Professional Documents
Culture Documents
T K Ray
Senior Faculty Member
NTPC Limited
rayt3@asme.org
11-Nov-10
T K Ray NTPC
Presentation Outline
Electricity Pricing
Cost elements
elements, Objectives
Objectives, Power gen
gen. eco
eco.
Single part and two part tariff
ABT
Features, Mechanisms, Benefits
Scheduling, Real Time Operation
Trading Opportunities
11-Nov-10
T K Ray NTPC
C t Elements
Cost
El
t
Fixed costs
Interest on loan,, Return on equity,
q y, Depreciation,
p
,
O&M expenses, Insurance, Taxes , Interest on
working capital
11-Nov-10
T K Ray NTPC
Objectives to be fulfilled
Encourage economic generation
Save
S
natural
t l resources
Help protect environment
Beneficiary
Gen
11-Nov-10
T K Ray NTPC
Load
Priority
P i it tto plants
l t with
ith llower variable
i bl costt off gen.
when reserved units are to be in service
11 November 2010
REC Presentation
Evolution of tariff
Single part
ABT
11-Nov-10
T K Ray NTPC
11-Nov-10
T K Ray NTPC
1. Fixed Charges
2 Variable charges
2.
11-Nov-10
T K Ray NTPC
11-Nov-10
T K Ray NTPC
ProblemsinGridoperation
Peak
Freq
Freq.
(Hz)
Load
(MW)
Off-Peak
Ti (hours)
Time
(h
)
T K Ray NTPC
10
Frequency
q
y problems
p
Wide frequency fluctuations:
- cause serious damages at generation/load ends
- damages are not perceived, quantified or evaluated
- not acceptable all over the world
No progress has been made to control these problems due to:
- absence of direct incentives or penalties for the utilities
- reluctance to introduce financial incentives or disincentives
11-Nov-10
T K Ray NTPC
11
Maximisation of generation
Load
(MW)
Off-Peak
Backingdownofgenerationtomatchthesystemload
ki d
f
i
h h
l d
reductionkeepingthemeritorderofgenerationinview
11-Nov-10
T K Ray NTPC
12
Presentation Outline
Electricity Pricing
Cost elements
elements, Objectives
Objectives, Power gen
gen. eco
eco.
Single part and two part tariff
ABT
Features, Mechanisms, Benefits
Scheduling, Real Time Operation
Trading Opportunities
11-Nov-10
T K Ray NTPC
13
ABT implementation
Western region: July 2002
Northern region: December 2002
Southern Region: January 2003
Eastern Region: April 2003
North Eastern Region: November 2003
11-Nov-10
T K Ray NTPC
14
Tariff Determination
As p
per Sec 79,, CERC has the jjurisdiction to regulate
g
tariff for the
generating companies owned & controlled by the CG
11-Nov-10
T K Ray NTPC
15
ABT Features
A day is divided into 96 time blocks of 15-minute each; Dayahead declaration for each time block:
Availability by Generators and Demand by beneficiaries;
Capacity Charges
based on the availability or DC of the generating station
Energy charges
based on scheduled drawal by the beneficiary
UI charges
payable/receivable by both generators/ beneficiaries for
deviating from the schedule; also subject to the grid conditions
11-Nov-10
T K Ray NTPC
16
ABT Features
Capacity charges are recovered at NAPAF & pro-rata recovery
below that.
that For generation above NAPAF,
NAPAF incentive at the rate of 25
P/kWh beyond NAPAF (DC=85%).
Energy charges are based on actual fuel price and normative
operating parameters. Energy charges are paid based on scheduled
generation.
UI charges
h
are linked
li k d to
t frequency
f
and
d are levied
l i d on deviations
d i ti
from schedules.
11-Nov-10
T K Ray NTPC
17
ISGS 500 MW
Aux
475 MW ex-bus
SEB1
11-Nov-10
SEB2
T K Ray NTPC
18
AFC components
a) Return on equity;
b) Interest on loan capital;
c) Depreciation;
d) Interest on working capital;
e) Operation and maintenance expenses;
f) Cost of sec fuel oil (for coal-based and lignite stations);
g) Special allowance in lieu of R&M or separate
compensation allowance, wherever applicable.
