Developing a Monitoring and Evaluation Framework

A monitoring and evaluation (M&E) framework is the holistic approach that can address your programme,
needs, monitor programme processes and outputs and evaluate goals and objectives. It should
encompass the programme planning process right down to the documentation and dissemination plan.

An M&E framework should always be developed before a programme has been initiated.
However, despite the pleads for M&E to built in, or rather mainstreamed in all operations, rapidly
constructing an M&E framework during a programme rather than before, is quite common (especially
among smaller and capacity restricted organizations). Sometimes, this afterthought approach can work,
for example in the case of programmes with simple goals – consider a basic capacity building programme
with the sole aim of building capacity in certain skills, a simple evaluation of knowledge following the
programme at timely intervals can allow you to assess impact. However if your programme seeks to
utilize this capacity building for a social/cultural/economic/structural change (which most of us do!) then
this afterthought approach is always ill advised.

Although creating a detailed M&E framework for larger programmes is time consuming, the process will
be worth the time invested. Not only does an M&E framework help in monitoring and evaluating the
programme, it is a detailed planning process that will aid you in strategically thinking through every detail
of the programme, from resources required to how the results will be disseminated. It is a key investment
that promotes implementation and will ultimately save time and stress.

Although, there are a number of approaches to creating a M&E framework. It is my personal preference
to conduct this activity in six steps. For those organizations who are limited in time and capacity and if the
programme is not extremely detailed, I suggest that you prioritize Step 1, 2 and 3.

Six Steps to Creating an M&E Framework

Step One – Participatory Programme Logic Planning

This is an approach to programme planning and design. Participatory programme logic planning refers to
the process of examining what your desired goal is and strategically thinking through proposed activities
to ensure that you maximize your ability to attain this goal. It is recommended that this process is
participatory and that a whole range of relevant expertise’s, partners and even the people whose life you
wish to positively impact should be involved. Simply because a whole range of stakeholder are involved, it
allows you to anticipate risks and acknowledge assumptions you are making that will lead to
the success of a programme. It also promotes the examination of unexpected outcomes.
Program logic planning can be represented as vertical logic that will highlight a cause and effect
Niamh Barry 2010| niamh.barry85@gmail.com
2|Page

relationship between your programme activities.


Like this:
Activities Outputs Outcomes Objectives Goal.

Or as a diagram like the causal pathway:

This is a very important step – all inputs must be enough to produce activities and these activities must
eventually produce the goal. Its logic is based on cause and effect or the ‘theory of change’ but you must
be careful to think of challenges during this exercise. Overall the participatory programme logic planning
will:

Help you gain a more fully shared understanding of how they believe change is likely to occur your
operational context

Identify gaps in the initial design of the programme and reach consensus to overcome these
challenges

Form the conceptual basis for the M&E framework

Niamh Barry 2010| niamh.barry85@gmail.com


3|Page

Step Two – Filling in the Logical Framework

Following the programme logic planning you are in a position to fill in the logical framework. As your
activities, outputs, outcomes, objectives and goal (s) are already established, you must begin to fill in the
full logical framework.

a) Insert all inputs into the log frame


This could include various technical support, human resources, financial resources, equipment etc
b) Establish indicators for all outputs, outcomes, objectives and goal(s)
Indicators enable us to track progress, demonstrate results, and take corrective action to improve service
delivery. Establishing indicators is a usually a simple and logical procedure – ask yourself if that output,
outcome, objective, goal is achieved then how can we know? It must follow the SMART principal. An
example of indicators for a goal is as follows:
Goal: A program has the goal to increase community knowledge of HIV prevention and access to HIV
testing treatment and care through targeted health talks
Indicators:

Number of community members reached

Improvement in community members knowledge on HIV

Improvement in number of people testing

Improvement in the number of people receiving treatment

Increase in condom use

Niamh Barry 2010| niamh.barry85@gmail.com


4|Page

Reduction in HIV transmission

The number of indicators per output, outcome, objective, and goal depends on the strength of the
indicator to capture the achievement. Indictors must also be numerated when applicable. Please do that
when we talk about any of the below type of indicators: Increase, Decrease, Improvement, Change, Etc.
We can only measure these if we have a BASELINE to compare it with. A baseline is information on
whatever we wish to impact prior to our program intervention.

c) Ascertain all indicators have a means of verification (MoV)


