Gosford Passing Loops Project

GPL-01-D&C

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Document Details
Submission information
This document and its contents have been prepared by Downer and are intended solely for
Transport for New South Wales (TfNSW) information and use in relation to the Gosford Passing
Loops (GPL) Project.

Document Preparation & Control

Document Review

Elisha Howells Quality Officer

Sheree Jones Quality Manager GPL

Document Approval

Signature

David Burkitt Project Director

Revision Status
Rev

Date

28-03-13

Associated documents

Document Number

Downer EDI Limited


ABN 66 008 709 608

Title

Revision

Date

www.downergroup.com
Page 2

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

TABLE OF CONTENTS
terms and definitions ________________________________________________________________________ 5
1 introduction _____________________________________________________________________________ 7
2 purpose of the quality management plan (QMP) __________________________________________ 8
3 project description _______________________________________________________________________ 9
3.1 operational project purpose ________________________________________________________ 9
4 project milestones ______________________________________________________________________ 11
5 management representative ____________________________________________________________ 13
6 quality document control _______________________________________________________________ 14
6.1 introduction document control _____________________________________________________ 14
6.2 document storage ________________________________________________________________ 14
6.3 plan review _______________________________________________________________________ 14
6.4 revisions and amendments _________________________________________________________ 15
6.5 qmp submission ___________________________________________________________________ 15
6.6 control of quality records __________________________________________________________ 15
7 communicating the qmp _______________________________________________________________ 16
8 qmp references ________________________________________________________________________ 17
8.1 general ___________________________________________________________________________ 17
8.2 legal and regulatory _______________________________________________________________ 17
9 downer australia integrated management system (IMS) ___________________________________ 18
9.1 structure of the IMS ________________________________________________________________ 18
9.2 audit of the ims____________________________________________________________________ 19
10 project quality objectives, organisation & resources _______________________________________ 20
10.1 introduction _______________________________________________________________________ 20
10.2 quality management objectives ___________________________________________________ 20
10.3 project organisation chart _________________________________________________________ 21
10.4 project responsibilities______________________________________________________________ 21
11 project administration ___________________________________________________________________ 26
11.1 project filing and storage system ___________________________________________________ 26
11.2 project meetings, reviews and reports ______________________________________________ 26
11.3 construction programme __________________________________________________________ 26
11.4 control of drawings and specifications ______________________________________________ 26
11.5 managing variations _______________________________________________________________ 26
12 internal audits and planned inspections __________________________________________________ 27
12.1 project audits _____________________________________________________________________ 27
13 purchasing _____________________________________________________________________________ 28
13.1 suppliers and subcontractors _______________________________________________________ 28
13.2 site induction and training _________________________________________________________ 29
13.3 plant and equipment ______________________________________________________________ 29

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 3

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
14 product and service control _____________________________________________________________ 30
14.1 project control documentation ____________________________________________________ 30
14.2 product identification and traceability ______________________________________________ 30
14.2.1
Identification ______________________________________________________________ 30
14.2.2
Traceability _______________________________________________________________ 30
14.3 handling and storage of construction materials _____________________________________ 30
14.4 inspection and test equipment _____________________________________________________ 30
14.5 control of non-conforming materials or work ________________________________________ 31
14.6 design control _____________________________________________________________________ 31
15 inspection and testing __________________________________________________________________ 32
15.1 itp compliance ____________________________________________________________________ 32
15.2 control and storage of itps ________________________________________________________ 32
15.3 management of itps ______________________________________________________________ 32
15.4 principal itp requirements __________________________________________________________ 32
15.5 development of itps ______________________________________________________________ 32
15.6 management of itps and lot checklists _____________________________________________ 33
15.7 hold points and witness points ______________________________________________________ 33
15.8 non-conformances ________________________________________________________________ 33
16 cleaning and protection of work_________________________________________________________ 34
APPENDIX A: IMS ACCREDITATION CERTIFICATES _______________________________________ 35
Appendix B: DOWNER AUSTRALIA BUSINESS POLICY ____________________________________ 36
Appendix C: HOLD AND WITNESS POINT REGISTER ______________________________________ 37
Appendix D: AUDIT AND REVIEW SCHEDULE ___________________________________________ 38
Appendix E: INDEX OF QUALITY PROCEDURES AND FORMS _____________________________ 39

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 4

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

TERMS AND DEFINITIONS


Term or
Acronym

Definitions

CAR

Acronym for Corrective Action Request (CAR) is raised when a process or


service is not performed in accordance with specified requirements resulting
in a failure of the process, service or product. Corrective action may result
from an incident or from findings during an audit.

CEMP

Acronym for Construction Environmental Management Plan

CMP

Acronym for Contract Management Plan identifies how DA will deliver all
requirements within contract GPL-01-D&C. The plan provides an overview of
all of the management plans that will be developed and executed for the
duration of the project.

CLP

Acronym for Community Liaison Plan

CoA

Acronym for Conditions of approval

Compliance
audit

Verification of how implementation is proceeding with respect to a


construction environmental management plan (CEMP) (which incorporates
the relevant approval conditions).

