Professional Documents
Culture Documents
Tender Document
VOLUME-II
(Part-A) General Conditions of Contract
(Part-B) Special Conditions of Contract
January-2005
Volume-II (PART A)
GENERAL CONDITIONS OF CONTRACT
CONTENTS
CLAUSE
NO
PARTICULARS
REMARKS
1. GENERAL PROVISIONS
1.1
Definitions
Modified
1.1.2.11
Engineer-in-Charge
Inducted
1.1.2.12
Tenderer / Bidder
Inducted
1.1.3.3
Time for Completion
Modified
1.1.4.6
Provisional Sum
Deleted
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
1.13
1.14
Interpretation
Modified
Communications
Modified
Law and Language
Modified
Priority of Documents
Modified
Contract Agreement
Modified
Assignment
Care and Supply of Documents
Confidentiality
Employers Use of Contractors Documents
Contractors Use of Contractors Documents
Confidential Details
Modified
Compliance with Laws
Modified
Joint and Several Liability
2. THE EMPLOYER
2.1
2.2
2.3
2.4
2.5
3.
3.1
3.2
3.3
3.4
3.5
4.
Deleted
Employers Claims
THE EMPLOYERS ADMINISTRATION
The
Employers
Modified
Other Employers Personnel
Delegation Persons
Instructions
Determinations
Representative
PAGE NO
CLAUSE PARTICULARS
NO
THE CONTRACTOR
4.1
4.2
4.3
4.4
Contractors
Modified
Performance Security
Modified
Contractors Representative
Subcontractors
Modified
Nominated Subcontractors
Co-operation
Setting Out
4.5
4.6
4.7
Modified
4.8
Safety Procedures
4.9
Quality Assurance
4.10
Site Data
Modified
4.11
Sufficiency of the Contract Price
4.12
Unforeseeable Difficulties
4.13
Rights of Way and Facilities
4.14
Avoidance of Interference
4.15
Access Route
Modified
4.16
Transport of Goods
4.17
Contractors Equipment
Modified
4.18
Protection of the Environment
Modified
4.19
Electricity, Water and Gas
Modified
4.20
Deleted
4.21
Progress Reports
4.22
Security of the Site
4.23
Contractors Operations on Site
4.24
Fossils
General
Obligations
5.
CLAUSE PARTICULARS
NO
DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
Manner of Execution
Samples
Inspection
Modified
Testing
Rejection
Remedial Work
Ownership of Plant and Materials
Royalties
Commencement of Work
Modified
Time For Completion
Modified
Programme
Modified
Extension of Time For Completion
Modified
PAGE NO
8.5 CLAUSE
PAGE NO
PARTICULARS
NO
8.6
8.7
8.8
Rate of Progress
Delay Damages
Modified
Suspension of Work
Modified
Deleted
8.9
8.10
8.11
8.12
Deleted
Deleted
Deleted
Deleted
9. TESTS ON COMPLETION
9.1
9.2
9.3
9.4
Contractors Obligations
Delayed Tests
Retesting
Failure to Pass Tests on Completion
Modified
10.
Modified
10.1
Taking Over of the Works and Sections
Modified
10.2
Taking Over of Parts of the Works
Modified
10.3
Deleted
11.
11.1
11.2
11.3
11.4
11.5
11.6
11.7
11.8
11.9
11.10
11.11
12.
12.1
12.2
12.3
DEFECTS LIABILITY
Completion of Outstanding Work and Remedying Defects
Modified
Cost of Remedying Defects
Failure to Remedy Defect
Removal of Defective Work
Further Tests
Right of Access
Deleted
Performance Certificate
Unfulfilled Obligations
Clearance of Site.
TESTS AFTER COMPLETION
Procedure for Tests after Completion
Modified
Deleted
Retesting
Deleted
12.4
13.
13.1
13.2
13.3
13.4
13.5
13.6
13.7
13.8
14.
14.1
14.2
14.3
14.4
14.5
14.6
14.7
14.8
14.9
14.10
14.11
14.12
14.13
14.14
14.15
14.16
15.
15.1
15.2
15.3
15.4
15.5
Deleted
Deleted
Adjustment for Charges in Legislation
Adjustments for Charges in Cost
CONTRACT PRICE AND PAYMENT
The Contract Price
Modified
Advance Payment
Modified
Application for Interim Payments
Modified
Schedule of Payments
Modified
Interim Payments
Modified
Timing of Payments
Modified
Delayed Payment
Deleted
Payment of Retention Money
Modified
Statement at Completion
Modified
Application for Final Payment
Modified
Discharge
Modified
Final Payment
Cessation of Employers Liability
Currencies of Payment
Modified
Price Adjustment
TERMINATION BY EMPLOYER
Notice to Correct
Termination by Employer
Valuation at Date of Termination
Payment after Termination
Employers Entitlement to Termination
Deleted
Modified
PAGE NO
CLAUSE PARTICULARS
NO
16.
Deleted
Indemnities
Contractors Care of the Works
Intellectual and Industrial Property Rights
Limitation of Liability
INSURANCE
General Requirements for Insurances
Modified
Insurance for Works and Contractors Equipment
Modified
Insurance against Injury to Persons and Damages to Property
Modified
Insurance for Contractors Personnel
Modified
General Requirements for Insurance
Inducted
FORCE MAJEURE
Definition for Force Majeure
Modified
Notice of Force Majeure
Modified
Duty to Minimise Delay
Consequences of Force Majeure
Modified
Deleted
Optional Termination, Payment and Release
Modified
Release from Performance under the Law
20.
20.1
20.2
Contractors Claims
Appointment of the Dispute Adjudication Board
Modified
Failure to Agree Dispute Adjudication Board
Modified
20.3
Deleted
Deleted
20.4
20.5
20.6
20.7
20.8
20.9
APPENDIX TO TENDER
ANNEXURE GCCI PROFORMA FOR PERFORMANCE SECURITY
ANNEXURE GCCII
GUARANTEE
VOLUME II
PART A
GENERAL CONDITIONS OF CONTRACT
PREFACE
The General conditions governing this contract shall be as stated in the Conditions of Contract for EPC
Turnkey Projects ( 1999 Edition ) Published by Federation International des Ingenieurs - Conseils (FIDIC)
designated. Some of the clauses in the Conditions of Contract for EPC Turnkey Projects ( 1999 Edition )
Published by Federation International does Ingenieurs - Conseils (FIDIC) are modified/amended/deleted as
indicated in the Contents. There are a few additional Sub-Clauses also. However, the bidder(s) should
carefully study all the clauses for comparison with the Conditions of Contract for EPC Turnkey Projects
( 1999 Edition ) Published by Federation International does Ingenieurs - Conseils (FIDIC)
VOLUME- II
(PART A)
General provision
1.1
Definitions
1.1.1
The Contract
1.1.1.1
Contract means the Contract Agreement, these Conditions, the
Employers Requirements, the Tender, and the further documents (if
any) which are listed in the Contract Agreement.
1.1.1.2
1.1.1.3
Tender means the Contractors signed offer for the Works and all
other documents which the Contractor submitted therewith (other
than these Conditions and the Employers Requirements, if so
submitted), as included in the Contract.
1.1.1.5
1.1.2
Parties And Persons
1.1.2.1
1.1.2.2
1.1.2.3
1.1.2.4
1.1.2.5
1.1.2.6
1.1.2.7
1.1.2.8
1.1.2.9
1.1.2.10
1.1.2.11
Engineer-in-charge
means
the
Executive
H.N.S.S.DIVISION
II,ANANTAPUR
to
whom
the
Representative may have delegated certain duties.
1.1.2.12
Engineer,
Employers
1.1.3
Dated, Test, Periods
and Completion
1.1.3.1
Base Date means the date 28 days prior to the latest date for
submission of the Tender.
1.1.3.2
1.1.3.3
1.1.3.4
1.1.3.5
1.1.3.6
Tests after completion means the test (if any) which are
specified in the Contract and which are carried out under Clause 12
[Tests after completion] after the Works or a Section (as the case may
be) are taken over by the Employer.
1.1.3.7
1.1.3.8
Performance certificate means the certificate issued under SubClause 11.9 [Performance Certificate]
1.1.3.9
1.1.4
1.1.4.2
1.1.4.3
1.1.4.4
(Deleted)
1.1.4.5
1.1.4.6
(Deleted)
1.1.4.7
1.1.4.8
1.1.5
Works and Goods
1.1.5.1
1.1.5.2
1.1.5.3
1.1.5.4
Plant
and
1.1.5.5
1.1.5.6
Section means five Sections I, II, III, IV and V of EPC part of the
Contract and Section VI of Operation and Maintenance part of the
contract.
1.1.5.7
1.1.5.8
1.1.6
Other Definitions
1.1.6.1
1.1.6.2
1.1.6.3
1.1.6.4
1.1.6.5
1.1.6.6
1.1.6.7
1.1.6.8
1.2
Interpretation
1.2.1
1.2.3
1.2.4
1.2.5
1.2.6
1.2.7
1.3
Communications
All communications during execution of the Contract shall be made at the
following address:
Superintending Engineer, I&CAD Deptt.,
H.N.S.S.CIRCLE,ANANTAPUR,, Andhra Pradesh,
India
PIN 515 004,
Tel : 08554-240237.
1.4.2
1.4.3
1.4.4
1.4.4.
1
1.4.4.
2
1.5
Priority of Documents
The documents forming the Contract are to be taken as
mutually explanatory of one another. For the purposes of interpretation,
the priority of the documents shall be in accordance with following
sequence:
a)
b)
c)
d)
e)
f)
g)
1.6
Contract Agreement
The Contractor shall execute formal Contract agreement on
appropriate value of stamp paper imposed by Law in connection
with entry into Contract Agreement within 15 days from the
date of Letter of Award.
The following documents shall be deemed to form and be read
and construed as part of Contract Agreement
1.8
Care and Supply
of Documents.
1.9
Confidentiality
c)
1.13
Compliance with Laws
The Contractor shall, in performing the Contract, comply with
applicable Laws.
a) the Employer shall have obtained (or shall obtain) the
planning, zoning or similar permission for the Permanent
Works as having been (or being) obtained by the Employer;
and the Employer shall indemnify and hold the Contractor
harmless against and from the consequences of any failure
to do so; and
b) the Contractor shall give all notices, pay all taxes, duties
and fees, and obtain all permits, licenses and approvals, as
required by the laws in relation to the design, execution and
completion of the Works and the remedying of any defects
and the Contractors shall indemnify and hold the Employer
harmless against and from the consequences of any failure
to do so.
1.14
Joint and Several Liability
If the Contractor constitutes (under applicable Laws) a joint
venture, consortium or other unincorporated grouping of two or
more persons;
a)
b)
c)
2.
The Employer
2.1
Right of Access to the Site
2.1.1
The Employer shall provide whole / part of the land already available with
the Employer or "as is where is basis" within 15 (fifteen) days from the
Letter of Award without cost to the Contractor.
The Contractor shall have right to use such land for the purpose of the
Contract and shall have unrestricted access to such land.
Within 30 (thirty) days of the date of signing of the Contract agreement,
the Contractor's shall submit for the Employer's approval the Contractors
phased requirement of additional land (if any).
2.1.2
2.2
The Contractor will do all further works in respect of internal project roads
and other infrastructure facilities and also its maintenance during the
currency of the construction period. The necessary cost in respect to
these works is deemed to have been included within the Contract Price.
co-operate with the Contractors efforts under SubClause 4.6 [Co-operation], and
Take actions similar to those which the Contractor is
required to take under sub-paragraphs a), b) and c) of
Sub-Clause 4.8 [Safety procedures] and under SubClause 4.18 [Protection of the Environment].
2.4
(Deleted)
2.5
Employers Claims
If the Employer considers himself to be entitled to any payment
under any Clause of these conditions or otherwise in connection with the
Contract, and/or to any extension of the defection notification period, he
shall give notice particulars to the Contractor. However, notice is not
required for payments due under Sub-Clause 4.19 (electricity, water and
Gas), under Sub-Clause 4.20 [Employers equipment and free issue
material], or for other service requested by the contractors.
The notice shall be given as soon as practicable after the
Employer became aware of the event or circumstances giving rise to the
claim. A notice relating to any extension of the Defects Liability Period shall
be given before the expiry of such period.
The particulars shall specify the Clause or other basis of the
claim, and shall include substantiation of the amount and/or extension to
which the Employer considers him to be entitled in connection with the
Contract. The Employer shall then proceed in accordance with Sub-Clause
3.5 [Determinations] to agree or determine (i) the amount (if any) which the
Employer is entitled to be paid by the Contractor, and/or (ii) the extension (if
any of the Defects Liability Period in accordance with Sub-Clause 11.3
[Extension of Defects Liability Period].
The Employer may deduct this amount from any moneys due,
or to become due, to the Contractor. The Employer shall only be entitled to
set off against or make any deduction from an amount due to the Contractor,
or to otherwise claim against the Contractor, in accordance with this SubClause or with sub paragraph a) and/or b) of Sub-Clause 14.6 [Interim
Payments].
3.
3.1
The Employers Representative
The Superintending Engineer, H.N.S.S.CIRCLE,ANANTAPUR is the
employers representative.
3.2
Other Employers Personnel
The
concerned
Executive
Engineers
of
H.N.S.S.CIRCLE,ANANTAPURare otherEmployers persons and incharge
Engineers to the works of their jurisdiction (Engineer-in-Charge) as per work
distributed by the Superintending Engineer, H.N.S.S.CIRCLE,ANANTAPUR.
The Engineer-in-Charge shall be suitably qualified person, who
are competent to carry out these duties and exercise this authority, and who
are fluent in the language for communication defined in Sub-Clause 1.4 [Law
and Language]
3.3
Delegated Persons
All these persons, including the Employers Representative and
assistants, to whom duties have been assigned or authority has been
delegated, shall only be authorised to issue instructions to the Contractor to
the extent defined by the delegation. Any approval, check, certificate,
consent, examination, inspection, instruction, notice, proposal, request, test,
or similar act by a delegated person, in accordance with the delegation, shall
have the same effect as though the act had been an act of the Employer.
However:
a) unless otherwise stated in the delegated persons communication
relating to such act, it shall not relieve the Contractor from any
responsibility he has under the Contract, including responsibility for
errors, omissions, discrepancies and non- compliances;
b)
any failure to disapprove any work, Plant or Materials shall not
constitute approval, and shall therefore not prejudice the right of the
Employer to reject the work, Plant or Materials; and
c) if the Contractor questions any determination or instruction of a
delegated person, the Contractor may refer the matter to the
Employer through the Employers Representative, who shall promptly
confirm, reverse or vary the determination or instruction.
3.4
Instructions
The Employer representative may issue to the Contractor instructions which
may be necessary for the Contractor to perform his obligations under the
Contract. Each instruction shall be given in writing and shall state the
obligations to which it relates and the Sub-Clause (or other term of the
4.
The Contractor
4.1
Contractors General Obligations
4.4.1
4.1.2
The contractor shall take full responsibility for the adequate stability and
safety for all its operations including site operations and methods of
construction and providing / arranging adequate security for all its and its
sub-contractors' personnel and their families, property either owned by it
or held by it in trust, work-in-progress and installation responsibilities etc.
in the project area.
If the Contractor or his sub-Contractor or their employees break, deface or
destroy any property belonging to the Employer or others during the
execution of the Contract, the same shall be made good by the Contractor
at his own expense and in default thereof, the Employers Representative
may cause the same to be made good by other agencies and recover
expenses from the Contractor for which the certificate of expenses from
the Employers Representative shall be final.
4.1.3
4.1.5
4.1.6
The Contractor shall be responsible for all arrangements for gas including
for all his work sites and colonies / camps.
4.1.7
4.1.8
4.1.9
The Site shall be handed over to the Contractor along with existing
infrastructure on "as is where is" basis. The Contractor shall be responsible
for up keeping and maintaining of all the infrastructure taken over by him.
4.2
Performance Security
4.2.1
4.2.3
4.3
Contractors
Representative
the
No part of the Contract sub-let by the Contractor directly or indirectly to any firm
or company without the prior consent the writing of the Employer for which the
Contractor shall give a written request to the Employer at least 15 (fifteen) days
in advance of the proposed day of sub-contacting (if any) which shall contain:
a) Contractors certification regarding the financial soundness of the
proposed sub-contractor for the work;
b) Its scope and estimated value in relation to the Contract Price;
c) Experience of the sub-contractor, in the related areas of work;
d) The manpower, equipment, material and other resources available with
the sub-contractor for the work;
Within four weeks of the date of the receipt of request for consent pursuant to
this Clause
4.4.1, the Employer shall either give in writing consent thereof or communicate
its refusal with reasons. In the event of the Employer failing to communicate its
refusal within the above said four weeks period, the Contractor shall be entitled to
proceed as if the Employer had granted consent to such request.
4.4.2 Notwithstanding the provisions contained in Clause 4.4.1 above the consent of
the Employer shall not be required in respect of the following transfer,
assignment, sub-contracting:
(a) any charge in favour of the Contractors bankers of the moneys due under the
Contract or the subrogation of insurers to the Contractors rights to receive
payments due under the Contract.
(b) sub-contracts for the supply of constructions materials such as steel and
cement and consumables such as explosives, oil and petroleum products
procured within India;
(c) sub-contracts with sub-contractors and suppliers named in the Contract;
(d) sub-contracts for Construction Equipment and Temporary Works;
(e) sub-contracts for clearance and/or transportation.
4.4.3
4.4.4
to the Employer for the quality, proper and expeditious execution and
performance of the Works and for due performance and observance of all the
conditions of the Contract in all respects, as if such transfer has not taken place
and as if the work so transferred has been done directly by the Contractor.
4.4.5
If any such sub-contractor engaged upon the Works, executes any work, which in
the opinion of the Employers Representative is not in accordance with the
Contract, the Employer may by written notice to the Contractor request him to
terminate such sub-contract and the Contractor upon the receipt of such notice
shall terminate such sub-contract and dismiss such sub-contractor and the later
shall forthwith leave the work failing which the Employer shall have the right to
remove such sub-contractor from the site. In such cases no liability whatsoever
will be attached to the Employer, nor will the Employer bear the cost of such subcontract.
4.4.6
Any action taken by the Employer under this sub-clause shall not relieve in any
manner whatsoever the Contractor of any of his liabilities and obligations under
the Contract including Time for Completion or give rise to any right to
compensation / extension of time or otherwise
4.5
Nominated
Subcontractors
4.6
Cooperation
The Contractor shall, as specified in the Contract or as
instructed by the Employer, allow appropriate opportunities for carrying
out work to:
a)
b)
c)
4.8
Safety Procedures
e)
4.9
Quality Assurance
4.11
Sufficiency of
the Contract Price
The Contractor shall be deemed to have satisfied himself as to
the correctness and sufficiency of the Contract Price.
Unless otherwise stated in the Contract, the Contract price
covers all the Contractors obligations under the Contract
(including those under provisional sums, if any) and all things
necessary for the proper design, execution and completion of
the Works and the remedying of any defects.
4.12
Unforeseeable
Difficulties
Except as other stated in the Contract:
a)
b)
c)
4.13
Rights of Way
and Facilities
The Contractor shall bear all costs and charges for special
and/or temporary rights-of-way which he may require, including
those for access to the Site. The Contractor shall also obtain, at
his risk and cost, any additional facilities outside the Site which
he may require for the purposes of the Works.
4.14
Avoidance of
Interference
The Contractor shall not interfere unnecessarily or improperly
with:
a)
b)
4.15
Access Route
c)
the
Contractor shall (as between the Parties) be
responsible for any maintenance which may be required
for his use of access routes;
the Contractor shall provide all necessary signs or
directions along access routes, and shall obtain any
permission which may be required from the relevant
authorities for his use of routes, signs and directions;
the Employer shall not be responsible for any claims
which may arise from the use or otherwise of any access
route,
d)
e)
4.17
Contractors
Equipment
Plant, etc.,
Exclusive Use for
the Works
Removal of Plant,
etc.
3) The Employer shall not at any time be liable for the loss of or
damage to any of the said Constructional Plant, Temporary Works or
materials .
Re-export of Plant
Customs Clearance
4.19
Electricity, Water
and Gas
Deleted
(b)
(c)
commencement of manufacture,
Contractors inspections,
tests, and
shipment and arrival at the Site;
(d)
4.22
Security of the Site
(a)
(b)
for
keeping
4.23
Contractor's Operations
on Site
The Contractor shall confine his operations to the Site, and to
any additional areas which may be obtained by the Contractor
and agreed by the Employer as working areas. The Contractor
shall take all necessary precautions to keep Contractor's
Equipment and Contractor's Personnel within the Site and these
additional areas, and to keep them off adjacent land.
During the execution of the Works, the Contractor shall keep the
Site free from all unnecessary obstruction, and shall store or
dispose of any Contractor's Equipment or surplus materials. The
Contractor shall clear away and remove from the Site any
wreckage, rubbish and Temporary Works, which are no longer,
required.
Upon the issue of the Taking-Over Certificate for the Works, the
Contractor shall clear away and remove all Contractors
Equipment, surplus material, wreckage, rubbish and Temporary
Works. The Contractor shall leave the Site and the Works in a
clean and safe condition. However, the Contractor may retain
on Site, during the Defects Liability Period, such Goods as are
required for the Contractor to fulfill obligations under the
Contract.
4.24
Fossils
All fossils, coins, articles of value or antiquity, and structures
and other remains or items of geological or archaeological
interest found on the Site shall be placed under the care and
authority of the Employer. The Contractor shall take reasonable
precautions to prevent Contractor's Personnel or other persons
from removing or damaging any of these findings.
The Contractor shall, upon discovery of any such finding,
promptly give notice to the Employer, who shall issue
instructions for dealing with it. If the Contractor suffers delay
and/or incurs Cost from complying with the instructions, the
Contractor shall give a further notice to the Employer and shall
be entitled subject to Sub-Clause.20.1 [Contractor's Claims] to:
(a)
(b)
5.
Design
5.1
General Design
Obligations
The Contractor shall be deemed to have scrutinized, prior to the
Base Date, the Employer's Requirements (including design
criteria and calculations, if any). The Contractor shall be
responsible for the design of the Works and for the accuracy of
such Employer's Requirements (including design criteria and
calculations), except as stated below.
(b)
(c)
(d)
5.4.
Technical Standards and Regulations
The design, the Contractors Documents, the execution and the
completed work shall comply with the Country's technical
standards, building, construction and environmental Laws, Laws
applicable to the product being produced from the Works, and
other standards specified
in the Employer's Requirements, applicable to the Works, or
defined by the applicable Laws.
All these Laws shall, in respect of the Works and each Section,
be those prevailing when the Works or Section are taken over
by the Employer under Clause 10 [Employer's Taking Over].
References in the Contract to published standards shall be
understood to be references to the edition applicable on the
Base Date, unless stated otherwise.
5.7
Operation and
6.1
Engagement of Staff
and Labour
Except as otherwise stated in the Employer's Requirements, the
Contractor shall make arrangements for the engagement of all
staff and labour, local or otherwise, and for their payment,
housing, feeding and transport.
6.2
Rates of Wages and
conditions of labour
The Contractor shall pay rates of wages, and observe,
conditions of labour which are not lower than those established
for the trade or industry where the work is carried out. If no
established rates or conditions are applicable, the Contractor
shall pay rates of wages and observe conditions which are not
lower than the general level of wages and conditions observed
locally by employers whose trade or industry is similar to that of
the Contractor
6.3
Persons in the Service of Others
The Contractor shall not recruit, or attempt to recruit, staff and
labour from amongst he Employers Personnel.
6.4
Labour Laws
The Contractor shall comply with all the relevant labour Laws
applicable to the Contractor's Personnel, including Laws relating
to their employment, health, safety, welfare, immigration and
emigration, and shall allow them all their legal rights.
6.8
Contractor's Superintendence
Throughout the design and execution of the Works, and as long
thereafter as is necessary to fulfill the Contractor's obligations,
the Contractor shall provide all necessary superintendence to
plan, arrange, direct, manage, inspect and test the work.
Superintendence shall be given by a sufficient number of
persons having adequate knowledge of the language for
communications (defined in Sub-Clause 1.4 [Law and Language]
and of the operations to be carried out (including the methods
and techniques required, the hazards likely to be encountered
and methods of preventing accidents), for the satisfactory and
safe execution of the Works.
6.9
Contractor's Personnel
The Contractor shall provide and employ on the site in
connection with the execution of the works and performance of
its obligations under the Contract:
(a) Only such technical personnel as are skilled and
experienced in their respective callings and such subagents, foremen and leading hands as are competent to do
or give proper supervision to the work they are required to
perform or supervise, and
(b) Such skilled, semi-skilled and unskilled labour as is
necessary for the proper and timely execution of the works.
The Employer may require the Contractor to remove (or cause
to be removed) any person employed on the Site or Works,
including the Contractor's Representative if applicable, who:
(a)
(b)
(c)
(d)
Discorderly Conduct
The Contractor shall at all times take all reasonable precautions
to prevent any unlawful, riotous or disorderly conduct by or
amongst the Contractors Personnel, and to preserve peace and
protection of persons and property on and near the Site.
7.
7.1
Manner of Execution
The Contractor shall carry out the manufacture of Plant, the
production and manufacture of Materials, and all other
execution of the Works:
(b)
(c)
(d)
7.2
Samples
The Contractor shall submit samples to the Employer for review
in accordance with the procedures for Contractor's Documents
described in Sub-Clause 5.2 [Contractor's Documents], as
specified in the Contract and at the Contractor's cost. Each
sample shall be labeled as to origin and intended use in the
Works.
7.3
Inspection
7.5
Rejection
7.6
Remedial Work
7.7
Employer ship of
Plant and Materials
Each item of Plant and Materials shall, to the extent consistent
with the Laws of the Country, become the property of the
Employer at whichever is the earlier of the following times, free
from liens and other encumbrances:
(a)
(b)
7.8
Royalties
Unless otherwise stated in the Employer's Requirements, the
Contractor shall pay all royalties, rents and other payments for:
(a)
(b)
8.
8.1
Commencement of Works
The Contractor shall commence the Design Engineering and
Infrastructure works within 15 days (fifteen) days from the date
of issue of Letter of Award (LOA). Execution of Civil Works shall
come into effect subsequent to when each and all of the
following conditions have been fulfilled, which shall be subject
to a maximum time limit of 15 (fifteen) days from the date of
issue of LOA.
(a) Signing of the Contract Agreement and Credit Agreements
(if any);
(b) Delivery to the Employer of the Performance Security
pursuant to Sub-Clause 4.2 hereof;
8.2
Time for Completion
8.2.1
8.2.2
The Contractor shall complete the whole of the works and each
section (if any) within the time for completion for the works or section
(as the case may be) including:
(a) Achieving the passing of the Tests on Completion and
(b) Completing all works which are stated in the Contract as being
required for the Works or Sections to be considered to be
completed for the purposes of issue of completion certificate
covering part A of the contract in accordance with Sub-Clause
10.1 [Taking Over of the Works and Sections].
8.2.3
For the purpose of Sub-Clause 8.2.3, 8.4 and 10.2 hereof "Works"
shall have the same meaning as defined in Sub-Clause 4.4 and shall
include all the Permanent and Temporary Works to be executed, all
items and things to be supplied / done and all services and activities
to be performed such as the planning, design and engineering
8.3.2
8.3.3
8.3.4
8.4
Extension of
Time for Completion
8.4.1
Time allowed for execution of the works as specified in SubClause 8.2.3 is the essence of the Contract.
8.4.2
8.5
(Deleted)
8.6
Rate of Progress
If, at any time:
(a)
(b)
(Deleted)
8.10
(Deleted)
8.11
(Deleted)
8.12
(Deleted)
9.
Tests on Completion
9.1
Contractors
Obligations
(b)
(c)
Delayed Tests
If the Tests on Completion are being unduly delayed by the
Contractor, the Employer may by notice require the Contractor
to carry out the Tests within 21 days after receiving the notice.
The Contractor shall carry out the Tests on such day or days
within that period as the Contractor may fix and of which he
shall give notice to the Employer
If the Contractor fails to carry out the Tests on Completion
within the period of 21 days, the Employers Personnel may
proceed with the Tests at the risk and cost of the Contractor.
These Tests on Completion shall then be deemed to have been
carried out in the presence of the Contractor and the results of
the Tests shall be accepted as accurate.
9.3
Retesting
If the Works, or a Section, fail to pass the Tests on Completion,
Sub-Clause 7.5 [Rejection] shall apply, and the Employer or the
Contractor may require the failed Tests, and Tests on
Completion on any related work, to be repeated under the same
terms and conditions.
9.4
Failure to Pass
Tests on Completion
If the Works, or a Section, fail to pass the Tests on Completion
repeated under Sub-Clause 9.3 [Retesting], the Employer shall
be entitled to:
(a)
(b)
(c)
10.
10.1
Taking Over of the
Works and Sections
Except as stated in Sub-Clause 9.4 [Failure to Pass Tests on
Completion], the total Works covering part A of the contract
comprising Sections I, II, III, IV and V shall be initially certified to
be complete by the Employer when (i) the Works have been
completed in accordance with the Contract, including the
matters described in Sub-Clause 8.2 [Time for Completion] and
except as allowed in sub-paragraph (a) below, and (ii) a
completion Certificate for the Works has been issued, or is
deemed to have been issued in accordance with this SubClause.
The Contractor may apply by notice to the Employer for a
completion Certificate not earlier than 14 days before the
Works will, in the Contractor's opinion, be complete and ready
for operation.
The Employer shall, within 28 days after receiving the
Contractor's application:
(a) Issue the completion certificate to the Contractor stating
the date on which the total works of part A comprising
Sections I, II, III, IV and V were completed in accordance
with the Contact; or
(b)
The Contractor shall be handed over the project along with all
its components including Intake pump house, intermediate and
booster pump houses, pipeline and allied works immediately
after issue of completion certificate for part A (EPC Part)
comprising Sections I, II, III, IV and V and the Contractor would
Operate and Maintain the project for a period of 2(two) years in
accordance with Employers Requirements. After completion of
the operation and maintenance period of 2(two) years, takingover certificate will be issued in accordance with the provision
in the Contract.
