Professional Documents
Culture Documents
Rehabilitation Manual
Learning from the Holcim Experience
For future reference, thank you for citing this report as:
CNRS-L/AFDC/IUCN/Holcim. 2014. Mediterranean Quary Rehabilitation Manual: Learn the Holcim Experience.
IUCN
AFDC
Christine Maksoud
Rita El-Hajj
Mufleh Al-Alaween
Elias Chnais
Boulos Frangieh
Ziad Samaha
Mediterranean Quarry
Rehabilitation Manual
Learning from the Holcim Experience
Credits
The designation of geographical entities in this book, and the presentation of the material, do not imply the expression of any
opinion whatsoever on the part of IUCN, CNRS, AFDC, AFC and ECO-MED concerning the legal status of any country, territory,
or area, or of its authorities, or concerning the delimitation of its frontiers or boundaries.
The views expressed in this publication do not necessarily reflect those of IUCN, CNRS, AFDC, AFC and ECO-MED.
IUCN and the other participating organizations do not take any responsibility for errors or omissions occurring in the translation
into Arabic of this document whose original version is in English.
This publication has been made possible in part by funding from Holcim Lebanon.
Published by:
Copyright:
Citation:
ISBN:
978-2-8317-1749-4
DOI: http://dx.doi.org/10.2305/IUCN.CH.2015.05.en
Cover photo:
Christine Maksoud
Layout by:
Printed by:
Available from:
Table of Contents
List of Figures
List of Tables
Table 1. Summary of HQS specificities and constraints, and suggested key rehabilitation objectives
Table 2. Plants used as seeds or seedlings in the rehabilitation of the HQS
Table 3. Objectives and techniques of the design
List of Acronyms
QRD
IUCN
ROWA
CNRS
AFDC
AFC
IDAF
HQS
DEM
BOQ
Bill of Quantities
CSR
I. QUARRY REHABILITATION:
AN imPOSSIBLE MISSION
10
4. AFC experts:
- Rachid Abou Chacra
- Joe Abou Chacra
- Boulos Frangieh
5. Eco-Med experts:
- Alexandre Cluchier (Ecological engineer)
- Christophe Coton (Ecological restoration)
- Julien Viglione (Ecologist)
- Paolo Varese (Flora and ecological restoration)
This report comes as a third step after a first phase (January 2012 - August 2012) focused on initial assessments (Arab Resources
Development, 2003; Alomari and Abbadi, 2012; Chnais and Poyatos, 2012), and a second phase (September 2012 - November
2012) concerned by the design of the rehabilitation scheme (CNRS/AFDC 2012). It covers the last implementation, supervision
and documentation stage of the project (May 2013 - April 2014).
Building on the experience of Holcim Lebanon in rehabilitating one of its degraded quarries after excavation activities, this
report will provide guidelines for rehabilitation practices in Lebanon and the Mediterranean. It will suggest milestones towards a
successful rehabilitation process and discuss the challenges and constraints facing restoration initiatives while highlighting the
main elements and lessons learned for future rehabilitation attempts in limestone quarries.
11
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
14
This rehabilitation initiative supports Holcim Lebanons credibility towards the local communities in dealing with the
environmental challenges of its activities and commitment to mitigate the impact. Furthermost, this initiative is presented as a
pilot project to serve as a model that can be replicated in Lebanon and the region.
Quarrying activities in the HQS have resulted in serious environmental damages. The main site specificities resulting from the
accrued excavation misdeeds can be briefly summarized as:
Chekka
15
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
16
a. Step 1: Benchmarking
The project benchmarking is the official launch of the projects design/implementation process. It is based on the identification
of the project needs including assessments, expenses, risks, resources allocation, etc. This step is considered an investigation
phase through which different systematic observations are carried out to identify the sites potentials which will guide the
future phases of rehabilitation.
a.1. Biodiversity assessment
Biodiversity assessment consist of collecting information (inventories) on the fauna and flora species present in a given area.
As confirmed by the IUCN guide to biodiversity released in
April 2000 (Assessing the status and trends of biodiversity
is essential for sustainable development strategies at all
levels), performing a biodiversity assessment is one of the
main components of a rehabilitation process. It allows the
determination of the floristic composition, the abundance and
density of the main species, and the diversity of species; it
defines the bio-geographical and bio-climatic features of the
site; it sets the recommendations for the most suitable species
for restoration; and it proposes actions to optimize vegetation
reinstatement in the quarry.
The period of assessment is a key element, as Otherwise, it will
be of a limited success.
A proper biodiversity assessment is usually performed over a
period of approximately three to nine months. It may sometimes
require a longer time-scale (an entire year or more) to ensure that
it covers all the species life cycles. The period of assessment
can be however reduced, in other cases, if sufficient data is
available for the site/area.
In the HQS, the biodiversity assessment, including floristic composition, abundance, percent cover, diversity, ecological
resilience of the identified plant communities and grazing impacts, was conducted in late Spring (during the period
of 2012/5/23-21), (Chnais and Poyatos, 2012). Some of the identified species were Inula viscosa, Calicotome villosa,
Sacropoterium spinosum, Onionis pubescens and Capparis spinosa.
Taking into consideration the current state of the quarry and the weak ecosystem dynamics prevailing within its plant
communities, several species were proposed for restoration.
As for the fauna, only the red fox, vulpes was recorded during the assessment. No rodents were found onsite due to the
complete removal of topsoil. A low number of birds were identified, with the presence of disturbance-resistant birds such
as: Falco tinnunculus, Galerida cristata, Prinia gracilis, Oenanthe oenanthe, Corvus cornix, Passer domesticus, Oenanthe
hispanica, Oenanthe isabellina, Monticola solitaries (Alomari and Abbadi, 2012) with the exception of disturbance. Turtles
such as Testudo terrestris, known to be vulnerable species, were spotted in the direct site surroundings. Finally, Laudakia
stellio and Cyrtopodion kotschyi, were the only species of reptiles identified onsite.
17
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
This area is mainly occupied by the Sannine - Maameltain formation (C5), which is composed of massive gray to white
limestone belonging to the Cenomanian Turonian. The Chekka formation (C6) of Senonian formation and the Quaternary
formation (Q) can also be found in this area (Arab Resources Development, 2003)
The hydrology assessment revealed that the closest major river is the Jouz River that has related water courses most of
which are seasonal and active only during the rainy season. Field surveys showed that the Asfour stream is the major
seasonal watercourse in the area. A seasonal wadi is present on the north eastern side of the site (Dalton, 2012).
a.3. Social assessment
This assessment aims at identifying the major stakeholders
involved in the quarry rehabilitation process, their roles,
responsibilities, influence and degree of intervention.
Interviews with concerned stakeholders are an important
element guiding the concept of a successful rehabilitation
scheme.
Quarrying activities have a direct impact on surrounding
communities. Consultation meetings with neighboring
villages will thus highlight their main concerns and assess
their opinion regarding the quarried site. This step is of
major importance in orienting the quarry rehabilitation
design with respect to locals needs (recreational, touristic,
educational or social values anticipated from the project),
fears and expectations.
Taking into consideration the current state of the quarry and the weak ecosystem dynamics prevailing within its plant
communities, several species were proposed for restoration.
The Holcim rehabilitation project did not consider the social aspect as part of the assessments, so no social surveys
were performed. The decision making processes were exclusively kept to the Holcim representatives as they are the sole
owners, investors, and only beneficiaries of the project.
