Professional Documents
Culture Documents
Khalid Altaslaq
Design engineer in the ministry of public works and
housing
Mobile : 0797124621
E mail : waleeds87@hotmail.com
1
Prepared By Eng Khalid Altaslaq
Table of contents
Topic
Drainage system
Introduction
Types of drainage
Page
Number
3
4
5
Vent system
15
24
36
Types of water
37
37
38
41
2
Prepared By Eng Khalid Altaslaq
3
Prepared By Eng Khalid Altaslaq
: Introduction
In the outlined plumbing course, we will discuss the main concept,
requirements and design
procedure for drainage system and water supply following the approved
codes such as the
Uniform Plumbing Code (UPC), International Plumbing Code (IPC), National
Plumbing Code
and Plumbing Design Guide (From the British (NPC).
Standard BS)
The concept of the drainage system is to draw out the drainage outside
* the building to a
proper disposal network such as sewer manholes, septic tank, treatment
unit or soak away
pits
The drainage system plays a big rule in the public health since it rids of *
the foul and soil
water from the building which will introduce a health hazard if it's not
removed properly and it will efect on the natural water stores under
ground
4
Prepared By Eng Khalid Altaslaq
Knowing the type of the drainage is important since every drainage type *
goes to a certain place because some types can be reused after treatment
.and some types not allowed to discharge into public sewer network
:Types of drainage
-from: Which comes out (Soil Drain (Black Water 1
a. Water Closet (WC)
b. Urinals
c. Bidet
this type can be discharged either to sewer network , holding tanks, or soil
treatment plant (STP)
e. Area Drain
this type can be discharged either to waste water network, holding tanks
or grey water treatment plant then reused in flushing tanks and irrigation
Hazard Drain which comes out from some hazard application like -4
chemicals
this type can be discharged to treatment plant or septic tank then to
sewer network to avoid destroying network's pipes or it can be discharged
to special drainage system and it depends on the hazard classification
.laboratories
this type can be discharged to treatment plants and septic tanks and its
very important to note that this type not allowed to discharge into public
.sewer network to avoid disease spreading
special Drain which comes out from special applications and not -7
allowed to discharge to sewer network before treatment like oils which
produced by kitchens, hotels, cars lubrication stations which assumed to
.be connected to a septic tank before sewer network
6
Prepared By Eng Khalid Altaslaq
And some of special drain types not allowed to discharge to sewer network
by any way like stones cutters and marble factories to avoid closing the
.network's pipes by the sludge
Drainage system
: description
The drainage system is an open hydraulic system and it is the only - 1
system in the building that runs by gravity force which makes it the most
difficult system to handle and design in order to produce a fully functional
system. Using the gravity force, a proper pipe slope shall be introduced
in order to maintain a proper flow; each pipe size has its own slope and
.requirements
although the drain water is a flow but it is not measured directly by 2
(l/s) or cfm or any (unit/time) when the calculations of pipe sizing are
estimated. Because that any fixture is not used overall the time of day and
.then the drain flow is not continuously
To solve this problem a new measuring unit was created which called
( drainage fixture unit) (DFU) and the size of any drain pipe selected upon
. the number of these fixture units which that pipe carry it
7
Prepared By Eng Khalid Altaslaq
8
Prepared By Eng Khalid Altaslaq
And the following table from the same code gives the size of pipes
:according to diferent values of drainage fixture unit
Outside
pipes
Riser +
Vent pipes
Inside
network
Internal
pipes
Fixture
sewer network
and pits
man
holes
9
Prepared By Eng Khalid Altaslaq
European)1(
(WC)
Eastern)2(
(WC)
floor
mounted
wall
mounted
Eastern (WC)
floor mounted
Wall mounted
10
Prepared By Eng Khalid Altaslaq
B Bidet
lAVATORI
ES
Pedestal
lavatory
Semi Pedestal
lavatory
wall mounted
lavatory
counter lavatory
Pedestal Type
Counter type
D Shower
It depends on accessories
12
Prepared By Eng Khalid Altaslaq
E bath tub
F Kitchen
sink
It either be single pole or double pole and both types can be marble or
steel
G Service sink
This type of sinks used in applications like hospital's and hotel's kitchens
H Floor Drain
it is a trap where fixtures without a trap or (fixture venting) is connected to
and contains three inlets can be 50 mm or 80 mm and one outlet to
connect to a main network can be 80 mm or 110 mm
13
Prepared By Eng Khalid Altaslaq
:Internal pipes 2