10.2
Taking Over of Parts of the Works
11.
(Deleted)
Defects Liability
11.1
Completion of Outstanding Work
and Remedying Defects
Defect liability period shall be two years from the date of issue
of completion certificate in accordance with Sub-clause 10.1.
In order that the Works and Contractors Documents, and each
Section, shall be in the condition required by the Contract (fair
wear and tear excepted) by the expiry date of the relevant
Defects Liability Period or as soon as practicable thereafter, the
Contractor shall:
(a)
(b)
(d)
11.3
(Deleted)
11.4
Failure to Remedy
Defects
(b)
(c)
11.5
Removal of Defective Work
If the defect or damage cannot be remedied expeditiously on
the Site and the Employer gives consent, the Contractor may
remove from the Site for the purposes of repair such items of
Plant as are defective or damaged. This consent may require
the Contractor to increase the amount of the Performance
Security by the full replacement cost of these items, or to
provide other appropriate security.
11.6
Further Tests
If the work of remedying of any defect or damage may affect
the performance of the Works, the Employer may require the
repetition of any of the tests described in the Contract,
including Tests on Completion and/or Tests after Completion.
(Deleted)
11.9
Performance Certificate
Performance of the Contractor's obligations shall not be
considered to have been completed until the Employer has
issued the Performance Certificate to the Contractor, stating the
date on which the Contractor completed his obligations under
the Contract.
The Employer shall issue the Performance Certificate within 28
days after the latest of the expiry dates of the Defects Liability
Periods, or as soon thereafter as the Contractor has supplied all
the Contractor's Documents and completed and tested all the
Works, including remedying any defects. If the Employer fails to
issue the Performance Certificate accordingly:
(a)
(b)
11.11
Clearance of Site
Upon receiving the Performance Certificate, the Contractor shall
remove any remaining Contractor's Equipment, surplus
material, wreckage, rubbish and Temporary Works from the Site.
If all these items have not been removed within 28 days after
the Employer issues the Performance Certificate, the Employer
may sell or otherwise dispose of any remaining items. The
Employer shall be entitled to be paid the costs incurred in
connection with, or attributable to, such sale or disposal and
restoring the Site.
Any balance of the moneys from the sale shall be paid to the
Contractor. It these moneys are less than the Employer's costs,
the Contractor shall pay the outstanding balance to the
Employer.
12.
12.1
Procedure for Tests after Completion
If Tests after Completion are specified in the Contract, this
Clause shall apply.
(a)
(b)
(c)
(Deleted)
12.3
Retesting
13.
13.1
Right to Vary
Variations may be initiated by the Employer at any time prior to
issuing the Taking-Over Certificate for the Works, either by an
instruction or by a request for the Contractor to submit a
proposal. A Variation shall not comprise the omission of any
work which is to be carried out by others.
The Contractor shall execute and be bound by each Variation,
unless the Contractor promptly gives notice to the Employer
stating (with supporting particulars) that (i) the Contractor
cannot readily obtain the Goods required for the Variation, (i) it
will reduce the safety or suitability of the Works, or (iii) it will
have an adverse impact on the achievement of the Performance
Guarantees. Upon receiving this notice, the Employer shall
cancel, confirm or vary the instruction.
13.2
Value Engineering
13.3
Variation Procedure
If the Employer requests a proposal, prior to instructing a
Variation, the Contractor shall respond in writing as soon as
practicable; either by giving reasons why he cannot comply (if
this is the case) or by submitting:
(a)
(b)
(c)
Price.
The Employer shall, as soon as practicable after receiving such
proposal (under Sub Clause 13.2 [Value Engineering] or
otherwise), respond with approval, disapproval or comments.
(Deleted)
13.6
(Deleted)
13.7
Adjustments for
Changes in Legislation
No price adjustment shall be applicable on any account either for
increase or decrease in cost resulting from a change in the laws of
Union of India including the introduction of new laws and also due to
variation in exchange rates for conversion of currencies.
13.8
Adjustments for
Changes in Costs
The Contract Price shall not be subject to adjustment for any
changes in the cost of labour, materials or other inputs to the
works during the Contract period.
(b)
(c)
(d)
(e)
(f) the Contract Price will be paid to the Contractor in Indian Rupees only as
indicated in the Contract Price Schedule.
14.2
Advance Payments
14.2.1
The Employer will make recoverable advance payments to the extent of 10%
(ten Percent) of the total value of the Part A of the Contract Price in two
installments. Interest @8% per annum (simple interest) against the above
advance shall be charged.
14.2.2
14.2.3
Clause 8.2 for Section (I), (II), (III), (IV) and (V) of the work.
14.3
(b)
amount to be deducted for retention, shall be @5% from the each interim
bills except form advance payments.
(c)
(d)
(e) any other additions or deductions which may have become due in
accordance with the Contract (including those under Clause 20)
(f)
Deduction of Income tax, works contract tax and other taxes etc. as
applicable.
(g) The total amounts certified on all previous Interim Payment Certificates.
14.3.1
14.3.2
14.3.3
of the structure till the date of next/preceding bill and the balance of the
amount payable under these items for individual structure.
Payment for Section III Hydro-mechanical works shall be made as under:
a) 70% of the quoted price shall be paid on receipt of each brought out item of
works as indicated in the Price Schedule (Ex-works) as progressive payment
against interim payment certificate.
b) 20% of quoted price shall be paid on erection of hydro-mechanical
equipment as progressive payment against interim payment certificate
prepared on the basis of various items erected.
14.3.4
14.3.5
14.3.6
Deleted
Schedule of Payments
The Contractor shall include a schedule of monthly payments for both Part A
and Part B of the Contract separately specifying the installments spread over
the stipulated entire construction period in which the Contract Price will be
paid.
The monthly installment as quoted in the schedule of payments during bidding
stage and subsequent revision / modification (if applicable) during Contract
Agreement stage shall be considered as guideline for interim payment
certificate.
Certification for interim payment shall be based on the assessment of actual
progress achieved in executing the works and if actual progress is found to be
less than the value on which the schedule of payment was based, then the
employer representative may proceed in accordance with Sub-Clause 3.5
(Determinations) to agree or determine revised installments, which shall take
account of the extent to which progressive executed value of the work is less
than that the value of work on which the installments were previously based.
14.5
(Deleted)
14.6
Interim Payment
No amount will be paid until the Employer has received and approved the
Performance Security. Thereafter, the Employer shall within 28 days after
receiving a Statement and supporting documents, give to the Contractor notice
of any items in the Statement with which the Engineer in charge disagrees,
with supporting particulars. Payments due shall not be withheld, except that:
(a) if any thing supplied or work done by the Contractor is not in accordance
with the Contract, the cost of rectification or replacement may be withheld until
rectification or replacement has been completed; and/or
(b) if the Contractor was or is failing to perform any work or obligation in
accordance with the Contract and had been so notified by the Engineer in
charge, the value of this work, or obligation may be withheld until the work or
obligation has been performed.
The Employer may, be any payment, make any correction or modification that
should properly be made to any amount previously considered due. Payment
shall not be deemed to indicate Engineer in charge acceptance, approval,
consent or satisfaction.
14.7
Timings of Payment
(a) the Employer shall pay the amount certified in each Interim Payment
Certificate within a reasonable time from the date on which the Engineer-incharge received the Contractor's statement and supporting documents;
otherwise the Contractors statement shall be returned within within a
reasonable time with specific remarks for reconciliation .
(b) the Employer shall pay the amount certified in the Final Payment Certificate
(Deleted)
Payment of Retention Money
When the Employers Representative has issued the Completion Certificate for
the Works covering Part A of the Contract, and the Works have passed all
specified tests, the first half of the Retention Money shall be certified by the
Engineer-in-charge for payment to the Contractor against submission of bank
guarantee of equivalent amount which shall be remain valid up to 3(three)
months in excess of defect liability Period. The bank guarantee shall be suitably
extended to such time any work remain to be executed under Clause 11 or
Clause 12.
Unless otherwise stated in the contract, upon expiry of the Defect Liability
period, the Engineer-in-charge shall certify the second half of the Retention
money to the Contractor for payment. Except that, if at such time any work
shall remain to be executed under Clause 11 or Clause 12, the Engineer-incharge shall be entitled to withhold certification, until completion of such work,
of so much of the balance of the Retention Money as shall represent the cost of
the work remaining to be executed.
14.10
Statement at Completion
within a reasonable time after the issue of the final Taking-Over Certificate
for the Works, the Contractor shall submit, to the Employer's Representative,
six copies of a statement at completion with supporting documents showing in
detail, in the form approved by the Employer's Representative under SubClause 13.3:
(a) the final value of all work done in accordance with the Contract up to the
date stated in such Taking-Over Certificate,
(b) any further sums which the Contractor considers to be due. and
(c) an estimate of amounts which the Contractor considers will become due to
him under the Contract.
The estimated amounts shall be shown separately in such statement at
completion..
14.11
Discharge
When submitting the Final Statement, the Contractor shall submit a written
discharge, which confirms that the total of the Final Statement represents full
and final settlement of all monies due to the Contractor under the Contract.
Such discharge may state that it shall become effective only after payment due
under the Final Payment Certificate has been made and the Performance
Security referred to in Sub-Clause 4.2 has been returned to the Contractor.
14.13
Final Payment
The Employers Representative shall issue to the Employer, with a copy to the
Contractor, the Final Payment Certificate within a reasonable time after
receiving the Final Statement and written discharge in accordance with SubClauses 14.11 and 14.12, stating:
(a) the amount which is finally due, and
(b) after giving credit to the Employer for all amounts previously paid by the
Employer and for all sums to which the Employer is entitled, the balance, if
any, due from the Employer to the Contractor or from the Contractor to the
Employer as the case may be.
If the Contractor has not applied for a Final Payment Certificate in accordance
with Sub-Clauses 14.11 and 14.12, the Employers Representative shall
request the Contractor to do so. If the Contractor fails to make such an
application within a reasonable time, the Employers Representative shall
issue the Final Payment Certificate for such amount as he considers to be due.
14.14
14.15
Currency of Payments
All payments whatsoever will be made in Indian Rupees only as per Contract
Agreement.
14.16
Price Adjustment:-
14.16.1 Procedure:
14.16.1(A)
No escalation on prices and wages will be paid. The bidder has to quote
the bid taking into account of any variation in rates and wages during the period
of execution i.e.; from the date of quoting the rates to the end of completion of
work in all respects.
(B)
However, in respect of cement and steel escalation of prices will be
made for the actual quantity used in the work if the prices increase by more than
5% over prevailing market rates of Rs2700 per M.T. and RS 27500 per M.T. for
cement and steel respectively. For the purpose of assessing the increase in prices,
the actual market price of cement and steel communicated by the Engineer-in
chief ,Admn.wing, I&CAD Dept. will be adopted.
The contract price shall be adjusted for increase or decrease in rates and prices for
labour, cement, steel, fuel, lubricants and other materials ( Electro mechanical
works) in accordance with the following principals and procedures as defined in
clause 20.9 of conditions of contract.
i)
Price adjustment shall apply only for work carried out within the stipulated time
or extension granted by the Employer and shall not apply to work carried out
beyond the stipulated time for reasons attributable to the Contractor, and
ii)
Price adjustment shall be calculated separately for the local and foreign
components of the payment for work done in the manner explained in the
following clauses.
iii)
The price adjustment formula shall be applied to the value of work done during
each quarter as defined below:
R=Total value of work done during the quarter as defined in clause 47.1 of
conditions
of contract.
RI= Portion of R, payable in local currency.
RF = Portion of R, payable in foreign currency (at fixed exchange rats)
R= RI + RF
14.16.2. Local Currency Component
a) Labour
Price adjustment for increase or decrease in local labour costs shall be paid in
accordance with the following formula.
VL
Where,
VL = Increase or decrease in the cost of work during the quarter under
consideration due to change in rates for local labour.
PL = % of labour component of the work.
LO = Average consumer price index for industrial workers for KURNOOL Center
for quarter preceding the stipulated date of opening of bids ( as published by the
Labour Bureau, the Ministry of Labour, Government of India ).
LI = Average consumer price index for industrial workers for KURNOOL Center
for the quarter under consideration (as published by the Labour Bureau, the
Ministry of the Government of India, New Delhi ).
b) Materials
The price adjustment for increase or decrease in cost of local materials shall be
paid in accordance with the following formula.
i) Cement
VC = 0.85 x PC/100 x RI (CI CO)/ CO
Where,
VC = Increase or decrease in the cost of work during the quarter under
consideration due to change in rates of cement.
PC = % of cement component of the work.
CO = Average whole sale price index for cement for the quarter preceding the
date of opening of bids (as published by the Ministry of Industrial Development,
Government of India, New Delhi ).
CI = Average wholesale price index for cement for the quarter under
consideration (as published by the Ministry of Industrial Development,
Government of India, New Delhi).
ii)
Steel
Other Material
MO = Average whole sale price index for all commodities for the quarter
preceding the stipulated last date of opening of the Bids (as published by the
Ministry of Industrial Development, Government of India, New Delhi).
MI = Average whole sale price index for all commodities for the quarter under
consideration ( as published by the Ministry of Industrial Development, the
Government of India, New Delhi ).
The price adjustment for increase or decrease in the cost of fuel and lubricants
shall be paid in accordance with the following formula.
VF = 0.85 x PF/100 x RI (FI FO)/ FO
Where,
VF = Increase or decrease in the cost of work during the quarter under
consideration due to change in rates for fuels and lubricants.
PF = % of fuel and lubricants component of the work.
FO = Average official retail price of HSD at the existing consumers pumps of
IOC at KURNOOL on the day one of the calendar month preceding the
stipulated date of opening of bids.
FI = Average official retail price of HSD at the existing consumers pumps of IOC
at KURNOOL on the 15th day of the middle calendar month of the quarter under
consideration.
Note :
PL + PC + PS + PM + PF should not be more than 100.
PLI = Index for the foreign inputs as published in the country of origin for the
quarter under consideration.
a) The Bidder shall in his Bid, indicate the appropriate Index / Indices, the
source of publication and the period in which it is published and furnish
copies or extracts from the preceding 12 months of publications. The
proposed Index or indices shall be subject to approval of the Employer.
b) Indices shall be appropriate for their purpose and shall relate to the
Contractors proposed source of supply of inputs on the basis of which his
Bid price and anticipated foreign currency requirements should have been
computed. As the proposed basis for price adjustment the Contractor shall
submit with the Bid.
i) Schedule of indices duly completed by the Bidder to show the source of all
indices and the latest value of official or provisional base indices.
ii) Official publications showing the values of the proposed indices as available
during the twelve months preceding to the stipulated date of opening date of
bids.
c) If the currencies in which the foreign exchange is expressed are different from
the currencies of the source of the relevant indices, the Engineer shall
determine the correction to be applied in calculating the price adjustment
factor in order to avoid difference in the amount of price adjustment. Such
correction should correspond to the ratio of the exchange rates between the
respective currencies on the date one of the calendar month prior to the
stipulated date of opening of Bids.
d) If the bidder has requested payment in more than one foreign currency,
foreign currency RF shall be suitably broken up and a separate formula be
applied to each currency component by applying the corresponding indices
for the foreign input procured with that currency.
Contractor, other than under the component indicated under the Sub-Clauses
14.16.1 to 14.16.3 above, in the execution of the works, such additional or
reduced cost shall be certified by the Engineer after examining the records
provided by the claimant and shall be paid by or credited to the Employer.
b) Notwithstanding the foregoing, such additional or reduced cost shall not be
separately paid or credited if, (i) the same has been paid in whatever manner
including payment made though any of the inputs to the price adjustment
formulae in accordance with the provisions of Clause 20.9.1 of General
Conditions of Contract or (ii) the same has been taken into account by any
other clause of the Contract.
14.16.5. Components with Percentages
The following percentages are estimated by the Employer for the price
adjustment for the entire contract. However, the Bidder may not be bound by
the following percentages, provided that the Bidder
shall indicate such percentages in appendix to the Bid with full evidence.
1.
2.
3.
4.
5.
Labour PL
Cement PC
Steel PS
POL PF
Other Materials PM
8%
1%
50%
24%
17%
15.2
Termination by Employer
The Employer shall be entitled to terminate the Contract if the
Contractor:
(a)
(b)
(c)
(d)
(e)
(f)
15.3
Valuation at Date of Termination
As soon as practicable after a notice of termination under SubClause 15.2 [Termination by Employer] has taken effect, the
Employer shall proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine the value of the Works,
Goods and Contractor's Documents, and any other sums due to
the Contractor for work executed in accordance with the
Contract.
15.4
Payment after
Termination
15.5
Employer's Entitlement
of Termination
The Employer shall be entitled to terminate the Contract, at any
time for the Employer's convenience, by giving notice of such
termination to the Contractor. The termination shall take effect
28 days after the later of the dates on which the Contractor
receives this notice or the Employer returns the Performance
Security.
16.
(Deleted)
17.
17.1
Indemnities
The Contractor shall indemnify and hold harmless the Employer,
the Employer's Personnel, and their respective agents, against
(b)
The Contractor shall take full responsibility for the care of the
Works and Goods from the Commencement Date until the
Taking-Over Certificate is issued (or is deemed to be issued
under Sub-Clause 10.1 [Taking Over of the Works and
Sections]) for the Works, when responsibility for the care of the
Works shall pass to the Employer. If a Taking-Over, Certificate is
issued (or is so deemed to be issued) for any Section of the
Works, responsibility for the care of the Section shall then pass
to the Employer.
After responsibility has accordingly passed to the Employer, the
Contractor shall take responsibility for the care of any work
which is outstanding on the date stated in a Taking-Over
Certificate, until this outstanding work has been completed.
(Deleted)
17.4
(Deleted)
17.5
Intellectual and
Industrial Property
Rights
In this Sub-Clause, "infringement" means an infringement (or
alleged infringement) of any patent, registered design,
copyright, trade mark, trade name, trade secret or other
intellectual or industrial property right relating to the Works;
and "claim" means a claim (or proceedings pursuing a claim)
alleging an infringement.
Whenever a Party does not give notice to the other Party of any
claim within 28 days of receiving the claim, the first Party shall
be deemed to have waived any right to indemnity under this
Sub-Clause.
The Employer shall indemnify and hold the Contractor harmless
against and from any claim alleging an infringement which is or
was:
(a) an unavoidable result of the Contractors compliance with
the Employer's Requirements, or
(b)a result of any Works being used by the Employer:
(i)
or
the
the
the
17.6
Limitation of Liability
Neither Party shall be liable to the other Party for loss of use of
any Works, loss of profit loss of any contract or for any indirect
or consequential loss or damage which may be suffered by the
other Party in connection with the Contract, other than under
Sub-Clause 17.1 [Indemnities].
The total liability of the Contractor to the Employer, under or in
connection with the Contract other than under Sub-Clause 4.19
[Electricity, Water and Gas], Sub-Clause 4.20 [Employer's
Equipment and Free-Issue Material], Sub-Clause 17.1.
[Indemnities] and Sub-Clause 17.5 [Intellectual and Industrial
Property Rights], shall not exceed the Contract Price stated in
the Contract Agreement.
This Sub-Clause shall not limit liability in any case of fraud,
deliberate default or reckless misconduct by the defaulting
Party.
18.
Insurance
18.1
the periods of his liability, under the Contract and under the law of
the Country. The Contractor undertakes to give the Employer
reasonable notice in the even of difficulty (if any) in extending,
renewing of reinstating such insurance.
18.2
18.3
18.4
from
the
(a) evidence that the insurances described in this Clause have been
effected, and
(b) copies of the policies for the insurances described in SubClauses 18.2 and 18.3.
When each premium has been paid, the Contractor shall submit copy
receipts to the Employer. The Contractor shall also, when providing
such evidence, policies and receipts to the Employer, notify the
Employers Representative of so doing.
The Contractor shall effect all insurance for which he is responsible
with insurers and in terms approved by the Employer. Each policy
insuring against loss or damage shall provide for payments to be
made in the currencies required to rectify such loss or damage.
Payments received from insurers shall be used for the rectification of
such loss or damage.
The Contractor (and, if appropriate, the Employer) shall comply with
the conditions stipulated in each of the insurance policies. The
Contractor shall make no material alteration to the terms of any
insurance without the prior approval of the Employer. If an insurer
makes (or purports to make) any such alteration, the Contractor shall
notify the Employer immediately.
If the Contractor fails to effect and keep in force any of the
insurances required under the Contract, or fails to provide
satisfactory evidence, polices and receipts in accordance with this
Sub-Clause, the employer may, without prejudice to any other right
or remedy, effect insurance for the coverage relevant to such default,
and pay the premiums due. Such payments shall be recoverable
from the Contractor by the Employer, and may be deducted by the
Employer from any monies due, or to become due, to the Contractor.
Nothing in this Clause limits the obligations, liabilities or
responsibilities of the Contractor or the Employer, under the other
terms of the Contract or otherwise. Any amounts not insured or not
recovered from the insurers shall be borne by the Contractor and/or
the Employer accordingly.
19.
Force Majeure
19.1
Definition of
Force Majeure
(vi)
19.2
Notice of Force Majeure
19.5
19.6
Optional Termination,
Payment and Release
If the execution of substantially all the Works in progress is
prevented for a continuous period of 84 days by reason of Force
Majeure of which notice has been given under Sub-Clause 19.2
[Notice of Force Majeure], or for multiple periods which total
more than 140 days due to the same notified Force Majeure,
then the Employer may give a notice of termination of the
Contract. In this event, the termination shall take effect 7 days
after the notice is given and the Contractor shall proceed in
accordance with sub-clause 16.3 (Cessation of work and
Removal of Contractors equipment)
Upon such
Contractor:
(a)
(b)
(c)
(d)
(e)
19.7
termination,
the
Employer shall
pay
to the
the amounts payable for any work carried out for which
a price is stated in the Contract;
the Cost of Plant and Materials ordered for the Works
which have been delivered to the Contractor, or of which
the Contractor is liable to accept delivery: this Materials
shall become the property of (and be at the risk of) the
paid for by the Employer and the Contractor shall place
the same Employer's disposal;
any other Cost or liability which in the circumstances
was reasonably incurred by the Contractor, expectation
of completing the Works;
the Cost of removal of Temporary Works and Contractor's
Equipment Site and the return of these items to the
Contractor's Works in his country (or to any other
destination at no greater cost); and
the Cost of repatriation of the Contractor's staff and
labour employed wholly in connection with the Works at
the date of termination.
(b)
20.
20.1
Contractors
Claims
20.2
Appointment
of Dispute
Adjudication
Board
20.3
Failure to Agree
Dispute
Adjudication
Board
20.4
Obtaining Dispute
Adjudication
Boards Decision
(d)
the Parties fail to agree upon the appointment of a
replacement person within 42 days after the date on which the sole
member or one of the three members declines to act or is unable to
act as a result of death, disability resignation or termination or
appointment,
In that case Employers representative shall, upon the request of
either or both of the Parties and after due consultation with both
Parties, appoint this member of the DAB. This appointment shall be
final and conclusive. Each Party shall be responsible for paying onehalf of the remuneration of the appointing entity or official.
20.5
Amicable
Settlement
20.6
Arbitration
If either Party is dissatisfied with the DAB's decision, then either Party
may, within 28 days after receiving the decision, give notice to the
other Party of its dissatisfaction. If the DAB fails to give its decision
within the period of 84 days (or as otherwise approved) after
receiving such reference or such payment, then either Party may,
within 28 days after this period has expired, give notice to the other
Party of its dissatisfaction.
In either event, this notice of dissatisfaction shall state that it is given
under this Sub Clause, and shall set out the manner in dispute and
the reason(s) for dissatisfaction. Except as stated in Sub-Clause 20.7
[Failure to Comply with Dispute Adjudication Board's Decision] and
Sub-Clause 20.8 [Expiry of Dispute Adjudication Board's
Appointment], neither Party shall be entitled to attempt any
discussion for amicable settlement of a dispute unless a notice of
dissatisfaction has been given in accordance with this Sub-Clause.
If the DAB has given its decision as to a matter in dispute to both
for
The arbitrator(s) shall have full power to open up, review and revise
any certificate, determination, instruction, opinion or valuation of (or
on behalf of) the Employer, and any decision of the DAB, relevant to
the dispute.
Neither Party shall be limited in the proceedings before the
arbitrator(s) to the evidence or arguments previously put before the
DAB to obtain its decision, or to the reasons for dissatisfaction given
in its notice of dissatisfaction. Any decision of the DAB shall be
admissible in evidence in the arbitration.
20.8
Expiry of Dispute
Adjudication
Board's
Appointment
(a)
(b)
20.9
Price Adjustment
The contract price shall be adjusted for increase or decrease in rates and
prices for labour, cement, steel, fuel, lubricants and other materials
(electro mechanical works) in accordance with the following principals
and procedures and as per formula given in the contract data.
a)
b)
c)
d)
R= Total value of work done during the quarter excluding the cost of
materials and electrical energy supplied by the Employer at the
fixed prices. It would include the value of materials on which
secured advance has been granted if any, during the quarter, less
the value of materials inrespect of which the secured advanced has
been recovered, if any, during the quarter.
20.9.1
To the extent that full compensation for any rise or fall costs to the
Contractor is not covered by the provisions of this or other clauses in the
Contract, the unit rates and prices included in the Contract shall be
deemed to include amounts to cover the contingency of such other rise
or fall in costs.
APPENDIX TO TENDER
Hereunder does the Employer provide the relevant data to the
specific work. However, bidders are required to fill the necessary
data in appropriate blank spaces below.
RATE OF PROGRESS
The total period of completion of work is 24 months from the date
of entering into agreement to proceed including rainy season the
work shall be programmed such as to achieve the milestones as
under.
1)WORK PROGRAMME OF ACHIEVING THE MILE STONES :
H.N.S.S CIRCLE ANANTAPUR, ANDHRA PRADESH, INDIA.
Item
Time
for
notice
commence
Defect Liability Period
to
Clause/SubClause
1.1.3.3 & 8.1
1.1.3.7
8.2
1 Up to 2 Month
Period in
Months
2 Months
2 (up to 6 months)
3 Months
Sl.No.
Particulars
15 ( Fifteen) days
2 (two) years after issue of completion
certificate for Part A of the Contract
comprising Sections I, II, III, IV and V
24(Twenty four) months as detailed below:
Description of
work
1) Completion of
Composite
Hydraulic Model
study and
submission of
detailed design &
drawings of the
total scheme and
approval.
1) Placing order and
manufacture of one
pump with motor
including all
accessories
2) Civil works
3) Supply of
PSC/Steel pipes for
one row.
4) Substation works
Phy/Qty. to be
Completed.
100 % of work
1 No.
50%
35% of total length
of one row.
50% of work
3 (Upto 10 Months)
4 Months
including
accessories
1 No.
1) Delivery of
pumps andmotors
including
accessories
100%
One Row 100 % full
length
3) Civil woirks
4.
4 (upto 13 months)
3 Months
4) Suppply and
laying of pressure
main 1 Row
100 %
1 No.
5) Supply, erection,
testing of
substation.
1) Erection, Testing
and commission of
pump and motors
including
accessories.
5.
5 (upto 17 months)
4 Months
2) Manufacture of
remaining pumps
and motors,
accessories.
3) Supply of pipes
of pressure main for
remaining rows.
6.
6 (upto 21 Months)
4 Months
1) Manufacture of
remaining pumps
and motors
accessories.
2) a) Supply of
pipes of pressure
main for remaining
two Rows.
b) Erection - do
1) Delver to site
Remaining Nos.
100% length of
remaining rows.
7.
7 (upto 24 Months)
3 Months
100%
2) Supply, laying
testing and
commissioning of
remaining Rows of
pressure main.
Trial run and
completion of works
in full as per
contract including
finishing works.
ii) HANDING OVER OF SITE.
Schedule of programme of handing over of Site to the Contractor.
Sl.No.
Reach
The entire site will be handed over to the contractor at a time on the date of concluding
Agreement itself./ finalization of alignment of canal and approval of H.P.s by the competent
authority.
Local currency
1.1.4.5
Definition of Section
Laws and Languages
Time for possession of
site
1.1.5.6
1.4
2.1
Amount
of
performance Security
4.2
Validity
of
performance Security
Indian Rupees
Under Special Conditions of Contract
Laws of Union of India, English
Within 15 days from the date of LOA. No
compensation is applicable within that period.
2.5% of Part A contract amount
2.5% of Part B contract amount
Notice
of
subcontractors
Normal working hours
4.4
6.5
8.6
8.7
Section of Works
All Civil Works
Pipelines
15% of the total Pipe Line length
25% of the total Pipe Line length
30% of the total Pipe Line length
including all civil works of Intake
pump
house,
Intermediate
pump house, cross drainage
work, Road crossing, Railway
crossing.
30% of the total pipeline length
including Gravity Canal.
100% of the Pipe Line including
all Cross Drainage Works
Pumps and other related equipment
Note:- Refer table against Clause
8.2
Limit
of delay
8.7
10 (ten) percent of the Total Part A Contract Price
damage
for delay
Liquidated
9.4
As given below
damage
for
failure
in
Performance
tests
The performance guarantees which shall attract liquidated damages are:
i)
ii)
iii)
2.
3.
Guarantee
Increase in power consumption, at
motor input terminals, for each pump
(as determined at site during
performance & guarantee tests).
Flow
through
each
pump
(as
determined at all delivery points
during performance & guarantee
tests).
Energy losses in the auxiliary
transformers on principal tap at rated
voltage and frequency.
a) Iron loss
The liquidated damages shall be prorated for the fractional pats of the
appropriate unit of
measurement indicated, unless otherwise specified.
One pump of each type (in case of more than one type of pump) shall
be
tested in each
pumping station. The pump to be performance
tested shall be selected solely at the discretion of the EMPLOYER. For
shortfall in performance, if found, in any of the pump, liquidated
damages shall be levied on all the pumps of same type & size by
multiplying the liquidated damages for one pump by number of such
pumps.