Scientific assessments and baseline surveys are key elements of a successful rehabilitation process. They highlight the
main socio-ecological aspects of a given site and therefore enable a better orientation of rehabilitation objectives and
schemes.
Table 1 summarizes the key issues of concern encountered onsite based on the surveys results, and highlights the
corresponding rehabilitation objectives and recommended actions in view of the sites constraints and specificities. This
table was developed upon the review of the flora, fauna and hydrological assessments performed during the first phase
of the design.
18
T A B L E
Sensitive key
issues onsite
Slow ecological
succession.
Few possibilities to
store water in soil
or natural
depressions. Thus,
rainfall will either
evaporate, run-off,
or drain quickly
into cracks in the
limestone.
The natural wadi
is the main water
source.
Uncontrolled
grazing onsite has
an impact on flora
cover (over 30%),
and perturbation
of the fauna life
cycle.
Turtles Testudo
terrestris are
vulnerable species
spotted in the
direct site
surroundings and
potentially present
onsite.
Possible hunting
activities onsite.
Poor vegetative
cover and high
disturbance
affected food
availability and
shelter for birds .
Reptiles
preference to
rocks like Laudakia
stellio and
Cyrtopodion
kotschyi are the
only species to
occur.
Rehabilitation
objectives
Limit soil erosion
and reduce water
runoff.
Promote
landscape
integration within
the surrounding,
and icrease site
capacity for
ecological
functionality.
Restore and keep
the site as close
as possible to
natural state.
Model for
restoration in the
region.
Serve for
educational and
research
purposes.
Improve fauna
presence and
use onsite
through habitat
creation and
management.
Recommended actions
1. Improve water availability
onsite.
2. Adjust timing, shaping,
and sizing of the
rehabilitation with respect
to fauna and flora life
cycles.
3. Substitution of early
successional species with
later successional
species to accelerate
ecological succession.
4. Enrichment of mature
community species to
increase the density of
their populations and
stabilize the system.
5. Reduce soil introduction
to limit risk of ruderal-in
vasive species potentially
present in the seed bank.
6. Soil can be mixed with
organic compost, gravels
and rocks to respect site
naturality.
7. Privilege, when possible,
transport topsoil from
neighboring reference
ecosystem in the site.
8. Benefit from direct seed
sowing and seedling
transplants.
9. Plan timing considering
rainfall periods and large
events, to provide soil
moisture for seed
germination and natural
regeneration.
10. Take into account the
wider landscape
functions.
11. Suggest long term
monitoring scheme based
on rapid assessment of
key species.
12. Use hard machinery from
Holcim in the rehabilitation execution.
13. Orient choice of species
to be used with respect of
existing species.
14. Promote habitat
creation for fauna
species.
19
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Project milestones:
- Gather the data (baseline surveys);
- Set the objectives;
- Search for a solution (concept);
- Illustrate with a design;
- Execute and supervise;
- Monitor the projects evolution over a given
period of time.
b.1. Objectives
Defining the rehabilitation objectives is one of the key
components of the project. No matter how wide the ambitions
are, setting clear objectives will help guiding the projects
activities into tangible results.
Knowing that the HQS site is characterized by serious environmental damages resulting from the excessive excavation
activities, the main objectives of the rehabilitation project were set as follow:
a. Re-integrate the quarry in its surrounding landscape.
b. Make the site safe and stable for frequentation.
c. Make the land functional after accrued usage and inquest a balance between environmental, social and economic
factors.
d. Reduce the long-term negative impacts on the environmental, social and economic levels.
b.2. Orienting the design
During the design phase of the rehabilitation scheme, aspects related to the season of intervention, the ecological
functionalities of the site, the integrated energy design, the landscape context, the site features, the water availability
onsite, the choice of plants, the available substrates (rocks, clinker, etc.), the natural dynamic zones, the technical tools to
be used, the budget, the project timeline, and the expected technical outputs, should be thoroughly considered in order
to achieve a successful rehabilitation plan.
b.2.1. Season of intervention
20
A rehabilitation scheme has to target the integration of the site with its natural surroundings
in order to create a robust environment based
on ecologically sound principles.
Site
heterogeneity
induces
significant
variations in landform which generates unique
microhabitats
under
various
conditions
(temperature, moisture, wind, light exposure,
etc) promoting microclimate differentiation at
a smaller scale, and therefore, higher biodiversity
potentialities.
21
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Wet areas encompass several microhabitats (surface habitat, shore habitat, etc.) serving as different niches for diverse
fauna and flora communities. Ponds are thus temporary water structures created in order to promote and boost the life
cycles of particular species, while improving landscape aesthetics and enhancing the sites ecological functionalities
b.2.7. Choice of plants
The success of plantation operations is strictly related to the choice of species with respect to the
concepts of biological integrity, local competitiveness and seed availability and adaptability
(Khater et al., 2003; Khater and Martin, 2007).
- Why re-vegetating a degraded area?
Vegetation is the best prevention against soil erosion. To re-vegetate holds many benefits such as conserving and
enriching native plant communities and improving wildlife habitats. It reduces soil erosion and water loss, and provides
shelter and shade while increasing soil fertility.
- What species to select?
As long as an intervention is planned (planting or seeding), the
major constraint is to make sure plant species are adapted to
the harsh conditions of the site. Hence, it is recommended
to select those from the list of species present in reference
ecosystems (being either neighboring ecosystems to the site,
or similar degraded sites in comparable environments).
Non-native plants might sometimes act as invasive species (competition with other plants over nutrients and water).
The use of native indigenous plants conserves the authenticity of the existing natural environment and contributes to
maintaining the unique character of the landscape. Native plants are more resilient and have a better ability to regenerate
after disturbance.
- What should be the source of the plants or seeds?
As plant growth follows specific biological cycles, seeds are not readily available throughout the year. The chosen
species are meant to replicate a natural Mediterranean coastal ecosystem as common in the quarry area. It would be
however impossible to grow all the species occurring within the sites proximity. However, with time, these species will
colonize the site again as the soil conditions and the ecosystem functions are restored.
The source of plants can be either from direct seed collection from natural populations or from transplanted plants from
stands or cuttings raised in nurseries.
Plant stocks and seeds used for the rehabilitation of a degraded
area are rarely available in nurseries. However, local councils
and land-care groups run nurseries specialized in indigenous
plants and sometimes keep stocks of local plants, or might be
able to collect seeds and grow the required plants.
22
The suggested list of species for plantation in the HQS is presented in Table 2.
T A B L E ( 2 )
Demographic Make-up of Maan Governorate
Seeds
Calicotome villosa
Seedlings
Quercus calliprinos
Pistacia palaestina
Salvia triloba
Olea europaea
Pistacia lentiscus
Oreganum syriacum
Ceratonia siliqua
Spartium junceum
Thymbra spicata
Pinus brutia
Thymbra spicata
Ficus carica
b.2.9. Rocks
The presence of rocks, stones and boulders highly contributes in breaking the monotonous aspects of a degraded site,
while creating safe microhabitats for particular fauna species (such as reptiles).
Different types of stones can be used in rehabilitation activities. However, the perfect choice would target rocks with
related value to the local landscape of the site in order to conserve its naturality.
If natural rocks already exist in or around the previously quarried
site, their use would bring an added value to the rehabilitation
process as the reuse of these leftovers would not only
valorize their presence onsite, but also contribute to achieving
the ecological rehabilitation targets.
The HQS rehabilitation design includes planted merlon-like
structures, which would improve the landscape and serve as
shelters for plants and animals.
