Professional Documents
Culture Documents
Introduction
Hydropower stands as the green solution to global energy demand. Most of the countries in Asian continent like
Nepal have recently entered into the pool of investment in hydropower sector. In fact hydropower development
requires long construction period, large investment and intense Research and Development. In case of compromise
in any of the variables may result into inefficient power development system. Moreover, here in this paper we are
focused on need of proper design and design analysis of Hydromechanical components whose failure may result into
catastrophic disasters like failure of 9/10 units at Sayano Shushenskaya Power Station, Russia in 2009, penstock
rupture in 2000 at Bieudron Power Station, Switzerland because of inability to resist the internal pressure, Penstock
rupture at Lapino Power Plant, Poland due to mechanical failure under water hammer, etc. (1).
Particularly, there can be many important reasons behind the need and use of bifurcation in the hydropower plant (2)
(3). These reasons are discussed below:
i.
Flow variation
There can be significant amount of flow variation in the water bodies in an Annual Seasonal Cycle [ASC]. Since the
part flow and part load operation of turbine results into efficiency deterioration along with the maintenance issues on
continuous operation in off design condition, a number of units are installed. Hence, instead of operating a turbine in
20% flow with single unit, one of the two units will be closed and more efficiency can be attained.
ii.
Economical perspective of penstock
An alternative for installation of two units without bifurcation is using two penstocks but this doubles the cost of
penstock installation, hence bifurcation is preferred.
iii.
Maintenance perspective
If bifurcation is included in a plant, then cyclic operation of plant on the basis of priority can be done without
completely shutting down the entire system for maintenance activities.
iv.
Geographical perspective
The topography of the area and the gradient in the site may not allow the installation of larger penstock or multiple
penstocks hence a bifurcation would be required to install multiple units.
v.
Technical specifications
Although it is rare but in some cases, the capacity of the turbine and the potentiality of the site may be different in
such case installation of multiple units may be assisted by it. In other cases there may be effect of the size of
penstock or material used in the penstock to select the branching in them.
3.
Daraudi Khola Hydropower Project is a run-of-river type hydropower project developed over Daraudi river situated
in Gorkha district of Western Nepal. This project is currently under construction phase.
Table 1 Specification of Daraudi Khola Project
Specification
Head
Main Flow
Each Flow
Penstock diameter
Length
Description
63.8
11.32
5.66
2.1
298.77 + 16
Unit
m
m3/s
m3/s
m
m
Figure 3 Miller's Plot for Head Loss Coefficient in Symmetric Bifurcation (5)
Geometry development and Computational analysis attempts
The branching sections were only considered during the modeling and the mesh was prepared. Primarily, Mesh
Independent Test with the predefined convergence criteria of 1% on the Design was performed and on that size i.e.
2,018,417 nodes, rest of the analysis was done. An important consideration during the analysis should be maintained
during the selection of the length for computational analysis to obtain steady developed flow.
After the predetermination of the size of computational model, mesh on the geometry of each angle from 45 o to 70o
was performed to determine the point of minimum head loss with the domain definition, boundary conditions and
solver parameters defined in Table 2. (7)
Table 2 Boundary conditions and fluid features for CFD analysis
Fluid
Density
Morphology
Domain motion
Turbulence Model
Inlet
Pressure
Outlet1
Mass flow rate
Outlet2
Mass flow rate
Mass & Momentum
Wall roughness
Analysis type
Min Iteration
Max Iteration
Domain Definition
Water
1000 kg /m3
Continuous fluid
Stationary
Shear Stress Transport
Boundary Conditions
624000.366 Pa
5682.9 kg/sec
5682.9 kg/sec
Wall Features
No slip wall
Smooth wall
Steady State Analysis
Convergence control
1
200
Convergence Criteria
RMS
10e-5
Residual type
Residual target
The head loss was determined by the Equation 1and described graphically as in the Figure 2.
=
[Equation 1]
51 53 55 57
59 61 63
65 67 69
Figure 6 Pressure distributin in the central plane and the point of maximum pressure
5. Mechanical Design of Bifurcation
5.1. Identification of basic mechanical features
The backgrounds like material properties and fluid properties are identified prior to the analysis. The Indian
Standard guide lines for the selection of the material, its allowable stress and corrosion allowance has been
allocated. Table 3 shows the background for the analysis.