CSMP

Acronym for Construction and Site Management Plan

DA-QA-FM

Document code for Downer Australia Quality Management Form

DA-QA-PR

Document code for Downer Australia Quality Management Procedure

DA-QA-RG

Document code for Downer Australia Quality Management Register

DA-QA-RI

Document code for Downer Australia Quality Management Record

DA-QA-TR

Document code for Downer Australia Quality Management Training


Resource

DirectorGeneral

Director-General of the NSW Department of Planning and Infrastructure (or


delegate)

DMP

Acronym for Design Management Plan

Downer

Downer Australia

DP&I

Acronym for Department of Planning and Infrastructure

EMP

Acronym for Emergency Management Plan

GCC

Acronym for Gosford City Council

Hold Point

Those points identified within the applicable Inspection and Test Plan,
beyond which the stated activity must not proceed within approval to
proceed from the nominated authority.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 5

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Term or
Acronym

Definitions

IMS

Acronym for Integrated Management System

Lot Checklist

Checklist to record performance and outcomes of project inspections and


testing

ITP

Acronym for Inspection and Test Plan.

Noncompliance

Failure to comply with the requirements of the Project approval or any


applicable license, permit or legal requirements.

Nonconformance
(NCR)

Failure to conform to the requirements of Project system documentation


including this CEMP or supporting documentation.

NSFC

Acronym for Northern Sydney Freight Corridor

NCR

Acronym for Non Conformance Report

Plan

A document setting out the specific practices, resources, activities and


responsibilities relevant to a particular project or contract.

Principal, the

The Project Principal Transport for NSW

Project, the

The Gosford Passing Loops Project

QA

Acronym for Quality Assurance. It refers to the planned and systematic


activities implemented under the Quality Management Plan.

QMP

Acronym for Quality Management Plan

REF

Acronym for Review of Environmental Factors, environmental assessment


prepared under Part 5 of the EP&A Act.

Stakeholders

Key Project Stakeholders.

SWMS

Acronym for Safe Work Method Statement

TfNSW

Acronym for Transport for NSW

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 6

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

1 INTRODUCTION
The Northern Sydney Freight Corridor (NSFC) Program is an initiative to improve capacity and
reliability for freight trains on the Main North Line between Sydney (Strathfield) and Hexham, west
of Newcastle.
The program is designed to:
Improve freight train access through northern Sydney
Relieve a serious bottleneck on the rail network
Create a more efficient freight rail network
Improve the reliability of passenger services on the Main North Line
Enable freight access during peak times
The Gosford Passing Loops project (the Project) is one of four projects as part of the wider NSFC
Program.
In October 2012, the Project was approved by the Deputy Director General Transport Projects,
Transport for NSW subject to Conditions of Approval (CoA).
In January 2013, Transport for NSW (TfNSW) appointed Downer EDI as the design and construct
contractor for the project.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 7

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

2 PURPOSE OF THE QUALITY MANAGEMENT PLAN (QMP)


This Quality Management Plan (QMP) identifies the project specific management structure,
resources, procedures and practices that Downer will implement for the following project:
Contract Number: GPL-01-D&C, Gosford Passing Loops
These controls will provide for the management of all issues relating to the quality of work and
delivery of the project.
This QMP has been developed to satisfy the technical requirements of the Contract and the
requirements outlined within TfNSW Standard Requirements (TSR Q1 Quality Management).
The development and execution of the QMP is guided by and complies with the Downer Australia
Integrated Management System (IMS). The IMS satisfies required international and national
standards, specifically AS/NZS ISO 9001:2008 and includes all of the Downer Australia quality
documentation.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 8

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

3 PROJECT DESCRIPTION
The Project comprises the construction of two electrified passing loops and associated
infrastructure north of Gosford Station to allow for the passing of faster passenger trains while
freight trains are held on the mainline or in the reverse arrangement as deemed necessary.
The Project comprises two new tracks for the passing loops (and associated overhead wiring, civil
and structural works) between Gosford and Narara stations. The total new track length would be
approximately 4 kilometres (km) (approximately 2 km for both the Up and Down Refuges). The
new tracks would be constructed on the outside of the existing rail tracks and would generally be
accommodated within the existing rail corridor boundary (with the exception of a short section of
track between chainages 82.40 km and 82.70 km, which would require the eastern corridor
boundary to be widened by up to approximately 3 metres to facilitate the construction of the
track and other railway infrastructure).
The key features of the GPL include:
Three new pairs of bridges (six bridges in total) over Bradys Gully, Wingello Creek and Wyoming
Creek, adjacent to the existing rail bridges.
One new crossover on the Up Main (adjacent to Brooks Avenue, Wyoming, between chainages
83.50 km and 83.80 km) and one new turnout on the Down Refuge (adjacent to Brooks Avenue,
Wyoming, between chainages 83.60 km and 83.80 km).
Maintenance access roads and gates.
A combined services route (approximately 2 kilometres long) on the eastern side of the rail
corridor between Gosford Station and the Etna Street overbridge, and on the western side of the
rail corridor between the Etna Street overbridge and Narara Station.
Three underline crossings (buried services route allowing services/utilities to cross beneath the rail
tracks) and associated cable routes at proposal chainages 81.54 km, 81.97 km and 84.52 km.
The refurbishment of an existing Up Refuge between Gosford Station and the Etna Street
overbridge the removal of two existing maintenance sidings (referred to as the Down Loco Sidings
1 and 2), adjacent to Gosford Showground.
The removal of two existing crossovers and one turnout between Gosford Station and Gosford
Showground.
The refurbishment of one existing catchpoint adjacent to Gosford Showground.
Modifications to the existing signalling system at various locations between Gosford Station and
north of Narara Station (proposal chainages 81.00 km to 86.00 km).
The adjustment, relocation, protection and/or provision of services and utilities, including
overhead wiring, high and low voltage, telecommunications/control, and earthing/bonding
operation of the Project.
3.1