The indicators that you created are only useful when supported with sound data collection. For every
indicator you create you must be able to verify it. That is, you must be able to collect data to prove that
your indicator is true.
Example:
Indicator: Decrease in the number of TB patients lost to follow up
MOV: National TB registers
Indicator: Increase in TB/HIV knowledge among clinic staff
MOV: TB/HIV knowledge questionnaire

In the end, MoV’s are the data collection tools you will use to monitor progress and evaluate impact.
Some may already be in existence such as national registers; others will have to be created. A list of all
the data collection tools that are already available and those that need to be designed should be
prepared. Simple design is always the best, do not collect too much data that is irrelevant to your
programme and above all ensure that they collect the desired indicator (s)!

d) Insert a time line for the collection of each indicators and persons responsible.
Some indicators may be collected daily and others may only be collected annually. A time line should be
devised for the collection of all indicators along with an allocation of persons responsible. Timelines will
support in project planning and consistent data collection.
e) Based on your programme logic discussion, consider all assumptions to your programme’s
success.
As we all know, despite careful programme logic planning this does not guarantee achieving the
programme goals. For example: supplying ARVs to a rural clinic to support treatment for HIV may not
translate to these ARVs being utilized. You are making the assumption that:

Community members are open to HIV testing and blood draws

Community members found positive is willing to use ARVs

Community members can avail of adequate nutrition to help take the ARVs with

There is no stigma or non disclosure in the community


Niamh Barry 2010| niamh.barry85@gmail.com
5|Page

There are no misconceptions and myths in the community

The community members further from the clinic can avail of transport…
You must note all your assumptions to your projects success and consider methods to mitigate these,
should they arise.

Following the creation of the logical framework there are a number of other steps to complete for the
development of a full and detailed M&E framework.

Step 3 Data Tool Collection Guide

In the past, I have found it extremely useful to create a data collection tool guide. This is a guide on how
to use all the data collections tools stipulated in the logical framework. It should have the following content
on each tool:

What the tool is? (approach/method/design)

How to use the tool?

When to use the tool?

Persons responsible for using the tool

What indicators the tool collects


I have found it quite useful, to have a data collection tool guide in circumstances where people who will
be collecting the data have little experience with M&E. A brief training should be conducted on the data
collection tool guide.

Step 4 Reviewing Revising and Reporting Plan

The reviewing revising and reporting (RRR) plan is an integral part of a monitoring and evaluation
framework. The purpose of the reviewing, revising and reporting plan is to support the implementation of
the M&E framework. The RRR plan is usually a 12 month plan. RRR plans provide an internal RRR
structure, however the reviewing and revising component should actively work in conjunction with
external reporting requirements.
The objectives of an RRR plan are as follows:

To monitor progress made on programme activities and indicators

To Identify and correct programmatic /data collection challenges early

To promote programmatic structure and internal reporting as a routine function of the implementing
team

Niamh Barry 2010| niamh.barry85@gmail.com


6|Page

Reviewing is a process by which the implementing teams’ activities, indicators and data collection
methods are consistently monitored. Its purpose is to focus on program’s overall achievements,
challenges and emerging issues, based on information obtained through the M&E framework/processes.
Revising is the action the implementing team takes following a reviewing process. This could mean
redesigning an activity area that is failing to meet indicator requirements, changing a data collection tool
to make it more user friendly or focusing more specifically on a particularly successful activity area.
Reporting is a routine and focused process by which the implementing team collectively discusses
progress towards established programmatic indicators.
The RRR plan combines textual and visuals descriptions of how the RRR component of the M&E
framework will be implemented. This could include monthly indicator meetings, quarterly revising
processes and interim and annual reporting. It should also describe how information flow is conducted
and managed.
Step 5 Documentation and Dissemination Plan

Information provided by a strong M&E framework is invaluable. Organizations should always try to
document: good practices, success stories and case studies. Information from a well monitored and
evaluated programme will facilitate the sharing of ideas for action among other organizations working in a
similar focus area. A good process of documentation will provide information on what people are doing
and what’s working, what communities have learned from their experience and how it made a difference.
They will provide inspiration and show what’s possible. Plans for disseminating the M&E findings (to
journals, online forums, partners etc) including the documentation should form a critical part of the overall
M&E activities.

Step 6 M&E Plan

An M&E plan is the summary of the M&E framework. Very simply, it is a description of how in practice, the
logical frame, RRR plan and documentation and dissemination plan work will work to effectively monitor
and evaluate the programme. It should be approx 3-4 pages long.

Niamh Barry 2010| niamh.barry85@gmail.com