The pipes which connected between fixtures and inside network which
.being inside the building
There are many size and types of inside pipes and the most commonly
:used are
A 50 mm (2 inch) pvc pipe
B 80 mm (3 inch) pvc pipe
C 110 mm (4 inch) pvc pipe
Inside network 3
The method and shape of connections between internal pipes and fixtures
.including the size, slope and bath of each pipe
:There are two types or methods for inside network connection
: A Single stack network
All fixtures in this method(waste and soil) are connected to a main pipe
and the pipe is then connected to the manhole network either directly or
. through a riser
14
Prepared By Eng Khalid Altaslaq
15
Prepared By Eng Khalid Altaslaq
The riser is the vertical pipe which the branches of each end of inside
networks connected to, and it collects the drain from it and we can see the
.riser as shown in the previous figure
16
Prepared By Eng Khalid Altaslaq
:Vent system- 5
One of the most important plumbing pipes in the drainage network is a
.vent pipe ,it doesnt carry water. It carries air
:Appliance venting 2
17
Prepared By Eng Khalid Altaslaq
: Pit venting 3
There are more than one method to vent the riser pipe and each of
:them depends on the height and drainage load of building
The main idea in this method is to vent the vent pipe itself by taking
a vent tap from each floor and connect it to a parallel vent stack to
.the riser, in other words create a bypass connection
By this method the circulation of air will be more efficient because
when the riser or drain pipe is fully loaded by drain water the air will
pass through alternative bath and then no bubbles or break down of
drain flow will occur, this method almost using for high rise building
and when the drainage load have a huge amount although when the
.building being small
20
Prepared By Eng Khalid Altaslaq
21
Prepared By Eng Khalid Altaslaq
outside pipes 6
The materials of these pipes can be (UPVC, HDPE, and clay) since
the outside piping is usually parried underground and the pipe
.material must carry out high pressure
Manholes 7
Note: the distance between inlet and outlet of manhole does not exceed
.60 cm ,if else then a drop manhole shall be used as will be shown
Note: the design of manholes will be explained later in the design
.procedure section
22
Prepared By Eng Khalid Altaslaq
:Manholes type
23
Prepared By Eng Khalid Altaslaq
Note :The distance between inlet and outlet for this type of
manholes is 60 cm and more so it used in case of change in levels
:Pits
The pits are used to collect the drain of building either when a treatment is
needed before connection to the sewer network or when the sewer
.network not available
:Types of pits
Impervious Cesspools 1
This type used to collect the drain of building when the sewer network not
available, and when being filled up it discharged by a septic cars
:Septic tank 2
This type used to separate the sludge from the drain of building which will
naturally analyzed or decomposed in the ground then the floating water
. transferred to pervious cesspool or goes through the ground soil directly
pervious Cesspools 3
This type used to collect the filtered drain which transferred from the
. septic tank and then it goes through the ground soil directly
:Grease tank 4
This type used to separate the oils from the drain of building then the
. floating water transferred to the sewer network
Note: types 2 and 3 not preferred and in almost times authority forbidden
there to avoid the pollution of underground water stores as explained in
.the introduction of this course
25
Prepared By Eng Khalid Altaslaq
27
Prepared By Eng Khalid Altaslaq
:Vent Sizing
The size of vent piping shall be determined from its length and the total
number of fixture units connected thereto, as set forth in the table
mentioned in drain pipe sizing, forth more some conditions for venting
:must be considered
A - The diameter of an individual vent shall not be less than one and onefourth (1-1/4) inches (32) mm nor less than one-half (1/2) the diameter of
.the drain to which it is connected to
B - the drainage piping of each building and each connection to a public
sewer or a private sewage disposal system shall be vented by means of
one or more vent pipes, the aggregate cross-sectional area of which shall
. not be less than that of the largest required building sewer
C - Vent Termination
Each vent pipe or stack shall extend through its flashing and shall
terminate vertically not less than six (6) inches (152 mm) above the roof
nor less than one (1) foot (305 mm) from any vertical surface. Each vent
shall terminate not less than ten (10) feet (3048 mm) from or at least
three (3) feet (914mm) above, any openable window, door, opening, air