Recovery
of
advance
Schedule
of
payment
Application
for
interim payment
and
interim
payments
Amount
of
insurance
for
works
and
Contractors
Equipment
Amount of third
party insurance
14.3
18.3
Rs. 20,00,000
Period
of
submissi
on of
Evidence of
insurance
Relevant policies
Sections
Description
Part A - EPC Turnkey
Contract
Design and Engineering
Civil works
Hydro-mechanical works
Electro-mechanical works
Pipeline and Allied Works
Total Part A Contract
Within 30 days
Within 60 days
INDIAN RUPEES
Percentage of Bid/Contract
price
ANNEXURE GCCI
PART - II
TECHNICAL SPECIFICATIONS
OFFICE OF THE
SUPERINTENDING ENGINEER
H.N.S.S. CIRCLE, ANANTAPUR
ANANTAPUR DISTRICT, ANDHRA PRADESH.
SPECIAL NOTE ON CONTRACT PRICE AND PAYMENTS:
The contract price shall be comprising of total value of the work for EPC Turn
Key Contract including operation and maintenance of the installation for a period of
2 (two) years as per contract agreement.
The employer will pay the contractor a firm contract price for completion of all
works as specified under the scope of the work / employers requirement which shall
include but not limited to supply and installation of all plants and its accessories leading
to successful commissioning of the pumping scheme with allied works including
operation and maintenance of the pumps, other allied electrical equipment for a period of
2 (two) years after successful commissioning of the project on EPC Turn Key cum O&M
contract basis.
Intermediate payment for the works shall be made on the basis of the quantity
executed and corresponding quoted rates in the contract. The measurement and
payment clause under the technical specification of various items in the Volume II
pertain to intermediate payments only and in all cases payment shall be limited to the
total price quoted by the contractor against each item of work.
SCHEDULE 'C'
SPECIAL SPECIFICATIONS (S.S.)
SCOPE OF WORK
The information and data furnished herein relevant to the work
and site conditions are general. It shall be the responsibility of
the contractor to fully acquaint himself with the nature and
location of works, quarries, local conditions and other aspects
which are relevant to the work.
A)
B)
D)
E)
Estimate Considerations (Soil Classifications and the
quantities of respective classifications.
The quantities of
excavation proposed for construction purpose.
All soils up to SDR, F & F Rock and Hard rock etc.,
F)
G)
Deleted.
H)
Any other information available with the department
relevant to the work
(land acquisition, funds)
A.P. State Funding
I)
GENERAL SPECIFICATIONS
1.a) These Technical specifications, shall apply to all works as are
required to be executed under the contract or otherwise directed by
the Engineer. In every case the work shall be carried out to the
satisfaction of the Engineer and conform to the location, lines, grades
and cross - sections shown on the drawings or as indicated by the
Engineer. The quality of work and materials, shall comply with the
requirements set-forth in this and succeeding sections. Where the
drawings and specifications describe a portion of the work in only
general terms and not in complete details. It shall be understood that
only the best general practice is to prevail, materials and
workmanship of the best quality are to be employed and the
instructions of the Engineer are to be fully complied with.
b)
The contractor shall carry out the works in accordance with the
specifications laid down in this section together with the detailed
specifications stipulated under succeeding sections, Andhra Pradesh
Standard Specification, relevant codes with the all amendments
published up to the date to tendering and the departmental manual
for quality control.
The basic center lines, reference points and bench marks will have to
be fixed.
b)
The Contractor shall be responsible for the correct setting out of all
works at his cost. The Contractor shall execute the work true to
alignment grade and levels as shown in the drawings and as directed
by the Engineer and shall check these at frequent intervals. The
contractor shall provide all facilities like labour and instruments and
shall cooperate with the departmental officers to check all alignments,
Grades, levels and dimensions such checking shall not absolve the
Contractor of his own responsibility of maintaining the accuracy of the
work.
2.0
CLEARING OF SITE
2.1.1 GENERAL
The date, pertaining to the work furnished in the relevant report and
drawings, are for information of tenderers the Govt. of Andhra Pradesh
does not guarantee the reliability or accuracy of any of the data and
shall assume no responsibilities for any deductions, conclusions or
interpretations that may be made from them. The contractor shall
undertake at his expenses such studies as are necessary to assess the
reliability and accuracy of the information presented in the data.
2.1.2 CLEARING AND GRUBBING:
a)
The portion of the right--of--way, where required for earth work under
these specifications, shall be cleared of all trees, bushes, rubbish and
other objectionable matter. Trees designated by the Engineer-incharge shall not be cut and shall be protected from injury, such
cleared material shall be disposed off as provided in paragraph-2.1. 4
below or removed from the site of work before the date of completion
of the contract as approved by Engineer in charge. The useful
materials should be stacked and handed over to the Department. The
clearing operation shall be in accordance with clause 4.1, 4.1.1, 4.2
and 4.3 of I.S. 4701-1982 Indian Code of Practice for earth work.
Surface boulders either loose or partly embedded in the ground will
have to be removed and stacked as directed. All holes and hollows
whether originally existing or produced by digging up roots shall be
filled with suitable earth, well rammed and leveled off. Thus more than
30 cms. girth, will be paid for separately at the rates specified in the
Schedule-'A'. The logs/stumps cleared shall be neatly stacked and
handed over to the representative of Engineer in charge as directed at
the places indicated. The pits formed up roots which shall be filled
with suitable earth and compacted and leveled at the cost of
contractor.
2.1.3. GRUBBING
a)
The ground surface under all the embankments and the surface of all
excavation is to be used for embankments as shown in the drawings
or as directed by the Engineer in charge shall be cleared of all stumps,
roots and vegetable matter of every kind the stumps shall be pulled or
otherwise and tools shall be grubbed.
2.14
a)
2.1.5 PAYMENT:
a)
Separate payment will not be made for clearing of trees below 30 cm.
girth and grubbing including filling of holes and hollows and disposal
of the cleared and grubbed material require under the above
paragraphs. The contractor shall include the cost thereof in the
Schedule 'A' of the contract for the relevant of finished item of work
for which clearing and grubbing as mentioned in the above para are
required. No payment towards removal of small stones and the
boulders of size less than 0.03 cubic meters will be made, and the rate
quoted for excavation should be inclusive of this item. However
surface boulders of size greater than 0.03 cubic meters but less than 3
cubic meters. either loose or partly embedded in the ground, when
removed payment will be made for actual quantity. Surface boulders
shall be premeasured, after removal, the quantity based on stack
measurement duly deducting 40% or more towards voids as
considered by the Engineer in charge will be compared and minimum
of the above measured quantity will be paid at the rate quoted in
schedule 'A' for the relevant classification.
3.1.1
Sl.No. :
01.
IS : 4701 - 1982
02.
IS : 7293 - 1974
machinery
Safety
code
for
working
with
construction
03.
IS : 3764 - 1966
04.
IS : 1498 - 1970
05.
IS 2720 - 1973
water
(Part. 2)
06.
IS 2720 - 1980
water
(Part. 7)
07.
Dry
IS 2720
content.
IS 2720 - 1976
(Part. 29)
09.
IS 1888 - 1982
10.
IS 2131 - 1981
11.
IS 4332 - 1967
sampling
(Part. 1)
12.
IS 2720 - 1983
(Part. 4)
Analysis.
IS 2720 - 1985
(Part. 5)
13.
14.
IS 2720 - 1971
relation
(Part. 9)
15.
IS 2720 - 1991
(Part. 10)
16.
IS 2720 - 1986
(Part. 13)
17.
IS 2720 - 1986
(Part. 15)
18.
IS 2720 - 1983
(Part. 14)
19.
IS 2720 - 1987
(Part. 16)
20.
IS 2720 - 1964
(Part. 18)
21.
IS 2720 - 1977
(Part. 40)
22.
IS 2720 - 1977
(Part. 41)
23.
IS 8237 - 1985
24.
IS 8414 - 1977
b)
3.1.3 SCOPE :
Excavation of canal/Channel/approach channel/drain/cut off trench/Key
trench/ toe wall/toe drain/foundations for structures/Cut off wall/Chute drains
etc. all soils/HDRI and 11/F&F rock/Nandyal Shales/HR in both wet and dry
conditions and disposal of spoil not useful for construction on spoil bank and
soils not required for construction of stock piles and stacking of useful stone,
disposal of not useful stone, conveyance of excavated spoil/soils including
swell, conveyance of excavated rock including voids, with all leads, lifts and
b)
The contractor shall present his planning of the work along with
required details to the Executive Engineer at least 15 days before
starting the work.
3.1.5 a)
b)
c)
d)
e)
The contractor shall take all precautions to see that the lines, points
and Bench Marks fixed by the Department are not disturbed by his
work and shall make good of any such damage.
f)
All materials and labour for setting out works including construction of
Bench Marks, reference lines, check profiles and surveys, as may be
required at various stages of construction shall be supplied by the
Contractor at his cost. The cost of such work shall be deemed to have
been included in the cost of the relevant item of excavation in the
Schedule - A.
g)
GENERAL :
The preparation of surfaces to the full width of proposed canal cutting
including the bed, berms and under canal banks and tank bund and
borrow area shall be in accordance with clause 6.5 IS: 4701 - 1982.
Before commencing the work, the toe of the slope on each side of the
banks plus 450 to 600 mm on each side for trimming to loose soils
from the edge after compaction shall be lock spitted (Dog-belled) and
marked by pegs, firmly driven into the ground at intervals of 25m. or
closer. Profiles made by bamboos, earth or other convenient materials
and strings shall be set up for the guidance of the workmen at about
50 meters apart over straight reaches and about 25 meters apart at
curves. In setting up the profile for an embankment a suitable
allowance shall be made for settlement.
b)
3.1.8. STRIPPING:
If separate schedule 'A' item for stripping is not provided the minimum
stripping depths are as follows:
TABLE.1 DEPTH OF STRIPPING
SL.
No.
TYPE OF VEGETATIVE
COVER ON THE SOIL
DEPTH OF STRIPPING
1)
2)
Agricultural Land
sually
a)
b)
c)
Where the ground surface is below the bed level of the canal this area
shall also be stripped.
e)
All the stripped material shall be deposited beyond the catch drain at
the rear toe of embankment.
3.1.9 SCARIFICATION:
a)
b)
Where the ground surface is below the bed level of the canal, the
entire surface of the foundations for bed filling shall also be scarified
above.
c)
After clearing the area required for canal excavation and construction
of embankments., in accordance with the provisions of specifications
2.1. cross sections shall be taken at every 25 M. interval or closer,
depending on the nature of ground, normal to axis of canal up to
sufficient distance outside the limits of the work. Levels on cross
sections shall be at 3M. intervals or closer intervals as directed by the
Engineer-in-charge and entered in level field books by the Engineer in
charge in the presence of the contractor or his authorised
representative and these shall be binding on the contractor. The
contractor shall write a certificate: Accepted the prelevels recorded on
page from .... to .... " and sign at the end of levels in the level field
book in token of acceptance.
b)
cross section sheets. The cross sections called initial cross section
taken after striping shall form the basis of all future measurements
and payments. These initial cross sections duly signed by the
contractor and Exe. Engineer shall be preserved. All linear dimensions
shall be measured in metres to the nearest 0.01 metre volumes
worked out in cubic metres corrected 0.01 cubie metre. However, In
case of rock excavation occurring in bed or sides, the actual quantity
of rock shall be arrived by taking block levels at 2.5M. intervals all
along the entire area of bed and sides.
c)
d)
b)
c)
Note : The department will have the right to reclassify the soils and rock
even after excavation and payment based on the inspection of
excavate materials and the existing slopes of the canal.
d)
ALL SOILS :
This shall comprise ordinary soils such as sand and loose soils, wet
sand not under water, silt in canals, channels and drains. Loamy and
clayey soils like black cotton soils, red earth and ordinary gravel.
Slushy soils, clayey soils in wet and slushy condition. Hard gravely
soils, mixture of gravel, and soft disintegrated rock like shales,
ordinary gravel, stoney earth and earth mixed with fair size boulders,
soft disintegrated rocks (removable by pick axes and crow bars) and
stone matrix in any direction and mixture of these and similar
materials in both dry and wet conditions.
b)
c)
d)
Hard Rock :
Hard rock and boulders of size greater than 3 cubic metres in size
requiring blasting.
3.1.13. EXCAVATION :
a)
b)
c)
d)
e)
f)
All washable materials and any soil which generally becomes unstable
on saturation such as organic soil, loose soils and expansive soils shall
be removed as directed by the Engineer-in-charge. Payment will be
made for this work as per the relevant rate in Schedule - "A".
g)
All suitable excavated material within economic lead shall be used for
construction of embankments.
h)
i)
In soils the Contractor shall not excavate out side the slopes or below
the established grades or loosen any materials outside the limits of
excavation. Any excess depth excavated below the specified levels it
shall be made good at the cost of the contractor to standards as
prescribed by the Engineer in charge.
j)
k)
Above the lining, in case of lined canals and above the proposed water
level in case of unlined canals, the rock may be allowed to stand at it's
safe angle and no finishing is required other than removal of rock
masses which are loose and are liable to fall.
l)
m)
n)
The regradation for tail channel and approach channel for structures
and diversion of drains or vagus shall conform to the lines,
dimensions, grades, side slopes, and levels as shown on drawings or
as directed by the Engineer in charge. Payment shall be made for this
work at the relevant rate of Schedule-"A" for excavation.
o)
p)
All gangways, roads and stopping shall be such that they fall within
the cross sections so that the final dressing of slope will consist of
digging and no rolling will be required.
q)
r)
s)
Final cutting for 300 MM. in rock shall be carried out by controlled
blasting or trimming or by chiseling wedging, barring with the help of
pneumatic paving breakers and no extra payment will be made. The
cost of such work shall be deemed to have been included in rates of
relevant item in Schedule - "A".
u)
v)
w)
3.1.15.
SLIDES / SLIPS :
a)
b)
If finished slope slide into the canal subsequently such slips in rock
shall be removed measured and paid, provided such slips are not due
to the negligence on the part of the contractor. The nature and
quantity of such slips shall be determined by a joint inspection by the
Executive Engineer / Inspection & Quality control and Executive
Engineer (Construction)
The decision taken by them is binding on the contractor.
c)
In soils any excess depth below the specified levels and any excess
excavation in slopes and widths shall be made good at the cost of the
contractor with suitable soils of similar characteristics and compacted
to a density not less than 95% of proctor's density.
3.1.17 For excavation in rock, tolerance of 75mm beyond the designed canal
profile will however be permitted. No extra payment will be made for
the excavation beyond the designed canal profile. The over breakage
within the tolerance limit of 75 mm shall be refilled with.
i)
Sand and metal in (1:2) ratio using 40mm & 20mm size metal
obtained from canal spoil in (4:1) ratio in bed.
ii)
M 7.5 mix using 40mm. MSA. H.B. Metal graded or approved quality
obtainable from canal spoil for side lining.
Payment for filling such over breakages shall be at the unit rate
quoted in Schedule-"A"
a)
Should any excavation occur beyond the tolerance limit, the excess
quantity so removed beyond tolerance limit, will not be paid on the
other hand the contractor is liable for penal recovery twice the
agreement rate for similar item for the excess quantity excavated. The
same shall also be refilled at contractor's own expenses, with
i)
Sand and metal in (1:2) ratio using 40 mm. and 20mm. size metal in
(4:1) ratio in bed.
ii)
b)
c)
In the land canal where expansive type of soil such as C.H. type of soil
is encountered and over which cement concrete lining directly be laid,
the canal prism shall be over excavated to the extents as directed by
the Engineer in charge and such over excavated section shall be filled
with suitable cohesive non-swelling (CNS) type soil and shall be placed
in uniform horizontal layers and compacted as directed by the
Engineer in charge. The over excavation made in such strata filling by
suitable soil locating and compacting of such soil will be paid
separately.
3.1.18 .
DEWATERING:
b)
c)
d)
e)
f)
g)
h)
The useful rock obtained from the cutting shall not be mixed with
other soils and shall be closely stacked to the gauge separately
beyond spoil bank and all other stone not useful for construction
purpose shall be deposited on the slopes of the canal spoil banks, If
the rock and soil or mixed up while depositing at the spoil banks
suitable deduction from the agreement rate as decided by the
Engineer-in-charge will be made which is binding on the contractor.
i)
j)
The contractor has no claim over any of the materials got out of
excavation of the canal cutting and foundation excavation.
k)
3.1.20 .
LEADS:
a)
The leads and lifts for the soils excavated either in canal or in
foundations of embankments and structures and deposited on spoil
bank or on stock piles will be measured as under.
i)
3.1.21.
i)
The head leads and lifts will be measured in accordance with the
clause 301.5.1.1 of A.P.S.S.
ii)
Above 100M. lead and depth of excavation exceeding 9M. the lead will
be measured along the shortest route from the centre of excavation to
the center of deposition.
b)
The leads and lifts will not be measured for the soils utilized for
formation of embankment obtained from canal excavation or from
foundation excavation or from cut off excavation or from Surplus
course excavation or from any soils excavated under the provisions of
schedule 'A' items or from borrowed soils.
NOTE : If no separate item is provided in Schedule ''A" for leads, delifts and
for conveyance the respective schedule 'A' item for excavation should
include the cost of leads, lifts, delifts and for conveyance for disposal
of spoil/soil/rock or any other excavated material for disposal as per
clause 3.1.19 above.
3.1.22.
PAY LINE:
a)
The canal shall be excavated to the lines, dimensions side slopes and
levels shown on the drawings. Pay line for excavation in all soils and
rocks including subsequent removal of the extra depth for seating to
lining shall be to the dimensions, slips and grades and levels as shown
on the drawings unless otherwise specified.
b)
3.1.23.
Measurement:
a)
b)
Where payments are to be made with reference to the levels the level
field Books, the cross-section sheets and the calculation sheets shall
be treated as adjuncts to the measurement books.
c)
d)
e)
f)
g)
3.1.24.
INTERMEDIATE PAYMENTS
a)
b)
c)
3.1.25.
The contract unit Quoted rate for the items of excavation in scheduleA for one cubic metre shall be the payment in full for carrying out the
following operations required for the individual items including full
compensation:
i)
Setting out
ii)
Site Clearance
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
Final cutting for 300mm in all rocks by control blasting or wedging &
baring or trimming with the help of pneumatic paving breakers for
finishing.
xi)
Safety measures
xii)
All dewatering
xiii)
xiv)
xv)
xvi)
b)
The work shall include providing all the materials, tools and plants and
labour required for presplitting and utilising controlled blasting
technique over and above the normal blasting technique in hard rock
and quartzes excavation, construction of the necessary coffer dams
and cribs and their subsequent removal and necessary sheeting,
shoring, strutting, benching, draining and pumping the removal of all
logs, stumps, grubs and other deleterious matter and obstructions
necessary for placing the foundations : trimming bottom of
excavations : all leads and all lifts of excavated materials back filling
with selected approved material and clearing up the site and the
disposal of all surplus materials, spoil and the stone not useful for
Setting - out
After the site has been cleared to the limits of excavation the work
shall be set out true to lines, curves, and slopes as shown on plans.
II)
EXCAVATION:
a)
Excavation shall be taken to the width of the lowest step of the footing
and the side shall be left to plumb where the nature of soil allows it.
Where the nature of soil or the depth of the trench does not permit
vertical sides, the contractor at his own expense shall put up
necessary shoring, strutting and planking or cut slopes to a safer
angle or both with due regard to safety of personnel and works and to
the satisfaction of the Engineer - in - charge.
b)
c)
Excavation in rock shall be carried out by crow bars, pick axes, chisels
or pneumatic drills etc., Unless permitted by Engineer-in-charge
blasting shall not be resorted to.
d)
e)
b)
c)
The Contractor shall take all precautions in diverting the channels and
discharging the drained water as not to cause damage to the works,
crops or any other property.
d)
b)
c)
When rock or other hard strata is encountered, it shall be free from all
soft and loose material, cleaned and cut to a firm surface either level,
stepped or serrated as directed by the Engineer-in-charge. All seams
shall be cleaned out and filled with cement mortar or grout to the
satisfaction of the Engineer-in-charge.
d)
e)
f)
i)
ii)
iii)
iv)
3.1.32.
3.1.34.
a)
PAY LINE:
BACK FILLING:
a)
b)
c)
The quantity for excavation in soils and rock will be arrived at form the
prelevels and finished levels of respective strata taken at 3 Metre or
less intervals both ways as decided by the Engineer in charge. The
levels will be plotted on graph sheet and average levels arrived at for
purpose of determining the quantity of excavation.
d)
3.1.36
a)
The contractor unit rate per cum. quoted in Schedule 'A' for the items
of excavation for structures shall be the payment in full for carrying
out the required operations including full compensation for.
i)
ii)
Setting out.
iii)
iv)
v)
Removal of all logs, stumps, grubs and other deleterious matter and
obstructions for placing the foundations including trimming of bottom
of excavation.
vi)
vii)
ix)
x)
xi)
Disposal of surplus materials, with all leads, lifts and delifts the
excavated material
xii)
3.1.37.
a)
PUBLIC SAFETY:
3.1.38.
a)
b)
3.1.39.
a)
SIDE DRAINS:
3.2
EMBANKMENT CONSTRUCTION
3.2.1 SCOPE:
Site clearance, stripping and formation of embankment of
homogeneous section/Zonal section viz., casing zone/hearting zone with the
useful excavated soils and balance soils of approved quality from the borrow
area including the cost of soil, if any, sampling, testing and pre-wetting of
soils at source of excavation and conveyance of Soil and extra soils required
for shrinkage including swell factor with all leads, lifts, delifts, laying on bank,
spreading breaking clods, sectioning, extra watering and consolidation
including benching of Old embankment Slopes, joining with the new
embankment formation, trimming of side slopes, formation and removal of
ramps, formation of Dowel banks etc., as per drawing and as directed by the
Engineer in charge to complete the finished item of work.
3.2.2. EMBANKMENT CONSTRUCTION
a)
b)
Embankment shall be built to the height, top width and side slopes as
shown on the drawings. All the edges of the embankment shall be
neatly aligned symmetrical to the central line. They shall be absolutely
straight in all reaches except at bends. At bends they shall be
smoothly curved.
c)
3.2.4.
a)
b)
Suitable excavated materials available from the cut off trenches, canal
cutting, extra cutting for seating to lining. Foundation excavation for
structures, approach and tail channels for structures, vagu diversions,
removal of ramps obstruction removal on the upstream and down
stream of surplus weirs and excavation in surplus course and any such
excavations, shall be used for construction of adjacent embankments
and also embankments of deficit reaches.
d)
e)
The soils and morum excavated and useful for construction of the
embankment shall be classified by the Superintending Engineer /
Executive Engineer as impervious and Semi-Pervious based on
Laboratory Test results. They shall be utilised on the embankment
work.
b)
c)
d)
e)
f)
Soil foundation.
The ground surface under embankment and area of bed filling
wherever necessary (except rock surfaces) shall be loosened or
g)
Rock foundation
The treatment of the rock surface under the embankment shall be
done so as to ensure tight bond between embankment and the
foundation. This shall be done by the following procedure.
i)
ii)
3.2.8. COMPACTION
a)
General
The earth compacting equipment specified in appendix-C of I.S. 47011982 shall be used for compacting the soils shown against them. The
compacting equipment shall conform to the relevant I.S. Specification.
While the I.S. Specifications specify the compacting. It is contended
that the use of improved compaction equipment for embankment
construction shall be encouraged as may be most suited to the site
conditions and the programme of construction. The methods of
compaction shall conform to clause 7.2., 7.2.2 and 7.2.3 of I.S. 4701 1982.
3.2.7. COHESIVE MATERIALS.
a.
tests shall be made after rolling and dry density attained shall be not
less than 98% of the maximum dry density (standard proctor) as
obtained in the laboratory for the type of materials used. The density
achieved shall not normally be less than the designed density. The dry
density of soil in field shall be determined in accordance with I.S. 2720
(Part - XXVIII) - 1974 or I.S. 2720 (Part. XXIX) - 1975.
b.
c.
d.
e.
f.
3.2.8 .
COHESIONLESS MATERIALS
a.
b.
b.
Where the natural ground surface is above the maximum water but
below the top of the embankment, the embankment shall be built in
layers not exceeding 15 cm. in thickness and to the full width of
embankment. Each layer shall be commenced from the edge farthest
from excavation. It shall be compacted with Two tons roller.
c.
3.2.10.
a.
b.
c.
lines of the finished embankment slopes shall have not less than
specified density.
(ii) Later the extra width shall be neatly trimmed and the trimmed
material shall be permitted for re-use in embankment at higher
elevations.
(iii) No payment shall be made for providing or removal of the extra
section. Removal of extra section in the embankment shall be deemed
to have been included in the item of compaction.
d.
e.
No fresh layer shall be laid until the previous layer is properly watered
and compacted as per requirement. The work of spreading and
compaction shall be so adjusted as not to interfere with each other
and in such a way that neither of the operations is held up because of
non-completion of the rolling and watering. The surface of the banking
shall at all times of construction be maintained true to required cross
section. If the surface of any compacted layer of earth fill is too dry or
too smooth it shall be moistened and scarified to provide a
satisfactory bonding surface before the succeeding layer is placed. All
the rollers used on any one layer of fill shall be of the same type and
same weight.
f.
The contractor shall ensure that only approved soils are used for
construction of embankment.
g.
For proper bond of the embankment done in the previous season with
the new embankment, the work shall be carried out as detailed
below :
(i) In case of the old bank to be extended horizontally. It shall be cut to
a slope not steeper than 1 in 4 and the surface so prepared shall be
scarified and made loose at least for a depth of 15 Cm. Necessary
watering shall be done and the earth surface shall be thus prepared to
receive the new embankments. The soils shall be laid in layers and
compacted to the required degree of compaction to have a proper
bond with the old one.
(ii)
If the old bank is to be raised vertically, vegetation shall be
cleared followed by scarifying, watering and placing of the new earth
layer as specified above.
(iii) The surface which are damaged due to rain shall be made good
by filling with proper soil duly compacted by tampers. A cross slope
away from the centre of canal of about 1 in 80 shall be maintained
throughout the rainy season to ensure proper drainage in the event of
occasional rainfall. No extra or separate payment shall be made for
these items of work.
h.
Settlement allowance:
(i) Care shall be exercised that all large clods are broken and no clod
bigger than say 8 cm. rock, are buried in the banks.
(ii)
Homogenous Section
Zonal Embankments.
Moisture Content :
The initial moisture content of the material shall be determined at
the source of supply (all excavations including from the borrow
areas) in field laboratory test. Prior to and during compaction
operations, the embankment shall have optimum moisture content
required for the purpose of compaction and this moisture content
shall be fairly uniform throughout the layer as per clause 6.6 of I.S.
4701 - 1982.
In so far as practicable the moistening of the material shall be
performed at the site of excavation but such moistening shall be
supplement as required by sprinkling water at the site of
compaction, if necessarily. Flooding shall not be permitted under
any circumstances. Sprinkling of water shall be done either through
a proper sprinkler tanker or using proper spray nozzles. Sprinkling
straight from the water hose shall not be allowed.
b)
c)
d)
3.2.12.
a)
b)
c)
d)
Special precautions shall also be taken while rolling the spread soil
near structures, conduits, sluice barrels, filters, rock toes at the
junctions of bank connections with the structures, using hand or
power tampers. It is essential that the compaction of filling should
be carried out in such a manner as to avoid an unbalanced thrust on
walls etc., which might displace or damage it. The equipment shall
be provided with suitably shaped heads to obtain the required
density.
The quantities between the levels taken after stripping and cross
sectional levels taken after construction of consolidated embankments with
the available useful excavation soils and with the soils obtained from Borrow
areas within the pay lines shall be worked out excluding rock toes and filters.
It shall be clearly understood that construction of embankments to extra
widths and extra height formed for shrinkage allowance as specified in
preceding paras will not include for payment.
3.2.15. INTERMEDIATE PAYMENT:
1)
level
may
be
taken
for
2)
3)
The payment shall be made for ten cubic meter of finished item of
work at the rate quoted in the Schedule "A" for the item of forming
embankment with excavated soils and the balance with Barrow Soils
& the rate shall include.
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
Key trench shall be back filled with impervious material of the same
specifications and in the same manner, as for the impervious
hearting zone of the embankment of the canal. The impervious soil
shall be placed in continuous and approximately horizontal layers
not more than 25 Cm. (loose) and compacted by 8 to 10 Tonne
Power roller under optimum moisture content.
b)
Rolling shall be done along the key trench and the roller shall be
taken close to the sides of the trench.
c)
d)
e)
f)
g)
a)
b)
c)
Each layer shall be compacted to not less than 90% dry density
(Proctor's density) at optimum moisture unless otherwise specified.
d)
e)
b)
b)
The contractor shall use only the suitable soils for formation of
embankments, out of the soils excavated under the provisions of
schedule 'A', if they are proved to be suitable, based on Laboratory
test results, and if they are with in the Economic lead. Otherwise the
contractor shall borrow the soils from the borrow area after test
The contractor shall be allowed to borrow the soils from the fore
shore areas of Reservoirs/tanks, upto the MWL contour and on the
sides of the Canal. Where the department is having provision to
borrow or exploit the soils. The Contractors can avail this provision.
If, for any reason, the contractor is not interested to borrow the
soils, from the above said areas the Contractor is free to borrow the
soils from any other places of his choice.
c)
The responsibility for arranging and obtaining the land for disposal
of spoil and the land for borrowing or exploitation in any other way
shall rest with the Contractor, who shall ensure smooth and
uninterrupted supply of materials/earth for the quantity required in
construction during the construction period.
d)
The Contractors quoted rates in schedule 'A' shall include all the
above considerations. No extra payment will be made for any of the
above considerations. The payment for respective schedule 'A' item
shall be at the quoted rate.
3.2.21.2.
BORROW PITS
1)
The borrow pits shall not normally be more than 25 M in length, and
10 M in width and 1 1/2M depth. A clear spacing of one metre
between each pit shall be left out. Each pit shall be clearly peg
marked and number tags of the pits shall be maintained.
2)
In the case of earth dams unless otherwise specified the borrow pits
shall not be located within a distance of 10 times the height of the
embankment on the upstream side and two times the height of the
embankment on the down-stream side.
3)
The depth of the pits shall be so regulated that their bottom does
not cut the hydraulic gradient line having a slope 4:1 from the top
edge of the embankment.