OPERATIONAL PROJECT PURPOSE

The fundamental purpose of the Gosford Passing Loops Project is to provide an alternative route
for freight trains, allowing them to be passed by faster passenger rolling stock.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 9

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
The operational purpose of the Gosford Passing Loops Project is to:
Improve the operational reliability of the RailCorp network, for the benefit of both freight
services and passenger services
Improve the ability of the RailCorp network to recover from operational incidents
Make allowance for known future projects
Achieve compliance with relevant legislation

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 10

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

4 PROJECT MILESTONES
For major project milestones, refer to the GPL Program that will be submitted as part of the
monthly report.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 11

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Figure 1 Project Overview

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 12

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

5 MANAGEMENT REPRESENTATIVE
The nominated Quality Management Representative for the Gosford Passing Loops Project is:
Name: Sheree Jones
Title: Quality Manager
Phone: 02 4918 7400
Mobile: 0418 493 503
Facsimile: 02 4918 7404
The Management Representative is contactable by telephone and/or email at all times during
the undertaking of the Contractors Activities and must be available to attend meetings at the
Principals office or at the Site within 48 hours of notice by the Principals Representative.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 13

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

6 QUALITY DOCUMENT CONTROL


6.1

INTRODUCTION DOCUMENT CONTROL

This document is authorised, distributed, amended and reviewed in accordance with DA-QAPR001 Document Management (included within the IMS). Records of distribution are maintained
by the Quality Manager.
All controlled copies of this document are registered in accordance with DA-QA-PR001
Document Management.
6.2

DOCUMENT STORAGE

Hard Copy Storage and Distribution


A hard copy of this document shall be maintained within the site office for the duration of the
project and may be accessed by employees, sub-contractors, Health and Safety Representatives
and project personnel.
Downer Electronic Document System
An electronic copy of the QMP and associated quality documentation will be stored within the
following project files held within the Gosford Project Server.
All Inspection and Test Plans (ITPs) and supporting information and evidence will be recorded
and stored in the Quality Database QAntrol.
Principal Electronic Document System
The principal has nominated the TeamBinder system as the channel for the sending and receiving
all documents, drawings, specifications and correspondence between the Principal and the
Project Team.
Documents to be stored within TeamBinder include all project administration, reports, plans,
drawings, O&M manuals, technical maintenance plans, services schedules and certificates
directly related to the project.
TeamBinder is available to the Project Team who are required to attend training to ensure
effective management of the document management system.
The Quality Manager will ensure that a master copy of the QMP and associated documentation
will be uploaded to TeamBinder and distributed to nominated Downer and Principal
Representatives.
6.3

PLAN REVIEW

This document shall be reviewed in response to reported issues and outcomes of internal or
external audits and/or changes to internal policies. In particular, a review will address:
Progress of Works

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 14

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Changes in project scope and/or timing
Changes in quality documentation requirements (i.e. new process that requires new
documentation)
Non-conformances and corrective actions raised as a result of audits or observations
6.4

REVISIONS AND AMENDMENTS

Revisions
All document revisions shall be made in accordance with DA-QA-PR001 Document Management
and with the authority of the Quality Manager.
Amendments
Amendments are only made as permitted under the contract.
When amendments are made, the entire document will be reissued and the revision number
updated. Registered recipients will automatically receive the new revision with advice on
amendments made.
Revised plans and associated documents will be issued together with a transmittal form and
recipients will ensure superseded versions are replaced and destroyed to prevent inadvertent use.
6.5

QMP SUBMISSION

The QMP will be submitted to the Principals Representative for review in accordance with the
requirements set out in the Contract.
6.6

CONTROL OF QUALITY RECORDS

The following controls will be implemented to manage quality records for the duration of the
project and for a period of five years from the Date of Completion. These controls satisfy TfNSW
quality requirements, and have been taken from TfNSW Standard Requirements TSR Q1 Quality
Management.

Downer will ensure that all quality records satisfy the requirements of the Contract

Downer will retain all product and service conformance records including the
Subcontractors service conformance records and certificates for a period of no less than
five years from the Date of Completion

All records will be made available to the Principal.

Where there is a requirement to forward records to the Principals Representative, Downer


will submit one original and three copies (one of which is unbound) of each document. In
addition to this an electronic copy on DVD/CD in PDF and native formats will be submitted
as required.

Where requested by the Principals Representative, Downer will provide the Principals
Representative with copies of any Quality Records. Those Records which are not available
on-site, will be forwarded to the Principals Representative within 3 business days of the
request.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 15

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

7 COMMUNICATING THE QMP


All project personnel are required to complete induction training prior to the commencement of
site works. The quality induction training will address:
1/ the content of the QMP and the specific quality responsibilities and obligations of project
personnel
2/ performance objectives and outcomes related to inspection and testing, and required record
keeping
3/ required management of non-conformances (NCR) and required reporting
The quality induction will form part of the Safety, Environmental, Community and Quality
Induction.
A record of quality inductions will be developed and updated monthly for the duration of the
project.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 16

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

8 QMP REFERENCES
8.1

8.2

GENERAL

Contract GPL-01-D&C (Gosford Passing Loops Project)

TfNSW Standard Requirements TSR Q1 Quality Management

TfNSW Inspection and Test Plans Minimum Requirements

TfNSW Project Compliance and Assurance 9TP-ST-020/4.0

IMS and Applicable Downer Quality Procedures and Forms

GPL Construction and Site Management Plan (CSMP)

