Al Tayar Plastic & Rubber Mfg. Co.

P.O. Box 4492 - Jeddah 21491 K.S.A.


Ferrara, 30th August 2016
SUB.: C-PVC de-bagging, silo filling and storing and extrudes feeding
To the kind att. of Eng. S. Nazeer
Dear Sir,
As per your kind inquiry and recent meeting on the 18th of August last, thank you very much for that,
herewith we are sending you offer no.2016.5350 Rev.0 relevant to C-PVC de-bagging, silo filling and
storing and extrudes feeding. Our proposal refers to your inquiry as well Penta long and qualified
experience in this field and covers the flexibility and reliability a C-PVC system and extruders feeding
system would need. Penta is highly specialized in design and manufacturing of automation systems
for the handling of raw materials that are mostly used by the plastic converting industries where
efficiency, flexibility, reliability and end product competitiveness are fundamental requirements for a
long lasting success.
For a better understanding of the proposed system, you may refer to the here listed main features of
our equipment & solutions.
a) De-bagging: For the incoming C-PVC by jumbo bags (bags too) a large 1.500 l hopper has been
offered. This hopper is complete with self-cleaning automatic filter, fan and min. level indicator. In
this way max de-dusting efficiency and lowest possible raw material waste will be ensured. An
extraction device, fitted at the bottom of each hopper, ensures a proper and safe material flow.
A rotary valve ensures the consistent feeding of the debagged C-PVC into the pneumatic conveying
line filling the silo .
b) Silos filling: An independent pressure pneumatic conveying system, having an approx. conveying
capacity of 10.000 kg/h driven by a heavy-duty Root type blower, transfers the C-PVC resin from
the debagging hopper into the relevant C-PVC silo.
c) C-PVC resin silos: One existing C-PVC silo will be filled. Assuming that Customer will be
offering the silo body only, Penta scope includes the following :
- A high efficiency / heavy-duty automatic self-cleaning filter
- Over-Under pressure safety valve
- Max level indicator
- Min level indicator
- Continuous level indicator that shows te actual level of product stored into the silos
- Product extraction aid that ensures consistent feeding of stored material
- Suction pot from where the suction nozzles the vacuum loaders are equipped with .

PENTA S.r.l.
Via Uccellino, 75/77 44028 Poggio Renatico - Ferrara
Tel.+39 0532 826301 Fax + 39 0532 826399
E.mail: penta@penta.piovan.com

d) Electrical control panels and management systems : One independent electric control panel has
been offered for manual and automatic control of proposed equipment, complete with OP .
e) Scope Penta scope includes :
- Listed offered equipment
- CIF Jeddah seaport delivery
- Start-up and commissioning
Our offer refers to the following main documents:
Offer

n 2016-5350 Rev.0

Flow sheet

n 2016.5350.001.00

Should you require any additional information / clarifications pls. dont hesitate to contact us, we are
at your full disposal and remain with
Best Regards
Penta S.r.l.

S. Bertolotti

PENTA S.r.l.
Via Uccellino, 75/77 44028 Poggio Renatico - Ferrara
Tel.+39 0532 826301 Fax + 39 0532 826399
E.mail: penta@penta.piovan.com

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

Index
A.0

Company introduction

B.0

General notes about our equipment and solutions

C.0

Prices and commercial terms of sale


C.1
Prices
C.2
Pricing
C.2.1 Packaging
C.3
Transport insurance
C.4
Delivery of materials
C.5
Terms of payment
C.6
Guarantee
C.7
Liability clause
C.8
Miscellaneous
C.9
Offer validity
C.10 Exclusions
C.11 Existing equipment

D.0

Technical data and performance parameters


D.1 Raw material
D.2
De-bagging unit
D.3 Pneumatic transports
D.4 Noise level
D.5 Filtration
D.6 Compressed air production and distribution system
D.7 Electrical wiring
D.8 Supporting frameworks

E.0

Operating data
E.1
General notes
E.2
Standards and norms
E.3
Electrical equipments
E.4
Compressed air
E.5
Surfaces treatments
E.6
Safety and hazardous areas and materials
E.7
Electrical control panel
E.8
Health / safety regulations and rules