4)
In no case the pits shall be located within 5m from the toe of the
embankment. If there are old pits in the borrow area the new pits
shall be located one metre away from them.
5)
If the contractor excavated the pits near to the toe against to the
above clauses and the same is observed at any time during or after
the execution of work, the contractor has to fill the same pits with
the soils suitable for hearting zone of embankment and compact to
98% proctors density at the cost of contractor.
all organic matter from the borrow area. The cleared areas shall be
maintained free of vegetable growth during the progress of work.
b)
b)
c)
The cost for such works shall be deemed to have been included in
the rate in Schedule "A" for the item of compacting borrow quantity.
GENERAL
2.
a)
The type of material used for backfill, and the manner of depositing
the material, shall be subject to approval of the Engineer. As far as
practicable, backfill material shall be obtained from the excavation
for structures or from adjacent canal excavation or from the
excavation of the other ancillary works. Back filling shall be done
with approved material after the concrete or masonry is fully set.
b)
Backfill material shall not contain stone larger than 7.5cm size.
c)
d)
Backfill shall not be placed against retaining walls until the retaining
wall is cured adequately and is strong enough to take lateral
pressure of the backfill. Trimming of the sides of excavation against
which the backfill is to be laid shall be delayed until immediately
prior to backfilling and any excessive drying of the surface shall be
conditioned properly and made adequately moist to avoid potential
desiccation of the rock or partly compacted/consolidated materials.
e)
f)
If a haul road is built over a pipe, all back fill around and over the pie
shall be placed to a uniform surface and no humps or depressions
shall be permitted at the pipe crossing.
COMPACTION OF BACKFILL
a)
When compacting the soil against the steep rock, abutment walls of
masonry or concrete structures, the construction surface of
embankment shall be sloped away from the rock or masonry or
concrete structure leaving a minimum distance of 0.6 metre and at
an inclination of 3:1. Roller shall not be used close to structures as
structural damage is very likely more particularly when structures
have not been fully cured. The size and weight of equipment will
depend on nature of material, the height and load assumed in
design of structure. The backfill close to the structure upto the rolled
layer shall be compacted in suitable uniform layers, using
pneumatic tampers as appropriate to obtain dry density of at least
98% of Proctor density. The moisture content of the earth fill placed
against rock or the structure shall be on higher side of OMC by
about 2% or so, to allow it to be compacted into all irregularities of
the rock. Profuse watering shall be done to pervious materials (sand)
3.
STRUCTURES ON BACKFILL :
Where the original ground surface is below the base of the structure
or below the bottom of pipe, all fill required for the structure
foundation and all fill upto the bottom in the pipe shall be placed as
compacted embankment. The embankment over nature ground upto
pipe bottom and over the pipe shall be laid in accordance with
Clause 9.2.4., 9.2.5 and 9.2.6 IS. 783 of 1985. the compacted back
fill shall be placed in horizontal layers not exceeding 15cm. after
compaction. Heavy stones shall either be dropped on top of pipes
nor shall be allowed to roll down the side of the embankment
against the pipes.
In
accordance
with
I.S.2720
EMBANKMENT:
i)
ii)
BORROW AREA.
i)
ii)
iii) Different samples shall be taken for laboratory analysis in case the
soil is of different characteristics.
These inspection checks shall be supplemented by sampling the
materials at prescribed minimum intervals and by testing the samples in the
laboratory for gradation and moisture content.
DURING COMPACTION:
It is intended that the checks in operations during compaction shall
verify.
i)
ii)
iii) That no excessive rutting, waving, or scaling of the fill occurs during
compaction.
5
AFTER COMPACTION:
C)
COMPACTION:
i)
ii)
iii)
iv)
v)
vi)
The test data summary sheets and inspection reports be used to form
the basis of construction control report. Which should be issued from the site
at fort-nightly intervals, during constructing season. The report would contain
narrative accounts of the progress and problems of field constructions,
statistical analysis of test data and photographs of the fill operations.
ANNEXURE-1
Earth work Engineers daily Report:
Construction
..........................................................................................................................................
................................
date ......................................
shift
Weather .......................................................
.............................................
Inspector...........................................................................................................................
.................Following
Inspector...........................................................................................................................
...................................
Type
roller
equipment
used...................................................................................................................
weight
of roller...............................................................................................................
(A) EXCAVATION
1.
Type of Excavator.
2. Depth of Cut.
3. Type of Soil.
4. Borrow Pit Location.
5. Whether water added at borrow pit.
6. Percentage of moisture content.
(B) FILL CONDITION
1.
2.
3.
4.
5.
Location of fill.
Elevation
Whether water added at the fill.
Moisture condition before rolling.
Roller passes.
(C) TEST DATA
1.
(a)
(b)
2.
3.
4.
5.
6.
1.
2.
3.
4.
Serial Number.
Optimum moisture content percent.
Maximum dry density (Gr/CC)
Plasticity needle reading (Kg./Sq.Cm).
(D) COMPACTION EFFICIENCY
1.
b)
c)
d)
FILTERS:
II) SCOPE:
Formation of sand filters of specified thickness using the sand of
approved quality including cost and conveyance of sand sampling,
testing and laying with all leads, lifts, delifts and compaction to 70%
relative density including hire and operational charges of power
roller seigniorage charges and all other incidental and operational
charges necessary to complete the finished item of work for filter
blanket, horizontal and inclined filter drains, longitudinal and
transverse filters around rock toe etc., as per drawings and as
directed by the Engineer-in-charge.
3.2.29.2.
a)
i)
D. 15 base material
ii)
Co-efficient of Uniformity:
Cu=D.60
>6 for SW
D.10
and
CU=D.60
>4 For GW
D.10
Where
SW: Sand Well Graded and
GW: Aggregate well graded.
b)
c)
D.15 is the size at which 15% of the total soil particles are smaller,
the percentage being by weight, is being propped to be determined
by mechanical analysis. D.85 size is that at which 85% of the total
soil particles are smaller. As more than one filter layer is required,
e)
(f) The thickness of each filter layer shall be less than 150 mm.
3.2.29.3.
PLACING OF FILTER
(a) Filters shall be laid to the lines and grades and dimensions shown on
the drawings.
(b) The foundation shall be cleared and stripped in accordance with
specification 2.0 before laying the bottom layer of filter material.
(c) Filter material shall be laid in layers of 150mm adequately watered
and compacted by required number of passes of crawler type tractor
or any method approved by the Superintending Engineer to get dense
and stable filter.
(d) Care shall be taken ensure that materials of different layers do not
get mixed both at the time of placing and during compaction.
Extreme care shall be taken when placing materials to obtain fill free
lenses, layers and streaks of segregated materials.
(e) In case of horizontal filters after being compacted earth fill material
shall be laid over it in layers of 150mm and compacted as directed by
the Engineer-in-charge sheep foot roller or DRR shall not be used till
earth has been laid and compacted to a thickness of 600mm over the
filter blanket. However the construction of earth fill in the initial 600
mm thickness shall be subject to the same quality control regarding
moisture content and dry density as for the rest of the embankment.
(f) In case of inclined filter, the filter shall be raised along the adjoining
embankment layers and shall be properly compacted by suitable
means., In order to avoid contamination of filters with adjoining earth
fill material, the top of filter be kept slightly higher than the adjacent
embankment level and any contaminated portion shall be scrapped
and removed before adding the new layer.
3.2.29.4.
The Coarse aggregate filter shall be laid to the lines and grades and
dimensions shown on the drawings.
ii)
iii) In case of horizontal filters, after being compacted, earth fill materials
shall be laid over it in layers of 150mm and compacted as directed by
the Superintending Engineer/Executive engineer sheep foot roller of
DRR shall not be used till earth has been laid and compacted to a
thickness of 600mm. over the filter blanket.
However, the
construction of earth fill in the initial 600., thickness shall be subject
Rock fill shall consist of sound, durable and well grade broken rock
obtained from approved excavation of work and /or from quarries and
shall be approved prior to being transported to the areas of
deposition. The materials shall range in size from 75mm to 450mm.
However, no load shall contain more than, 10 percent by volume of
rock fragments smaller than 75mm in size. All brush roots, or other
perishable materials shall be removed from rock fill during the
spreading.
D) PLACING
i)
The rock fill shall be constructed, true to the lines and grades as
shown in the drawings.
ii)
The rock fill shall be placed and packed to obtain a suitable well
graded and free draining fill.
iii) The smaller rock fragments shall be placed adjacent to the filter of
embankment and large rock fragments near the outer edge of the fill.
iv) The rock fill shall be placed and roughly leveled in layers not greater
than one meter in thickness.
v)
The stones shall be properly hand packed and the interstices shall be
well filled with spalls and chip and tightly wedged to ensure firm
packing so as to have dense well graded fill with no larger voids and
cavities.
vi) Contamination of rock toe with finer material from any other zones
shall be avoided.
vii) Suitable outfall for draining out the seepage water collected in the
rock toe shall be provided depending upon the site conditions.
3.2.33.
PROTECTION
The contractor shall take all precautions necessary for the protection of
the work by diversion of stream local Surface drainage, rain water etc., if
these are likely to damage the work. Any damage to earthwork due to any
reason what so even shall be made good by the contractor at his cost till the
work is certified as completed and taken over by the, superintending
Engineer/Executive Engineer.
3.2.35.
3.3.
3.3.1
a)
b)
Explosive such as gelatin, detonators and fuse coils etc required for
the rock blasting are to be procured by the Contractor at his cost. It
shall be responsibility of the Contractor to store the explosives
purchased by him in accordance with the rules of the explosives act
and other rules framed by Government of India.
c)
______________________________________________________________________________
___________
Capacity
License No.
Validity
and date
period
______________________________________________________________________________
___________
______________________________________________________________________________
___________
d)
The Contractor shall acquaint himself with all the applicable laws and
regulations concerning storing, handling and the use of explosives.
All such laws, regulations and rules, as prevalent from time to time
shall be binding upon the Contractor.
c)
01 IS
4081-1986
02 IS
4668-1985
03 IS
6609-19
Method test for commercial blasting explosives
(part 1 to 5) and
accessories.
04 IS
7632-1975
Detonators
05 IS
5454-1986
06 IS
3764-1966
3.3.3. PERSONNEL
a)
b)
c)
The Contractor shall make sure that his supervisor workmen are fully
conversant with all the rules to be observed in storing, handling and
use of the explosives, It shall be assured that the supervisor in
charge, is thoroughly acquainted with all the details of handling and
the blasting operations.
For the transport of the explosives and detonators between the store
and the site, closed and strong container made of soft materials such
as timber, zinc, copper, leather shall be used.
b)
c)
The boxes and containers used shall be kept closed. Explosive shall
be stored and used chronologically, earlier received shall be used
first. A make up house shall be provided at each working place in
which cartridges will be made up by competent and licensed men as
required for the work. The make up house shall be separated from
other buildings. Only electric storage battery lamps shall be used in
this house.
d)
The primers shall not be prepared near open places or fire. The work
of preparation of primers shall always be entrusted to the same
The work of charging of holes shall not commence before all the
drilling work at the site is completed and the Contractors supervisor
shall satisfy himself to that effect by actual inspection, while charging,
open lamps shall be kept way, For charging with powered explosives,
a naked flame shall not be allowed only wooden tamping rods,
without any kind of metal on the rod shall be allowed to be used. The
tamping rods shall have cylindrical ends. Borehole must be of such
size that the cartridges can easily pass down them; they shall not
however be too big.
b)
Only one cartridge shall be inserted at a time and gently pressed into
the hole with the tamping rods. The sand, clay or other tamping
materials used for filling the holes completely shall not be tamped to
hard.
3.3.8. BLASTING:
a)
Blasting shall be carried during the fixed hours of the day which shall
have the approval of the Engineer, the hours once fixed shall not be
altered without prior written approval of the Engineer.
b)
c)
d)
All the rods and footpaths leading to the blasting areas shall be
watched.
e)
f)
The Contractors supervisor shall watch the required time for the
firing of the fuses and shall see that all the workmen are under safe
shelters in good time.
a)
b)
The detonators shall be checked before use. For blast in series, only
detonators of the same manufacture and of the same group of
electrical resistance shall be used. Such of the electrical lines as
could constitute danger for work of charging shall be removed from
the site. The firing cables shall have a proper, insulating cover so as
to avoid short-circuiting due to contact with water, metallic parts of
rock.
c)
3.3.10.
a)
After the blast, the Contractors supervisor must carefully inspect the
work and satisfy himself that all the charges have exploded. After the
blast has taken place in the under-ground works, workmen shall not
be allowed to go to the place till the toxic gases are evacuated from
the face.
b)
c)
None of the drillers are to work near this hole until one of the two
following operations have been carried out by the supervisor.
Either (i) the supervisor should very carefully (when the tamping is of
damp clay) extract the tamping with a wooden scraper or jet of water or
compressed air using pipe of soft materials) and withdraw the fuse with the
primer and detonator attached after which a fresh primer and detonator with
fuse should be placed in this hole and fired out or (ii) the hole may be cleared
of 300mm, of capping and the direction and then be ascertained by placing a
stick in the hole. Another hole may be drilled at least 225 mm away, and
parallel to it. This hole should then be charged and fired. The balance of the
cartridge and detonators found in the muck shall be removed.
d)
Before leaving his work, the contractors supervisor should inform the
supervisor of the relieving shift of any case of misfires and should
point out the position with red cross denoting the same, also stating
what action if any, he has taken in the matter, A register of misfires
and their location and how they were dealt with shall be maintained
by the Contractor.
e)
f)
The names of the day and night shift supervisors of the contractor
must be noted daily in the contractors Office. If misfire has been
found to be due to a defective detonator. Or dynamite, the whole
quantity of box from which the defective articles was taken must be
returned to the contractors office for inspection, and shall be
disposed off.
g)
h)
The contractor should produce the firers license and furnish the
particulars in the following statement.
______________________________________________________________________________
_____________
SL
Name
No.of firers
Validity
No.
period
______________________________________________________________________________
______________
i)
SL.No
IS.Number
1 (a) 456-1978
1 (b) 457-1963
Short title
Code of practice for plain and reinforced concrete.
Code of practice for plain and reinforced concrete for
dams and mass concrete.
2.
2386-1977
3.
516-1959
4.
4925-1968
5.
1791-1985
6.
650-1991
7.
2330-1986
8.
2722-1964
9.
4634-1991
Batch
type
performance.
10.
5515-1983
11.
5640-1970
12.
5816-1970
13.
5889-1970
14.
5892-1970
Specifications
agitators.
15.
6461-1972&
1973
Glossary of terms relating to cement
aggregate, materials etc. (Part. 1-12)
concrete
for
concrete
mixers-methods
transit
mixers
test
and
concrete
16.
6925-1973
17.
1838
18.
7320-1974
19.
7861-1975&
1981
Code of practice for extreme weather concreting.
20.
8142-1976
21.
9013-1978
Method
of
making
curing
and
determining
compressive strength of accelerated cured concrete
test specimen.
22.
9284-1979
23.
1200-1974
(Part 2)
5751-1984
24.
25.
3085-1965
26.
3873-1978
27.
2506-1985
28.
3363-1965
29.
1199-1959
30.
3370-1965 &
1967
Code of practice for concrete structures for the
storage of liquids
(Part 1 to 4)
31.
2505-1980
32.
3558-1983
33.
4656-1968
34.
8989-1978
35.
4990-1981
36.
6505-1985
37.
3696-1991
4.2.0.
GENERAL:
a.
b.
c.
4.3.0.
SCOPE:
The specifications covers the requirements of plain and reinforced
concrete for various structures and comprised of:
1.
2.
3.
4.
5.
6.
7.
8.
Transporting, the concrete with all leads, lifts, delifts either by labour
or by placing in position, vibrating, compacting, finishing and curing
of the cement concrete, plain or reinforced and performing all other
operations necessary and ancillary thereto, compete for finished
item of works as specified in Schedule A for M 7.5, M10, .M15, M20
and above concrete mixes in any structural portion or its
components as per the drawings and as directed by the Engineer in
charge of the work.
9.
4.4.1.
PLAIN C.C.
CEMENT
W.C.R
(Kg/cum.)
(kq/cum.)
W.C.R
R.C.C
CEMENT
1.
Structural component
completely protected
220
0.70
250
Structural component
saturated with water
buried concrete in soil and
continuously under water
250
0.60
290
Structural component
exposed to sea water and
310
0.50
360
0.65
against weather or
aggressive conditions
2.
0.55
3.
0.45
subject to heavy corrosive fumes
4.
Structural component
of bridges
360
0.45
400
Structural component
of bridges (pre-stressed)
400
150-230
355
7.
350
8.
250
0.6
0.45
5.
0.40
6.
In no case the cement content in a concrete mix for all case should
not exceed 540 kg/cum.
4.4.2.
COMPONENT
M.S.A
i)
ii)
Bridge works:
mm
20
1.
20
2.
40
3.
mm
mm
40
mm
4.
20
PSC work
20
mm
5.
mm
iii) Foundations of structure and
retaining walls (Mass concrete)
40
mm
iv) Canal lining
1.
40
2.
Lining of thickness 75 mm
20
v.
25
mm
mm
mm
vi. Dams, spillways and Mass concrete structures 75, 150 - 230 mm
NOTE: 1)
a.
b.
c.
d.
2)
a.
b.
4.4.3.
SPECIFIED
10
15
20
25
30
40
45
50
4.5.2.
CHARACTERISTIC
10
15
20
25
30
40
45
50
NOMINAL MIX CONCRETE :
The following proportions shall be adopted for the nominal mix concrete.
GRADE OF
TOTAL
QUANTITY
OF
MAXIMUM QUANTITY
DRY
AGGREGATE
CONCRETE
PER 50 KGS
PER 50 KG OF CEMENT
OF WATER
OF
CEMENT
M 5
Litres
800 KG
60
M 7.5
Litres
625 KG
45
M 10
Litres
840 KG
34
M 15
Litres
350 kg
32
M 20
Litres
250 kg
30
NOTE:
a)
b)
d)
e)
f)
4.6.0.
PRODUCTION OF CONCRETE:
4.6.1.
BATCHING OF MATERIALS:
In case uniformity in the materials used for concrete making has been
established over a period of time, the proportioning may be done by volume
batching, provided periodic checks are made on weight/volume relationships
of materials.
Where weigh batching is not practicable, the quantities of fine coarse
aggregate (not cement) may be determined by volume.
If fine aggregate (sand) is moist and volume batching is adopted,
allowance shall be made for bulking in accordance with IS: 2386 (part. III) 1963-Methods of test for aggregates for concrete.
The amount of the added water to concrete shall be adjusted to
compensate for any observed variations in the moisture contents determined
by the above tests for both design and nominal mix of concrete making for
weigh and volume batching.
4.6.2.
MIXING:
WORKABILITY
.................25 mm
.....................25 mm
2.
3.
4.
5.
....................40-50 mm
..................50-75
..............75-125 mm
..........100 - 200 mm
FORM WORK:
4.7.1
General
The form work shall conform to the shape, lines and dimensions as
shown on the plans and be so constructed as to remain sufficient rigid during
the placing and compaction of the concrete and shall be sufficiently water
tight to prevent loss of cement slurry from the concrete. The form work shall
be made leak proof by providing kraft paper.
Form work or centering shall be constructed of steel or timber and
adequately designed to support the full weight of wet concrete without
deflection and retain its form during laying, ramming, vibrating and setting of
concrete. Timber uses shall be properly seasoned to avoid deformation when
wetted.
All rubbish, particularly chippings, shavings and sawdust, shall be
removed from the interiors of the forms before the concrete is placed and the
form work in contact with the concrete shall be cleaned and thoroughly
wetted (in case of timber) or treated by coating with a constraining mineral
oil or other approved material. Care shall be taken that such approved
composition is kept out of contact with the reinforcement.
The forms shall be removed after expire of the following periods in the
normal circumstances and when O.P.C is used for making concrete.
i)
ii)
................
iii)
................
iv)
1)
................
2)
................
V)
1)
................
2)
................
(b).
COVER REQUIREMENTS :
At each end of reinforcing bar not less than 25 mm nor less than
twice the diameter of such rod or bar.
b)
c)
For longitudinal reinforcing bar in a beam, not less than 25mm, not
less than the diameter of such bar.
d)
e)
For footing, resting directly on soil the minimum clear cover shall be
50 mm and in the case of concrete in contact with earth faces
contaminated with chemicals, it shall be 75mm.
f)
g)
...........
Minimum 25 mm or
which
the
cover
as
with
respect
to
structural member.
All reinforcement shall be placed and maintained in position as shown
in the drawings as directed by the Engineer- in - charge adopting chairs and
cover blocks with in the tolerance limits specified in clause : 11.3 of IS : 4561978.
The bars shall be supported / held in position by suitable means until
concrete is poured. Any one of the following devices shall be used for the
purpose. (i) providing steel reinforcement supports/spacers, (ii) providing of
mortar supports/spacers and (iii) providing plastic supports/ spacers.
The steel support/spacers shall be used for slabs except in case of form
finished surfaces. The mortar units can be used for slabs, beams and
columns as well as plastered or form finished surfaces.
Use of pebbles, broken stone, metal pipe, brick, wooden blocks etc., as
devices for positioning reinforcement will not be permitted.
Suitable shape and size of cement mortar cover block with proportion
of (1:1) shall be used on the work as per the drawing and as directed and
approved by the Engineer in charge.
4.7.3.
FORM WORK
FINISHING:
The following specifications shall apply for the various types of formed
surfaces:4.7.3.1. GENERAL:
The classes of finish for formed concrete surfaces shall be designed by
the use of symbol F1,F2,F3,F4 and shall be as described below.
FINISH F1: shall apply to formed surface upon which or against which
backfill of concrete is to replaced. The surface requires no treatment after
removal of forms except removal and repairs of defective concrete.
Correction of surface irregularities shall be done only for depressions which
when measured exceed 25 mm.
FINISH F2: shall apply to all permanently exposed formed surfaces of which
finishes F3 and F4 are not specified. Surfaces for which finish F2 specified
will read no filling of pits or Sack rub and no grinding other than that needed
for repair of surface. Imperfect surface, irregularities, measured shall not
exceed 6 mm for abrupt irregularities and 12 mm for gradual irregularities.
FINISH F3: Immediately after removal of forms from surfaces designated for
F3 finish, all required patching, clean up and correction of major
imperfections shall be completed and the surfaces shall be given a rubbed
mortar finish as described below. The surfaces shall be thoroughly wetted
and permitted to approach surface drying before starting, The surfaces shall
be finished in areas sufficiently large and shall prevent complete drying of
any part before the sack-rubbing is completed for that area. The mortar used
for the sack-rubbing shall consist of one part of cement to two parts, by
volume, of sand passing on IS sieve too and enough water so that the
consistency of the mortar is that of thick cream. The mortar shall be rubbed
thoroughly over the area with clean brush be a sponge rubber float,
completely filling all pits and irregularities.
4.7.3.2. UNFORMED SURFACES
The classes of finish for unformed concrete surfaces are designed by
the symbols U1 U2 and U3. Inter for surfaces, shall be stopped for drainage
where shown on the drawings. Surfaces, which will be exposed to, the
whether and which would normally believe, shall be slopped for drainage.
Unless the one of other slopes or level surfaces specifies narrow surface such
as tops of walls and curbs, shall be slopped approximately at 3.0 cm per
meter. Border surfaces such as walls, roadway platforms and decks, shall be
approximately at 1.5 cm per meter.
4.7.3.3. Classes of finish to be applied shall be as detailed below.
FINISH U1: (Screeded Finish) shall apply to unformed surfaces that are to be
covered by back fill or by concert, and surfaces of sub-floors which will be
covered by concrete floor topping, Finish KU1 is also used as the first stage
for finishers U2 and U3. Finishing operation shall consist of sufficient leveling
and screening to produce even and uniform surfaces. Surface irregularities,
measured shall not exceed 10 mm.
4.7.3.4. FINISH U2 (Floated finish) shall apply to uniformed surfaces that
are to be covered by back filled by concrete or unformed surfaces
for which finishes U1 and U3 are not specified, and shall include
floors of sumps, tops of walls. Parking areas, parapet, walls, surface
of gutters, sidewalls and entrance slabs. Finish U2 is also used as
the second stage for finish U3. Floating may be per formed by use
of hand or power driven equipment. Floating shall be started as
soon as the screeded surface has stiffened sufficiently, and shall be
the minimum necessary to produce a surface that is free from
screed marks and is uniform in texture. Finish U3 is to be applied,
floating shall be continued until a small amount of mortar
irregularities, shall not exceed 6 mm joints and edges of gutters,
sidewalls, entrance slabs, another joints and edges shall be tooled
where necessary, dry ingredients of the mortar, in the same
proportions shall be rubbed over the area. After the mortar has
stiffened adequately to prevent but before it hardened the excess
mortars shall be removed by rubbing with clean bur lap. After the
final scrubbing a light fog spraying shall be applied to the coated
surface, the moisture thus applied being just sufficient to damp the
surface with out all owing water to run down the face of the walls.
Spillway crest
Spillway stilling basin
Spillway pipe
Spillway bridge road slab
Elevator tower exterior face
-do- Interior
Around sluice
Around galleries, audits, sump well
Face concrete in retaining wall
divide wall, or retaining wall (water side).
F1
F3
F3
F2
F4
F2
F3
F2
F3
or
or
or
or
U2
U2
U3
U2
or
or
or
or
U2
U2
U2
U2
a)
b)
12 mm
18 mm
Variation from the plumb from the specified batter or from the curved
surface of all structures, including the lines and surfaces of columns
walls, piers and vertical joint grooves.
In 3 meters
In 6 meters
In 12 meters or more
12 mm
20 mm
30 mm
Variation from level from the grades indicated on the drawings in slabs.
beams, soffits and horizontal joint grooves and visible arises.
In 3 meters
In 10 meters
6 mm
12 mm
f)
g)
For sill and side walls for gate and similar water tight joints variation from
the plumb and level should not be greater than 3 mm, in 3 mts.
h)
i)
ii)
6 mm
12 mm
greater than 15 cm
less than 15 cm.
GENERAL REQUIREMENTS.
4.7.3.8 Forms shall be used wherever necessary to confine the concrete,
shape it to the required lines, or to ensure against contamination of the
concrete by materials caving or Sloughing from adjacent excavations or other
features of the work. All exposed concrete surfaces having slopes of 1 to 1 or
steeper shall be formed where the side slopes of walls of an excavation for
concrete structure can be trimmed to the prescribed lines without Sloughing,
the Sloughing, the use of forms, will not be required. Forms shall have
sufficient strength to with stand the pressure resulting from placement and
vibration of the concrete and shall be maintained rigidly in correct position.
Forms shall be tight to prevent loss of mortar from the concrete.
Steel sheathing or
lining
Any grade
Steel
Formed surface
F1
permitted
sheathing
F2
permitted
Steel
sheathing
Steel sheathing
permitted
Sheathing is specifically required
F4
not permitted.
F5
not permitted
Steel sheathing
Steel sheathing
permitted.
NOTE:
"Steel sheathing" denoted steel sheets not supported by backing of
wooden boards. "Steel lining" denotes then steel sheets supported by
backing of wooden boards.
4.7.3.11. Absorptive form lining: Absorptive form lining, where directed
to be used, shall be of the type and quality approved by the Executive
Engineer. The form lining shall be highly absorptive to air and water and
through its absorptive capacity able to eliminate voids, pits and other
common effects from the concrete surface. The lining shall be readily
removable from the concrete without damage to the surface. It shall produce
dense concrete surface of uniform and satisfactory texture and colour. The
lining itself and treatment employed in its manufacture shall not discolor the
concrete nor interfere with normal chemical reaction of the cement. The
backing to which absorptive lining is attached shall be sufficiently smooth,
even and free from cracks, knot holes, and other imperfections to avoid
unevenness in the finished surface. The lining shall be in sheers of uniform
length and width. Location and direction of the joints shall be approved by the
Executive Engineer. The joints between sheets shall be fitted smoothly and
accurate and patching shall be avoided. Cutting and trimming shall be true
and shall be done with tools well adopted to this work so that sharp, smooth,
square edges are produced. The lining shall be attached to the forms in such
a manner that it is held securely and smoothly in place. Nails or tacks, if
used, shall be spaced in uniform pattern and shall be driven flush. Dents and
hammer marks in the surface of the lining shall be avoided. After then lining
has been attached in the form. The joint shall be rubbed with a smooth tool to
press down any projecting fibers. Where absorptive form lining is in contact
with the face of previous pour, care shall be used in setting and sufficient
pressure shall be applied in tightening form anchors to produce continuity
and evenness at the face, free from offset, and streaks, and other
irregularities. The lining shall be kept dry and shall not be reused.
4.8.0. TRANSPORTATION OF CONCRETE:
Concrete shall be transported from the mixer to the formwork as
rapidly as possible by methods grooved by the Engineer-in-charge, which will
prevent the separation or loss of any of the ingredients and maintaining the
required workability.
The concrete shall be transported, laid and compacted in its final
position with in 30 minutes of its discharge from the mixer unless carried by
in properly designed agitators.
Where the time of haul exceeds 20 minutes, mixed concrete shall be
transported in a suitable agitators or transit mixer as directed and approved
by the Engineer-in-charge.
4.9.0. PLACING OF CONCRETE:
All surfaces upon or against which concrete is to be laid shall be
prepared in accordance with the drawings.
No concrete shall be placed until all form works; installation of parts to
be embedded and preparation of surface involved in the placing have been
approved by the Engineer-in-charge. No concrete shall be placed in water
except when specifically so permitted. All surfaces of forms and embedded
materials have become incrusted with dried mortar from previously placed
shall be cleaned before surrounding of adjacent concrete is placed.
If concreting is not started within 24 hours of the approval being given,
it shall have to be obtained again. The contractor shall notify the Engineer at
least 24 hours before batching begins for placement of concrete.
All absorptive surfaces against which concrete is to be laid shall be
moistened thoroughly so that moisture will not be method of placing should
be such as to preclude segregation with drawn from the freshly placed
concrete. The concrete shall be deposited as nearly as possible in its final
position and compacted before setting commences and should not be
subsequently disturbed.
