To
ROTODYNE ENGG SERVICES PVT LTD
ROTODYNE HOUSE,PLOT NO.9 &10
ANNAPURNA ENCLAVE ADJ LANE TO
HYDERABAD
Telangana
India - 500050
Tel: 040-2303 2362...
Fax: 040-2303 4508
E-Mail : MARKETING@ROTODYNEINDUSTRIES.COM
Subject:
NIT NO.
Your Offer No.
Your Reference
Our Reference
: Annual Contract for Routine & Breakdown Maintenance of Turbine & Aux. for St-II at
Barh STPP.
: 40053299 Dated
: 60154631
:
: BR/CS/15402
Dear Sir,
This has reference to our above mentioned NIT, Your offer and subsequent discussions. We are pleased
to accept your offer opened on and confirm having awarded on you the work of Annual Contract for Routine &
Breakdown Maintenance of Turbine & Aux. for St-II at Barh STPP. of total value INR 6,800,518.00 (Rupee
SIXTY-EIGHT LAKH FIVE HUNDRED EIGHTEEN ONLY) mentioned in the scope of works, special terms &
conditions, Bill of quantities etc.
The duration of the service period shall be from 06.08.2016 to 05.08.2017. Though the duration of contract
shall remain same, the actual date of commencement of the contract shall be as per the direction of EIC.
DGM(TMD) shall be EIC for this work.
This service purchase order along with its annexure is being issued to you in duplicate .We request you to
return the duplicate copy of this service purchase order, duly signed on each page by your authorised signatory
in token of your unequivocal acknowledgment of the same within 15 days from the date of this service purchase
order. If no communication is received within 15 days of receipt of Purchase Order, it will be treated that order
has been accepted in entirety.
We thank you for the interest shown by you in our project and the cooperation extended to us. We expect
to receive your continued cooperation in future also.
Thanking You,
For & on behalf of NTPC Limited.
S K SAHA, DGM(C&M)
Registered Office: NTPC Bhawan, Core-7, Scope Complex, Institutional Area, Lodhi Road, New Delhi-110003
Phone No. -(011)24360100, Fax No. -(011)24361018. Website: www.ntpc.co.in
PO No. : 4000170293
Enclosures :
Page No. 2 / 60
PO No. : 4000170293
Page No. 3 / 60
(Bill of Quantity)
Annual Contract for Routine & Breakdown Maintenance of
Turbine & Aux. for St-II at Barh STPP.
Name of Work:
SI No.
Code
Description
Unit
Quantity
Net Price
Amount
Delivery Address:
Long
Text
AU
1.000
6,800,518.00
6,800,518.00
NO
72
2,430.0000
174,960.00
TMCEP04OH00 CEP(>500-660MW#)-OH
1
NO
28,350.0000
56,700.00
NO
36
3,240.0000
116,640.00
YES
NO
14,175.0000
14,175.00
YES
NO
4,860.0000
4,860.00
YES
NO
16
3,240.0000
51,840.00
YES
NO
7,290.0000
14,580.00
YES
NO
300
610.0000
183,000.00
YES
SET
2,577.0000
10,308.00
YES
NO
3,240.0000
12,960.00
YES
NO
48
2,835.0000
136,080.00
NO
5,265.0000
10,530.00
NO
4,860.0000
NO
10,935.0000
32,805.00
NO
3,240.0000
19,440.00
YES
NO
24
2,835.0000
68,040.00
YES
NO
37
3,240.0000
119,880.00
YES
NO
24
1,215.0000
29,160.00
YES
S K SAHA, DGM(C&M)
19,440.00
YES
YES
YES
PO No. : 4000170293
10 .190
10 .200
10 .210
10 .220
10 .230
10 .240
10 .250
10 .260
10 .270
10 .280
10 .290
10 .300
10 .310
10 .320
10 .330
10 .340
10 .350
10 .360
10 .370
10 .380
10 .390
10 .400
10 .410
10 .420
10 .430
10 .440
10 .450
10 .460
Page No. 4 / 60
TMSST07GN10 STRAINER/FILTER (50NB) Cleaning
0
SET
24
1,620.0000
38,880.00
YES
NO
200
610.0000
122,000.00
YES
NO
12,960.0000
25,920.00
YES
NO
4,860.0000
14,580.00
YES
NO
4,050.0000
12,150.00
YES
NO
5,670.0000
17,010.00
YES
NO
4,860.0000
14,580.00
YES
NO
4,860.0000
14,580.00
YES
NO
5,670.0000
11,340.00
YES
NO
4,050.0000
8,100.00
YES
NO
5,670.0000
11,340.00
YES
NO
4,050.0000
4,050.00
YES
TMBFP03BD80 BFP(>210-500MW#)-Repl
0
NO
12,960.0000
12,960.00
NO
4,860.0000
4,860.00
NO
6,480.0000
4,050.0000
4,050.00
YES
NO
6,075.0000
6,075.00
YES
NO
10
6,885.0000
68,850.00
YES
NO
4,050.0000
12,150.00
YES
NO
24
2,430.0000
58,320.00
YES
NO
2,835.0000
22,680.00
YES
SET
2,835.0000
22,680.00
YES
NO
3,645.0000
21,870.00
YES
NO
72
1,448.0000
104,256.00
YES
NO
36
3,240.0000
116,640.00
YES
NO
4,050.0000
24,300.00
YES
NO
3,240.0000
6,480.00
NO
3,240.0000
3,240.00
S K SAHA, DGM(C&M)
NO
6,480.00
YES
YES
PO No. : 4000170293
10 .470
10 .480
10 .490
10 .500
10 .510
10 .520
10 .530
10 .540
10 .550
10 .560
10 .570
10 .580
10 .590
10 .600
10 .610
10 .620
10 .630
10 .640
10 .650
10 .660
10 .670
10 .680
10 .690
10 .700
10 .710
10 .720
10 .730
10 .740
Page No. 5 / 60
TMAOP03BD80 Turbine AOP(>210-500MW#)-Repl
0
NO
4,860.0000
4,860.00
NO
10
3,240.0000
32,400.00
YES
NO
40
3,240.0000
129,600.00
YES
NO
4,860.0000
9,720.00
YES
NO
4,050.0000
8,100.00
NO
48
2,025.0000
97,200.00
YES
NO
32
1,620.0000
51,840.00
YES
NO
16
3,240.0000
51,840.00
YES
NO
96
1,620.0000
155,520.00
YES
NO
64
1,620.0000
103,680.00
YES
NO
4,050.0000
12,150.00
YES
NO
2,835.0000
17,010.00
YES
NO
3,240.0000
9,720.00
YES
NO
3,240.0000
9,720.00
YES
NO
12
3,240.0000
38,880.00
YES
NO
12
1,215.0000
14,580.00
YES
NO
60
410.0000
24,600.00
YES
NO
3,240.0000
6,480.00
YES
NO
1,620.0000
3,240.00
YES
NO
7,290.0000
14,580.00
YES
NO
8,100.0000
32,400.00
NO
8,100.0000
32,400.00
YES
NO
8,100.0000
16,200.00
YES
NO
8,100.0000
16,200.00
YES
NO
3,240.0000
6,480.00
YES
NO
32,400.0000
129,600.00
NO
4,050.0000
8,100.00
NO
10,125.0000
50,625.00
TMDEA00OH00 Dearator(<>)-Insp
0
S K SAHA, DGM(C&M)
YES
PO No. : 4000170293
10 .750
10 .760
10 .770
10 .780
10 .790
10 .800
10 .810
10 .820
10 .830
10 .840
10 .850
10 .860
10 .870
10 .880
10 .890
10 .900
10 .910
10 .920
10 .930
10 .940
10 .950
10 .960
10 .970
10 .980
10 .990
10 .1000
10 .1010
10 .1020
10 .1030
Page No. 6 / 60
0
NO
100
410.0000
41,000.00
YES
NO
100
810.0000
81,000.00
YES
NO
40
1,215.0000
48,600.00
YES
NO
24
3,240.0000
77,760.00
YES
NO
12
6,885.0000
82,620.00
YES
NO
20
1,215.0000
24,300.00
YES
NO
12
2,430.0000
29,160.00
TMHPV02BD80 HP Valves(Dia>6"-12")-Repl
0
NO
6,075.0000
36,450.00
NO
24
1,013.0000
24,312.00
YES
NO
12
3,645.0000
43,740.00
YES
TMLPV01BD80 LP Valves(Dia<=6")-Repl
0
NO
25
1,620.0000
40,500.00
TMLPV02BD80 LP Valves(Dia>6"-12")-Repl
0
NO
4,050.0000
20,250.00
NO
3,240.0000
16,200.00
YES
SET
7,128.0000
14,256.00
YES
NO
1,420.0000
35,500.00
YES
NO
25
NO
24
2,430.0000
12
2,025.0000
77,760.00
YES
NO
6,480.0000
58,320.00
24,300.00
YES
TMHPV01BD80 HP Valves(Dia<=6")-Repl
0
20
56,700.00
YES
NO
NO
12
5,265.0000
63,180.00
YES
NO
7,290.0000
43,740.00
YES
NO
10,125.0000
60,750.00
YES
NO
24
1,620.0000
38,880.00
YES
NO
12
3,645.0000
43,740.00
YES
NO
5,265.0000
31,590.00
YES
NO
200
410.0000
82,000.00
YES
25
610.0000
15,250.00
YES
25
2,025.0000
50,625.00
YES
NO
200
610.0000
122,000.00
YES
S K SAHA, DGM(C&M)
12
2,835.0000
YES
PO No. : 4000170293
10 .1040
10 .1050
10 .1060
10 .1070
10 .1080
10 .1090
10 .1100
10 .1110
10 .1120
10 .1130
10 .1140
10 .1150
10 .1160
10 .1170
10 .1180
10 .1190
10 .1200
10 .1210
10 .1220
10 .1230
10 .1240
10 .1250
10 .1260
Page No. 7 / 60
TMFLG12BD00 FLANGE (DN300) Attend Defect
0
NO
100
2,025.0000
202,500.00
YES
NO
50
4,860.0000
243,000.00
YES
NO
7,290.0000
14,580.00
YES
NO
6,893.0000
13,786.00
YES
NO
14,175.0000
14,175.00
YES
PDY
200
1,015.0000
203,000.00
18,300.00
YES
YES
NO
365
1,215.0000
443,475.00
YES
UNT
365
2,025.0000
739,125.00
YES
NO
50
610.0000
30,500.00
YES
NO
40
610.0000
24,400.00
YES
OPR
50
1,015.0000
50,750.00
YES
NO
70
810.0000
56,700.00
YES
M2
50
1,015.0000
50,750.00
YES
FRQ
50
490.0000
24,500.00
YES
PC
40
810.0000
32,400.00
YES
MT
40.000
810.0000
32,400.00
YES
NO
70
610.0000
42,700.00
YES
NO
70
610.0000
42,700.00
YES
NO
60
610.0000
36,600.00
YES
NO
50
1,215.0000
60,750.00
YES
NO
40
610.0000
24,400.00
YES
NO
100
610.0000
61,000.00
YES
00010
00010
NO
30
610.0000
INR 6800518.00
-----------------------------------------------6800518.00
0.00
-----------------------------------------------INR 6800518.00
INR 6,800,518.00
INR 0.00
INR 6,800,518.00
PO No. : 4000170293
INR SIXTY-EIGHT LAKH FIVE HUNDRED EIGHTEEN ONLY
S K SAHA, DGM(C&M)
Page No. 8 / 60
PO No. : 4000170293
Page No. 9 / 60
Terms & Conditions
------------------------------
Special Instruction
1. Total Contract Value : Rs. 68,00,518.00 (Rupees Sixty Eight lakh Five hundred Eighteen only).
2. Completion Period : 12 (Twelve) Months and shall be extended in continuous for another twelve months at the
same rates, terms and conditions.