GPL Design Management Plan (DMP)

GPL Contract Management Plan (CMP)


LEGAL AND REGULATORY

Legal and Regulatory compliance documents are managed within Downer Australia using a
number of centralised reference matrices. These detail the references applicable to all aspects
of the work to be carried out in the course of this contract.
Functional Area

Applicable Matrix

Environment
Health and Safety

DA-QA-FM007.4 Relationship of IMS to AS-NZS-ISO Standards

Quality

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 17

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

9 DOWNER AUSTRALIA INTEGRATED MANAGEMENT SYSTEM


(IMS)
The Downer Australia Integrated Management System (IMS) is a business management system
that guides and controls all processes required to carry out the business. The IMS satisfies the
following International and National standards:

AS/NZS ISO 9001:2008 Quality Management Systems - Requirements


AS/NZS 4801:2001

Occupational Health & Safety Management System

AS/NZS ISO 14001:2004

Environmental Management System

Australian Government Building and Construction OHS Accreditation Scheme

9.1

STRUCTURE OF THE IMS

The core of the IMS is a set of Downer Australia documents that reflect processes conducted
across all Australian business units. Key documents at the national level are:

Strategies, Objectives and Policies guide our business and how we conduct operations
Management Standards (MS) are the core national standards that cover the business

processes and risk controls. They describe the systems, methods and forms that are used to
plan, manage and control our processes and risk controls. They also define the minimum
standards we apply to our worksites in the areas of Health, Safety and the Environment

Handbooks provide information on how the IMS is used and operates and provide
specific information in key areas

Forms, Zero Harm Notifications, Risk Assessments, SWMS and other documents are the
details of the work we do, help control our risks and provide records

The IMS is hosted on the Downer Australia intranet, a business application available to all
employees and providing a set of key resources including:

Document management
Records management
Risk management
Incident reporting and investigation
Non-conformance management
Training provision and record management

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 18

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
9.2

AUDIT OF THE IMS

The IMS is audited, and has been certified by, by an accredited 3rd Party organisation to verify
compliance with the above standards as well as legislative and regulatory requirements. A copy
of the certificate confirming the currency of certification is provided in Appendix A, and a
summary of the certification is reflected in the following table.
Compliance Area

Accreditation Standard

Audit Authority

Certificate Number

Quality Assurance

AS/NZS ISO 9001:2008

BVQI SAI Global

149150 QEC7718

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 19

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

10 PROJECT QUALITY OBJECTIVES, ORGANISATION &


RESOURCES
10.1 INTRODUCTION
Downer Australia is engaged in Australia wide engineering and project management of
infrastructure including design, construction and maintenance services (civil, rail, electrical,
instrumentation, telecommunication and power generation).
The Downer Australia vision is to be regarded as an industry leader in these chosen fields which
will be achieved by focusing on the following business goals:
Ensuring clients are satisfied with our service and performance
Observing and fulfilling statutory obligations and client specifications
Achieving Shareholders expectations
Ensuring employees are accountable, motivated and perform to their full potential
This project will achieve these goals by ensuring all contractual obligations and specified
standards are met.
10.2 QUALITY MANAGEMENT OBJECTIVES
The Quality Management objectives for this project include:

Key Result
Area
Quality
Management

Project Quality Objectives

Downer EDI Limited


ABN 66 008 709 608

All personnel engaged on the project


have appropriate training and have
demonstrated competency required to
meet the quality obligations of the
project
Monitor quality through a formal program
of inspection by those responsible for the
quality of work
Ensure that planned quality control
programs are being carried out through
a series of audits conducted by
personnel not responsible for the day to
day delivery of works

Performance Measures &


Targets

All work complies with the


quality requirements of
the contract

No loss in time and cost


due to rework or
replacement

All defects identified and


resolution agreed without
delay to contract works

There are no negative


observations or
Corrective Actions as a
result of client audits

Ensure all quality documentation used by


those responsible for inspection is being
completed, controlled and stored as
outlined within the QMP

www.downergroup.com
Page 20

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
10.3 PROJECT ORGANISATION CHART
Refer to the CMP for the project Organisational Chart.
10.4 PROJECT RESPONSIBILITIES
Project Manager
The Project Manager (Greg Barnes) has responsibility for the timely execution of the project in
accordance with contract requirements, the Downer IMS, safety, environment and quality
procedures, including client and authority requirements. The following table details this
responsibility:
Area

General

Communication

Systems of Work

Description of Responsibility

Be familiar with legislation and codes of practice relevant to this role

Work is completed as per Contract Gosford Passing Loops GPL-01-D&C

Hold points are signed off on after completion of relevant task

Client CARs/ Non-Conformances are actioned promptly

Requirements of the CSMP are communicated to all personnel, sub


contractors and, where appropriate visitors to site

Chair regular meetings between the project team

Distribute information pertaining to the project is distributed amongst the


workforce

Direct communication with and reporting to the Principals Representatives

Implement systems of work in accordance with statutory obligations and


the Downer IMS

Oversee sub contractors performance of all work in accordance with


statutory obligations and the Downer IMS.

Liaise with the Safety, Environment & Quality Manager on any unique
activities that may require special operating standards or supervision.

Employees are licensed where required and are competent.

All supervisory personnel are fully instructed in the requirements of any


statutory obligations and relevant procedures contained within the IMS.

Record any client induction requirements in accordance with MS006


Training Awareness & Competency and any Principal requirements.