F.0

Scope of supply
F.1
Basic plant configuration equipment and services

G.0

Documents and drawings

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

A.0

Company introduction

Personnel stability: Persons with key position have been with Penta since more than ten years granting
in this way to Penta Customers well consolidated experience and continuity in fact they can regularly
deal with the same sales and contract engineers.
Competence: Penta is a highly specialized company exclusively dealing with the plastic processing
industries: automation of the raw materials and / or compounded materials in powder and granular
form is our field of operation. The satisfaction of our Customers is our best advertisement!
Companys Policy: while most of our competitors are mainly going for engineering, Penta is putting a
lot of efforts on manufacturing as well. In fact, we do offer well-proven consolidated quality and
reliable services at very competitive price. That means, better quality / price ratio.
Customers: we are exclusively focusing on worldwide plastic converters.
Market: Penta is mostly dealing with export. Saudi Arabia is among our best markets since more than
twenty years !
Service: our sound reputation is based on the successful results we got and the continuous and active
support we grant to our customers.
Products: we engineer, manufacture and commission full automatic systems for the plastic industry.
The result are well-proven solutions that grant some essential basic features as reliability, flexibility
and safe operation of the plant and consistency of the final product.

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

B.0

General notes about our equipment and solutions

Referring to the offered equipment and solutions, the following would have to be noted:
De-dusting filters: all filters are automatic ones, i.e. are fitted with filtering elements that are
automatically cleaned by means of compressed air controlled by an electronic timer.
Pre-assembling: in order to reduce the erection time the major equipments are, as far a
technically and logistic possible, delivered pre-assembled.
De-bagging: the de-bagging system raw materials consists of compact and flexible unit suitable for
bags and 1,000 Kg big-bags.
Components: along with a well-designed system we do offer high quality equipment.
Electric panels and management control: The design of the electrical control panels and the
management system is based on tailor made software, we design, based on the specific process. The
hardware is sourced out from worldwide well reputable companies as Siemens, HP, Compaq, etc.
Further features:
Expandability of the system in case of upgrading of the plant;
Automatic control of the whole process as well as manual one of the various equipment
composing the plant;
Management control as stock, raw materials consumption, formulations, trouble shooting,
preventive maintenance, etc.;
Centralised control system and operators interface, by using a OP with a dedicated video graphic
system, that will enable a friendly operation of the raw materials preparation plant as well.

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

C.0

Prices and commercial terms of sale

C.1

Prices

Equipment as detailed described from pos. 1 to pos. 2


Electrical control panels and management systems as detailed
described under pos. 3
CIF Jeddah K.S.A. seaport delivery of the offered equipment
Total price

86.842,00

8.314,00

Services:
Start up and commissioning as detailed described under pos. 4
Total price
C.2

Pricing

The grand total has to be understood CIF Jeddah - K.S.A. seaport delivered in box containers
according to INCOTERMS 2010 including packing as far as necessary and usual for container
transport. Buyer shall pay any taxes, customs duties, fees and other costs
C.2.1 Packaging
Our offer includes packing as far as necessary and usual for containers transport and in particular:
- control panels are packed in wooden crate with barrier envelop
- equipment are on wooden pallet suitable for fork lift handling protected by shrink PE
- loose parts are on wooden crate suitable for fork lift handling protected by shrink PE
C.3

Transport insurance

Price includes insurance from sellers premises to Jeddah seaport.


C.4

Delivery of materials

3 months from order / receipt of L/C.


C.5

Terms of payment

100 % by irrevocable Letter of Credit confirmed by first rate European bank, (cost of confirmation to
be paid by the customer), issued at order and payable as follows:
- 30 % down-payment at order
- 70 % against shipping documents.

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

C.6

Guarantee

The Seller guarantees that all goods supplied under this contract shall be free from all defects in
design, workmanship and materials and shall be of appropriate quality in accordance with the
present technological standards.
This guarantee shall be for a period of twelve months from date of completion of erection, however, at
the latest eighteen months from shipping date.
Any defect covered by the aforesaid guarantee shall be remised at Seller's expense arranging the
replacement ex-works of damaged parts only.
The guarantee mentioned above shall not be applicable to the following:
C.6.1 Damage or defects which result from wear and tear.
C.6.2 Damage or defects resulting from modification of the supplies by the Buyer without the consent
of the seller.
C.6.3 Damage of defects which result from operation, maintenance and servicing not in accordance
with the instructions of the seller's supervising staff and / or the operating manuals and / or the
operating manuals and / or any other relevant instruction books supplied by the seller.
C.6.4 Damage or defects due to causes attributable to the Buyer's personnel and / or to the third
parties after delivery ex seller's works of the said supplies.
C.6.5 Damage or defects which result from causes under Force Majeure.
C.7