3. Defect Liability period : Three Months from date of execution of work
4. Engineer-In-Charge: DGM (TMD)
5. Payment Terms : Payments shall be releasaed on monthly
running bill basis on the actual quantity of
work executed during the month against submission of bills subject to verification by EIC after completion of
work and after
compliances of all statutory requirements, after deduction
of IT & other statutory
deductions etc.
6. The rates are inclusive of all taxes, duties, levies etc. excluding Service Tax. Service Tax is Extra as
applicable.
7. EMD/SD : S.D. applicable as per GCC for civil Works and shall be recovered from R.A Bill. SD shall be
released on certification of EIC.
8. Rate shall remain firm during the tenure of the contract.
9. Execution to be restricted to BOQ quantity of item sl.no. 10.10, 10.60, 10.90, 10.110, 10.160, 10.180, 10.190,
10.360, 10.370, 10.380, 10.410, 10.420, 10.440, 10.480, 10.490, 10.520, 10.530, 10.550, 10.560, 10.620,
10.650, 10.720, 10.870, 10.880, 10.940, 10.1040, 10.1050, 10.1060, 10.1070 & 10.1120 of PO.
9. All other conditions shall be as per terms of B.I. no. 40053299 and as per GCC for Civil works of NTPC.
PO No. : 4000170293
Page No. 10 / 60
canister in horizontal position. Cleaning of canister thoroughly. Removal of bottom bush from position.
13. Measure the total axial travel of the rotating assembly by pushing & pulling the pump shaft.
14. Dismantling of the pump assembly such as casing, impellers, wear rings, shaft, shaft sleeves, rubber
bearings etc.
15. Through cleaning of all parts and measurements of all controlled dimensions & clearances.
16. Examine the internals such as wear rings, shaft sleeves, shaft, impeller & casings, rubber bearings for
wear & damage and renew as necessary. Examine the shaft for damage & check the concentricity. Renew as
necessary.
17. Assembly of pump internals. Replace all interstage joint O-rings.
18. Check the total axial float of the rotating assembly.
19. Make the canister vertical with proper temporary support in a suitable location. Lower the head piece &
pump assembly in to the canister. Mount the bottom bush of Canister into the 1st t stage pump casing. Secure
the head piece with canister along with bolts & nuts. Lower the Head piece along with the canister into the sump
carefully. Connect the pump suction & discharge pipe with pump.
20. Place the motor spool piece on head piece.
21. Checking of stuffing box restriction bush, renew if required & Install the stuffing box.
22. Install new/ repaired mechanical seal onto the pump.
23. Assemble the bearing housing, thrust bearing, thrust collar etc in reverse order with old/ repaired/ new
spares as per requirement.
24. Check cooling coil leakage, make necessary repair and do hydro test and install it back as per
requirement.
25. Box up the bearing covers. Measuring of axial float of pump. Install coupling hubs, spacer.
26. Carry out alignment of CEP with motor as per EIC / OEM Manual.
27. Couple the pump with motor after placement of motor.
28. Take trail run after charging and attend defects if any.
29. Dismantle the removed seal, renew/ lap the sealing surfaces as per requirement.
30. Assemble the mechanical seal by using new `O' rings and gasket and keep it as spare.
PO No. : 4000170293
11.
12.
13.
14.
Page No. 11 / 60
Install coupling hubs, spacer & couple pump with motor after placement of motor.
Take trail run after charging and attend defects if any.
Dismantle the removed seal, renew/ lap the sealing surfaces as per requirement.
Assemble the mechanical seal by using new `O' rings and gasket and keep it as spare.
S K SAHA, DGM(C&M)
PO No. : 4000170293
4)
Page No. 12 / 60
Decouple pump from motor/ gear box & remove coupling hub from pump as per requirement.
Remove oil/water pipes attached to the bearings/seals etc.
Loosen / Remove parting plane bolts/jacket cooler bolts of the pump.
S K SAHA, DGM(C&M)
PO No. : 4000170293
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Page No. 13 / 60
16.Coupling/de-coupling of BFP to Turbine (HC) / BP to Gear box (Motor)/ Turbine to Gear box/Hydraulic
coupling to Motor/ CEP to Motor :
Schedule No. 10.150:
Service Code: TMCPL02GN402
01) Open coupling housing top half / Coupling guard as applicable.
02) Loosen all coupling fasteners & remove the coupling spacer /hub.
03) Clean coupling housing/couplings etc as per requirement.
04) Replace defective parts with new one.
05) Do the alignment work as per EIC Instruction.
05) Mount coupling and tightened coupling bolts.
06) Install coupling housing top half / coupling guard.
07) Take trial and attend defects if any.
17. Cleaning of BFP Mechanical seal cooler:
Schedule No. 10.160:
Service Code: TMBFP54GN100
01)
02)
03)
04)
05)
18. Suction strainer cleaning of BFP booster pump / BFP main pump:
Schedule No. 10.170:
Service Code: TMBFP53GN100
1)
2)
3)
4)
5)
6)
Make necessary platform and use necessary lifting arrangement as per requirement
Loosen the necessary fasteners of Strainer lid / flange
Remove the strainer element as per requirement, thoroughly clean it and check for damage in mesh etc.
Repair mesh as per requirement and install strainer element with new gasket
Box up strainer lid with new gasket and tighten the fasteners, the vent line etc.
Attend for any leakage after charging
19. BFP Booster Pump/Main pump seal water fitters cleaning (2 Nos.):
Schedule No. 10.180
Service Code: TMBFP64GN100
1.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 14 / 60
2.
Remove the filter element as per requirement, thoroughly clean it and check for damage in mesh etc.
3.
Replace the filter element / magnetic disc etc. as per requirement and install filter element with new gasket
/ o ring
4.
Box up filter element with new gasket / o ring and tighten the fasteners etc.
5.
Attend for any leakage after charging.
20. Turbine Governing rack / LP Bypass Governing rack all rotating filters/TDBFP Governing rack duplex filters(2
nos) cleaning:
Schedule No. 10.190
Service Code: TMSST07GN100
1.
Removal of top cover of rotating filters one by one.
2.
Removal of bottom dummy plug & draining of oil.
3.
Removal of filter element from position, Cleaning of the filter element & filter block with diesel, air, marking
cloth as per requirement up to the satisfaction of EIC.
4.
Box up of filter with new O-ring. charging of the system and attend leakage / defects etc if any
21. TDBFP AOP or EOP or JOP Suction filters cleaning:
Schedule No. 10.200
Service Code: TMBFP60GN100
1.
Closing of Inlet & out let valve of pump.
2.
Draining of oil from filter and collecting the oil in drum.
3.
Removal of End covers of the filter & removing the filter from location.
4.
Cleaning of the filter element by using compressered air, diesel, marking cloth etc as per requirement up to
the satisfaction of EIC.
5.
Box up of end cover with new gaskets, charging of the system and attend leakage / defects etc if any.
22. TDBFP AOPS overhauling:
Schedule No. 10.210:
Service Code: TMBFP63OH001
1.
Close the suction & discharge valves of the pump and drain the oil from the barrel
2.
Remove the pipe connections as per requirement
3.
De couple the pump from the motor & remove the motor from position
4.
Remove the pump barrel from the position & keep the barrel in vertical position on the stand
5.
Remove the cartridge from the barrel & dismantling the pump internals
6.
Repair / replace damaged internals such as bearing, Screws, Bushes, Cartridge, Mech. Seal spares, end
cover etc. as per requirement
7.
Clean the internals as per requirement
8.
Box up the pump with new o ring / gasket/sealing ring etc. as per requirement
9.
Mount the Cartridge inside the barrel
10. Place the pump in position
11. Tighten the base bolts & pipe connections with new o ring/gaskets etc. as per requirement
12. Place the motor in position.
13. Carry out alignment of pump with motor as per EIC/ OEM manual.
14. Carry out coupling the motor with pump.
15. Charge the system and attend if any defects.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 15 / 60
Loosen the fasteners of the coupling and remove coupling spacer/ coupling hub as per requirement.
Remove the oil/ seal water connections as per requirement.
Open bearing covers, remove bearing, bearing housing, thrust collar etc from shaft as per requirement.
Remove complete seal assembly from pump after necessary locking arrangement etc..
Install the new/ repaired seal with pump.
Fix the bearing/ bearing housing into the shaft/ housing after necessary cleaning.
Measurement of bearing clearances & thrust bearing float as per requirement.
Normalize the oil/ seal water lines.
Fit the coupling spacer/ hub and tighten the fasteners as per torque requirement etc as per requirement.
Take trail and attend defects, if any.
Dismantle the removed mechanical seal, renew/ lap sealing surface as per requirement.
Assemble the mechanical seal by using new `O' ring/ gasket and keep it ready as spare.
PO No. : 4000170293
Page No. 16 / 60
Loosen the fasteners of the coupling and remove coupling spacer etc. as per requirement.
Remove the necessary pipe connections as per requirement.
Open bearing cover, remove bearing from shaft.
Removal of thrust collar from position as per requirement
Thoroughly clean the parts and replace/ repair damaged parts, if any.
Checking of bearing clearances as per requirement and carry out necessary corrections if any.
Assemble the bearing/ bearing housing into the shaft.
Normalize the pipe connection.
Fit the coupling spacer and tighten the fasteners as per torque requirement etc.
Take trail run and attend defects, if any.
PO No. : 4000170293
02)
03)
04)
05)
Page No. 17 / 60
Align pump with gear box/ motor, after matching if required as per EIC / OEM manual.
Fitting of keys & bushes after alignment & carry out necessary correction in keys & bushes by grinding etc.
Fit the coupling spacer/ hub and tighten the fasteners as per requirement etc.
Take trail run and attend defects, if any.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 18 / 60
01) Loosen the fasteners of coupling (DE & NDE) side and remove coupling spacer/ hub. Loosening of
foundation bolts. Removal of necessary keys etc from position.