23
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Natural dynamics zones serve as experimental areas for the study of natural dynamics and successions in degraded
sites with no human intervention for restoration. These areas have to be regularly observed and monitored in order to
understand natures potentials and compare (over time) the difference between the results achieved in rehabilitated
sectors to those reached in patches where nature was left to evolve on its own.
Hence, aiming to at understanding the natural processes involved
in the normal evolution of the landscape, some areas within the
HQS were left with no intervention for monitoring and scientific
research purposes. These areas will further serve as a reference
to determine whether the suggested rehabilitation scheme
succeeded in complying with natures trajectory.
b.2.11.Technical tools
Several tools were used to orient the rehabilitation scheme of the
HQS: a digital elevation model (DEM), topographic maps and a
water flow model.
The DEM thoroughly assesses the topography of the site. It
highlights the variability in terrain elevations over a specific area
and for exact spatial intervals (2.5m).
The DEM facilitated the production of a rainfall-runoff hydro
model, which facilitated the analysis of the sites hydrology in
order to better orient water management onsite. Flow direction,
flow accumulation and stream networks were assessed through
Arc Hydro.
The results exhibited a highly irregular terrain with narrow drainage
The DEM study facilitates the development of an in-situ
rainfall-runoff hydro model. It gives a clear location of
water drainage paths and collection areas.
paths, and detected areas where water is mostly collected.
b.2.12.Project timeline
The project implementation timeline is a schedule which sets for
each activity:
- The time for execution;
- The duration for achievement;
24
can be executed in parallel to reduce the overall timeline, and those which have to be accomplished sequentially. The
schedule should take into consideration the hours during which the employees are available, their vacations, and the
companys holidays.
The project should also have a fixed deadline for completion. Once the deliverables satisfy the projects funders,
beneficiaries, and end-users, the project is considered achieved. At this stage, post-closure agreements including postdelivery support, warranties, inspections and payments should
be carried out.
The key to a successful project implementation is
scheduling the priorities and optimizing time use.
Throughout the Holcim experience, schedules were submitted
before work initiation (Appendix 1).
b.2.13. Budget and investment
A project has to be set along with a budget which quantitatively
reflects the cost of execution. The budget exhibits the expenses
or financial liabilities which will allow implementing the related
project activities.
Budgeting is a crucial step in the design of a project. It predicts and calculates all the costs related to implementation
including labor, material, expertise, field expenses, etc. along specific budget lines.
Throughout the Holcim experience, time and money were invested to achieve quality end results.
Most of the material used for rehabilitation were already found onsite which reduced the expenses related to the purchase
of rocks (considering that Holcim is the only funder of this project).
With respect to a budget envelop of 255.000 USD set by Holcim Lebanon, bills of quantity (BOQ) including plantation,
labor work (terrain preparation), irrigation, material purchase, removal of existing material, and cost of maintenance and
management of the site over two years were developed.
b.2.14. Technical outputs
Many tools are available to facilitate the design of the rehabilitation scheme:
- Sketches: freehand drawings executed to develop and graphically demonstrate a concept. Sketches can be
considered as preliminary draft outputs of the rehabilitation schemes.
- Software products: computer programs which illustrate the technical detailed design along with the visual aspects.
The following technical outputs were attained in the process
of the quarry restoration design using Autocad, GIS and
Photoshop:
25
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Hidden for a long period across the year a crucial component triggering natural dynamic processes, water is the primary loop
of the final suggested design, sustaining long-term ecological dynamics across the quarry site dry environment.
This design is oriented towards creating a water web inside the quarry site to act as a network to slow down water runoff and
temporarily increase its availability onsite. The importance accorded to water availability makes the latter the core intervention
of the final adopted restoration scheme. This approach secures a pertinent future ecological reinstatement of the site by owing
it with a complex network of water ponds that will support fauna and flora development.
The rehabilitation scheme divides the quarry site into four main subunits: Highland, Cliffland, Coreland and Lowland according
to the main concept of the design aiming at creating coherently structured subunits respecting the key principles of ecological
restoration and providing a fair space for education and scientific research purposes (Table 3 and Figures 4 and 5).
The rehabilitation scheme divides the quarry site into 4 main subunits: Highland, Cliffland, Coreland and Lowland according to the
main concept of the design aiming to create coherently structured subunits respecting the key principles of ecological restoration
and providing a fair space for education and scientific research purposes (Table 3 and Figures 4 and 5).
T A B L E
( 3 )
Techniques
Highland
Cliffland
- Cover the area with an irregular layer of topsoil and plant it with native species
and shrubs.
- Make use of and expand the natural landform as an impluvium (catchment
basin) to retain soil.
- Install internal gabion structures (close and parallel to the existing impluvium)
to serve as a second defense line.
Create a water web throughout the quarry site composed of a network of three ponds aiming at:
- Slowing down water run-off.
- Guiding water across the site.
- Creating temporary water retaining structures
providing humidity to the site.
- Creating a network of sub-humid habitats in an overall
dry environment.
- Improving amphibians and insects frequentation.
- Boosting overall site visual appearance
- Use the clinker pile available next to the suggested P3 for ground leveling
within the low-land.
- Build a stone/retaining wall of 100 cm on the northern and eastern sides of the
existing clinker in order to retain soil and stabilize the structure, and mount 2
traditional stone walls of 100 cm height within the clinker along with small
terraces of 20-25 cm height to improve visual integration.
- Install a 20cm bed of gravels on top of the clinker to improve water drainage.
- Add approximately 80 cm of topsoil layer.
- Plant with the panel of species (trees and shrubs) used in the restoration of the
quarry site.
Coreland
Lowland
26
Objectives
Figure 5. Satellite image of the HQS displaying the four suggested subunits
27
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Figure 6. Initial rehabilitation design of the HQS (before and after site panoramas)
(This design was amended during implementation to cope with unexpected site constraints)
28
29
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
- Defining the next steps for work execution (workflow,workplan and deliverables).
c.3. From bare-land to structured-land
The implementation process of the quarry rehabilitation scheme is detailed in Appendix 2, which thoroughly presents
the workers involved in the execution of each activity, the duration of work, and the detailed quantities for execution.
Appendix 2 served as basis for the analysis provided in this section.
To achieve successful rehabilitation of the HQS, the site requires the installation of a number of structures in order to
shape the suggested design and to convert the existing bare-land into a productive structured-land: stone walls, gabions
walls, merlon-like structures, open excavated ponds, and topsoil addition.
c.3.1. Stone walls construction
Stone walls are a main component of the HQS rehabilitation design (Figure 6). Their construction consumed a great
amount of time and work effort, as walls are generally composed of several parts: foundation, footing, lifts, hearting and
stones.
The foundation is the surface on which the wall is built (Figure 7). Sometimes walls are built over a bed of crushed stone
or a bed of concrete. Walling over the bedrock is one of the best options, as this substrate is the most solid foundation for
construction (case of the HQS). In some cases (such as in the third level of the Lowland where clinker dust have greater
depth variation) walls were built over a foundation of barren soil surface. This method was adopted to avoid the use of
concrete and given that constructed walls were not meant to be large enough to require a solid foundation.
Stone wall construction has been practiced in Chekka-Lebanon
and the Mediterranean region for centuries. Calcareous stones
are locally available in Holcim Lebanon quarries, which further
lowered the implementation expenses. Stone is a hard material
which is not affected by decay. Irregular stones were used
during the construction to give a random shape for the wall.