intake, or vent shaft, nor less than three (3) feet (914 mm) in every
.direction from any lot line, alley and street excepted
28
Prepared By Eng Khalid Altaslaq
:pipe slope 5
Each size of pipe have a certain slope which estimated in codes according
:to
A - providing the drain by enough force component in the direction of flow,
.which caused by gravity force
B keep the floating of drain to avoid the drying of network which causing
(odors, siphonage, and back flow under negative pressure which will
.occur)
The following tables indicates the slope of pipes according to (IPC) code
:but in almost time we take the slope of inside piping as (1% per meter)
29
Prepared By Eng Khalid Altaslaq
: Manholes design 6
each manhole must located at appropriate level to make the drain flow
.under gravity force efect
:Three points shall be considered in manholes design
A check the level of natural water stores under ground
B Estimate a manhole at (any change of direction, any change of
elevation, any Connection point, each 30m for 6inch pipe and less and
each 60m for 8inch pipe and larger)
30
Prepared By Eng Khalid Altaslaq
11
(2)
(3)
2
3
m 20
5
m 30
The top of each manhole called cover level which always being on the *
ground surface
.The points (1,3,5) called invert or inlet level for each manhole *
.The points (2,4,6) called outlet level for each manhole *
:Now Assume a slope of 2% for each pipe then
Determine the depth of the first manhole which must be at least (60 1
cm) then the invert level of this manhole will be at (60 cm) from the cover
.level
the outlet level of manhole (1) = 60cm + 5cm (the pipe diameter of 2
manhole pipe
:Manhole no (2) 3
:Manhole no (3) 4
= the invert level of manhole no (3) *
the invert level of manhole no (2) + 5cm (the pipe diameter of manhole
(2)) + (the length of connection pipe*connection pipe slope)
.cm 116 = (0.02*30) + 5 + 105 =
the outlet level of manhole no (3) = 116cm + 5cm (the pipe diameter of *
manhole(3)) = 121
the depth of manhole (3) = the cover level invert level = 0 116 = *
-116 cm
:Notes
in case of drop manholes instate of 5 cm (the pipe diameter of manhole) 1
put 60 cm or 50 cm ( the distance between inlet and outlet of drop
manhole which difers from type to other
the cover level not necessary to be at 0.0 level but it depends on the 2
ground level which given by the arch engineer, in other words the cover
levels not necessary to be in decreasing but it necessary to decreasing in
:invert levels, look at the figure below
32
Prepared By Eng Khalid Altaslaq
33
Prepared By Eng Khalid Altaslaq
: pits design 7
Pit size =(the demand of water per person(m) )*(no of persons )+ 2
The following table gives the demands of water for many applications *
according to (IPC) code
34
Prepared By Eng Khalid Altaslaq
:Underground Drainage - 8
Drain located beneath the discharge level must be directed to a sump pit
with a submersible pumps to lift the drain to the required level. Size of the
pit shall be minimum of 18 inches (465 mm) in diameter and 24 inches
deep (610mm). Maximum effluent level shall be 2 inches below the lowest
:inlet pipe. Discharge pipe size shall be as follows
35
Prepared By Eng Khalid Altaslaq
:Run Coefficient
for roofs and balcony 1
for hard-scape 0.9
for soft-scape 0.5 0.3
if a harvesting tank will be estimated then the size of it = Q* (no of
storage hours)/1000
Below is the table to determine the size and the number of roof drain - 2
:outlets
37
Prepared By Eng Khalid Altaslaq
38
Prepared By Eng Khalid Altaslaq
39
Prepared By Eng Khalid Altaslaq
:raw water 1
it Is the natural water found in the environment, such as rainwater, ground
.water, and water from bodies like lakes and rivers
:treated water 2
:It is the water which treated before consumption like
a - drinking water : water which acceptable for human consumption
b - soft water: water which filtered from solid and chemical particles
c R.o water: which filtered from solid particles like sands
d filtered water : water which filtered from solid and chemical particles
.by a carbon or sand filter
e - waste water which has been used in an industrial process like cooling
.process
Make-up Water which using for water base system (chilled water, -5
fire protection expansion tanks, Humidification)
:System components
collectors
Cabinets
Pipes from
shafts to
cabinet
exposed
pipes
tanks
valves
fixtures
Pipes from
collectors to
fixtures
:Tanks - 1
:The most commonly types are
a PVC tanks
b steel tanks (galvanized)
c fiber glass tanks (which have a spherical shape)
d GRP tanks (glass fiber reinforced plastic tanks
2 exposed piping :
41
Prepared By Eng Khalid Altaslaq
The pipes which extend from tanks to shafts and usually being mounted
and exposed on roofs and walls so they must carry out high pressure and
hard conditions.