02) Align gear box with drive turbine, after matching if required as per EIC / OEM manual.
03) Fitting of keys etc after alignment & carry out necessary correction in keys by grinding etc.
04) Fit the coupling spacer/ hub and tighten the fasteners as per requirement etc.
05) Take trail run and attend defects, if any.
34. Complete replacement of TDBFP Gear box:
Schedule No. 10.330:
Service Code: TMG/B00BD800
01)
side.
02)
03)
04)
05)
06)
07)
08)
Loosen the fasteners of coupling (DE & NDE) side and remove coupling spacer/ hub in both DE & NDE
Loosening of foundation bolts. Removal from position.
Removal of all piping connection from gear box.
Removal of complete gear box from position.
Positioning of new gear boxes in foundation frame. Mounting of coupling hubs (DE & NDE).
Assembly of all oil pipes with new O-rings / gaskets.
Fit the coupling spaces and tighten the fasteners as per requirement etc.
Take trail run and attend defects, if any.
Loosen the fasteners of coupling (DE & NDE) side and remove coupling spacer/ hub in both DE & NDE
Removal of all piping connection from gear box as per requirement.
Removal of top cover from position.
Removal of input & output shaft from position.
Cleaning & inspection of all parts.
Replacement of defective parts, bearings, Oil seals etc as per requirement.
Assembly of gear box and box up of top cover.
Assembly of all oil pipes with new O-rings / gaskets.
Fit the coupling hubs & spaces and tighten the fasteners as per requirement etc.
Take trail run and attend defects, if any.
PO No. : 4000170293
Page No. 19 / 60
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 20 / 60
(Total accumulators #12) Payment will be made on prop ornate basis based on the actual quantity executed.
1)
2)
3)
4)
5)
6)
Isolation & draining of Control fluid and BFP accumulators one by one.
Fix the testing kit on the accumulator and check the N2 gas pressure
Shift the N2 gas cylinder and fill the accumulator to the required gas pressure using charging kit
Again ensure the gas pressure using testing kit
Check for leakages in the filling valve and attend to it if any.
Charging the CF accumulators with oil & attending of defects if any
42. TDBFP hand barring and BFP freeness checking when not coming on barring gear:
Schedule No. 10.410:
Service Code: TMBFT05GN359
01) Decouple of TDBFP drive turbine (both gear box & BFP side) and remove the spool piece of
engage-disengage coupling / flexible coupling as applicable.
02) Carry out hand barring of drive turbine as per requirement.
03) Fix the clamp in the coupling hub of BFP for rotation
04) Rotate the BFP using the clamp till freeness is achieved
05) Once freeness is achieved, box up the spool piece of Coupling
06) Box up engage-disengage / flexible coupling.
07) Charge barring gear system and check for leakages and attend if any.
Inspection of all parts & all O-rings, Replacement of defective parts if any.
Assembly of bowl discs & tightening of locking rings and box up of bowl assembly.
Inspection & cleaning of suction strainer.
Checking of gear box oil level, top up or replacement of gear box oil as per requirement.
Centrifuge integral gear pump coupling inspection & replacement of defective parts if any.
Inspection of break shoe and replacement if any.
Charging of system & attending of defects if any
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 21 / 60
11) Run and check for leakage and vibration and attend for defects if any.
12) In case of stage-II, centrifuge belt tension adjustment & replacement of all defective components.
45. Centrifuge Gear pump overhaul or Control fluid Regeneration gear pump overhaul:
Schedule No. 10.440:
Service Code: TMCEN51OH001
1.
Removal of oil piping as per requirement.
2.
Decoupling of gear pump and removal of gear pump from position.
3.
Checking of pump oil seals & O-rings and Replacement of defective parts.
4.
Checking of gear pump internals such as impellers , bearings , Rulan gasket & relief valve etc as
applicable and replacement of defective parts if any
5.
Box up of gear pump & oil piping.
6.
Charging of system & attending of defects if any.
46. Main turbine AOP / EOP Overhauling:
Schedule No. 10.450:
Service Code: TMAOP03OH001
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Loosen the fasteners motor base frame & remove the necessary pipe connections
Remove the pump along with motor and base frame from tank
De-coupling the pump from motor
Remove the pump from position
Dismantling the pump internals
Repair / replace damaged internals such as bearing, impeller etc. as per requirement
Clean the internals as per requirement
Box up the pump with new o ring / gasket/sealing ring etc. as per requirement
Mount the pump in the base plate & coupling with motor
Place the pump along with motor & base frame on the tank
Tighten the base frame fasteners & pipe connections with new o ring/gaskets etc. as per requirement
Charge the system and attend if any defects.
PO No. : 4000170293
1.
2.
3.
4.
5.
6.
7.
8.
Page No. 22 / 60
Loosen the fasteners motor base frame & remove the necessary pipe connections
Remove the pump along with motor and base frame from tank
De-coupling the pump from motor
Remove the pump from position
Mount the new pump in the base plate & coupling with motor
Place the pump along with motor & base frame on the tank
Tighten the base frame fasteners & pipe connections with new o ring/gaskets etc. as per requirement
Charge the system and attend if any defects.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 23 / 60
1.Loosening of fasteners of DMCW cooling water piping connections at Cooler top water box.
2.
Removal of oil inlet & outlet pipe connections to cooler.
3.
Removal of all cooler vent lines.
4.
Loosening the fasteners of cooler inlet & outlet water box flange connections.
5.
Removal of Top water box from position.
6.
Removal of tube bundle from position.
7.
Removal of cooler shell from position.
8.
Removals of tube bundle cover plate.
9.
Through cleaning of tube bundle from both tube side & shell side by the help of wire brush, compressed,
water, diesel/petrol etc as applicable.
10. Cleaning of cooler shell, water box etc
11. Positioning of tube bundle cover plate with new gasket.
12. Assembly of Cooler shell, tube bundle, top water box in position with new O-rings.
13. Normalization of piping connections with new gasket/O-rings.
14. Charge the system and attend leakage / defects etc if any.
55. Servicing of Dosing pump(ammonia/ hydrazine/ dosing pumps): Schedule No. 10.540:
Service Code: TMCDP00OH000
1. Disconnect suction/discharge pipes and remove NRV as per requirement.
2.Drain oil from gear box/ hydraulic chamber as per requirement.
3.Loosen the diaphragm/plunger housing bolts and remove diaphragm./plunger
4.Dismantle the gearbox completely.
5.Clean thoroughly & repair / replace components of pump, gear box etc. as per requirement.
6.Box up the gearbox & plunger assembly and connect necessary pipe connections etc.
7. Fill up with required quantity of fresh oil in gearbox etc.
8.Take trail run and attend defects if any.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 24 / 60
56. PM checks of LP pump (Dia <6") such as Primary water pump/ TDBFP AOP or EOP / flushing pumps / CT
Pump / dewatering pumps:
Schedule No. 10.550:
Service Code: TMLPP01PM012
1.
Checking of couplings healthiness and tightening the same
2.
Checking of gland packing healthiness and tightening the same or tightness of grub screw of mech seal etc
as applicable.
3.
Tightening of all foundation and flange bolts
4.
Checking gear box oil quality and top up if required.
5.
Replacement of gear oil if required.
6.
Tightening of deflector plates as per requirement
7.
Suction filter cleaning as per requirement
8.
Greasing of bearings as per requirement
9.
Cleaning of the equipment and surrounding piping & trays
57. PM checks of LP water pump (Dia >12") ARCW or DMCW pump Schedule No. 10.560:
Service Code: TMLPP03PM012
1.
2.
3.
4.
5.
6.
7.
Checking of coupling pins & bushes healthiness and replacement as per requirement.
Checking of gland packing healthiness and tightening the same.
Checking the mech seal grub screw tightness as applicable.
Tightness checking of foundation bolts.
Greasing of bearings as per requirement.
Tightening of deflector plates as per requirement.
Cleaning of the equipment and surrounding piping & trays.
58. Overhauling of LP water pump (Dia >12") such as DMCW / ARCW pumps:
Schedule No. 10.570:
Service Code: TMLPP03OH001
01)
02)
03)
04)
05)
06)
07)
08)
09)
10)
11)
12)
13)
14)
59.Overhauling of LP water pump (DIA<6") such as Primary water pump / COLTCS Flushing pump /ACW self
cleaning filter flushing pump / TDBFP EOP:
Schedule No. 10.580:
Service Code: TMLPP01OH001
1.
Close the pump inlet & outlet valves. Drain oil/ water from pump casing.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 25 / 60
2.
De-couple motor with pump and take out the coupling spacer/ hub as per requirement.
3.
Drain the oil completely from bearing housing.
4.
Remove pump cartridge assembly from volute casing.
5.
Dismantle the pump assembly completely, like bearing covers, seals, bearings, bushes, impeller and
mechanical seal.
6.
Thoroughly clean the parts and replace/ repair damaged parts if any.
7.
Assemble the pump in order with new/ repaired parts as per requirement.
8.
Fill it up with required quantity of fresh oil in bearing chamber.
9.
Carry out alignment of pump with motor as per EIC / OEM Manual.
10. Couple motor with pump.
11. Take trail run and attend defects if any.
60. Overhauling LP water pump (DIA>6"-12") such as Condensate Transfer (CT) Pump:
Schedule No. 10.590:
Service Code: TMLPP02OH001
01)
02)
03)
04)
05)
06)
07)
08)
09)
10)
11)
12)
61. LP water pump Mechanical Seal replacement (Such as Primary water pump / COLTCS Flushing pump
/ACW self cleaning filter flushing pump / TDBFP EOP):
Schedule No. 10.600:
Service Code: TMLPP01BD798
1.Close the pump inlet & outlet valves. Drain oil/ water from pump casing.
2.De-couple motor with pump and take out coupling spacer.
3.Remove pump cartridge assembly from volute casing.
4.Take out impeller from shaft.
5.Take out mechanical seal from pump and clean thoroughly.
6.Install the new/ repaired seal on the pump.
7.Fit the impeller on the shaft and tighten and tighten the lock nut.
8.Assembly the pump with volute casing with new gasket and O-ring.
9.Carry out alignment of pump with motor as per EIC / OEM Manual.
10.Couple motor with pump.
11.Dismantle the removed mechanical seal, renew/ lap sealing surfaces as per requirement.
12.Assemble the mechanical seal by using new `O' rings & gaskets and keep it as spare.
13.Take trail run and attend defects, if any.
62. Alignment of LP pump with motor (DMCW / ARCW / Vacuum pump / Primary water pump/ COLTC flushing
pump/ ACW self cleaning filter flushing pump/TDBFP AOP & EOP):
Schedule No. 10.610:
Service Code: TMLPP00GN152
01) De-couple motor from pump, remove coupling bolts / bushes/ spacers/ hubs etc as applicable.
02) Match motor with base plate, if required.