Care should be taken to avoid displacement of reinforcement or
movement of formwork.
Placing is allowed with a limitation of free fall of 1.5 meter.
All concrete shall be placed in continuous and approximate horizontally
layers, the thickness of which shall not more than 450mm for mass concrete
and 150mm for RCC and plain cement concrete works)
Concrete shall not be placed faster than the placing crew can compact it
properly.
On sloping surfaces, concrete should be placed at the lower end of the
slope first, progressing upwards, and thereby increasing natural compaction
of the concrete.
After surfaces have been prepared satisfactory, all surfaces, rock, old
concrete and old masonry shall be coated with a thin layer of cement slurry
(comprising 1 cement to 2/3 water by volume) and covered with a layer of
mortar not less than 12mm, not more than 20 mm thick. The mortar shall be
similar to the mortar in the regular concrete mixture having the same cement
sand ratio of the mortar used in concrete unless otherwise directed. The
cement slurry and mortar shall be spread uniformly and shall be worked
thoroughly, into all regulates of the surface. Concrete shall be placed
immediately up on the fresh concrete.
4.10.0. COMPACTION OF CONCRETE:
4.10.1
GENERAL:
Compaction should preferably be achieved by mechanical vibration.
But in isolated locations, it can also be achieved if approved by the Engineerin-charge by manual methods, namely, Roding, spading and tamping. The
mechanical compaction is achieved by vibration. The methods like spinning
mechanical tamping and use of shock are restricted to special situations as
approved by the Engineer.
Under vibration is harmful should be avoided. Even vibration
may cause
i.
IMMERSION VIBRATORS:
b.
Concrete vibrators of screed board type as per IS: 2506 - 1964 shall be
used for compaction of concrete beds, floors, pavements and then slabs,
Where the area to be compacted is large or the thickness is too small (less
than 200 mm) to allow the use of immersion vibration.
Operational frequency: 3500 per minute (under no load state)
4.10.4. FORMWORK VIBRATORS:
Formwork vibrators as per IS: 4656 - 1968 shall be used for compaction
of concrete, precast concrete moulds, gullies and deep post-tensioned
beams. They shall be used for compaction of in situ concrete is small and
narrow sections of very, heavily reinforced section where immersion of
vibrators cannot be used. There are of two types
a. The fixed on clamped type, and
b. The manual type.
Operational frequency: 2800 per minute (Under no load state)
4.10.5. VIBRATING TABLE:
Vibrating table as per IS: 2514 - 1963 shall be used for compaction of
concrete in moulds for the manufacture of precast products and structural
elements. They compact concrete through rapidly alternating horizontal,
vertical or circular vibrations, which are transmitted to moulds filled with
concrete and placed or clamped on the tabletop.
Operational frequency: 3000 to 6000 cycles per minute.
Immediately after compaction concrete shall be protected against
harmful effects of weather, including rain, running water, shocks, vibration.,
traffic, rapid temperature changes and drying out.
4.11.0. CONSTRUCTION
BLASTING:
JOINTS
GREEN
CUTTING
AND
SAND
wetted. For vertical joints neat cement slurry shall be applied on the surface
before it is dry. For horizontal joints the surface shall be covered with a layer
of mortar about 10 to 15 mm thick compound of cement and sand in the
same ration as the cement and sand in concrete mix. This cement slurry or
mortar shall be freshly mixed and applied immediately before placing of the
concrete.
Where the concrete has not full hardened, all laitance shall be removed
by scrubbing the wet surface with wire or bristle brushes, care being taken to
avoid dislodgement of particles of aggregate. The surface shall be thoroughly
wetted and all free water removed. The surface shall be then be coated with
neat cement slurry. On this surface, layer of concrete not exceeding 150 mm
in thickness shall first be placed and shall be well rammed against old work,
particular attention shall be paid to corners and close spots; work thereafter
shall proceed in the normal way.
4.11.2. GREEN CUTTING:
The surface of the respective lift shall be thoroughly green cut with an
air water jet. Green cutting is usually done 8 to 12 hours after the top surface
of a concrete lift had been completed and sufficiently hardened. The actual
time for taking up the green cutting operation shall depend upon the
following factors.
a.
b.
Atmospheric temperature;
c.
d.
Slump.
The air water jet will remove the thin surface film of laitance and grout
to expose clean surface.
Green cutting, if done at the proper time, shall yield very good results.
When started too early, it shall result in over cutting and removing too much
mortar. It is also liable to loosen the aggregate particles and leaving too poor
a surface to bind the fresh concrete. On the other hand, if green cutting were
delayed too long, the cutting action of the air and water jet would be
ineffective for proper removal of laitance. It, therefore, requires much greater
care and judgment for proper use at proper time.
Skill of Jet Operator: Besides determining the proper time for initiating
green cutting, the process will require constant attention on the part of the
air water jet operator. By correct manipulation of the high velocity air-water
get, a trained operator can ensure the removal of the thin surface film of
laitance and grout effectively and at the same time, leaving, the aggregate
stones, already embedded in the mortar, undisturbed.
Proper Air-water Gun: In addition to the skill of the jet operator, a
proper air water gun is also a vital requirement for effective green-cutting,
the issuing nozzle must be about 460 mm (18 inches) long to ensure the
requisite cutting force close to the concrete surface.
Quantum of Compressed air and Water: For effective green cutting, it is
essential that the air pressure should be around 6.33 to 7.03 Kg/Cm 2. It
should not be allowed to fall below 6.33 kg/cm 2. The water pressure, of
course, should be sufficient to bring the water into effective influence of the
air pressure. As an approximate estimate, the quantity of compressed air
required by the green-cutting gun is 2 cubic meters per minute and the
quantity of water is 60 gallons (273 Liters) per minute.
An important aspect to be taken note of is that green cutting as an
exclusive operation shall be fully useful only if the next lift of concrete is
placed within 3 to 4 days (or a maximum of 5 days) of the placement of the
previous lift. If there be a delay in concrete placement beyond this period, the
laitance will come up to the concrete surface again at some places. Removal
of such laitance shall then be not possible by the ordinary green cutting
operation alone. Light sand blasting of even the green-cut lifts shall have to
be resorted to. However, if there is excessive delay in concrete placement, it
will require either "Wet sand blasting" or the application of high pressure
"Water blaster" to remove the laitance for effective binding with the fresh
concrete. The effect to achieve this will be considerably less if green cutting
has already been done.
4.11.3. SAND BLASTING:
Sand blasting is the process of roughening and cleaning the surface of
old and set concrete by means of coarse sand and air applied under pressure
of 6.33 to 7.03 KG/CM 2 through a nozzle, so as to erode the laitance and grout
from the old concretes. Sand blasting of rock is also done so that concrete
may be placed on or against a clean surface of rock as required according to
specifications.
There are two types of sand blasting, namely "Wet sand blasting" and"
dry sand blasting". In wet blasting water is also used along with sand and air
under pressure, while in the later, only sand and air under pressure are used.
Normally the concrete and rock surface etc., are wet sand blasted to keep
down the dust.
The percentage of different sizes of sand particles for efficient sand
blasting shall be as follows:
SIZE
PERCENTAGE
26
16
30
30
23
50
21
High pressure Water Blasters Green cutting is far cheaper than sand
blasting. Proper quality sand (known as sand-blast sand) is most expensive
item and special efforts are needed to arrange such sand. High-pressure
water blaster offers a breakable alternative to sand blasting.
Summary: Green-cutting offers the most economical methodology in the
preparation of good construction joints. It has, however, to be initiated at the
proper time and with a proper air-water gun to yield the best results. It is far
cheaper than sand blasting. If a delay of more than 3 to 5 days is anticipated
in placing the concrete over the previous lift, the concrete surface of the lift
should be properly "green cut" and thereafter (say one day prior to
placement of concrete) it should be light sand blasted or water blasted in
order to remove the "re-appeared" laitance.
4.11.4. OTHER REQUIREMENTS OF CONCRETE CONSTRUCTION:
4.11.4.1
All Concrete construction shall confirm to the permissible tolerances
and technical provisions as described in the section. All structures shall be
built in a workman-like manner, to the lines, grades and dimensions shown in
the drawings or as prescribed by the Engineer. The location of all the
construction joints shall be subject to the approval of the Engineer. The
dimensions of each structure shown on the drawings shall be subject to such
change as may be found necessary by the Engineer to adopt the structure to
the conditions disclosed by the excavation.
4.11.4.2.
Concrete in various components of Bridges, under tunnels,
Aqueducts etc.
Expansion joints shall be constructed as shown on the drawings or as
directed. Pre-moulded bituminous fiber type expansion joint material shall be
constructed in the parapets as directed by the Engineer. Open joints or false
joints shall be constructed as shown on the drawings or as directed by the
Engineer. Preformed expansion joint filler shall be placed in the roadway and
sidewalls where shown on the drawings or as directed by the Engineer.
4.11.4.3.
CONCRETE IN BLOCKOUTS:
(a) Care shall be taken in placing the concrete in block outs in order to
ensure satisfactory bond with the concrete previously placed and to
secure complete contact with all metal work in the block outs. (b)
The roughening of the concrete surface performed by chipping or
sand blasting as approved by the Engineer and in such a manner as
not to loosen, crack or shatter any part of the concrete beyond the
roughened surface. The surface of the concrete shall then be
cleaned thoroughly of loose fragments, dirt and other objectionable
substances in order to ensure good mechanical bond between the
existing and new concrete. All concrete, which is not hard, dense
and durable, shall be removed to the depth required to the
satisfaction of the Engineer.
4.11.4.4.
EMBEDMENT IN CONCRETE:
.GENERAL:
ii.
At least one cube forming an item of the sample representing the lot
shall be taken from concrete of the same grade and mix proportions
cast any day.
b)
c)
d)
These test specimens shall be made from each sample for testing at
28 days. Additional cubes may be required for various purposes
such as to determine the strength of concrete at 7 days or for any
other purpose.
e)
The test strength of the sample shall be the average of the strength
of 3 cubes. The individual variation should not be more than 15%
of average.
f)
1
2
3
4 + one additional
sample
for
each
part there of.
Compressive
Strength
on 15 cm
Cubes,
Modules of Rupture
By Beam Test, Min
at 72+2h
at
(3)
N/mm2
1.2
1.5
1.7
(4)
N/mm2
1.7
2.1
2.4
days
(1)
M-10
M-15
M-20
Min,
at 7 days
(2)
N/mm2
7.0
10.0
13.5
-----(n-1)
Where,
delta = deviation of the individual test strength from the average
n = number of sample test results.
(c) When significant changes are made in the production of concrete
batches (for example changes in the materials used, mix design,
equipment or technical control) the standard deviation value shall
be separately calculated for such batches of concrete.
4.13.3.2
Where sufficient test results for a particular grade of concrete are not
available, the value of standard deviation given in the following table may be
assumed.
ASSUMED STANDARD DEVIATION
______________________________________________________________________________
________
Standard Deviation
Grade of concrete
For Different degree of Control in
N/mm2
______________________________________________________________________________
__________
Very good
Good
M 10
2.0
2.3
M 15
2.5
3.5
M 20
3.6
4.6
Fair
3.3
4.5
5.6
However, when adequate past records for a similar grade exist and
justify to the designed value of standard deviation different from that shown
in the above table, it shall be permissible to use that value.
4.13.3.3.
ACCEPTANCE CRITERIA:
2)
standard
deviation
No of samples
Concrete, which does not meet the strength requirements as specified
but has strength greater than that required may, at the discretion of the
designer, be accepted as being structurally adequate without further testing.
If the concrete is deemed not comply the structural adequacy, of the
parts affected shall be investigated and any consequential action as needed
shall be taken.
Concrete of each grade shall be assessed separately.
Concrete shall be assessed daily for compliance.
Concrete is liable to be rejected if it is porous or honeycombed; its placing has been
Interrupted without providing a proper construction joint (or)
been met. However, the hardened concrete may be accepted after
carrying out suitable measures to the satisfaction of the Engineer.
4.13.3.4: CORE AND LOAD TESTS:
Inspection: Immediately after stripping the formwork, all concrete shall be
carefully inspected and any defective work or small defects either removed or
make good before concrete has thoroughly hardened.
In case of doubt regarding the grade of concrete used, either due to
poor workmanship on based or results of cube strength tests, compressive
strength tests of concrete and/or load test may be carried out.
A)
CORE TEST:
The points from which cores are to be taken and the number of cores
required shall be at the discretion of the Engineer and shall be representative
of the whole of concrete concerned. In no case, however, shall fewer than
three cores be tested.
b)
Requirements of workmanship.
Compression strength:
Concrete is liable
rejected if it is
to
be
a) Porous or honey-combed,
(due
to
incorrect
mix
proportion
or
improper
compaction techniques
b) Its placing has been
interrupted without providing
proper construction joint.
c) The reinforcement has
been displaced beyond the
tolerance have not been.
d) If the core tests / load test
does not yield the results.
e) If the strength of the
concrete produced and tested
does not yield the strength
requirements of the code.
f) If the test results of the test
cubes obtained as per IS:
1199 and tested as per IS:516
does not yield the strength
requirements of the code
accordance
criteria,
the
Engineer-in-charge with the
consultation of the Designer
will consider the technical
consequences
such
as
durability,
strength,
serviceability,
economic
consequences,
cost
replacement,
cost
of
strengthening the weak point
etc.,
However, the hardened concrete shall be accepted only after carrying
out suitable remedial measures to the satisfaction of the Engineer-in-charge.
4.14.
UNACCEPTABLE WORK:
All under water concreting shall be carried out by Tremie method only,
using Tremie of appropriate diameter. The number and spacing of the tremles
should be worked out to ensure proper concreting. The tremie concreting
when started should continue without interruption for the full height of
member being concreted. The concrete production and placement equipment
should sufficient to enable the underwater concrete to be completed
uninterrupted within the stipulated time. Necessary stand-by equipment
should be available for emergency situation.
The top section of the tremie shall have a hopper large enough to hold
one full batch of the mix or the entire contents of the transporting basket as
the case may be. If tremie pipe shall not be less than 200 mm in diameter
and shall be large enough to allow a free flow of concrete and strong enough
to withstand the external pressure of the water in which it is suspended, even
if a partial vacuum develops insider the pipe. Preferably, flanged steel pipe of
adequate strength for the job each tremie pipe with its hopper at the upper
end. Unless the lower end of the pipe is equipped with an approved
automatic check valve, the upper end of the pipe shall be plugged with a
wadding of gunny sacking or other approved material before delivering the
concrete to the tremie pipe through the hopper, so that, when the, concrete
is forced down from the hopper to the pipe it will force the plug (and along
with if any water in the pipe) down the pipe and out of the bottom end, thus
establishing a continuous stream of concrete. It will be where only in raise
slowly the tremie in order to allow a uniform flow of concrete, but it shall not
be emptied so that water is not allowed to enter above the concrete in the
pipe. At all times after placing of concrete is started and until all the required
quantity has been placed, the lower of the tremie pipe shall be kept below
the surface of the plastic concrete. This will cause the concrete to build up
from below instead of flowing out over the surface and thus avoid formation
at large of sustime. If the sand in the tremie is lost while depositing the
tremie shall be raised above the concrete surface and unless sealed by a
check value, it shall be re-plugged at the top end, as at the beginning before
refilling for depositing further concrete.
4.15.2. COLD WEATHER CONCRETING.
Where concrete is to be deposited at or near freezing temperature,
precautions shall be taken to ensure that at the time of placing, it has a
temperature of not less than 5 degrees Celsius and that the temperature of
the concreting shall be maintained above 4 degree Celsius until it has
thoroughly hardened. When necessary concrete ingredients shall be heated
before mixing but cement not be heated artificially other than by the heat
transmitted to it from other ingredients of the concrete. Stock-piles aggregate
may be heated by the use of dry heat or steam. Aggregates shall not be
heated directly by gas or on sheet metal over fire. In general the temperature
of aggregates or water shall not exceed 65 degrees Celsius. Salt or other
chemicals shall not be used for the prevention of freezing. No frozen material
or materials containing ice shall be used. All concrete damaged by frost shall
be removed. It is recommended that concrete exposed to freezing weather
shall have entrained air and the water content of the mix shall not exceed so
litres per 50 kg of cement.
FINISHING:
4.17.1. GENERAL
Immediately after removal of forms, exposed bars or bolts, if any, shall
be cut inside the concrete member to a depth at least 50 mm below the
surface of the concrete and the resulting holes filled with cement mortar. All
fins caused by form joints all cavities produced by the removal of form ties
and all other holes and depression honey comp spots, broken edges or
corners and other defects, shall be through, cleaned, saturated with water,
and carefully pointed and rendered with mortar of cement and fine aggregate
mixed in the proportion used in the grade of concrete that is being finished
and of as dry a consistency as is possible to use. Considerable pressure shall
be applied in filling and pointing to ensure through filling in all voids.
Surfaces, which have been pointed, shall be kept moist for a period of 24
hours. Special pre-packed proprietary mortars shall be used where
appropriate or where specified in the drawing.
All construction and expansion of joints in the complete work shall be
left carefully tooled and free from any mortar and concrete. Expansion joint
filler shall be left exposed for its full length with clean and true edges.
Immediately on removal of forms, the concrete work will be examined
by the Engineer before any defects are made good.
a)
b)
b)
c)
d)
4.17.3.1.
REPAIR OF CONCRETE
GENERAL
(a) Repair of concrete shall be performed by skilled workers and in the
presence of an Engineer-in-charge. Repairs and correction of all
imperfection on formed concrete shall be completed as soon as
practicable after removal of forms and within 25 hours after removal
of forms. Concrete that is damaged from any cause and concrete
that is honey combed, fractured on otherwise defective and
concrete, which because of excessive surface depressions, must be
excavated and built up to bring the surface to the prescribed lines,
shall be removed and replaced by dry pack mortar or concrete as
hereinafter specified. Where bulges and abrupt irregularities
protrude outside the limits specified the protrusions shall be
reduced by bush hammering and grinding or that the surfaces are
within the specified limits.
(b) Before repair is to commence, the methods proposed for the repair
shall be approved by the Engineer. Routine curing should be
interrupted only in the area of repair operations.
4.17.3.2.
METHODS OF REPAIRS
ii)
iii) The top edge of the face of the structure should be cut to a fairly
horizontal line. If the shape of the defect males it advisable the top
of the cut may be stepped down and continued on a horizontal line.
The top of the hole should be cut 1 to 3 upward stop from the back
towards the face of the wall on beam. It may be necessary in fill the
hole from both sides, in which case the slope of the top of the cut
should be modified accordingly.
iv) The bottom and sides of the holes should be cut sharp and
approximately square with the face of the wall when the hole goes
entirely through concrete section. Spalls or feather edges shall be
4.18.1
MEASUREMENT:
The unit rate for concrete shall include the cost of all materials,
labour, tools and plant required for mixing, placing in position,
vibrating and compacting, finishing as per directions of the
Engineer, curing and all other incidental expenses for producing
concrete of specified strength to complete the structure or its
components as shown on the drawings and according to these
specifications. The rate shall also include the cost of providing,
fixing and removing of all centering, scaffolding formwork
requirement for the work unless otherwise specified in the contract.
(b) The unit rate also includes the cost of dewatering, diversion and
protection work as may be necessary during and after concreting
work.
(c) All expenses likely to be incurred by the contractor in transporting
materials supplied to him to the site of work, the expenses incurred
improving the quality of materials to acceptable levels (such as
screening, washing etc.) and the expenses incurred in proper
storage of materials as directed by the Engineer are deemed to be
included in the unit rate.
(d) Payment of the various classes of concrete shall be made on the
basis of unit rate per cubic metre entered in respective items in the
Schedule 'A'.
(e) In respect of cross drainage structures, even if these shall be
completed to the specified quality standards, they will not qualify for
full payment until and unless the respective in fall and outfall
channels are duly excavated and graded as per design
requirements. Payment of the value of work done on cross drainage
structures shall not be released until the above requirements are
met.
(f) For reinforced concrete works, the cost of steel and its fabrication
changes are not included in the unit rate.
4.20.
STEEL REINFORCEMENT
4.20.1. GENERAL:
a)
walls, Canal Side Walls, Inlets, Outlets, Head Walls, Cut of walls,
cross Regulators, Off-take Sluices and of other similar Structures.
b)
I.S.1786-1985
(Part-I)
I.S. 818-1968
I.S.3016-1986
I.S. 280-1978
I.S. 2502-1963
I.S. 9417-1989
I.S. 2751-1979
I.S. 814-1991
I.S.1278-1972
ii)
(b) Bars shall be bent to the specified shape and dimensions by the
bender by hand or power to attain proper radii of bends as shown in
drawings or as directed by the Engineer.
(c) Bars shall not be bent or straightened in a manner that will injure
the material.
(d) Bars bent during the transport or handling shall be straightened
before being used on work, they shall not be heated to facilitate
bending.
(e) "U" hooks shall invariably be provided at the end of each bar, if
specified in Drawing or ordered by the Engineer. The radius of the
bend shall not be less than twice the diameter of round bar and the
length of the straight part of the bar beyond the end of the curve
shall be at least four times the diameter of the round bar. In the
case of bars, which are not round, and in the case of deformed bars,
the diameter shall be taken as the diameter of a circle having an
equivalent effective area.
(f) The hook shall be suitably encased to prevent any splitting of the
concrete.
4.20.4. PLACING OF REINFORCEMENT:
(a) Before the reinforcement is placed, the surface of the bars and the
surfaces of any metal bar supports shall be cleaned of the rust,
loose mill scale, dirt, grease and other objectionable foreign
substances.
(b) All reinforcing bars shall be securely held in position during placing
of concrete by annealed binding wire, and by using stays, blocks or
metal chairs, spacers, metal hangers, supporting wires or other
approved devices, at sufficiently close intervals.
(c) Wire for binding reinforcement shall be soft and annealed mild steel
of 16 SWG and shall conform to IS: 280-1978. Binding wire shall
have tensile strength of not less than 5600 Kg/CM 2. and an yield
point of not less than 3850 Kg/CM2.
(d) Bars shall not be allowed to sag between supports. They shall not be
displaced during concreting or any other operation over the work.
(e) The contractor shall also ensure that there is no disturbance caused
to the reinforcing bars already placed in concrete.
(f) All devices used for positioning shall be of non-corrodible material.
Metal supports shall not extend to the surface of the concrete,
except where shown on the drawing. Pieces of broken stone or brick
and wooden blocks shall not be used. Where portions of such
supports will be exposed on concrete surfaces designated to receive
F2 or F3 finish, the exposed portion of support shall be galvanized or
coated with other corrosion resistant materials without which the
concreting will not be permitted. Such supports shall not be exposed
on surfaces designated to receive F4 finish unless otherwise shown
on the drawings.
j)
As far as possible, bars of full length shall be used. In case this is not
possible, overlapping of bars shall be done as directed by Engineer.
When practicable, overlapping bars shall not touch each other, but
be kept apart by 25mm or 1 1/4 times the maximum size of the
coarse aggregate whichever is greater, by concrete between them
where, not feasible. Overlapping bars shall be bound with annealed
steel wire, not less than 1mm thickness twisted tight. The overlaps
shall be staggered for different bars and located at points, along the
span where neither shear nor bending moment is maximum.
(m) The minimum allowable clearance between parallel round bars shall
not be less than 1 1/2 times the diameter of the larger bars and for
square bars shall not be less than twice the side dimensions of the
larger bars or 1 1/2 times, the maximum size aggregate whichever
is greater.
(n) Dissimilar diameter rods should not be joined together.
4.20.5. SPLICING:
(a) Where it is necessary to splice reinforcement the splices shall be
made by lapping, by welding or by mechanical means.
(b) When permitted or specified on the drawings, joints of
reinforcement bars shall be but welded so as to transmit their full
strength, welding of bars shall be done as directed by the Engineer
and conforming with requirements of Clause. 11.4 of IS: 456-1978.
or reinforcement placing.
(c) Reinforcing bars 25mm in diameter and less may be either lapped or
Butt-welded, whichever is the most practicable.
(i)
ii)
found to be more practical than butt welding and if lapping does not
encroach on cover limitation or hinder concrete.
4.20.7
a)
4.20.8
a)
i)
ii)
b)
4.20.9. DOWELS:
a)
b)
c)
d)
e)
i)
ii)
PAYMENT RATE:
The tender rate in the schedule-A for reinforcement shall include cost
of steel, sampling and testing binding wire or welding material at site of work,
its cutting, bending, cleaning, placing, binding or welding and fixing in
position as shown on the drawings and as directed by the Engineer. The unit
rate shall also include cost of all devices for keeping reinforcement in
approved position, cost of jointing as per approved methods and all wastage,
overlaps, dowels, binding wire or welding material and spacers of bars and
cost of all incidental operations necessary to complete the work as per
drawings and as per specifications.
5.0. CANAL LINING
5.1. GENERAL:
(a) These specifications apply to:
Clearing site, preparation of sub grade in soils and rock, providing
under drainage, pressure relief arrangements, anti salt treatment,
placing model sections, laying plain cement concrete with machine
crushed hard broken graded quartzite/granite/other than granite
metal of 40 mm/20 mm maximum nominal size and using cement
level of not less than 250 kgs. per cubic meter of concrete to yield a
28 days characteristic compressive strength specified based on
laboratory tests for bed and sides respectively using conventional
placement of concrete lining.
(b) If during construction, it is found necessary to after the canal
sections and side slopes without altering the thickness of lining, the
contractors shall be informed in writing of such changes. The rates
quoted being on one square meter basis for specified thickness, the
contractor shall have to execute the work at the same tender rates
as quoted in schedule-A without any extra claim for change in the
section of canal.
(c) The scope of work also includes the following :
i)
Dewatering the canal section for preparing the base for lining and
for laying concrete lining.
ii)
iv) Bed and side lining of the grade as specified in the schedule=A i.e.
cement concrete with machine crushed hard broken graded
Quartzite/granite/other than granite metal of 40 mm/20mm nominal
size and using cement of not less than 250 kgs/cum of concrete to
yield a characteristic compressive strength specified based on
laboratory tests respectively.
v)
vi) Curing
vii) filling joints :
5.2. APPLICABLE PUBLICATIONS
All concrete, its constituents, methods and procedures of manufacture
shall conform to Indian Standard Specifications and other publications listed
below unless otherwise specified.
Indian Standards.
1.
IS: 456-1978 Code of practice for plain and reinforced concrete (Second
Revision) (Amendment No.1)
2.
IS: 3873-1978
3.
IS: 2505-1980
General requirements
immersion type.
4.
IS: 2506-1985
5.
IS: 3366-1965
6.
IS: 3558-1983
7.
IS: 4558-1983
8.
IS: 5256-1968
9.
IS: 3085-1965
for
concrete
vibrators
Method of tests
(Amendment No.1)
for
strength
of
concrete
GENERAL:
The provisions of this Para shall apply to the preparation of all sub
grade upon which concrete lining it to be laid.
The work of trimming canal section up to the under side of concrete
lining and preparing sub-grade for concrete placement includes removal of
ground section. Ground equivalent to thickness of lining on sides and in bed
on the underside of lining should be left un-excavated and the removal of this
ground should be done prior to laying of lining but in no case, should the time
interval exceed 3 days in normal weather and two days in adverse weather
conditions.
It shall be ensured that the sub grade is made thoroughly moist with
fine water spray, through deployment of proper nozzles, to a depth of about
15 cms to prevent it from absorbing water from the freshly laid concrete.
Soil in all reaches should be tested for salt content before lining is
started. Where the salt content is over one percent or sodium sulphate is
over 0.36 percent, the sub grade should first be covered with about 2 mm
thick layer of bitumen if ordered by the Engineer. It shall be treated in
accordance with para 4.3 of IS: 873-1978.
Preparation of sub grade for concrete lining shall conform to clause 4.1
to 4.5 of IS 3873-1978.
Wherever rock is over excavated it shall be filled as specified under
subsequent paras.
At the end panels of existing lining against which lining is to be laid
under these specifications, all these materials shall be removed and all voids
beneath the existing lining shall be refilled and thoroughly compacted.
5.3.4.
(i)
SUB-GRADE
Preparation of sub grade consisting of earth.
(a) The sub grade shall be prepared, dressed and rolled true to level
and according to the required cross - section of the canal to form a
firm compacted bed for the lining.
(b) The contractor shall place selected bedding material, test profile
true to the cross - section of the canal at times and places
designated by the Engineer to show the adequacy of his
construction procedures for laying bedding material. The test
sections shall conform to clause 4.5.2 of I.S. 3873-1978. The cost of
this operation shall be deemed to have covered in the rates quoted
for side and bed lining.
(c) In other than predominantly sandy reaches where the dry density of
the natural soil is not less than 1.8 gms per cubic centimetres initial
excavation shall be done upto about 300 mm above the final section
and the cutting to final shape shall be done immediately before
lining. The compaction shall conform to Clause 4.5.6 of IS 3873 1978.
(d) If at any point material of prepared sub grade has been excavated
beyond the neat lines required to received to receive lining, the
excess excavation shall be filled in horizontal layers with suitable
semi pervious soil material compactable with the sub grade material
moistened and thoroughly compacted in accordance with CI. 4.5.5
and 4.5.6 of IS 3873 - 1978. Where placing and compacting bedding
material is on sloping foundation, the layers may be placed parallel
to the surface of the foundation. If at any point, the foundation
material is disturbed or loosened during the excavation process or
other wise, it shall be moistened if required, and thoroughly
compacted by tamping, rolling or other approved methods to form
firm foundation for placing the concrete lining. Slope compactors
may also be used for effective compaction of subgrade.
(e) In bed, where the dry density of the natural soil is less than 1.8 gm
per cubic centimetres and sub soil water is near the sub grade, the
consolidation shall be done by under cutting the bed by 7.5 cm and
then ploughing upto 15.0 cm below the sub grade level. The
loosened soil shall then be re-compacted with suitable devices. All
along the canal alignment the rain cuts on the banks shall be filled
up with approved soil and shall be compacted adequately to
required lines, dimensions and levels.
