Professional Documents
Culture Documents
Abstract: The growing demand for reliable and environmental friendly energy has led to an increased number of High Voltage DC transmission systems. Researchers and manufacturers worldwide are pushing the
limits further to meet tomorrows demand. At the same pace that the HV DC equipment is advancing, the
testing equipment for HV DC equipment have to advance as well so that manufacturers can prove the performance and quality of their components and researchers have the tools to further investigate the insulation
systems at increased voltage levels. This paper provides a brief overview of the different HV DC test requirements and procedures according to IEC standards as well as Cigre recommendations. The peculiarities
for HV DC cables, DC bushings, converters, etc as well as general purpose testing will be introduced and
discussed. An alternative to the common Greinacher cascade UHV DC generators will be presented in detail.
1.
INTRODUCTION
WITHSTAND TESTING
Converter Transformers,
Smoothing Reactors and Bushings
The minimum voltage test ( 10 min) is for proving performance of IGBT valves which derive the
necessary operating power from the voltage between the terminals. Valve support d.c. voltage
test and multiple valve unit d.c. voltage test to
earth follow the same scheme as LCC.
The test duration is significantly extended for Development tests with 30 and 40 LC24 cycles compared to 8 and 12 LC24 during Type Test for LCC
and VSC cables respectively.
2.3.
Power Cables
Converter Transformers,
Smoothing Reactors and Bushings
Power Cables
PR testing on cable is done for non-polymeric cables and polymeric cables used with LCCs. Polymeric cables used with VSCs are not exposed to
PR and consequently not tested.
During PR testing, the cable is exposed to LC24
heating/cooling cycles. During this cycle, the polarity is reversed every 4 h for non polymeric and
every 8 h for polymeric cables with an allowed
transition time of 2 min. This procedure is repeated for 10 heat cycles at 1.4 * U0. For polymeric cables 8 heat cycles at 1.45 * U0 are applied for type test and 20 cycles at 1.25 * U0 during development tests
4.
4.1.
Bushings
Isolators
5.1.
Only cables are tested with impulse voltages superimposed on the DC voltage. Table 1 shows
possible configurations of the combined voltages
and the configurations. The indices used are 1
for lightning and 2 for switching impulse, while
S stands for same and O for opposite polarity.
Table 1: Combined voltage tests
Polarity
DC
Lightning
Impulse
UP1
Switching
Impulse
UP2
Pos.
Pos.
Pos.
UP2S
Neg.
Neg.
-UP1
Neg.
-UP2O
Pos.
Neg.
UP1
Pos.
Neg.
UP2O
-UP2S
5.2.
DC and AC Testing
Stored energy
The considerations on thermal and electrical design for long term testing also apply for the measuring equipment. Stressing the equipment with
heat and electrical field over a long time will affect
the aging of the components and impact the long
term stability of the measuring device.
Long term stability can be estimated from experience and material parameters of the used components, mainly capacitors and resistors for the
high voltage dividers and the low arm.
6.5.
Ripple measurement
Although the ripple factor is as important for describing a DC voltage as the frequency is for AC
voltages, its measurement was often not realized.
This is due to the fact that a separate measurement system had to be used for the ripple measurement. For most DC generators, the ripple frequency is the power frequency or a multiple of it.
In praxis, the limit requires a bandwidth of approx.
7 times of the ripple frequency. For Greinacher
cascades the bandwidth must be 350/420 Hz and
700/840 Hz for symmetrical voltage doubler circuits for power supplies with 50/60 Hz mains frequency.
HVDC dividers realized as resistive dividers have
very limited bandwidth and may produce unacceptable measuring errors for frequencies of a few
Hz already: Capacitive compensated dividers are
mandatory for ripple measurement.
Modern digitizers provide sufficient resolution and
capabilities to measure the arithmetic mean value
and ripple with the required uncertainties within
one measurement device.
7.
Theory of Operation
HV output
Y2
H1
D1
D2
CD1
RB1
CD2
RB2
RM
CM
H2
X1
X2
Mains input
M
DC return to current meter
To kilovoltmeter
Polarity motor
Height [m]
top electrode [m]
Voltage
[kV]
@ ripple < 3 %
Current [mA]
Greinacher
Cascade
12
9.7
1500
20 cont.
Modular
Cascade
11.2
3.1
1600
1800 (@ 5 mA)
10 cont. / 20 (4 hr ON)
A
B
C
D
7.2.
7.3.
Advantages
9.
[4]
[5]
[6]
[7]
[8]
8.
CONCLUSION
REFERENCES
[1]
IEC SMB/4272/R, TC 115: Strategic business plan, High Voltage direct Current Transmission for DC voltages above 100 kV
[2]
[3]
[9]
Power
Cables;