03) Align motor with pump.
04) Couple motor with pump after necessary replacement of worn out parts of coupling bolts/ spacers/hubs,
torque tighten coupling bolts as per requirement.
05) Take trail and attend defects, if any.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 26 / 60
64. LP water pump Gland repacking of pump DE and NDE side of ARCW pump or Vacuum pump:
Schedule No. 10.630:
Service Code: TMLPP55BD800
1)
2)
3)
4)
5)
6)
7)
Remove the suction foot valve from suction line / suction strainer of the pump
Clean the perforated grill off debris
Check the perforated suction grill for damage and repair as per requirement
Place the foot valve / submersible pump in location with new gasket for flange
Start the pump and check for discharge and attend to defect if any.
Make necessary lifting & holding arrangement for the manhole door opening fixture
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 27 / 60
2)
Loosen the manhole door bolts and remove the studs after connecting the fixture
3)
Remove the manhole door and take it outside
4)
Inspect the internal parting plane doors and the heater dome for erosion and other damages.
5)
Open the parting plane bolts and remove the parting planes as per requirement
6)
Clean the gasket area of parting plane and check for erosion marks
7)
Repair the erosion / damages by welding & grainding if any as per requirement
8)
Cut new gasket for parting plane and box up the parting plane
9)
Clean the gasket area of the manhole door and Heater body face
10) Check the gasket area faces and repair for any erosion / defects by welding & grinding as per requirement.
11) Cut new gasket / use new gasket as per requirement
12) Hold the manhole door in the fixture and insert inside the heater after keeping gasket in place
13) Tighten the manhole door studs
14) Remove the fixture from manhole door
15) Charge the heater and pressure tighten / hot tightening of the door studs and check for leaks and attend
defect if any.
68.Inspection & cleaning of De-aerator tower and FST :
Schedule No. 10.670:
Service Code: TMDEA00OH000
1)
Opening of manholes of De-aerator tower & FST.
2)
Inspection of De-aerator & FST internals like trays, spray valves, supports etc and rectification of any
defects as per requirement.
3)
Replacement of defective nozzles. Repair of internals like trays, spray valves, supports etc by welding &
grinding as per requirement. All fasteners tightness checking.
4)
Manual cleaning of debris & sediments.
5)
Cleaning of chockage in drain pots / other connections.
6)
Box up of all manhole doors with new gasket
69.Condenser Hot well cleaning:
Schedule No. 10.680:
Service Code: TMCND53GN100
01)
02)
03)
04)
05)
06)
07)
PO No. : 4000170293
Page No. 28 / 60
1)
2)
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 29 / 60
3)
Open the flanges and remove the ACW inlet & outlet elbows
4)
Loosen the holding studs of PHE
5)
Move the front holding plate and loosen the plate stack
6)
Inspect each and every plate for damage and check the sealing ring condition
7)
Clean each and every plate from scales & debris as per requirement by using a soft brush as per
requirement.
8)
Replace sealing rings in plates as per requirement.
9)
Addition / replacement of plates as per instruction of EIC.
10) Arrange the plate stack and tighten with tightening studs
11) Cut new gaskets from sheet as per requirement for all flanged joints
12) Box up and tighten DMCW and ACW inlet & outlet elbows
13) Charge and check for leakages and attend to if any
76.Valve Gland packing replacement up to 200 NB:
Schedule No. 10.750:
Service Code: TMLPV52BD800
Loosen gland follower bolts and lift gland follower.
Take out the old packing from stuffing box.
Clean the stuffing box.
Cut the new gland rope to size or preformed packing and pack the stuffing box.
Tighten the gland nuts uniformly.
Plug the online injection adaptor holes & weld if it is a online injected valve
Check free operation of valve
Check free operation of valve. Charge the system and attend leakage if any.
Gland tightening after charging the system if required.
77. Valve Gland packing replacement above 200NB size:
Schedule No. 10.760:
Service Code: TMHPV51BD800
1)
2)
3)
4)
5)
6)
7)
8)
9)
PO No. : 4000170293
10)
11)
12)
Page No. 30 / 60
PO No. : 4000170293
Page No. 31 / 60
PO No. : 4000170293
Page No. 32 / 60
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 33 / 60
PO No. : 4000170293
08)
09)
Page No. 34 / 60
PO No. : 4000170293
Page No. 35 / 60
Making the necessary arrangement for removing the gear box from valve shaft.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 36 / 60
2.
Removal of gear box from valve.
3.
Dismantling of gear box internals.
4.
Replacing & repairing the defective parts.
5.
Box up of gear box with new grease.
6.
Mounting the gear box on the valve shaft. Adjustment of mechanical stopped arrangement for full open
and close of the valve.
7. Charging the system and attending of defects if any.
101. Welding of pipe punctures and pipe welding cracks by patch welding
Schedule No. 10.1000:
Service Code: TMMSW00GN972
01)
02)
03)
04)
05)
06)
102. L.P. Pipe line lying of length one meter of size up to 6" size.
(Estimation for laying of pipe for 1mtr length)
Schedule No. 10.1010:
Service Code: TMMSL01GN552
1)
2)
3)
4)
5)
6)
7)
8)
103. L.P. Pipe line lying of length one meter of size 6-12" size.
(Estimation for laying of pipe for 1mtr length)
Schedule No. 10.1020:
Service Code: TMMSL02GN552
1)
Make necessary approach platform as per requirement
2)
Take necessary measurements and cut the pipe as per requirement
3)
Edge prepare the pipes by grinding and lay the pipes as per requirement
4)
Align the pipes and make fitment
5)
Root weld the pipe and do DPT as per requirement and rectify for any defects
6)
Do build up welding of joints. Welding of pipes with flanges as per requirement.
7)Putting new gasket in flange joints as per requirement.
8)Charge and check for leakages and attend if any
104. Flange gasket replacement up to 4"
Schedule No. 10.1030:
Service Code: TMFLG07BD000
1)
Remove flange bolts.
2)
Remove old gasket & clean the flange surfaces.
3)
Check the surface area for any cut, build up the cut area by welding and then finish by grinding when ever
required.
S K SAHA, DGM(C&M)
PO No. : 4000170293
4)
5)
6)
Page No. 37 / 60
PO No. : 4000170293
7.
Page No. 38 / 60
109. Duct (CW SYS) 2300 NB Temporary Blanking Install/Remove for Condenser Cleaning:- Schedule No.
10.1080:
Service Code: TMDCT01GN400
1. Giving necessary assistance for isolation & draining of condenser pass.
2.
Making necessary platform for opening of manhole doors of condenser front & rear side water box.
3.
Making necessary platform inside condenser CW Duct both in front & rear side for Welding and fabrication
work.
4.
Blanking of both I/L & O/L CW Duct closer to Water box with 10/12mm MS plate, approx. Dia 2300 NB and
support stiffeners.
5.
MS plate to be cut to the suitable size so that it can be entered through manhole and welding to be done
inside the duct to blank the entire I/L and O/L duct.
6. Back side of the Blanking plate suitable stiffener to be welded to ensure the sufficient strength so that it can
withstand the water Load of water box.
7. Total 4 No's of blanking plate to be welded 2 I/L and 2 O/L.
8. After completion of the acid cleaning job all blanking plate to be removed and surface area to be properly
cleaned.
9. Removing the scaffolding material from the condenser water box.
10. Steel for the above job will be supplied by NTPC but agency has to arrange all other consumables.
11. Work to be completed in scheduled time accordingly sufficient gang to be deployed after draining of the
water BOX.
Fabrication of MS boxes as per requirement for arresting leakages and welding the same in position.
Fabrication of small platforms, hand rails etc and attending of 24x7 safety defects.
Fabrication of racks for keeping spares & tools as per requirement.
Up keeping of turbine maintenance stores / T&P stores etc.
Fabrication of clamps for water leakage arresting.
Dewatering from drain pits / CW ducts etc as per requirement by putting portable de watering pumps.
Cleaning of Instrument air compressor drain traps provided in TG hall.
Any other misc jobs as per instructions of EIC.
PO No. : 4000170293
2.
Page No. 39 / 60
Gang should be capable for executing all kind of emergency related to minor breakdown work.
113. Operation & Minor maintenance of TG Hall EOT crane & Misc hoists in Turbine & Aux. area
Schedule No. 10.1120:
Service Code: TMEOT00GN702
EOT/Cranes (<>) OPN/MTC
01) Operation of 105T (main hoist) / 15T (Aux. hoist) Electrically operated Overhead Travelling crane (EOT
crane) - 2Nos., Misc. hoists in Turbine area, Misc. hoists in Compressor house and ACW pump house on daily
basis as per requirement & instruction of EIC
02) Carrying out minor preventive maintenance jobs in the EOT crane & Misc. hoists in the areas mentioned
above like Lubrication, Brake adjustment, cleaning etc. as per requirement
03) Regular inspection of both the EOT cranes & Misc hoists for defects in mechanical, Electrical, C&I
components etc. and bringing it to the notice of EIC immediately
04) Regular observation of EOT cranes & Misc hoists during operation for abnormal sounds, jerks, limit
switches functioning, backlash in commands etc. and bringing to the notice of EIC immediately
05) The crane operators deployed should have at least one year experience in operation of similar EOT cranes
of capacity 105T/15T or above and should be physically & mentally fit.
06) During non working days & requirements beyond working hours in working days the contractor should
arrange the crane operator within 1 hour after information of crane operator requirement.
07) During Long shutdown / overhaul periods the contractor should supply crane operators in shifts on round
the clock basis and as per requirement & instructions of EIC
08) The performance of the operator will be tested by NTPC during initial and during the course of operation
and if found unsatisfactory by EIC, the contractor should replace the operator immediately.
09) The contractor should bear the cost & risk of damage of components being lifted / lowered and damage of
components of EOT crane due to negligence on the part of crane operator or mal operation or mishandling.
10) Each Man Day of 8 hr deployment of the crane operator will be considered as one Unit .
114. Replacement of HPBP/LPBP hoses
SCHDULE NO: 10.1130
SERVICE CODE: TMHPB61BD001
HPBP Valves (HOSE) ATTEND BREAKDOWN
1. After ensuring permit, remove the damaged hoses.
2. Replace the same with new one. During the replacement of hoses any leakages of lub oil should be avoided.
3. Take trail and attend defects if any.
115. Misc Works Attend Defect
SCHDULE NO: 10.1140
SERVICE CODE: TMMSW00BD000
Misc Works (<>) Attend Defect
1. Take permit if required then do the misc jobs at the sites. The jobs may be unforeseen and unplanned
depending upon the condition of the plants
2. During performing of these type of jobs follow the safety rules strictly inside plant premises.
116. Misc Works OIL FILLING
SCHDULE NO: 10.1150
SERVICE CODE: TMMSW00BD600
Misc Works (<>) OIL FILLING
1. There are various equipments in which lub oil filling is required from time to time except MOT,and TDBFP.in
those equipments oil is to be topped/filled upto normal level as per instruction of EIC/ Site Engineer.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 40 / 60
Repair and maintenance of the various spare equipments, assisting service Engineer during repair work.