Implement Zero Harm (Safety and Environment) Management in


accordance with the Zero Harm Management Plan (ZHMP)

Training

Zero Harm
(Safety &
Environment)

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 21

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Project Engineers
The project engineers are responsible for technical support including planning, managing and
controlling the project activities to ensure delivery of quality, safety and rail safety objectives. The
Project Engineers are accountable to the Project Manager. The Project Engineers responsibilities
are detailed in the following table:
Area

Description of Responsibility

Requirements of relevant legislations and codes of practise are


implemented throughout the project site when directed by the Project
Manager

Plan, manage and control project activities to assist the construction works

Manage staff to achieve a team environment to meet project objectives


and the objectives of the project manager

Manage sub-contractors to achieve project objectives including material


supply, material recovery, structures and earthworks

Manage the project quality system to ensure contractual obligations are


met

Monitor material stockpile levels to ensure no delays to the program

Regular reporting to the project manager on progress and any issues


which may impact on safety or quality

Update construction program

Provide assistance to project staff in planning, programming and


administration

Procure and expedite materials necessary to perform the works (within


expenditure limits) with no delays to program

Manage plant and labour, in conjunction with supervisors

Appropriate construction methodology and programming options are


explored and are practical, timely and cost effective

All temporary works are designed, verified, documented, fabricated,


installed and safely used in accordance with all method statements and
project procedures within Downers Integrated Management System (IMS)

Identify and investigate project specific engineering advantages

Requirements of the CSMP are communicated to all personnel, sub


contractors and, where appropriate visitors to site

Work collaboratively with the Project Manager, Construction Manager


and Foremen to deliver the project works

Implement Zero Harm (Safety and Environment) Management in


accordance with the Zero Harm Management Plan (ZHMP)

General

Communication

Zero Harm
(Safety &
Environment)

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 22

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Construction Manager
The Construction Manager is directly responsible for the site operations and the implementation of
all relevant site procedures. The Construction Manager is responsible for ensuring all safety,
quality, environmental procedures are followed in relation to the execution of the works.
The Construction Manager is accountable to the Project Manager. The Construction Managers
responsibilities are detailed in the following table:
Area
General

Communication

Zero Harm
(Safety &
Environment)

Downer EDI Limited


ABN 66 008 709 608

Description of Responsibility

Lead and direct the entire construction team;

Plan, coordinate and monitor the construction activities across the project
against project objectives

Progress procurement of key materials, subcontractors and resources

Manage resources across the project

Work is completed as per Contract Gosford Passing Loops GPL-01-D&C

Hold points are signed off on after completion of relevant task

Client CARs/ Non-Conformances are actioned promptly

Implement requirements of relevant legislation and codes of practice

Document and implement systems of work in accordance with statutory


obligations and the IMS

Oversee sub contractors performance of all work in accordance with


statutory obligations and the IMS

Liaise with the Safety, Environment & Quality Manager on any unique activities that
may require special operating standards or supervision

Implement Zero Harm (Safety and Environment) Management in


accordance with the Zero Harm Management Plan (ZHMP)

www.downergroup.com
Page 23

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Supervisors and Foremen
The Supervisors and Foremen are directly responsible for the day to day operations and the
implementation of all relevant site procedures, and that project operations comply with relevant
statutory obligations.
The Foreman is accountable to the Construction Manager. The Supervisors and Formans
responsibilities are detailed in the following table.
Area

General

Communication

Zero Harm
(Safety &
Environment)

Downer EDI Limited


ABN 66 008 709 608

Description of Responsibility

Implement the requirements of relevant legislations and codes of practise

All work is completed to GPL-01-D&C Contract, ensuring that work is


signed off

All employees and subcontractors are inducted using the Induction


Handbook and in accordance with DA-ZH-PR003 Training and
Competency Management

All visitors onsite are inducted and registered and shall be accompanied
at all time while on site

Introduce new employees to project work standards before they


commence work

Provide clear job instruction and methods to personnel for all tasks
performed

Tasks are performed according to the stipulated Technical Procedures,


other process documents

Client CARs/ Non-Conformances are implemented promptly

Continually observe the process of work for sub standard


practices/methods, reinforcing the required standard of practice

Requirements of the CSMP are communicated to all personnel, sub


contractors and, where appropriate visitors to site

Any relevant bulletin or information pertaining is distributed

Advising personnel of required standards of work, new or amended work


practices that are introduced and hazards associated with specific types
of work.

Implement Zero Harm (Safety and Environment) Management in


accordance with the Zero Harm Management Plan (ZHMP)

www.downergroup.com
Page 24

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Safety, Environment, Quality Manager (SEQM)
The SEQM is responsible for the monitoring and review of the effectiveness of the safety,
environmental and quality controls during the conduct of the contract. Specifically the SEQM has
the responsibilities detailed below.
Area

Safety, Quality
and
Environment

Downer EDI Limited


ABN 66 008 709 608

Description of Responsibility

Provide technical advice and support to the project manager in the


establishment of safety, quality and environmental objectives, targets and
strategies for the project

Facilitate the reporting of project safety, quality and environmental


performance, including trends analysis of lag and lead indicators

Provide technical advice and support in the identification, assessment


and control of workplace risks, SWMS, including purchasing decisions and
plant modifications

Monitor and communicate legislative changes and best practice


initiatives to management and employees

Advise on project compliance with legislation and the Downer Australia


IMS

Establish and implement internal safety, quality and environmental


auditing programs for the project including the development of
subsequent action plans to address identified deficiencies