While selecting stones, it is recommended to pick those with
at least one or more sides roughly angled at 90 to the other
sides, as acute or obtuse angled stones are much harder to
manipulate and would require extra handwork to adjust sides.
Footing is the bottom layer of stones which supports the wall. These rocks are called the foundation stones, since they
are usually the largest in the wall. As shown in figure 5, the walls across the quarry site have only one lift and are topped
with the cope which serves to add additional height and capping to the wall. The gaps between face stones are filled
with small stones generally called hearting. A solid structure is built when gaps between rocks are tightly filled with few
large hearting stones placed individually and not randomly.
Finally, walls have a batter, which is the angle of the face of the wall. This angle is created by the difference of depth and
every wall should have a narrower top than the bottom. The HQS walls are battered by 5 every 1m, as illustrated in figure 8.
30
31
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
32
Batter the wall! And reinforce the wall with an angle of 5 every 1m.
Trees and walls dont fit together, roots are free spirited, they dont like boundaries and they push walls away.
c.3.2. Gabion walls construction
Purchasing gabion baskets is better than manufacturing them from scratch as it is a time consuming job which requires a high
level of expertise.
Gabion baskets can also serve as tools to stabilize eroded areas as well as planting containers.
33
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
To determine the width and height of the gabions to be purchased as well as the number of gabion rows needed, the first
step is to measure the area desired to the area which will host the wall. The baskets are available in the market in different
sizes and styles and only require onsite assembly (Figure 7).
After leveling and smoothing the foundation with a backhoe, gabions can be installed and basket edges wrapped together
with wires to ensure stability.
Stones must be evenly distributed in the basket to minimize voids and provide an aesthetic appearance. Rocks diameters
must be bigger than mesh perforations to prevent stones from washing out through wires mesh.
In the HQS, gabions were used in two sections: the Highland and the Cliffland, and in both cases, baskets had uniform
dimensions [1m*2m*1m (length*width*height)]. The use of gabions in the HQS rehabilitation scheme is meant to stabilize
the added topsoil and prevent its erosion. As shown by the design, gabions baskets were split into two categories: one
where gabions are filled with rocks and backfilled with planted topsoil (in the Cliffland and in a part of the Highland: Figure
8), and one where gabions are filled with topsoil and planted (in a small section of the Highland intended for research
purposes to enable the monitoring of natural recovery of the degraded area without human intervention).
An additional coating of the back face of the baskets with geotextile blankets extending for an additional 1 meter under
the topsoil allows adequate water drainage and prevents soil erosion.
In planted gabion walls, baskets are tailored to be used as containers filled with rocks and topsoil and planted with small
shrubs (Figure 10). The installation of appropriate sized geotextile fabric in the baskets prevents soil percolation and loss
through gabion holes. Planted gabions further improve the aesthetic features of the rehabilitated Highland.
34
35
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Piles of rocks are useless to humans but are highly valuable for small wild creatures! Keeping these structures is a
must! And if not present try introducing some.
The construction of rock piles isnt usually a time consuming task as it can be mechanically performed with an excavator.
However, although these structures are easy to compile, it remains crucial to respect the order of their different layers.
From inside to outside, the S-structures are made of large rocks overlaid with topsoil and planted with native flora species
(to reduce visual impact).
After several visits to the HQS, it was observed that these rock piles were immediately vegetated. Snakes were also
detected.
36
A wide range of equipment can be used for excavation activities. Choosing the right equipment should take into
consideration access restrictions, ground conditions, type and depth of the desired pond and volume of soil/rocks to be
excavated.
Ponds in the HQS were created by digging a pit in a nearly leveled area. Long narrow ponds yield more water than square
ponds. However, rectangular shapes remain the most convenient for excavation equipment.
According to the water-flow model, the capacity of the HQS ponds doesnt exceed 50cm in depth. Capacity estimations
are made to ensure that enough water is stored in the pond to satisfy the intended water uses.
Once excavated, P2 was topped with a layer of compacted clay to improve impermeability and reduce water leakage. Silt
can also be used as a substitute of clay to create an impermeable layer.
Based on the results of the water flow model, which highlighted the areas where water mainly collects in the HQS
after rain events, three ponds were conceived in the Coreland section to collect rain water and reduce runoff. Different
dimensions were required with variable depths according to the outcomes of the water flow model. The ponds took
10 days to be dug and finalized. Located over the bed-rock, P1 was successfully installed and immediately started to
collect water (Figure 14). No clay layer was added to P1. P2 formed a mud-hole as the clay aggregated with the substrate
beneath. Accordingly, it was relocated to a nearby position on a bed-rock substrate where water indeed collected during
a rain event and further enlarged to convey a greater capacity. P3 had to be cancelled and filled with S-structures as it
did not collect water.
37
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
Stop water leakage! Add an impermeable clay or silt layer to reduce seepage. Always shape your pond
structure to actual water collection capacity.
Topsoil or productive soil, was largely used in the rehabilitation process of the HQS (Figure 15).
In the Lowland, topsoil was added to cover the clinker dust which resulted from previous quarrying activities. In other
subunits, topsoil was added to be later planted in order to accelerate natural recovery processes.
As the site was heavily disturbed, no topsoil was available. Hence, soil was extracted from neighboring undisturbed areas
and thoroughly analyzed to validate its suitability for plantation (Appendix 3).
Adding topsoil over the toxic quarry waste (clinker dust) of the Lowland promotes a nontoxic environment for plants
growth. Yet, since clinker is a very toxic material, it was recommended to add a thick layer of gravels (20cm depth) before
topsoil addition to prevent roots getting in direct contact with clinker. This method was indeed expensive, especially that
gravels had to be transported from a long distance.
Compaction ruins the soil and affects rooting and hinders growth.
Wet clay soils are highly compatible as clay material form water bonds which act as lubricants that bring together the soil
particles.
Due to the heavy machinery used on the HQS, the clay soil slightly compacted. Therefore, it was important to improve soil
structure through conventional scarifying or plowing of the compacted soil layer in order to create a favorable seedbed
for germination. Plowing to a depth of 30-20 cm was enough to break the aggregates and ruts of the upper soil layer and
prevent invasive weed development. The chisel plowing method is moderately inexpensive, it consists of raking the soil
surface with ripper shanks pulled behind a tractor (Figure 16).
38
Figure 18. Organic compost and peat moss amendments added to the topsoil
39
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
40
Plant preparation
Quercus calliprinos seeds were collected during autumn 2012 (October) from stands located in Ramlieh prepared in
AFDC nursery in winter 2012 (December). They were stored in the chiller without any ventilation for a month and a half.
Sowing process initiated in late January 2013 and ended in late February. Pinus brutia seeds were collected and prepared
in November 2012. The seeds geographic origin is Nabeh el Safa. Seeds were then stored in the shed for 4 months and
sowing process was accomplished during two days in early April 2013.
Ceratonia siliqua, Pistacia palaestina, Spartium junceum, Salvia triloba, Origanum syriacum and Thymbra spicata seeds
were collected from areas close to Ramlieh and planted in AFDCs nurseries.
Olea europea, Rhus coriaria, were purchased from several local nurseries.
During the transplanting process, the substrate used in the nursery was cocopeat and peatmoss; a substrate which
reduces weeds development risks. Slow fertilizer release was applied for 6 months before sowing to regulate the pH level.
Yet in nurseries, fertilizers arent needed unless they are used to boost the development of the rooting system and foliage.