Deployment and mobilization of All necessary T&P for assistance of the above job
S K SAHA, DGM(C&M)
PO No. : 4000170293
2.
Page No. 41 / 60
Removal of cladding, insulation etc in case attending jobs like leakages from pipes.
After rectification of the problem again cladding, Insulation to be replaced.
PO No. : 4000170293
Page No. 42 / 60
2. Scope of Work:- Preventive maintenance and break down Maintenance of Turbine & auxiliaries of TMD as per
detail scope of work of following areas: -a. Steam Turbine and Auxiliaries b. Service and instrument air system c.
EOT Crane
3. Material and facilities to be provided by NTPC:- Following material are to be provided by the NTPC for the
above work. a. Workshop facility. b. Water, air and electricity required for the work. c. Special tools and tackles
as required for carrying out this work. d. Hydra Crane, BOT, Fork lift, Suitable scaffolding material & ladders.
4. Material and facilities to be provided by Contractor:- a. Experienced, qualified and competitive manpower. b.
Safety helmet, safety shoes and other PPE for contractor's manpower. c. Contractor will have to arrange their
own arrangement for boarding, lodging and conveyance for manpower deployed.. d. T&P for satisfactory and
timely completion of job as per list enclosed.(Annexure I) e. Consumables like kerosene, diesel, rustoline,
thinner, cotton waste, marking/cloth, emery paper, hacksaw blades, wire brushes, scrappers, cutting & grinding
wheels, general purpose electrodes, cutting gases(DA &O2)etc. f. Two numbers of cutting & welding set and one
set of Argon welding set along with DA, Oxygen, argon cylinders.
5. Site Clean - Up After completion of the work, all sites and work area has to be cleaned properly by the
Contractor. Scrap and waste generated during work has to be shifted to scrap yard or place as per direction of
EIC.
6. Safety All safety measures in respect of contractor' s personnel has to be taken care by the contractor. Safety
personal protection equipment's e.g. Safety helmet and safety shoes are to be arranged by contractor from the
first day of work as required for the successful completion of the work. Failing which, on very next day NTPC will
provide the above PPEs on non returnable basis as per standard NTPC rate.
7. Defect Liability Period -Three months
1. The works are to be carried out under strict, efficient supervision and with utmost safety. To ensure the same,
contractor shall post qualified, experienced & adequate site supervisors.
2. PERIOD OF CONTRACT - shall be 12 months from the date of commencement of work and shall be
extended in continuous for another 12 Months on same rate terms & conditions . During the contract period, the
contractor shall attend to various jobs detailed in subsequent chapters as per the instruction of
engineer-in-charge. NTPC reserves its right to terminate the contract before the completion period. Since it is a
rate contract, the quantities indicated in the contract are indicative only and may vary depending on actual
requirement. The contractor shall not have any extra claims over the agreed rates on account of increase or
decrease in quantities during the contract period.
3. PAYMENT TERM - Monthly payments shall be made on the basis of actual quantity of work executed during
the month against submission of bills subject to verification by engineer-in-charge.
4. PRICE BASIS - The contract shall be executed on firm price basis and during the contract period, no deviation
in rates shall be accepted. Hence, it is advised that Contractor should make himself familiar with the nature,
location and type of jobs. The rate shall be inclusive of service charges, overheads, profits, consumables, safety
appliances, T&P etc.The Quoted rates shall be inclusive of all taxes and duties except service tax.Service Tax
will reimbursed extra on submission of documentary evidence.
5. Quality of work:
5.1 NTPC will give PTW for Preventive Maintenance as well as Breakdown Maintenance work depending upon
the plant condition. However, no idling charge shall be paid to the contractor under any circumstances
whatsoever it may be.
5.2 All preventive work will be planned one day in advance and same will be intimated to contractor and
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 43 / 60
accordingly contractor has to make necessary arrangement of additional manpower if required to carry out work.
5.3 Quality & Standard of routine and preventive maintenance works have to be ensured by contractor so that no
breakdown of equipment or system should occur thereafter or during its running. Standard engineering practices
/ instruction of engineers to be followed. No additional payment will be made for break down job/works. In case
of unsatisfactory job quality, party may be asked to redo the job or rectify the defects without any extra cost.
5.4 The contractor will have to submit program one-day in advance to arrange permit to work. The contractor
shall also ensure HOT WORK PERMITS applicable for any gas cutting, welding or hot work and should also
observe full safety precaution to avoid any fire/other accident.
5.5 The contractor should ensure his or his authorized representative availability to receive all instructions
regarding execution of work and to handle to site activity.
5.6 Jobs have to be done in the working plant. Hence, as per situation, if work has to be stopped in between, no
extra charge will be made. Permit system operative in BSTPP has to be strictly adhered to.
5.7 All the drawings are indicative and can be seen from TMD office. The contractor may be asked to do the
maintenance as per existing arrangement and repair accordingly and the fitment will have to be ensured.
5.8 PAINTING: All the new fabricated and erected structure/pipe lines (if any) ,are to be painted with one coat of
red-oxide and two coats final paints. The color will be as per requirement and instructions of Engineer-in-charge
or his authorized representative. Painting after OH of Pumps/equipments to be carried out. Painting material will
be provided by NTPC.
5.9 The works, depending on their nature, are to be carried out by experienced & suitable qualified man power.
To ensure the same NTPC may ask and check the qualification of the technicians.
5.10 All scrap and excess materials will have to be shifted to a store or place as decided by engineer-in-charge
or his representative.
5.11 The contractor or his authorized permanent, technical and administration representatives should be
available at site office all the time. The representative shall meet the engineer-in-charge for receiving the
necessary instruction on day to day basis.
5.12 On receiving instructions from engineer-in-charge, the contractor shall deploy experienced and adequate
number of man-power to carry out the work with the stipulated time schedule. The contractor may also have to
deploy additional manpower if required by engineer-in-charge.
5.13 The supervisor employed must be having sufficient experience in maintenance of Turbine, Turbine
auxiliaries, valves, fans, pumps, blowers, fabrication work and other mechanical equipments.
5.14 NTPC shall provide all type of lubricants and spare parts used in the equipment. The contractor shall take
delivery of these at NTPC store, transport it to site, do the work and return the defective spares removed (if any)
to designated places as per instructions of NTPC representative without any extra cost. All arrangements for
above shall be done by the contractor for which required hydra, pick-up van etc. will be arranged by NTPC.
However, a manual trolley for transportation of small volume material has to be maintained by the contractor.
5.15 Consumables like kerosene, diesel, thinner, cotton waste, cloth, emery paper, hacksaw blades, wire
brushes, scrappers, cutting & grinding wheels, general purpose electrodes (6013/7018 of make D&H, ADVANI,
ESSAB only) etc. Shall be arranged by the contractor at his own cost. The contractor shall ensure that all the
required consumables are stocked at site in sufficient quantity so that work is not hampered at any point of time
due to un-availability of these items.
5.16 T&P - contractor has keep to minimum tools tackles as per enclosed list however this list is not exhaustive
& will have to arrange additional T&P as and when required, as directed by engineer-in-charge.
5.17 All special tools and tackles shall be provided by NTPC. The broad meaning of special tool and tackles
shall be "all those tools which are of not general purpose and have been specifically tailored to meet a particular
requirement of particular equipment shall be designated as special tools and tackles". However, final meaning of
this will be as interpreted by engineer-in-charge. Normal hand tools shall have to be provided by contractor.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 44 / 60
5.18 Contractor has to depute sufficient additional manpower for emergency jobs within the short notice period.
In case the contractor fails to provide the additional man-power within the notice period given, NTPC will have
the right to arrange the same and will recover the cost from the contractor.
5.19 Contractor shall maintain a work order book at site to get instructions from engineer-in-charge.
5.20 Contractor will be required to work on Sundays, holidays, in shifts and during night also seeing the urgency
/ requirement of the work. The payment shall be made as per the rates quoted only. Contractor shall not demand
any extra payment from NTPC towards this.
5.21 All scaffoldings made for maintenance has to be removed immediately after the completion of work and for
this no charge will be paid.
5.22 Any damage to NTPC property has to be repaired/ renewed by the party free of cost. If any spares are to
be provided in this work by NTPC, the cost of such spares will be recovered from contractor.
5.23 Food and snacks etc to be arrange by the contractor, at his own cost, for his manpower on site during
emergency/ break down work.
5.24 Two numbers of cutting & welding set and one set of Argon welding set along with DA, Oxygen, argon
cylinders should always be available at site. Empty cylinders are to be immediately get filled to avoid any delay in
work.
6. FAILURE OF CONTRACTOR TO ATTEND A JOB IN A STIPULATED TIME : In case, contractor leaves the
work partially, the same left out work can be completed departmentally or with the help of some other agency.
The cost thus incurred shall be deducted from the bills of the contractor.
7. COMPLETION OF JOB : 1 The job shall be defined as completed only after the equipment is recharged and
the defects observed earlier do not reoccur. The equipment will be put on trial run and observed for a time period
as decided by engineer-in-charge before accepting completion of the job. In case the maintenance carried out is
not accepted by engineer-in-charge, the same shall be redone by the contractor without any extra cost. 2 Any
machining or other workshop facility required will be extended as per availability of same on free of cost.
8. LABOUR RULES & REGULATION :
1 The contractor shall comply with all the industrial acts, viz. Minimum wages act, employees liability act.
workmen compensation act, contract labour regulation, arbitration act & the employees state insurance act, or
any modification thereof or any other law relating thereto and made there under from time to time and maintains
various all records required.
2 Contractor will pay wages, allowances including other benefits such as workman's compensation, provident
fund, bonus and any other claims arising out of such employment under law and award as may be payable to
the workers employed by contractor from time to time and also furnish P.F. code certificates issued from
appropriate authority for contractor's employees.
3 The contractor shall provide all details of payment made by him to his employees to the engineer-in-charge, if
asked for.
4 The contractor shall ensure discipline and integrity of the personnel deployed by him and disobedience and
indiscipline by any of the contractors employee, he will be removed from work as per the directions of
engineer-in-charge.
5 The contractor is required to pay wages in presence of NTPC representative.
6 The contractor and his employees shall co-operate with all other agencies working at site.
7 Necessary entry gate pass for BSTPP premises will be required for the contractor employees as per rules
pertaining at the time of contract. The necessary formalities required to get the gate pass shall be done by
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 45 / 60
contractor.
8 The party has to provide proper identity cards to all the workmen before engaging them at work site.
9 If any misconduct, negligence or incompetence of any worker is reported, he is to be removed immediately
from the work site as per the instruction of Engineer-in-charge.