Description
ID
Angle
Design Head
Flow
Units
Max. Static Head
Max. Surge Head
Total Head
Buried Pressure [8 m buried]
Mild steel of the standard
Density
Youngs Modulus
Poissons Ratio
Ultimate Tensile Strength
Yield Strength
allowable
Hydraulic Parameters
Internal Pressure
External Pressure
Material Properties
[IS Standard]
Allowable Stress
(8)
Thickness
IS code 2825:
(Clause 3.2.2)
1969
2100 mm
51o
63.8 m
11.32 m3/s
2
63.8 m
26.2 m
90 m
435.8465 N/mm
MS IS-2062
7850 kg/m3
210 GPa
0.3
410 MPa
250 MPa
102.5 MPa
18.03 mm
1.5 mm
20 mm
A penstock wye or branch connection usually has several stiffening beams to resist the loads applied by the shell of
the pipe. The method incorporated rib shortening, shear deformation of the stiffener beams, and variable flange
width. Although valid, this systematic design process is not efficient considering available modern computing
methods. However, a spreadsheet can be used to drastically cut down the time involved with this design method.
To analyze the wye and branch connections using beams, many simplifications and approximations are used (10).
The localized effect of structural discontinuities, restraints of the stiffening beams, foundation support, and dead
load of the water filled pipe are neglected. End load effects and conicity of the outlet pipes are also neglected and
considered to be small in comparison to the vertical load on the beams. Here a finite certain sections are considered
and computation is prepared based on this approach. This analysis also includes this approach of approximation.
The prime design processes include the deflection of the members AO and BO at point O is equal from figure 5.
This computation was performed considering the uniformly distributed load on symmetric section as shown in figure
6.
The finite element analysis design method provides a more complete representation of the penstock shell stiffener
system. It is becoming the standard design tool for penstock wye design in the hydropower industry (2) (3). The
main aim in this analysis will be fulfilled by this method. Where the detail analysis will be explained and performed
based on this process.
The minimum shell thickness was determined using the analytical methodology for pre-setting the computational
limit. based upon which 3D CAD was developed to perform the unstiffened structural analysis for locating the
critical locations with maximum stress and deflection.
The primary dimensions are then modified to counter act on the resultant deflections and stresses. The result was
obtained with iterative computation of the stiffer and girdle rings. The main constraint for the selection of the size of
the support is the site consideration.
Figure 7 shows the result of the finite element analysis. After an iterative computation for the sizes, 20 mm thickness
at the point of division, 26 mm girdle thickness and 16 mm pipe thickness in the branched segments has been
identified. Both the manufacturability and the performance were considered during the analysis.
6.
Conclusion
The paper discusses over the design of bifurcation for a hydropower plant. The hydraulic design of the bifurcation
was performed considering the standard design guidelines and further computational analysis regarding selection of
angle.
This selected angle was applied with mechanical features and iterative analysis for thickness of pipe and stiffeners
was performed. All the analysis was focused on developing optimum geometry of the bifurcation with minimum
head losses for reliability.
Based upon this design experience, it can be seen that the hydraulic and mechanical structures are either operating in
risk or in high safety factor. A proper engineered structure should be hydraulically, structurally and economically
optimum for sustainability of the plant and it is the recommendation to uplift the existing standard with modern days
design and developmental tools.
7.
Bibliography
1. Case Study: Lapino Power Plant Penstock Failure . Adamkowski, A. 2001, Journal of Hydraulic Engineering ,
Vol. 7, pp. 547 - 555.
2. Bambei, John H. Steel Penstocks, Second Edition. s.l. : ASCE Publications, 2012.
3. Staff, AWWA. Steel Pipe: A Guide for Design and Installation, 4th Edition. s.l. : American Water Works
Association .
4. Divatia, E, Chelvaraj, A.S. and Murthy, G.N. Manual on Design Fabrication Erection and Maintenance of Steel.
New Delhi : Central Water Commission, 1974.