(f) In bed, where the sub soil water is low, requiring no dewatering and
the dry density of the natural soil is less than 1.8 gm per cubic
centimetres, the consolidation shall be done by digging the canal
upto sub grade level and after loosening the earth below subgrade
upto 15.0 cm by disc-harrows, or ploughing and compacting the
same to a layer of 11.0 cm. After that, the second layer of 15.0 cm
of earth shall be laid over the compacted layer by taking earth from
lip cutting and compacting this to a depth of 11.00 cm. The
compacted layer of 7.0 cm above the subgrade level shall be
removed and the subgrade brought to design profile before laying
the lining.
control moisture contend to ensure that the specified density is obtained. All
tests shall be done in accordance with the relevant Indian standards. The
frequency of the test shall be as determined by the Engineer-in-charge. The
work shall be done to the construction profile.
The canal section including the thickness of the lining shall be
excavated in CNS soils and canal sides and bed are trimmed to receive PCC
slab lining and cast-in-situ lining respectively.
The soils excavated shall be re-handled and used for forward reach as
directed by the Engineer. No extra payment will be made for the excavation
of CNS soil in canal section and re-handling the soils as above separately.
i)
15 to 20%
2.
Silt (0.06mm-0.002mm)
30 to 40%
3.
Sand (2 mm - 0.06mm)
30 to 40%
4.
0 to 10%
ii)
GENERAL
For a lined canal where the ground water level is higher or likely to be
higher than the water level inside the canal so as to cause damaging
differential pressure on the lining or where the subgrade is sufficiently
impermeable to prevent free drainage of the under side of lining in case of
rapid draw-down, pressure relief arrangements for under drainage shall be
provided suitably as indicated in the drawing in accordance with IS: 4551968.
5.4.2.
FILTER DRAINS:
a)
b)
c)
The longitudinal drains shall be laid to the grade of the canal while
the transverse drains in bed shall have a fall towards the centre of
the canal bed from the edge as shown in the drawing.
The sand shall be clean, round and well graded before placing the
filter, the bed shall be prepared as specified in paragraph above.
d)
A) SCOPE:
Laying and fixing of porous concrete plugs is in position in bed/sides
of specified size including manufacturing of plugs, using 20mm size
machine crushed aggregate of specified variety and cement of
specified quantity for each plug including cost and conveyance of
cement and all other materials. Seigniorage charges, labour charges
for manufacturing of plugs, form work, moulds, machine mixing,
manufacturing, curing, sampling and testing laying and fixing in
position with all leads, lifts, delifts, dewatering, all water leads and
all other incidental and operation charges necessary to complete
the finished item of work as per drawings and as directed by
Engineer in charge.
b)
POROUS PLUG :
(i)
5.4.3.
(a) Laying and fixing of porous concrete plugs/flap valves in position in
filter pockets including (a) Manufacturing of plugs using 20mm size
machine crushed/hand broken aggregate of specified variety and
Cement of specified quantity for each plug (or) Manufacturing of flap
valves consisting specified internal diameter with P.V.C. pipe, with
P.V.C. flange and rubber flap with all accessories and (b) excavation
of pit for laying filter pocket and filling the filter pocket with filter
materials including cost and Conveyance of Cement and all other
materials, Seigniorage charges, labour charges for Manufacturing
plugs/flap valves, excavation of filter pocket, filling of pocket with
specified grade of filter material, form work, moulds and machine
mixing, manufacturing, curing, sampling, testing, laying, fixing in
position with all leads, lifts, delifts, dewatering, all water leads, all
other operational and incidental charges necessary to complete the
finished item of work as per drawings and as directed by the
Engineer in charge.
(b) The porous plug/flap valve shall be installed in position in the filter
drains in the bed, normal to the canal slope in the local filters in the
sides at the locations shown in the drawings or as directed by the
Executive Engineer.
C)
FLAP VALVES:
Measurement and payment for the anchor bolts shall be made on the
basis of number at the unit rate in schedule 'A'. The rate shall include the
cost of steel rod, cutting, bending, splitting and drilling in rock, fixing and
labour as per drawings and incidental operations necessary to execute the
work as per specifications as well as those defined in the nomenclature of the
item.
5.6 LAYING OF C.C LINING:
A)
SCOPE:
c)
Alternatively:
ii)
h)
b)
c)
d)
e)
f)
g)
The design mix for lining shall to secure dense concrete of required
strength for that grade.
The concreting near the joints shall be done with utmost care so as
to avoid segregation and collection of goose place of aggregate
along form work which may result in honey combing.
j)
The concrete near the junction of the side concrete panels and bed
concrete shall be done as shown in drawings such that both shall
rest firmly against each other to resist any back kick from external
hydrostatic forces.
k)
For vibrators shall be used in conjunction with slip form lining machines
for consolidation. The Engineer may remove samples of hardened concrete
for testing and examination and the contractor shall replace at no extra cost
to the department concrete from which such samples are removed.
5.6.3.
FINISHING:
a)
b)
d)
e)
The top portions of the side slopes of the canal lining extending 1.5
meter vertically below the top of the lining shall receive a nonskid
longitudinal brush finish as approved by the Engineer.
f)
Use of any finishing tool in areas where water has accumulated shall
be prohibited and all finishing operations shall be delayed until the
water has been absorbed evaporated or removed by draining,
mopping or such other means.
g)
The contractor is not entitled for any extra payment for the work
under finishing paragraph as the tender rates in the schedule 'A' are
inclusive of finishing the lining.
5.6.4.
TOLERANCES
tangents
(b) Departure from Established grade
CURING
The joints of plain cement concrete slabs lining on side slopes shall be
water cured through sprinkling of water at regular intervals for at least 21
days.
The Engineer-in-Charge may instruct contractor to provide pipeline
system and sprinklers for curing of the lining work. If the Engineer-in-charge
feels that the manual curing is not sufficient. The Contractor shall abide by
the instructions and erect the pipe line system the quoted date shall include
for erection of pipe line system and dismantling of the pipes after curing
instead of manual curing if the work involved is more in length and quantity
no separate payment will be allowed and the quoted rates for respective
schedule 'A' item shall include the erection of pipe line system pumping of
water, dismantling of pipe line system after curing.
If the contractor fails to do curing to the satisfaction of the Engineer
the latter shall make arrangements for curing at the first and cost of the
contractor or the lining work will be pulled down. The contractor at his own
cost shall rebuild the lining so pulled down.
The Contractor is not entitled for any extra payment for curing as the
tender rate for lining in schedule-'A' is inclusive of curing.
5.6.6.
A)
GENERAL:
ii)
Quantity of concrete
Number of Samples
(Cubic meter in the work.)
1-5
6 - 15
16 - 30
31 - 50
1
2
3
4
51 and above
additional 50
part there of
CORE TEST:
The points from which cores are to be taken and number of cores
required shall be at the discretion of the Engineer. In no case however shall,
fewer than three cores be taken and tested. Core shall be tested as
described in IS: 516-1959.
5.6.7
ACCEPTANCE CRITERIA:
(a) The cores shall be tested for 28 days compressive strength. These
shall be inspected examined for segregation / honey combing and
checking the thickness of lining. The engineer may also arrange to
test the core for permeability and cement content. If considered
necessary. Concrete in the member represented by core test shall
be considered acceptable if the average equivalent cube strength of
cones is equal to at least 85 percent of the cube strength of the
grade of concrete specified for the corresponding age and no
individual core has a strength not less that 75 percent.
(b) The density of concrete shall not be less that 85 percent of specified
density of 2400 kgs/m3.
(c) In case the concrete does not conform to the accepted criteria for
strength as specified above, the Engineer reserved the right to
reject the work or accept the same at a reduced rate derived from
tendered rate and as approved by him after examining all aspects
and provided structural integrity is not effected. In case the cores
taken from concrete lining panels. Inherit heavy segregation or
honey combing the engineer shall reject the concerned panels and
the contractor shall have to dismantle the same and have to cast
new panels at his expense.
Whenever necessary for the purpose of obtaining economy, work
ability, density, impermeability, durability, strength or on account of
variation in the quality and gradation of aggregates or other
materials, except cement the Executive Engineer shall based on
laboratory tests make necessary changes in the proportion of mix
and vibration. Contractor shall have to affect these changes and will
not be entitled to any compensation. On account of such changes,
relevant para of IS: 456 - 1778 shall apply.
Regarding particular canal reach/reaches, though the lining is fully
completed to acceptable quality, levels, such reach/reaches will not quality
for acceptance and payment till the associated works necessary for safely of
lining during rains, such as dowel banks, drainage are also completed along
with.
d)
5.6.8.
The final payment shall be made only after satisfactory core tests
acceptable to the engineer as per IS: 456 - 1978.
CONSTRUCTION JOINTS:
(a) The concrete for sides and bed lining should be placed in alternate
days of not more than 3mts. days remaining in between may be
filled after a gap of at least one day with premier one litre per four
square meters.
(b) The shuttering should be clean, well - oiled, smooth and firmly fixed
to the sub-grade and concrete near the shuttering properly placed
and specially compacted.
(c) Faces to be painted with scaling compound.
(d) The concrete shall be laid continuously and the construction joints
shall be left at the close of the day (or) 45 meters whichever is less
vide clause in column 26.3 of I.S. 456/1978.
5.6.9.
concrete placed and area covered (ii) use of probe when concrete is given
and (iii) cores if required. Any over run in lining shall not be paid to the
contractor.
5.6.10. RATE:
The unit rate for lining includes:
1)
2)
3)
4)
5)
6)
7)
8)
9)
Preparation of sub-grade.
From work.
Plants and equipment.
Mixing and conveying.
Placing.
Compaction with vibrators.
Curing.
Finishing.
Dewatering the sections during placing of canal lining where
required.
Cost of all ingredients of concrete.
Cost of cutting groves for contraction and expansion joints, cost of
construction joints and their treatment.
Cost of producing samples for testing.
All incidental operations, equipment, Labour, tools, etc., required for
carryingout this work.
Cost of sampling and testing of materials and concrete.
10)
11)
12)
13)
14)
5.7.
R.R. LINING
a)
b)
c)
5.8. JOINTS:
5.8.1.
EXPANSION JOINTS:
CONTRACTION JOINTS:
30% by volume.
Sand
51% by volume.
Cement
17% by volume.
2% by volume.
----------------------100% by volume.
SLUMP:
shall not vary more than 20 mm.which would otherwise interfere with the
aggregate and quality of the work.
5.9.1.
A) CURING.
After 24 hours of casting the P.C.C. slabs, the moulds shall be removed
and the slabs shall be kept in the curing ponds for at least 28 days for curing.
After 28 days curing, P.C.C. slabs shall be taken out of curing ponds, stacked
carefully for use as directed by Engineer. After about four to six hours of
casting, the moulds shall be properly covered by the Hessian cloth rolls which
are to be kept continuously wet till the moulds are removed and P.C.C. slabs
are put in the curing tanks (moulds to be placed in shed).
b)
In
In
In
In
the
the
the
the
length
width
diagonals
thickness
+
+
+
+
3 mm.
3 mm.
4.50 mm.
2 mm.
for Slabs
550x275x50 mm
+ 3 mm.
+ 1.5 mm.
+2.25 mm.
+ 2 mm.
6mm thick cement mortar (1:3). The slabs shall be pressed gently so that the
mortar squeezes through joints. These joints are neatly finished flush with top
surface of the slab. The P.C.C. slab lining shall be done from bottom to the top
in a stretch no more than 10 mts length and vertical break joints shall be
ensured in P.C.C. slabs completion of P.C.C. lining in length of not less than
100 meters, the in-situ bed lining and top plug shall be laid in the next 100
meters reach cast in-situ cement concrete with a cement level of not less
than 250 kgs/cum. The line surface shall be even true to the face smooth to
give designed co-efficient of rugosity.
TOLERANCE IN ALIGNMENT AND GRADE
a) Departure from established alignment.
reaches.
20
millimeters
straight
50 millimeters on curves or
tangents.
b)
5.9.4.
(i)
(ii)
(vi) Dewatering the sections during placing P.C.C. slab lining where
required.
(vii) Cost of all ingredients required for CM (1:5), first layer, CM (1:3) for
second layer and CM (1:3) for third layer for fixing slabs.
(viii) Cost of producing samples for testing.
(ix) All incidental operations, equipment Labour for fixing curing tools
etc., required for the finished item of work.
(x)
2.
3.
Method of identification
building stones.
4.
5.
6.
7.
8.
9.
of
natural
of
Specification
mortals.
for
sand
for
masonry
Measurement of
engineering works
stone masonry.
(Part IV)
building
and
civil
SCOPE:
CONSTRUCTION OPERATIONS
6.6.1.
GENERAL REQUIREMENTS.
(j)
Face work and hearting shall be brought up evenly. The top of each
course, however, shall not be leveled up by use of flat chips.
(k) After the day's work, the face and top of masonry shall be cleaned
well with brushes or broomsticks to remote all the dead mortar on
the stones.
(l)
the end of the day. During hot weather all finished or partly
completed work shall be covered or wetted in such a manner as to
prevent rapid drying. The racking of joints where necessary shall be
done at the end of day's work when mortar is green.
(m) When fresh masonry is to be placed against existing surface
material, roughened and wetted as directed the Engineer so as to
achieve a good bond with the new work.
(n) Stone shall be sufficiently wetted before laying, to prevent
absorption of water from mortar. The bed which is to receive the
stones shall be cleaned wetted and covered with a layer of fresh
mortar.
(o) The scaffolding shall be sound and strong to withstand all loads
likely to come upon it; The holes, which provide resting space for
horizontal members shall not be left in masonry less than one metre
wide. The holes left in the masonry work for supporting the
scaffolding shall be filled and made good.
6.7 UNCOURSED RUBBLE OR RANDOM MASONRY
6.7.1
a)
6.7.2.
DRESSING.
The face stone shall be hammer dressed on the face, side and the
beds to enable it to come into close proximity with the neighboring
stone. The bushing in the face shall not project more than 40mm on
an exposed face and 12mm on a face to be plastered. Stones with
round surface shall not be used in construction.
SIE OF FACE STONES
a)
The width of face stones shall be not less than 150 mm of walls of
400mm thick, 200mm for walls 450mm thick, 250mm for walls of
600mm thick or more. Half the quantity shall not be less than 1/70
cum, 1/50 cum and 1/35 cum in volume for walls of the above
thicknesses respectively. No stone less than 150mm in height shall
be used on the face.
b)
6.7.3
a)
CHIPS.
Chips and spalls of stone may be used wherever necessary to avoid
thick mortar beds or joints and it shall also be ensured that no
hollow spaces are left anywhere in the masonry. The chips shall not
be used below hearting stones to bring these up to the level of face
stones. Use of chips shall be restricted to filling of interstices
between the adjacent stones in hearting and they shall not exceed
10 percent of the quantity of stone masonry.
6.7.4.
a)
6.7.5.
a)
6.7.6.
a)
6.7.7.
HEARTING STONES
The hearting or interior filling of wall face shall consist of rubble
stones not less than 15 cm in any direction, carefully laid and
hammered down with a wooded mallet into position and solidly
bedding in mortar and should be laid nearly level with facing and
backing.
BOND STONES.
Through bond stones shall be provided in masonry upto 60 cm
thickness and in case of masonry above 60 cm thickness, a set of
two or more bond stones over lapping each other at least by 15 cm
shall be provided in a line from face to back. In case of highly
absorbed types of stones (porous limestone and sand stone, etc.,)
the bond stone shall extent only about two-third into the wall as
through stones in such cases may give rise to penetration of
dampness and, therefore, for all thicknesses of such masonry a set
of two or more bond stones over lapping each other by at least 15
cm shall be provided. One bond stone or a set of bond stones shall
be provided in each layer at 1.5 to 1.80 m interval.
QUOIN STONE
The stone specially and neatly dressed for forming an internal angle
in masonry work shall not be less than 0.03 cubic metre in volume.
PLUM STONE
The Plum Stones are selected long stones embedded vertically in
the interior of masonry to form a bond between successive courses
and shall be provided at about 90 cm interval.
6.7.8.
a)
6.7.9.
a)
LAYING
the masonry shall be laid with or without courses as specified. The
quoins shall be laid header and stretcher alternately. Every stone so
as to form neat and close joint, face stone shall extent and bond
well in the back. These shall be arranged to break joints, as much as
possible, and to avoid long vertical lines of joints.
JOINTS
The face joints shall not be more than 20mm thick, but shall be
sufficiently thick to prevent stone-to stone contact and shall be
completely filled with mortar.
DRESSING
Face stones shall be hammer dressed on all beds and joints so as to
give them approximately rectangular shape. These shall be square
on all joints and beds. The bed joints shall be chisel drafted from at
least 8 cm back from the face and for at least 4cm for the side
joints. No portion of the dressed surface shall show a depth of gap
more than 6 mm from straight edge placed on it. The remaining
unexposed portion of the stone shall not project beyond the surface
of bed and side joints. The requirements regarding bushing shall be
same as for random rubble masonry.
6.8.2.
a)
6.8.3.
a)
6.8.4.
a)
HEARTING STONE
The hearting or interior filling of the wall shall consist of flat-bedded
stone carefully laid on their proper beds in mortar. The use of chips
shall restrict to the filling in interstices between the adjacent stones
in hearting and these shall not exceed 10 per cent of the quantity of
masonry. While using chips it shall be ensured that no hollows
spaces are left anywhere in the masonry.
BOND STONES.
The requirements regarding through or bond stone shall be same as
for random rubble masonry but these shall be provided at 1.5 metre
to 1.8 metre apart clear in every course.
QUOIN STONES
The quions which shall be of the same height at the course in which
these occur shall be formed of header stones not less than 45 cm in
length. They shall be laid lengthwise alternately along each face,
square in their beds, which shall be fairly dressed to a depth of at
least 10 cm.
6.8.6.
a)
6.8.7.
a)
Face stone shall tail into the work for not less than their heights and
at least one-third of the stones shall tail into the work for a length
not less than twice their height. These shall be laid headers and
stretchers alternately.
LAYING
The stones shall be laid on horizontal courses and all vertical joints
shall be truly vertical. The quoin stones shall be laid stretches and
headers alternately and shall be laid square on their beds. Which
shall be roughly chisel dressed to a depth of at least 10 cm.
JOINTS.
The face joints shall not be more than 10mm thick but shall be
sufficiently thick to prevent stone-to-stone contact and shall be
completely filed with mortar.
6.9. TESTS.
a)
1. MM
30 Kgs/Square centimeter
2. MM
50 Kgs/Square centimeter
3. MM
7.5
75 Kgs/Square centimeter
b)
From the design mortar mix, cubes shall be cast in the laboratory at
suitable intervals and their strength found out.
1)
2)
3)
Not more than 10% of the specimen strength be less than 85% of
the specimen strength.
6.9.1.
6.9.2.
6.10.
CURING
a)
b)
6.11.
a)
mortar mix MM5 grade and the balance thickness of wall will be
measured as Random Rubble masonry in cement mortar mix MM5
grade.
b)
Payment for stone masonry shall be made at the quoted rate in the
schedule A for 1 cubic metre of finished work.
MATERIALS:
Provision of schedule 'D' shall apply for cement, sand, water etc.,
7.1.4.
MORTAR
7.1.5.
7.1.6
PREPARATIONS OF SURFACE:
a)
LAYING OF PLASTERING :
a)
The mortar used for plastering shall be stiff enough to cling and hold
when laid. To ensure even thickness and true surface, plaster shall
be applied in patches of 150mm X 150mm of the required thickness
more than 2 meters intervals horizontally and vertically over the
entire surface to serve as guides. The surface of these guides shall
be truly in the plane of the finished plaster surface and truly plumb.
Plastering shall be started from top and worked down. All the pot log
holes shall be properly filled in advice of the plastering. The mortar
shall then be applied to the surface to be plastered between the
guides with a trowel. Each trowel fall of mortar shall overlap and
sufficient presence shall be used to force it into thorough contact
with the surface. On relatively smooth surfaces, the mortar shall be
dashed on with the trowel to ensure adequate bond. The mortar
shall be applied to a thickness lightly more than specified using a
steering, stretched out between the guides. This shall then be
brought to a true surface by working with a long wooden float with
upward and side ways motion 50mm or 75mm at a time. The
surface shall be periodically checked with a steering stretched
across it. Finally the surface shall be rendered smooth with a small
wooden float: over working shall be avoided. All corners, arises, and
junctions shall be neatly finished. Metal floats shall not be used I.S.
1661-Code of practice for application of cement and cement lime
plaster finishes shall be applicable for this section.
b)
c)
After the plaster has sufficiently hardened cement slurry with cream
like consistency shall be applied evenly and rubbed to a fine
condition.
d)
e)
The average thickness of plaster shall not be less than the specified
thickness but not be thicker than 25mm in any case. Any cracks
which appear on the surface and all portions which sound hollow
when tapped or found to be sort or other-wise defective, shall be cut
in rectangular shape and redone as directed by the Engineer at no
extra cost, plastering shall be cured for 10 days.
7.2.1.
SCOPE:
Flush pointing/with cement mortar of specified proportion to the
exposed faces of CRS masonry including cost and conveyance of
cement and all other materials, sampling, testing, mixing of mortar,
labour charge, all leads, lifts, de-lifts, seigniorage charges,
scaffolding, curing all other operations necessary to complete the
finished item of work as per drawings and as directed by the
Engineer-in-charge.
7.2.2.
a)
PREPARATION OF SURFACE:
The joints in the masonry shall be raked out to a depth not less than the
width of the joint or as directed when the mortar is green. Joints are
to be brushed to clean the dust and loose particles with a stiff brush.
The area shall then be washed and the joints, thoroughly wetted
before pointing is commenced.
Flush pointing shall be done with cement mortar mix MM 7.5 grade
or any other specified grade. The mortar shall be pressed into the
rated out joints. The mortar shall not be spread over the corners,
edges on surface of the masonry. The pointing shall then be finished
as detailed below. The mortar, shall be, finished of flush and level
with true edges of the stones, so as to give a smooth appearance.
The edges shall be neatly trimmed with a trowel and straight edge.
d)
b)
The specifications provide for drilling of "A" and "B" holes and grouting
of "A" and "B" holes with cement slurry for foundation treatment.
8.1.
01.
02 .
03.
8.2. a)
b)
C)
8.3.
EQUIPMENT:
2)
Deep hole jackhammer with 80'-0 drill capacity and its equipment.
3)
b)
1.
Four specially equipped, air driven duplex, double action slush pumps,
capable of operating at a maximum discharge pressure of about 500
P.S.I/35.00 Kgs/Sq. Cm.
2.
3.
4.
Two high head water pumps for auxiliary water supply to be used in
pressure testing flushing and pressure washing operations.
5.
6.
c)
Hand operated grout pumps shall not be used to grouting low or high
pressure holes, only pumps which are capable of injecting grout into
holes at sustained highest allowable safe pressure are suited for this
type of grouting.
d)
e)
connected to the grout cap or expanding packer the other gauge shall
be mounted on the supply line at the pump.
8.4.
less than 50 MM core recovery will not be required. Grout holes shall be
drilled to varying depths and at carrying inclination, not to exceed 30 degrees
from that vertical. The exact depth direction and interval between holes will
be determined in the field from the conditions encountered, and as directed
by the geologist of Geological Survey of India, drilling of any grout hole to a
total depth greater than 60mm is not anticipate; however holes to greater
depths may have to be drilled if found necessary during execution whenever,
the drill water is lost on artesian flow encountered, the drilling operations or
not to be stopped, but continued taking precautionary steps.
Upon
completion of drilling of a hole, it shall be temporarily capped or otherwise
protected from entry of foreign material until grouting operations required it
to be opened.
8.5.
a)
b)
8.6.
a)
b)
8.7.
When the seam washing is completed the holes are to be flushed with
air and water to full depth and pressure testing of holes to be taken
up by fixing expanding packers for zone required and water to be
pumped under pressure through water meter to record water
consumption. This consumption of water will decide the consistency
of cement grout. After pressure testing, the zone will be taken up for
grouting.
PRESSURE TESTING OF HOLES
a)
b)
c)
______________________________________________________________________________
___________
Step No.
Pressure (p)
P.S.I.
______________________________________________________________________________
____________
1.
1/3
2.
2/3
3.
10
4.
2/3
5.
1/3
______________________________________________________________________________
__________
The Pressure P shall be
determined,
depending on geological conditions and on the depth of
8.8. GROUT:
a)
ii)
b)
GROUT PRESSURE:
b)
b)
For doing the high pressure grouting, the first holes shall be spaced
widely and shall be grouted before intermediate holes are drilled and
in this manner the drilling and grouting of the holes shall be
completed with such final spacing and depth of holes so as obtain to
continuous grout curtain.
8.11
a)
b)
8.12
The core drill holes shall be tested under a water pressure equal to or
a little less than the pressure for high pressure grouting and the
accounting and the account and limit of leakage in each hole
measured. If any hole should seam excessive leakages it shall be
grouted under pressure no test hole shall be driven and tested under
pressure the same manner. The foundation will be considered to the
consolidation satisfactory if the cement consumption less than 0.5
bags (25 Kgs) per 0.3 m of grout hole. If the cement consumption is
more, secondary and or tertiary and shall be drilled and grouted. The
test efficiency and generation of the low pressure grouting more drill
test holes shall be drilled at the rate of one for either 90 mm grouted
area.
.TECHNICAL FIELD RECORDS:
a)
1.
Hole number.
2.
3.
4.
5.
6.
Date of Completion.
7.
8.
8.13.
PAYMENT
a)
b)
CURTAIN GROUTING:
a)
b)
Payment for drilling of curtain grout hole 50mm to 75mm as per the
pattern indicated by the Geological Survey of India shall be made on
the unit rate of each running metre of holes drill as entered for in
schedule A and shall include cost of drilling 50mm to 74mm holes,
washing of holes conducting in-situ permeability test, cost of all
materials, all leads and lifts and de-lifts initial dewatering, dewatering
during drilling, mobilisation and demobilisation of labour and
equipment and all other operations necessary to complete the
finished item of work as per drawings and as directed by the
Executive Engineer.
8.15.
GROUTING
a)
b)
9.0.
OTHER ITEMS
9.1GRAVEL BACKING
Morum or Gravel backing to rough stone dry packing.
9.1.1. Gravel backing specified thickness to the rough stone dry packing
using the gravel of approved quality including cost and conveyance of
gravel, sampling and testing of gravel, stacking of gravel, seigniorage
b)
c)
d)
Gravel shall be mixed with water on the previous day. Next day
morning it shall be well mixed and worked with mamoties till it can be
formed into stiff plastic walls.
b)
c)
d)
One cubic metre of finished item of work shall not be less than 1.16
cubic metre of stack measurement.
B) PAYMENT:
ROUGH STONE
REVITMENT
DRY
PACKING
FOR
APRONS
AND
SIDE
9.2.1. GENERA:
The specifications for construction of 600mm/ 450mm/ 300mm rough
stone dry packing for aprons and revetments as specified in schedule A and
its materials.
9.2.2. SCOPE
Rough stone dry packing of specified thickness in single layer upto
600mm thick, in two layers for 1000mm (400mm thick layer in the bottom
and 600 mm thick layer on the top) and in three layers for 100 mm thick
using the stone of specified variety for bed pitching/side revetment including
cost and conveyance of stone, sampling and testing of stone, seigniorage
charges, preparation of bed, stacking of stone to departmental gauge for
premeasurements, packing, all leads, lifts, de-lifts, seigniorage charges,
labour charges, and all other operations necessary to complete the finished
item of work to the specifications as per drawings and as directed by the
Engineer-in-charge.
9.2.3. MATERIAL:
The provision of schedule D shall apply
a)
i)
ii)
9.2.5.
i)
a)
b)
c)
The thickness of the apron shall be made with one stone only. Total
thickness shall not be made up in two or more layers.
d)
The stones shall be laid closely in position of the prepared bed and
firmly set with their broadest ends downwards so that they may meet
all round their bases and with the top of the stone level with finished
surface of packing. The stones shall be laid breaking joint as far as
possible in the direction of the flow of water. The stones shall be
placed normal to the surface to be protected.
e)
f)
ii)
a)
b)
Profiles or strings and pegs shall be put up to ensure that the pitching
is done true, straight and to the proper slope throughout.
c)
Revetment shall in all cases be built up from the foot of the bund to
be riveted and built up in courses upward Care is necessary that a
strong toe wall or other protection is always given to the revetment.
Which protective measure shall be shown on the plans.
d)
i)
ii)
iii) Preparation of bed and trimming of the side slopes for laying apron
and revetment to sides shall be deemed to have been included in the
main item and shall not be measured separately unless otherwise
specified.
iv) No extra payment for the construction of template, cross walls in
apron shall be made.
2) PAYMENT:
a)
The tender rate for one cubic metre in the schedule A for finished
work of apron shall include the cost of preparing base, profiles, cost of
all material, conveyance, labour, tools and plants for laying
completing the work according to the drawings and specifications.
b)
The rate for one cubic metre of stone pitching to side slopes in
schedule A shall include the cost preparing the base by trimming,
putting the profiles, laying stone pitching of dry rubble to the
specified thickness, lines, curves, slopes and levels and cost of all
labour and materials including conveyance as well as tools and plants
required for the work in completing the work as per drawings.
ELASTOMERIC BEARING
Value of the
characteristic
Property
Unit
specification
specified
reference
______________________________________________________________________________
____________
1.
Physical Properties
1.1. Hardness
60+5
IRHD
IS:
3400
(Part II)
1.2.
17
Minimum Tensile
MPa
Strength
1.3
400
Minimum Elongather
Maximum Compression
Set
Per cent
IS
(Part I)
Per cent
IS : 3400
(Part X)
duration
temperature
(h)
(deg C)
3400
3400
(Part I)
at break
2.
IS
CR
100+135
3.
+0
to
24.2
Accelerated Ageing
IS : 3400
(Part IV)
duration
temperature
(h)
(deg C)
CR
100+1
3.1 Max change in Hardness
+15
3.2
15
+70
IRHD
-
Strength
3.3 Max change in Elongation
Per cent
40
______________________________________________________________________________
___________
II) ADHESIVE
Adhesive used in bearing location or attachment to bridge decks shall
be subject to the approval by the Engineer. It shall be of high viscosity
resign, which are cold setting and free of solvent. Adhesives shall not be
used to bond layers of cured elastomer.