:The most commonly types are
A black steel pipe: this type usually used in large installations like
:hospitals and hotels, it carry out unlimited pressure and classified as
- . + Seamless type: which carry 12 bar and
-Seam type: which carry 5.5 bar .
B galvanized steel pipe
.C CPVC pipe
.D PEX pipe
:Cabinets - 4
It is a collection box from which the pipes distributed to fixtures, it made
: from steel and there are many sizes of cabinets
A 60 cm * 60 cm * 10 cm : the capacity of this size is (1 - 6) pipes
B - 80 cm * 60 cm * 10 cm : the capacity of this size is (7 - 8) pipes
C - 100 cm * 60 cm * 10 cm: the capacity of this size is (9 - 12) pipes
:Collectors - 4
It is a collection pipe where the supplying pipes of fixtures are connected *
. to, usually made from copper or chromium
The collector connected to the main pipe which come from shaft then it *
supplies the fixture pipes by a small ports
The collector classified upon the number of ports which ranges from 2 to *
.12
The size of main or inlet port can be (3/4,1,1.25) inches *
42
Prepared By Eng Khalid Altaslaq
valves 6
The valves connected in many positions in network for deferent purposes
:like (isolating for maintenance , balancing, regulating) for example
A isolating valve, which usually connected before and after any device or
components like pumps, tanks , collectors ..to provide adequate
.maintenance without closing the overall network
B Double regulating valve : which usually connected before the
components which need a flow regulation and balancing like radiators
C - angle valve : this valve have an angle (90) shape which usually
connected before fixtures to provide adequate maintenance without
.closing the overall network
:The angle valve estimated on wall at the following levels above ground
.cm for sinks and lavatories 55 . cm for (WC's) and bidets 7 .cm for showers 60-70 .cm for unknown fixtures 25 -
43
Prepared By Eng Khalid Altaslaq
:Design procedure
:General notes
although the water is a flow but it is not measured directly by (l/s) or - 1
cfm or any (unit/time) when the calculation be estimated. Because that
any fixture is not used overall the day and then the water flow is not
.continuously
To solve this problem as in drainage system a new measuring unit was
created which called (water supply fixture unit) (WSFU)
water supply fixture unit : it is a statistical number that indicates - 2
.the flow of each fixture along with the frequency of using this fixture
WSFU have a diferent values in each code and standard, the most - 3
important point is to use the tables and charts in the same code that
.water supply fixture unit are taken from
WSFU for each fixture in the network must obtained and then the total - 4
WSFU are converted again to flow by referring to the tables from the same
code which obtained from then the calculations of pipe size and pumps
. estimated according to this flow
It is not allowed to sum the flow of each unit fixture directly because it - 5
is non algebraic number so the sum of all unit fixtures calculated then
converted to flow, for example assume we have two fixtures (bathtub
: and bidet)
Now from the table(1) shown below we can see that we have 2 WSFU for
bidet and 4 WSFU for bathtub then the flow according of these WSFU's
: from the table(2) are
gpm for 2 WSFU 5
gpm for 4 WSFU 8
gpm for 6 WSFU 10.7
If we calculate the sum of flow directly then ( flow = 5 + 8 = 13 gpm)
which is the wrong method but the right method is (2 WSFU + 4 WSFU = 6
.WSFU) then the flow according of 6 WSFU is 10.7 gpm
44
Prepared By Eng Khalid Altaslaq
(table 1)
45
Prepared By Eng Khalid Altaslaq
(table 2)
46
Prepared By Eng Khalid Altaslaq
:Design steps
