Professional Documents
Culture Documents
Section SCMT 03
SCMT-2016
Q.1) Identify the key challenges faced by the Baroda Union. How
important is in-bound logistics for Baroda Union?
A. The major Challenge for the Baroda Union was to minimize the total cost
so that their members get highest payment per litre of milk. The
transportation costs involved in milk procurement accounted for 17% of the
total cost involved, thus reducing transportation cost was a main step
towards minimizing the total cost. The process of procuring milk faced
various issues like:
The in-bound logistics are very important for Baroda Union as they form the
major crux of the business. The major responsibilities of the in-bound
logistics are:
The milk was procured twice a day and the delivery has to be at specified
hours in order to prevent curdling of milk and the penalty faced by the
contractors. Thus a sound and highly efficient inbound logistics was the basic
and far most important need of the Baroda Union model.
Q.2) Suggest a suitable approach that Baroda Union can use for
designing efficient routes for milk collection. What kind of conflicts
are these revised routes likely to create at Baroda dairy? How
should Baroda Union handle these issues?
A.
Route 51:`
An enhanced analysis taking savings matrix into consideration reveals an
optimum route design which is depicted as follows:
0
(Chillin
g
Centre)
5
Thus, the total time taken by the modified route path lies within the time lag
constraint of seven hours.
From the attached excel sheet, the total capacity of route 51 = 80 cans.
Since, the capacity of each tempo is 100 cans, it also satisfies the capacity
constraint.
Route 52:
The optimum route design by incorporating the analysis of savings matrix
into account is as follows:
0
(Chillin
g
Centre)
10
11
Thus, the total time taken by the modified route 52 is 3.5 hours. This is well
within the time lag constraint of seven hours.
From the attached excel sheet, the total capacity of route 52 = 55 cans.
Hence, the modified route 52 also satisfies the capacity constraint.
Route 54:
The total capacity of Route 54 from the attached excel sheet = 102 cans. But
this exceeds the mandated capacity of 100 cans per tempo. Hence
integrating the analysis of savings matrix, along with the capacity
constraints, results in the design of two optimal routes which is as follows:
0
(Chillin
g
Centre)
16
14
15
12
13
0
(Chillin
g
Centre)
17
Total time taken by Route 54 (i) is 2.83 hours which is limited within the time
lag constraint of seven hours.
The capacity of Route 54 (i) (from the attached excel sheet) = 96 cans.
Now, the time taken for Route 54 (ii) is as follows:
PATH
0 17
17 - 0
TOTAL TIME
Total time taken by Route 54 (ii) is 1 hour which is well within the time lag
constraint of seven hours.
The capacity of Route 54 (ii) (from the attached excel sheet) = 6 cans.
Route 55:
The optimum route design by incorporating the analysis of savings matrix
into account is as follows:
0
(Chillin
g
Centre)
22
20
21
18
19
The total time of 4.26 hours which satisfies the time lag constraint of lying
within seven hours.
The total capacity of Route 55 from attached excel sheet = 61 cans. This also
satisfies the capacity constraint.
Route 60:
Analysis of savings matrix results in the following optimized route design:
0
(Chillin
g
Centre)
27
25
26
23
24
Thus, the total time taken by the modified Route 60 is 1.77 hours. This is well
within the time lag constraint of seven hours.
From the attached excel sheet, the total capacity of route 60 = 71 cans.
Hence, the modified route 60 also satisfies the capacity constraint.
Route 62:
The optimum route design by incorporating the analysis of savings matrix
into account is as follows:
0
(Chillin
g
Centre)
31
33
30
28
32
29
The total time of 2.26 hours which satisfies the time lag constraint of lying
within seven hours.
The total capacity of Route 62 from attached excel sheet = 38 cans. This also
satisfies the capacity constraint.
Therefore, due to the low expense incurred, Jashwant must be applied as the
contractor for Route 60.
Route 62:
Total Distance = 13 + 12 + 10 + 6 + 5 + 4 + 18 = 68 kms
Cost of using Gabubhai as contractor = 3.34 * 68 = Rs.227.12
Since Gabubhai is the only contractor for Route 62, he must be appointed as
the contractor for the route.
Thus, Jagdish can design the routes as described in Q.2 and appoint the
contractors as mentioned above to reduce costs incurred.