Plantation
Lack of rain delayed the first phases of the plantation process in the HQS. Plantations were then initiated in December
2013. The entire plantation of a total number of 1533 seedlings took approximately 8 days (6 hours and 5 workers per
day) (Appendix 4).
The seedlings plantation followed the steps hereafter:
- All the equipment and plants needed in the plantation process were prepared and made easily reachable to the
workers.
- Plantation holes were prepared: 40*40*40cm, 5 liters of peat moss and 15g/plant of slow fertilizer release.
- Added material (peat moss and fertilizer) were then well mixed with soil until the medium is homogenized.
- The seedlings were placed in the plantation holes, which were then filled with soil. The soil must be firm around the
seedling to make sure that the roots are fully covered with topsoil.
No mulching was needed during the HQS rehabilitation. Optional additions of mats for weed control and shelters against
grazing can be performed. Tall plants such as Olea europea required stacking during the first year (Figures 20 and 21).
41
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
42
43
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
44
- The walls of the Lowland section were adapted to the existing topography. Four walls amongst which one was
double leveled were thus built instead of three. This adjustment was made due to the instability of the clinker dust
deposited over this area. Between the two additional walls a small road was left for small trucks to access the area
(Figure 24).
- Few adjustments were done in the Highland section which was initially devided into two parts: one with unplanted
gabions and another with planted gabions. The adjustment was made between these two sections due to a leveling
problem, as a deep sector was left as a physical split between the two parts. This amendment resulted in the
use of a reduced number of gabion baskets and the additional construction of a stone wall and another gabion wall
to close both sections and avoid substrate loss (Figure 25).
- The Coreland adjustment was based on a trial and error experiment. The first rain events were considered as the
base of the changes made to this section.
45
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
* Pond (P3) did not succeed to collect rain water. Therefore, partners decided to cover this pond with S-structures.
* Pond (P2) collected rain water but it had impermeability problems. P2 formed a mud-hole as the clay aggregated
with the substrate beneath. Accordingly, it was relocated to a nearby position on a bed-rock substrate where
water was collected during a rain event and further enlarged to convey a greater capacity.
- The last changes tackled plantations. As presented before, the recommended method of plantation was the creation
of patches with masses of plants. However, during execution, workers only created unequally linear aspects with the
vegetation (Figure 26).
Figure 25. Lowland adjustment, double wall constructed over two levels
46
47
,
II. THE CHEKKA QUARRY: FOLLOWING HOLCIM LEBANON S STEPS
c.7. Maintenance
Maintenance operations promote maximum performance of the site and increase the chances of its endurance. They
include frequent routine actions which ensure the proper establishment of the project elements in order to prevent
eventual failures. This activity, through which broken material is replaced, adjusted or repaired to save its intended
functional conditions, tests the sustainability of the projects units.
Maintenance operations promote maximum performance of the site and increase the chances of its endurance. They
include frequent routine actions which ensure the proper establishment of the project elements in order to prevent
eventual failures. This activity, through which broken materials are replaced, adjusted or repaired to save their intended
functional conditions, tests the sustainability of the projects units.
Two main types of maintenance can be performed: preventive maintenance
(which prevents the failure of equipment); and corrective maintenance (when
equipment fails and requires elimination and replacement).
48
49
One of the pioneer initiatives in Lebanon and the Mediterranean, the Holcim experience has proven the success of adopting a
scientific-based approach for quarry rehabilitation, integrating both social and ecological aspects. Throughout the rehabilitation
process, several challenges and constraints were confronted. Coping with these realities is a must to achieve a successful
rehabilitation scheme.
Many lessons arise from this experience. Learning from these lessons will definitely facilitate the orientation for future similar
rehabilitation initiatives in Lebanon and the Mediterranean.
The main purpose of a rehabilitation process is to reduce the gap between what existed before the perturbation (initial
state) and the post-rehabilitation status. It is mandatory to either perform exhaustive biodiversity assessments before any
activity is planned on a site or (in case this is impossible), to perform these assessments in neighboring similar ecosystems.
It is important to consider any restoration intervention as a medical transplant on a degraded ecosystem. The main
challenge resides in succeeding at integrating this transplant. They key to success is to therefore identify, within the
biodiversity assessments, key species to serve as indicator targets for the restoration. The more key indicator species to
orient the rehabilitation design the more the chances of success are.
The key step to ensure the achievement of a self-sustained restored ecosystem supporting clear onsite ecological functions
and efficiently connected to neighboring ecosystems is to escort the rehabilitation process far beyond the intervention
period. Clear successful results can only be observed after 4 to 5 years in Mediterranean environment, and monitoring this
progress is a key component of evaluating the success.
Keeping an emergency budget in the planning in order to be able to adapt to sudden difficulties is crucial.
Flexibility in implementation is key to success. Nothing is perfect. Sometimes, actual onsite rehabilitation might not
achieve to execute the conceived design per se. Being flexible and creative helps better adapting/coping with constraints.
Setting clear and concise objectives and goals from the beginning of the project, respecting the project timeline and in
case of complications, adapting to reality while always considering time priorities are basic elements to achieve a successful
implementation.
Team collaboration, dedication and constant follow-up are key to efficient achievements.
52
Bibliographic References
Alomari, K. and Abbadi, M. 2012. Ecological Rapid Assessment Surveys, HOLCIM Quarry in Chekka, Lebanon
Arab resources development. 2003. Description of the Environment, SLCB Quarry
Aronson, J. Fled, C., Le Floch, E. Ovalle, C., et Pontanier, R. 1993. Restoration and rehabilitation of degraded ecosystems in arid
and semi-arid lands.I. A view from the South. Restor. Ecol., 17-8 ,)1(1.
Aronson, J. and Le Floch, E. 1995. Ecologie de la restauration, dfinition de quelques concepts de base. Natures Sciences
Socits. Hors-srie: 35-29.
Atallah, Th., Hajj, S., Rizk, H., Cherfane, A., El-Alia, R. and Delajudie, P. 2003. Soils of urban, industrial, traffic and mining.
SUITMA, Nancy, Paris. 119 July, 2003.
Benayas R., Bullock, JM. And Newton, AC. 2008. Creating woodland islets to reconcile ecological restoration, conservation, and
agricultural land use. Front Ecol Environ 336-6:329.
Cantore, E. 1977. The Humanistic Significance of Science, p.85, ISH Publications, New York, 1977.
Chnais, E. and Poyatos, M. 2012. Vegetation study of the HOLCIM Quarry in Chekka, Lebanon
Corbin, JD. and Holl, KD. 2012. Applied nucleation as a forest restoration strategy. For Ecol Manag 46-265:37.
Daily, GC. 1995. Restoring value to the worlds degraded lands. Science 354-269:350.
Dalton, J. 2012. Hydrology Study for the Planned Rehabilitation of the HOLCIM Quarry Site at Chekka, Northern Lebanon
Dar Al-Handasah Shair. 1996. A Nation-wide Study of Quarries, Beirut, Lebanon, Ministry of Public Works, Republic of Lebanon,
General Directorate of Urban Planning, January 1996
Darwish, T.M. et al. 2011. Environmental impact of quarries on natural resources in Lebanon. Land Degrad. Dev.