Liability clause

Penta liability is limited to services and / or supplies the present proposal / order confirmation refers
to. Excluded is any real and/or alleged liability claims that might be directly and/or indirectly
attributed to Penta in connection to the here offered/confirmed services or supplies for directed and / or
indirect damages resulting from loss of production, loss of profit, loss of image as well as
deterioration / loss of raw materials and/or finished products.
C.8

Miscellaneous

All disputes, controversies of differences which may arise between the parties in connection with this
contract shall be settled amicably. Should the parties not come to an amicable settlement, such cases
shall be finally settled under the Rules of Conciliation and Arbitration Chamber of Commerce by one
or more Arbitrators appointed in accordance with the said rules. The Court of Arbitration shall hold its
meeting at Milan, Italy.
The Seller's liability towards the Buyer shall only be as expressively set out in this contract.
The Seller shall in no event be liable for any consequential damages such as loss of profit, loss of
production, etc.
The Seller may adjust the technical specification if such modifications constitute an improvement of
the supplies in line with the technical progress provided that the contract price and the mechanical
guarantees remain unchanged.
C.9

Offer validity

One month from offer date.

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

C.10

Exclusions

The supply includes the equipment and services described in this offer only.
The following is excluded:
all parts highlighted by red colour in the here-enclosed flow-sheet n2016.5350.001.00.
big bags hoist, relevant railway / hanger cross.
big bags supporting structures.
C-PVC storage silos.
template fitted with anchor bolts and relevant nuts for anchoring the storage silo on the
concrete slab.
C-PVC pneumatic transport, equipment and electrical control panel from storage silo to
vacuum loader.
modification at the existing equipment.
conditioned air control room for electrical control panel.
civil works.
engineered components (if any ) that would have to be incorporate in our design.
noise insulation of product and air conveying pipes.
ducts / pipes for exhaust air from de dusting filters, vent pipes, blowers and fans.
steel frame of any nature for equipment and / or for piping.
mechanical installation of the supplied equipment, to be executed as per our drawings and
indications, as well as fork lifts, cranes and / or scaffoldings.
electrical wiring, to be executed as per our indications, from the main supply to the
electrical panels and from the electrical panels to all electrical utilities as motors, switches,
coils, etc.
compressed air distribution system, to be executed from your compressor to all pneumatic
utilities as pneumatic cylinders, automatic filters, fluidising devices, etc, accordingly to the
pneumatic utilities features (list of connecting point and relevant size, individual consumption,
features and pressure of the air etc.) indicated on our P&ID.
legalization of any documents including certificate of origin, invoices, etc.. called by the L/C.
transport of equipment from Jeddah K.S.A. seaport to your factory.
mechanical erection supervision.
local transportations, hotel, food, beverage and laundry, local taxes (if due) of our technicians.
whatever else not specified in this offer.
C.11

Existing equipment

It has been assumed that all existing equipment and / or equipment supplied by others are perfectly
working and fit to the offered system. However, in case Penta will be requested to perform any
modifications / repairs / replacements of existing equipment and / or equipment supplied by others the
relevant cost will be invoiced as per actual costs for labour and / or required parts.

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

D.0 Technical data and performance parameters.


The engineering details of the equipment / plant will be developed according to the technical notes of
the following paragraphs as well as the following complementary data you will provide us (products
samples, products data sheets, recipes details (minimum and maximum quantity), etc.).
Please note that not having these data could prejudice the correct design of the plant and might lead to
not proper functioning of the system. In the latter case further costs, if any, which might be needed in
order to rectify equipment and/or technical solutions cant be directly and/or indirectly attribute to
Penta and would have to be bear by others.
D.1

Raw material
Raw material:

Form:

Bulk weight (Kg/dm3)

C-PVC

Powder

0.55

Rheological features of raw material: For this project it is been temporarily assumed that the raw
materials correspond to comparable products of general industrial origin currently used in well
comparable automatic compounding plants with regard to their quality and processing behaviour and
rheological features. For all powdered materials it has been assumed that normal flow characteristics
are granted and the moisture content is below 0.3 %. Samples as well as data sheet of each of the a.m.
raw materials would have to be provided to supplier prior to beginning of the detailed engineering of
the plant especially bulk density, flow ability and (for solid additives) the relevant melting point. If not
differently specified melting point over 85C will be considered. Based on that we reserve the right to
change the design accordingly: any impact on costs would have to be re-adjusted accordingly.
Note: in case of order a sample and the relevant data sheet (rheological features, etc.) will be required
for further evaluation and proper design of the various parts of the plant.
D.2

De-bagging unit : Our project includes n 1 de-bagging unit as following:

D.3

De-bagging unit:

Capacity (m3):

Stored raw material:

Suitable for de-bagging of:

1.5 m3

C-PVC

bags / 1,000 Kg big bags

Pneumatic transport : Our proposal includes the following pneumatic transport:

Pneumatic
transport:

From
/
to:

Products:

Type:

Capacity
(Kg / h):

Max product
distance
(m + bends):

Max air distance


(m + bends):

C-PVC de bagging unit


/
Storage silo

C-PVC

Pressure

10,000

36 + 5

12 + 3

Differently the requested data concerning distance, pneumatic transport capacity, pipe diameters,
blowers, etc. would be needed in order to check the conveying features of the system and reconfirm if
they are suitable or not. In the latter case, the conveying systems would have to be upgraded as needed
and a fresh new technical and economical proposal would have to be submitted.

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

D.4

Noise level.

The individual noise level of the machines and apparatus is normally less than 85 Db.
D.5

Filtration

At the end of the pneumatic transports and at on the de-bagging units a dedicated automatic jet filters
will be provided; therefore the powder emissions will be less of 15 mg / Nm3 of filtered air.
D.6

Compressed air production and distribution system.

We exclude materials for carrying out the pneumatic distribution system from your
compressed air network close to the plant, to users such as galvanised pipes, pipe fittings and joints,
reducers, filter' s lubricators, cocks and valves, flexible connections, etc.
To enable you to locally procure the necessary materials and design the compressed air
distribution system, we will supply the following:
- list of connecting point;
- individual consumption;
- features and pressure of the compressed air.
D.7

Electrical wiring.

We exclude materials for carrying out the electric wiring from your net to new switchboard and
from this one to all the users and in particular: cables raceway, lids, conduits, shunting boxes,
flexible connections, pipe fittings power cables, special cables (wherever required).
To enable you to locally purchase the necessary materials and perform the electrical wiring, we will
supply the list, features and consumption of the electrical users.

D.8

Supporting frameworks.

We exclude all the supporting framework.


To enable you to procure the a.m. parts, our scope of supply includes the relevant system drawings
that consist in detail of:
Dimensional drawings complete with equipment bearing points and relevant weights.
Consequently, the following is specifically excluded from our scope of supply:
- static calculations of the frames as well as sizing of beams, profiles, plates, etc.
- workshop drawings;
- material list and relevant specifications.

10

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

E.0

Operating data.

E.1

General notes.

Plant destination:
Altitude above sea level:
Ambient temperature range:
Relative humidity:
E.2

Standards and norms.

System of measure:
Language:
E.3

380 V / 3 Ph / 60 Hz
suitable for installation safety area
380 V / 3 Ph
220 V AC
24 V
+/- 5 % of line voltage
+/- 1 % of line frequency
neutral conductor.

Compressed air.

Effective working pressure:


E.5

metric
English.

Electrical equipments.

Overall designation:
Electrical parts:
Supply voltage:
Control voltage:
Signals voltage:
Permissible voltage fluctuations:
Permissible frequency fluctuations:
Protective measure:
E.4

K.S.A.
1 mt a.s.l.
+ 10 to 48 C
40 to 75 %, no condensation.

7 bar.

Surfaces treatments.

Material in touch with the product:


please refer to the here enclosed equipment descriptions.
Painting:
Steel parts:

5015 or to be agreed.

Piping, non-rusting steel/galvanised


and aluminium parts:
no painting required.

11

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

E.6

Safety and hazardous areas and materials

According to our knowledge and experience made on similar plants, there arent hazardous areas
within our battery limits of the plant. Thus, such kind of plants would have to be classified as SAFETY
AREAS.
Differently, detailed information about raw materials along with features and data sheets relevant to
hazardous features / behaviours of the handled products would have to be submitted for further
evaluations that might lead to different technical solutions than the proposed ones and relevant impact
of given prices.
E.7

Electrical control panel

If not differently specified the offered electrical control panels are designed to be installed in an
environment having a max temperature of 25 C and relative humidity of approx 50 %.
E.8

Health / safety regulations and rules

For health and safety view point the plant this plant has been designed and offered as per consolidated
technology, experience and standards that, to our knowledge, should be applicable in the customers
country too.

12

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

F.0

Scope of supply.

F.1

Basic plant configuration equipment and services.