Assist the project manager in the identification, development and


implementation of safety, quality and environmental training programs for
project employees and management

www.downergroup.com
Page 25

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

11 PROJECT ADMINISTRATION
11.1 PROJECT FILING AND STORAGE SYSTEM
Refer to the Quality Document Control section of the QMP for information on electronic and
hard copy document storage and the nominated quality database
11.2 PROJECT MEETINGS, REVIEWS AND REPORTS
Project and subcontractor meetings will be held weekly on site and will be documented
according to Downer Project Management procedures.
Internal project meetings will be conducted on an as needs basis and minutes of those meetings
recorded and filed in accordance with DA-QA-PR001 Document Management.
The Weekly and Monthly will be prepared as per procedure DA-PM-PR020 Monthly Project
Reporting and Review and as stipulated in the Contract.
11.3 CONSTRUCTION PROGRAMME
The construction program will be handled according to procedure DA-PM-PR011 Project
Management Plans. Refer to the CSMP for further information on the management of the
Program. The program will be submitted as part of the monthly report.
11.4 CONTROL OF DRAWINGS AND SPECIFICATIONS
Refer to the Design Management Plan developed to meet the requirements of contract and TSR
T1 Technical Requirements.
11.5 MANAGING VARIATIONS
Contract variations will be managed according to procedure DA-PM-PR025 Managing Variations,
Delays and Disputes, and in accordance with the contract terms and conditions. No variations
will be implemented without written client approval or direction.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 26

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

12 INTERNAL AUDITS AND PLANNED INSPECTIONS


12.1 PROJECT AUDITS
Project Audits are planned by the Project Manager in consultation with the Quality Manager and
completed according to procedure DA-QA-PR007 Internal Audits. This will ensure the ongoing
effectiveness of the system and to facilitate continuous improvement.
Audit Reports are available for review on request by the Client and will include the following types
of Audit:
1/ audits of the operation or the quality management system to evaluate its effectiveness as
applied to the project
2/ Project and service audits to assess the conformity of the project or service with the specified
requirements; and
3/ audits of work process control, to evaluate how effectively work process controls are
implemented in practice
(Taken from TfNSW Standard Requirements TSR Q1 Quality Management)
Audits will be continually evaluated and the scope of the activities and products to be audited
adjusted based on the performance of the activities. Frequency and areas targeted for audit will
then be relevant to the performance and activities undertaken.
The Principal may request the opportunity to audit to ensure compliance with the Contract
requirements.
The Principal may request access to audit documentation, records and applicable personnel. All
materials, records and personnel will be made available by Downer.
The internal audit and planned inspection register will be included as an Appendix to this plan
once completed.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 27

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

13 PURCHASING
Downer as the main contractor will manage all of the operating areas of the project and
subcontractors.
Downer will ensure that all relevant procurement processes (as outlined within Downers IMS
System) will be followed so that subcontractors are selected and appointed to deliver their
relevant scope of works and services in accordance with the contract.
Refer to the Contract Management Plan that stipulates that the requirements of the head
contract will be reflected in the subcontracts and will also ensure that these are also passed
down to lower tier subcontractors. The Contract Management Plan also provides a figure that
diagrammatically shows the hierarchy of contracts developed for the establishment of the
project.
13.1 SUPPLIERS AND SUBCONTRACTORS
Approved key subcontractors at the time of issue of the QMP are noted in the following table.
Subcontractor / Supplier Name

Scope

SMEC

Civil, structures and track design

Robson Civil Projects

Construction of earthworks, culverts, retaining walls and


bridges

WS Atkins International

Safety Assurance

Degotardi, Smith and Partners

DSS survey

DA-ZH-022 Visitor & Contractor Management is applied to ensure that all subcontractors perform
their duties to the required specified requirements for the duration of the project. The following
specific controls apply:
Assessment of subcontractors including past performance
Use of purchase orders and plant-hire/sub-contract agreements
Supervision and continuous monitoring of operations on site
Use of ITPs
Implementation of Downer management processes, Critical Risk Controls and other
process controls over work practices to ensure that subcontractor work is completed
safely and to specification.
All subcontractors are engaged and work on site under the Authority to Work Permit (ATWP)
system, as detailed in DA-ZH-022 Visitor & Contractor Management. A valid work permit is required
prior to a subcontractor undertaking any work on a Downer site.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 28

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
Subcontractors engaged on the project are allowed to operate under the Downer IMS. However,
Subcontractors can work under their own safety system also, provided the system and
documents, such as Safe Work Method Statements, are to the satisfaction of Project Manager.
Subcontractors will make available (given reasonable notice) all relevant documents and records
as required for auditing purposes.
13.2 SITE INDUCTION AND TRAINING
Site induction and training of all personnel including subcontractors must be completed prior to
undertaking work including:

Project specific induction

Task/work area induction

Daily pre-start, pre-work briefings and visitor induction

Off-site office induction

13.3 PLANT AND EQUIPMENT


All plant and equipment used on site complies with applicable Regulations, and is subject to
regular maintenance per manufacturers specifications and used in accordance with MS024
Vehicle & Mobile Plant.
Downer will control delivery schedules in order to minimise long term storage of products on site.
Specifically Downer will ensure minimum holding and storage times for products and materials
that are hazardous, flammable, sensitive to deterioration, easily damaged, and other causes of
loss. Refer to the CSMP that addresses the transportation and handling of materials.
All internal Plant Risk assessments will be completed on all plant in accordance with DA-ZH-PR028
Zero Harm Risk Management and regulatory requirements.
As stipulated within TfNSW Standard Requirements (TSR Q1 Quality Management), proposed
product substitution under the Contract is at the sole discretion of the Principals representative.
Operation of plant and competency of plant operators, including subcontractor and hired plant
is addressed via:
DA-ZH-PR003 Training and Competency Management
DA-ZH-PR022 Visitor & Contractor Management
MS024 Vehicles & Mobile Plant
MS025 Fixed Plant & Powered Hand Tools

