METHODE PROCEDURE FOR BACKFILLING WORK

CONTENTS
A. PURPOSE
B. SCOPE OF WORK
C. REFERENCE DOCUMENT
D. BACKFILL PROCEDURE
E. EQUIPMENT TO BE USED
F. FLOW CHART PROCEDURE

METHODE PROCEDURE
for FOR BACKFILLING WORK

Rev. no.

:0

Date

: 1 Jun 2015

Doc. No.

: SSP/MP-RTF/004

PROCEDURE FOR BACKFILL


a.

Purpose
The purpose of this procedure is to detail the means and materials that will be
used to perform structural backfilling on the project.

B.

Scope of Work
-

C.

Backfilling
Soil investigation & Density test

Reference Document
The following documents are the reference documents for this work :

D.

PT.RTF PROJECT, CONST SPEC


Civil Technical Specification Document
Issued for Shop Drawings
ASTM D 1556
SNI 03 - 2828 - 1992
AASHTO T 191 - 61

Location and Material


The location and extent of structural backfilling shall be as indicated on the
drawings or defined in the reference documents.
Material to be used for backfilling shall base on drawing.
The Contractor shall perform filling and backfilling work in accordance with
this section and as shown on the approved drawings or as directed by the
Owner.

E.

Sequence of Works
a.

On completion of the foundation or footing, and the inspection of the


same the excavated areas shall be backfilled with the above material in
lifts the thickness of which shall be determined by the type of equipment
to be used for the compaction of the backfill Please refer to the equipment
list below.

b.

Backfilling shall not commence until the request for inspection before
backfilling is completed and any deficiencies corrected. All areas to

Page
2 of 4

METHODE PROCEDURE
for FOR BACKFILLING WORK

Rev. no.

:0

Date

: 1 Jun 2015

Doc. No.

: SSP/MP-RTF/004

receive backfill shall be free of water, debris and organic material and
shall be sufficiently wide to permit the equipment to operate efficiently.
c.

F.

Backfill work shall to be with approved material refer specification to


elevation and lines indicated on drawing. Backfill work will be compacted
layer per layer use vibro roller or stampper with every layer. Material back
filling will be carry from quarry distance of project. The estimation
volume, heavy equipment requirement will be follow construction
drawing.

Density Test
The required density for structural backfilling shall be as follows :
b.
Layer 30 cm from the finished surface shall be compacted to 90% of
maximum dry density according to AASHTO
c.
Field density test (CBR) shall be carried out for 2500 m2 or 50 m x 50 m
of each lift / layer.
d.
If location not properly for CBR Test shall be conform to ASTM D 1556
for sand cone replacement method.

G.

Equipment to be used
The following equipment shall be available for the purpose of compacting
structural fill :
1.
2.
3.
4.
5.

H.

Stampers MIKASA, 4 units


Vibro Roller 12 Ton, 2 units
1 Ton Baby Roller, 2 units
Wheel Barrow
Hand tools for trimming.

Quality Control Reporting


The following items shall be inspected and recorded on the appropriate
inspection form during execution of the work:
a. Sub-grade Preparation Inspection.
b. Fill Material Inspection.
c. Lift Thickness
d. Density Testing Results
e. Final Level.

Page
3 of 4

METHODE PROCEDURE
for FOR BACKFILLING WORK

I.

Flow Chart for Excavation & Backfill Procedure

Rev. no.

:0

Date

: 1 Jun 2015

Doc. No.

: SSP/MP-RTF/004

Page
4 of 4