Darwish, T., Stehouwer, R., Khater, C., Jomaa, I., Miller, D., Sloan, J., Shaban, A. and Hamze, M. 2010. Rehabilitation of Deserted
Quarries in Lebanon to initial Land Cover or Alternative Land Uses. In: Land Degradation and Desertification: Assessment,
Mitigation and Remediation (Zdruli, Pagliai, Kapur and Faz Cano (Eds). Springer-Verlag Berlin Heidelberg New York; 345-333 :25.
ISBN9048186563-978 :13-.
Delpeuch, Benoit. 2012. Contribution llaboration dune stratgie de rhabilitation des carrires au Liban Lgislation et acteurs
- Etat des lieux et prospectives 2010
53
Bibliographic References
El-Fadel, M., Zeinati, M., El-Jisr, K., Jamali, D., 2001. Industrial-waste management in developing countries: The case of Lebanon.
J of Env. Manage. 300-61:281.
El Moujjabber M., Bou Samra B., Darwish T.M. and Atallah T. 2006. Comparison of different indicators for groundwater
contamination by seawater intrusion on the lebanese coast. Water Resour. Manag., 180-162:)2(20.
Groom, M.J., Meffe, G.K. and Carroll, C.R. 2006. Principles of Conservation Biology, third edition, chapter 3. Sinaure.
Khan, A. S. 2006. Methodology for Assessing Biodiversity. Centre of Advanced Study in Marine Biology, Annamalai University.
Khater, C. and Martin, A. 2007. Application of restoration ecology principles to the practice of limestone quarry rehabilitation in
Lebanon. Lebanese Science Journal 28-19 :)1(8
Khater, C., Martin, A., Maillet, J., 2003. Spontaneous vegetation dynamics and restoration prospects for limestone quarries in
Lebanon. Applied Vegetation Science. 204-2:199.
Khater, C. and Martin, A. 2007. Application of Restoration Ecology Principles to the Practice of Limestone Quarry Rehabilitation
in Lebanon. Lebanese Science Journal 1(8).
Khater, C. 2010. Plant dynamics post-disturbance on the limestone quarries in Lebanon. Strategies for Ecological Restoration in
Mediterranean regions. European Universities editions. ISBN9-54089-1-613-978 :13-.
Khater, C., El-Hajj, R. et Viglione, J. 2011a. Rhabiliter les carrires du Liban: mission impossible, ou travailler avec et pour le
dveloppement ? Actes de colloque du sminaire rgional Environnement et gestion durable des cosystmes naturels au
Moyen-Orient , AUF, 20-18 Avril 2011, Beyrouth, Liban.
Khater, C., Raevel, V., Sallantin, J., Thompson, JD., Hamz, M, and Martin, A. 2011b. Restoring Ecosystems Around the
Mediterranean Basin: Beyond the Frontiers of Ecological Science. Restoration Ecology 6-1:)1( 20. (DOI: 10.1111/j.1526
100X.2011.00827.x). IF= 1.927
Bossidy, L., Charan, R. and Burck, C. 2002. Execution: the discipline of getting things done. Crown Business.
Le Floch E. and Aronson J., 1995. Ecologie de la restauration. Dfinition de quelques concepts de base. Natures Sciences
Socits, Hors-Srie, 35-29.
Martin, A., Khater, C., Mineau, H. and Puech, S. 2002. Rehabilitation ecology by revegetation.
Approach and results from two Mediterranean countries. Korean Journal of Ecology 17-9:)1(25
Ministry of Environment (Lebanon) list of related decisions 2006-1997
Ministry of Environment. National Health Statistics Report in Lebanon 2007.
Mitsch W.J. and Jorgensen, S.E. 1989. Introduction to Ecological Engineering. In: W.J. Mitsch and S.E. Jorgensen (Editors),
Ecological Engineering: An Introduction to Ecotechnology. John Wiley & Sons, New York, pp. 12-3.
National Research Council (Ed.) (1992). Restoration of aquatic ecosystems. Science, technology and public policy. Committee
on restoration of aquatic ecosystems, Water Science and Technology Board, Natl. Academy Press Washington, DC.
Questard, EJ. and Foster, BL. 2008. Coexistence through spatio-temporal heterogeneity and species sorting in grassland plant
communities. Ecol Lett 726-11:717.
54
See Lovei, M., 1994. Institutional Issues of Environmental Management and the Banks Approach in Development Countries,
ENVPE, World Bank
SER 2002. Society for ecological restoration and policy working group, The SER primer on ecological restoration.
SER, 2004. Society for ecological restoration and policy working group, The SER primer on ecological restoration.
http://www.ser.org/content/ecological_restoration_primer.asp.
Suding, K.N., Gross, K.L. and Houseman, G.R. 2004. Alternative states and positive feedbacks in restoration ecology. Trends in
Ecology and Evolution, 53-46 :)1(19.
Tilman D. and Pacala, S. 1993. The maintenance of species richness in plant communities. In: Rickefs RE, Schluter D (eds)
Species diversity in ecological communities: historical and geographical perspectives. University of Chicago Press, Chicago,
pp. 15-13
Ward, J.P. and Anderson, S. H. 1988. Influences of cliffs on Wildlife communities in Southcentral Wyoming. Journal of Wildlife
Management, 8-673 :52.
Website Resources
http://www.quarry-plant.net/articles/HistoryOfQuarrying.htm
http://www.ehow.com/about_6505724_environmental-problems-limestone-quarries.html
http://www.aqa.org.nz/about-us/quarrying/
http://test.moe.gov.lb/Documents/SOER20%Chap20%202%reduced.pdf
55
56
Highland
Cliff-land
Core-land
Low-land
Activity
I M P L E M E N T A T I O N
21-Jul
22-Aug
23-Sep
29-Sep
16-Aug
4-Aug
19-Jul
8-Jul
10-Jun
20-May
7-May
CNRS
Date of the visit
1. Establish ponds
Sub-activity
1 :
S C H E D U L E
15-Oct
3-Sep
23-Jul
11-Jun
Report
First week of March
AFDC
This workplan displays the dates of the field visits performed by the three partners to the HQS
A P P E N D I X
30-May
Report
5-Sep
25-Jul
14-Jun
7-May
IUCN
Maintenance visit
Maintenance visit
Rest-land
Cliff-land
High-land
Core-land
Low-land
Planting of subunits:
Maintenance visit
Planting
Soil preparation
Description
Activity
Site visit
Mid June
12-Nov
7-Nov
24-Jun
1 April - 13
May 2014
18-Mar
7-Jan
26-Nov
Mid June
1-14 Nov.
15 -Oct.
30-Jun
30-Nov.
30-Oct
17-May
20-May
28 - nov.
57
58
Site Preparation
List of
Subsection
+ furniture
+water tank +
generator+
light tower
Pick-up
Removal of
obstacles
Loader + Truck
Loader
Preparation of
stock areas
Loader
0.9
Access road
preparation
Furn +
electricity, etc.)