11-Nov-10
T K Ray NTPC
19
11-Nov-10
T K Ray NTPC
20
11-Nov-10
T K Ray NTPC
21
Part
a t II. Energy
e gy (Variable)
( a ab e) charge
c a ge
The energy charge is worked out on the basis of
P/kWh rate on ex-bus energy scheduled to be sent out
from the generating station
Energy
gy Charges
g
= ECRX RLDC SG(Ex-Bus)
(
)
11-Nov-10
T K Ray NTPC
22
11-Nov-10
T K Ray NTPC
23
UI Charges
UI RATE
U
UI RATE Vs FREQUENCY
800
700
600
500
400
300
200
100
0
48.5
UI RATE
735, 49.2
UI RATE FOR
BENEFICIARIES
408, 49.62
UI RATE FOR
GENERATORS
480, 49.5
180 50
180,
49
49.5
50
50.5
FREQUENCY
UI rate is capped at 408 paise per kWh for all generating stations using coal or
li it or gas supplied
lignite
li d under
d Administered
Ad i i t d Price
P i Mechanism
M h i
(APM) as the
th fuel
f l in
i
case when actual generation is higher or lower than the scheduled generation in the
frequency range between 50.3
50 3 Hz and upto 49.2
49 2 Hz
11-Nov-10
T K Ray NTPC
24
T K Ray NTPC
25
11-Nov-10
T K Ray NTPC
26
11-Nov-10
T K Ray NTPC
27
11-Nov-10
T K Ray NTPC
28
11-Nov-10
T K Ray NTPC
29
Trading Opportunity
GeneratingStations
The two areas marked X represent the off-peak
hour capability
p
y of the Central generating
g
g station
i)
11-Nov-10
T K Ray NTPC
30
Trading Opportunity
Generating Stations
GeneratingStations
ii) Find a buyer (other than State - C)
As long as the energy sale rate agreed upon is higher
than the fuel cost per kWh of the station.
It
would
also
reduce
the
technical
problems
T K Ray NTPC
31
Trading Opportunity
GeneratingStations
iii) The station may accept the schedule given by the RLDC,
but generate power to its full capability of 900 MW even
during off-peak hours.
11-Nov-10
Earn UI*
T K Ray NTPC
32
Trading Opportunity
State
The options for the generating station arise only in
case a State
St t has
h nott requisitioned
i iti
d it
its ffullll entitlement
titl
t in
i
the first place.
In fact, the same three options are available to State C before they get passed on to the Central station
C,
i) Requisition power from the Central station only
as per its own requirement,
requirement and draw power as per
the resulting schedule.
11-Nov-10
T K Ray NTPC
33
Trading Opportunity
State
ii) Requisition full entitlement of 360 MW from the Central
station for the entire 24 - hour period, find a buyer for the offpeak surplus, and schedule a bilateral sale. This would make
sense as long as the sale rate per kWh is more than the
energy charge rate of the Central station.
11-Nov-10
T K Ray NTPC
34
Trading Opportunity
State
iii) Requisition the full entitlement for the entire 24 - hour
period but draw power only according to its actual
period,
requirement . UI
11-Nov-10
T K Ray NTPC
35
1))
Prospective
p
revision of ISGS availability
y
States options
Rework the requisitions to ensure maximum economy in
the operation of power system in the state.
11-Nov-10
T K Ray NTPC
36
St t (SEB)s
State
(SEB) drawal
d
l reduces
d
and
d it receives
i
UI
payment
States options
Draw less than schedule & get UI
Reduce net drawal further by increasing own
generation & get additional UI
Draw as per schedule & forego UI
11-Nov-10
T K Ray NTPC
37
States options
Continue to overdraw and pay UI
Reduce
R d
nett drawal
d
l by
b lload-shedding
d h ddi or b
bringing
i i
up all available generation
T K Ray NTPC
38
Reduce own g
generation if respective
p
energy
gy rate is higher
g
than the UI rate
11-Nov-10
T K Ray NTPC
39
Generator required
q
to demonstrate the declared capability
p
y as and
when asked by the RLDC of the region
11-Nov-10
T K Ray NTPC
40
ABT Advantages
11-Nov-10
T K Ray NTPC
41
Benefits of ABT
a)
Grid discipline
b)
c)
Utilization of resources
d)
e)
Power Trading
11-Nov-10
T K Ray NTPC
42
post-ABT
pre-ABT
Western:
violations below 49HZ
111
267
15.3% of time
24% of time
Southern:
frequency in IEGC band
99.45% of time
31.14% of
time
Eastern:
frequency in IEGC band
95% of time
Northern:
frequency out of IEGC
band
11-Nov-10
T K Ray NTPC
43
Thanks
tapankray@ntpc.co.in
@
rayt3@asme org
rayt3@asme.org
11 November 2010
T K Ray NTPC
44