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 29

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

14 PRODUCT AND SERVICE CONTROL


14.1 PROJECT CONTROL DOCUMENTATION
The CSMP provides a high level understanding of Downers approach to delivering the works.
The CSMP also provides an overview of Construction Method Statements (CMS) that define the
approach to procurement and delivering the works in a specific discipline (work area). The CMS
describe the approach to delivering that discipline (work area) with respect to scope, method,
risk, constraints and interface with other disciplines.
Each CMS will be supported by a Site Safety Plan, a Construction Environmental Management
Impact Plan, a Traffic Control Plan and one or more work packages including applicable work
method statements, Lot checklists and ITPs.
The CSMP also provides a figure that diagrammatically shows the hierarchy of management
plans, sub plans, statements and other documentation used to manage and all contractor
activities under the contract.
14.2 PRODUCT IDENTIFICATION AND TRACEABILITY
OP 21 Construction Materials Receiving, Storing and Traceability shall be extended for use in
compliance checking of purchased and client supplied works, products and materials.
14.2.1 Identification
The Project Manager will sub-divide the whole of the work into work packages, establish a lot
identification system and identify each lot on the Lot Register, as prescribed under OP19 Planning
and Checking Construction Work.
14.2.2 Traceability
Traceability of materials will be recorded in accordance with OP21 Construction Materials
Receiving, Storage and Traceability. Furthermore, the Project Manager or nominated
representative will ensure that those measures prescribed under OP21 Construction Materials
Receiving, Storage and Traceability, meet those requirements specified under the contract
agreement.
14.3 HANDLING AND STORAGE OF CONSTRUCTION MATERIALS
Refer to the Construction and Site Management Plan (CSMP) that addresses the transportation
and handling of materials.
14.4 INSPECTION AND TEST EQUIPMENT
All inspection, measuring and testing equipment will be controlled as per procedure DA-QAPR008 Inspection, Measuring & Test Equipment. In the event that inspection, measuring or testing is
proposed via means of a secondary subcontractor, Downer Australia will maintain copies of
calibration records for all subcontractors in accordance with the above procedure.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 30

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
All Inspection & Test equipment used on site is subject to regular maintenance and is calibrated
as per procedure DA-QA-PR008 Inspection, Measuring & Test Equipment.
Identified Inspection & Test equipment will be recorded in the Calibrated Equipment Register.
Testing of Materials
An accredited NATA laboratory shall conduct testing of materials and samples where required
using approved NATA testing processes.
14.5 CONTROL OF NON-CONFORMING MATERIALS OR WORK
Non-conforming materials or work will be recorded on Non-conformance Reports and handled as
per OP20 Handling Non-Conforming Materials or Work. A Non-conformance Register will be
established by the Project Manager, which will be used to identify the status of each Nonconformance report.
The Project Manager will obtain the clients written approval for proposed repairs, rework or
concessions in accordance with the requirements of the Clients Quality Assurance
Requirements. The Clients approval will be obtained prior to the implementation of the Downers
proposal.
14.6 DESIGN CONTROL
The Project Design Management Plan (DMP) defines project overview, design strategic
objectives, design processes and procedures of managing delivery of design for all design
packages. The DMP has been developed to meet the specific requirements of the Project. The
DMP represents the overarching management plan for control of design and will be used to
guide and inform the development of the individual design consultant management plans in the
delivery phase. For further information regarding Design Management, refer to the Design
Management Plan developed to meet the requirements of contract and TSR T1 Technical
Requirements.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 31

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

15 INSPECTION AND TESTING


15.1 ITP COMPLIANCE
All quality related construction activities shall be managed by Downer using ITPs and associated
Lot Checklists developed by the Engineering Team and Project Manager.
Downer will prepare, maintain and update ITPs in accordance with TfNSW Inspection and Test
Plans Minimum Requirements 4TP-ST-068.
15.2 CONTROL AND STORAGE OF ITPS
All ITPs and supporting information and evidence will be recorded and stored in the Quality
Database QAntrol.
Hard Copies ITPs will be stored as outlined within the Quality Document Control section of this
plan.
15.3 MANAGEMENT OF ITPS
ITPs will be managed by the Project Team (Engineering Managers, Design Manager and Project
Manager) in consultation with the Quality Manager. The requirements for the ITPs will be
determined by the applicable Engineering Manager, and all ITPs developed by subcontractors
for their portion of the work will be reviewed and approved by the applicable Engineering
Manager or his delegate.
15.4 PRINCIPAL ITP REQUIREMENTS
The Principal may provide specific requirements and inspection and testing regimes for inclusion
within the ITPs. These requirements will be incorporated into the ITPs. This will ensure that ITPs
include acceptance criteria and design intent prior to submission to the Principals Representative
for review as set out in the contract.
15.5 DEVELOPMENT OF ITPS
The following process will be used to review and approve ITPs:
1.