Mobilization of
equipment
Delineate work
subzone
0.3
Start
16-May
14-May
12-May
10-May
5-May
0.8
Depth
17-May
15-May
13-May
13-May
6-May
4-May
2-May
End
Provided
Schedule
Install signage
Length
As per
execution
Equipment and
Machinery
S H E E T
3-May
Height
As per
design
Materiel
I M P L E M E N T A T I O N
Delineate the
site boundaries
Depth
As per execution
Dimension
T E C H N I C A L
1-May
Height Length
As per design
2 :
Site visit
Subunits
A P P E N D I X
1 day
2 days
2 days
4days
2 days
2 days
period
Eng +
worker
1 driver 1
worker
Eng + 2
workers
1 Electrician
1 Plumber
3 Workers
1 Site
engineer
3 Workers
1 Topographer 1
Worker
2 workers
2 workers
3 workers
6 workers
3 workers
2 workers
Nb. of workers
W O R K )
Worker title
( H A R D
Loader + truck
Loader work
Loader work
1 bought and
second
existed
+Electric
connection
5 signs/day
1. 1st day :
reference
points (30
minutes)
2. 2nd day :
locating the
points onsite
Lowland
300 m
1.25 m
1.25 m
1.25 m
Construction of
1st wall
Construction of
2nd wall
Construction of
3d wall
1m
1381 m3
8351.7 m3
Place topsoil
and strip of
rocks
0.8 m
0.2 m
85 m
112 m
112 m
112 m
72 m
300 m
270 m3
9470 m3
1826 m3
0.80 m
Construction of
6th wall
Place gravel
layer
2.2 m
Construction of
5th wall
2m
2m
0.45 m
0.45 m 1.25 m
0.45 m
Construction of
4th wall
112 m
72 m
165 m3
Rocks needed
for construction
0.2m
0.75 m
0.75 m
0.75 m
0.75 m
0.60 m
0.80 m
Calcisol +
Organic
matter
Rock
Stone
Rock
Stone
Rock
Stone
Rock
Stone
Rock
Stone
Rock
Stone
Clay soil +
amendments
Crushed
limestone
Rocks
22-Jun
16-Jun
Loader, Truck,
Crusher,
Grader
Trucks, Loader
15-Sep
10-Jun
10-Jun
10-Jun
4-Jun
24-May
18-May
Excavator + Truck
+ Loader
Excavator + Truck
+ Loader
Excavator + Truck
+ Loader
Excavator + Truck
+ Loader
Excavator + Truck
+ Loader
Excavator + Truck
+ Loader
Excavator
30-Jul
21-Jun
20-Sep
15-Jun
15-Jun
15-Jun
9-Jun
3-Jun
23-May
35 - 40
days
5-6 days
5-6 days
5-6 days
5-6 days
5-6 days
5-6 days
9-10 days
5 days
3 Drivers 2
workers
2 Drivers 1
Worker
2 Masons
Teams
3 Masons
Teams
3 Masons
Teams
3 Masons
Teams
2 Masons
Teams
3 Masons
Teams
1 Driver 1
worker
5 workers
3 workers
9 workers
18 workers
18 workers
18 workers
9 workers
18 workers
2 workers
12-15 trucks /
day
12 - 15 trucks /
day
12-15 m / day
20-25 m / day
20-25 m / day
20-25 m / day
12-15 m / day
30-35 m / day
59
60
Core-land
1
0.25
0.4
0.5
0.6
Calcisol +
Organic
matter
Construct
merlon-like
structures
Add topsoil
around pond
1785 m3
1834 m3
Rocks
(195m3 )
+ Gravel
(39m3 )
Calcisol
(143m3)
and
organic
matter
(15.6kg )
Calcisol +
Organic
matter
Clay
8-Jul
Excavator+Truck
+Loader
Small Loader/
JCB
Trucks + Loader
Excavator
16-Jul
8-Jul
Excavator+Truck
+Loader
Compactor
8-Jul
Excavator+Truck
+Loader
4-Aug
29-Jul
21-Jul
75
Establish
connecting
Cannals
0.1 m
19-Jul
0.1 m
0.5 m
0.5 m
1-May
Ensure
waterflows as
per design
1m
35 m
Pond 3
95 m
62 m
Pond 2
35 m
Pond 1
Ponds
deliniation
11-Aug
3-Aug
28-Jul
20-Jul
18-Jul
15-Jul
15-Jul
15-Jul
2-May
7 - 8 days
7 days
8 days
3 days
7 days
7 days
7 days
1 day
3 Drivers + 3
worker
2 Drivers + 1
worker
1 Driver
1 driver 1
worker
1 driver 1
worker
1 driver 1
worker
Topographer
6 workers
3 workers
1 worker
4 workers
2 workers
2 workers
2 workers
1 worker
RestLand
HighLand
Cliff-Land
3.6 m
Geotextile
behind
unplanted
gabions
0.5 m
Concrete
0.6 m
Banches
2m
Rocks +
concrete
1.15 m
2.11 m
2125 m3
165 m
1.4 m
4 m3
165
Toilets
implementation
1m
2.8 m
Rocks
2346.75 m3
1.4 m
2 m3
2m
Cover the
housing facility
with rocks
Topsoil behind
unplanted
gabions
2.8 m
Coconut
blancket
Topsoil in the
planted
Gabions
82 m
Calcisol
and
organic
matter
Clay soil +
amendments
Clay soil +
amendments
Loader
Loader
Truck + loader
Loader
Manual
Manual
Manual
Loader
1m
18
Calcisol
and
organic
matter
Rocks + Gravel
+ Clay soil +
amendment
Gabion
structure +
limestone
rocks
Unplanted
Gabion Wall
Metal
structure +
Rocks
Rocks
(195 m3 ) +
Gravel
(39 m3 )
Calcisol
existing
(143 m3)
and
organic
matter
(15.6 kg )
Loader
2m
5560 m3
existing
89
1m
82 m
existing
Planted Gabion
Wall
5.460 m3
4m
2m
Small Loader/
JCB
1.5 m
82 m
Base of Gabion
Baskets leveling
Topsoil behind
Gabions
Merlon like
structures
construction
1m
Small Loader/
JCB
Impluvium
structure
Place the
gabion Walls
Small Loader/
JCB
10-Oct
7-Oct
5-Oct
2-Oct
5-Sep
29-Aug
25-Aug
7-Sep
22-Aug
16-Aug
12-Aug
30-Oct
9-Oct
6-Oct
4-Oct
1-Oct
4-Sep
28-Aug
2-Oct
6-Sep
21-Aug
15-Aug
20 days
2 days
1 days
2 days
25 - 27
days
4- 5 days
3 -4 days
25 - 27
days
existing
14 - 15
days
4- 5 days
3 -4 days
1 Driver 1
worker
2 workers
4 workers
5 workers
7 workers
7 workers
1 Driver
3 Drivers 3
workers
3 Drivers + 3
worker
1 Driver
1 Driver
2 workers
2 workers
4 workers
5 workers
7 workers
7 workers
1 worker
6 workers
5-6 worker /
day
1 worker
1 worker
70 - 80 m / day
5-6 Gabions /
day
3-4 Gabions /
day
10-12 trucks /
day
5-6 Gabion /
day
61
62
63
64
Seed
preparation
Seedbed
and sowing
preparation
Treatment
stratification,
scarification)
Seed
storage
Natural air
cirulation
Natural air
circulation
Row
per bed
12,000
seeds
Quantity
of seeds
treated
Seedbed
dimensions
2 to 4
in chiller +2
+4 (4
weeks)
Temperature
of treatment
10000
seeds
24 h
chiller
cold
stratification
48 h
soaking in
running
water
Soaking in
water: period
Width
Dry
conditions
Dry
conditions
3 months
around 85
from 5-25
from 5 -25
4 months
from 2 to 4
Storage
shed
Storage
shed
15000
2 to 4
24 h
chiller
cold
stratification
4 months
none
600
2 to 4
24 h
Chiller
cold
stratification
1 year and
4
months
natural air
circulation
dry
conditions
from 5 - 25
storage
shed
drying and
removal
from
pods
Removal of
pulp under
running
water
Drying
of cones
None
chiller
Ramlieh
Ammatour
Nabe3
l Safa
Sep-11
Aug-11
Spartium
junceum
Chouaifet
September
through
October
2012
not
successful
Calicotome
villosa
Oct-12
Pistacia
palaestina
Tamarix
sp.