9.SAFETY:
9.1 The work is to be carried out only after getting "permit to work" (PTW) from area maintenance engineer.
9.2 The contractor has to make all safety arrangements for men and material during the work. He has to follow
all safety rules strictly. The contractor shall be held responsible for any lapse in safety. During the work, if any
persons of contractor meet with an accident, the responsibility of medical treatment of the labour and payment of
compensation if any under applicable rules/regulations/statutory requirement lies with the contractor.
9.3 Party has to impart awareness to all his personnel regarding safety. They may approach NTPC safety deptt.
for guidance in this regard
9.4 The contractor's workmen will be required to work at various heights, locations and in vicinity of rotating /
running equipment and also equipment in not working conditions. He should give proper instructions to workmen
to be careful to avoid accidents.
9.5 All safety measures in respect of contractor's personnel have to be take care by the contractor The
contractor shall arrange proper and sufficient number of Personal Protective Equipments such as hand gloves,
helmets, nose-muff, ear muffs, safety shoes, first aid box, safety belt, protective equipments for welding and gas
cutting etc., and ensure that his workmen use them during the execution of work as deemed fit by
Engineer-in-charge. The PPE should be of good quality and damaged/unusable PPE is to be replaced by the
party free of cost.
9.6 The contractor shall ensure that his manpower strictly adhere to safety rules and instructions given to them
by NTPC Safety Engineer / Engineer-in-charge or his representative during execution of the work.
9.7 It is mandatory for all workers to wear boiler suit, safety helmet and safety shoes at work place. Failure to
compliance of above them shall not be allowed in the work place.
10. COMMUNICATION The contractor shall provide mobile phone to the site in-charge / supervisor for BSTPP
for effective and efficient communication with NTPC officials
11. The contractor shall immediately vacate the premises allotted to him during execution of the contract, on
completion of the contract.
12. Normal working times will be from 0830 hrs to 1730 hrs (8 hrs / day) excluding lunch break from 1300 hrs to
1400 hrs. During brake down / in emergency, manpower will have to be deployed during off hours timing/
Sunday/holiday also, same rate will be applicable during off hours working. Work has to be carried out in shifts
also as per the requirement of the job. Contractor has to deploy manpower accordingly without any additional
cost to NTPC.
13. Minimum Manpower - following are required to be deployed for smooth functioning of day to day jobs.
sn Manpower qty.
1 Supervisor 1
2 M/W fitter 2
3 Gen. Fitter 2
4 Gen Welder 1
5 Rigger
2
6 Semi Skilled 6
7 Semi Skilled (assistance to hydra operator) 2
Total-------------- - -------->> 16
8 HP Welder -as per requirement
The minimum manpower as mentioned above is indicative only. Man power may be increased or decreased as
per the need/nature of the work and contractor has to mobilize/arrange manpower accordingly as per instruction
of EIC. NO UNSKILLED MANPOWER SHALL BE DEPLOYED BY THE CONTRACTOR DURING THE
CURRENCY OF THE CONTRACT. Payment of Wages:The contractor shall pay not less than fair wage to
workers engaged by him on the work. "Fair Wages" means wages to be paid should consider the nature of the
work being carried out, the qualification and the experience of the worker to carry out the job as per requirement
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 46 / 60
of the contract. However in any case it shall not be less than the minimum wages fixed by the Govt. of Bihar or
Govt. of India whichever is higher for the class of employees engaged.
The contractor shall ensure the payment to the workers before 5th of each month. The contractor shall maintain
a wage register as per the format provided by the area engineer. The payment shall be made after taking the
signature of the worker in the wage register and duly certified by the area engineer. The copy of this wage sheet
shall be submitted along with the monthly bill.
The contract shall also submit the copy of the PF Challan, clearly certifying the name of the workers who's PF
has been deposited under that Challan. After one year the contractor shall also give the PF balance sheet for
the entire year, issued from the Office of the PF commissioner.
In case of non-observance of the above, NTPC will not accept and process the bill for payment and shall not be
responsible for delay in payment of the bill.
Contract value will remain firm during the complete execution period of the contract. If there is any wage revision
by Govt. of Bihar or Govt. of India, The contractor has to pay the wages whichever is higher and the extra
financial cost on account of wage revision has to be borne by the contractor/Party.
17. As NTPC is an ISO-14001 & ISO-18001 certified organization, contractor is bound to dispose the removed
gaskets (graphite, asbestos etc.), insulation material & other hazardous material to designated places only.
Annexure-I LIST OF TOOLS (TO BE ARRANGED BY THE PARTY) (FOR ONE SCHEDULE):
This is only indicative list, if any other general purpose tools are required for successful completion of job/
smooth operation of contract has to be arranged by party.
1. Spanner set (Ring) up to 36 mm : 03 sets. 2. Spanner set (DE) up to 36 mm : 03 sets 3. Spanner set (Ring)
up to 1.3/4" : 03sets 4. Spanner set (DE) up to 1.3/4" : 03 sets 5. Box spanner set inch size up to 1.1/2", mm
size up to 40 mm : 01 set each
6. Pneumatic impact wrench up to " drive : 01 no. 7. Ratchet handle up to " drive : 02 nos. 8. Die and taps
with handles inch and mm size up to " / 20 mm : 01 set each 9. Chisel : 02 sets 10. Gasket cutter : 01 set 11.
Center punch : 02 sets 12. Letter punch, number punch, hole punch : 01 set each 13. Combination and nose
plier : 02 each 14. Circlip plier (inside and outside) : 02 each 15. Pipe wrench 8" / 12" / 14" / 24" : 02/02/02/01
nos. 16. Allen Key set mm size up to 20 mm : 03 sets 17. Allen key set inch size up to " : 03 sets 18. Vernier
Calliper 150 mm / 300 mm : 01 no. each 19. Steel rule 300 mm / 1000 mm : 02 nos. each 20. Screw driver 6,&12" : 04Nos. each 21. Cutting plier - 10" : 04Nos. 22. Slide Wrench 12", 6" size : 04 nos. each 23. Steel
Hammer 1 kg, 2 kg, 5 kg : 04 Nos. each 24. Brass hammer 1 kg, 2 kg : 03 nos. each 25. Nylon /mallet hammer :
04 nos. 26. Rubber hammer : 04 nos. 27. Measuring tape -3 Mtr. : 04 Nos. 28. Right angle - 6" : 02 No. 29.
Files-250 mm size (bastard, smooth, triangular, half found, round) : 04 each 30. Needle file set : 02 sets 31.
Hacksaw frame : 03 Nos. 32. Hand lamp 24 volts : 06 Nos. 33. Torch 4 cell : 04 Nos. 34. Chain pulley block 1T,
3T cap. : 04 each 35. D shackle 1T, 2T, 3T cap. : 04 Nos. each 36. Slings - 10, 12, length up to 05 M. : 04 Nos.
each 37. Extension board with 30 M cable : 03 Nos. 38. Portable drilling machine up to 13mm size : 02 nos. 39.
Angle Grinder Size - 100 /125 mm : 04 nos. 40. Portable drilling M/C Size -10 mm : 02 nos 41. Straight Grinder
Size -10 mm : 02 Nos. 42. Welding Gen with all accessories : 01 Set. 43. Single phase portable welding
machine with all accessories : 02 set 44. Argon welding Set : 01 No 45. Cutting set with hose etc. : 02 nos. 46.
Copper hammer / rods : 04 nos. (min.) 47. Dial gauges : 04 nos. (min.) 48. Bearing puller : 02 set 49. Pipe vice
and bench vice : 01 each (min.) 50. Safety helmet : for all 51. Safety shoe : for all 52. Safety belt : 10 nos. (min.)
53. Mechanized / hand operated trolley : 01 no. min 54. Tool box : 04 nos. Note - one number of tool box
containing all necessary general purpose tools to be issued / given to each technician.
PENALTY CLAUSE:
Penalty rates for the following reasons:
01) For not complying safety rules : Rs.100/- per day per work. 02) Not deploying manpower within reasonable
time after issuing PTW : Rs.50/- per hour per work.
03) Non-supply of manpower : Double the rate of the type of manpower.
04) Work delay due to shortage of general T&P : Rs.200/- per job per day.
05) Delay in schedule completion time : Rs. 500/- per day.
06) Not using safety appliances : Rs. 50/- per day per item per Man power deployed.
07) Damage of NTPC machinery & T&P : Repair of machinery/T&P free of Cost or 1.5 times the present cost
08) Loss of NTPC T&P and other items. : Replacement item from market or 1.5 times the present cost.
Manpower Requirement and Deputation
The contractor shall depute experienced, qualified and competitive manpower to take up this job. The manpower
should be sufficient to complete the job within the time frame and with acceptable quality standard. If require the
interview of manpower will be taken by NTPC after the award of work.
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 47 / 60
a.i) SUPERVISORS Skilled, well qualified and experienced supervisors for coordination, planning, and execution
of job are required. They should have sufficient previous working experience of Min 3 years of such type of
similar work in power station or in other reputed organization. They should be able to plan the jobs, material and
manpower etc. as per day to day activities. They should have good communication skills with workmen and be
able to motivate them for timely and qualitative completion of job. They shall be able to read the drawings of
assemblies and evaluate and plan the job accordingly.
Qualification - minimum Diploma in Engineering or from Industrial Training Institute.
a.ii) MILL WRIGHT FITTERSITTER/HIGH SKILLED They should have sufficient working experience of
Overhauling/ ALIGNMENT of mechanical equipments like PUMPS/COMPRESSORS /BLOWERS
/AGITATOR/FANS/ VALVES/SAFETY VALVES/NRV/GEAR BOX etc. Mill Wright fitters should be capable of
using and reading precision measuring instrument like Micrometer, Vernier, Filler gauge, Dial gauge etc. Mill
Wright fitters should have done alignment of such type machine previously and should be able to do the same
independently.
a.iii) FITTERS/GRINDERS They should be capable of dismantling, repairs and assembly PUMPS/
COMPRESSORS BLOWERS /AGITATOR/FANS/ VALVES/ SAFETY VALVES/NRV/ GEAR BOX etc. he should
have experience of fabrication work. He should be able to do precision work with cutting, grinders, scrapping,
polishing, gas heating torches, various other special tools and use precision measuring instruments. Fitters
should be capable of using and reading precision measuring instrument like Micrometer, Vernier, Filler gauge,
Dial gauge etc.
a.iv) RIGGERS / SARANG They should be capable of using right tools, tackles and other equipment for lifting &
shifting of dismantled and heavy parts with expertise. They should be capable of guiding and co-ordinations with
crane operator by giving signals and signs for crane movements. Manpower should also know the scaffolding
work.
a.v) SEMI-SKILLED They have to provide support to other category manpower for all the work activities. They
should have experience of mechanical jobs and should have knowledge of working tools, scaffolding work etc.
a.vi) HP WELDERS HP Welders should have GTAW and GMAW certificates of quality welding for stainless
steel and alloy steel from boiler inspector or some other standard welding institution.
a.vii) GENERAL WELDER They should have sufficient working experience of grinding, cutting and welding. He
should be able to carry out both arc and gas welding with safety. He should be able to carry out fabrication work
as per site requirement
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 48 / 60
Break up of Price
---------------------------
Sl No. Service
Code
10 .10 TMCEP04
PM004
10 .20 TMCEP04
OH001
Description
Qty.