III) REINFORCEMENT
Mild steel used for plate reinforcement shall comply with the
requirements of IS: 226.
9.4.6. CERTIFICATION
The contractor shall furnish to the Engineer a certificate by the
Manufacturer that, the elastomer and fabric (if used) in the Elastomeric
bearing conform to all the above requirements. The certification shall be
supported by an authenticated copy of the results of tests, performed by the
Manufacturer upon samples of the elastomer and fabric to be used in the
bearings.
9.4.7. GENERAL REQUIREMENTS
(a) Thickness of a single layer bearing shall not exceed 20 percent of the
least plan dimension. The total thickness of a laminated bearing shall
not exceed 40 percent of the least plan dimension.
(b) Thickness of any internal layer of elastomer shall not be less than
6mm, nor greater than 12mm.
(c) The thickness of outer plates shall not be less than 3 mm and that of
inner plate not less than 1.5mm. Metal plates in which dowels are
located shall be in general, not less than 6mm. Thick. The edges of
all plates shall be slightly rounded to approximately 15mm radial.
The metal plates referred above should not be composed of thinner
plates joined together.
(d) Lamination bearing shall have side cover of elastomer of minimum
thickness of 6mm to protect the ends of the steel plates and to give a
reduced surface to that occurring at the edge of the bonded plates
but shall not be considered in evaluation of deformations. The cover
of elastomer at the top and bottom surfaces shall neither less than
3mm nor more than half the thickness of internal layer. The outer
cover at top and bottom surfaces, having thickness less than half that
of a single internal layer and not exceeding 3mm, may be considered
as a simple protection and need not therefore be considered in
calculating deflections.
Where the above elastomer covers are
provided, there is no objection to keep the thickness of top most and
bottom most plates same as that of inner plates.
(e) Bearing shall be set back from the edge of a bearing surface at a
distance not less than the thickness of the layer of Elastomer in
contact with the bearing surface to allow for spreading of the
elastomer under load.
(f) Bearing may be located in position by means of dowels or studs or
their devices, or bonded to the structure with approved adhesives
which shall general be of the high viscosity resin type, cold setting
and free from solvent.
(g) For spans on an inclined grade and without hinge bearings, the sole
plates shall be provided and the same beveled so that the concrete
surfaces and the bearing shall be kept horizontal.
(h) The plan dimensions of the bearings to be finally adopted shall
preferably be selected from series R 20 of IS: 1076-1967.
(i)
(j)
The bearings shall be fully moulded when metal laminations are used.
These laminated Elastomeric bearings shall consist of one or more
elastomer slabs bonded to metal plates so as to from a sandwich
arrangement. Such fully moulded bearings shall be manufactured to
required size.
(k) The Bond between elastomer and metal or fabric shall be such that,
when a sample is tested for separation, failure shall occur within the
elastomer and not between the elastomer and metal or fabric.
9.4.8. INSPECTION AND TESTING
(a) The Contractor shall, whenever required during the course of
manufacture, arrange and offer all facilities for the purpose of
inspection and test of all or any of the materials used therein, any
officer as directed by the Engineer and the bearing OR, similar parts
shall not be used in the superstructure except on the production of
b)
It shall be ensured that bearings are set truly leveled and in exact
position as indicated on the drawing so as to have find and even
bearings on the seat. Thin mortar pads (not exceeding 12mm) may
be made to meet with these requirements.
c)
d)
e)
f)
The concrete surface shall be free from any loose material and
cleaned of any grease, oil paint etc., and it shall be dry at the time of
fixing.
g)
h)
i)
j)
k)
9.4.11.
TOLERANCES:
a)
b)
The rate of each type of bearings shall include the cost of supplying
including labour, material, equipment cost of anticorrosive
applications, cost of samples and their testing as directed by the
Engineer, the cost of adhesive for fixing them, fixing the bearing in
position and also costs of all operations necessary to complete the
work as per the drawings.
9.5.
IS: 459 - 1988 Specifications for concrete pipes with and without
reinforcement (Third revision)
2)
3)
IS:
4)
5)
6)
7)
IS: 5382 - 1985 Rubber sealing rings for gas mains water mains and
sewers (First revision)
8)
OTHER PUBLICATIONS
Ministry of Shipping and Transport Specifications for road and bridge
works N. 7900
9.5.2. SCOPE
The scope for the items include supply, laying joining reinforced
cement concrete pipes including collars of the diameter and lengths
require at the locations as shown on the drawings or as ordered by
the Engineer and in accordance with the requirements of these
specifications.
9.5.3. SUPPLY OF PIPES
a)
Pipes shall be of specified diameter. NP Class conforming to IS: 4581988. Minimum length of the pipe shall not be less than 2.5 Meters.
The contractor shall order and supply the pipes for work on the basis
of the drawings.
The following information shall be clearly marked on each pipe for
acceptance.
i)
Class of pipe
ii)
Date of manufacture
(j)
Trenches shall be kept free from water until the material in the Joints
has hardened. Walking or working on the completed pipe shall not be
permitted until the trench has been back filled to height of at least 45
com over the pipe except as may be necessary for back filling and
compaction.
b)
Trench shall be back filled after pipe has been laid subject to the
condition that jointing material has hardened. Only selected material
shall be used for back filling. Filling of the trench shall be carried out
simultaneously on both sides of pipe in such a manner that unequal
pressure does not occur.
c)
The cement concrete for pipe bedding and around joints shall be
provided as per drawings. The specifications of concrete mix shall be
as per the relevant specification N. 4.0
to be laid and deposited in layers of 150 mm thick and shall be well rammed
in position with wooden or iron rammers.
The finished surface of morum shall be left untouched until it dries up
and does not show signs of yielding.
MEASUREMENT:
Dimensions shall be measured to the nearest 0.01 meters and volume
worked out to the nearest 0.01 cum.
RATE:
The rate shall be for a unit of 10 cum and shall include all
operations of quarrying, transporting, watering, mixing, puddling and
laying in a position, ramming etc., complete. The rate shall include
cost and conveyance of water and earth with all leads lifts and de-lifts
and all other operations necessary to complete the finished item of
work as per drawings and as directed by the Engineer-in-Charge.
9.7. PROVIDING AND FIXING IN POSITION 25 MM EXPASION JOINTS
WITH 300 MM WIDE P.V.C. WATER STOPPERS AT JOINTS IN
BARRELS AND WING WALLS ETC. INCLUDING APPROVED JOINT
FILTER.
9.7.1. GENERAL
a)
Polyvinyl Chloride (PVC) water stops shall normally have a centre Bulb
of 12.4 mm inside diameter and 25 mm out side diameter. It shall be
300 mm width and shall have minimum of two or three longitudinal
ribs on each side of the bulb evenly distributed between the bulb and
the edge of the Water stop, Each rib being 635 mm heigh and the rib
adjacent to the edge shall have a web thickness of 12.5mm and the
rib adjacent to the edge shall have a web thickness of 10mm and the
Contractor however, will be permitted to use water stops of any
alternative manufacture, such as water stops with diamond shape and
bulb provided, they conform to the specifications and the functional
and constructional requirements. For this purpose, the Contractor
shall submit to the Engineer for approval, four sets of drawings
showing details of the water stops, including dimensions, shapes and
details of intersections and splices between water stops of the same
size and of different sizes. Fabrication and procurement of materials
shall be made only after the approval of the drawing by the Engineer.
Any fabrication or procurement of material performed prior to
approval of the drawings shall be at the Contractors risk. The
Engineer shall have the right to ask the Contractor to make any
changes in the drawings, which may be necessary to make the
finished installation conforming to the requirements and intent of
these specifications without additional cost. Approval by the Engineer
to the Contractors drawings shall not relieve the Contractor of his
obligation to meet all the requirements of these specifications or of
the responsibility for the correctness of the Contractors drawings.
b)
c)
The water stops shall be dense, homogeneous and free from holes
and other imperfections. The water stops shall meet the material and
test requirements given hereinafter. The cross section of the water
stops shall be uniform along its length and the thickness shall be
symmetrical transversely. Tolerance for the dimensions given above
shall be plus 5mm in width, plus 2mm in thickness and plus 1mm for
other dimensions.
d)
e)
The contractor shall arrange to obtain the water stops from the
supplies in rolls securing packed, containing a single length of not less
than 12 linear meters and having inside diameter of not less than 0.3
meter.
9.7.2. MATERIALS
a)
b)
i)
ii)
116 Kg/sq.cm
300%
49kg/Sq.cm
24.6 Kg/Sq.cm
v)
Accelerated extraction
24.6 Kg/Sq.cm
105 Kg/sq.cm
250%
viii) When tested in accordance with the effect of alkali test as described
in the following paragraphs, the material shall not shown an increase
in weight of more tan 0.25 percent or a loss in weight of more than
0.10 percent after 7 days, or more than 0.40 percent increase in
weight or more than 0.30 percent loss in weight after 28 days. After
28 days immersion the dimensions of the samples shall not differ
from those of the original sample by more that than 1.0 percent.
After 7 days immersion, the Durometer hardness reading of the
sample shall not differ by more than plus or minus 5 from reading the
original sample.
ix) When tested in accordance with the cold bend test described in the
following paragraph, the material shall show no signs of cracking or
hipping.
9.7.3. INSPECTION AND TESTS:
a)
b)
c)
d)
i)
ii)
iii)
iv)
v)
vi)
vii)
9.7.4. INSTALLATION:
a)
Additional vibration, over and above that used for adjacent concrete
placement, shall be carried out to assure complete embedment of the
water stop in the concrete. Large pieces of aggregate near the water
stop shall be removed in hand during embedment to assure complete
contact between the water stop and the surrounding concrete.
Splices in the continuity or at the intersection of junctions of PVC
water stops shall be performed by heat scaling the adjacent surface
in accordance with the Manufacturers recommendations.
A
thermostatically controlled electric heat source shall be used to make
all splices. The correct temperature at which splices should be made
will differ with the material compounds but should be sufficient to
melt. All splices shall be neat with ends of the joined water stops in
true alignment. A meter box guide and portable saw shall be
provided and used to cut the ends to be joined to ensure good
alignment and contact between joined surfaces. After splicing a remoulding iron with ribs and corrugations to match the pattern of the
water stop shall be used to reform the ribs at the splices. The
continuity of the members of the cross sections of the water stop (ribs
tubular center axis, protrusions and the like) shall be maintained
across the splices.
c)
Where splices are required between water stops of different sizes, the
splices shall be made as recommended by the manufacturer of the
water stops and drawings showing the details of the splices shall be
submitted to the Engineer for approval as required in paragraph
General above.
d)
In case of pipes, where the length of pipe falls short of the required
length, it shall be joined with necessary collars in CM 1:3 or as
directed by the Engineer to form a continuous hole in the body of
wall.
c)
Defective work shall not be paid. The interior of the weep holes shall
be free from all sand, mortar, stone pieces, dirt and other foreign
matter. Care shall be taken to prevent entrance of any foreign matter
into the weep holes during progress of the work.
9.9.1. SCOPE:
The waterspout shall be 100mm internal dia G.I. pipes. The pipe shall
be of medium grade used for domestic water supply conforming to IS: 1239
(Part. 1) - 1979 and shall also bear the mark of certification issued by the
Bureau of Indian Standards. The wall thickness shall be 4.5mm. The spouts
shall project at least 10cm outside the concrete and shall be rigidly fixed. A
cast iron grating shall be provided at the entry of the waterspout and shall be
fixed in the recess so as to be flush with the road surface. The grating shall
be painted with two coats of anticorrosive black bitumen paint. The quantity
and the size of the grating shall be got approved from the Engineer.
9.9.2. MEASUREMENT AND PAYMENT:
Measurement for payment shall be per number of water spouts fixed.
Payment at the unit rate mentioned in schedule A shall include cost of all
materials, labour, tools and incidental operations to complete the work as per
the specifications.
9.10
The coping slabs shall be precast with M-10 grade concrete using not
less than 220.00 Kgs of cement per cubic meter of concrete with
machine crushed graded aggregate of 40mm maximum size.
b)
c)
d)
9.11. RAILINGS:
9.11.1 General:
Railings shall not be placed until the centering of false work for the
span has been released and the pan is self-supporting.
The type of railing to be constructed shall be as shown on the
drawings.
The railing shall be carefully erected true to line and grade. Posts shall
be vertical within a tolerance not to exceed 6mm in 3 meters.
9.11.2 .
METAL RAILING:
All pipes used for railing shall be wrought iron, and all steel elements
shall be galvanized.
All complete steel rail elements, terminal sections posts, bolts, nuts,
hardware and other steel fittings shall be galvanized or painted with an
approved paint.
a)
b)
c)
9.11.4.
a)
PRECAST RAILING:
9.11.5.
General
a)
No material shall be used for construction in any work until
notice has been given by the Executive Engineer that the test results
are satisfactory. No oral instruction should be followed.
b)
Recommendation of stacking and storage of construction
materials at site shall be in accordance with IS: 4082-1977.
c)
To be the best Quality: All materials, articles, and
workmanship shall be the best of their respective kinds for the class
of work described in the contract specifications and schedule. The
word best as used in the specifications shall mean, that in the
opinion of the Executive Engineer there is no superior quality of
material or finish of articles on the market and that there is no better
class of workmanship available for the nature of the particular item
described in the contract schedule. The contractor shall upon the
request of the Executive Engineer, furnish him with the vouchers to
prove that the materials are such as are specified.
1.1.2.
1.1.3.
1.2.
SAMPLES
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5.
PROCUREMENT
1.3.1
The rates quoted for all items shall include cost and conveyance of all
materials with all leads.
1.3.2
1.3.3
1.3.4
The contractor shall make his own enquiries regarding the availability
of other materials and make his own arrangements for procuring
them.
1.3.5
1.3.6
1.3.7
The contractor has to open and develop the quarry for the stone and
aggregate required. All incidentals such as removal of over burden,
stripping etc. in the quarry should be done by the contractor. The
contractor shall make his arrangements for maintaining the approach
roads to quarry for conveying the materials to site of work.
1.3.8
1.3.9
The tenderer should inspect the site and check-up the possible water
source for carrying out the entire work throughout the year in
monsoon and non-monsoon seasons irrespective of the quantum of
DEFECTIVE MATERIAL:
1.4.1
1.4.2
The rejected rubble and spoils should be dumped far away from work
spot as directed by the Engineer in charge. The muck, boulders etc.
fallen on the approach roads, ramps, etc. below the place should be
removed by the contractor immediately after blasting at the
contractors cost. In case the above materials are not cleared within
24 hours of issue of departmental instructions, the same will be
removed by the Department and the cost thereof will be recovered
from the contractors bills.
1.4.3
The Dept. will not be liable for any compensation due to breakdown in
machinery, water supply or electricity or delay in supply of materials
and for damage due to rains and floods.
1.4.4
The Executive Engineer shall have power to reject at any stage, any
work which he considers being defective in quality of material or
workmanship and he shall not be debarred from rejecting wrought
materials by reason of his having previously passed them in not
worked condition. Any portion of the work or materials rejected or
pronounced to be inferring or not in accordance with the drawings
and specifications shall be taken down and removed from the worksite at the contractors expense, within 24 hours after written
instructions to that effect have been given by the Executive Engineer.
Replacement shall at once be made in accordance with the
specifications and drawings, at the contractors expense.
1.4.5
persons to carry out the orders at the contractors risk and all
expense consequent thereon and incidental thereto shall be borne by
the contractor.
1.4.6
LABORATORY SETUP:
1.5.1.
For the works costing Rs. 50.00 lakhs and above the contractor shall
setup a laboratory and equip the same with adequate equipment and
personnel in order to carry out all required tests and Quality Control
work as per specifications or as directed by the Engineer. The internal
layout of the laboratory shall be as given in the drawing and list of
equipment shall be got approved from the Engineer in advance.
1.6.1.
1.6.2.
The material, mixes and cores etc., shall be tested day to day
periodically at the laboratory available at the site or at other
laboratory or place that the Executive Engineer may direct and the
results given thereby shall be considered correct authentic by the
contractor. It shall then be the contractors responsibility to execute
work to the standard, based on the laboratory designs and tests.
1.6.4.
The contractor shall provide proper facilities at all times, for the
testing of materials, and inspection of work by the Engineer in charge,
and the Engineer in charge shall accordingly also have access at all
times to the place of storage or manufacture where materials are
being made for use under the contract to determine that manufacture
is proceeding in according with drawings and specifications.
1.6.5.
The contractor shall, upon demand, also forward for the Executive
Engineers inspection, test certificates supplied by the vendors, when
he is purchasing consignments of cement, steel and other materials in
respect of which such certificates are usually available.
2.1.
2.1.1.
2.1.2.
2.1.3.
2.2. CEMENT:
2.2.1.
2.2.2.
The contractor has to purchase the cement on the name of work and
on the name of contractor. The cement without mentioning the above
two names will not be accepted. Vendors test certificates and
weighment bills are to be furnished to the Executive Engineer. Any
quantity purchased without test certificate will not be accepted for
use on the work.
2.2.4.
a)
The contractor should procure the cement, required during the
next 30 days, at least a fortnight in advance to facilitate conducting
test on the quality of cement, so brought to site and shall be stored in
accordance with clause No.112 of APSS The contractor shall forth with
remove from the work site any cement that the Engineer in charge
may disallow for use on account of its failure to meet with the
required standards.
b)
No cement procured by the contractor shall be used in any work
until notice has been given by the Executive Engineer, that test
results are satisfactory. Physical and chemical requirement shall
conform to IS: 269-1989.
c)
The contractor has to furnish the test certificates and samples
for testing of each batch and each consignment to the Executive
Engineer immediately after receipt of cement into the godown for
verification and testing.
2.2.5.
2.2.6.
2.2.7.
2.2.8.
2.2.9.
a)
b)
The height of stack shall not ordinarily be more than 10 bags and in
no case more than 15 bags (except for very short periods) to prevent
possibility of lumping up under pressure. Cement bag shall be
stacked in a manner to facilitate their removal and use in the order in
which they are received.
c)
d)
e)
2.3.
STEEL:
2.3.1.
The contractor has to purchase the steel on the name of work and on
the name of contractor and furnish the same Executive Engineer. The
steel with out mentioning the above two names will not be accepted,
vendors test certificates and weighment bills are to be furnished to
the Executive Engineer. Any quantity purchased without test
certificates will not be accepted for use on the works.
2.3.4.
2.3.5.
______________________________________________________________________________
_________
Sl.
meter
No
______________________________________________________________________________
___________
1.
6 Millimeters
0.22
2.
8 Millimeters
0.39
3.
10 Millimeters
0.62
4.
12 Millimeters
0.89
5.
14 Millimeters
1.21
6.
16 Millimeters
1.58
7.
8.
18 Millimeters
20 Millimeters
2.00
2.47
9.
22 Millimeters
2.98
10.
25 Millimeters
3.85
11.
28 Millimeters
4.83
12.
32 Millimeters
6.31
13.
33 Millimeters
6.71
14.
36 Millimeters
7.99
15.
40 Millimeters
9.86
16.
42 Millimeters
10.88
Note: If any rods other than those specified above are used, the weights shall
be as per standard steel tables.
2.3.6. PROCUREMENT
a)
and
samples
for
testing
for
each
batch
and
each
Storage:
2.4.
BLASTING MATERIALS
2.4.1.
mentioning the above two names on the bills will not be accepted.
2.4.2.
materials etc., that are proposed to be used in the blasting operations shall
have the prior approval of the Engineer. Only explosives of required make and
strength are to be used.
Black powder and safe explosives shall be used wherever possible.
Explosives with nitro-glycerin shall be used where the above explosives are
not effective.
The use of use with only one protective coat is prohibited., The fuse
shall be sufficiently water resistance as to be unaffected when immersed in
water for thirty minutes. Rate of burning of the fuse shall be uniform and not
less than 25 millimeters of length per 4 seconds with 10% (ten percent)
tolerance on either side. The fuse known as instantaneous fuse shall not be
used.
The fuse shall be inspected before use and the moist, damaged or
broken ones discarded. The rate of burning of all new types of fuses shall be
examined.
When they have been in stock for a long time, they shall be
not to put their feet on the clear floor unless they have the magazine
shoes on :
(ii) not to allow the magazine shoes to touch ground outside the clean
floor:
(iii) not to allow any dirt or grit to fall on the clean floor.
Persons with bare foot shall, before entering the magazine, dip their
feet in water and then step direct from tub over the barrier (if there be one)
on the clean floor.
A brush or broom shall be kept in the lobby of the magazine, for
cleaning the magazine on each occasion it is opened for the receipt, delivery
or inspection of explosives. No matches or inflammable material shall be
allowed in the magazine. Light shall be obtained from the electric storage
battery lantern.
No person having articles of steel or iron on him shall be allowed to
enter the magazine.
b)
c)
d)
2.5.
STONE FOR MASONRY:
2.5.1. GENERAL
2.5.2.
Type of Stone
1.
Granite
2.
Basalt
400 Kg/Sq.cm.
3.
Lime Stone
200 Kg/Sq.cm.
2.5.11. Stone for coursed face work: The height of the stone for face work
shall be uniform and is recommended to be 300 mm including mortar joint.
The length and depth of the face stone shall not be less than the height of
the stone. At least 50 percent of the stones shall have length more than
twice the height of the stone. At least one third of the stones shall be bond
stones projecting not less than 2 1/2 times the height into the masonry. The
remaining shall be header stones with depth not less than 1 1/2 times the
height of the stone. The stones shall hammer dressed on face and one line
chisel dressed on bed, top and sides for a minimum depth of 75 mm upto,
which the stones shall be true and rectangular. Beyond 75mm depth, the
stones may be tapered but the tail end of the stones shall have at least half
the area of the face.
Bushing on the faces of the stones shall not project more than
40mm.
2.5.12.
HEADER STONES
The header stones shall not be less than 300mm in length, one and
half times in depth.
2.5.13.
STRETCHER STONES
The stretcher, stones shall not be less than 600mm in length and not
less than its height in depth.
2.5.14.
QUOINS:
Quin stones shall be of the same height as the faces but shall be true
and rectangular on two faces with the face dressing for 75mm depth in beds
and sides. The stone shall be at least 300 mm long on one face and 450 mm
on the other face.
2.5.15.BOND STONES:
The bond stones shall not be less than 300 mm in length and two and
half times its height in depth.
2.5.16.
Stone for uncoursed face work: Stones for uncoursed face work
shall be selected from stones meeting the requirement of stones for coursed
face work (See 5.11) except that the stones shall be hammer dressed. The
stones shall be nearly rectangular.
2.5.17.
Stone shall be used from the surplus useful excavated rubble or from
the approved quarries if required, and shall be subject to through inspection
and approval by the Engineer. The bed pitching material shall consist of the
most durable rock fragments of approved quality selected for the purpose.
The stone shall be sound, hard, dense, resistant to abrasion, durable, and
free from segregation, seams, cracks, shale partings weathered portions,
conglomerate bands and other structural defects or imperfections tending to
affect their soundness and strength.,
quarried with sharp edges and clean faces. They shall be free from rounded,
worn or weathered surfaces or skin or coating.
hours shall not absorb water by more than 5% of their weight when tested as
per IS: 125-1974 or its Latest edition.
2.5.18.
SIZE OF STONE
In no case any
fragment shall weigh less than 40 Kg. The specific gravity of stones shall be
as high as possible and it shall not be less than 2.50.
Unless otherwise specified, for revetments upto 450mm thickness,
the length of the stone shall be equal to the revetment thickness.
For
revetment over 450mm thick at least 50% of the stones shall be 450mm
long. No stone shall have any dimension less than 150mm or less than 50%
of the maximum dimension of the stone.
The minimum volume of the individual stones used for various
thickness of revetments shall be as follows:
Thickness of revetment
Volume of stones.
225 mm
0.015 Cum
300 mm
0.015 Cum
450 mm
0.030 Cum
600 mm
0.045 Cum
2.5.19. STACKING.
ii)
COARSE AGGREGATE
2.6.1. GENERAL
For the purposes of these specifications, the term Coarse Aggregate
designates clean well graded aggregate most of which is retained on 4.75mm
I.S. Sieve and containing only so such finer materials permitted for various
types described under clause 2.2 of I.S.383-1970. Coarse aggregate for
concrete shall consist of uncrushed gravel for stone, crushed gravel or stone
and partially crushed gravel or stone. Course Aggregate shall generally have
uniform and stable moisture content. In case of variations, clause 9.2.3. Of
I.S.456-1978 shall govern during batching.
2.6.2. QUALITY
The coarse aggregate shall consist of naturally occurring (crushed or
uncrushed) stones and shall be hard, strong, durable clear and free from
veins and adherent coating and free from injurious amounts of disintegrated,
pieces alkaline aggregate will be rejected if it fails to meet any of the
following requirements.
2.6.3. LOS-ANGLES ABRASION TEST:
The abrasion value of aggregates when tested in accordance with the
method specified in I.S.2386 (part-IV) using Los-Angles machine shall not
exceed 30% for aggregates to be used in concrete for wearing surface and
50% for Aggregates to be used in other concrete.
b)
Nominal sizes and Corresponding grading for single size and graded
aggregates.
IS Sieve
passing
Graded
Percentage
by weight for
aggregated of nominal size
2
11
10
80mm
100
--
--
--
--
--
--
100
--
63mm
85-100
--
100
--
--
--
--
--
--
--
40mm
0-3085
--
100
100
--
--
--
95-100
100
--
20mm
0-5
100
0-20
100
85-100
100
--
--
16mm
100
---
--
--
85-100
100
--
--
--
90-
-90-100
--
--
--
85-100
100
--
--
--
0-5
40-85
0-5
0-20
0-30
0-45
4.75mm
10
-0-10
--
0-5
0-5
0-10
0-20
0-5
0-10
0-
2.36mm
---
--
--
--
--
0-5
--
--
--
12.5mm
10mm
70
30-70 95-100
d)
III) STORAGE
a)
Deleterious Substances
2.7.9. The amounts of deleterious substances in sand shall not exceed the
maximum permissible limits prescribed in table I Clause 3.2.1. of I.S.383 1970 (Indian Standard Specification for coarse and fine aggregates from
natural source for concrete) when tested in accordance with I.S. 2386-1963.
2.7.10.
GRADING: Sand for mortar shall conform to the grading of
sand given in Clause 4 of I.S.2116-1980 as indicated below.
Grading of Sand for use in masonry mortars
I.S. Sieve designation
Percentage by weight passing by
mass
4.75 mm
100
2.36 mm
90 to 100
1.18 mm
70 to 100
600 micron
40 to 100
300 micron
5 to 70
150 micron
0 to 15
2.7.11. Sand whose grading falls out-side the specified limits due to excess
deficiency of coarse of fine particles may be processed to comply with the
standard by screening through a suitably sized sieve and/or blending with
required quantities of suitable size sand particles. The sand for concrete as
batched shall be well graded and when tested by means of standard sieves
shall conform to the limits given in table-4 of I.S.383-1970 and shall be
described as Fine aggregates, grading zones - I, II, III and IV. Sand complying
with the requirements of any of the fourth grading zones is suitable for
concrete. But, sand conforming to the requirements of grading zone-IV shall
not be used for reinforced cement concrete work.
2.7.12.
FINENSES MODULUS:
a)
Sand shall have a fineness modulus between 2.4 to 3.0 subject to the
gradation specified in the preceding paragraph.
b)
STORAGE
All sand shall be stored on the site of work in such manner as to
prevent intrusion of foreign matter.
2.8.
2.8.1. The filter material shall consist of clean, sound and well graded sand
and crushed rock. The materials shall be free from debris, organic matter
and other deleterious matter. It shall be ensured that the surface over which
the filter is to be laid has been well consolidated to not less than 95 percent
of proctors density.
2.8.2. The filter materials in contact with earth or foundation soil shall be of
any available clean, well graded sand having a maximum size of 6mm. This
shall be over laid with well graded, hard durable coarse aggregate of size
10mm to 75 mm. IN contact with rock fill, riprap shall be used.
2.9.
2.10.1. Rock fill shall consist of sound, durable and well graded broken rock
obtained from approved from excavation of work and / or from
approved quarries and shall be approved prior to being transported to
the areas of deposition., The materials shall range in size from 75mm
to 450mm. However, no load shall contain more than 15 percent by
volume or rock fragments smaller than 75mm in size All brush roots,
or other perishable materials shall be removed from rock fill during
the spreading.
2.11
.WATER
2.11.1. The water used in making and curing of concrete, mortar and grout
shall be free from objectionable quantities of silt, organic matter
injurious amounts of oils, acids, salts and other impurities etc., as per
I.S. Specification No. 456-1978. Potable water generally considered
satisfactory for mixing and curing.
2.11.2. The Engineer-in-charge will determine whether or not such quantities
impurities are objectionable.
2.11.3. Such determination will usually be made by comparison of
compressive strength, water required, time of set and other
properties of concrete made with distilled or very clean water and
concrete made with the water proposed for use. Permissible limits for
Organic
2.
Inorganic
3000mg/litre
3.
500 mg/litre
works
works
Suspended matter
2000 mg/litre
.ADMIXTURES/AIR-ENTRAINING AGENTS:
. STORAGE OF MATERIALS.
Storage of materials shall conform to the I.S.458 - 1978 and I.S.
457 - 1957.
payment shall be limited to the total price quoted by the contractor against each item of works.
WELL FOUNDATIONS
3.1.40. DESCRIPTION:
This work consists of construction of well foundation, taking it down to the founding level
through all kinds of sub-strata, plugging the bottom, filling the inside of the well, plugging the top and
providing a well cap in accordance with the details shown on the drawing and as per these specifications, or
as directed by the Engineer.
In case of well foundations of size larger than 12m diameter, supplemental construction
specification will be necessary.
3.1.41. GENERAL:
(a) Wells may have a circular, rectangular, or D-shape in plans and may consist of one, two or
more compartments in plan. The outer well of the well is known as well staining, which may be cellular.
The process of taking down the well to the founding level is known as well sinking. After
reaching the founding level, the hollow inside the well (Dredge hole) is plugged at the bottom by concrete
(bottom plug). The dredge hole is then filled with approved filling upto the level indicated on the drawings
and provide with a concrete plug (Top plug).