400
2 to 4
24 h
200
6 months
natural air
circulation
natural air
circulation
one year
and 4
months
dry
conditions
from 5-25
storage
shed
Removal of
twigs
and
leaves
Ramlieh
August
Oreganum
syriacum
dry
conditions
from 5-25
storage
shed
Seperation
through
water
Damour
June
Salvia
triloba
S H E E T
Nov-12
Nov-12
Pinus brutia
P L A N T A T I O N
Mar-13
Nov-12
Ceratonia
siliqua
T E C H N I C A L
in nursery
No
treatment
1.5 months
None
around 85
Relative
humidity
Ventillation
2+ - 4+
Temperature
chiller
Olea
europea
Purchased
Location of
treatment
Type
of treatment
Time
of storage
before
sowing
Condition
of storage
Location
of storage
cleaning
and
floating
Seed
extraction
Dec-12
Ramlieh
Oct-12
Collected
Prepared in
nurseries
Seed
geographic
origin
Seed
supplier
Purchased
Quercus
calliprinos
4 :
Rhus
coriaria
Ficus
carica
Purchased
A P P E N D I X
40 x 25
styrofoam
boxes
200
one year
and 4
months
natural air
circulation
dry
conditions
from 5-25
storage
shed
Removal of
twigs
and
leaves
Ramlieh
JulyAugust
Thymbra
spicata
65
Sowing
66
To
Type
60%
none
Period from
seedling (or
seed) to
emergence
Period to
transfer to
another pot
38 cm x 30 cm x 28 c
Dimensions
650 cc containers
Type
Purpose
Density
Type
cocopeat + peatmoss
none
sprinkler
Machine type
Frequency
1 worker
Nbr. of
workers or
machines
Germination %
Pots and
trays
Pesticides
Type of soil
used +
compost
Irrigation
1 day
Work load
Palatable to rodents
Challenges
Sowing machines or
manually
20%
perlite
0.5 cm
Type
Depth
max 2 cm
31/1/2013
27/2/2013
From
Losses of
seeds
Mulch
Sowing
depth
Sowing
date
none
none
first
emergence
after 20
days
first
emergence
after 15
days
38 x 30cm
35 cm x60
cm
75%
20 cells per
container
91 cells
per
container
45%
D27 (475
ml)
None
cocopeat +
peatmoss
130 cc
styrofoam
None
cocopeat
+
peatmoss
varies, on
average 4
days
varies, on
average
every 3
days
none
none
3 workers
sprinkler
1 worker
1 day
1 day
none
none
birds and
rodents
like the
seeds
removing
broken
seeds
sprinkler
30%
20%
50%
perlite
none
first
emergence
after 3
weeks
65%
43x31 cm
50 cells per
container
300 cc
None
cocopeat +
peatmoss
varies, on
average 4
days
sprinkler
1 day
0.5 cm
perlite
0.5 cm
perlite
max 1 cm
max 1 cm
0.5 cm
surface
sowing
12-Apr
1-May-13
3-Mar
10-Apr
25-Apr-13
none
first
emergence
after one
week
90%
43 x 31 cm
none
first
emergence
after 3
weeks
first
emergence
after
one
week
none
50%
43 x 31 cm
80%
43 x 31
cm
50 cells
50 cells per
per
containcontainer
er
50 cells
per
container
300 cc
None
cocopeat +
peatmoss
varies, on
average
4 days
sprinkler
none
1 worker
1 day
cleaning
the
debris
from the
seeds
0.5 cm
perlite
surface
sowing
15-May
300 cc
None
cocopeat
+
peatmoss
varies, on
average
4 days
sprinkler
none
1 worker
1 day
none
0.5 cm
perlite
surface
sowing
15-May
300 cc
None
cocopeat
+
peatmoss
varies, on
average
4 days
sprinkler
none
1 worker
1 day
none
10%
0.5 cm
perlite
0.5 cm
2-Mar
none
first
emergence
after 3
weeks
50%
43 x 31 cm
50 cells
per
container
300 cc
None
cocopeat
+
peatmoss
varies, on
average
4 days
sprinkler
none
1 worker
1 day
cleaning
the
debris
from the
seeds
0.5 cm
perlite
surface
sowing
20-Apr
Purchased
Purchased
Pesticides
Weeding
(the use of
cocopeat
and peat
moss
greatly
reduces
weed
problems
Fertilisation
Herbicide
used
Stage of
species
attacked
(seed,
germination,
roots)
Method of
control
(fumigation,
seed
treatment,
drench or
spray)
Type of
pesticide
Purpose
(preventive)
Time of the
year
Purpose
Amount
2 applications
Worker
Diseases
Handweeding
Application
timing
(pre-seeding)
Purpose of
application
Type of
fertilizer
Amount
applied
one
permanent
and two seasonal
None
so far
In nursery
Time of
application
Slow
release
(6 months)
Before
sowing
one
permanent
and two
seasonal
one
permanent
and two
seasonal
none,
limited
attack
leaves
insect
foraging
None
so far
none
so far
none
so far
None
so far
slow
release
(6 months)
slow
release
(6 months)
None
None
so far
one
permanent
and two
seasonal
none
so far
slow release
(6 months)
None
one
permanent
and two
seasonal
none
so far
slow
release
(6 months)
none
so far
slow
release
(6 months)
None
None
one
one
permanent
permanent
and two
and two
seasonseasonal
al
none
so far
slow
release
(6 months)
None
one
permanent
and two
seasonal
none
so far
slow
release
(6 months)
67
Purchased
Purchased
Highland
Section
Quantities
Lowland
Coreland
Cliffland
None
Transplanting
62
149
149
As per design
As per
execution
62
As per
execution
As per
execution
62
As per design
62
31
As per
execution
As per design
31
As per design
11 months
Greenhouse
Frost
protection
Period
Sprayers
Photos
Shears
Pruning
slow release
mixes
Fertilization
Herbicide
and
insecticide
spraying
manual
sprinklers
Sowing
chiller
Seed
storage and
handling
irrigation
None
From
seeding to
plantation
Equipment
68
Seed
processing
Purchased
149
149
30
30
52
52
27
27
74
74
10
10
20
20
7 months
None
None
17
17
62
62
22
22
8 months
165
185
101
52
40
103
62
60
39
9 months
slow release
mixes
slow
release
mixes
40
60
20
40
149
149
73
63
83
83
32
29
9 months
None
slow
release
mixes
sprinklers
manual
manual
sprinklers
manual
sprinklers
chiller
chiller
chiller
none
sieves
none
60
20
40
40
7 months
None
slow
release
mixes
sprinklers
manual
chiller
none
60
20
40
40
7 months
None
slow
release
mixes
sprinklers
manual
chiller
none
Purchased
10
10
30
10
20
20
8 months
Hand
picking
slow
release
mixes
sprinklers
manual
chiller
none
INTERNATIONAL UNION
FOR CONSERVATION OF NATURE
Regional Office for West Asia
Hasan Baker Al Azazi St. #20
Sweifiyeh - Amman - Jordan
T. +962 6 554 6912 /3/4
F. +962 6 554 6915
M.+962 777 888 377
westasia@iucn.org