CEP(>500-660MW#)-04W
Chks
CEP(>500-660MW#)-OH
UOM
Rate
Premium Discount
Addl
Net
Discount Rate
Value
72
NO
2,430.00
0.00
0.00
NO
28,350.00
0.00
0.00
0.00 28,350.00
00
36
NO
3,240.00
0.00
0.00
NO
14,175.00
0.00
0.00
NO
4,860.00
0.00
16
NO
3,240.00
NO
300
56,700.00
0.00 14,175.00
00
14,175.00
0.00
0.00 4,860.000
0
4,860.00
0.00
0.00
0.00 3,240.000
0
51,840.00
7,290.00
0.00
0.00
14,580.00
NO
610.00
0.00
0.00
0.00 7,290.000
0
SET
2,577.00
0.00
NO
3,240.00
48
NO
0.00 610.0000
183,000.00
0.00
0.00 2,577.000
0
10,308.00
0.00
0.00
0.00 3,240.000
0
12,960.00
2,835.00
0.00
0.00
NO
4,860.00
0.00
0.00
NO
5,265.00
0.00
0.00
NO
10,935.00
0.00
0.00
NO
3,240.00
0.00
24
NO
2,835.00
37
NO
24
NO
10 .90
S K SAHA, DGM(C&M)
0.00 4,860.000
0
19,440.00
0.00 5,265.000
0
10,530.00
0.00 10,935.00
00
32,805.00
0.00
0.00 3,240.000
0
19,440.00
0.00
0.00
68,040.00
3,240.00
0.00
0.00
0.00 2,835.000
0
1,215.00
0.00
0.00
0.00 1,215.000
29,160.00
PO No. : 4000170293
Page No. 49 / 60
Sl No. Service
Code
Description
Qty.
GN100 (SEALWATER
FILTER) Cleaning
10 .190 TMSST07
GN100 STRAINER/FILTER
(50NB) Cleaning
UOM
Rate
Premium Discount
Addl
Net
Discount Rate
Value
24
SET
1,620.00
0.00
0.00
0.00 1,620.000
0
38,880.00
200
NO
610.00
0.00
0.00
0.00 610.0000
122,000.00
NO
12,960.00
0.00
0.00
25,920.00
NO
4,860.00
0.00
0.00
0.00 12,960.00
00
NO
4,050.00
0.00
0.00
12,150.00
NO
5,670.00
0.00
0.00
0.00 4,050.000
0
NO
4,860.00
0.00
0.00
14,580.00
NO
4,860.00
0.00
0.00
0.00 4,860.000
0
NO
5,670.00
0.00
0.00
NO
4,050.00
0.00
NO
5,670.00
NO
10 .310 TMBFP03
BD800
0.00 4,860.000
0
14,580.00
0.00 5,670.000
0
17,010.00
0.00 4,860.000
0
14,580.00
0.00 5,670.000
0
11,340.00
0.00
0.00 4,050.000
0
8,100.00
0.00
0.00
0.00 5,670.000
0
11,340.00
4,050.00
0.00
0.00
4,050.00
NO
12,960.00
0.00
0.00
0.00 4,050.000
0
NO
4,860.00
0.00
0.00
NO
6,480.00
0.00
0.00
NO
4,050.00
0.00
0.00
NO
6,075.00
0.00
0.00
10
NO
6,885.00
0.00
NO
4,050.00
24
NO
NO
BFP(>210-500MW#)-Repl
S K SAHA, DGM(C&M)
0.00 12,960.00
00
12,960.00
0.00 4,860.000
0
4,860.00
0.00 4,050.000
0
4,050.00
0.00 6,480.000
0
6,480.00
0.00 6,075.000
0
6,075.00
0.00
0.00 6,885.000
0
68,850.00
0.00
0.00
0.00 4,050.000
0
12,150.00
2,430.00
0.00
0.00
58,320.00
2,835.00
0.00
0.00
0.00 2,430.000
0
0.00 2,835.000
22,680.00
PO No. : 4000170293
Page No. 50 / 60
Sl No. Service
Code
BD800
Description
(BLADDER) Repl
Qty.
UOM
Rate
Premium Discount
Addl
Net
Discount Rate
SET
2,835.00
0.00
0.00
NO
3,645.00
0.00
0.00
0.00 3,645.000
0
72
NO
1,448.00
0.00
0.00
36
NO
3,240.00
0.00
0.00
NO
4,050.00
0.00
0.00
NO
3,240.00
0.00
NO
3,240.00
NO
10
0.00 2,835.000
0
Value
22,680.00
21,870.00
24,300.00
0.00
0.00 3,240.000
0
6,480.00
0.00
0.00
3,240.00
4,860.00
0.00
0.00
0.00 3,240.000
0
0.00 4,860.000
0
4,860.00
NO
3,240.00
0.00
0.00
32,400.00
40
NO
3,240.00
0.00
0.00
0.00 3,240.000
0
NO
4,860.00
0.00
0.00
9,720.00
NO
4,050.00
0.00
0.00
0.00 4,860.000
0
0.00 4,050.000
0
8,100.00
48
NO
2,025.00
0.00
0.00
0.00 2,025.000
0
97,200.00
32
NO
1,620.00
0.00
0.00
0.00 1,620.000
0
51,840.00
16
NO
3,240.00
0.00
0.00
51,840.00
96
NO
1,620.00
0.00
0.00
0.00 3,240.000
0
64
NO
1,620.00
0.00
0.00
NO
4,050.00
0.00
0.00
12,150.00
NO
2,835.00
0.00
0.00
0.00 4,050.000
0
NO
3,240.00
0.00
0.00
9,720.00
NO
3,240.00
0.00
0.00
0.00 3,240.000
0
S K SAHA, DGM(C&M)
0.00 2,835.000
0
17,010.00
0.00 3,240.000
9,720.00
PO No. : 4000170293
Page No. 51 / 60
Sl No. Service
Code
BD798
Description
(Dia<=6")
RPL-M-SEAL
Qty.
UOM
Rate
Premium Discount
Addl
Net
Discount Rate
Value
12
NO
3,240.00
0.00
0.00
0.00 3,240.000
0
38,880.00
12
NO
1,215.00
0.00
0.00
0.00 1,215.000
0
14,580.00
60
NO
410.00
0.00
0.00
0.00 410.0000
24,600.00
NO
3,240.00
0.00
0.00
6,480.00
1,620.00
0.00
0.00
0.00 3,240.000
0
NO
NO
7,290.00
0.00
0.00
14,580.00
NO
8,100.00
0.00
0.00
0.00 7,290.000
0
NO
8,100.00
0.00
NO
8,100.00
NO
10 .730 TMSST04
OH000 STRAINER/FILTER
(800NB) Serv
10 .740 TMPHE00 Plate Heat
GN100 Exchngr(<>)Cleaning
0.00 1,620.000
0
3,240.00
32,400.00
0.00
0.00 8,100.000
0
0.00 8,100.000
0
32,400.00
0.00
0.00
16,200.00
8,100.00
0.00
0.00
0.00 8,100.000
0
0.00 8,100.000
0
16,200.00
NO
3,240.00
0.00
0.00
0.00 3,240.000
0
6,480.00
NO
32,400.00
0.00
0.00
NO
4,050.00
0.00
0.00
0.00 4,050.000
0
8,100.00
NO
10,125.00
0.00
0.00
0.00 10,125.00
00
50,625.00
100
NO
410.00
0.00
0.00
0.00 410.0000
41,000.00
100
NO
810.00
0.00
0.00
0.00 810.0000
81,000.00
40
NO
1,215.00
0.00
0.00
48,600.00
24
NO
3,240.00
0.00
0.00
0.00 1,215.000
0
12
NO
6,885.00
0.00
0.00
82,620.00
20
NO
1,215.00
0.00
0.00
0.00 6,885.000
0
10 .810 TMHPV01 HP
BD800 Valves(Dia<=6")-
12
NO
2,430.00
0.00
0.00
0.00 2,430.000
0
29,160.00
S K SAHA, DGM(C&M)
0.00 3,240.000
0
77,760.00
0.00 1,215.000
0
24,300.00
PO No. : 4000170293
Sl No. Service
Code
Page No. 52 / 60
Description
Repl
10 .820 TMHPV02 HP
BD800 Valves(Dia>6"-12")Repl
Qty.
UOM
Rate
Premium Discount
Addl
Net
Discount Rate
Value
NO
6,075.00
0.00
0.00
0.00 6,075.000
0
36,450.00
24
NO
1,013.00
0.00
0.00
24,312.00
12
NO
3,645.00
0.00
0.00
0.00 1,013.000
0
10 .850 TMLPV01 LP
BD800 Valves(Dia<=6")Repl
25
NO
1,620.00
0.00
0.00
10 .860 TMLPV02 LP
BD800 Valves(Dia>6"-12")Repl
NO
4,050.00
0.00
NO
3,240.00
SET
25
0.00 3,645.000
0
43,740.00
0.00 1,620.000
0
40,500.00
0.00
0.00 4,050.000
0
20,250.00
0.00
0.00
16,200.00
7,128.00
0.00
0.00
0.00 3,240.000
0
NO
1,420.00
0.00
0.00
35,500.00
20
NO
2,835.00
0.00
0.00
0.00 1,420.000
0
24
NO
2,430.00
0.00
0.00
58,320.00
12
NO
6,480.00
0.00
0.00
0.00 2,430.000
0
12
NO
2,025.00
0.00
0.00
24,300.00
12
NO
5,265.00
0.00
0.00
0.00 2,025.000
0
NO
7,290.00
0.00
0.00
43,740.00
NO
10,125.00
0.00
0.00
0.00 7,290.000
0
24
NO
1,620.00
0.00
0.00
38,880.00
12
NO
3,645.00
0.00
0.00
0.00 1,620.000
0
NO
5,265.00
0.00
0.00
31,590.00
200
NO
410.00
0.00
0.00
0.00 5,265.000
0
25
610.00
0.00
25
2,025.00
200
NO
100
50
S K SAHA, DGM(C&M)
0.00 7,128.000
0
14,256.00
0.00 2,835.000
0
56,700.00
0.00 6,480.000
0
77,760.00
0.00 5,265.000
0
63,180.00
0.00 10,125.00
00
60,750.00
0.00 3,645.000
0
43,740.00
0.00 410.0000
82,000.00
0.00
0.00 610.0000
15,250.00
0.00
0.00
50,625.00
610.00
0.00
0.00
0.00 2,025.000
0
0.00 610.0000
NO
2,025.00
0.00
0.00
NO
4,860.00
0.00
0.00
122,000.00
PO No. : 4000170293
Page No. 53 / 60
Sl No. Service
Code
BD800
Description
(GASKET) Repl
Qty.