To facilitate sinking of well, steel cutting edges is fabricated and connected to a concrete well curb
of required shapes. On top of the well curb, adequate height of well staining is cast and the process of
sinking is carried out. After a portion of the well has been sunk, another height of well staining in cast on
top of the previous section and further sinking carried out. This process is continued till the bottom level of
the well reaches the founding level.
At the top of the well staining, an adequately designed well cap is laid which transmits the loads
and forces from the Sub-structure (Piers abutments) to the foundations.
(b) At least one borehole must be available / carried out in accordance with these specifications at
each well foundation location, prier to commencement of work. The depth of boreholes should extend upto
a depth equal to one and a half time the outer diameter/least dimension of the well below the anticipated
founding level. The results of soil exploration should be presented in accordance with SS 3.1.12 in case the
well foundation is to rest on a rocky strata, it may be necessary to undertake additional borings/probing
prior to commencement of work to ascertain the actual profile and the quality of the rocky state, at the level
of which the well has to be seated etc.
Blasting may have to be resorted to in order to facilitate sinking through difficult strata, such as
boulders and rocks etc. In case blasting in anticipated, protective/strengthening measuring specified in SS
3.3 shall be taken. The grade of concrete in bottom 3 meters of staining shall not be leaner than M 20 or as
shown on the drawings.
(d) In case the borehole data shows the presence of steeply dipping rock, chiseling may have to be
resorted to so as to obtain proper seating of the foundation. For this purpose, the well may require to be
dewatered completely under high air pressure inside the well. This process is known as pneumatic sinking.
Pneumatic sinking may also have to be resorted to in cases where obstacles such as tree trunks, large size
boulders or hard strata etc., not be removed by open dredging. The necessity of adopting pneumatic
sinking shall be decided by the Engineer.
The curb and steining have to be specifically designed for special leading when pneumatic sinking
is added.
3.1.42
SETTING OUT AND IREPARATIONS FOR SINKING:
(a)
Necessary reference points shall be fixed, away from the Zone of blow-ups or possible settlements
resulting from well sinking operations.
Such references points shall be connected to the
permanent theologize stations with the base line on the banks. The center of the individual wells
shall be marked with reference these stations. The distance, wherever practicable, shall be
checked with the help of accurate tapes and precision distomat.
Reference points shall also be fixed to mark X-X axis (usually canal flow direction) and Y-Y axis
(normal to X-X axis) accurately.
A temporary benchmark shall also be established near the well foundation, away from the zones of
blow-ups or possible settlement. The benchmark shall be checked regularly with respect to the
permanent benchmark established at the Aqueduct site.
(b)
For wells, which are to be pitched in water, an earthen or sand island shall be constructed. Sand
islands are practicable for water depths of about 5 M under stable bed soil conditions. For greater
depths or in fast flowing rivers or for locations where soil is too weak to sustain Sand Island,
floating caissons may have to be adopted.
The plan dimensions of sand islands shall be such as to have a working space of at least 2 meters
all around the steining. The dimension of the sand island shall-however be not less than
twice___________________________
The dimension in plan of the well or caisson. Sand islands shall be maintained to perform their
functions, until the well is sunk to a depth below the bed level at least equal to the depth of water.
Sand Island shall be protected against scour and the top level shall be sufficiently above
the prevailing water level to be decided by the Engineer so that it is safe against wave action.
While Sand Island is constructed at well location, floating caissons are generally
fabricated at or near the banks on dry land or dry docks. Floating caissons are towed into position
in floating caissons are towed into position in floating condition.
Floating caissons may be of steel, reinforced concrete or combination of the two. They
should have at least 1.5m free board above water level and increased, if considered necessary, in
case there is a possibility of caissons sinking suddenly owing to reasons such as scour likely to
result from the lowering of caissons, effect of waves, sinking in very soft strata etc.,
Stability of floating caissons shall be ensured against over turning and capsizing while
being towed and during a sinking for the caution of water current, wave pressure, wind etc.,
For floating caissons, a detailed method statement for fabrication, floating and sinking of
caissons shall be prepared and furnished to the Engineer. Such statement shall include the total
tonnage of steel involved, fabrication and welding specifications, list of materials and plant and a
description of operations and manpower required for the work., The caisson shall be tested for
leakages before being towed to site.
EQUPMENT:
Equipment shall be deployed for construction of well foundation as required and as
directed by the Engineer. Generally, the following equipment may be required for the work.
i)
ii)
iii)
iv)
v)
vi)
vii)
3.1.43.
CUTTING EDGE:
(a)
The mild steel cutting edge shall be made from structural steel sections.
The cutting edge shall weigh not less than 40 Kgs. Per meter lengths
and he properly anchored into the well curb, as shown in the drawing.
When there are two or more compartments in a well, the bottom end of the cutting edge of the
inner walls of such wells shall be kept at about 300mm above that of outer walls.
(b)
The cutting edge shall be laid about 300mm above prevalent water level.
3.1.43
WELL CURB:
a)
The formwork on outer face of curb may be removed within 24 hours after concreting.
formwork of inner face shall be removed after 72 hours.
(c)
The
.
3.1.44
.WELL STEINING:
(a)
The dimensions, shape, concrete strength and reinforcements of the well shall strictly conform
to those shown on the drawings. The formwork shall preferably be of M.S. Sheets shaped
and stiffened suitably. In case timber forms are used, they shall be lined with plywood or
M.S. Sheets.
(b)
Steining built in the first lift above the well curb shall not be more than 2 meters and in
subsequent lifts if shall not exceed the diameter of the well or the depth of well sunk below
the adjoining bed level at any time. For stability, the first lift of steining shall be cast only
after sinking the curb at least partially for stability. Concreting of steining may be carried out
in subsequent lifts of about 2 to 2.5 meters. Attempts should be made to minimize the
number of construction joints. The concreting layers shall be limited to about 450mm
restricting the free fall of concrete to not more than 1.5m Laitance formed at the top surface of
a lift shall be removed to expose coarse aggregates before setting of concrete at the proposed
construction joint. As per as possible, construction joints shall not be kept at the location of
lapse in the vertical steining bars.
(b)
The steining of the well shall be built in the straight 1m from bottom to top such that if the wall is
tilted, the next
of steining will be aligned in the direction of the tilt. They will be checked
carefully with the said of straight edges of lengths approved by the Engineer. Plumb bob or spirit level
shall not be used for alignment. After sinking of a stage is complete, damaged portions if any, of steining
at top of the previous stage shall be properly repaired before constructing the next stage.
(c)
The height of steining shall be calibrated by making at least 4 gauges (preferably in canal
flow direction and in a direction normal to canal flow direction) distributed equally on the
outer periphery of the well each in the form of a 100mm wide strip painted on the well, with
every meter mark shown in black paint. V The gauges shall start with zero at the bottom of
the cutting edge. Marking of the gauges shall be done carefully with a steel tape.
(d)
After reaching the founding level, the well steining shall be inspected to check for any damage or
cracks. The Engineer will direct and the contractor shall execute the remedial measures before acceptance
of the well steining. In case the well cannot be accepted even with any remedial measures, then the well
shall stand rejected.
(B) Use of Kent ledge as Sinking load.
Kent ledge shall be placed in an orderly and safe manner on the loading platform and in such a
way that it does not interfere with the excavation of the material from inside the dredge hole and also does
not in any way damage the steining of the well.
Where tilts are present or there is a danger of well developing a tilt, the position of the load shall
be regulated in such a manner as to provide greater sinking effort on the higher side of the well.
Use of Water jetting.
Water jetting may be employed for well sinking wherever necessary.
(d)
Use of Explosives.
All prevalent laws concerning handling, storing and using of explosives shall be strictly followed.
All safety precautions shall be taken as per IS 4081 Safety code for Blasting and related Drilling
operations to the extent applicable, whenever blasting is resorted to.
There should be no equipment inside the well nor shall there be any labour in the close vicinity of
the well at the time of exploding the charges.
If rock blasting is to be done for seating of the well, the damage caused by flying debris should be
minimized by covering blasting holes by rubber mats before blasting.
(e)
Use of divers:
Use of divers may be made both for sinking purpose like removal or obstructions, rock blasting and for
inspection. All safety precautions shall be taken as per any acceptable safe code for sinking with
divers or any statutory regulations in force.
Only persons trained for the diving operation shall be employed and shall be certified to befit for
diving by an approved doctor.
They shall work under expert supervision.
The diving and other equipments shall be of
acceptable standard and certified to this effect by an approved independent agency. It shall be well
maintained for safe use.
Arrangement for sample supply of low-pressure clean cool air shall be ensured through an
armored flexible hosepipe stand by compressor plant shall be provided in case of breakdown.
Separate high-pressure connection for use of pneumatic shall be made. Electric lights w\here
provided shall be at 50
(maximum). The raising of the diver from the bottom of wells is
controlled so that decompression rate conforms to the rate
laid down in appropriate regulations.
f)
i)
The Engineer shall familiarize himself with particular reference to caisson diseases and working of the
medical air lock. A Doctor competent to deal with cases of Caisson Diseases or other complications
rising as a result of working under high pressure shall be stationed at the construction site when
pneumatic sinking is under progress.
The Contractor shall provide complete facilities including the issuing of orders to ensure strict
enforcement of the equipments outlined in these specifications.
A safety provision as contained in IS 1138 and these specifications shall be strictly followed.
Pneumatic sinking shall be restricted to a depth of 30.0m.
ii)
Locks, reducers, and shaft used in connection with casing shall be of reverted construction throughout.
The material used in their manufacture shall be steel plate with thickness not less than 6 mm.
Shafts shall be subjected to hydrostatic or air pressure test of at least 0.5 Mpa, at which pressure
they shall be tight. The pressure at which testing has been done shall be clearly and visibly displayed.
Shafts shall be provided, with a safe, proper and suitable staircase for its entire length including
landing platforms, which are not more than 6 metres apart. Where this is impossible due to space
constraint, suitable ladders along with landing platforms shall be installed. These shall be kept clear
and in good condition at all time and shall be constructed, inspected and maintained to the entire
satisfaction of the Engineer.
A.1.o m wide platform with 1.0 m high railing shall be provided, all round the caisson air locks.
Where 15 or more man are employed, caissons shall have to locks, one of which shall be use dasa
man lock.
Locks shall be located so that the lowest part of the bottom door shall not be less than1 metre
above high water level.
The supply of fresh air to the working chamber shall at all times be sufficient to permit work to be
done without any danger or excessive discomfort. All air supply lines shall be supplied with check
valves and carried as near to the face as practicable.
A man-lock shall be used solely for the compression or de compression of persons, and not for the
passage of plant and shall be maintained in a reasonably clear and sufficiently term state. However,
any hand tool or hand instruments used for the purpose of the work may be carried in to the man-lock.
Where it is not reasonably practicable to provide a separate man-lock for use by persons only, the
lock when it is in actual use for compression or decompression of a person of persons shall not be put
simultaneously, to any other use and shall be in a reasonably clean and sufficiently war state.
iii)
Valves:
Exhaust valves shall be provided, having risers extending to the upper part of the chamber. These
shall be operated, whenever necessary especially after a blast. Precautions shall be taken that men and
not allowed to resume work after a blast until the gas and smoke are cleared.
iv)
Every employee absent from work for 10 or more consecutive days due to illness or any other
disability shall be required to pass the regular physical examination by the doctor before being
permitted to return to work.
After a person has been employed continuously in compressed air for a period of 2 months. He
shall be re-examined by the doctor and shall not be permitted to work until such re-examination has
been made and the report in satisfactory.
No person known to be addicted to the excessive intoxicants
shall be permitted to work in compressed air.
The doctor shall, at all times keep a complete and full record of examination made by him, which
shall contain dates of examination, a clear and full description of the person examined, his age and
physical condition at the time of examination and a statement as to the period such a person has been
engaged in such employment. Records shall be kept at the place where the work is in progress and
shall be subject to inspection by authorised officers.
Every man lock shall always have a doctor or a responsible person in attendance. In case the
person in charge is note doctor he must have positive means of promptly communicating with and
securing the services of a competent doctor in case of emergency. Such arrangements shall invariably
be subject to the approved of the Engineer.
If the air pressure exceeds 0.2 Ta gauge of if 50 o9rmore men are employed, it is obligatory for the
person in charge of medical lock to be a doctor experienced in this type of work.
All cases of compressed air illness shall be reported and copies of all such reports shall be kept on
file at the place of work.
(ii) Lighting:
All lighting in compressed air chambers shall be operated only by electricity. Two independent
electric lighting systems with independent sources of supply shall be used. These shall so arrange that
the emergency source shall become automatically operative in case of failure of the regularly used
source.
The minimum intensity of light on any walkway ladder, stairway, or lower working level shall be
one quarter (1/4) candlepower. In all work places, the lighting shall always be such as to enable
workmen to see their way about clearly.
All external parts of lighting fixtures and electrical
equipment lying with the 2.5 metres above the floor shall be constructed of non-combustible nonabsorbing insulating materials. If metal is used it must be effectively earthed. Portable lamp shall
have non-combustible non- absorbing insulating sockets, approved handles, bucket guards and
approved cables. The use of worn of defective portable and pendant conductors, shall be prohibited.
(vi)
No oil, gasoline, or other combustible material shall be stored within 30 metres of any shaft,
caisson, or funnel opening. However, oil may be stored in suitable tanks in isolated fire
buildings, provided such buildings are not less than 15 meters any shaft, caisson, or tunnel
opening or any building directly connected there to.
Positive means shall be taken to prevent leaking flam
specifically mentioned in the proceedings paragraph.
Where feasible, a fire hose connected to suitable sources of water shall be provided at the
top o every caisson. Where fire means are not accessible, a supply of water shall be stored in
tanks near the top of every caisson, provided fire pails or suitable pumps are kept available.
Approved fire extinguishers shall also be provided.
(vii)
Sanitation:
Properly boated, lighted and ventilated dressing rooms shall be provided for all employees
engaged in compressed air work, such rooms shall contain lockers and benches and be open and
accessible to men during intermission between shifts. Adequate toilet gas accommodation of one
for every twenty-five employees shall be provided.
Care shall be taken to keep all parts of the caissons and other working compartments,
including locker rooms, dry rooms, rest house, and other equipment in a good sanitary condition
an free from fuse, decaying or other objectionable matter.
No nuisance shall be tolerated in the air chamber. Sinking shall be strictly prohibited
and all matches and smoking materials shall be left out of the locker rooms.
A separate dry-room shall be provided where working clothes may be dried within
reasonable time.
(viii) Protection against gases:
In all cases where gas is expected including alluvium impregnated with decayed
vegetable matter the use of divvy safety lamp shall be compulsory.
(ix) Additional safety provisions.
a)
The weight of the pneumatic platform and that of steining and Kent ledge, if any, shall be
sufficient to resist the uplift from air in side, skin friction being neglected in this case. If at any
section the total weight acting down word pressure more than the uplift pressure of air inside,
additional Kent ledge shall be placed on the wall.
If it is not possible to make the wall heavy enough during
excavation, blowing down may be used. The men
should be within and air pressure reduced.
The well
should then begin to move small deduction in air
pressure. Blowing down should only used when the
ground is such that it will not heavy up inside chamber
when the pressure is reduced. When the well does not
with the reduction in air pressure, Kent ledge should be
added. Blowing down should be in short stages and
the drop should not exceed metre at any stage.
To
control sinking during blowing down, use of packing are
recommended.
(b)
The pneumatic sinking plant and other allied machinery shall not only be of proper
design and make, but also shall be worked by complete at and well trained personnel. Every part
of the machinery and its fixtures shall be minutely examined before installation and use.
Availability of appropriate spares, standbys, safety of personnel as recommended in IS 14138 for
working in compressed air must be ensured at site. Codes for safety and for working in
compressed air & other labour laws and practices prevalent in the country, as specified to provide
safe, efficient and expeditious sinking shall be followed.
c)
Inflammable materials shall not be taken in to air locks and smoking shall be prohibited.
Wherever gasses are suspected to be gushing out of dredge hole, the same shall be analyzed by
trained personnel and necessary precautions adopted to avoid hazard to life and equipment.
d)
Where blasting is resorted to, is shall be carefully controlled and all precautions regarding
blasting shall be observed.
Workers shall be allowed inside after blasting only when a
competent and qualified person has examined the chamber and steining thoroughly and found the
same to be safe.
g)
c)
Bore chart shall be referred to constantly during sinking for taking adequate care while
piercing different types of strata. The type of soils as obtained during the well sinking should be
compared with bore chart so as to take prompt decisions.
d) Before seasonal floods all wells on which sinking in progress shall be sunk to sufficient depths
bellow the designed occur level. Further, they shall be temporarily filled and plugged so that they do
no suffer any tilt or shift during the floods.
e) All necessary precautions shall be taken against any possible damage to the foundations of existing
structures in the vicinity of the wells, prior to commencement of dredging from inside the well.
f)
The dredged material shall not be allowed to accumulate over the well, It shall be dumped and
spread, as far away as possible, and them continuously and simultaneously recovered as directed by the
Engineer. In case the river steam flows along one edge of the well being sunk, the dredged material shall
not be dumped on the dry side of the bank but on the side on which the river current flows.
g)
Very deep sump shall not be made below the well curb, as it entails risk of jumping (sudden
sinking) of the well. The depth of sump shall be generally limited to one-sixth of the outer diameter/least
lateral dimension of the well in plan. Normally, the depth of sump shall not exceed 3.0 metres flow the
level of the cutting edge unless otherwise specifically permitted by the Engineer.
h)
In case a well sinks suddenly with a jerk, the steining of the well shall be examined to the
satisfaction of the Engineer to see that no damage has occurred to it.
i)
In pneumatic sinking, the well shall not, at anytime, be dropped to a depth greater than 500 mm
by the method of blowing down.
j)
Dewatering shall be avoided if sand blows are expected. Any equipment and men working in
side the well shall be brought out of the well as soon as there are nay indications of a sand-blow.
k)
Sand blowing in wells can often be minimized by keeping the level of water inside the well
higher then the water table and also by adding heavy kept ledge.
l)
In soft strata prone to settlement/creep, the construction of the abutment wells shall be taken up
only after the approach embankment for a sufficient distance near the abutment has been
completed.
determination of shifts, locations of the ends of the two diameters shall be precisely measured the ends
of the two diameters shall be precisely measured the ends of the two diameters shall be precisely
measured along the two axes, with reference to fixed reference points.
Whenever any tilt is noticed, adequate preventive measures like placing econotric Kent ledge,
pulling, strutting, anchoring or dredging unevenly and depositing dredge material unequally, putting
obstacles below cutting edge. Water jetting etc., shall be adopted before any further sinking. After
correction, the dredged material shall be spared out uniformly.
A pair of wells close to each other has a tendency to come closer while sinking; timber struts may
be introduced in between the steining of these wells to prevent tilting.
Tilts occurring in a well during sinking in dipping rocky strata can be safeguarded by suitably
supporting the curb.
In the event of a well developing tilt or shift beyond the specified permissible values, the
Contractor shall have to carryout, at his own cost, suitable remedial measures to satisfaction of the
Engineer, to bring the tilt and shift within permissible values, as far as practicable.
If the resultant tilt and / or shift of any well exceed the specified permissible values, generally it
should not exceed 1 in 50 and 300 mm respectively.
The well so sunk shall be regarded as not
conforming to specifications and a substandard work.
The Engineer in his sole discretion may
consider accepting such a well provided.
(i) Calculations for foundation pressures and steining stresses, accounting for the actual tilt and shift
furnished by the contractor show that the well is safe. Any remedial measures required to bring the
stresses within permissible values (such as increase in the dimension of the well cap, provision of
dummy weights on the
well cap etc.,) shall be carried out by the Contractor with out claiming for any extra
cost.
(ii)
In case the Engineer, in his discretion, rejects the wells, the Contractor shall
dismantle the rejected well to the extent directed by the Engineer and
remove the debris. Further, the contractor shall, at his own risk and expense
complete the aqueduct with modified span arrangement acceptable to the
Engineer.
I) Seating of Wells:
The well shall be uniformly seated at the founding strata. It shall be ensured by test borings that
the properties of the soil encountered at the founding strata and upto a depth of one and a half times the
well diameter is identical to the adopted in the design. The procedure for test borings shall satisfy the
provisions of these specifications. In case, the soil encountered is inferior to that adopted in design, the
well shall be redesigned by the Engineer adopting the soil properties actually encountered and the founding
level intimated the contractor, who shall carry out the work.
In case of seating of wells in hard rocky strata, where the rock profile is steeply sloping,
pneumatic methods of sinking may be adopted to seat the well evenly as directed by the Engineer. The
decision of adopting pneumatic sinking shall be taken by the Engineer. The cutting edge may also be
embedded for a suitable depth in the rocky strata, and decided by the Engineer keeping in view the quality
of rock. As an additional measure of safety, the well shall be anchored to the rocky strata by anchor bars
provided in the steining of the well, as shown on the drawing irrespective of the fact of the well, as shown
on the drawing irrespective of the fact that tension develops or not at the base of the well under design
loads. After the wall has been evenly seated on good hard rock, arrangements shall be made to facilitate
proper in dry and visible conditions before the bottom plug is laid.
3.1.47.
BOTTOM PLUG.
For bottom plug, the concrete mix shall be designed (in dry condition) to attain the concrete
strength as mentioned on the drawing and shall contain10 per cent more cement that required for
the same mix placed dry, to cater for under water concreting. However, the total cement content
shall not be less than 363 Kg/Cum. of concrete with as lump in the range of 150 mm to200mm.
Admixtures maybe added to the concrete to impart the required characteristics indicated herein.
Concrete for the bottom plug shall be laid by tramio pipe method. Tammie concrete
when started shall be continued without interruption for full operating in the bottom plug. The
Concrete reduction equipment and placement equipment should be sufficient to enable under
water concreting within stipulated time. Necessary standby equipment should be available for
emergency situation.
Before commencing plugging, all loose material from the bottom of the well shall be
removed.
Concreting shall be done in one continuous operation till the dredge hole is filled up to
the required height and there after sounding shall betaken up to ensure that the concrete has been
laid to the required height.
Least disturbance shall be caused to the water inside the well while laying concrete in the
bottom plug.
Concrete shall not be disturbed in any way for at least.
14 Days.
In order to check any rise in the level of the bottom plug soundings should be taken at the close of
concreting and once every day for the subsequent 3 days.
The soundness of the bottom plug mazy be tested by dewatering the well by 5 metres below the
surrounding water level and checking the rise of water. The rate of rise shall preferably be less than 10
cum. per hour. In case the rate is higher, suitable remedial measures as directed by the Engineer, shall be
taken by the Contractor at his own cost.
3.1.48. SAND FILLING:
Sand filling shall commence after a period of 3 days of laying of bottom plug. Also, the height of
the bottom plug shall be verified before starting sand filling.
Sand shall be clean and free from earth, clay clods, roots, boulders, shingles, etc., and shall be
compacted as directed, sand filling shall be carried out up to the level shown on the drawing, or as directed
by the Engineer.
]
3.1.49
TOP PLUG:
After filling sand up to the required level a plug of concrete shall be provided over it as shown on
the drawing, or as directed by the Engineer.
3.1.50.
WELL CAP:
A reinforced cement concrete well cap will be provided over the top of steining in accordance with
the drawing. Formwork will be prepared conforms the shapes of well cap. Concreting shall be
carried out in dry condition. Properly designed false steining maybe provided where possible
toensurethewe3ll cap is laid in dry conditions.
The bottom of the well cap shall be laid preferably and lows possible, account the water
level prevalent at the time of casting.
Bond rods of steining shall be anchored in to the well cap.
3.1.51.
TOLERANCES:
The permissible tilt and shift shall not exceed I (horizontal) in 80 (Vertical) and the shift at the
well base shall not be more than 150 mm in any resultant directions.
For the well steining and well cap the permissible tolerances shall be as follows:-
1 + 50mm 10 mm
15mm
:
:
5mm
+25mm
The cutting edge shall be measured in tones based on the net weight of material used in it,
as per A.P.S.S. 110.
(b)
The concrete in curb, well steining and well cap shall be measured in cubic meters in
each of the items as per 5.5.4.18. The reinforcements shall be measured in tones
separately in each of the items as per 5.5.4.20.10.
(c)
The measurement for well sinking shall be made in running metres only irrespective of
clarification of soils mint with. The depth of sinking shall be measured from the level
specified in the contract. If no level has been specified in the Contract, sinking shall be
measured from the low water level or from the level at which the cutting edge was laid,
whichever is higher. Pneumatic sinking shall not be paid separately. The quoted rate for
well sinking shall include this cost also.
(d)
The quantity of concrete in bottom and top plug shall measured in cubic metres as per
5.5.4.18.
(e)
3.1.53.
RATE:
a)
The Contract unit rates of cutting edge shall cover all costs of labour material,
tools, plant and equipment, including placing in position, sampling and testing,
and supervision, all as per respective section of Structural steel work and as
described in this section.
b)
The Contract unit rates for concrete in curb, steinig, bottom plug, top plug and
well cap shall cover all costs of labour, material, tools, plant and equipment,
form work and staging including placing, in position, sampling and testing, and
supervision, all as per respective section of structural concrete and as described
in this section.
c)
The Contract unit rates for reinforcement in curb, steining, and well cap, shall
cover all costs of labour material, tools, plant and equipment, including bending
to shape, placing in position, sampling, testing and supervision, all as per
respective section of steel reinforcement and as described in this section.
d)
The Contract unit rates for sand filling shall cover all costs of labour, materials,
tools, plant and equipment, including placing in position, sampling testing and
supervision, all as described in this section.
e)
The concrete unit rates for sinking shall cover the costs of labour, tools, and
equipment and plant and for all operations and other incidentals for sinking of
well including seating excepting provisions, of pneumatic sinking described in
this Section. The unit rates shall be for all soils, H.D.R. I & rock and Hard
rock. The rate shall cover all testing and supervision required for the work.
f)
The contract unit rate of material to be excavated pneumatic sinking shall cover
all costs of labour, materials, tools, plant and other equipment and other
incidental and safety provision and supervision required for pneumatic sinking
as per this section.
g)
If any well with tilt and / or shift exceeding beyond permissible values is accepted
by the Engineer, the Contractor shall give a reduction is the rates as follows:-
S.No
1.
2.
3.
5 per cent.
10 per cent
Tilt exceeding 1 in 50
20 per cent.
4.
5.
2 per cent.
5 per cent.
6.
Shift exceeding 300 mm.
10 per cent.
- - - - - - - - - - - - -- -- - - - - -- - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Penalties for excessive tilt and shift shall be deducted separately.
APPENDEX - I.
HISTORY OF SINKING OF WELL No. ____________
BED LEVEL _________ _ LOWER WATER LEVEL _______ HIGHEST OF FLOOD
LEVEL ___________ FOUNDING LEVEL __ _ ___ _ OF CURB _ _ _ ___.
-------------------------------------------------------------STEINING
SINKING
- - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Reduced
RL of
RL of
Height
Total
RL of
Initial
Level (RL) Top
Top
of Stein- Height of
reference
Gauge
Of Bottom
of
steining
ing
of steining
level ( at
Reading
Of cutting
steining after castcasting
(including)
which
Metre.
Edge.
Casting.
Ing.
Cast(Col.1, Curb &
cutting Edge
Col.3
cutting
is placed).
Metre.
Edge(Col.4,
Col.3)Metre.
- -- - - - - - - - - -- - -- - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - 1.
3.
4.
5.
6.
7.
8.
- - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - SinkRL of
Depth of
Strata
KENTILEDGE
Ing
Bottom
Sump
Net
Weight Eccentri- Eccentricity
During of Cutting
below
With
Tonnes. City
Along
The Day Edge(Col.7 cutting edge
Along
Y- AXIS
(Col.9
Col.8)
Metre
XZXIX
Col.8)
Metre.
Metre.
Metre.
- - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - 9.
10.
11.
12.
13.
14.
15.
16.
---------------------------------------------------------------------------------------------------------------------------
2.
Report Regarding
Report Any
Remarks.
SIGNATURE OF
Obstacles or sand
special method
SUPERVISING OFFICER:
Or sand below
of sinking
During sinking.
Employed.
--------------------------------------------------------------
APPENDIX II.
TILT AND SHIFT IN WELL No:_________________
-----------------------------------------------------------Total Total
ALONG X. A XIX
ALONG Y. AXIX
Steining sinking (PLACE) (PLACE) Differ- (U/s) (D/s) Difference
Metre. Metre.
END
END. ence.
Col.8,
(Col.5,
Col.7)
Col.4)
METRES.
METRE.
-- - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1.
2.
3.
4.
5.
6.
7.
8.
9.
- -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Along Tilt Along Resultant
SHIFT ---------Y. AXIX
Tilt.
Along
Along
RESILTANT
Col. 9
(Col.10,
X.AXIX
Y.AXIX
S((Col.13)2+
Divided by
Col.11).
With
With
Col.14)2)
Well Dia.
Direction
Direction
METRE.
Hire.
Metre.
------------------------------------------------------------10.
11.
12.
13.
14.
15.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - -------------------------------------------------------------Action Taken for
Remarks
Signature of
Rectification.
Supervising Officer.
-------------------------------------------------------------16.
17.
18.
--------------------------------------------------------------
Prepare all necessary calculations and details of arrange for such load testing, well in time.
The magnitude of the test load, mode and method of carrying out the test, the application of
Kent ledges, duration of keeping the test load, the observations to be made during placement
of the test loads in position etc., shall be got approved by the Engineer, before commencement
of the load testing work.
(ii)
Make all necessary arrangements for the observations, the centering equipments etc., that may
be needed for measuring the settlements, dislocations etc., as required for the test to the entire
satisfaction of the Engineer.
(iii)
Provide all labour and materials and make all observations during the test.
After the load test, the Contractor shall submit a report on the results of the test. The Engineer shall
then communicate as to whether the test has been satisfactory or not or any further tests if
reconstruction or strengthening will be necessary to correct any limits revealed during the test.
Any defect in the Structure or any damage done to the bridge at the time of testing which affects
or is likely to effect the strength of the bridge shall be rectified by the contractor at his own cost by
remedial measure of replacement as approved by the Engineer.