipe and structures,
building structure demolition, seeding, and
other miscellaneous improvements.
Project will be delivered as DesignBidBuild.

AnticipatedAdvertisingDate

1stQuarter2018

EstimatedValue

$300 $350 million


32

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RELOCATION OF TAXIWAYS A&B - CONSTRUCTION

General Description
Partial relocation of two terminal
perimeter taxiways. Final configuration
is subject to be defined through design.
Anticipated scope includes replacement
of 190K SY of PCC pavement.

AnticipatedAdvertisingDate

2ndQuarter2018

EstimatedValue

$80 $100million
33

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

RWY 9C/27C PACKAGE 3 - CONSTRUCTION


Package3Area

AnticipatedAdvertisingDate

General Description
Construction of approximately 150K SY of
PCC pavement, and placement of
approximately 82K SY of asphalt concrete
pavements.
Earth moving, excavation,
embankment, placement of base materials,
sediment and erosion control, electrical and
lighting, storm drain pipe and structures,
building structure demolition, seeding, and
other miscellaneous improvements.

1stQuarter2019

EstimatedValue

$100 $130 million


34

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

ATS LOT E STATION DEMOLITION - CONSTRUCTION


General Description
Scope includes the demolition of the
structure and platform of this station,
modification of wayside systems, power
systems and track work as required and
site restoration.
Construction will require coordination
with and limited interruption of services
of the Airports Transit System
Project may be delivered as designbid
build or design/build.

AnticipatedAdvertisingDate

4thQuarter2019

EstimatedValue

$10 $15 million


35

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

CAPITAL IMPROVEMENT PROGRAM (CIP)


OHARE PROJECTS

36

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

AMC BUILDING EXPANSION - CONSTRUCTION

General Description
Construction of a 88,500 square foot steel frame,
precast exterior walls equipment storage facility
at the corner of Montrose and Spine Road. All
associated mechanical, electrical, and fire
suppression systems are included in this
construction cost.
Services provided include; Construction, 10%
Construction Contingency, Construction Phase
Design Services, and Quality Assurance/Material
Testing.

OutforBid

BidsDueAugust 4,2016

ProjectedContractValue

$15 $17Million
37

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

REPLACEMENT OF HIGH TEMPERATURE


WATER GENERATORS - CONSTRUCTION
General Description
Replacement of all eight 75,000 MBH High
Temperature Water (HTW) Generators along with
their associated equipment. Equipment to be
replaced includes: HTW Generators, pumps, piping,
controls and power distribution systems. This
project also involves developing designs necessary
to replace the North High Temperature Water
(HTW) Pumps P4, P5 and P6. Additionally, the
scope includes upgrading the functionality of
existing piping crossconnections.

AnticipatedAdvertisementDate

3rdQuarter2016

ProjectedContractValue

$55 $60million
42

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

EMERGENCY STANDBY POWER SYSTEM


UPGRADE - CONSTRUCTION

General Description
The project scope of work includes complete
replacement of the Standby Power System located
at the H&R Plant. Including housing of the new
generators in a separate building adjacent to the
H&R Plant. This will be a new 18 MW system to
replace the current 5.2 MW system to
accommodate existing and future loads allowing for
future growth.

BidOpeningDate

August1, 2016

ProjectedContractValue

$25 $30million
39

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

TRUNK RADIO SYSTEM REPLACEMENT - RFP


General Description:
The proposed scope of work includes design,
construction and maintenance of a new 470 MHz
operations and 800 MHz public safety trunk radio
system to replace the existing systems installed in
2001 and 1990 respectively. This proposed hybrid
solution will be fully redundant with high voice quality
in both above ground, underground, and ring tunnel
locations providing service to the airport perimeter.
The public safety system shall have interoperability
with the Chicago Police and Fire Department radio
systems. Funding will cover design, equipment
purchase, installation, and all frequency licensing.
Scope of the RFP also includes a ten year
maintenance program*. (*Maintenance funded
separately) This request includes 10% construction
contingency and 2% for design/system validation.

AnticipatedAdvertisementDate

3rdQuarter2016

EstimatedValue

$6 $9million
40

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice

COMED DUCT BANK - CONSTRUCTION


General Description:
The existing Com Ed duct that provides primary
feeders to the Airport is original and has failed to
the point that replacement of cable is not possible.
The new duct will be made up of 9way and 18way
5 concrete encased duct connecting from near the
Runway 28R ALSF shelter to the D179 substation.
The duct will be installed primarily in the east lane
of Spine Road on the NS run and along the south
edge for the EW portion. A connection across
Mannheim Road will also be replaced.

AnticipatedAdvertisementDate

3rdQuarter2016

EstimatedValue

$2.5 $5million
41

Disclaimer Anyandallinformationcontainedhereinissubjecttochangewithoutnotice