UOM
Rate
Premium Discount
Addl
Net
Discount Rate
Value
NO
7,290.00
0.00
0.00
0.00 7,290.000
0
14,580.00
NO
6,893.00
0.00
0.00
13,786.00
NO
14,175.00
0.00
0.00
0.00 6,893.000
0
200
PDY
1,015.00
0.00
30
NO
610.00
365
NO
365
14,175.00
0.00
0.00 14,175.00
00
0.00
0.00
0.00 610.0000
18,300.00
1,215.00
0.00
0.00
UNT
2,025.00
0.00
0.00
50
NO
610.00
0.00
0.00
0.00 610.0000
30,500.00
40
NO
610.00
0.00
0.00
0.00 610.0000
24,400.00
50
OPR
1,015.00
0.00
0.00
50,750.00
70
NO
810.00
0.00
0.00
0.00 1,015.000
0
0.00 810.0000
56,700.00
50
M2
1,015.00
0.00
0.00
50,750.00
50
FRQ
490.00
0.00
0.00
0.00 1,015.000
0
0.00 490.0000
24,500.00
40
PC
810.00
0.00
0.00
0.00 810.0000
32,400.00
40.000
MT
810.00
0.00
0.00
0.00 810.0000
32,400.00
70
NO
610.00
0.00
0.00
0.00 610.0000
42,700.00
70
NO
610.00
0.00
0.00
0.00 610.0000
42,700.00
60
NO
610.00
0.00
0.00
0.00 610.0000
36,600.00
50
NO
1,215.00
0.00
0.00
0.00 1,215.000
0
60,750.00
40
NO
610.00
0.00
0.00
0.00 610.0000
24,400.00
100
NO
610.00
0.00
0.00
0.00 610.0000
61,000.00
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 54 / 60
SCOPE OF WORK
--------------------------------
S K SAHA, DGM(C&M)
PO No. : 4000170293
Page No. 55 / 60
SERVICE SPECIFICATIONS
-----------------------------------------------
S K SAHA, DGM(C&M)
PO No. : 4000170293
10 .220 - TMBBP52BD800 (BFP BP (DE MECH SEAL) Repl)
As Per SOW
10 .230 - TMBBP53BD800 (BFP BP (NDE MECH SEAL) Repl)
As Per SOW
10 .240 - TMBFP56BD800 (BFP (DE MECH SEAL) Repl)
As Per SOW
10 .250 - TMBFP57BD800 (BFP (NDE MECH SEAL) Repl)
As Per SOW
10 .260 - TMBBP05GN402 (BFP BP (BRG) INSPECTION)
As per SOW.
10 .270 - TMBFP03BD799 (BFP (>210-500MW#) RPL-BRG)
As Per SOW
10 .280 - TMBBP03GN152 (BFP BP (>210-500MW#) Decpl/Cpl/Algn)
As Per SOW
10 .290 - TMBFP03GN152 (BFP (>210-500MW#) Decpl/Cpl/Algn)
As Per SOW
10 .300 - TMHCP00GN152 (HYD CPLG (<>) Decpl/Cpl/Algn)
As per SOW.
10 .320 - TMG/B00GN152 (Gear Boxes (<>) Decpl/Cpl/Algn)
As Per SOW
10 .330 - TMG/B00BD800 (Gear Boxes (<>) Repl)
As Per SOW
10 .340 - TMG/B00OH001 (Gear Boxes (<>) OH)
As Per SOW
10 .350 - TMBFT05GN003 (TD BFP Turbine (TURB ROT) ALIGNING)
As Per SOW
10 .360 - TMBFT10BD800 (TD BFP Turbine (RUPTURE DIAPHRAGM) Repl)
As Per SOW
10 .370 - TMBFT08OH000 (TD BFP Turbine (SERVOMOTORS) Serv)
As Per SOW
10 .380 - TMTGS53OH000 (Turbine Gov. Sys (PILOT VV) Serv)
As Per SOW
10 .390 - TMACL51BD800 (ACCUMULATOR (BLADDER) Repl)
As Per SOW
10 .400 - TMACL00GN106 (ACCUMULATOR (<>) Checking)
As Per SOW
10 .410 - TMBFT05GN359 (TD BFP Turbine (TURB ROT) HAND BARRING)
As Per SOW
10 .420 - TMCEN00PM004 (CENTRIFUGE (<>) 04W Chks)
As Per SOW
S K SAHA, DGM(C&M)
Page No. 56 / 60
PO No. : 4000170293
10 .430 - TMCEN00OH000 (CENTRIFUGE (<>) Serv)
As Per SOW
10 .440 - TMCEN51OH001 (CENTRIFUGE (BOOSTERFEED PUMP) OH)
As Per SOW
10 .480 - TMMOT51GN100 (MOT (BASKET STRNR) Cleaning)
As Per SOW
10 .490 - TMMOT52GN100 (MOT (DUPLEX STRNR) Cleaning)
As Per SOW
10 .500 - TMTGS51GN106 (Turbine Gov. Sys (EHC) Checking)
As Per SOW
10 .520 - TMMOT03BD600 (MOT (>210-500MW#) OIL FILLING)
As Per SOW
10 .530 - TMCDP00PM012 (Chem Dosing Pump (<>) 12W Chks)
As Per SOW
10 .540 - TMCDP00OH000 (Chem Dosing Pump (<>) Serv)
As per SOW.
10 .550 - TMLPP01PM012 (LP Water Pump (Dia<=6") 12W Chks)
As Per SOW
10 .560 - TMLPP03PM012 (LP Water Pump (Dia>12") 12W Chks)
As Per SOW
10 .570 - TMLPP03OH001 (LP Water Pump (Dia>12") OH)
As Per SOW
10 .580 - TMLPP01OH001 (LP Water Pump (Dia<=6") OH)
As Per SOW
10 .590 - TMLPP02OH001 (LP Water Pump (Dia>6"-12") OH)
As Per SOW
10 .600 - TMLPP01BD798 (LP Water Pump (Dia<=6") RPL-M-SEAL)
As Per SOW
10 .610 - TMLPP00GN152 (LP Water Pump (<>) Decpl/Cpl/Algn)
As Per SOW
10 .620 - TMCPL01GN402 (COUPLING (100NB) INSPECTION)
As Per SOW
10 .630 - TMLPP55BD800 (LP Water Pump (GLAND) Repl)
As Per SOW
10 .640 - TMVTP00OH001 (VERT PP (<>) OH)
As Per SOW
10 .650 - TMFVV00GN100 (FOOT V/V (<>) Cleaning)
As Per SOW
10 .660 - TMHHH00GN402 (HP Heater-Horz (<>) INSPECTION)
As Per SOW
S K SAHA, DGM(C&M)
Page No. 57 / 60
PO No. : 4000170293
10 .680 - TMCND53GN100 (CONDENSER (HOTWELL) Cleaning)
As Per SOW
10 .690 - TMCND00GN255 (CONDENSER (<>) FLOOD TEST)
As Per SOW
10 .700 - TMCND52GN100 (CONDENSER (WATERBOX) Cleaning)
As Per SOW
10 .710 - TMCND51GN402 (CONDENSER (COLTCS) INSPECTION)
As Per SOW
10 .730 - TMSST04OH000 (STRAINER/FILTER (800NB) Serv)
As Per SOW
10 .750 - TMLPV52BD800 (LP Valves (GLAND) Repl)
As Per SOW
10 .760 - TMHPV51BD800 (HP Valves (GLAND) Repl)
As Per SOW
10 .770 - TMHPV01OH001 (HP Valves (Dia<=6") OH)
O/H of HP Bypass Spray Valve
10 .780 - TMHPV02OH001 (HP Valves (Dia>6"-12") OH)
As per SOW.
10 .790 - TMHPV03OH001 (HP Valves (Dia>12") OH)
As per SOW.
10 .800 - TMHPV13BD800 (HP Valves (50NB) Repl)
As Per SOW
10 .830 - TMLPV01OH000 (LP Valves (Dia<=6") Serv)
As Per SOW
10 .840 - TMLPV02OH000 (LP Valves (Dia>6"-12") Serv)
As per SOW.
10 .870 - TMNRV02OH000 (NRV (DIA 6"-12") Serv)
AS PER SOW
10 .880 - TMNRV03OH001 (NRV (DIA>=12") OH)
O/H OF COLD REHEAT NRV
10 .890 - TMS/V02OH000 (Safety Valve (1-4") Serv)
As Per SOW
10 .900 - TMS/V03OH000 (Safety Valve (4-8") Serv)
As Per SOW
10 .910 - TMC/V01OH000 (CONT VV (<=6") Serv)
As Per SOW
10 .920 - TMC/V02OH000 (CONT VV (6-12") Serv)
As Per SOW
10 .930 - TMBFV01OH000 (BFV (DIA<=6") Serv)
As per SOW.
S K SAHA, DGM(C&M)
Page No. 58 / 60
PO No. : 4000170293
Page No. 59 / 60
PO No. : 4000170293
10 .1130 - TMHPB61BD001 (HPBP Valves (HOSE) ATTEND BREAKDOWN)
As per SOW
10 .1140 - TMMSW00BD000 (Misc Works (<>) Attend Defect)
As Per SOW
10 .1150 - TMMSW00BD600 (Misc Works (<>) OIL FILLING)
As Per SOW
10 .1160 - TMMSW00BD801 (Misc Works (<>) Repair)
As Per SOW
10 .1170 - TMMSW00GN100 (Misc Works (<>) Cleaning)
As Per SOW
10 .1180 - TMMSW00GN106 (Misc Works (<>) Checking)
As Per SOW
10 .1190 - TMMSW00GN120 (MISC WORKS (<>) CUTTING)
As per SOW
10 .1200 - TMMSW00GN250 (Misc Works (<>) Fabrication)
As Per SOW
10 .1210 - TMMSW00GN402 (Misc Works (<>) INSPECTION)
As per SOW
10 .1220 - TMMSW00GN554 (MISC WORKS (<>) LUBRICATION)
As per SOW
10 .1230 - TMSFL02BD000 (SCAFFOLDING (>=500MW) Attend Defect)
As per SOW
10 .1240 - TMMSW00GN800 (MISC WORKS (<>) Remove & Apply)
As per SOW
10 .1250 - TMMSW00GN916 (MISC WORKS (<>) TIGHTENING)
As per SOW
10 .1260 - TMMSW00PM000 (Misc Works (<>) Daily Chks)
As Per SOW
Prepared By:
Sangita Kumari
S K SAHA, DGM(C&M)
Page No. 60 / 60