Applicable Engineering Manager prepares ITP based on requirements and


specifications and submits to Design Manager for review

2.

Design Manager reviews ITP and either sends back to Engineering Manager with
changes or approves

3.

Design Manager submits ITP to Project Manager for review and approval. Project
Manager either makes changes or provides approval ensuring that it satisfies all
relevant standards and specifications for the proposed works

4.

Once approved, the Project Manager will then submit to the Quality Manager

5.

Quality Manager will submit to Principal for review and approval

6.

Once approved, the Quality Manager will enter the ITP into QAntrol

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 32

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A
7.

The ITP will then be undertaken by the engineer responsible for the work or the
approved representative and entered into QAntrol.

15.6 MANAGEMENT OF ITPS AND LOT CHECKLISTS


Lot checklists (for each Lot created under the ITP code) will be generated from QAntrol by the
Engineering Manager responsible for that work. The lot checklist will be provided to the Supervisor
or Foreman to confirm compliance. The responsible Engineering Manager will also be responsible
for progressive inspection and audit of site works to ensure conformance.
Lot Checklists document:

notification timeframes

release of witness and hold points

evidence of site inspections

the verification of recorded information

15.7 HOLD POINTS AND WITNESS POINTS


Compliance with critical aspects of the project is addressed via the use of nominated Hold Points
and Witness Points.
Planned Hold Points and Witness Points form part of the individual Work Instructions and ITPs and
are approved by the Engineering Manager, Design Manager, Project Manager and by the
Principals Representative.
TfNSW Standard Requirements TSR Q1 Quality Management Appendix A5 lists the Principals
nominated Hold Points and Witness Points. Details of these Hold Points and Witness Points will be
included within the applicable ITPs, as well as the specific process to be held and/or witnessed,
submission requirements and the process of approval by the Principal.
The Engineering Manager / Site Supervisor is responsible for advising the Principals Representative
that a Witness Point or Hold Point is due for inspection.
Notifications of Hold Points and Witness Points will be included within the Lot Checklists and
completed ITPs and Lot Checklists recorded within QAntrol.
15.8 NON-CONFORMANCES
All non-conforming materials or work will be managed in accordance with the contract
requirements and DA-QA-PR005 Corrective and Preventive Action.
Note: Non-conformances automatically create a Hold Point.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 33

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

16 CLEANING AND PROTECTION OF WORK


Downer will ensure that all works and temporary works on site will remain clean and protected for
the duration of the contract. This will include:

protection of newly installed works to ensure no damage or deterioration


cleaning and maintaining newly installed works as frequently as required according to
the manufacturers specifications

cleaning and rectification of any works soiled, marred or damaged.


Downer will also ensure final cleaning of building works prior to completion to the satisfaction of
TfNSW Standard Requirements (TSR Q1 Quality Management).
Please refer to the CSMP for further information on Cleaning and Protection of Site Work.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 34

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

APPENDIX A: IMS ACCREDITATION CERTIFICATES

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 35

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Appendix B: DOWNER AUSTRALIA BUSINESS POLICY

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 36

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Appendix C: HOLD AND WITNESS POINT REGISTER


This is currently under development

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 37

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Appendix D: AUDIT AND REVIEW SCHEDULE


This is currently under development.

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 38

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

Appendix E: INDEX OF QUALITY PROCEDURES AND FORMS


Note: Downer Australia is currently rolling out updated business processes (to form a new Downer
Australia IMS). Consequently as new Downer Australia forms and procedures become available
they will replace the existing Downer EDI equivalents.
QUALITY MANAGEMENT - PROCEDURES
DA-QA-PR001

Document Management

DA-QA-PR002

Downer Australia Document Implementation

DA-QA-PR003

Business Planning, Objectives and Targets

DA-QA-PR004

Management Review

DA-QA-PR005

Non Conformance, Corrective and Preventative Action

DA-QA-PR006

Inspection & Testing

DA-QA-PR007

Internal Audit

DA-QA-PR008

Inspection, Measure and Test Equipment

DA-QA-PR009

Records Management

QUALITY MANAGEMENT - FORMS


DA-QA-FM001.1

Document distribution register

DA-QA-FM001.2

Authority to release to document centre

DA-QA-FM001.3

Management Procedure template

DA-QA-FM001.4

Work Instruction template

DA-QA-FM001.5

Form template

DA-QA-FM001.6

Document numbering convention

DA-QA-FM001.7

Flowchart template portrait

DA-QA-FM001.8

Flowchart template landscape

DA-QA-FM001.9

Document review template

DA-QA-FM003.1

Downer Australia bluesheet template

DA-QA-FM003.2

Objectives and targets register

DA-QA-FM003.3

Plans Objectives and Targets review checklist

DA-QA-FM004.1

Management review agenda and minutes

DA-QA-FM005.1

Corrective Action Report

DA-QA-FM005.2

CAR Register

DA-QA-FM007.2

Internal Audit register

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 39

Quality Management Plan


Document Number GPL-DWNR-PM-000110
Revision A

QUALITY MANAGEMENT - FORMS


DA-QA-FM007.3

Internal Audit schedule

DA-QA-FM007.4

Relationship of IMS to AS/ISO standards

DA-QA-FM007.5

Audit checklist template

DA-QA-FM008.1

Test Equipment Register

DA-QA-FM009.1

Archive Register

DA-QA-FM009.2

Archive Register

DA-QA-FM009.3

Destruction Authority

Downer EDI Limited


ABN 66 008 709 608

www.downergroup.com
Page 40