C-PVC de bagging unit and storage silo feeding as per here enclosed flow-sheet n 2016.5350.001.00
We herewith list in detail the plant composition with reference to a.m. drawings and to the
positions indicated in the flow sheet.
Item Q.ty Description
---------------------------------------------------------------------------------------------------------------------1
C-PVC bags and 1,000 Kg big bags de-bagging.
1,1

De-bagging hopper - 1.5 m3 - AISI 304.

1,2

Level probe - min.

1,3

Automatic bags jet filter - 3,5 m2 - AISI 304.

1,4

Electro fan - 1.5 kW - painted carbon steel.

1,5

Compressed air extraction system - injectors type - complete with accessories.

1,6

Butterfly valve - cast iron / AISI 316 - manually operated.

C-PVC pneumatic transport from de-bagging unit to storage silo.

2,1

Rotary valve - NN - AISI 321 - complete with accessories.

2,2

Root type blower - Complete with sound proof cabin.

2,3

42
14
5
3
19
19
1
1

m of piping - AISI 304.


"U" bolt.
Bend - AISI 304 - Large radius.
Bend - AISI 304 - R 1.5 D.
"Morris" type connection.
Electric continuity.
Quick coupling.
Hose heavy spiral - l = 3,000 mm.

2,4

Automatic bags jet filter - 16 m2 - AISI 304.

2,5

Safety valve.

13

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

Item Q.ty Description


---------------------------------------------------------------------------------------------------------------------2,6
1
Level probe - max.
2,7

Level probe - min.

2,8

Continuous level indicator , yo-yo type complete with OP display

2,9

Compressed air extractor - injectors type - complete with accessories.

2,10

Compressed air extraction system - complete with accessories.

2,11

Butterfly valve - cast iron / AISI 316 - manually operated.

2,12

Buffer tank - 50 dm3 - AISI 304.

14

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

3
3,1

Electrical control panel and management system.


1

The a.m. plant will be manage by a new electrical control panel / management system
having the following technical features:
Technical data:
- Dimensions (preliminary)

: approx. length
1.200 mm.
: approx. height
2.000 mm.
: approx. dept.
500 mm.
The logic will be provide by a Siemens PLC.
The control of the electrical utilities will be done by an OP (Operator panel) Siemens
type KTP600.
Alarms signals will be shown by a proper video page.
Electric power
: 380 V - 60 Hz.
Control voltage : 220 V A.C. 60 Hz.
Protection degree : IP 54.
Internal components for the electrical control board:
- master switch;
- power contactors;
- motor protection by thermal overload circuit breakers with voltage, high rupturing capacity fuses or motor protection switches.
Sequencing and interlocking control by PLC logic.
The PLC Consists of:
- central controller with mains supply;
- central processing unit (CPU);
- input modules;
- output modules;
- all necessary connecting cable within PLC modules;
- all units are assembled and wired to modular terminal blocks;
- a duct wiring system is provided for interwiring the switchgear.

15

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

Item Q.ty Description


---------------------------------------------------------------------------------------------------------------------4
Start up and commissioning.
Our scope of supply include the supervision during start up & commissioning
operations as following:
N 1 technician for start up & commissioning for up to 7 days including travel
time. Customer will provide local workers.
The number and qualification as well as equipment and tools will be informed later
based on the commissioning schedule.
The time of commissioning will depend from the local skilled workers and available
equipment and tools.
During start up operation, our technicians will put in operation the equipment, first
without products, and then they will test the plant capacity and performances as per
paragraph D of the present offer.
In addition to our technicians costs, entry working visa included, n 1 air tickets
are already included in our scope of supply, as described in the paragraph
exclusions, the buyer will be paying the following only:
- hotel, food, beverage and laundry
- local transportation
- any local expenses related to the presence / works of our technicians.
Remarks
Our technicians have to complete their job in a better way and as soon as possible.
In case they have to stay in the yard inoperative not due to sellers responsibility, this
time will be charge to buyer as working time. Any additional days based on tariffs in
force.

16

Al Tayar (K.S.A.)
Off. n 20165350 Rev.0 of 30st August 2016

G.0

Documents and drawings.

Our scope of supply include n 1 copy (in software version on CD support) in English language of the
following documentation:
Flow diagram (P& I);
Foundation indications, footing and loads static and dynamic;
Layouts of the various parts of the plants;
Electrical diagram of the electrical control panel;
Terminal strips of the electrical control panel;
Compressed air list and consumption users;
Electrical list and consumption users;
Dimensional drawings & machinery loads for your calculation of supporting frameworks;
Documentation for:
operating maintenance;
spare parts;
List of documents to be provided by customer to the supplier prior to initiate the engineering
Buildings drawings complete with all necessary indications/details;

17