:small systems (A)
48
Prepared By Eng Khalid Altaslaq
:A - supply pump
usually the farthest floor and (HWC) are the main points in the system
which need a pressure rising and so there are two methods for pumps
: calculations
The first method is to select two pumps; one for the farthest floor 1
and the other for (HWC) then find the head and flow rate for each one, and
the following example explain that: assume the following water supply
: riser diagram
Roof
tank
54
Cab
3
1
Cab 2
HWC
8
50
Prepared By Eng Khalid Altaslaq
Fixture
1
: Then estimate the following table to find the head of farthest floor pump
bath
1-2
2-3
3-4
4-5
type
Cold
Cold
Cold
Cold
Positive pressure(
pgh)
(x)
negative
***pressure
(y)
(x-y)
water
water
water
water
(table 1)
.(pa/m) + Residual pressure
: Then estimate the following table to find the head of HWC pump
bath
type
1-2
2-6
6-7
7-8
8-7
7-6
6-2
2-3
3-4
4-5
Cold water
Cold water
Cold water
Cold water
Hot water
Hot water
Hot water
Hot water
Hot water
Hot water
Positive pressure(
pgh)
(x)
negative***
pressure
(y)
(x-y)
(table 2)
51
Prepared By Eng Khalid Altaslaq
52
Prepared By Eng Khalid Altaslaq
And The tables below use the type of the building to determine the hot
:water demand
53
Prepared By Eng Khalid Altaslaq
The concept of the hot water return pump is to keep the temperature of
the water in the hot water pipes since the non circulating water will loss
.energy
: To calculate the flow rate of the hot Water Return Pump then *
the total length of the hot water and the hot water return pipes shall - 1
.be determined
:use the Following equation to find the flow rate of pump 2
The heat loss can be calculated by multiplying the total length of the hot
water and hot water return pipes by the loss value (w/m) of each pipe size
which obtained from ASHRAE Application (service water heating chapter)
:as follows
54
Prepared By Eng Khalid Altaslaq
the first method is to take the return pipes from the main pipes which 1
.connected to cabinets
this method save materials and pumping energy , but the circulating of
hot water will be between HWC and cabinets which mean that some losses
will occur in the hot water in the pipes which connected between cabinets
and fixtures which make the person or customer waiting for a few minutes
.for reaching the hot water
the second method is to take a return pipe from each fixture supply 2
pipe and the size of this pipe determined by selecting the first smaller size
after supply pipe size, for example if the supply pipe size 20 mm then the
.size of return pipe will be 16 mm
Although this method consumes pumping energy and materials, but the
hot water will be available at any time without waiting which reducing
. water consumption
the third method is same as the second method but the size of return 3
.pipe taken as the size of supply pipe
Note : the most commonly used method is method no (1) then (2) then
(3), but methods 2 and 3 not used in water supply system which contains
.cabinets
55
Prepared By Eng Khalid Altaslaq
:The design steps in large systems is the same in small systems but
without point (2) , because the cabinets contain the main valves of 1
supply pipes which means that anyone can adjust the flow or close system
, and you can imagine for example what will occur in operations room in
hospitals when the water closed suddenly. It is
!!!!!!!looooooooooooooooooooool
without point (4), because in large systems underground tanks - 2
installed instead of roof tanks since the heavy weight of roof water tanks
efects on the structure of building, and the shape of tanks on roofs not
.acceptable by architect engineers
56
Prepared By Eng Khalid Altaslaq
57
Prepared By Eng Khalid Altaslaq